Академический Документы
Профессиональный Документы
Культура Документы
Construction Work
Tender Number: WS1026624444
METHOD STATEMENT OF
CONCRETE FOUNDATION
Page 1 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Revision note
1. Contents
1. Contents..........................................................................................................................2
2. General information .........................................................................................................3
3. Purpose ...........................................................................................................................3
4. Shallow foundation work procedure. ..................................................................................3
4.1. Concrete base work ...................................................................................................4
4.2. Reinforcement work ..................................................................................................4
4.3. Form work ...............................................................................................................4
4.4. Concrete pouring work ..............................................................................................5
4.5. Concrete curing work ................................................................................................5
5. Concrete joint ..................................................................................................................6
5.1. Construction joint......................................................................................................6
5.2. Contraction joint .......................................................................................................7
6. Plant and Machinery Selection ...........................................................................................8
6.1. Concrete Truck Mixer................................................................................................8
6.2. Concrete Pump .........................................................................................................9
7. Equipment list................................................................................................................ 10
8. MANPOWER PLANNING ............................................................................................. 11
8.1. List of employees .................................................................................................... 11
8.2. Job Discription ....................................................................................................... 12
9. QA/QC procedure .......................................................................................................... 13
10. Safety ........................................................................................................................... 13
Page 2 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
2. General information
Project title: OT Site Kitchen & Dining Facility Project
Foundation concrete C35: 1275 m3
Foundation concrete C40: 72 m3
Foundation concrete C20: 214m3
Rebar: 90t
Concrete Work covers the formwork, erection of rebar and pouring work for porch, grease trap,
HVAC room, dewater room, freezer room, rubbish compactor and dry storage buildings and equipment
foundation concrete work.
All concrete work will be carried out in accordance with the related norms and rules. In any
circumstances where specifications are not provided or they are in any way incomplete, the matter shall be
referred back to consultant for additional information.
3. Purpose
The purpose of this method statement is to define procedures, resources and durations which will be
necessary to execute each stage of concrete work with high quality and safety.
Page 3 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 4 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 5 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
5. Concrete joint
In long span concrete slab or raft foundation, concrete crack can be emerging due to concrete
shrinkage and movement. To prevent such crack construction or contraction joints made in concrete slab or
raft foundation.
Page 6 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 7 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 8 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 9 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
7. Equipment list
# Tools Figure Capacity rating
5 Trowel h=20-50m
9 Concrete vibrator
11 Level 2m
Page 10 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
8. MANPOWER PLANNING
All the employees/staffs who are pouring concrete shall carefully study Method statement of
concrete foundation and job descriptions. All the employees/staffs shall be trained in HSE training and
provided by PPE /personal protection equipment/. Geodesy engineer and technician shall work within 2
groups and shall be responsible for monitoring the location and distance.
Position
1 Project manager
2 QA/QC engineer
3 Drawing engineer
4 Material engineer
5 Geodesy engineer
6 HSE engineer
8 Document controller
Position
1 Pump operator
2 Pump assistance
3 Pump gun operator
4 Vibrator man
5 Concrete pouring staff
6 Finisher
7 Curing work assistance
8 Crane operator
9 Iron worker
10 Carpenter
11 Laborer
Page 11 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 12 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
9. QA/QC procedure
Slump test, air and concrete temperature check will be done of each concrete truck as soon as concrete
truck delivery. Slump test shall be recorded per 50m3 concrete at site6
Additional 9 test cubes from each 20m3 of concrete will be cured under the field condition:
- to verify the actual concrete strength,
- to verify if the concrete has achieved 70% of compressive strength
- to verify if the concrete can achieve 28 days design strength
Field test cubes will be protected by wooden timbers.
10.Safety
All required permits will be obtained prior to any works commencing
All works shall comply with Safety Plan and municipality rules and regulations.
Trained operator and banksman would be engaged to control or operate heavy equipment
machine.
Provide sufficient lighting whenever night casting.
Skilled and unskilled labor shall need to use safety requirements such as safety helmet, safety
shoes, goggles, gloves, vest etc.
Safety devices and safety warnings shall be provided starting from the site entrance gate till the
casting area.
Page 13 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
APPENDIX A
Concrete Quality Control Laboratory Testing Report
Page 14 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Comments :
Tested By:
Comments :
Laboratory Testing Results
Cubes. ID # Cured days Cube. Wt. (kg) Cube Size (mm) Date Tested M ax Load (N) Str.Result (M Pa) Fract.
1 3 100x100 3-Jan-00 0
2 3 100x100 3-Jan-00 0
3 3 100x100 3-Jan-00 0
4 7 100x100 7-Jan-00 0
5 7 100x100 7-Jan-00 0
6 7 100x100 7-Jan-00 0
7 14 100x100 14-Jan-00 0
8 14 100x100 14-Jan-00 0
9 14 100x100 14-Jan-00 0
10 28 100x100 28-Jan-00 0
11 28 100x100 28-Jan-00 0
12 28 100x100 28-Jan-00 0
() Cone and Split (b) Cone and Split (c) Cone and Shear (d) Shear (e) Columnar
Fracture
Comments :
Page 15 of 18
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
APPENDIX B
Field test report of concrete
Page 16 of 18
Field test (Batching plant) report of fresh concrete product for. Project
Client Date
Project Mix ID
Casted structure Tested location Plant: Site:
Arrived time Test time at Cast start Cast finished Slump& Air Slump& Air Concrete Ambient Slump, flow
Size m3 Total m3 Batch plant Adjustments
at site site time time content content site Temp Temp (mm)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Page 17 of 18
Tender Number: WS1026624444
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Mine Dry Conversion to Site Kitchen- Turn-Key
Construction Work
Tender Number: WS1026624444
Page 18 of 18