AIC/MIT/CF/CIVIL/2K6CE508(P)/LP

MALABAR INSTITUTE OF TECHNOLOGY


Department Of Civil Engineering
LESSSON PLAN
Name of Faculty: BINOY GEORGE

Subject: 2K6CE 508 (P) Concrete Lab

Semester: 5th Semester (1st Batch)

Sl .no Experiment Planned Date/Hr Actual Date/Hr


1 Normal consistency of cement 07/06/2016 07/06/2016
2 Initial & final setting time of 14/06/2016 21/06/2016
cement 21/06/2016 28/06/2016
3 Bulking of cement 28/06/2016 05/07/2016
4 Bulk density ,void ratio &
specific gravity
05/07/2016 12/07/2016
5 Compressive strength of cement 12/07/2016 19/07/2016
6 Grain size analysis 19/07/2016 26/07/2016
7 Slump test 26/07/2016 09/08/2016
8 Compaction factor test

9 Compression test on concrete 09/08/2016 16/08/2016


10 Aggregate crushing value 16/08/2016 23/08/2016
11 Aggregate impact value 23/08/2016 30/08/2016

Signature of faculty Signature of HOD


AIC/MIT/CF/CIVIL/2K6CE508(P)/LP
AIC/MIT/CF/CIVIL/2K6CE508(P)/LP

MALABAR INSTITUTE OF TECHNOLOGY


Department Of Civil Engineering
LESSSON PLAN
Name of Faculty: BINOY GEORGE

Subject: 2K6CE 508 (P) Concrete Lab

Semester: 5th Semester (2nd Batch)

Sl .no Experiment Planned Date/Hr Actual Date/Hr


1 Normal consistency of cement 09/06/2016 16/06/2016
2 Initial & final setting time of 16/06/2016 23/06/2016
cement 23/06/2016 30/06/2016
3 Bulking of cement 30/06/2016 14/07/2016
4 Bulk density ,void ratio &
specific gravity

5 Compressive strength of cement 07/07/2016 21/07/2016


6 Grain size analysis 14/07/2016 28/07/2016
7 Slump test 21/07/2016 11/07/2016
8 Compaction factor test 28/07/2016 18/08/2016

9 Compression test on concrete 04/08/2016 25/08/2016


10 Aggregate crushing value 11/08/2016 01/09/2016
11 Aggregate impact value 18/08/2016 08/09/2016