1. What is total float?

2. What are the difference between free float and total float?
3. What is a constraint?
4. What are the difference between MS Project and Primavera?
5. How to load cost & resource in a program?
6. What is WBS?
7. What is a milestone? What are the types of milestone?
8. What are the difference between flag and milestone activity?
9. What is a critical activity?
10. What is resource allocation and leveling?
11. What is a Baseline Program?
12. What are BSWS, BSWP, and ACWP?
13. What are SV and CV?
14. What is a Budget and how do you compare budget against Actual cost?
15. What is an S Curve?
16. What is the difference between P3.1, P3E, and P5 etc.
17. What is an open end activity?
18. How often you update your program?

Q1:What are the difference between free float, total float and what is different between
Float and Slack?
This is very common question in a primavera interview, Float and slack are the two different
words for the same meaning.

Free Float : amount of time , an activity can be delayed without delaying the successor activity

Total Float : amount of time , an activity can be delayed without delaying the project finish date.

Q2:What is a constraint in primavera?

Constrains in primavera is to fix the early or late start or finish date of an activity as per following
options:

1) Project Must Finish by

2) Mandatory Start / Mandatory Finish

3) Start / Finish On or After

4) Start / Finish On or Before

5) Start / Finish On

6) Expected Finish

Q3:How can you define the Critical Path in primavera?


The sequence of activities which describe the longest path from the data date to the end of the
project. In a schedule without any constraints, this will be all activities with zero total float.
(if you have constrains which force negative float, simply filtering on total float equal to or less
than zero can bring up activities which are not on the critical path)

Q4:What is WBS?
WBS means Work Breakdown Structure. it represents a hierarchical breakdown of a Project into
elements and deliverables.

Q5:What is an open end activity in primavera?


The open end activity is the activity that does not have any successor. Normally open end activity
is not accepted in schedule because the total float will be calculate from the end of the project and
these entire activities late dates gather at the end of the project and can not be prepare a logical
late start plan.

Q6:What is the difference between Retained Logic & Override Logic in progress update?
If a project is generally running according to plan and activities are not progressed out of
sequence then there will be virtually no difference between the two methods. BIG differences
come when activities are progressed out of sequence.
I believe in retained logic. Invariably that will produce the longest critical path but if activities
have been progressed out of sequence, there could be some resulting illogical dependencies
remaining, in particular resulting from dependencies with durations.
Progress override invariably produces a shorter critical path and again there could be some
illogical lack of dependencies resulting from activities having been progressed out of sequence.

Q7:How do u measure & compare the progress using primavera?


This is one of the Hard primavera Interview Questions, try to explain without confusion.

Progress is measured primarily against the baseline. If the baseline has been loaded with cost
and/or resources, earned value management can be used for this purpose. If not, progress is
measured as variance to baseline dates.
Budget at Completion (BAC)
Planned Value (PV) = budget at Completion (BAC) x Planned % Complete
Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What youve actually spent on the project
Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV)
Schedule Variance (SV) =Earned Value (EV) Planned Value (PV)
Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC)
To Complete Performance Index (TCPI) =(Budget at Completion (BAC) Earned Value (EV) ) /
(Budget at Completion (BAC) -Actual Cost (AC) )
Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC)
For more information see this article: EVM earned value management
Q8:What is resource allocation and resource leveling?
Resource allocation is assigning resources to activities,determine the amount of labor, equipment
and money required for any activity.
Resource leveling is Resource requirements of all scheduled activities are compared to the
maximum quantity available at the time of leveling.An activity is delayed if too few resources are
available at any time during the activitys duration.The maximum quantity for a resource is
determined through the Max units/time for a particular resource in the Resources Tab.

Q9:What is an S Curve and how to create S Curve in primavera?


An S-curve is a graph showing cumulative cost or value (measured in terms of money or
manhours) against time. On a typical project, these graphs follow an S shape, hence the name.
Typical data to be plotted on an S-Curve includes:

Actual Cost (ACWP)

Planned Value (BCWS) Early dates

Planned Value (BCWS) Late dates

Earned Value (BCWP)

Forecast Value Early dates

Forecast value Late dates

Forecast Cost Early dates

Forecast cost Late dates

Q10:What are the difference between flag and milestone activity in primavera?
This is one of the tricky Primavera Interview questions.

Mile stone & flags both are events rather then activities. Some client likes to use flags rather than
mile stone due the following differences.
1- With the use of flags the logic of main event can be easily tracked as these can not be created
without predecessor as stand alone allocating the constraint.Where as mile stone can.
2- Flags can not update manually as Primavera automatically update the status where as
milestone can be update manually.
3- Flags can not be constraint only driven by predecessor where as milestone can.

Read more: http://planningengineer.net/top-10-primavera-interview-questions-and-model-


answers/#ixzz4hmRc43MI