JOBPROCEDURE FOR
INSTALLATION ANDTESTING OF
ELECTRICAL WORKS
Doc.No.UKon-PGP/E&I-001 Rev.0
o 20.04.2011 IssueforComments
TABLEOFCONTENTS
1.0 PURPOSE 3
2.0 SCOPE 3
3.0 REFERENCES 3
4.0 TERMS&DEFINITIONS 3
5.0 RESPONSIBILITIES 4
6.0 METHODOLOGY 5
7.0 HEALTH,SAFETYANDENVIRONMENT 12
8.0 QUALITYASSURANCEIQUALITYCONTROL 12
9.0 APPENDICESIFORMATS 12
INSTALLATION & TESTING OF
NN ELECTRICAL WORKS
Doc.No.:UKon-PGP/EI-001, Rev-O
1.0 PURPOSE
Thepurposeofthisdocumentistolaydownspecificguidelinesandrequirements
forElectricalworksinaccordancewithdrawingsandstandardstobeusedin the Up-
gradationofKonabanGGSandPipeline GridProjectofTripuraAsset
ConstructionWorkby KSS.
2.0 SCOPE
ThisProcedurecovers theworkmethodforelectricalworksinaccordancewith
drawingsandstandardstobeusedintheUp-gradationof KonabanGGSand
PipelineGridProjectof TripuraAssetConstructionWorkbyKSS.
Thescope ofworkincludesfacilitiesforpipelinenetworkfor.
A. 20" dia.pipelinefrom
I. ADBGGStoPalatanaterminal(53km)
B. 16"dia.Pipelinefrom
I. KonabanGGStoNimbutaliJunction(12km)
II. SonamuraGGStoPalatanaTerminal(22km),
C. 8"dia.Pipelinefrom
I. KunjabanManifoldtoADBGGS(18km)
II. SundalbariManifoldtoSonamuraGGS(12km),
D. 6"dia.Pipelinefrom
I. KunjabanManifoldto ADBGGS(18km)
II. SundalbariManifoldtoSonamuraGGS(12kM).
3.0 REFERENCES
Followingdocumentsintotalityorinpartshallformthereferencedocuments:
-, cificationforScopeof WorkandSupply(Electrical)
I,\ ;~ signandConstructionRequirementsForCrossCountryHydrocarbonPipelines
01SDB141.
GasTransmissionanddistributionPipingSystemASMEB31.8.
For the Purpose of this document, the term "shall" indicates a mandatory
requirementand"should"indtcatesarecommendedpractice.
QualityAssuranceManual
b) ONGe'sSpecification
-.0 RE PO lBLUT
ResidentConstructionManager - ShallreporttotheProjectManager.
Shall beresponsibleforoverallimplementation,
monitoring andcontrolofconstructionand
commissioningactivIties
SiteEngIneer ShallreporttotheResidentConstructionManager.
PreparationorElectrlcalwokschedulesaddressing
specificissuesandcharacteristicsofeach spread.
- Overallcontrolandsafetymanagementandforthe
[m~l~mentationof procedure a.ndsupe~. iSIS.e
activity.
Generationofreportsduringtheactivity. .
UoI"'~...._
Explainingiallother persons involvedin.,q::r1~!iMi"~:J:
worktobedonepriortostarttheactivity.
Ensuringthatthecommunicationsystemisworking
properlyandthatemergencyequipmentisinplace.
6.0 METHODOLOGY
LAYINGOFCABLE
1. InspectionofcabledrumshallbecarriedoutforitsconformitywithONGCSpecs.
Beforepullingthecables.Cablesshallbelaidintrenches,cabletraysorconduits
asrequired.
2. Beforecablelaying,cableroutinggivenonthelayoutdrawingsshallbecheckedin
thefieldtoavoidinterferencewithstructures,heatresources,drains,piping,air
conditioningductetc.andminoradjustmentsifrequired,shallbedonetosuitthe
fieldconditionswithinformationtoONGC.
3. Cabledrumshallberolledinthedirectionindicationonthesideof thedrum.Care
should be taken to avoid sharp turns, tension, twists etc. in order to avoid
mechanicalinjuries to thecables.
4. Highvoltage,mediumvoltageandothercontrolcablesshallbeseparated from
eachotherbyadequatespacingorrunningthroughindependentpipes,trenches
orcablestrays,asapplicable.
5. Cablingforfirewatersystemshallbeasfaraspossibletakeninexclusiveroute
throughundergroundtrench.
6. Allcableroutes shallbecarefullymeasuredandcablescuttotherequiredlengths,
leavingsufficientlengthforthefinalconnectionofthecabletotheterminalofthe
equipment.Thequantityindicatedinthecablescheduleisonlyapproximate.
7. Allcableroutesshallbecarefullymeasuredandcablecuttotherequiredlength,
leavingsufficientlengthforterminationtoequipment.
8. Cablesshallbeneatly arrangedinthetrenches/traysinsuchamannerthatcriss
crossingisavoidedandfinaltakeofftothemotor/switchgearisfacilitated.Cable
routingbetweenlinedcabletrenchandequipment/motorsshallbetakenthrough
GIpipesleevesofadequatesize.
9. Allcableswillbeidentifiedclosetotheirterminationpointbycablenumbersas
perthecableschedule.
10.Directlyburiedcableshall belaidundergroundinexcavatedcabletrenches.
11.Beforethestartofcablelayingdrumscheduleshallbepreparedanditshallbe
followed&recorded.
12.Trenchesshallbeofsufficientdepthandwidthforaccommodationofallcables
correctlyspacedandarrangedwithaviewofheatdissipationandeconomyof design.
13. Minimumdepthofburiedcablestrenchshallbe900mmfor lowvoltage.The
'I. dthewidthofthetrenchshallvarydependinguponthenumberoflayers
'~bijIS..~.~ its" voltagegrade.
re lesrisefromtrenchestomotor,controlstation,lighting panelsetc.they
'4
be eninGIpipesformechanicalprotectionuptoaminimumof300mm
above Fe
&~ ~ lingstresslimitshall beobservedtopreventanydamagetocableduring
~~rQ .Thecablemanufacturer'sminimumbendingradiussh "be maintained, .JII
I . Cable trenches, to be dug, should be according to specified length, width, and depth
asper theapproved construction drawings. Cable laying, dressinq, testing, qualified
workmen shalldocrimping &termination.
18. Cables shall beneatly arranged inthetrench/trays insuch amanner so that the
criss-crossing is avoided and final take off to equipment and local panels is facilitated.
19. To protect cable against dirt&moisture their ends shall besealed with aPVCor
Rubber hood (ifrequired).
20.AII Ihe specified tests for the cables shall be performed asper ONGC standards
andshould berecorded onapproved formats anddocumented properly.
21.Cable markers shall beusedaspertheONGC standards and Specification.
Earthing Materials
1. The earthing materials shall be checked for any damage caused during
transportation quantity withpacking list.
2. Allhardware used forearthing installation shall behotdip galvanized. Thickness
ofhotdipgalvanizing shallnotbelessthan75microns.
3. Theearthelectrode andearth plateshallbeasperONGC standard.
Connections
ELECTR,ICALWORKS
~Doc.No.:UKon.PGPJEI-001. Rev..()
9. Thefollowing shallbeearthed:
a)System neutral.
b)Current andPotential Transformer Secondary Neutral.
0)Lightning!arrestors.
d)Alltransformers, switchgear andtheirearth buses, busduct. e)Motor
frames. Etc
10.Lightning protection- shall be provided for the equipment, structures and
buildings which arehigher than20meters oraspertheriskindexanalysis worked out.
11. The shield wire shall be connected with main grid solidly andnot through
supporting steelstructures.
1i2. Lightjng fixtures shall be earthed through the extra core provided inthe lighting cable
forthispurpose.
BatteryCharger
S
W
i
t
c
h
o
n
t
IN.STALLAT,I,ON &TESTING'OF
ELECTRICALWORKS
Doc.No.:UKon,..pGPIEI001,Rev..o
K5
'Battery Bank
1. FlOOring, cable entries and floor supporting steelwork will be checked, before transport
ofbatteries andother accessories.
2. Battery rackswillbeassembled asperapproved relevant.drawings.
3. Battery rackwillbepositioned aspertheapproved layoutdrawings.
4. Battery cells wHIbe placed onthe rack suitably soastopermit connection ofthe positive
andnegative terminals according tothewiring diagram.
5. Electrolyte willbeprepared aspervendor speeitlcation,
6,.. Electrolyte willbeadded intothebattery cells byusing aclean plastic funnel and
jug,fromthetopofvent.
7. Check the batterycells for electrolyte levels after 30 minutes and add the electrolyte,
if the level has dropped. Check specific gravity &cell'veltage before charging.
8. Ba.tterybankterminals willbeconnected tothecharging UPSorBatterycharger.
9. Polarity bechecked atthebattery terminals.
10. Itwinbeensured thatcell vent caps are inclosed position before charging,(Itwin:
beopenduring charging).
11. Battery bank charging/dischargingwill be conducted as per vendor
recommendations.
MVSWITCH GEARS
This specificationis intended to cover the receipt at site, installation, testing and
commissioning of medium voltage switchgear comprising of Power Control Centres (PCC).
Motor Control Centres (MCC), Power-cum-Motor Control Centres (PMCC) etc..
and c?mplete with all materials and accessories for efflcient and tfci't\bl~- e "
operatron. \.,_,....J.~. .
~~
a rnentwillbeshipped tositeandstored inadryplace. ,.;.
a wmmD.Qar~willbehandled withcare, avoiding,impact ~otheequipment. .~ -- ......-.
a es,''>~oor supporting steelwork &.Ievellng will be checked b
-6f WI Iflgear.
of ......tiqfidquipment(cranes/hydra)will be decided atsiteaspersize/weight'
-a tronprJhe equipment
P , ...eveuRg' ofbase framewillbeensured.
All loose wiring &accessories will be completed as per manufacturer
recommendation.
9
INSTALLATION&TESTINGOF
ELECTRICALWORKS
CocoNo.:UKon-PGPIEI-001, R.ov-O
All cubicles, switches, starters, CT &PT chambers, bus bar chamber will be cleaned
andchecked fortightness ofallthecomponents.
Inter-panel wiring/bus coupling will bedone at site as per interconnection details
andvendor recommendations.
Allloosely supplied itemswillbeinstalled aspervendor's recommendations.
Incoming cables willbeterminated inadressed manner andproper supporting for heavy
cables willbeensured.
Erection ofequipment willbeasper"Equlpment Layout" drawings.
Before equipment isfinally grouted, itwould beshown toCHentRepresentative for approval.
Electrical connections wiJIbemade asperconnections details.
Mechanical &Electrical operation ofbreaker, modules andinterlock shall be checked.
After termination, spare entrywillbeplugged withmetallic/PVC plugs.
Proper sizelugsandferrules would beprovided.
" Earthing ofaltequipment willbedone asperearthingdetails anddrawing.
Equipment shallbecleaned internally andexternally. "
Proper tightness ofboltsofbusbars willbeensured.
Testing andcommissioning would bedone asperField Inspection ReportsNendor
recommendations.
Allinterlocks asperschematic drawings/logic would bechecked.
Allindicating lampsandinstruments wlllbechecked forcorrect operation.
Earthing ofSwitchboard willbedone asperInstallation StandardsNendor
recommendations.
~
9 "~,
specification isintended tocover theInstallation andcornmlssienlnq atsiteof
medium voltage motors withallmaterials andaccessories forefflcrent andtrouble
freeoperation.
INSTALLATIO &TESTING OF
N ELECTRICA WORKS
L Doc.No.:UKonPGPlEl"()O1,Rev..()
Motorswillbeshipped tositesafely andstored inadryplace.
Useoferection equipment(cranes, hydraetc)willbedoneaspersizeand location
ofthemotors.
DC- ACConverter
Cable entries, floor supporting steelwork &leveling will be checked before transport
ofDC-to-DC converter system cabinet.
Proper leveling ofbaseframe willbeensured.
All loose wiring &accessories will be completed as per manufacturer
recommendanon.
Check outvoltage oftheconverter.
Incoming power supply, battery bank oonnection &outgoing feeder cables willbe checked.
Verification ofmaterial willbedoneasperpacking list.Anypartmissing/damaged would
bereported immediately
Erection ofequipment willbeasper "Equipment Layout" drawings.
Before equipment isfinally grouted, itwould beshown toClient Representative for approval.
Electrical connections willbemadeasperconnections details.
After terrninanon, spare entrywillbeplugged WithmetalliclPVC plugs.
Proper sizelugsandferrules would beprovided.
Earthing ofallequipment willbedone asperearthing details anddrawing.
Equipment shallbecleaned internally andexternally.
Testing andcornmissioninq would bedone aspervendor recommendations.
INSTALLATION&TESTINGOF
ELECTRICALWORKS
Doc.No.:UKon-PGPIEI..()01,Rev..()
AllPPEisamustinthisactivity.
Onlytrained personnel tobedeployed forthisactivity.
Personnel around mustbeinformed evacuated toasafedistance.
AllMeasurin9 &TestEquipments used mustbewellmaintained.
Regular awareness program shallbearranged.
KSSshallarrange firstaidbox.
Appendix: 01 ITP-Battery
(UKON-PGPJE&IIITP-01 Rev0)
(UKON-PGP/E&I/FM-03Rev0)
Format: 04 InspectionReportLighting
(UKON-PGP/E&IIFM-04Rev0)
Format: 05 InspectionTestReportEarthing
(UKON-PGP/E&I/FM-05Rev0)
Format: 06 InspectionTestReportSwitchBoards
(UKON-PGP/E&I/FM-06Rev0)
Format: 07 IRValueofLighting
(UKON-PGP/E&IIFM-07Rev0)
Format: 08 IlluminationLevel
(UKON-PGP/E&IIFM-08Rev0)
Format: 09 InspectionReportMisc.Elect.EquipmentInstallation
(UKON-PGP/E&I/FM-09Rev0)
Format: 10 InspectionTestReportEarthingWorkS
(UKON-PGP/E&IIFM-10Rev0)
Format: 11 InspectionReportCable
(UKON-PGP/E&I/FM-11Rev0)
Format: 13 CommissioningTestReportPotentialTransformer
(UKON-PGP/E&I/FM-13Rev0)
Format: 15
Format: 16
IRValueofCable
(UKON-PGP/E&IIFM-17Rev0)