Weekly Planning Report

Date of Report Jun 28, 2017

Company ATS
Description Weekly Progress Plan for ELM-HQ1

Start Date 1/07/2O17 End Date

Actual Planning Repo

Ref No Activity Planned % Actual %

HVAC-Ducting
1 Ducting of Exhaust toilets, Connection of Air Terminals LSD, RD, SD of Fourth Floor 100 99

2 Ducting of Exhaust toilets, Connection of Air Terminals LSD, RD, SD of Third Floor 100 98

3 Ducting of Exhaust toilets, Connection of Air Terminals LSD, RD, SD of Second Floor 100 96

Ducting of Exhaust toilets, Fresh air & Exhaust duct, Supply Flexible Duct Dropings, Connection of Air
4 100 90
Terminals LSD, RD, SD of First Floor
FCU Installation, Ducting of Supply Duct, Plenum, Return Duct, Exhaust toilets, Fresh air & Exhaust duct,
5 100 77
Supply Flexible Duct Dropings, Connection of Air Terminals LSD, RD, SD of Ground Floor

5 Testing & Commisioning For Fourth & Third Floor 60 60

6 Testing & Commisioning For Second, First Floor, Ground Floor 60 60

HVAC-Chilled Water Piping


7 Chilled Water Piping, Insulation, Flushing, passing of water for Remaining all FCU'S of Fourth Floor 100 100
8 Chilled Water Piping, Insulation, Flushing, passing of water for Remaining all FCU'S of Third Floor 100 100
9 Chilled Water Piping, Insulation, Flushing, passing of water for Remaining all FCU'S of Second Floor 100 100
10 Chilled Water Piping, Insulation, Flushing, passing of water for Remaining all FCU'S of First Floor 100 100
11 Chilled Water Piping, Insulation, Flushing, passing of water for Remaining all FCU'S of Ground Floor 100 85
12 Testing & Commisioning For fourth & Third Floor 60 60
13 Testing & Commisioning For Second , First floor, & Ground Floor 50 50

PLUMBING-Drainage
18 Condensate Drain Piping(CDP) & Insulation for Ground Floor 100 79
19 Testing & Commisioning For fourth & Third Floor 100 95
20 Testing & Commisioning For Second & First floor 100 95
21 Testing & Commisioning For Ground Floor 100 40
22 Plumbing Drainage System , Installation of pipes & Sanitary Fixtures for fourth floor 100 95
23 Plumbing Drainage System , Installation of pipes & Sanitary Fixtures for Third floor 100 95
24 Plumbing Drainage System , Installation of pipes & Sanitary Fixtures for second floor 100 90
25 Plumbing Drainage System , Installation of pipes & Sanitary Fixtures for first floor 100 75
26 Plumbing Drainage System , Installation of pipes & Sanitary Fixtures for Ground floor 100 46
27 Testing & Commisioning For fourth & Third Floor 100 30
28 Testing & Commisioning For Second, First floor & Ground Floor 100 30

PLUMBING-Water Supply system


28 Water Supply Systeml For Fourth Floor 100 95

29 Water Supply System Third Floor 100 95

30 Water Supply System For Second Floor 100 90

31 Water Supply System For First Floor 100 85

32 Water Supply System For Ground Floor 100 69

33 Testing & Commisioning 100 20


FIRE FIGHTING
34 Fire Fighting piping, supports, droppings, Flushing, & Sprinkler head installation for fourth floor 100 98
35 Fire Fighting piping, supports, droppings, Flushing, & Sprinkler head installation for Third floor 100 98
36 Testing & Commisioning For fourth & Third Floor 100 86
37 Testing & Commisioning For Second , First floor & Ground Floor 100 60
38 Fire Fighting piping, supports, droppings, Flushing, & Sprinkler head installation for Second floor 100 90
39 Fire Fighting piping, supports, droppings, Flushing, & Sprinkler head installation for first floor 100 92
40 Fire Fighting piping, supports, droppings, Flushing, & Sprinkler head installation for Ground floor 100 86

Major Issues
Ref No Description Location

1 HVAC-DUCTING & PIPING Schedule as

2 MECHANICAL MATERIAL Remaining Pu

3 HVAC-DUCTING Sub-Contractors

4 STEEL STRUCTURE
Client:

Consultant KESCOM

6/07/2O17

tual Planning Report

Variance % Start Date Finish Date Remarks

-1 1/07/2O17 6/07/2O17 As-built under progress

-2 1/07/2O17 6/07/2O17 Exhaust Grilles Will Pending due to Aluminum Ceiling Work,

-4 1/07/2O17 6/07/2O17 Exhaust Grilles Will Pending due to Aluminum Ceiling Work,

-10 1/07/2O17 6/07/2O17 LSD, SD, RD

-23 1/07/2O17 6/07/2O17 Parallely with Civil,

0 Parallely with Civil & Electrical work

0 Parallely with Civil & Electrical work

0 As-built under progress


0 Completed, Rectification Work is under Progress
0 Completed, Rectification Work is under Progress
0
-15 1/07/2O17 6/07/2O17
0 Parallely with Civil & Electrical work
0 Parallely with Civil & Electrical work

-21 1/07/2O17 6/07/2O17 Demolition work by civil dept


-5
-5
-60
-5 As-built under progress & parelelly with civil
-5 Installation of Sanatary fixtures after Civil Work & Parrallely
-10 Installation of Sanatary fixtures after Civil Work & Parrallely
-25 Installation of Sanatary fixtures after Civil Work & Parrallely, PR N0- 39 40 & 41 Pending, ISSUE 2
-54 Installation of Sanatary fixtures after Civil Work & Parrallely, PR N0- 39 40 & 41 Pending, ISSUE 2
-70
-70

-5
As-built under progress & parelelly with civil

-5 Remaining Paralelly with civil

-10 Remaining Paralelly with civil

-15 Up to 80%, Remaining Parallely with civil

-31 Up to 80%, Remaining Parallely with civil, ISSUE2

-80
-2 Snag work is pending, Social Area Work under progress
-2 Snag work is pending, Social Area Work under progress
-14 1/07/2O17 6/07/2O17
-40 1/07/2O17 6/07/2O17
-10 Sprinkler head installation is pending move parrellely with Civil,
-8 1/07/2O17 6/07/2O17 Sprinkler head installation & Dropping is pending move parrellely with Civil,
-14 1/07/2O17 6/07/2O17 ISSUE 2 & move parallely with civil

Major Issues
Comments Status

Schedule as per 12 manpower from each Sub-Contractor consistently

Remaining Purchase Requests & Pending Items Should be delivered ,