Академический Документы
Профессиональный Документы
Культура Документы
1
4/3/2014
Acme Stamping
Workday = 8 hours; 2 10 minute breaks
Building to a Supermarket
2
4/3/2014
Production Control
schedules assembly
Meeting demand:
Use customers 30-day forecast for
initial forecast
Redistribute work elements & adjust
# to match demand & output of
operators
Kanban from supermarket
determines actual production
Kanban size: 20-bracket tray
Future State Strategy
3
4/3/2014
assemble
assemble
weld
1 s. weld
stamp
Stamping?
NO cycle time of 1 sec. is too short
Run stamping as a batch operation
Assembly workstations
Close proximity
Cycle times are near takt time
Dedicated to steering bracket product
Weld workstations
Same characteristics
4
4/3/2014
Takt= 60 sec.
C/T = 55 sec
C/O = 0
Uptime = 100%
2 shifts
Continuous Flow
Stamped Parts
Weld/assembly cell requires 600 LH & 320 RH
stamped parts/day
Parts containers sized to allow close placement
Small containers keep both LH & RH parts in
the cell
Reduced changeover time at pacemaker process
Very frequent changeovers is key for leveling mix
5
4/3/2014
Kanban
One Option
6
4/3/2014
Signal Kanban
Another Option
7
4/3/2014
Progress