Академический Документы
Профессиональный Документы
Культура Документы
1. Background
The risk analysis was then based on the engineering experience and
knowledge of the wells. The similar nature of data set selected underpin
this process and provide an auditable backup.
A plan simple listing the main activities required to achieve the well
objectives and the relevant depths was constructed.
1
2.3 Analyse Offset Performance
Drilling times on each data set of wells were broken down into
performance summaries at a level of detail which was considered fit for
purpose. This data was then used to estimate the duration of the
planned well.
NPT and train-wrecks are included as specific line items in the risk
analysis and are treated separately for two main reasons:
The figures for the hole sections (36, 26, 17 12 and 8 ) are
expressed in metres per day (m/d). The performance was kept simple
to illustrate the risk analysis process. The train-wrecks both refer to
stuck pipe, casing and equipment related incidents and were by far the
largest single sources of NPT. Note that Total Days includes the train-
wreck duration.
Job A B C D E F
12-1/4" (m/d) 426 406 499 490 398 367
9-5/8" Casing 1.13 1.17 1.33 1.17 1.26 1.18
8-1/2" (m/d) 323 348 253 366 391 417
Log 1.50 1.46 2.52 1.54
7" Liner 0.86 1.19 1.17 0.98 0.96 1.02
%NPT 13.6 1.2 5.7 0.7 5.6 2.4
Total Days 14.57 20.88 21.42 13.89 13.73 13.31
Train-Wrecks 4.92 4.06
2
It is obviously important to allow for these when compiling the estimate,
however, it is equally important to allow for the uncertainty that such
adjustments may introduce into the estimate. This can be done by
careful selection of the distributions and parameter ranges, as discussed
in the following sections.
This is the key step in the risk analysis process because it defines the
input distributions to the subsequent Monte Carlo simulation. Monte
Carlo simulation is the basis of most risk analyses and is an effective method for
modelling the uncertainty of real problems which are invariably too complex to
be solved analytically.
.053 52.5
.035 35
.018 17.5
.000 0
3
above which 50% of values lie. The P90 is the time above which 10% of
values lie. In this case, the three percentiles are as follows.
Note the skewness of the results, again reflecting the train-wreck risk.
The cumulative distribution is shown below.
.750 750
.500 500
.250 250
.000 0
It is common to take the P50 value as the time or cost estimate with the
P10 and P90 values characterising the uncertainty. However, be careful
when summing P50 values over a number of wells as the sum of many
P50 values may yield a total which is significantly less than a P50 due to
the skewness of the underlying distributions. This problem does not
occur when dealing with means and, for this reason, some practitioners
of risk analysis prefer the mean to the P50 (the GIAPPS process is
based on the mean). This problem can be avoided by setting up a
separate risk analysis for the whole well programme using the
uncertainty estimates of each individual well as the inputs. Be careful to
take account of dependency when building such a model (see 2.8).
4
The Generic Method
In this approach, a list of potential risks is identified for the planned well.
This could be based on a detailed analysis of hazards experienced on
offset wells or on the results of a brainstorming session of engineers
familiar with the area to be drilled. In either case, the output is a list of
potential risks. The second stage is to go through each risk and
estimate the probability of occurrence and likely impact based on a
consensus of those involved. Multiplying the probabilities by the impacts
gives the risked impact, which may be used to eliminate risks of little
consequence. The remaining risks are then included in the risk analysis
in the manner described previously.
2.8 Dependency
5
2.9 Sensitivity Analysis
Sensitivity Chart
%NPT .23
Log .16
Train-Wreck .12
-1 -0.5 0 0.5 1
6
2.10 Communication of Results
7
3. Bullets
q Allow for a wide range of NPT. Estimate the probability and impact
of train-wrecks using offset frequency, a detailed study of potential
risks or a combination of both.
4. Software Tools
Time Forecasting
Available in DEAP, automatically breaks down performance on wells
which have passed through Phase/Job Allocation. Uses resultant data
to generate a forecast for a planned well based on Monte Carlo
simulation. Very powerful tool but requires training to use effectively.
Crystal Ball
Inexpensive add-in to Excel which performs Monte Carlo simulation.
The program is supported by an excellent and easy to follow manual.