Вы находитесь на странице: 1из 177

Relazione illustrativa e di calcolo Progetto Definitivo

Indice

1 PREMESSA E DESCRIZIONE DELLE OPERE ...............................................................................................3

2 FASI COSTRUTTIVE .................................................................................................................................4

3 QUADRO NORMATIVO ............................................................................................................................5

4 MATERIALI .............................................................................................................................................7

4.1 Durabilita..............................................................................................................................................7
4.2 Classe di esposizione ambientale...........................................................................................................7
4.3 Classe di resistenza................................................................................................................................9
4.4 Copriferro ............................................................................................................................................13
4.5 Materiali da progetto ...........................................................................................................................16

5 ANALISI DEI CARICHI ............................................................................................................................19

5.1 Peso proprio.........................................................................................................................................19


5.2 Permanenti portati................................................................................................................................19
5.3 Spinta delle terre e sovraccarico variabile a tergo della spalla ............................................................19
5.4 Azione termica.....................................................................................................................................20
5.5 Variabili ...............................................................................................................................................20
5.5.1 Definizione delle corsie convenzionali...................................................................................................................20
5.5.2 Schemi di Carico ....................................................................................................................................................21
5.5.3 Categorie Stradali ...................................................................................................................................................21
5.5.4 Disposizione dei carichi mobili ..............................................................................................................................22

5.6 Azione longitudinale di frenamento o di accelerazione.......................................................................23


5.7 Azione del vento..................................................................................................................................23
5.7.1 Velocit di riferimento ...........................................................................................................................................23
5.7.2 Pressione cinetica di riferimento ............................................................................................................................24
5.7.3 Coefficiente di esposizione.....................................................................................................................................24
5.7.4 Coefficiente dinamico ............................................................................................................................................25
5.7.5 Coefficiente di forma..............................................................................................................................................25
5.7.6 Pressione del vento.................................................................................................................................................25

5.8 Azione sismica.....................................................................................................................................25


5.9 Combinazioni di carico........................................................................................................................30

6 MODELLAZIONE AGLI ELEMENTI FINITI (FEM) ...................................................................................46

7 VERIFICA IMPALCATO ..........................................................................................................................48

8 VERIFICA SOLETTA ...............................................................................................................................51

9 VERIFICA APPARECCHI DI APPOGGIO ...................................................................................................53

9.1 Appoggio unidirezionale trasversale_Spalla S01 ................................................................................54


9.2 Appoggio fisso_Spalla S01..................................................................................................................60
9.3 Appoggio unidirezionale longitudinale_Spalla S02 ............................................................................62

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 1
Relazione illustrativa e di calcolo Progetto Definitivo

9.4 Appoggio multidirezionale_Spalla S02...............................................................................................64


9.5 Appoggio unidirezionale longitudinale_Pile P01-P02 ........................................................................70
9.6 Appoggio multidirezionale_Pile P01-P02 ...........................................................................................77

10 VERIFICA PILE ......................................................................................................................................85


10.1 Verifica sezione di base pila ................................................................................................................85
10.2 Verifica fondazione pila ......................................................................................................................92
10.2.1 Azione verticale sul palo ........................................................................................................................................92
10.2.2 Momento agente sul palo......................................................................................................................................100
10.2.3 Verifica capacit portante palo .............................................................................................................................108
10.2.4 Verifica strutturale palo D1200mm ......................................................................................................................110

11 VERIFICA SPALLE .........................................................................................................................111


11.1 Verifica fondazione spalla S01..........................................................................................................112
11.1.1 Azione verticale sul palo ......................................................................................................................................112
11.1.2 Momento agente sul palo......................................................................................................................................121
11.1.3 Verifica capacit portante palo .............................................................................................................................124
11.1.4 Verifica strutturale palo D1000mm ......................................................................................................................126

11.2 Verifica fondazione spalla S02..........................................................................................................128


11.2.1 Azione verticale sul palo ......................................................................................................................................128
11.2.2 Momento agente sul palo......................................................................................................................................137
11.2.3 Verifica capacit portante palo .............................................................................................................................140
11.2.4 Verifica strutturale palo D1000mm ......................................................................................................................142

12 VERIFICA MURO NUOVA ROTONDA ....................................................................................................144

ALLEGATO A: Relazione illustrativa e di calcolo del ponte provvisorio in acciaio tipo Bailey e
del ponte tecnologico temporaneo piperack

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 2
Relazione illustrativa e di calcolo Progetto Definitivo

1 PREMESSA E DESCRIZIONE DELLE OPERE

Oggetto della presente relazione sono le verifiche strutturali nellambito del progetto definitivo
di nuovi parcheggi a servizio del complesso monumentale della Reggia di Venaria e di un nuovo
ponte sul torrente Ceronda nel Comune di Venaria Reale.
Nello specifico verranno analizzati nel seguito i vari componenti del ponte in oggetto.
Lopera, classificabile ai sensi del DM2008 come ponte di prima categoria, caratterizzata da
una lunghezza complessiva di 80m circa e da una larghezza di 15.50m comprendente due corsie
per gli autoveicoli, due banchine e un marciapiede per ogni senso di marcia.
E prevista la realizzazione di due spalle (S01 e S02) sulle due sponde del fiume e di due pile in
alveo (P1 e P2), il tutto su fondazioni indirette. Sono infatti previsti pali di fondazione di
diametro 1000mm e 1200mm rispettivamente.
La quota di pelo libero dellacqua TR200 di 253.50m, il che considerando un franco di 1m,
porta a considerare come quota minima di intradosso del ponte a 254.50m. Da progetto, si
posizionato lintradosso del ponte in mezzeria alla quota assoluta di 254.99m.
Il ponte stato posizionato planimetricamente in modo che lasse longitudinale del ponte non sia
perpendicolare alle sponde del fiume ma bens inclinato di circa 30. Le spalle, le pile e i traversi
dellimpalcato sono invece allincirca parallele allandamento del torrente Ceronda.

Limpalcato costituito da travi prefabbricate in calcestruzzo precompresse e dal getto di una


soletta in c.a. su predalles dello spessore complessivo di 30cm. Sono presenti cavi di post-
tensione longitudinale nella trave e nella soletta e cavi di post-tensione trasversale dei traversi.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 3
Relazione illustrativa e di calcolo Progetto Definitivo

Le luci previste sono di 26.29m tra spalla e pila e di 26.70m tra le due pile. Limpalcato
appoggia sulle spalle e sulle pile su opportuni apparecchi di appoggio in acciaio-teflon a disco di
elastomero incapsulato, analizzati nel dettaglio nei capitoli che seguono.

In relazione alle caratteristiche geomeccaniche del sito si fatto riferimento alla


caratterizzazione geotecnica dei materiali a cura del Dott.Ing.Geol. Giuseppe Massone.

2 FASI COSTRUTTIVE

Lintervento in oggetto prevede innanzitutto la costruzione del ponte provvisorio in acciaio tipo
Bailey e la conseguente deviazione del traffico su tale ponte.
Si procede poi con la demolizione del ponte esistente, con la realizzazione di un piperack
impiantistico e con la demolizione di una porzione del manto stradale per la realizzazione della
spalla sud (S01).
Una volta realizzata una penisola provvisionale ed infisse le palancole viene costruita la pila 1 in
alveo. Dopo aver opportunamente scavato viene realizzata la spalla sud.
Asportato il terreno per la realizzazione della pila 1 e riempito con materiale di riporto lo scavo
della spalla sud, si realizza come gi fatto per la pila 1 una penisola provvisionale con massi di
contenimento e materiali da rilevato e dopo aver infisso le palancole si procede alla costruzione
della pila 2. Dopo aver opportunamente scavato viene realizzata la spalla nord.
Asportato il terreno per la realizzazione della pila 2 e riempito con materiale di riporto lo scavo
della spalla nord, vengono posati gli elementi prefabbricati autoportanti da spalla a pila, da pila a
pila, da pila a spalla.
Realizzati i traversi in opera e le suture longitudinali, si procede con la post-tensione
longitudinale e dei traversi. Posate le predalles, si getta la soletta e si post-tendono i cavi della
soletta a cavallo della pila. Per ultimo si chiudono le tasche di precompressione.
In ultima fase si smonta il ponte provvisorio tipo Bailey in acciaio e si devia il traffico stradale
sul nuovo ponte.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 4
Relazione illustrativa e di calcolo Progetto Definitivo

3 QUADRO NORMATIVO
Decreto del Presidente della Repubblica 6 giugno 2001, n. 380
Testo unico delle disposizioni legislative e regolamentari in materia edilizia Circ. n.11651 del
14/02/1974
DM 14/01/2008, Norme Tecniche per le Costruzioni
Normativa tecnica di riferimento. Essendo un documento generale di carattere prestazionale per
la definizione di parametri specifici e per le regole di dettaglio, come previsto dal Decreto stesso,
ci si riferiti alle seguenti normative:
Ministero delle infrastrutture e dei Trasporti, circolare n. 617 del 2 febbraio 2009
Istruzioni per lapplicazione delle Norme tecniche per le costruzioni di cui al D.M. 14 Gennaio
2008.

UNI EN 1990:2006
Eurocodice Criteri generali di progettazione strutturale
UNI EN 1991-1-1:2004
Eurocodice 1 Azioni sulle strutture Parte 1-1: Azioni in Generale Pesi per unit di volume,
pesi propri e sovraccarichi per gli edifici.
UNI EN 1991-1-4:2005
Eurocodice 1 Azioni sulle strutture Parte 1-4: Azioni in Generale Azioni del Vento
UNI EN 1992-1-1:2005
Eurocodice 2 Progettazione delle strutture di calcestruzzo Parte 1-1: Regole generali e regole
per gli edifici.
UNI EN 1993-1-1:2005
Eurocodice 3 - Progettazione delle strutture di acciaio Parte 1-1: Regole generali e regole per
gli edifici.
UNI EN 1998-1:2005
Eurocodice 8 - Progettazione delle strutture per la resistenza sismica Parte 1: Regole generali,
azioni sismiche e regole per gli edifici.
UNI EN 206-1:2006
Calcestruzzo Parte 1: Specificazione, prestazione e conformit.
UNI 11104:2004
Calcestruzzo: Specificazione, prestazione e conformit. Istruzioni complementari per
lapplicazione della EN 206-1

Linee guida per la messa in opera del calcestruzzo strutturale e per la valutazione delle
caratteristiche meccaniche del calcestruzzo indurito mediante prove non distruttive (Febbraio
2008)

Circ. Min. LL.PP. 14.02.1974, n.11951


Applicazione della legge 05.11.1971, n. 1086
Circ. Min. LL.PP. 31.07.1979, n.19581
Legge 05.11.1971, n. 1086, art. 7- Collaudo Statico
Circ. Min. LL.PP. 23.10.1979, n.19777
Competenza amministrativa: Legge 05.11.1971, n. 1086 02.02.1974, n.64
Circ. Min. LL.PP. 09.01.1980, n.20049

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 5
Relazione illustrativa e di calcolo Progetto Definitivo

Istruzioni relative ai controlli sul conglomerato cementizio adoperato per le strutture in cemento
armato.
Circ. Min. LL.PP. 01.09.1987, n.29010
Legge 05.11.1971, n. 1086 DM 27.07.1985, Controllo dei materiali in genere e degli acciai per
cemento armato normale in particolare.
CNR-DT 207/2008
Istruzioni per la valutazione delle azioni e degli effetti del vento sulle costruzioni.

Legislazione regionale di riferimento


Legge regionale 9 maggio 1988, n.27
Norme sullosservanza delle disposizioni sismiche ed attuazione della rticolo 20 della legge 10
dicembre 1981, n. 741

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 6
Relazione illustrativa e di calcolo Progetto Definitivo

4 MATERIALI

4.1 Durabilita
Il presente capitolo consiste nella valutazione dei requisiti di durabilit richiesti.
Una struttura durevole deve soddisfare i requisisti di attitudine al servizio, resistenza e stabilit
durante la sua vita utile di progetto, senza presentare perdite significative di funzionalit n
richiedere manutenzione straordinaria eccessiva.
La protezione delle armature dacciaio contro la corrosione dipende dalla massa volumica,dalla
qualit e dallo spessore del copriferro di calcestruzzo e dalla fessurazione. La massa volumica e
la qualit del copriferro si ottengono controllando il massimo rapporto acqua/cemento e il
minimo contenuto di cemento e possono essere associate ad una classe di resistenza minima del
calcestruzzo.
Oggetto di questo capitolo sono le strutture in calcestruzzo armato di peso normale delle quali
vengono fornite le caratteristiche in termini di classe di resistenza, composizione e copriferro.

4.2 Classe di esposizione ambientale


Le condizioni di esposizione sono le condizioni chimiche e fisiche alle quali la struttura
esposta, in aggiunta alle azioni meccaniche.
Le condizioni ambientali sono classificate secondo il prospetto 4.1 dellEurocodice 2, basato
sulla EN 206-1.
La classe di esposizione ambientale per le strutture in elevazione (pile e spalle) la XC3
corrispondente a strutture soggette a corrosione indotta da carbonatazione in condizioni di
umidit moderata.
Le strutture di fondazione (plinti delle pile e delle spalle) e i pali sono invece soggette a
corrosione indotta da carbonatazione per contatto con acqua in condizioni di bagnato-raramente
asciutto. Condizioni queste che corrispondono alla classe XC2.
La soletta di impalcato da considerarsi in un ambiente soggetto a corrosione indotta da
carbonatazione in condizioni cicliche di bagnato e asciutto e per di pi soggetto a cicli di
gelo/disgelo in condizioni di elevata saturazione dacqua con antigelo. Situazione questa tipica di
impalcati da ponte esposti ad agenti antigelo e per tali ragioni classificati come XC4-XF4.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 7
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 8
Relazione illustrativa e di calcolo Progetto Definitivo

4.3 Classe di resistenza


Poich la composizione del calcestruzzo influenza sia la protezione delle armature che la
resistenza del calcestruzzo agli attacchi, vengono fornite nellappendice E dellEurocodice 2 le
classi di resistenza indicative per le diverse classi di esposizione.

Nel caso di strutture soggette a corrosione indotta da carbonatazione in condizioni di umidit


moderata come sono le strutture in elevazione (pile e spalle) in oggetto in classe di esposizione
XC3, la classe di resistenza del calcestruzzo indicativa la C30/37.
Per le strutture di fondazione (plinti delle pile e delle spalle) e i pali, classificate come XC2, la
classe di resistenza del calcestruzzo indicativa la C25/30.
La soletta di impalcato in classe di esposizione XC4-XF4, la classe di resistenza del calcestruzzo
indicativa la C30/37.
Per la scelta dei valori limite per la composizione e le propriet del calcestruzzo in relazione alle
classi di esposizione si fa anche riferimento allappendice F della UNI 206-1.
I valori riportati nel prospetto F.1 presuppongono una durata prevista della struttura di 50 anni,
luso di cemento tipo CEM I in conformit alla EN 197-1 e dellaggregato avente dimensione
nominale massima compresa tra 20 mm e 32 mm.
Le classi di resistenza minima sono desunte dalla relazione tra il rapporto acqua/cemento e la
classe di resistenza del calcestruzzo realizzato con un cemento di classe di resistenza 32,5.
Anche per la UNI 206-1 come per lEurocodice 2 la classe di resistenza minima corrispondente
ad una classe di esposizione XC3 la C30/37 cos come per la soletta di impalcato in classe
XC4-XF4 mentre per le fondazioni in classe XC2 la classe minima la C25/30.
La normative UNI 206-1 fornisce inoltre il valore massimo del rapporto acqua/cemento e il
minimo contenuto di cemento richiesto.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 9
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 10
Relazione illustrativa e di calcolo Progetto Definitivo

La norma UNI 11104:2004 contiene le istruzioni complementari per lapplicazione in Italia della
EN 206-1. Il prospetto 4 della UNI 11104:2004 fornisce i valori limite per la composizione e le
propriet del calcestruzzo in relazione alle classi di esposizione.
I valori riportati nel prospetto 4 sono idonei per i cementi di classe 32.5 e 42.5 conformi alla UNI
EN 197-1 e ad un aggregato avente dimensione massima del granulo compresa fra 20 mm e 32
mm.
Per il cemento di classe 52.5 devono essere rispettati i limiti del prospetto 4 relativi al rapporto
acqua/cemento e al dosaggio minimo di cemento, mentre i valori di resistenza minima devono
essere opportunamente elevati.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 11
Relazione illustrativa e di calcolo Progetto Definitivo

La norma UNI 11104:2004 indica che la classe di resistenza minima corrispondente ad una
classe di esposizione XC3 la C28/35, per la soletta di impalcato in classe XC4-XF4 la classe di
resistenza minima richiesta la C32/40 mentre per le fondazione in classe XC2 la C25/30.
Il DM 2008 al capitolo 4 nella tabella 4.1.I fornisce le varie classi di resistenza disponibili:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 12
Relazione illustrativa e di calcolo Progetto Definitivo

Definite quelle che sono le classi di resistenza minima indicate dalle normative in vigore come
descritto nei paragrafi precedenti, dal punto di vista progettuale si deciso di utilizzare per le
fondazioni un calcestruzzo di classe di resistenza cilindrica/cubica pari a C25/30. Per le strutture
in elevazione viene utilizzato un calcestruzzo di classe di resistenza cilindrica/cubica C28/35
mentre per la soletta di impalcato si scelto un calcestruzzo C32/40.

4.4 Copriferro
Il copriferro la distanza tra la superficie esterna dellarmatura (inclusi staffe, collegamenti e
rinforzi superficiali) pi prossima alla superficie del calcestruzzo e la superficie stessa del
calcestruzzo. Secondo le indicazioni dellEurocodice 2 al punto 4.4.1 definito come il
copriferro minimo cmin pi un margine di progetto per gli scostamenti, cdev.
c nom = c min + c dev
Un copriferro minimo, cmin, deve essere garantito al fine di garantire la corretta trasmissione
delle forze di aderenza, la protezione dellacciaio contro la corrosione e unadeguata resistenza al
fuoco.
Deve essere utilizzato il massimo valore di cmin che soddisfi sia i requisiti relativi alladerenza,
sia quelli relativi alle condizioni ambientali.
cmin = max(cmin,b; cmin,dur + cdur, - cdur,add; 10 mm)
cmin,b: per far s che le forze di aderenza siano trasmesse adeguatamente, e che il
calcestruzzo sia sufficientemente compatto, il copriferro minimo non deve essere
inferiore ai valori di cmin,b dati nel prospetto 4.2:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 13
Relazione illustrativa e di calcolo Progetto Definitivo

Nel caso in esame si considera per le strutture in elevazione e in fondazione:

cmin,dur: copriferro minimo dovuto alle condizioni ambientali. Viene fornito al punto
4.4.1.2 (5) in funzione della classe strutturale e della classe di esposizione ambientale.
La classe strutturale raccomandata per le resistenze indicative del calcestruzzo date
nellappendice E dellEurocodice 2 la S4 e fa riferimento ad una vita utile di progetto di
50 anni. Eventuali modifiche alle classi strutturali sono date nel prospetto 4.3N. Una
volta definita la classe strutturale, i valori raccomandati di cmin,dur sono dati nel prospetto
4.4N per gli acciai da armatura ordinaria e nel prospetto 4.5N per gli acciai da
precompressione.
Nel caso in esame la vita utile di progetto di 50 anni il che significa che sia per le
strutture in elevazione (XC3) che per quelle di fondazione (XC2) che per la soletta di
impalcato (XF4) la classe strutturale la S4.

Definita la classe strutturale, i valori raccomandati di cmin,dur per gli acciai da armatura
ordinaria sono dati nel prospetto 4.4N:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 14
Relazione illustrativa e di calcolo Progetto Definitivo

Se ne deduce che per le strutture in elevazione cmin,dur vale 35 mm, per le strutture in
elevazione assimilabili a solette cmin,dur vale 30 mm mentre per le strutture di fondazione
vale 30mm.
cdur,: margine di sicurezza aggiuntivo assunto pari a 0mm.
cdur,add: riduzione del copriferro quando si ricorre a protezione aggiuntiva. Assunto
pari a 0 mm.
Si ha quindi che per le strutture in elevazione e di fondazione il copriferro minimo vale:
cmin = max(cmin,b; cmin,dur + cdur, - cdur,add; 10 mm) = max(20mm; 25mm; 10 mm) = 25mm
Per la soletta di impalcato il copriferro minimo vale:
cmin = max(cmin,b; cmin,dur + cdur, - cdur,add; 10 mm) = max(20mm; 30mm; 10 mm) = 30mm
Nel calcolo del copriferro nominale, cnom, si deve aumentare il copriferro minimo per tener conto
degli scostamenti (cdev). Il copriferro minimo richiesto deve essere aumentato del valore
assoluto dello scostamento negativo accettato.
Il valore di cdev raccomandato di 10mm.
In conclusione si ha che per le strutture in elevazione il copriferro nominale vale:
c nom = c min + c dev =25+10 = 35mm
Per la soletta di impalcato il copriferro nominale vale:
c nom = c min + c dev =30+10 = 40mm

Al fine di aumentare la durabilit dellopera si assumono i seguentti copriferri:


Strutture in elevazione: 4cm
Strutture di fondazione: 5cm

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 15
Relazione illustrativa e di calcolo Progetto Definitivo

4.5 Materiali da progetto


In definitiva le caratteristiche dei materiali impiegati e i copriferri necessari sono cos riassunti:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 16
Relazione illustrativa e di calcolo Progetto Definitivo

Acciaio per carpenteria S355

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 17
Relazione illustrativa e di calcolo Progetto Definitivo

PREFABBRICATI

per cassoni prefabbricati: Rck (28 gg) 50 MPa e Rckj 30 MPa


Tensione massima di compressione del calcestruzzo nelle condizioni di esercizio
Rara) c < 0,60 fck = 24 MPa
Quasi permanente) c < 0,45 fck = 18 Mpa

Tensioni iniziali nel calcestruzzo


Allatto della precompressione le tensioni di compressione non debbono superare il valore:
c < 0,70 fckj = 17.5 MPa

Acciaio per precompressione


Trefoli 0,6 Super (1,50 cmq) a basso rilassamento stabilizzato
fptk = 1860 MPa
fpt(1)k = 1670 MPa
spi = 1390 MPa (tensione di tesatura iniziale effettiva)
Le tensioni iniziali allatto della tesatura dei cavi devono rispettare le pi restrittive delle
seguenti limitazioni:
spi < 0,90 fp(0,1)k= 1503Mpa
spi < 0,80 fptk = 1488 MPa

Nello specifico sono presenti i seguenti cavi:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 18
Relazione illustrativa e di calcolo Progetto Definitivo

5 ANALISI DEI CARICHI

Le azioni considerate nella progettazione del ponte stradale in oggetto sono:


pesi propri (g1)
permanenti portati (g2)
spinta delle terre (g3)
termica (3)
variabili da traffico (q1)
azione longitudinale di frenamento o di accelerazione (q3)
vento (q5)
neve (trascurabile a fronte del carico variabile)
azioni sismiche (q6)

5.1 Peso proprio


I pesi propri degli elementi strutturali vengono valutati in automatico nel modello di calcolo
tenendo conto delle diverse sezioni e dei diversi materiali.
Peso specifico utilizzato per il c.a.: c.a.=25kN/m3

5.2 Permanenti portati


I carichi permanenti portati sono costituiti da:
- pavimentazione stradale
- marciapiedi
- sicurvia
- parapetti
Il tutto stato stimato pari a 9.5kN/m2.

5.3 Spinta delle terre e sovraccarico variabile a tergo della spalla


La spinta che la terra produce su un muro di contenimento strettamente legata alla deformabilit di
questultimo. Una struttura rigida, incapace di subire deformazioni anche di piccola entit subir una
pressione pari ai carichi verticali moltiplicati per il coefficiente di spinta a riposo K0. Se essa invece in
grado di ruotare, traslare o deformarsi, la pressione sar legata al coefficiente di spinta attiva Ka.
Nel nostro caso per il calcolo del muro di spalla si andr a considerare la spinta a riposo.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 19
Relazione illustrativa e di calcolo Progetto Definitivo

5.4 Azione termica


In termini di variazioni termiche, ai sensi del paragrafo 5.2.2.5.2 delle NTC 2008 si considera
una variazione uniforme di temperatura pari a 15C.

5.5 Variabili

Si fa riferimento al D.M. 14.01.08 norme tecniche, di cui si riporta una breve sintesi.

5.5.1 Definizione delle corsie convenzionali

Le larghezze wl delle corsie


convenzionali su una carreggiata ed il
massimo numero (intero) possibile di tali
corsie su di essa sono indicati nel
prospetto seguente (Fig. 5.1.1 e Tab.
5.1.I).

Se non diversamente specificato, qualora la carreggiata di un impalcato da ponte sia divisa in due parti
separate da una zona spartitraffico centrale, si distinguono i casi seguenti:
a) se le parti sono separate da una barriera di sicurezza fissa, ciascuna parte, incluse tutte le corsie di
emergenza e le banchine, autonomamente divisa in corsie convenzionali.
b) se le parti sono separate da barriere di sicurezza mobili o da altro dispositivo di ritenuta, lintera
carreggiata, inclusa la zona spartitraffico centrale, divisa in corsie convenzionali.

La disposizione e la numerazione delle corsie va determinata in modo da indurre le pi sfavorevoli


condizioni di progetto. Per ogni singola verifica il numero di corsie da considerare caricate, la loro
disposizione sulla carreggiata e la loro numerazione vanno scelte in modo che gli effetti della
disposizione dei carichi risultino i pi sfavorevoli. La corsia che, caricata, d leffetto pi sfavorevole
numerata come corsia Numero 1; la corsia che d il successivo effetto pi sfavorevole numerata come
corsia Numero 2, ecc.
Quando la carreggiata costituita da due parti separate portate da uno stesso impalcato, le corsie sono
numerate considerando lintera carreggiata, cosicch vi solo una corsia 1, solo una corsia 2 ecc, che
possono appartenere alternativamente ad una delle due parti.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 20
Relazione illustrativa e di calcolo Progetto Definitivo

Quando la carreggiata consiste di due parti separate portate da due impalcati indipendenti, per il progetto
di ciascun impalcato si adottano numerazioni indipendenti. Quando, invece, gli impalcati indipendenti
sono portati da una singola pila o da una singola spalla, per il progetto della pila o della spalla si adotta
ununica numerazione per le due parti.
Per ciascuna singola verifica e per ciascuna corsia convenzionale, si applicano gli Schemi di Carico
definiti nel seguito per una lunghezza e per una disposizione longitudinale, tali da ottenere leffetto pi
sfavorevole.

5.5.2 Schemi di Carico

Le azioni variabili del traffico, comprensive degli effetti dinamici, sono definite dai seguenti Schemi di
Carico:
Schema di Carico 1: costituito da carichi concentrati su due assi in tandem, applicati su impronte di
pneumatico di forma quadrata e lato 0,40 m, e da carichi uniformemente distribuiti come mostrato in Fig.
5.1.2. Questo schema da assumere a riferimento sia per le verifiche globali, sia per le verifiche locali,
considerando un solo carico tandem per corsia, disposto in asse alla corsia stessa. Il carico tandem, se
presente, va considerato per intero.
Schema di Carico 2: costituito da un singolo asse applicato su specifiche impronte di pneumatico di
forma rettangolare, di larghezza 0,60 m ed altezza 0,35 m. Questo schema va considerato autonomamente
con asse longitudinale nella posizione pi gravosa ed da assumere a riferimento solo per verifiche locali.
Qualora sia pi gravoso si considerer il peso di una singola ruota di 200 kN.
Schema di Carico 3: costituito da un carico isolato da 150kN con impronta quadrata di lato 0,40m. Si
utilizza per verifiche locali su marciapiedi non protetti da sicurvia.
Schema di Carico 4: costituito da un carico isolato da 10 kN con impronta quadrata di lato 0,10m. Si
utilizza per verifiche locali su marciapiedi protetti da sicurvia e sulle passerelle pedonali.
Schema di Carico 5: costituito dalla folla compatta, agente con intensit nominale, comprensiva degli
effetti dinamici, di 5 kN/m2. Il valore di combinazione invece di 2,5 kN/m2. Il carico folla deve essere
applicato su tutte le zone significative della superficie di influenza, inclusa larea dello spartitraffico
centrale, ove rilevante.

5.5.3 Categorie Stradali

Limpalcato viene considerato di 1a Categoria: ponti per il transito dei carichi mobili sopra indicati con il
loro intero valore.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 21
Relazione illustrativa e di calcolo Progetto Definitivo

5.5.4 Disposizione dei carichi mobili

Il numero delle colonne di carichi mobili da considerare nel calcolo dei ponti di 1a e 2a
Categoria quello massimo compatibile con la larghezza della carreggiata, comprese le eventuali
banchine di rispetto e per sosta di emergenza, nonch gli eventuali marciapiedi non protetti e di
altezza inferiore a 20 cm, tenuto conto che la larghezza di ingombro convenzionale stabilita per
ciascuna colonna in 3,00 m.

In ogni caso il numero delle colonne non deve essere inferiore a 2, a meno che la larghezza della sede
stradale sia inferiore a 5,40 m. La disposizione dei carichi ed il numero delle colonne sulla carreggiata
saranno volta per volta quelli che determinano le condizioni pi sfavorevoli di sollecitazione per la
struttura, membratura o sezione considerata. Per i ponti di 1a Categoria si devono considerare,
compatibilmente con le larghezze precedentemente definite, le seguenti intensit dei carichi:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 22
Relazione illustrativa e di calcolo Progetto Definitivo

5.6 Azione longitudinale di frenamento o di accelerazione


La forza di frenamento o di accelerazione q3 funzione del carico verticale totale agente sulla corsia
convenzionale n. 1 ed uguale a:

180 kN q3 = 0,6(2Q1k ) + 0,10q1k wl L 900 kN


La forza, applicata a livello della pavimentazione ed agente lungo lasse della corsia, assunta
uniformemente distribuita sulla lunghezza caricata e include gli effetti di interazione.
Lazione frenante massima complessiva vale:

q3 = 0,6(2300) + 0,109 3 80 = 576 kN


Lazione di frenamento agisce al livello della pavimentazione stradale ed applicata nel modello di
calcolo come carico distribuito in direzione dellasse del ponte pari a 576/80=7.2kN/m.

5.7 Azione del vento


Il presente capitolo consiste nella valutazione dellazione del vento come da normativa di
riferimento DM2008. Lazione del vento pu essere convenzionalmente assimilata ad un carico
orizzontale statico, diretto ortogonalmente allasse del ponte e/o diretto nelle direzioni pi
sfavorevoli per alcuni dei suoi elementi. Tale azione si considera agente sulla proiezione nel
piano verticale delle superfici direttamente investite.
La superficie dei carichi transitanti sul ponte esposta al vento si assimila ad una parete
rettangolare continua dellaltezza di 3 m a partire dal piano stradale.

5.7.1 Velocit di riferimento


La velocit di riferimento del vento vb, cos come definita al punto 3.3.2 del DM 2008, il
valore caratteristico della velocit del vento a 10m dal suolo su un terreno di categoria di
esposizione II mediata su 10 minuti e riferita ad un periodo di ritorno di 50 anni.
Lintervento in oggetto classificabile come tipo di costruzione 2 secondo il paragrafo 2.4.1 del
DM 2008, cui corrisponde una vita nominale >50 anni.
Il sito dove sorge la costruzione , in Piemonte, classificato come zona 3 secondo la tabella 3.3.I
del DM 2008 cui corrispondono vb0=25 m/s
a0=1000m
ka=0.01 1/s

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 23
Relazione illustrativa e di calcolo Progetto Definitivo

Poich as, altitudine sul livello del mare del sito dove sorge la costruzione, minore di a0, risulta
che vb= vb0=25m/s.

5.7.2 Pressione cinetica di riferimento


La pressione cinetica di riferimento qb (N/m2) data dallespressione fornita al punto 3.3.6 del
DM 2008:
1 2
qb = vb
2
dove vb la velocit di riferimento del vento
la densit dellaria assunta convenzionalmente costante e pari a 1.25kg/m3
Risulta quindi:
1 2 1
qb = vb = 1.25 25 2 = 390.625 N / m 2
2 2

5.7.3 Coefficiente di esposizione


Il coefficiente di esposizione Ce dipende dallaltezza z sul suolo del punto considerato, dalla
topografia del terreno e dalla categoria di esposizione del sito ove sorge la costruzione.
Considerando la topografia del sito in esame, la classe di rugosit del terreno classificata come
C secondo la tabella 3.3III del DM 2008 mentre la categoria di esposizione corrispondente alla
zona 1 e rugosit C la III a cui corrispondono i seguenti parametri: forniti dalla tabella 3.3II
kr=0.20
z0=0.1m
zmin=5m
In assenza di analisi specifiche che tengano in conto la direzione di provenienza del vento e
leffettiva scabrezza e topografia del terreno che circonda la costruzione, per altezze sul suolo
non maggiori di z=200m, il coefficiente di esposizione dato dalle formule fornite al punto 3.3.7
del DM 2008 a seconda che laltezza z del punto considerato sia maggiore o minore della zmin
corrispondente.
ce ( z ) = k r2 ct ln( z / z 0 )[7 + ct ln( z / z 0 )] per z zmin

ce ( z ) = ce ( z min ) per z < zmin


Il coefficiente di topografia ct posto generalmente uguale a 1 sia per le zone pianeggianti che
per quelle ondulate.
Il coefficiente di esposizione risulta :
ce ( z min = 5m) = k r2 ct ln( z min / z 0 )[7 + ct ln( z min / z 0 )] = 0.20 2 1 ln(5 / 0.1)[7 + 1 ln(5 / 0.1)] = 1.71

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 24
Relazione illustrativa e di calcolo Progetto Definitivo

5.7.4 Coefficiente dinamico


Il coefficiente dinamico tiene conto degli effetti riduttivi associati alla non contemporaneit delle
massime pressioni locali e degli effetti amplificativi dovuti alla risposta dinamica della struttura.
Esso pu essere cautelativamente assunto pari a 1 nelle costruzioni a tipologia ricorrenti quali
edifici di forma regolare non eccedenti 80 m di altezza e capannoni industriali.

5.7.5 Coefficiente di forma


Il coefficiente di forma (o coefficiente aerodinamico) funzione della tipologia e della geometria
della costruzione e del suo orientamento rispetto alla direzione del vento.
Il suo valore ricavato da quanto riportato al punto C3.3.10.1 della Circolare 2 febbraio 2009,
n.617.

5.7.6 Pressione del vento


Definiti i vari parametri come riportato nei paragrafi precedenti, la pressione del vento data
dallespressione:
p=qb ce cp cd
Le pressioni del vento si possono cos riassumere:
z=zmin: p= qb ce cp cd=39.066x1.71x1x1=66.8 kg/m2

Tale pressione del vento applicata nel modello allimpalcato come carico uniformemente
distribuito ortogonale allasse del ponte: 0.668x4.87=3.25kN/m.
Tale carico distribuito produce anche un momento che allasse della soletta dellimpalcato
(Sp.30cm) pari a: 3.25x0.88=2.9kNm/m.

5.8 Azione sismica


Ai sensi del par. 3.2 delle NTC 2008 si proceduto alla definizione di spettri di risposta
adeguati.
Innanzitutto sono state determinate le coordinate dellarea di interesse pari a 451310 lat
NORD e 76310 long EST, quindi sono stati valutati i parametri ag, F0 e T*C in tali coordinate
andando a fare una media pesata tra i valori riportati allallegato B delle NTC per i valori assunti
nei 4 vertici del reticolo allinterno dei quali cade il punto di interesse.
Considerando la vita nominale (2) e la classe duso (IV) dellopera si giunge ad un tempo di
riferimento pari a 100 anni. Sulla base della campagna di indagini geognostiche e della
caratterizzazione geotecnica del sito si pu inoltre classificare il sedime fondale in categoria C
ai sensi della Tab. 3.2.II delle NTC.
I dati di ingresso per la valutazione degli spettri per i differenti SL sono quelli riportati nella
tabella seguente.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 25
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 26
Relazione illustrativa e di calcolo Progetto Definitivo

Pertanto gli spettri di risposta elastici in accelerazione per lo stato limite di salvaguardia per la
vita il seguente:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 27
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 28
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 29
Relazione illustrativa e di calcolo Progetto Definitivo

5.9 Combinazioni di carico

Le combinazioni di carico da considerare per la normativa vigente sono le seguenti.

Ai fini della determinazione dei valori caratteristici delle azioni dovute al traffico, si considerano, le
combinazioni riportate in Tab. 5.1.IV.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 30
Relazione illustrativa e di calcolo Progetto Definitivo

La Tab. 5.1.V fornisce i valori dei coefficienti parziali delle azioni da assumere nellanalisi per la
determinazione degli effetti delle azioni nelle verifiche agli stati limite ultimi.
I valori dei coefficienti 0j, 1j e 2j per le diverse categorie di azioni sono riportati nella Tab.5.1.VI
delle norme tecniche.
Il significato dei simboli il seguente:
G1 coefficiente parziale del peso proprio della struttura, del terreno e dellacqua, quando
pertinente;
G2 coefficiente parziale dei pesi propri degli elementi non strutturali;
Q coefficiente parziale delle azioni variabili da traffico;
Qi coefficiente parziale delle azioni variabili.
Il coefficiente parziale della precompressione si assume pari a p=1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 31
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 32
Relazione illustrativa e di calcolo Progetto Definitivo

Le combinazioni di carico utilizzate nel modello FEM sono le seguenti:

TABLE: Combination Definitions


ComboName ComboType AutoDesign CaseName ScaleFactor
Text Text Yes/No Text Unitless
STR1 Linear Add No G1 1.35
STR1 G2 1.35
STR1 P 1
STR1 MOVE1 1.35
STR1 q5 0.9
STR1 QT 0.72
STR1 q3 0
STR2 Linear Add No G1 1
STR2 G2 1
STR2 P 1
STR2 MOVE1 1.35
STR2 q5 0.9
STR2 QT 0.72
STR2 q3 0
STR3 Linear Add No G1 1.35
STR3 G2 1.35
STR3 P 1
STR3 MOVE1 1.35
STR3 q5 -0.9
STR3 QT 0.72
STR3 q3 0
STR4 Linear Add No G1 1
STR4 G2 1
STR4 P 1
STR4 MOVE1 1.35
STR4 q5 -0.9
STR4 QT 0.72
STR4 q3 0
STR5 Linear Add No G1 1.35
STR5 G2 1.35
STR5 P 1
STR5 MOVE1 1.35
STR5 q5 0.9
STR5 QT -0.72
STR5 q3 0
STR6 Linear Add No G1 1
STR6 G2 1
STR6 P 1
STR6 MOVE1 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 33
Relazione illustrativa e di calcolo Progetto Definitivo

STR6 q5 0.9
STR6 QT -0.72
STR6 q3 0
STR7 Linear Add No G1 1.35
STR7 G2 1.35
STR7 P 1
STR7 MOVE1 1.35
STR7 q5 -0.9
STR7 QT -0.72
STR7 q3 0
STR8 Linear Add No G1 1
STR8 G2 1
STR8 P 1
STR8 MOVE1 1.35
STR8 q5 -0.9
STR8 QT -0.72
STR8 q3 0
STR9 Linear Add No G1 1.35
STR9 G2 1.35
STR9 P 1
STR9 MOVE1 1
STR9 q5 1.5
STR9 QT 0.72
STR9 q3 0
STR10 Linear Add No G1 1.35
STR10 G2 1.35
STR10 P 1
STR10 MOVE1 1
STR10 q5 -1.5
STR10 QT 0.72
STR10 q3 0
STR11 Linear Add No G1 1
STR11 G2 1
STR11 P 1
STR11 MOVE1 1
STR11 q5 1.5
STR11 QT 0.72
STR11 q3 0
STR12 Linear Add No G1 1
STR12 G2 1
STR12 P 1
STR12 MOVE1 1
STR12 q5 -1.5
STR12 QT 0.72

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 34
Relazione illustrativa e di calcolo Progetto Definitivo

STR12 q3 0
STR13 Linear Add No G1 1.35
STR13 G2 1.35
STR13 P 1
STR13 MOVE1 1
STR13 q5 1.5
STR13 QT -0.72
STR13 q3 0
STR14 Linear Add No G1 1.35
STR14 G2 1.35
STR14 P 1
STR14 MOVE1 1
STR14 q5 -1.5
STR14 QT -0.72
STR14 q3 0
STR15 Linear Add No G1 1
STR15 G2 1
STR15 P 1
STR15 MOVE1 1
STR15 q5 1.5
STR15 QT -0.72
STR15 q3 0
STR16 Linear Add No G1 1
STR16 G2 1
STR16 P 1
STR16 MOVE1 1
STR16 q5 -1.5
STR16 QT -0.72
STR16 q3 0
STR17 Linear Add No G1 1.35
STR17 G2 1.35
STR17 P 1
STR17 MOVE1 1
STR17 q5 0.9
STR17 QT 1.2
STR17 q3 0
STR18 Linear Add No G1 1.35
STR18 G2 1.35
STR18 P 1
STR18 MOVE1 1
STR18 q5 -0.9
STR18 QT 1.2
STR18 q3 0
STR19 Linear Add No G1 1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 35
Relazione illustrativa e di calcolo Progetto Definitivo

STR19 G2 1
STR19 P 1
STR19 MOVE1 1
STR19 q5 0.9
STR19 QT 1.2
STR19 q3 0
STR20 Linear Add No G1 1
STR20 G2 1
STR20 P 1
STR20 MOVE1 1
STR20 q5 -0.9
STR20 QT 1.2
STR20 q3 0
STR21 Linear Add No G1 1.35
STR21 G2 1.35
STR21 P 1
STR21 MOVE1 1
STR21 q5 0.9
STR21 QT -1.2
STR21 q3 0
STR22 Linear Add No G1 1.35
STR22 G2 1.35
STR22 P 1
STR22 MOVE1 1
STR22 q5 -0.9
STR22 QT -1.2
STR22 q3 0
STR23 Linear Add No G1 1
STR23 G2 1
STR23 P 1
STR23 MOVE1 1
STR23 q5 0.9
STR23 QT -1.2
STR23 q3 0
STR24 Linear Add No G1 1
STR24 G2 1
STR24 P 1
STR24 MOVE1 1
STR24 q5 -0.9
STR24 QT -1.2
STR24 q3 0
STR25 Linear Add No G1 1.35
STR25 G2 1.35
STR25 P 1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 36
Relazione illustrativa e di calcolo Progetto Definitivo

STR25 MOVE1 1
STR25 q5 0.9
STR25 QT 0.72
STR25 q3 1.35
STR26 Linear Add No G1 1.35
STR26 G2 1.35
STR26 P 1
STR26 MOVE1 1
STR26 q5 -0.9
STR26 QT 0.72
STR26 q3 1.35
STR27 Linear Add No G1 1.35
STR27 G2 1.35
STR27 P 1
STR27 MOVE1 1
STR27 q5 0.9
STR27 QT -0.72
STR27 q3 1.35
STR28 Linear Add No G1 1.35
STR28 G2 1.35
STR28 P 1
STR28 MOVE1 1
STR28 q5 -0.9
STR28 QT -0.72
STR28 q3 1.35
STR29 Linear Add No G1 1
STR29 G2 1
STR29 P 1
STR29 MOVE1 1
STR29 q5 0.9
STR29 QT 0.72
STR29 q3 1.35
STR30 Linear Add No G1 1
STR30 G2 1
STR30 P 1
STR30 MOVE1 1
STR30 q5 -0.9
STR30 QT 0.72
STR30 q3 1.35
STR31 Linear Add No G1 1
STR31 G2 1
STR31 P 1
STR31 MOVE1 1
STR31 q5 0.9

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 37
Relazione illustrativa e di calcolo Progetto Definitivo

STR31 QT -0.72
STR31 q3 1.35
STR32 Linear Add No G1 1
STR32 G2 1
STR32 P 1
STR32 MOVE1 1
STR32 q5 -0.9
STR32 QT -0.72
STR32 q3 1.35
CHR1 Linear Add No G1 1
CHR1 G2 1
CHR1 P 1
CHR1 MOVE1 1
CHR1 q5 0.6
CHR1 QT 0.6
CHR1 q3 0
CHR2 Linear Add No G1 1
CHR2 G2 1
CHR2 P 1
CHR2 MOVE1 1
CHR2 q5 -0.6
CHR2 QT 0.6
CHR2 q3 0
CHR3 Linear Add No G1 1
CHR3 G2 1
CHR3 P 1
CHR3 MOVE1 1
CHR3 q5 0.6
CHR3 QT -0.6
CHR3 q3 0
CHR4 Linear Add No G1 1
CHR4 G2 1
CHR4 P 1
CHR4 MOVE1 1
CHR4 q5 -0.6
CHR4 QT -0.6
CHR4 q3 0
CHR5 Linear Add No G1 1
CHR5 G2 1
CHR5 P 1
CHR5 MOVE1 0.75
CHR5 q5 1
CHR5 QT 0.6
CHR5 q3 0

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 38
Relazione illustrativa e di calcolo Progetto Definitivo

CHR6 Linear Add No G1 1


CHR6 G2 1
CHR6 P 1
CHR6 MOVE1 0.75
CHR6 q5 1
CHR6 QT -0.6
CHR6 q3 0
CHR7 Linear Add No G1 1
CHR7 G2 1
CHR7 P 1
CHR7 MOVE1 0.75
CHR7 q5 -1
CHR7 QT 0.6
CHR7 q3 0
CHR8 Linear Add No G1 1
CHR8 G2 1
CHR8 P 1
CHR8 MOVE1 0.75
CHR8 q5 -1
CHR8 QT -0.6
CHR8 q3 0
CHR9 Linear Add No G1 1
CHR9 G2 1
CHR9 P 1
CHR9 MOVE1 0.75
CHR9 q5 0.6
CHR9 QT 1
CHR9 q3 0
CHR10 Linear Add No G1 1
CHR10 G2 1
CHR10 P 1
CHR10 MOVE1 0.75
CHR10 q5 -0.6
CHR10 QT 1
CHR10 q3 0
CHR11 Linear Add No G1 1
CHR11 G2 1
CHR11 P 1
CHR11 MOVE1 0.75
CHR11 q5 0.6
CHR11 QT -1
CHR11 q3 0
CHR12 Linear Add No G1 1
CHR12 G2 1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 39
Relazione illustrativa e di calcolo Progetto Definitivo

CHR12 P 1
CHR12 MOVE1 0.75
CHR12 q5 -0.6
CHR12 QT -1
CHR12 q3 0
CHR13 Linear Add No G1 1
CHR13 G2 1
CHR13 P 1
CHR13 MOVE1 0.75
CHR13 q5 0.6
CHR13 QT 0.6
CHR13 q3 1
CHR14 Linear Add No G1 1
CHR14 G2 1
CHR14 P 1
CHR14 MOVE1 0.75
CHR14 q5 -0.6
CHR14 QT 0.6
CHR14 q3 1
CHR15 Linear Add No G1 1
CHR15 G2 1
CHR15 P 1
CHR15 MOVE1 0.75
CHR15 q5 0.6
CHR15 QT -0.6
CHR15 q3 1
CHR16 Linear Add No G1 1
CHR16 G2 1
CHR16 P 1
CHR16 MOVE1 0.75
CHR16 q5 -0.6
CHR16 QT -0.6
CHR16 q3 1
FRQ1 Linear Add No G1 1
FRQ1 G2 1
FRQ1 P 1
FRQ1 MOVE1 0.75
FRQ1 q5 0.2
FRQ1 QT 0.6
FRQ1 q3 0
FRQ2 Linear Add No G1 1
FRQ2 G2 1
FRQ2 P 1
FRQ2 MOVE1 0.75

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 40
Relazione illustrativa e di calcolo Progetto Definitivo

FRQ2 q5 -0.2
FRQ2 QT 0.6
FRQ2 q3 0
FRQ3 Linear Add No G1 1
FRQ3 G2 1
FRQ3 P 1
FRQ3 MOVE1 0.75
FRQ3 q5 0.2
FRQ3 QT -0.6
FRQ3 q3 0
FRQ4 Linear Add No G1 1
FRQ4 G2 1
FRQ4 P 1
FRQ4 MOVE1 0.75
FRQ4 q5 -0.2
FRQ4 QT -0.6
FRQ4 q3 0
QP1 Linear Add No G1 1
QP1 G2 1
QP1 P 1
QP1 MOVE1 0
QP1 q5 0
QP1 QT 0.5
QP1 q3 0
QP2 Linear Add No G1 1
QP2 G2 1
QP2 P 1
QP2 MOVE1 0
QP2 q5 0
QP2 QT -0.5
QP2 q3 0
QKE1 Linear Add No G1 1
QKE1 G2 1
QKE1 P 1
QKE1 MOVE1 0.2
QKE1 q5 0
QKE1 QT 0.5
QKE1 q3 0
QKE1 RSX 1
QKE1 RSY 0.3
QKE2 Linear Add No G1 1
QKE2 G2 1
QKE2 P 1
QKE2 MOVE1 0.2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 41
Relazione illustrativa e di calcolo Progetto Definitivo

QKE2 q5 0
QKE2 QT -0.5
QKE2 q3 0
QKE2 RSX 1
QKE2 RSY 0.3
QKE3 Linear Add No G1 1
QKE3 G2 1
QKE3 P 1
QKE3 MOVE1 0.2
QKE3 q5 0
QKE3 QT 0.5
QKE3 q3 0
QKE3 RSX 0.3
QKE3 RSY 1
QKE4 Linear Add No G1 1
QKE4 G2 1
QKE4 P 1
QKE4 MOVE1 0.2
QKE4 q5 0
QKE4 QT -0.5
QKE4 q3 0
QKE4 RSX 0.3
QKE4 RSY 1
Env_rara Envelope No CHR1 1
Env_rara CHR10 1
Env_rara CHR11 1
Env_rara CHR12 1
Env_rara CHR13 1
Env_rara CHR14 1
Env_rara CHR15 1
Env_rara CHR16 1
Env_rara CHR2 1
Env_rara CHR3 1
Env_rara CHR4 1
Env_rara CHR5 1
Env_rara CHR6 1
Env_rara CHR7 1
Env_rara CHR8 1
Env_rara CHR9 1
CHRnoG1_1 Linear Add No G1 0
CHRnoG1_1 G2 1
CHRnoG1_1 P 1
CHRnoG1_1 MOVE1 1
CHRnoG1_1 q5 0.6

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 42
Relazione illustrativa e di calcolo Progetto Definitivo

CHRnoG1_1 QT 0.6
CHRnoG1_1 q3 0
CHRnoG1_2 Linear Add No G1 0
CHRnoG1_2 G2 1
CHRnoG1_2 P 1
CHRnoG1_2 MOVE1 1
CHRnoG1_2 q5 -0.6
CHRnoG1_2 QT 0.6
CHRnoG1_2 q3 0
CHRnoG1_3 Linear Add No G1 0
CHRnoG1_3 G2 1
CHRnoG1_3 P 1
CHRnoG1_3 MOVE1 1
CHRnoG1_3 q5 0.6
CHRnoG1_3 QT -0.6
CHRnoG1_3 q3 0
CHRnoG1_4 Linear Add No G1 0
CHRnoG1_4 G2 1
CHRnoG1_4 P 1
CHRnoG1_4 MOVE1 1
CHRnoG1_4 q5 -0.6
CHRnoG1_4 QT -0.6
CHRnoG1_4 q3 0
CHRnoG1_5 Linear Add No G1 0
CHRnoG1_5 G2 1
CHRnoG1_5 P 1
CHRnoG1_5 MOVE1 0.75
CHRnoG1_5 q5 1
CHRnoG1_5 QT 0.6
CHRnoG1_5 q3 0
CHRnoG1_6 Linear Add No G1 0
CHRnoG1_6 G2 1
CHRnoG1_6 P 1
CHRnoG1_6 MOVE1 0.75
CHRnoG1_6 q5 1
CHRnoG1_6 QT -0.6
CHRnoG1_6 q3 0
CHRnoG1_7 Linear Add No G1 0
CHRnoG1_7 G2 1
CHRnoG1_7 P 1
CHRnoG1_7 MOVE1 0.75
CHRnoG1_7 q5 -1
CHRnoG1_7 QT 0.6
CHRnoG1_7 q3 0

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 43
Relazione illustrativa e di calcolo Progetto Definitivo

CHRnoG1_8 Linear Add No G1 0


CHRnoG1_8 G2 1
CHRnoG1_8 P 1
CHRnoG1_8 MOVE1 0.75
CHRnoG1_8 q5 -1
CHRnoG1_8 QT -0.6
CHRnoG1_8 q3 0
CHRnoG1_9 Linear Add No G1 0
CHRnoG1_9 G2 1
CHRnoG1_9 P 1
CHRnoG1_9 MOVE1 0.75
CHRnoG1_9 q5 0.6
CHRnoG1_9 QT 1
CHRnoG1_9 q3 0
CHRnoG1_10 Linear Add No G1 0
CHRnoG1_10 G2 1
CHRnoG1_10 P 1
CHRnoG1_10 MOVE1 0.75
CHRnoG1_10 q5 -0.6
CHRnoG1_10 QT 1
CHRnoG1_10 q3 0
CHRnoG1_11 Linear Add No G1 0
CHRnoG1_11 G2 1
CHRnoG1_11 P 1
CHRnoG1_11 MOVE1 0.75
CHRnoG1_11 q5 0.6
CHRnoG1_11 QT -1
CHRnoG1_11 q3 0
CHRnoG1_12 Linear Add No G1 0
CHRnoG1_12 G2 1
CHRnoG1_12 P 1
CHRnoG1_12 MOVE1 0.75
CHRnoG1_12 q5 -0.6
CHRnoG1_12 QT -1
CHRnoG1_12 q3 0
CHRnoG1_13 Linear Add No G1 0
CHRnoG1_13 G2 1
CHRnoG1_13 P 1
CHRnoG1_13 MOVE1 0.75
CHRnoG1_13 q5 0.6
CHRnoG1_13 QT 0.6
CHRnoG1_13 q3 1
CHRnoG1_14 Linear Add No G1 0
CHRnoG1_14 G2 1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 44
Relazione illustrativa e di calcolo Progetto Definitivo

CHRnoG1_14 P 1
CHRnoG1_14 MOVE1 0.75
CHRnoG1_14 q5 -0.6
CHRnoG1_14 QT 0.6
CHRnoG1_14 q3 1
CHRnoG1_15 Linear Add No G1 0
CHRnoG1_15 G2 1
CHRnoG1_15 P 1
CHRnoG1_15 MOVE1 0.75
CHRnoG1_15 q5 0.6
CHRnoG1_15 QT -0.6
CHRnoG1_15 q3 1
CHRnoG1_16 Linear Add No G1 0
CHRnoG1_16 G2 1
CHRnoG1_16 P 1
CHRnoG1_16 MOVE1 0.75
CHRnoG1_16 q5 -0.6
CHRnoG1_16 QT -0.6
CHRnoG1_16 q3 1
Env_rara_noG1 Envelope No CHRnoG1_1 1
Env_rara_noG1 CHRnoG1_2 1
Env_rara_noG1 CHRnoG1_3 1
Env_rara_noG1 CHRnoG1_4 1
Env_rara_noG1 CHRnoG1_5 1
Env_rara_noG1 CHRnoG1_6 1
Env_rara_noG1 CHRnoG1_7 1
Env_rara_noG1 CHRnoG1_8 1
Env_rara_noG1 CHRnoG1_9 1
Env_rara_noG1 CHRnoG1_10 1
Env_rara_noG1 CHRnoG1_11 1
Env_rara_noG1 CHRnoG1_12 1
Env_rara_noG1 CHRnoG1_13 1
Env_rara_noG1 CHRnoG1_14 1
Env_rara_noG1 CHRnoG1_15 1
Env_rara_noG1 CHRnoG1_16 1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 45
Relazione illustrativa e di calcolo Progetto Definitivo

6 MODELLAZIONE AGLI ELEMENTI FINITI (FEM)

I calcoli sono stati eseguiti con i seguenti codici di calcolo:

- il SAP2000 versione 14.2.4 prodotto dalla Computers and Structures Inc. di Berkeley
California, come programma principale per la modellazione globale e le verifiche;
- ProVlim (applicativo del PROSAP) per la verifica delle sezioni in c.a. serie 2009.07.0020d

Vista 3D_Modello FEM

Vista 3D_Modello FEM

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 46
Relazione illustrativa e di calcolo Progetto Definitivo

Vista 3D_Modello FEM

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 47
Relazione illustrativa e di calcolo Progetto Definitivo

7 VERIFICA IMPALCATO

In questa fase del progetto si proceduto con la modellazione di ununica fase. A rigore, come si
provveder a fare in fase di progettazione esecutiva, andrebbe considerata una prima fase nella
quale i cavi di pretensione, opportunamente dimensionati, delle travi dellimpalcato vanno ad
annullare le tensioni di trazione che invece si produrrebbero allintradosso per effetto del peso
proprio della trave stessa e del getto della soletta sovrastante in fase di autoportanza in semplice
appoggio. In una seconda fase, realizzati gli appoggi di continuit, le tensioni di trazione dovute
ai carichi permanenti portati e ai carichi da traffico sono affidate allazione dei cavi di post-
tensione.
Per ovviare a tale carenza nella modellazione stata creata una serie di combinazioni
caratteristiche nelle quali il coefficiente moltiplicativo del peso proprio stato posto uguale a
zero per simulare il fatto che le tensioni prodotte dal peso proprio sono gi state assorbite dai
cavi di pretensione delle travi prefabbricate. Estata poi creata una combinazione di inviluppo
comprendente tutte queste combinazioni
Si riportano nel seguito i grafici raffiguranti le tensioni nel calcestruzzo, nella combinazione di
inviluppo appena descritta, rispettivamente per il lato inferiore e per il lato superiore di tutte le
travi costituenti limpalcato.
In particolar modo si vanno a verificare le tensioni in esercizio a tempo infinito che devono
rispettare i seguenti limiti:
Classe di resistenza del calcestruzzo: C40/50
in compressione: c < 0,60 fck = 24 N/mm2 (comb.rara)
in trazione: il valor medio della resistenza a trazione per flessione assunto come
definito al paragrafo 11.2.10.2 del DM 2008 cio f cfm = 1.2 f ctm , dove

f ctm = 0.3 f ck2 / 3 = 0.3 40 2 / 3 = 3.5 N / mm 2

f cfm = 1.2 f ctm = 1.2 3.5 = 4.2 N / mm 2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 48
Relazione illustrativa e di calcolo Progetto Definitivo

Massimo valore di trazione registrato: 2.36N/mm2


Massimo valore di compressione registrato: -9.44N/mm2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 49
Relazione illustrativa e di calcolo Progetto Definitivo

Massimo valore di trazione registrato: 4.2N/mm2


Massimo valore di compressione registrato: -9.7N/mm2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 50
Relazione illustrativa e di calcolo Progetto Definitivo

8 VERIFICA SOLETTA

Si riportano nel seguito i grafici raffiguranti le tensioni nel calcestruzzo, nella combinazione di
inviluppo delle combinazioni caratteristiche (quelle senza peso proprio), rispettivamente per il
lato inferiore e per il lato superiore della soletta in c.a. dello spessore di 30cm.
In particolar modo si vanno a verificare le tensioni in esercizio che devono rispettare i seguenti
limiti:
Classe di resistenza del calcestruzzo: C32/40:
in compressione: c < 0,60 fck = 19.2 N/mm2 (comb.rara)
in trazione: il valor medio della resistenza a trazione per flessione assunto come
definito al paragrafo 11.2.10.2 del DM 2008 cio f cfm = 1.2 f ctm , dove

f ctm = 0.3 f ck2 / 3 = 0.3 32 2 / 3 = 3.02 N / mm 2

f cfm = 1.2 f ctm = 1.2 3.02 = 3.6 N / mm 2

Massimo valore di trazione registrato sugli appoggi intermedi: 3.48N/mm2


Massimo valore di compressione registrato: -10.4N/mm2
Si nota come alle estremit del ponte il limite di trazione del calcestruzzo viene superato. In
realt tale valore fa riferimento alla tensione che si produce allestremit sinistra e destra della
soletta e lo si ritiene non significativo.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 51
Relazione illustrativa e di calcolo Progetto Definitivo

Inoltre nella parte terminale del ponte la sezione di impalcato si allarga. Tale allargamento si
ottiene aumentando lo sbalzo di soletta con linserimento di una trave post-tesa a sbalzo
fuoriuscente dai traversi di testata. Tale verifica si rimanda alla progettazione esecutiva.

Massimo valore di trazione registrato: 2.8N/mm2


Massimo valore di compressione registrato: -10.2N/mm2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 52
Relazione illustrativa e di calcolo Progetto Definitivo

9 VERIFICA APPARECCHI DI APPOGGIO

Limpalcato prefabbricato appoggia sulle spalle e sulle pile su opportuni apparecchi di appoggio
in acciaio-teflon a disco di elastomero incapsulato. Con lesattezza sono previsti tre appoggi
unidirezionali trasversali e un appoggio fisso sulla spalla S01, tre appoggi multi direzionali e un
appoggio unidirezionale longitudinale su ciascuna pila e tre appoggi multi direzionali e uno
unidirezionale longitudinale sulla spalla S02, con la seguente disposizione:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 53
Relazione illustrativa e di calcolo Progetto Definitivo

Dove:

I valori sopra riportati sono stati arrotondati per eccesso rispetto agli scarichi ottenuti dal
modello FEM al fine di unificare le tipologie degli appoggi.
Si analizzano nel seguito le reazioni ottenute dal modello FEM sui vari appoggi i quali sono cos
identificati:

Il sistema di riferimento da intendersi come F1 direzione verticale, F2 direzione trasversale e


F3 direzione longitudinale.

9.1 Appoggio unidirezionale trasversale_Spalla S01


TABLE: Joint Reactions
Joint OutputCase CaseType StepType F1 F3
Text Text Text Text KN KN
1 STR1 Combination Max 3014 2437
1 STR1 Combination Min 1017 -405
1 STR2 Combination Max 2525 2240
1 STR2 Combination Min 528 -602
1 STR3 Combination Max 2942 2327
1 STR3 Combination Min 946 -515
1 STR4 Combination Max 2453 2130
1 STR4 Combination Min 456 -712
1 STR5 Combination Max 3755 2957
1 STR5 Combination Min 1759 114
1 STR6 Combination Max 3266 2760
1 STR6 Combination Min 1269 -82
1 STR7 Combination Max 3684 2846
1 STR7 Combination Min 1687 4
1 STR8 Combination Max 3194 2650

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 54
Relazione illustrativa e di calcolo Progetto Definitivo

1 STR8 Combination Min 1198 -193


1 STR9 Combination Max 2639 2035
1 STR9 Combination Min 1160 -71
1 STR10 Combination Max 2520 1851
1 STR10 Combination Min 1041 -254
1 STR11 Combination Max 2150 1838
1 STR11 Combination Min 671 -267
1 STR12 Combination Max 2030 1654
1 STR12 Combination Min 551 -451
1 STR13 Combination Max 3381 2554
1 STR13 Combination Min 1902 449
1 STR14 Combination Max 3261 2370
1 STR14 Combination Min 1782 265
1 STR15 Combination Max 2891 2357
1 STR15 Combination Min 1412 252
1 STR16 Combination Max 2772 2174
1 STR16 Combination Min 1293 68
1 STR17 Combination Max 2368 1825
1 STR17 Combination Min 889 -281
1 STR18 Combination Max 2296 1715
1 STR18 Combination Min 817 -391
1 STR19 Combination Max 1879 1628
1 STR19 Combination Min 400 -477
1 STR20 Combination Max 1807 1518
1 STR20 Combination Min 328 -588
1 STR21 Combination Max 3604 2691
1 STR21 Combination Min 2125 585
1 STR22 Combination Max 3532 2580
1 STR22 Combination Min 2053 475
1 STR23 Combination Max 3114 2494
1 STR23 Combination Min 1636 388
1 STR24 Combination Max 3043 2384
1 STR24 Combination Min 1564 278
1 STR25 Combination Max 2604 1817
1 STR25 Combination Min 1125 -289
1 STR26 Combination Max 2532 1707
1 STR26 Combination Min 1053 -399
1 STR27 Combination Max 3346 2336
1 STR27 Combination Min 1867 231
1 STR28 Combination Max 3274 2226
1 STR28 Combination Min 1795 121
1 STR29 Combination Max 2115 1620
1 STR29 Combination Min 636 -485

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 55
Relazione illustrativa e di calcolo Progetto Definitivo

1 STR30 Combination Max 2043 1510


1 STR30 Combination Min 564 -596
1 STR31 Combination Max 2856 2139
1 STR31 Combination Min 1377 34
1 STR32 Combination Max 2784 2029
1 STR32 Combination Min 1305 -76
1 QKE1 Combination Max 1580 1912
1 QKE1 Combination Min 708 -690
1 QKE2 Combination Max 2095 2273
1 QKE2 Combination Min 1223 -329
1 QKE3 Combination Max 1710 1742
1 QKE3 Combination Min 578 -520
1 QKE4 Combination Max 2225 2103

1 QKE4 Combination Min 1093 -159

Appoggio Unidirezionale trasversale


F1 F3
KN KN
Max 3755 2957

Min 328 -712

Joint OutputCase CaseType StepType F1 F3


Text Text Text Text KN KN
3 STR1 Combination Max 2435 -246
3 STR1 Combination Min 1253 -1330
3 STR2 Combination Max 2189 -85
3 STR2 Combination Min 1006 -1169
3 STR3 Combination Max 2513 -193
3 STR3 Combination Min 1330 -1276
3 STR4 Combination Max 2266 -31
3 STR4 Combination Min 1084 -1115
3 STR5 Combination Max 1710 -665
3 STR5 Combination Min 528 -1749
3 STR6 Combination Max 1464 -504
3 STR6 Combination Min 281 -1588
3 STR7 Combination Max 1788 -612
3 STR7 Combination Min 605 -1695
3 STR8 Combination Max 1541 -450
3 STR8 Combination Min 359 -1534
3 STR9 Combination Max 2152 -368
3 STR9 Combination Min 1276 -1171
3 STR10 Combination Max 2282 -279

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 56
Relazione illustrativa e di calcolo Progetto Definitivo

3 STR10 Combination Min 1406 -1082


3 STR11 Combination Max 1906 -207
3 STR11 Combination Min 1030 -1010
3 STR12 Combination Max 2035 -118
3 STR12 Combination Min 1159 -921
3 STR13 Combination Max 1428 -787
3 STR13 Combination Min 552 -1590
3 STR14 Combination Max 1557 -698
3 STR14 Combination Min 681 -1501
3 STR15 Combination Max 1181 -626
3 STR15 Combination Min 305 -1429
3 STR16 Combination Max 1310 -537
3 STR16 Combination Min 434 -1340
3 STR17 Combination Max 2420 -211
3 STR17 Combination Min 1544 -1014
3 STR18 Combination Max 2497 -157
3 STR18 Combination Min 1621 -960
3 STR19 Combination Max 2173 -49
3 STR19 Combination Min 1298 -852
3 STR20 Combination Max 2251 4
3 STR20 Combination Min 1375 -799
3 STR21 Combination Max 1212 -909
3 STR21 Combination Min 336 -1712
3 STR22 Combination Max 1289 -856
3 STR22 Combination Min 413 -1658
3 STR23 Combination Max 965 -748
3 STR23 Combination Min 89 -1551
3 STR24 Combination Max 1043 -694
3 STR24 Combination Min 167 -1497
3 STR25 Combination Max 2161 -543
3 STR25 Combination Min 1285 -1345
3 STR26 Combination Max 2238 -489
3 STR26 Combination Min 1362 -1292
3 STR27 Combination Max 1436 -962
3 STR27 Combination Min 560 -1764
3 STR28 Combination Max 1513 -908
3 STR28 Combination Min 637 -1711
3 STR29 Combination Max 1914 -381
3 STR29 Combination Min 1038 -1184
3 STR30 Combination Max 1992 -328
3 STR30 Combination Min 1116 -1131
3 STR31 Combination Max 1190 -800
3 STR31 Combination Min 314 -1603

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 57
Relazione illustrativa e di calcolo Progetto Definitivo

3 STR32 Combination Max 1267 -747


3 STR32 Combination Min 391 -1550
3 QKE1 Combination Max 1513 417
3 QKE1 Combination Min 857 -1508
3 QKE2 Combination Max 1010 126
3 QKE2 Combination Min 353 -1799
3 QKE3 Combination Max 1598 3
3 QKE3 Combination Min 772 -1093
3 QKE4 Combination Max 1095 -288

3 QKE4 Combination Min 269 -1384

Appoggio Unidirezionale trasversale


F1 F3
KN KN
Max 2513 417

Min 89 -1799

Joint OutputCase CaseType StepType F1 F3


Text Text Text Text KN KN
4 STR1 Combination Max 2491 1417
4 STR1 Combination Min 1077 -1073
4 STR2 Combination Max 2011 1328
4 STR2 Combination Min 598 -1162
4 STR3 Combination Max 2519 1500
4 STR3 Combination Min 1105 -990
4 STR4 Combination Max 2040 1411
4 STR4 Combination Min 626 -1079
4 STR5 Combination Max 3239 1743
4 STR5 Combination Min 1825 -746
4 STR6 Combination Max 2759 1654
4 STR6 Combination Min 1346 -835
4 STR7 Combination Max 3267 1826
4 STR7 Combination Min 1853 -663
4 STR8 Combination Max 2787 1737
4 STR8 Combination Min 1374 -753
4 STR9 Combination Max 2213 1078
4 STR9 Combination Min 1166 -766
4 STR10 Combination Max 2260 1216
4 STR10 Combination Min 1213 -628
4 STR11 Combination Max 1734 989
4 STR11 Combination Min 687 -855

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 58
Relazione illustrativa e di calcolo Progetto Definitivo

4 STR12 Combination Max 1780 1127


4 STR12 Combination Min 734 -717
4 STR13 Combination Max 2961 1405
4 STR13 Combination Min 1914 -439
4 STR14 Combination Max 3008 1543
4 STR14 Combination Min 1961 -301
4 STR15 Combination Max 2482 1315
4 STR15 Combination Min 1435 -529
4 STR16 Combination Max 2528 1454
4 STR16 Combination Min 1481 -391
4 STR17 Combination Max 1973 997
4 STR17 Combination Min 926 -847
4 STR18 Combination Max 2001 1080
4 STR18 Combination Min 954 -764
4 STR19 Combination Max 1494 908
4 STR19 Combination Min 447 -936
4 STR20 Combination Max 1522 991
4 STR20 Combination Min 475 -853
4 STR21 Combination Max 3219 1541
4 STR21 Combination Min 2173 -303
4 STR22 Combination Max 3248 1624
4 STR22 Combination Min 2201 -220
4 STR23 Combination Max 2740 1452
4 STR23 Combination Min 1693 -392
4 STR24 Combination Max 2768 1535
4 STR24 Combination Min 1721 -309
4 STR25 Combination Max 2205 919
4 STR25 Combination Min 1158 -925
4 STR26 Combination Max 2233 1002
4 STR26 Combination Min 1186 -842
4 STR27 Combination Max 2953 1246
4 STR27 Combination Min 1906 -599
4 STR28 Combination Max 2981 1328
4 STR28 Combination Min 1934 -516
4 STR29 Combination Max 1726 830
4 STR29 Combination Min 679 -1014
4 STR30 Combination Max 1754 913
4 STR30 Combination Min 707 -931
4 STR31 Combination Max 2474 1156
4 STR31 Combination Min 1427 -688
4 STR32 Combination Max 2502 1239
4 STR32 Combination Min 1455 -605
4 QKE1 Combination Max 1510 1441

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 59
Relazione illustrativa e di calcolo Progetto Definitivo

4 QKE1 Combination Min 796 -1016


4 QKE2 Combination Max 2030 1667
4 QKE2 Combination Min 1315 -789
4 QKE3 Combination Max 1504 1209
4 QKE3 Combination Min 803 -784
4 QKE4 Combination Max 2023 1436

4 QKE4 Combination Min 1322 -558

Appoggio Unidirezionale trasversale

F1 F3
KN KN
Max 3267 1826

Min 447 -1162

9.2 Appoggio fisso_Spalla S01


Joint OutputCase CaseType StepType F1 F2 F3
Text Text Text Text KN KN KN
2 STR1 Combination Max 2890 858 232
2 STR1 Combination Min 1811 203 -728
2 STR2 Combination Max 2556 743 334
2 STR2 Combination Min 1478 88 -626
2 STR3 Combination Max 2847 727 166
2 STR3 Combination Min 1768 72 -794
2 STR4 Combination Max 2513 612 268
2 STR4 Combination Min 1434 -43 -692
2 STR5 Combination Max 2199 1019 -183
2 STR5 Combination Min 1120 365 -1143
2 STR6 Combination Max 1865 904 -81
2 STR6 Combination Min 787 249 -1041
2 STR7 Combination Max 2156 888 -249
2 STR7 Combination Min 1077 233 -1209
2 STR8 Combination Max 1822 773 -147
2 STR8 Combination Min 743 118 -1107
2 STR9 Combination Max 2663 784 137
2 STR9 Combination Min 1864 299 -575
2 STR10 Combination Max 2592 565 27
2 STR10 Combination Min 1792 79 -684
2 STR11 Combination Max 2330 669 239
2 STR11 Combination Min 1531 184 -473
2 STR12 Combination Max 2258 449 129
2 STR12 Combination Min 1459 -36 -582
2 STR13 Combination Max 1973 945 -279

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 60
Relazione illustrativa e di calcolo Progetto Definitivo

2 STR13 Combination Min 1173 460 -990


2 STR14 Combination Max 1901 726 -389
2 STR14 Combination Min 1101 241 -1100
2 STR15 Combination Max 1639 830 -177
2 STR15 Combination Min 840 345 -888
2 STR16 Combination Max 1567 611 -287
2 STR16 Combination Min 768 125 -998
2 STR17 Combination Max 2879 686 253
2 STR17 Combination Min 2080 201 -458
2 STR18 Combination Max 2836 555 187
2 STR18 Combination Min 2037 70 -524
2 STR19 Combination Max 2546 571 355
2 STR19 Combination Min 1747 86 -356
2 STR20 Combination Max 2503 439 289
2 STR20 Combination Min 1704 -46 -422
2 STR21 Combination Max 1728 955 -440
2 STR21 Combination Min 929 470 -1151
2 STR22 Combination Max 1685 823 -506
2 STR22 Combination Min 886 338 -1217
2 STR23 Combination Max 1394 840 -338
2 STR23 Combination Min 595 355 -1049
2 STR24 Combination Max 1351 708 -404
2 STR24 Combination Min 552 223 -1115
2 STR25 Combination Max 2636 804 -73
2 STR25 Combination Min 1837 319 -784
2 STR26 Combination Max 2593 672 -139
2 STR26 Combination Min 1794 187 -850
2 STR27 Combination Max 1945 965 -489
2 STR27 Combination Min 1146 480 -1200
2 STR28 Combination Max 1902 833 -555
2 STR28 Combination Min 1103 348 -1266
2 STR29 Combination Max 2303 689 29
2 STR29 Combination Min 1503 204 -682
2 STR30 Combination Max 2259 557 -37
2 STR30 Combination Min 1460 72 -748
2 STR31 Combination Max 1612 850 -387
2 STR31 Combination Min 812 365 -1098
2 STR32 Combination Max 1568 718 -453
2 STR32 Combination Min 769 233 -1164
2 QKE1 Combination Max 1815 805 765
2 QKE1 Combination Min 1300 -276 -1206
2 QKE2 Combination Max 1335 917 477
2 QKE2 Combination Min 821 -164 -1494

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 61
Relazione illustrativa e di calcolo Progetto Definitivo

2 QKE3 Combination Max 1780 1183 374


2 QKE3 Combination Min 1335 -653 -814
2 QKE4 Combination Max 1300 1295 85

2 QKE4 Combination Min 855 -541 -1103

Appoggio fisso
F1 F2 F3
KN KN KN
Max 2890 1295 765

Min 552 -653 -1494

9.3 Appoggio unidirezionale longitudinale_Spalla S02


Joint OutputCase CaseType StepType F1 F2
Text Text Text Text KN KN
22 STR1 Combination Max 2628 227
22 STR1 Combination Min 1648 -132
22 STR2 Combination Max 2300 242
22 STR2 Combination Min 1320 -117
22 STR3 Combination Max 2625 114
22 STR3 Combination Min 1645 -245
22 STR4 Combination Max 2297 129
22 STR4 Combination Min 1316 -230
22 STR5 Combination Max 2065 254
22 STR5 Combination Min 1085 -105
22 STR6 Combination Max 1736 269
22 STR6 Combination Min 756 -90
22 STR7 Combination Max 2062 141
22 STR7 Combination Min 1082 -218
22 STR8 Combination Max 1733 156
22 STR8 Combination Min 753 -203
22 STR9 Combination Max 2406 218
22 STR9 Combination Min 1680 -48
22 STR10 Combination Max 2401 30
22 STR10 Combination Min 1675 -236
22 STR11 Combination Max 2078 233
22 STR11 Combination Min 1352 -33
22 STR12 Combination Max 2072 45
22 STR12 Combination Min 1346 -221
22 STR13 Combination Max 1843 245
22 STR13 Combination Min 1117 -21
22 STR14 Combination Max 1838 57
22 STR14 Combination Min 1112 -209

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 62
Relazione illustrativa e di calcolo Progetto Definitivo

22 STR15 Combination Max 1514 261


22 STR15 Combination Min 788 -5
22 STR16 Combination Max 1509 72
22 STR16 Combination Min 783 -194
22 STR17 Combination Max 2593 171
22 STR17 Combination Min 1867 -95
22 STR18 Combination Max 2590 58
22 STR18 Combination Min 1864 -208
22 STR19 Combination Max 2264 187
22 STR19 Combination Min 1538 -79
22 STR20 Combination Max 2261 74
22 STR20 Combination Min 1535 -192
22 STR21 Combination Max 1654 217
22 STR21 Combination Min 928 -49
22 STR22 Combination Max 1651 104
22 STR22 Combination Min 925 -162
22 STR23 Combination Max 1326 232
22 STR23 Combination Min 600 -34
22 STR24 Combination Max 1322 119
22 STR24 Combination Min 596 -147
22 STR25 Combination Max 2406 183
22 STR25 Combination Min 1680 -83
22 STR26 Combination Max 2403 70
22 STR26 Combination Min 1677 -196
22 STR27 Combination Max 1843 210
22 STR27 Combination Min 1117 -56
22 STR28 Combination Max 1840 97
22 STR28 Combination Min 1114 -169
22 STR29 Combination Max 2077 198
22 STR29 Combination Min 1351 -68
22 STR30 Combination Max 2074 85
22 STR30 Combination Min 1348 -181
22 STR31 Combination Max 1514 225
22 STR31 Combination Min 788 -40
22 STR32 Combination Max 1511 112
22 STR32 Combination Min 785 -153
22 QKE1 Combination Max 1585 398
22 QKE1 Combination Min 1228 -376
22 QKE2 Combination Max 1194 417
22 QKE2 Combination Min 837 -357
22 QKE3 Combination Max 1593 813
22 QKE3 Combination Min 1220 -791
22 QKE4 Combination Max 1202 832

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 63
Relazione illustrativa e di calcolo Progetto Definitivo

22 QKE4 Combination Min 829 -773

Appoggio Unidirezionale

F1 F2
KN KN
Max 2628 832

Min 596 -791

9.4 Appoggio multidirezionale_Spalla S02


Joint OutputCase CaseType StepType F1
Text Text Text Text KN
21 STR1 Combination Max 2476
21 STR1 Combination Min 1137
21 STR2 Combination Max 2037
21 STR2 Combination Min 698
21 STR3 Combination Max 2417
21 STR3 Combination Min 1078
21 STR4 Combination Max 1978
21 STR4 Combination Min 639
21 STR5 Combination Max 3108
21 STR5 Combination Min 1769
21 STR6 Combination Max 2669
21 STR6 Combination Min 1330
21 STR7 Combination Max 3048
21 STR7 Combination Min 1710
21 STR8 Combination Max 2609
21 STR8 Combination Min 1271
21 STR9 Combination Max 2208
21 STR9 Combination Min 1217
21 STR10 Combination Max 2110
21 STR10 Combination Min 1118
21 STR11 Combination Max 1769
21 STR11 Combination Min 778
21 STR12 Combination Max 1671
21 STR12 Combination Min 679
21 STR13 Combination Max 2840
21 STR13 Combination Min 1848
21 STR14 Combination Max 2741
21 STR14 Combination Min 1750
21 STR15 Combination Max 2401
21 STR15 Combination Min 1409
21 STR16 Combination Max 2302

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 64
Relazione illustrativa e di calcolo Progetto Definitivo

21 STR16 Combination Min 1310


21 STR17 Combination Max 1978
21 STR17 Combination Min 986
21 STR18 Combination Max 1919
21 STR18 Combination Min 927
21 STR19 Combination Max 1539
21 STR19 Combination Min 547
21 STR20 Combination Max 1480
21 STR20 Combination Min 488
21 STR21 Combination Max 3031
21 STR21 Combination Min 2039
21 STR22 Combination Max 2972
21 STR22 Combination Min 1980
21 STR23 Combination Max 2592
21 STR23 Combination Min 1600
21 STR24 Combination Max 2532
21 STR24 Combination Min 1541
21 STR25 Combination Max 2192
21 STR25 Combination Min 1200
21 STR26 Combination Max 2133
21 STR26 Combination Min 1141
21 STR27 Combination Max 2824
21 STR27 Combination Min 1832
21 STR28 Combination Max 2764
21 STR28 Combination Min 1773
21 STR29 Combination Max 1753
21 STR29 Combination Min 761
21 STR30 Combination Max 1694
21 STR30 Combination Min 702
21 STR31 Combination Max 2385
21 STR31 Combination Min 1393
21 STR32 Combination Max 2325
21 STR32 Combination Min 1334
21 QKE1 Combination Max 1404
21 QKE1 Combination Min 717
21 QKE2 Combination Max 1842
21 QKE2 Combination Min 1155
21 QKE3 Combination Max 1562
21 QKE3 Combination Min 559
21 QKE4 Combination Max 2000
21 QKE4 Combination Min 997

Appoggio Multidirezionale
F1
KN
Max 3108
Min 488

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 65
Relazione illustrativa e di calcolo Progetto Definitivo

23 STR1 Combination Max 2863


23 STR1 Combination Min 1756
23 STR2 Combination Max 2515
23 STR2 Combination Min 1408
23 STR3 Combination Max 2896
23 STR3 Combination Min 1788
23 STR4 Combination Max 2547
23 STR4 Combination Min 1440
23 STR5 Combination Max 2270
23 STR5 Combination Min 1162
23 STR6 Combination Max 1921
23 STR6 Combination Min 814
23 STR7 Combination Max 2302
23 STR7 Combination Min 1194
23 STR8 Combination Max 1954
23 STR8 Combination Min 846
23 STR9 Combination Max 2604
23 STR9 Combination Min 1784
23 STR10 Combination Max 2658
23 STR10 Combination Min 1838
23 STR11 Combination Max 2256
23 STR11 Combination Min 1436
23 STR12 Combination Max 2310
23 STR12 Combination Min 1489
23 STR13 Combination Max 2011
23 STR13 Combination Min 1190
23 STR14 Combination Max 2064
23 STR14 Combination Min 1244
23 STR15 Combination Max 1662
23 STR15 Combination Min 842
23 STR16 Combination Max 1716
23 STR16 Combination Min 896
23 STR17 Combination Max 2813
23 STR17 Combination Min 1993
23 STR18 Combination Max 2845
23 STR18 Combination Min 2025
23 STR19 Combination Max 2465
23 STR19 Combination Min 1644
23 STR20 Combination Max 2497
23 STR20 Combination Min 1677

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 66
Relazione illustrativa e di calcolo Progetto Definitivo

23 STR21 Combination Max 1823


23 STR21 Combination Min 1003
23 STR22 Combination Max 1856
23 STR22 Combination Min 1035
23 STR23 Combination Max 1475
23 STR23 Combination Min 655
23 STR24 Combination Max 1507
23 STR24 Combination Min 687
23 STR25 Combination Max 2614
23 STR25 Combination Min 1794
23 STR26 Combination Max 2647
23 STR26 Combination Min 1826
23 STR27 Combination Max 2021
23 STR27 Combination Min 1200
23 STR28 Combination Max 2053
23 STR28 Combination Min 1232
23 STR29 Combination Max 2266
23 STR29 Combination Min 1446
23 STR30 Combination Max 2298
23 STR30 Combination Min 1478
23 STR31 Combination Max 1672
23 STR31 Combination Min 852
23 STR32 Combination Max 1704
23 STR32 Combination Min 884
23 QKE1 Combination Max 1732
23 QKE1 Combination Min 1352
23 QKE2 Combination Max 1320
23 QKE2 Combination Min 940
23 QKE3 Combination Max 1749
23 QKE3 Combination Min 1336
23 QKE4 Combination Max 1337

23 QKE4 Combination Min 923

Appoggio Multidirezionale
F1
KN
Max 2896

Min 655

24 STR1 Combination Max 2412


24 STR1 Combination Min 758
24 STR2 Combination Max 1984
24 STR2 Combination Min 330

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 67
Relazione illustrativa e di calcolo Progetto Definitivo

24 STR3 Combination Max 2450


24 STR3 Combination Min 797
24 STR4 Combination Max 2022
24 STR4 Combination Min 368
24 STR5 Combination Max 3009
24 STR5 Combination Min 1355
24 STR6 Combination Max 2581
24 STR6 Combination Min 927
24 STR7 Combination Max 3047
24 STR7 Combination Min 1394
24 STR8 Combination Max 2619
24 STR8 Combination Min 965
24 STR9 Combination Max 2090
24 STR9 Combination Min 865
24 STR10 Combination Max 2155
24 STR10 Combination Min 930
24 STR11 Combination Max 1662
24 STR11 Combination Min 437
24 STR12 Combination Max 1727
24 STR12 Combination Min 502
24 STR13 Combination Max 2687
24 STR13 Combination Min 1462
24 STR14 Combination Max 2752
24 STR14 Combination Min 1527
24 STR15 Combination Max 2259
24 STR15 Combination Min 1034
24 STR16 Combination Max 2324
24 STR16 Combination Min 1099
24 STR17 Combination Max 1904
24 STR17 Combination Min 679
24 STR18 Combination Max 1943
24 STR18 Combination Min 718
24 STR19 Combination Max 1476
24 STR19 Combination Min 251
24 STR20 Combination Max 1515
24 STR20 Combination Min 290
24 STR21 Combination Max 2899
24 STR21 Combination Min 1674
24 STR22 Combination Max 2938
24 STR22 Combination Min 1713
24 STR23 Combination Max 2471
24 STR23 Combination Min 1246
24 STR24 Combination Max 2510

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 68
Relazione illustrativa e di calcolo Progetto Definitivo

24 STR24 Combination Min 1285


24 STR25 Combination Max 2106
24 STR25 Combination Min 881
24 STR26 Combination Max 2145
24 STR26 Combination Min 920
24 STR27 Combination Max 2703
24 STR27 Combination Min 1478
24 STR28 Combination Max 2742
24 STR28 Combination Min 1517
24 STR29 Combination Max 1678
24 STR29 Combination Min 453
24 STR30 Combination Max 1717
24 STR30 Combination Min 492
24 STR31 Combination Max 2275
24 STR31 Combination Min 1050
24 STR32 Combination Max 2314
24 STR32 Combination Min 1089
24 QKE1 Combination Max 1252
24 QKE1 Combination Min 664
24 QKE2 Combination Max 1667
24 QKE2 Combination Min 1078
24 QKE3 Combination Max 1312
24 QKE3 Combination Min 604
24 QKE4 Combination Max 1726

24 QKE4 Combination Min 1019

Appoggio Multidirezionale
F1
KN
Max 3047

Min 251

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 69
Relazione illustrativa e di calcolo Progetto Definitivo

9.5 Appoggio unidirezionale longitudinale_Pile P01-P02


Link LinkElem Station OutputCase CaseType StepType P V2
Text Text Text Text Text Text KN KN
27 27 I-End STR1 Combination Max -5072 1054
27 27 J-End STR1 Combination Max -5072 1054
27 27 I-End STR1 Combination Min -11282 -2
27 27 J-End STR1 Combination Min -11282 -2
27 27 I-End STR2 Combination Max -3353 890
27 27 J-End STR2 Combination Max -3353 890
27 27 I-End STR2 Combination Min -9563 -165
27 27 J-End STR2 Combination Min -9563 -165
27 27 I-End STR3 Combination Max -4865 1176
27 27 J-End STR3 Combination Max -4865 1176
27 27 I-End STR3 Combination Min -11075 120
27 27 J-End STR3 Combination Min -11075 120
27 27 I-End STR4 Combination Max -3145 1012
27 27 J-End STR4 Combination Max -3145 1012
27 27 I-End STR4 Combination Min -9356 -43
27 27 J-End STR4 Combination Min -9356 -43
27 27 I-End STR5 Combination Max -4800 1078
27 27 J-End STR5 Combination Max -4800 1078
27 27 I-End STR5 Combination Min -11011 23
27 27 J-End STR5 Combination Min -11011 23
27 27 I-End STR6 Combination Max -3081 915
27 27 J-End STR6 Combination Max -3081 915
27 27 I-End STR6 Combination Min -9291 -140
27 27 J-End STR6 Combination Min -9291 -140
27 27 I-End STR7 Combination Max -4593 1200
27 27 J-End STR7 Combination Max -4593 1200
27 27 I-End STR7 Combination Min -10803 145
27 27 J-End STR7 Combination Min -10803 145
27 27 I-End STR8 Combination Max -2874 1037
27 27 J-End STR8 Combination Max -2874 1037
27 27 I-End STR8 Combination Min -9084 -19
27 27 J-End STR8 Combination Min -9084 -19
27 27 I-End STR9 Combination Max -5591 838
27 27 J-End STR9 Combination Max -5591 838
27 27 I-End STR9 Combination Min -10191 56
27 27 J-End STR9 Combination Min -10191 56
27 27 I-End STR10 Combination Max -5245 1041
27 27 J-End STR10 Combination Max -5245 1041

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 70
Relazione illustrativa e di calcolo Progetto Definitivo

27 27 I-End STR10 Combination Min -9845 259


27 27 J-End STR10 Combination Min -9845 259
27 27 I-End STR11 Combination Max -3871 674
27 27 J-End STR11 Combination Max -3871 674
27 27 I-End STR11 Combination Min -8472 -108
27 27 J-End STR11 Combination Min -8472 -108
27 27 I-End STR12 Combination Max -3526 877
27 27 J-End STR12 Combination Max -3526 877
27 27 I-End STR12 Combination Min -8126 95
27 27 J-End STR12 Combination Min -8126 95
27 27 I-End STR13 Combination Max -5319 862
27 27 J-End STR13 Combination Max -5319 862
27 27 I-End STR13 Combination Min -9919 81
27 27 J-End STR13 Combination Min -9919 81
27 27 I-End STR14 Combination Max -4973 1066
27 27 J-End STR14 Combination Max -4973 1066
27 27 I-End STR14 Combination Min -9574 284
27 27 J-End STR14 Combination Min -9574 284
27 27 I-End STR15 Combination Max -3600 699
27 27 J-End STR15 Combination Max -3600 699
27 27 I-End STR15 Combination Min -8200 -83
27 27 J-End STR15 Combination Min -8200 -83
27 27 I-End STR16 Combination Max -3254 902
27 27 J-End STR16 Combination Max -3254 902
27 27 I-End STR16 Combination Min -7854 120
27 27 J-End STR16 Combination Min -7854 120
27 27 I-End STR17 Combination Max -5612 870
27 27 J-End STR17 Combination Max -5612 870
27 27 I-End STR17 Combination Min -10212 88
27 27 J-End STR17 Combination Min -10212 88
27 27 I-End STR18 Combination Max -5405 992
27 27 J-End STR18 Combination Max -5405 992
27 27 I-End STR18 Combination Min -10005 210
27 27 J-End STR18 Combination Min -10005 210
27 27 I-End STR19 Combination Max -3893 706
27 27 J-End STR19 Combination Max -3893 706
27 27 I-End STR19 Combination Min -8493 -75
27 27 J-End STR19 Combination Min -8493 -75
27 27 I-End STR20 Combination Max -3685 828
27 27 J-End STR20 Combination Max -3685 828
27 27 I-End STR20 Combination Min -8286 47
27 27 J-End STR20 Combination Min -8286 47
27 27 I-End STR21 Combination Max -5159 911

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 71
Relazione illustrativa e di calcolo Progetto Definitivo

27 27 J-End STR21 Combination Max -5159 911


27 27 I-End STR21 Combination Min -9760 130
27 27 J-End STR21 Combination Min -9760 130
27 27 I-End STR22 Combination Max -4952 1033
27 27 J-End STR22 Combination Max -4952 1033
27 27 I-End STR22 Combination Min -9552 252
27 27 J-End STR22 Combination Min -9552 252
27 27 I-End STR23 Combination Max -3440 748
27 27 J-End STR23 Combination Max -3440 748
27 27 I-End STR23 Combination Min -8040 -34
27 27 J-End STR23 Combination Min -8040 -34
27 27 I-End STR24 Combination Max -3233 870
27 27 J-End STR24 Combination Max -3233 870
27 27 I-End STR24 Combination Min -7833 88
27 27 J-End STR24 Combination Min -7833 88
27 27 I-End STR25 Combination Max -5539 894
27 27 J-End STR25 Combination Max -5539 894
27 27 I-End STR25 Combination Min -10139 112
27 27 J-End STR25 Combination Min -10139 112
27 27 I-End STR26 Combination Max -5331 1016
27 27 J-End STR26 Combination Max -5331 1016
27 27 I-End STR26 Combination Min -9931 234
27 27 J-End STR26 Combination Min -9931 234
27 27 I-End STR27 Combination Max -5267 919
27 27 J-End STR27 Combination Max -5267 919
27 27 I-End STR27 Combination Min -9867 137
27 27 J-End STR27 Combination Min -9867 137
27 27 I-End STR28 Combination Max -5060 1041
27 27 J-End STR28 Combination Max -5060 1041
27 27 I-End STR28 Combination Min -9660 259
27 27 J-End STR28 Combination Min -9660 259
27 27 I-End STR29 Combination Max -3819 730
27 27 J-End STR29 Combination Max -3819 730
27 27 I-End STR29 Combination Min -8419 -51
27 27 J-End STR29 Combination Min -8419 -51
27 27 I-End STR30 Combination Max -3612 852
27 27 J-End STR30 Combination Max -3612 852
27 27 I-End STR30 Combination Min -8212 71
27 27 J-End STR30 Combination Min -8212 71
27 27 I-End STR31 Combination Max -3548 755
27 27 J-End STR31 Combination Max -3548 755
27 27 I-End STR31 Combination Min -8148 -26
27 27 J-End STR31 Combination Min -8148 -26

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 72
Relazione illustrativa e di calcolo Progetto Definitivo

27 27 I-End STR32 Combination Max -3340 877


27 27 J-End STR32 Combination Max -3340 877
27 27 I-End STR32 Combination Min -7940 95
27 27 J-End STR32 Combination Min -7940 95
27 27 I-End QKE1 Combination Max -4092 1008
27 27 J-End QKE1 Combination Max -4092 1008
27 27 I-End QKE1 Combination Min -6197 -407
27 27 J-End QKE1 Combination Min -6197 -407
27 27 I-End QKE2 Combination Max -3904 1025
27 27 J-End QKE2 Combination Max -3904 1025
27 27 I-End QKE2 Combination Min -6008 -390
27 27 J-End QKE2 Combination Min -6008 -390
27 27 I-End QKE3 Combination Max -3971 1471
27 27 J-End QKE3 Combination Max -3971 1471
27 27 I-End QKE3 Combination Min -6318 -870
27 27 J-End QKE3 Combination Min -6318 -870
27 27 I-End QKE4 Combination Max -3782 1488
27 27 J-End QKE4 Combination Max -3782 1488
27 27 I-End QKE4 Combination Min -6130 -853

27 27 J-End QKE4 Combination Min -6130 -853

Appoggio Unidirezionale longitudinale


F1 F2
KN KN
Max -2874 1488

Min -11282 -870

35 35 I-End STR1 Combination Max -5802 115


35 35 J-End STR1 Combination Max -5802 115
35 35 I-End STR1 Combination Min -12425 -680
35 35 J-End STR1 Combination Min -12425 -680
35 35 I-End STR2 Combination Max -3795 212
35 35 J-End STR2 Combination Max -3795 212
35 35 I-End STR2 Combination Min -10418 -583
35 35 J-End STR2 Combination Min -10418 -583
35 35 I-End STR3 Combination Max -5567 241
35 35 J-End STR3 Combination Max -5567 241
35 35 I-End STR3 Combination Min -12190 -554
35 35 J-End STR3 Combination Min -12190 -554
35 35 I-End STR4 Combination Max -3559 338
35 35 J-End STR4 Combination Max -3559 338

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 73
Relazione illustrativa e di calcolo Progetto Definitivo

35 35 I-End STR4 Combination Min -10182 -457


35 35 J-End STR4 Combination Min -10182 -457
35 35 I-End STR5 Combination Max -5548 159
35 35 J-End STR5 Combination Max -5548 159
35 35 I-End STR5 Combination Min -12171 -636
35 35 J-End STR5 Combination Min -12171 -636
35 35 I-End STR6 Combination Max -3540 256
35 35 J-End STR6 Combination Max -3540 256
35 35 I-End STR6 Combination Min -10163 -539
35 35 J-End STR6 Combination Min -10163 -539
35 35 I-End STR7 Combination Max -5312 285
35 35 J-End STR7 Combination Max -5312 285
35 35 I-End STR7 Combination Min -11935 -510
35 35 J-End STR7 Combination Min -11935 -510
35 35 I-End STR8 Combination Max -3305 382
35 35 J-End STR8 Combination Max -3305 382
35 35 I-End STR8 Combination Min -9928 -413
35 35 J-End STR8 Combination Min -9928 -413
35 35 I-End STR9 Combination Max -6346 -23
35 35 J-End STR9 Combination Max -6346 -23
35 35 I-End STR9 Combination Min -11252 -613
35 35 J-End STR9 Combination Min -11252 -613
35 35 I-End STR10 Combination Max -5954 187
35 35 J-End STR10 Combination Max -5954 187
35 35 I-End STR10 Combination Min -10860 -402
35 35 J-End STR10 Combination Min -10860 -402
35 35 I-End STR11 Combination Max -4338 74
35 35 J-End STR11 Combination Max -4338 74
35 35 I-End STR11 Combination Min -9245 -515
35 35 J-End STR11 Combination Min -9245 -515
35 35 I-End STR12 Combination Max -3946 284
35 35 J-End STR12 Combination Max -3946 284
35 35 I-End STR12 Combination Min -8852 -305
35 35 J-End STR12 Combination Min -8852 -305
35 35 I-End STR13 Combination Max -6091 21
35 35 J-End STR13 Combination Max -6091 21
35 35 I-End STR13 Combination Min -10998 -569
35 35 J-End STR13 Combination Min -10998 -569
35 35 I-End STR14 Combination Max -5699 231
35 35 J-End STR14 Combination Max -5699 231
35 35 I-End STR14 Combination Min -10605 -358
35 35 J-End STR14 Combination Min -10605 -358
35 35 I-End STR15 Combination Max -4084 118

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 74
Relazione illustrativa e di calcolo Progetto Definitivo

35 35 J-End STR15 Combination Max -4084 118


35 35 I-End STR15 Combination Min -8990 -472
35 35 J-End STR15 Combination Min -8990 -472
35 35 I-End STR16 Combination Max -3692 328
35 35 J-End STR16 Combination Max -3692 328
35 35 I-End STR16 Combination Min -8598 -261
35 35 J-End STR16 Combination Min -8598 -261
35 35 I-End STR17 Combination Max -6352 4
35 35 J-End STR17 Combination Max -6352 4
35 35 I-End STR17 Combination Min -11258 -585
35 35 J-End STR17 Combination Min -11258 -585
35 35 I-End STR18 Combination Max -6117 130
35 35 J-End STR18 Combination Max -6117 130
35 35 I-End STR18 Combination Min -11023 -459
35 35 J-End STR18 Combination Min -11023 -459
35 35 I-End STR19 Combination Max -4345 101
35 35 J-End STR19 Combination Max -4345 101
35 35 I-End STR19 Combination Min -9251 -488
35 35 J-End STR19 Combination Min -9251 -488
35 35 I-End STR20 Combination Max -4109 227
35 35 J-End STR20 Combination Max -4109 227
35 35 I-End STR20 Combination Min -9016 -362
35 35 J-End STR20 Combination Min -9016 -362
35 35 I-End STR21 Combination Max -5928 77
35 35 J-End STR21 Combination Max -5928 77
35 35 I-End STR21 Combination Min -10834 -512
35 35 J-End STR21 Combination Min -10834 -512
35 35 I-End STR22 Combination Max -5693 203
35 35 J-End STR22 Combination Max -5693 203
35 35 I-End STR22 Combination Min -10599 -386
35 35 J-End STR22 Combination Min -10599 -386
35 35 I-End STR23 Combination Max -3921 174
35 35 J-End STR23 Combination Max -3921 174
35 35 I-End STR23 Combination Min -8827 -415
35 35 J-End STR23 Combination Min -8827 -415
35 35 I-End STR24 Combination Max -3685 300
35 35 J-End STR24 Combination Max -3685 300
35 35 I-End STR24 Combination Min -8591 -289
35 35 J-End STR24 Combination Min -8591 -289
35 35 I-End STR25 Combination Max -6265 15
35 35 J-End STR25 Combination Max -6265 15
35 35 I-End STR25 Combination Min -11171 -574
35 35 J-End STR25 Combination Min -11171 -574

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 75
Relazione illustrativa e di calcolo Progetto Definitivo

35 35 I-End STR26 Combination Max -6030 141


35 35 J-End STR26 Combination Max -6030 141
35 35 I-End STR26 Combination Min -10936 -448
35 35 J-End STR26 Combination Min -10936 -448
35 35 I-End STR27 Combination Max -6011 59
35 35 J-End STR27 Combination Max -6011 59
35 35 I-End STR27 Combination Min -10917 -530
35 35 J-End STR27 Combination Min -10917 -530
35 35 I-End STR28 Combination Max -5775 185
35 35 J-End STR28 Combination Max -5775 185
35 35 I-End STR28 Combination Min -10681 -404
35 35 J-End STR28 Combination Min -10681 -404
35 35 I-End STR29 Combination Max -4258 112
35 35 J-End STR29 Combination Max -4258 112
35 35 I-End STR29 Combination Min -9164 -477
35 35 J-End STR29 Combination Min -9164 -477
35 35 I-End STR30 Combination Max -4022 238
35 35 J-End STR30 Combination Max -4022 238
35 35 I-End STR30 Combination Min -8928 -351
35 35 J-End STR30 Combination Min -8928 -351
35 35 I-End STR31 Combination Max -4003 156
35 35 J-End STR31 Combination Max -4003 156
35 35 I-End STR31 Combination Min -8909 -433
35 35 J-End STR31 Combination Min -8909 -433
35 35 I-End STR32 Combination Max -3768 282
35 35 J-End STR32 Combination Max -3768 282
35 35 I-End STR32 Combination Min -8674 -307
35 35 J-End STR32 Combination Min -8674 -307
35 35 I-End QKE1 Combination Max -4300 539
35 35 J-End QKE1 Combination Max -4300 539
35 35 I-End QKE1 Combination Min -7015 -727
35 35 J-End QKE1 Combination Min -7015 -727
35 35 I-End QKE2 Combination Max -4124 570
35 35 J-End QKE2 Combination Max -4124 570
35 35 I-End QKE2 Combination Min -6838 -697
35 35 J-End QKE2 Combination Min -6838 -697
35 35 I-End QKE3 Combination Max -3594 1028
35 35 J-End QKE3 Combination Max -3594 1028
35 35 I-End QKE3 Combination Min -7722 -1216
35 35 J-End QKE3 Combination Min -7722 -1216
35 35 I-End QKE4 Combination Max -3417 1059
35 35 J-End QKE4 Combination Max -3417 1059
35 35 I-End QKE4 Combination Min -7545 -1186

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 76
Relazione illustrativa e di calcolo Progetto Definitivo

35 35 J-End QKE4 Combination Min -7545 -1186

Appoggio Unidirezionale longitudinale

F1 F2
KN KN
Max -3305 1059

Min -12425 -1216

9.6 Appoggio multidirezionale_Pile P01-P02


Link LinkElem Station OutputCase CaseType StepType P
Text Text Text Text Text Text KN
29 29 I-End STR1 Combination Max -5698
29 29 J-End STR1 Combination Max -5698
29 29 I-End STR1 Combination Min -11831
29 29 J-End STR1 Combination Min -11831
29 29 I-End STR2 Combination Max -3632
29 29 J-End STR2 Combination Max -3632
29 29 I-End STR2 Combination Min -9766
29 29 J-End STR2 Combination Min -9766
29 29 I-End STR3 Combination Max -5914
29 29 J-End STR3 Combination Max -5914
29 29 I-End STR3 Combination Min -12047
29 29 J-End STR3 Combination Min -12047
29 29 I-End STR4 Combination Max -3849
29 29 J-End STR4 Combination Max -3849
29 29 I-End STR4 Combination Min -9982
29 29 J-End STR4 Combination Min -9982
29 29 I-End STR5 Combination Max -5502
29 29 J-End STR5 Combination Max -5502
29 29 I-End STR5 Combination Min -11635
29 29 J-End STR5 Combination Min -11635
29 29 I-End STR6 Combination Max -3437
29 29 J-End STR6 Combination Max -3437
29 29 I-End STR6 Combination Min -9570
29 29 J-End STR6 Combination Min -9570
29 29 I-End STR7 Combination Max -5719
29 29 J-End STR7 Combination Max -5719
29 29 I-End STR7 Combination Min -11852
29 29 J-End STR7 Combination Min -11852
29 29 I-End STR8 Combination Max -3654
29 29 J-End STR8 Combination Max -3654
29 29 I-End STR8 Combination Min -9787

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 77
Relazione illustrativa e di calcolo Progetto Definitivo

29 29 J-End STR8 Combination Min -9787


29 29 I-End STR9 Combination Max -6098
29 29 J-End STR9 Combination Max -6098
29 29 I-End STR9 Combination Min -10641
29 29 J-End STR9 Combination Min -10641
29 29 I-End STR10 Combination Max -6459
29 29 J-End STR10 Combination Max -6459
29 29 I-End STR10 Combination Min -11002
29 29 J-End STR10 Combination Min -11002
29 29 I-End STR11 Combination Max -4033
29 29 J-End STR11 Combination Max -4033
29 29 I-End STR11 Combination Min -8576
29 29 J-End STR11 Combination Min -8576
29 29 I-End STR12 Combination Max -4394
29 29 J-End STR12 Combination Max -4394
29 29 I-End STR12 Combination Min -8937
29 29 J-End STR12 Combination Min -8937
29 29 I-End STR13 Combination Max -5903
29 29 J-End STR13 Combination Max -5903
29 29 I-End STR13 Combination Min -10446
29 29 J-End STR13 Combination Min -10446
29 29 I-End STR14 Combination Max -6264
29 29 J-End STR14 Combination Max -6264
29 29 I-End STR14 Combination Min -10807
29 29 J-End STR14 Combination Min -10807
29 29 I-End STR15 Combination Max -3838
29 29 J-End STR15 Combination Max -3838
29 29 I-End STR15 Combination Min -8381
29 29 J-End STR15 Combination Min -8381
29 29 I-End STR16 Combination Max -4198
29 29 J-End STR16 Combination Max -4198
29 29 I-End STR16 Combination Min -8741
29 29 J-End STR16 Combination Min -8741
29 29 I-End STR17 Combination Max -6236
29 29 J-End STR17 Combination Max -6236
29 29 I-End STR17 Combination Min -10779
29 29 J-End STR17 Combination Min -10779
29 29 I-End STR18 Combination Max -6452
29 29 J-End STR18 Combination Max -6452
29 29 I-End STR18 Combination Min -10995
29 29 J-End STR18 Combination Min -10995
29 29 I-End STR19 Combination Max -4170
29 29 J-End STR19 Combination Max -4170

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 78
Relazione illustrativa e di calcolo Progetto Definitivo

29 29 I-End STR19 Combination Min -8713


29 29 J-End STR19 Combination Min -8713
29 29 I-End STR20 Combination Max -4387
29 29 J-End STR20 Combination Max -4387
29 29 I-End STR20 Combination Min -8930
29 29 J-End STR20 Combination Min -8930
29 29 I-End STR21 Combination Max -5910
29 29 J-End STR21 Combination Max -5910
29 29 I-End STR21 Combination Min -10453
29 29 J-End STR21 Combination Min -10453
29 29 I-End STR22 Combination Max -6126
29 29 J-End STR22 Combination Max -6126
29 29 I-End STR22 Combination Min -10669
29 29 J-End STR22 Combination Min -10669
29 29 I-End STR23 Combination Max -3845
29 29 J-End STR23 Combination Max -3845
29 29 I-End STR23 Combination Min -8388
29 29 J-End STR23 Combination Min -8388
29 29 I-End STR24 Combination Max -4061
29 29 J-End STR24 Combination Max -4061
29 29 I-End STR24 Combination Min -8604
29 29 J-End STR24 Combination Min -8604
29 29 I-End STR25 Combination Max -6217
29 29 J-End STR25 Combination Max -6217
29 29 I-End STR25 Combination Min -10760
29 29 J-End STR25 Combination Min -10760
29 29 I-End STR26 Combination Max -6434
29 29 J-End STR26 Combination Max -6434
29 29 I-End STR26 Combination Min -10977
29 29 J-End STR26 Combination Min -10977
29 29 I-End STR27 Combination Max -6022
29 29 J-End STR27 Combination Max -6022
29 29 I-End STR27 Combination Min -10565
29 29 J-End STR27 Combination Min -10565
29 29 I-End STR28 Combination Max -6238
29 29 J-End STR28 Combination Max -6238
29 29 I-End STR28 Combination Min -10781
29 29 J-End STR28 Combination Min -10781
29 29 I-End STR29 Combination Max -4152
29 29 J-End STR29 Combination Max -4152
29 29 I-End STR29 Combination Min -8695
29 29 J-End STR29 Combination Min -8695
29 29 I-End STR30 Combination Max -4368

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 79
Relazione illustrativa e di calcolo Progetto Definitivo

29 29 J-End STR30 Combination Max -4368


29 29 I-End STR30 Combination Min -8911
29 29 J-End STR30 Combination Min -8911
29 29 I-End STR31 Combination Max -3957
29 29 J-End STR31 Combination Max -3957
29 29 I-End STR31 Combination Min -8500
29 29 J-End STR31 Combination Min -8500
29 29 I-End STR32 Combination Max -4173
29 29 J-End STR32 Combination Max -4173
29 29 I-End STR32 Combination Min -8716
29 29 J-End STR32 Combination Min -8716
29 29 I-End QKE1 Combination Max -4443
29 29 J-End QKE1 Combination Max -4443
29 29 I-End QKE1 Combination Min -6994
29 29 J-End QKE1 Combination Min -6994
29 29 I-End QKE2 Combination Max -4307
29 29 J-End QKE2 Combination Max -4307
29 29 I-End QKE2 Combination Min -6858
29 29 J-End QKE2 Combination Min -6858
29 29 I-End QKE3 Combination Max -4400
29 29 J-End QKE3 Combination Max -4400
29 29 I-End QKE3 Combination Min -7037
29 29 J-End QKE3 Combination Min -7037
29 29 I-End QKE4 Combination Max -4265
29 29 J-End QKE4 Combination Max -4265
29 29 I-End QKE4 Combination Min -6901

29 29 J-End QKE4 Combination Min -6901

Appoggio Multidirezionale
F1
KN
Max -3437

Min -12047

Link LinkElem Station OutputCase CaseType StepType P


Text Text Text Text Text Text KN
37 37 I-End STR1 Combination Max -4673
37 37 J-End STR1 Combination Max -4673
37 37 I-End STR1 Combination Min -11225
37 37 J-End STR1 Combination Min -11225
37 37 I-End STR2 Combination Max -2902
37 37 J-End STR2 Combination Max -2902

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 80
Relazione illustrativa e di calcolo Progetto Definitivo

37 37 I-End STR2 Combination Min -9454


37 37 J-End STR2 Combination Min -9454
37 37 I-End STR3 Combination Max -4911
37 37 J-End STR3 Combination Max -4911
37 37 I-End STR3 Combination Min -11463
37 37 J-End STR3 Combination Min -11463
37 37 I-End STR4 Combination Max -3140
37 37 J-End STR4 Combination Max -3140
37 37 I-End STR4 Combination Min -9692
37 37 J-End STR4 Combination Min -9692
37 37 I-End STR5 Combination Max -4468
37 37 J-End STR5 Combination Max -4468
37 37 I-End STR5 Combination Min -11020
37 37 J-End STR5 Combination Min -11020
37 37 I-End STR6 Combination Max -2697
37 37 J-End STR6 Combination Max -2697
37 37 I-End STR6 Combination Min -9249
37 37 J-End STR6 Combination Min -9249
37 37 I-End STR7 Combination Max -4706
37 37 J-End STR7 Combination Max -4706
37 37 I-End STR7 Combination Min -11258
37 37 J-End STR7 Combination Min -11258
37 37 I-End STR8 Combination Max -2935
37 37 J-End STR8 Combination Max -2935
37 37 I-End STR8 Combination Min -9487
37 37 J-End STR8 Combination Min -9487
37 37 I-End STR9 Combination Max -5160
37 37 J-End STR9 Combination Max -5160
37 37 I-End STR9 Combination Min -10014
37 37 J-End STR9 Combination Min -10014
37 37 I-End STR10 Combination Max -5557
37 37 J-End STR10 Combination Max -5557
37 37 I-End STR10 Combination Min -10410
37 37 J-End STR10 Combination Min -10410
37 37 I-End STR11 Combination Max -3389
37 37 J-End STR11 Combination Max -3389
37 37 I-End STR11 Combination Min -8243
37 37 J-End STR11 Combination Min -8243
37 37 I-End STR12 Combination Max -3786
37 37 J-End STR12 Combination Max -3786
37 37 I-End STR12 Combination Min -8639
37 37 J-End STR12 Combination Min -8639
37 37 I-End STR13 Combination Max -4955

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 81
Relazione illustrativa e di calcolo Progetto Definitivo

37 37 J-End STR13 Combination Max -4955


37 37 I-End STR13 Combination Min -9808
37 37 J-End STR13 Combination Min -9808
37 37 I-End STR14 Combination Max -5352
37 37 J-End STR14 Combination Max -5352
37 37 I-End STR14 Combination Min -10205
37 37 J-End STR14 Combination Min -10205
37 37 I-End STR15 Combination Max -3184
37 37 J-End STR15 Combination Max -3184
37 37 I-End STR15 Combination Min -8037
37 37 J-End STR15 Combination Min -8037
37 37 I-End STR16 Combination Max -3581
37 37 J-End STR16 Combination Max -3581
37 37 I-End STR16 Combination Min -8434
37 37 J-End STR16 Combination Min -8434
37 37 I-End STR17 Combination Max -5308
37 37 J-End STR17 Combination Max -5308
37 37 I-End STR17 Combination Min -10161
37 37 J-End STR17 Combination Min -10161
37 37 I-End STR18 Combination Max -5546
37 37 J-End STR18 Combination Max -5546
37 37 I-End STR18 Combination Min -10399
37 37 J-End STR18 Combination Min -10399
37 37 I-End STR19 Combination Max -3537
37 37 J-End STR19 Combination Max -3537
37 37 I-End STR19 Combination Min -8390
37 37 J-End STR19 Combination Min -8390
37 37 I-End STR20 Combination Max -3775
37 37 J-End STR20 Combination Max -3775
37 37 I-End STR20 Combination Min -8628
37 37 J-End STR20 Combination Min -8628
37 37 I-End STR21 Combination Max -4966
37 37 J-End STR21 Combination Max -4966
37 37 I-End STR21 Combination Min -9819
37 37 J-End STR21 Combination Min -9819
37 37 I-End STR22 Combination Max -5204
37 37 J-End STR22 Combination Max -5204
37 37 I-End STR22 Combination Min -10057
37 37 J-End STR22 Combination Min -10057
37 37 I-End STR23 Combination Max -3195
37 37 J-End STR23 Combination Max -3195
37 37 I-End STR23 Combination Min -8048
37 37 J-End STR23 Combination Min -8048

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 82
Relazione illustrativa e di calcolo Progetto Definitivo

37 37 I-End STR24 Combination Max -3433


37 37 J-End STR24 Combination Max -3433
37 37 I-End STR24 Combination Min -8286
37 37 J-End STR24 Combination Min -8286
37 37 I-End STR25 Combination Max -5228
37 37 J-End STR25 Combination Max -5228
37 37 I-End STR25 Combination Min -10081
37 37 J-End STR25 Combination Min -10081
37 37 I-End STR26 Combination Max -5466
37 37 J-End STR26 Combination Max -5466
37 37 I-End STR26 Combination Min -10319
37 37 J-End STR26 Combination Min -10319
37 37 I-End STR27 Combination Max -5023
37 37 J-End STR27 Combination Max -5023
37 37 I-End STR27 Combination Min -9876
37 37 J-End STR27 Combination Min -9876
37 37 I-End STR28 Combination Max -5261
37 37 J-End STR28 Combination Max -5261
37 37 I-End STR28 Combination Min -10114
37 37 J-End STR28 Combination Min -10114
37 37 I-End STR29 Combination Max -3457
37 37 J-End STR29 Combination Max -3457
37 37 I-End STR29 Combination Min -8310
37 37 J-End STR29 Combination Min -8310
37 37 I-End STR30 Combination Max -3695
37 37 J-End STR30 Combination Max -3695
37 37 I-End STR30 Combination Min -8548
37 37 J-End STR30 Combination Min -8548
37 37 I-End STR31 Combination Max -3252
37 37 J-End STR31 Combination Max -3252
37 37 I-End STR31 Combination Min -8105
37 37 J-End STR31 Combination Min -8105
37 37 I-End STR32 Combination Max -3490
37 37 J-End STR32 Combination Max -3490
37 37 I-End STR32 Combination Min -8343
37 37 J-End STR32 Combination Min -8343
37 37 I-End QKE1 Combination Max -4127
37 37 J-End QKE1 Combination Max -4127
37 37 I-End QKE1 Combination Min -6545
37 37 J-End QKE1 Combination Min -6545
37 37 I-End QKE2 Combination Max -3985
37 37 J-End QKE2 Combination Max -3985
37 37 I-End QKE2 Combination Min -6402

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 83
Relazione illustrativa e di calcolo Progetto Definitivo

37 37 J-End QKE2 Combination Min -6402


37 37 I-End QKE3 Combination Max -3453
37 37 J-End QKE3 Combination Max -3453
37 37 I-End QKE3 Combination Min -7219
37 37 J-End QKE3 Combination Min -7219
37 37 I-End QKE4 Combination Max -3311
37 37 J-End QKE4 Combination Max -3311
37 37 I-End QKE4 Combination Min -7076

37 37 J-End QKE4 Combination Min -7076

Appoggio Multidirezionale
F1
KN

Max -2697

Min -11463

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 84
Relazione illustrativa e di calcolo Progetto Definitivo

10 VERIFICA PILE

10.1 Verifica sezione di base pila


Si riporta nel seguito la verifica strutturale delle pile del ponte considerando le sollecitazioni
agenti alla base.

DATI GENERALI DELLA SEZIONE

Calcestruzzo: Rck = 35.00 N/mmq

Sezione:
Vertice X (cm) Y (cm)
1 0.0 0.0
2 0.0 100.0
3 506.0 100.0
4 506.0 0.0
5 0.0 0.0
6 0.0 0.0

Acciaio: fyk = 450.00 N/mmq

Ferro N. X (cm) Y (cm) Area (cmq)


1 5.0 5.0 3.14
2 24.8 5.0 3.14
3 44.7 5.0 3.14
4 64.5 5.0 3.14
5 84.4 5.0 3.14
6 104.2 5.0 3.14
7 124.0 5.0 3.14
8 143.9 5.0 3.14
9 163.7 5.0 3.14
10 183.6 5.0 3.14
11 203.4 5.0 3.14
12 223.2 5.0 3.14
13 243.1 5.0 3.14
14 262.9 5.0 3.14
15 282.8 5.0 3.14
16 302.6 5.0 3.14
17 322.4 5.0 3.14
18 342.3 5.0 3.14
19 362.1 5.0 3.14
20 382.0 5.0 3.14
21 401.8 5.0 3.14
22 421.6 5.0 3.14
23 441.5 5.0 3.14
24 461.3 5.0 3.14
25 481.2 5.0 3.14
26 501.0 5.0 3.14
27 5.0 95.0 3.14

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 85
Relazione illustrativa e di calcolo Progetto Definitivo

28 24.8 95.0 3.14


29 44.7 95.0 3.14
30 64.5 95.0 3.14
31 84.4 95.0 3.14
32 104.2 95.0 3.14
33 124.0 95.0 3.14
34 143.9 95.0 3.14
35 163.7 95.0 3.14
36 183.6 95.0 3.14
37 203.4 95.0 3.14
38 223.2 95.0 3.14
39 243.1 95.0 3.14
40 262.9 95.0 3.14
41 282.8 95.0 3.14
42 302.6 95.0 3.14
43 322.4 95.0 3.14
44 342.3 95.0 3.14
45 362.1 95.0 3.14
46 382.0 95.0 3.14
47 401.8 95.0 3.14
48 421.6 95.0 3.14
49 441.5 95.0 3.14
50 461.3 95.0 3.14
51 481.2 95.0 3.14
52 501.0 95.0 3.14

Caratteristiche limite della sezione:


Nu [kN] Mxu [kN m] Myu [kN m]
Sezione completamente tesa -6392.5 0.0 0.0
Sezione completamente compressa 89688.5 0.0 0.0
Fibre inferiori tese 0.0 2934.1 0.0
Fibre superiori tese 0.0 -2934.1 0.0
Fibre di sinistra tese 0.0 0.0 14489.5
Fibre di destra tese 0.0 0.0 -14489.5

VERIFICA AGLI STATI LIMITE ULTIMI

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Coef. sicurezza: Gamma

Soll.n. Nd Mxd Myd Nu Mxu Myu EpsC EpsA Gamma


1 22735.0 2496.0 3739.0 22735.0 10191.5 15266.9 -0.35 0.44 4.08 Ok
2 17551.0 -92.0 -12610.0 17551.0 -326.5 -44758.5 -0.35 0.77 3.55 Ok
3 17927.0 2095.0 5673.0 17927.0 8238.7 22309.4 -0.35 0.49 3.93 Ok
4 12742.0 -494.0 -10676.0 12742.0 -1718.0 -37129.0 -0.35 0.82 3.48 Ok
5 22738.0 2795.0 2068.0 22738.0 10781.1 7976.9 -0.35 0.51 3.86 Ok
6 17554.0 207.0 -14281.0 17554.0 646.1 -44577.7 -0.35 0.74 3.12 Ok
7 17930.0 2394.0 4002.0 17930.0 9055.3 15137.6 -0.35 0.55 3.78 Ok
8 12746.0 -195.0 -12347.0 12746.0 -602.9 -38172.2 -0.35 0.98 3.09 Ok
9 22901.0 2734.0 2539.0 22901.0 10685.2 9923.0 -0.35 0.49 3.91 Ok
10 17717.0 146.0 -13810.0 17717.0 474.5 -44878.1 -0.35 0.75 3.25 Ok
11 18093.0 2332.0 4473.0 18093.0 8910.3 17090.8 -0.35 0.53 3.82 Ok
12 12909.0 -256.0 -11876.0 12909.0 -824.9 -38266.4 -0.35 0.94 3.22 Ok
13 22905.0 3033.0 867.0 22905.0 11033.9 3154.1 -0.35 0.57 3.64 Ok
14 17720.0 445.0 -15482.0 17720.0 1271.3 -44230.0 -0.35 0.68 2.86 Ok
15 18096.0 2632.0 2801.0 18096.0 9502.0 10112.1 -0.35 0.62 3.61 Ok
16 12912.0 43.0 -13548.0 12912.0 122.4 -38569.1 -0.33 1.00 2.85 Ok
17 21511.0 1966.0 2314.0 21511.0 10214.2 12022.2 -0.35 0.50 5.20 Ok
18 17670.0 49.0 -9796.0 17670.0 224.9 -44951.7 -0.35 0.78 4.59 Ok
19 21516.0 2465.0 -472.0 21516.0 10748.5 -2058.1 -0.35 0.64 4.36 Ok
20 17676.0 547.0 -12582.0 17676.0 1887.3 -43411.6 -0.35 0.64 3.45 Ok
21 16702.0 1565.0 4248.0 16702.0 7998.6 21711.1 -0.35 0.52 5.11 Ok
22 12862.0 -353.0 -7862.0 12862.0 -1677.2 -37354.1 -0.35 0.82 4.75 Ok
23 16708.0 2063.0 1462.0 16708.0 9319.0 6604.2 -0.35 0.74 4.52 Ok
24 12868.0 146.0 -10648.0 12868.0 526.4 -38394.2 -0.35 0.99 3.61 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 86
Relazione illustrativa e di calcolo Progetto Definitivo

25 21677.0 2204.0 1114.0 21677.0 10680.4 5398.4 -0.35 0.58 4.85 Ok


26 17837.0 287.0 -10997.0 17837.0 1160.9 -44481.8 -0.35 0.68 4.04 Ok
27 21682.0 2703.0 -1672.0 21682.0 10624.4 -6572.0 -0.35 0.56 3.93 Ok
28 17842.0 785.0 -13783.0 17842.0 2434.2 -42739.8 -0.35 0.60 3.10 Ok
29 16868.0 1803.0 3048.0 16868.0 8790.2 14859.9 -0.35 0.58 4.88 Ok
30 13028.0 -115.0 -9063.0 13028.0 -490.4 -38646.9 -0.35 0.99 4.26 Ok
31 16874.0 2301.0 262.0 16874.0 9546.3 1087.0 -0.35 0.92 4.15 Ok
32 13034.0 384.0 -11849.0 13034.0 1234.5 -38093.4 -0.35 0.87 3.21 Ok
33 21456.0 1987.0 2157.0 21456.0 10271.0 11149.7 -0.35 0.51 5.17 Ok
34 17616.0 69.0 -9953.0 17616.0 310.9 -44844.7 -0.35 0.77 4.51 Ok
35 21460.0 2286.0 486.0 21459.8 10730.5 2281.3 -0.35 0.64 4.69 Ok
36 17620.0 368.0 -11625.0 17620.0 1392.2 -43978.1 -0.35 0.67 3.78 Ok
37 16648.0 1585.0 4091.0 16648.0 8093.7 20890.6 -0.35 0.52 5.11 Ok
38 12808.0 -332.0 -8019.0 12808.0 -1549.6 -37428.6 -0.35 0.84 4.67 Ok
39 16651.0 1884.0 2420.0 16651.0 8995.9 11555.3 -0.35 0.64 4.77 Ok
40 12811.0 -33.0 -9691.0 12811.0 -130.8 -38413.2 -0.33 1.00 3.96 Ok
41 21733.0 2383.0 157.0 21732.9 10821.7 713.0 -0.35 0.66 4.54 Ok
42 17893.0 466.0 -11954.0 17893.0 1711.6 -43906.8 -0.35 0.64 3.67 Ok
43 21737.0 2682.0 -1515.0 21737.0 10665.1 -6024.4 -0.35 0.57 3.98 Ok
44 17897.0 765.0 -13626.0 17897.0 2405.9 -42852.5 -0.35 0.60 3.14 Ok
45 16925.0 1982.0 2090.0 16925.0 9202.4 9703.9 -0.35 0.66 4.64 Ok
46 13085.0 64.0 -10020.0 13085.0 247.9 -38816.1 -0.34 1.00 3.87 Ok
47 16928.0 2281.0 419.0 16928.0 9551.8 1754.6 -0.35 0.89 4.19 Ok
48 13088.0 363.0 -11692.0 13088.0 1186.6 -38218.2 -0.35 0.87 3.27 Ok
49 21579.0 2105.0 1576.0 21579.0 10526.1 7880.8 -0.35 0.54 5.00 Ok
50 17739.0 187.0 -10535.0 17739.0 793.2 -44688.4 -0.35 0.72 4.24 Ok
51 21583.0 2404.0 -96.0 21583.0 10790.3 -430.9 -0.35 0.68 4.49 Ok
52 17743.0 486.0 -12206.0 17743.0 1739.7 -43693.2 -0.35 0.64 3.58 Ok
53 21745.0 2343.0 375.0 21744.8 10808.2 1729.9 -0.35 0.64 4.61 Ok
54 17905.0 425.0 -11735.0 17905.0 1596.0 -44069.4 -0.35 0.65 3.76 Ok
55 21749.0 2642.0 -1297.0 21749.0 10703.3 -5254.4 -0.35 0.58 4.05 Ok
56 17909.0 724.0 -13407.0 17909.0 2322.5 -43008.5 -0.35 0.60 3.21 Ok
57 16771.0 1703.0 3509.0 16771.0 8508.0 17530.6 -0.35 0.55 5.00 Ok
58 12931.0 -214.0 -8601.0 12931.0 -950.4 -38198.3 -0.35 0.92 4.44 Ok
59 16774.0 2002.0 1838.0 16774.0 9235.3 8478.8 -0.35 0.70 4.61 Ok
60 12934.0 85.0 -10273.0 12934.0 319.1 -38569.6 -0.34 1.00 3.75 Ok
61 16937.0 1941.0 2309.0 16937.0 9127.7 10858.2 -0.35 0.64 4.70 Ok
62 13097.0 24.0 -9802.0 13097.0 95.1 -38854.4 -0.33 1.00 3.96 Ok
63 16941.0 2240.0 637.0 16941.0 9536.1 2711.8 -0.35 0.85 4.26 Ok
64 13100.0 323.0 -11473.0 13100.0 1079.2 -38333.4 -0.35 0.89 3.34 Ok
65 14983.0 3434.0 4927.0 14983.0 8459.7 12137.8 -0.35 0.68 2.46 Ok
66 12118.0 -2084.0 -11067.0 12118.0 -5287.2 -28077.3 -0.35 0.61 2.54 Ok
67 15099.0 3599.0 4093.0 15099.0 8651.9 9839.5 -0.35 0.73 2.40 Ok
68 12233.0 -1918.0 -11901.0 12233.0 -4815.2 -29877.8 -0.35 0.62 2.51 Ok
69 14356.0 5807.0 9725.0 14356.0 8151.4 13651.2 -0.35 0.68 1.40 Ok
70 12745.0 -4457.0 -15865.0 12745.0 -6541.7 -23285.7 -0.35 0.59 1.47 Ok
71 14472.0 5973.0 8891.0 14472.0 8288.0 12336.9 -0.35 0.70 1.39 Ok
72 12860.0 -4292.0 -16698.0 12860.0 -6333.6 -24640.7 -0.35 0.59 1.48 Ok
73 22900.0 399.0 12755.0 22900.0 1542.7 49317.5 -0.35 0.52 3.87 Ok
74 17721.0 -1552.0 -5397.0 17721.0 -7534.4 -26200.3 -0.35 0.48 4.85 Ok
75 18088.0 637.0 11561.0 18088.0 2376.1 43124.2 -0.35 0.60 3.73 Ok
76 12908.0 -1314.0 -6591.0 12908.0 -5599.4 -28086.4 -0.35 0.58 4.26 Ok
77 22897.0 708.0 10969.0 22897.0 3019.1 46774.4 -0.35 0.46 4.26 Ok
78 17718.0 -1243.0 -7183.0 17718.0 -5825.3 -33663.1 -0.35 0.49 4.69 Ok
79 18085.0 947.0 9775.0 18085.0 3875.4 40001.9 -0.35 0.53 4.09 Ok
80 12906.0 -1005.0 -8376.0 12906.0 -3981.7 -33184.7 -0.35 0.64 3.96 Ok
81 23070.0 274.0 13380.0 23070.0 1025.0 50053.0 -0.35 0.54 3.74 Ok
82 17891.0 -1677.0 -4772.0 17891.0 -8112.5 -23084.6 -0.35 0.49 4.84 Ok
83 18258.0 512.0 12187.0 18258.0 1854.3 44137.0 -0.35 0.62 3.62 Ok
84 13078.0 -1439.0 -5965.0 13078.0 -6198.8 -25695.5 -0.35 0.58 4.31 Ok
85 23068.0 584.0 11594.0 23068.0 2422.9 48100.2 -0.35 0.48 4.15 Ok
86 17888.0 -1367.0 -6558.0 17888.0 -6506.1 -31212.3 -0.35 0.47 4.76 Ok
87 18255.0 822.0 10401.0 18255.0 3284.4 41558.1 -0.35 0.55 4.00 Ok
88 13076.0 -1129.0 -7751.0 13076.0 -4618.4 -31707.2 -0.35 0.61 4.09 Ok
89 21678.0 59.0 10766.0 21678.0 270.2 49310.8 -0.35 0.62 4.58 Ok
90 17841.0 -1386.0 -2680.0 17841.0 -8842.9 -17098.7 -0.35 0.53 6.38 Ok
91 21673.0 575.0 7790.0 21673.0 3321.6 45000.6 -0.35 0.48 5.78 Ok
92 17837.0 -871.0 -5656.0 17837.0 -5423.6 -35219.1 -0.35 0.49 6.23 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 87
Relazione illustrativa e di calcolo Progetto Definitivo

93 16865.0 297.0 9573.0 16865.0 1338.0 43125.3 -0.35 0.70 4.50 Ok


94 13029.0 -1148.0 -3873.0 13029.0 -6732.7 -22714.1 -0.35 0.59 5.86 Ok
95 16861.0 813.0 6597.0 16861.0 4539.7 36836.9 -0.35 0.53 5.58 Ok
96 13024.0 -632.0 -6849.0 13024.0 -3233.2 -35037.9 -0.35 0.68 5.12 Ok
97 21848.0 -66.0 11392.0 21848.0 -286.6 49467.5 -0.35 0.61 4.34 Ok
98 18011.0 -1511.0 -2054.0 18011.0 -9291.9 -12631.0 -0.35 0.58 6.15 Ok
99 21843.0 450.0 8415.0 21843.0 2504.3 46830.5 -0.35 0.50 5.57 Ok
100 18007.0 -995.0 -5031.0 18007.0 -6336.9 -32041.2 -0.35 0.47 6.37 Ok
101 17035.0 172.0 10198.0 17035.0 740.1 43878.9 -0.35 0.75 4.30 Ok
102 13199.0 -1273.0 -3248.0 13199.0 -7319.0 -18674.2 -0.35 0.63 5.75 Ok
103 17031.0 688.0 7222.0 17031.0 3728.8 39141.2 -0.35 0.56 5.42 Ok
104 13194.0 -757.0 -6224.0 13194.0 -4060.9 -33388.4 -0.35 0.63 5.36 Ok
105 21620.0 203.0 9963.0 21620.0 992.8 48727.1 -0.35 0.58 4.89 Ok
106 17784.0 -1242.0 -3483.0 17784.0 -8128.9 -22796.4 -0.35 0.49 6.55 Ok
107 21617.0 513.0 8177.0 21617.0 2879.2 45893.7 -0.35 0.49 5.61 Ok
108 17781.0 -932.0 -5269.0 17781.0 -5911.2 -33418.6 -0.35 0.48 6.34 Ok
109 16808.0 442.0 8769.0 16808.0 2118.3 42024.8 -0.35 0.65 4.79 Ok
110 12971.0 -1004.0 -4677.0 12971.0 -5836.7 -27189.4 -0.35 0.58 5.81 Ok
111 16805.0 751.0 6983.0 16805.0 4085.9 37991.7 -0.35 0.55 5.44 Ok
112 12968.0 -694.0 -6462.0 12968.0 -3656.2 -34044.1 -0.35 0.66 5.27 Ok
113 21904.0 -4.0 11005.0 21904.0 -18.0 49640.2 -0.35 0.63 4.51 Ok
114 18067.0 -1449.0 -2441.0 18067.0 -9077.6 -15292.2 -0.35 0.55 6.26 Ok
115 21901.0 305.0 9219.0 21901.0 1598.5 48315.9 -0.35 0.54 5.24 Ok
116 18064.0 -1140.0 -4227.0 18064.0 -7392.4 -27410.3 -0.35 0.47 6.48 Ok
117 17091.0 234.0 9811.0 17091.0 1042.2 43696.9 -0.35 0.72 4.45 Ok
118 13255.0 -1211.0 -3634.0 13255.0 -7040.1 -21126.2 -0.35 0.60 5.81 Ok
119 17089.0 544.0 8026.0 17089.0 2793.0 41207.2 -0.35 0.60 5.13 Ok
120 13252.0 -902.0 -5420.0 13252.0 -5077.9 -30512.3 -0.35 0.59 5.63 Ok
121 21662.0 153.0 10214.0 21662.0 733.9 48990.7 -0.35 0.59 4.80 Ok
122 17825.0 -1292.0 -3232.0 17825.0 -8394.8 -20999.9 -0.35 0.50 6.50 Ok
123 21659.0 463.0 8428.0 21659.0 2557.7 46557.8 -0.35 0.50 5.52 Ok
124 17823.0 -982.0 -5018.0 17823.0 -6275.3 -32066.6 -0.35 0.48 6.39 Ok
125 21832.0 29.0 10839.0 21832.0 132.5 49526.0 -0.35 0.63 4.57 Ok
126 17995.0 -1417.0 -2607.0 17995.0 -8947.2 -16461.1 -0.35 0.54 6.31 Ok
127 21829.0 338.0 9053.0 21829.0 1791.5 47984.1 -0.35 0.53 5.30 Ok
128 17993.0 -1107.0 -4393.0 17993.0 -7164.4 -28431.2 -0.35 0.47 6.47 Ok
129 16849.0 391.0 9021.0 16849.0 1841.3 42481.0 -0.35 0.66 4.71 Ok
130 13013.0 -1054.0 -4425.0 13013.0 -6150.2 -25820.2 -0.35 0.58 5.84 Ok
131 16847.0 701.0 7235.0 16847.0 3763.2 38839.8 -0.35 0.56 5.37 Ok
132 13010.0 -744.0 -6211.0 13010.0 -3990.2 -33310.7 -0.35 0.64 5.36 Ok
133 17019.0 267.0 9646.0 17019.0 1202.9 43458.3 -0.35 0.71 4.51 Ok
134 13183.0 -1178.0 -3800.0 13183.0 -6870.3 -22162.4 -0.35 0.59 5.83 Ok
135 17017.0 576.0 7860.0 17017.0 2986.0 40746.3 -0.35 0.59 5.18 Ok
136 13180.0 -869.0 -5586.0 13180.0 -4847.3 -31158.7 -0.35 0.60 5.58 Ok
137 14828.0 2482.0 8819.0 14828.0 6963.6 24743.0 -0.35 0.54 2.81 Ok
138 12591.0 -2782.0 -6958.0 12591.0 -7194.6 -17994.3 -0.35 0.65 2.59 Ok
139 14946.0 2395.0 9253.0 14946.0 6746.6 26065.2 -0.35 0.53 2.82 Ok
140 12709.0 -2868.0 -6524.0 12709.0 -7359.7 -16741.5 -0.35 0.67 2.57 Ok
141 14488.0 4972.0 14881.0 14488.0 7323.0 21917.4 -0.35 0.56 1.47 Ok
142 12931.0 -5272.0 -13021.0 12931.0 -7301.6 -18033.8 -0.35 0.64 1.38 Ok
143 14607.0 4885.0 15316.0 14607.0 7241.7 22704.9 -0.35 0.55 1.48 Ok
144 13049.0 -5358.0 -12586.0 13049.0 -7405.7 -17396.0 -0.35 0.65 1.38 Ok

VERIFICA AGLI STATI LIMITE DI ESERCIZIO

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Tensioni: [N/mmq] (CLS: SigC+ = max; SigC- = min) (Acciaio: SigA+ = max; SigA- = min)
Fessurazione: Wk [mm]
Coef. sicurezza: GammaC = SigC/fck; GammaA = SigA/fyk

COMBINAZIONI DI CARICO RARE:

Soll.n. Nd Mxd Myd SigC+ SigC- SigA+ SigA- GammaC GammaA Wk


145 16718.0 1734.0 3312.0 -0.57 -5.73 -11.57 -82.97 0.20 0.18 0.000 Ok
146 12878.0 -183.0 -8798.0 -0.27 -4.58 -4.93 -67.90 0.16 0.15 0.000 Ok
147 16720.0 1933.0 2198.0 -0.61 -5.69 -12.38 -82.17 0.20 0.18 0.000 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 88
Relazione illustrativa e di calcolo Progetto Definitivo

148 12880.0 16.0 -9912.0 -0.20 -4.66 -3.67 -69.17 0.16 0.15 0.000 Ok
149 16856.0 1932.0 2312.0 -0.61 -5.74 -12.40 -82.92 0.20 0.18 0.000 Ok
150 13016.0 15.0 -9798.0 -0.25 -4.66 -4.44 -69.16 0.16 0.15 0.000 Ok
151 16859.0 2132.0 1198.0 -0.65 -5.71 -13.20 -82.13 0.20 0.18 0.000 Ok
152 13019.0 214.0 -10913.0 0.00 -5.12 2.12 -75.72 0.18 0.17 0.000 Ok
153 15843.0 1360.0 2268.0 -1.04 -4.94 -17.88 -71.72 0.17 0.16 0.000 Ok
154 12963.0 -78.0 -6815.0 -0.84 -4.05 -13.18 -60.13 0.14 0.13 0.000 Ok
155 15982.0 1559.0 1268.0 -1.08 -4.95 -18.70 -71.68 0.17 0.16 0.000 Ok
156 13102.0 121.0 -7815.0 -0.60 -4.34 -9.67 -64.42 0.15 0.14 0.000 Ok
157 15847.0 1693.0 411.0 -1.10 -4.88 -19.21 -70.40 0.17 0.16 0.000 Ok
158 12967.0 255.0 -8672.0 -0.24 -4.65 -4.56 -68.77 0.16 0.15 0.000 Ok
159 15986.0 1891.0 -590.0 -0.88 -5.15 -16.18 -74.22 0.18 0.16 0.000 Ok
160 13106.0 453.0 -9673.0 0.00 -5.11 1.18 -75.29 0.18 0.17 0.000 Ok
161 15798.0 1361.0 2230.0 -1.04 -4.92 -17.86 -71.48 0.17 0.16 0.000 Ok
162 12918.0 -77.0 -6853.0 -0.82 -4.05 -12.94 -60.11 0.14 0.13 0.000 Ok
163 15800.0 1560.0 1116.0 -1.07 -4.88 -18.67 -70.68 0.17 0.16 0.000 Ok
164 12920.0 122.0 -7967.0 -0.53 -4.34 -8.65 -64.42 0.15 0.14 0.000 Ok
165 16029.0 1691.0 563.0 -1.10 -4.94 -19.26 -71.39 0.17 0.16 0.000 Ok
166 13149.0 253.0 -8520.0 -0.31 -4.65 -5.60 -68.75 0.16 0.15 0.000 Ok
167 16031.0 1890.0 -552.0 -0.89 -5.15 -16.45 -74.21 0.18 0.16 0.000 Ok
168 13151.0 452.0 -9635.0 0.00 -5.11 0.91 -75.28 0.18 0.17 0.000 Ok
169 15894.0 1455.0 1762.0 -1.06 -4.93 -18.32 -71.56 0.17 0.16 0.000 Ok
170 13014.0 17.0 -7321.0 -0.80 -4.10 -12.53 -61.06 0.14 0.14 0.000 Ok
171 15896.0 1655.0 648.0 -1.10 -4.90 -19.12 -70.78 0.17 0.16 0.000 Ok
172 13016.0 217.0 -8435.0 -0.34 -4.57 -6.02 -67.58 0.16 0.15 0.000 Ok
173 16033.0 1654.0 762.0 -1.10 -4.95 -19.14 -71.52 0.17 0.16 0.000 Ok
174 13153.0 216.0 -8321.0 -0.39 -4.57 -6.80 -67.58 0.16 0.15 0.000 Ok
175 16035.0 1853.0 -353.0 -0.98 -5.07 -17.64 -73.04 0.17 0.16 0.000 Ok
176 13155.0 415.0 -9436.0 0.00 -5.03 -0.29 -74.10 0.17 0.16 0.000 Ok
177 16878.0 441.0 8732.0 -0.77 -5.60 -12.76 -82.69 0.19 0.18 0.000 Ok
178 13042.0 -1004.0 -4714.0 -0.34 -4.58 -7.03 -66.72 0.16 0.15 0.000 Ok
179 16876.0 648.0 7542.0 -0.81 -5.55 -13.69 -81.74 0.19 0.18 0.000 Ok
180 13040.0 -798.0 -5904.0 -0.29 -4.62 -6.07 -67.67 0.16 0.15 0.000 Ok
181 17020.0 337.0 9253.0 -0.79 -5.63 -12.94 -83.31 0.19 0.19 0.000 Ok
182 13183.0 -1108.0 -4193.0 -0.37 -4.60 -7.65 -66.90 0.16 0.15 0.000 Ok
183 17018.0 544.0 8063.0 -0.83 -5.58 -13.87 -82.36 0.19 0.18 0.000 Ok
184 13182.0 -901.0 -5383.0 -0.33 -4.64 -6.71 -67.84 0.16 0.15 0.000 Ok
185 16005.0 203.0 7284.0 -1.18 -4.86 -18.45 -72.06 0.17 0.16 0.000 Ok
186 13128.0 -881.0 -2801.0 -0.91 -4.03 -15.31 -58.93 0.14 0.13 0.000 Ok
187 16147.0 100.0 7805.0 -1.20 -4.89 -18.62 -72.69 0.17 0.16 0.000 Ok
188 13269.0 -984.0 -2280.0 -0.95 -4.05 -15.94 -59.09 0.14 0.13 0.000 Ok
189 16002.0 547.0 5299.0 -1.25 -4.78 -20.03 -70.46 0.16 0.16 0.000 Ok
190 13125.0 -537.0 -4785.0 -0.84 -4.11 -13.72 -60.50 0.14 0.13 0.000 Ok
191 16144.0 444.0 5820.0 -1.27 -4.81 -20.19 -71.10 0.17 0.16 0.000 Ok
192 13266.0 -640.0 -4264.0 -0.87 -4.13 -14.35 -60.67 0.14 0.13 0.000 Ok
193 15957.0 307.0 6713.0 -1.18 -4.83 -18.70 -71.54 0.17 0.16 0.000 Ok
194 13080.0 -777.0 -3371.0 -0.89 -4.04 -14.80 -59.17 0.14 0.13 0.000 Ok
195 15955.0 513.0 5523.0 -1.23 -4.78 -19.65 -70.58 0.16 0.16 0.000 Ok
196 13078.0 -571.0 -4562.0 -0.84 -4.09 -13.83 -60.12 0.14 0.13 0.000 Ok
197 16193.0 134.0 7582.0 -1.22 -4.89 -18.99 -72.58 0.17 0.16 0.000 Ok
198 13316.0 -950.0 -2503.0 -0.94 -4.08 -15.83 -59.47 0.14 0.13 0.000 Ok
199 16192.0 340.0 6391.0 -1.27 -4.84 -19.95 -71.62 0.17 0.16 0.000 Ok
200 13314.0 -744.0 -3693.0 -0.90 -4.12 -14.87 -60.42 0.14 0.13 0.000 Ok
201 15993.0 266.0 6919.0 -1.19 -4.84 -18.71 -71.73 0.17 0.16 0.000 Ok
202 13116.0 -818.0 -3166.0 -0.90 -4.05 -14.98 -59.19 0.14 0.13 0.000 Ok
203 15991.0 472.0 5728.0 -1.24 -4.79 -19.66 -70.77 0.16 0.16 0.000 Ok
204 13114.0 -612.0 -4356.0 -0.85 -4.09 -14.02 -60.14 0.14 0.13 0.000 Ok
205 16135.0 162.0 7440.0 -1.21 -4.87 -18.89 -72.35 0.17 0.16 0.000 Ok
206 13258.0 -922.0 -2645.0 -0.93 -4.07 -15.60 -59.37 0.14 0.13 0.000 Ok
207 16133.0 368.0 6249.0 -1.26 -4.83 -19.84 -71.39 0.17 0.16 0.000 Ok
208 13256.0 -716.0 -3835.0 -0.88 -4.11 -14.64 -60.32 0.14 0.13 0.000 Ok

COMBINAZIONI DI CARICO FREQUENTI:

Soll.n. Nd Mxd Myd SigC+ SigC- SigA+ SigA- GammaC GammaA Wk


209 15845.0 1493.0 1525.0 -1.06 -4.91 -18.42 -71.19 0.17 0.16 0.000 Ok
210 12965.0 55.0 -7558.0 -0.70 -4.19 -11.07 -62.24 0.14 0.14 0.000 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 89
Relazione illustrativa e di calcolo Progetto Definitivo

211 15846.0 1560.0 1154.0 -1.07 -4.90 -18.68 -70.93 0.17 0.16 0.000 Ok
212 12966.0 122.0 -7929.0 -0.55 -4.34 -8.90 -64.42 0.15 0.14 0.000 Ok
213 15983.0 1691.0 525.0 -1.10 -4.92 -19.25 -71.13 0.17 0.16 0.000 Ok
214 13103.0 253.0 -8558.0 -0.29 -4.65 -5.35 -68.75 0.16 0.15 0.000 Ok
215 15984.0 1758.0 153.0 -1.11 -4.91 -19.51 -70.88 0.17 0.16 0.000 Ok
216 13104.0 320.0 -8930.0 -0.14 -4.80 -3.17 -70.93 0.17 0.16 0.000 Ok
217 16004.0 341.0 6490.0 -1.21 -4.83 -19.08 -71.43 0.17 0.16 0.000 Ok
218 13126.0 -743.0 -3594.0 -0.88 -4.06 -14.68 -59.55 0.14 0.13 0.000 Ok
219 16003.0 410.0 6093.0 -1.22 -4.81 -19.39 -71.11 0.17 0.16 0.000 Ok
220 13126.0 -674.0 -3991.0 -0.87 -4.08 -14.37 -59.86 0.14 0.13 0.000 Ok
221 16146.0 237.0 7011.0 -1.23 -4.86 -19.26 -72.05 0.17 0.16 0.000 Ok
222 13268.0 -847.0 -3073.0 -0.92 -4.09 -15.30 -59.73 0.14 0.13 0.000 Ok
223 16145.0 306.0 6614.0 -1.24 -4.84 -19.57 -71.73 0.17 0.16 0.000 Ok
224 13268.0 -778.0 -3470.0 -0.90 -4.10 -14.99 -60.04 0.14 0.13 0.000 Ok

COMBINAZIONI DI CARICO QUASI PERMANENTI:

Soll.n. Nd Mxd Myd SigC+ SigC- SigA+ SigA- GammaC GammaA Wk


225 13236.0 621.0 -2992.0 -1.17 -3.82 -18.71 -56.14 0.13 0.12 0.000 Ok
226 13236.0 621.0 -2992.0 -1.17 -3.82 -18.71 -56.14 0.13 0.12 0.000 Ok
227 13351.0 786.0 -3825.0 -0.83 -4.20 -13.94 -61.56 0.14 0.14 0.000 Ok
228 13351.0 786.0 -3825.0 -0.83 -4.20 -13.94 -61.56 0.14 0.14 0.000 Ok
229 13394.0 -141.0 799.0 -2.20 -2.85 -33.23 -42.51 0.10 0.09 0.000 Ok
230 13394.0 -141.0 799.0 -2.20 -2.85 -33.23 -42.51 0.10 0.09 0.000 Ok
231 13512.0 -227.0 1233.0 -2.03 -3.06 -30.91 -45.50 0.11 0.10 0.000 Ok
232 13512.0 -227.0 1233.0 -2.03 -3.06 -30.91 -45.50 0.11 0.10 0.000 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 90
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 91
Relazione illustrativa e di calcolo Progetto Definitivo

10.2 Verifica fondazione pila


Per le verifiche delle fondazioni della pila si utilizzato lapproccio 2, secondo cui si adotta una sola
combinazione di gruppi di coefficienti parziali: A1+M1+R3.

10.2.1 Azione verticale sul palo


Si analizza nel seguito il carico verticale massimo agente sui pali di fondazione della pila.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 92
Relazione illustrativa e di calcolo Progetto Definitivo

Reazioni esportate dal modello FEM alla base delle pile:


Joint OutputCase CaseType StepType F1 M2 M3 g1

Text Text Text Text KN KNm KNm

1107 STR1 Combination Max 22735 2496 3739 1.35


1107 STR1 Combination Min 17551 -92 -12610 1.35
1107 STR2 Combination Max 17927 2095 5673 1.35
1107 STR2 Combination Min 12742 -494 -10676 1.35
1107 STR3 Combination Max 22738 2795 2068 1.35
1107 STR3 Combination Min 17554 207 -14281 1.35
1107 STR4 Combination Max 17930 2394 4002 1.35
1107 STR4 Combination Min 12746 -195 -12347 1.35
1107 STR5 Combination Max 22901 2734 2539 1.35
1107 STR5 Combination Min 17717 146 -13810 1.35
1107 STR6 Combination Max 18093 2332 4473 1.35
1107 STR6 Combination Min 12909 -256 -11876 1.35
1107 STR7 Combination Max 22905 3033 867 1.35
1107 STR7 Combination Min 17720 445 -15482 1.35
1107 STR8 Combination Max 18096 2632 2801 1.35
1107 STR8 Combination Min 12912 43 -13548 1.35
1107 STR9 Combination Max 21511 1966 2314 1.35
1107 STR9 Combination Min 17670 49 -9796 1.35
1107 STR10 Combination Max 21516 2465 -472 1.35
1107 STR10 Combination Min 17676 547 -12582 1.35
1107 STR11 Combination Max 16702 1565 4248 1.35
1107 STR11 Combination Min 12862 -353 -7862 1.35
1107 STR12 Combination Max 16708 2063 1462 1.35
1107 STR12 Combination Min 12868 146 -10648 1.35
1107 STR13 Combination Max 21677 2204 1114 1.35
1107 STR13 Combination Min 17837 287 -10997 1.35
1107 STR14 Combination Max 21682 2703 -1672 1.35
1107 STR14 Combination Min 17842 785 -13783 1.35
1107 STR15 Combination Max 16868 1803 3048 1.35
1107 STR15 Combination Min 13028 -115 -9063 1.35
1107 STR16 Combination Max 16874 2301 262 1.35
1107 STR16 Combination Min 13034 384 -11849 1.35
1107 STR17 Combination Max 21456 1987 2157 1.35
1107 STR17 Combination Min 17616 69 -9953 1.35
1107 STR18 Combination Max 21460 2286 486 1.35
1107 STR18 Combination Min 17620 368 -11625 1.35
1107 STR19 Combination Max 16648 1585 4091 1.35
1107 STR19 Combination Min 12808 -332 -8019 1.35
1107 STR20 Combination Max 16651 1884 2420 1.35
1107 STR20 Combination Min 12811 -33 -9691 1.35
1107 STR21 Combination Max 21733 2383 157 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 93
Relazione illustrativa e di calcolo Progetto Definitivo

1107 STR21 Combination Min 17893 466 -11954 1.35


1107 STR22 Combination Max 21737 2682 -1515 1.35
1107 STR22 Combination Min 17897 765 -13626 1.35
1107 STR23 Combination Max 16925 1982 2090 1.35
1107 STR23 Combination Min 13085 64 -10020 1.35
1107 STR24 Combination Max 16928 2281 419 1.35
1107 STR24 Combination Min 13088 363 -11692 1.35
1107 STR25 Combination Max 21579 2105 1576 1.35
1107 STR25 Combination Min 17739 187 -10535 1.35
1107 STR26 Combination Max 21583 2404 -96 1.35
1107 STR26 Combination Min 17743 486 -12206 1.35
1107 STR27 Combination Max 21745 2343 375 1.35
1107 STR27 Combination Min 17905 425 -11735 1.35
1107 STR28 Combination Max 21749 2642 -1297 1.35
1107 STR28 Combination Min 17909 724 -13407 1.35
1107 STR29 Combination Max 16771 1703 3509 1.35
1107 STR29 Combination Min 12931 -214 -8601 1.00
1107 STR30 Combination Max 16774 2002 1838 1.00
1107 STR30 Combination Min 12934 85 -10273 1.00
1107 STR31 Combination Max 16937 1941 2309 1.00
1107 STR31 Combination Min 13097 24 -9802 1.00
1107 STR32 Combination Max 16941 2240 637 1.00
1107 STR32 Combination Min 13100 323 -11473 1.00
1107 QKE1 Combination Max 14983 3434 4927 1.00
1107 QKE1 Combination Min 12118 -2084 -11067 1.00
1107 QKE2 Combination Max 15099 3599 4093 1.00
1107 QKE2 Combination Min 12233 -1918 -11901 1.00
1107 QKE3 Combination Max 14356 5807 9725 1.00
1107 QKE3 Combination Min 12745 -4457 -15865 1.00
1107 QKE4 Combination Max 14472 5973 8891 1.00
1107 QKE4 Combination Min 12860 -4292 -16698 1.00
1147 STR1 Combination Max 22900 399 12755 1.35
1147 STR1 Combination Min 17721 -1552 -5397 1.35
1147 STR2 Combination Max 18088 637 11561 1.35
1147 STR2 Combination Min 12908 -1314 -6591 1.35
1147 STR3 Combination Max 22897 708 10969 1.35
1147 STR3 Combination Min 17718 -1243 -7183 1.35
1147 STR4 Combination Max 18085 947 9775 1.35
1147 STR4 Combination Min 12906 -1005 -8376 1.35
1147 STR5 Combination Max 23070 274 13380 1.35
1147 STR5 Combination Min 17891 -1677 -4772 1.35
1147 STR6 Combination Max 18258 512 12187 1.35
1147 STR6 Combination Min 13078 -1439 -5965 1.35
1147 STR7 Combination Max 23068 584 11594 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 94
Relazione illustrativa e di calcolo Progetto Definitivo

1147 STR7 Combination Min 17888 -1367 -6558 1.35


1147 STR8 Combination Max 18255 822 10401 1.35
1147 STR8 Combination Min 13076 -1129 -7751 1.35
1147 STR9 Combination Max 21678 59 10766 1.35
1147 STR9 Combination Min 17841 -1386 -2680 1.35
1147 STR10 Combination Max 21673 575 7790 1.35
1147 STR10 Combination Min 17837 -871 -5656 1.35
1147 STR11 Combination Max 16865 297 9573 1.35
1147 STR11 Combination Min 13029 -1148 -3873 1.35
1147 STR12 Combination Max 16861 813 6597 1.35
1147 STR12 Combination Min 13024 -632 -6849 1.35
1147 STR13 Combination Max 21848 -66 11392 1.35
1147 STR13 Combination Min 18011 -1511 -2054 1.35
1147 STR14 Combination Max 21843 450 8415 1.35
1147 STR14 Combination Min 18007 -995 -5031 1.35
1147 STR15 Combination Max 17035 172 10198 1.35
1147 STR15 Combination Min 13199 -1273 -3248 1.35
1147 STR16 Combination Max 17031 688 7222 1.35
1147 STR16 Combination Min 13194 -757 -6224 1.35
1147 STR17 Combination Max 21620 203 9963 1.35
1147 STR17 Combination Min 17784 -1242 -3483 1.35
1147 STR18 Combination Max 21617 513 8177 1.35
1147 STR18 Combination Min 17781 -932 -5269 1.35
1147 STR19 Combination Max 16808 442 8769 1.35
1147 STR19 Combination Min 12971 -1004 -4677 1.35
1147 STR20 Combination Max 16805 751 6983 1.35
1147 STR20 Combination Min 12968 -694 -6462 1.35
1147 STR21 Combination Max 21904 -4 11005 1.35
1147 STR21 Combination Min 18067 -1449 -2441 1.35
1147 STR22 Combination Max 21901 305 9219 1.35
1147 STR22 Combination Min 18064 -1140 -4227 1.35
1147 STR23 Combination Max 17091 234 9811 1.35
1147 STR23 Combination Min 13255 -1211 -3634 1.35
1147 STR24 Combination Max 17089 544 8026 1.35
1147 STR24 Combination Min 13252 -902 -5420 1.35
1147 STR25 Combination Max 21662 153 10214 1.35
1147 STR25 Combination Min 17825 -1292 -3232 1.35
1147 STR26 Combination Max 21659 463 8428 1.35
1147 STR26 Combination Min 17823 -982 -5018 1.35
1147 STR27 Combination Max 21832 29 10839 1.35
1147 STR27 Combination Min 17995 -1417 -2607 1.35
1147 STR28 Combination Max 21829 338 9053 1.35
1147 STR28 Combination Min 17993 -1107 -4393 1.35
1147 STR29 Combination Max 16849 391 9021 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 95
Relazione illustrativa e di calcolo Progetto Definitivo

1147 STR29 Combination Min 13013 -1054 -4425 1.00


1147 STR30 Combination Max 16847 701 7235 1.00
1147 STR30 Combination Min 13010 -744 -6211 1.00
1147 STR31 Combination Max 17019 267 9646 1.00
1147 STR31 Combination Min 13183 -1178 -3800 1.00
1147 STR32 Combination Max 17017 576 7860 1.00
1147 STR32 Combination Min 13180 -869 -5586 1.00
1147 QKE1 Combination Max 14828 2482 8819 1.00
1147 QKE1 Combination Min 12591 -2782 -6958 1.00
1147 QKE2 Combination Max 14946 2395 9253 1.00
1147 QKE2 Combination Min 12709 -2868 -6524 1.00
1147 QKE3 Combination Max 14488 4972 14881 1.00
1147 QKE3 Combination Min 12931 -5272 -13021 1.00
1147 QKE4 Combination Max 14607 4885 15316 1.00
1147 QKE4 Combination Min 13049 -5358 -12586 1.00

Azioni verticali sul singolo palo:


Azioni verticali sul singolo palo

Azione verticale Azione verticale Azione verticale


Load combination P1 P2 P3 P4
dovuta a N dovuta a M2 dovuta a M3

N1 N2 N3 tot++ tot-+ tot+- tot--

kN kN kN kN kN kN kN

STR1 3652 180 156 3988 3628 3676 3316


STR1 3004 -7 -525 2472 2485 3523 3536
STR2 3051 151 236 3438 3136 2965 2664
STR2 2403 -36 -445 1922 1994 2812 2883
STR3 3652 201 86 3940 3537 3768 3365
STR3 3004 15 -595 2424 2394 3614 3584
STR4 3051 172 167 3390 3046 3057 2712
STR4 2403 -14 -514 1875 1903 2904 2932
STR5 3673 197 106 3975 3581 3764 3370
STR5 3025 10 -575 2460 2439 3611 3590
STR6 3072 168 186 3426 3090 3053 2717
STR6 2424 -18 -495 1910 1947 2900 2937
STR7 3673 219 36 3928 3491 3855 3418
STR7 3025 32 -645 2412 2348 3702 3638
STR8 3072 190 117 3378 2999 3145 2766
STR8 2424 3 -564 1863 1856 2992 2985
STR9 3499 142 96 3737 3454 3544 3261
STR9 3019 4 -408 2614 2607 3430 3423
STR10 3500 178 -20 3657 3302 3697 3342

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 96
Relazione illustrativa e di calcolo Progetto Definitivo

STR10 3020 39 -524 2535 2456 3583 3504


STR11 2898 113 177 3188 2962 2833 2608
STR11 2418 -25 -328 2065 2116 2720 2771
STR12 2898 149 61 3108 2811 2986 2689
STR12 2418 10 -444 1985 1964 2873 2852
STR13 3520 159 46 3725 3407 3632 3314
STR13 3040 21 -458 2602 2561 3518 3477
STR14 3520 195 -70 3645 3256 3785 3395
STR14 3040 57 -574 2523 2409 3671 3558
STR15 2919 130 127 3175 2916 2921 2662
STR15 2439 -8 -378 2053 2069 2808 2824
STR16 2919 166 11 3096 2764 3074 2743
STR16 2439 28 -494 1973 1918 2961 2905
STR17 3492 143 90 3725 3439 3545 3259
STR17 3012 5 -415 2602 2592 3432 3422
STR18 3492 165 20 3677 3348 3637 3308
STR18 3012 27 -484 2555 2502 3523 3470
STR19 2891 114 170 3176 2947 2835 2606
STR19 2411 -24 -334 2053 2101 2721 2769
STR20 2891 136 101 3128 2856 2926 2655
STR20 2411 -2 -404 2005 2010 2813 2818
STR21 3527 172 7 3705 3361 3692 3348
STR21 3047 34 -498 2582 2515 3578 3511
STR22 3527 193 -63 3657 3271 3783 3397
STR22 3047 55 -568 2534 2424 3670 3560
STR23 2926 143 87 3155 2870 2981 2696
STR23 2446 5 -418 2033 2023 2868 2858
STR24 2926 164 17 3108 2779 3073 2744
STR24 2446 26 -487 1985 1933 2959 2907
STR25 3507 152 66 3725 3421 3593 3290
STR25 3027 13 -439 2602 2575 3480 3453
STR26 3508 173 -4 3677 3331 3685 3339
STR26 3028 35 -509 2554 2484 3571 3501
STR27 3528 169 16 3713 3375 3681 3344
STR27 3048 31 -489 2590 2529 3568 3506
STR28 3529 190 -54 3665 3284 3773 3392
STR28 3049 52 -559 2542 2438 3659 3555
STR29 2906 123 146 3175 2930 2883 2637
STR29 2216 -15 -358 1843 1873 2559 2590
STR30 2697 144 77 2918 2629 2764 2476
STR30 2217 6 -428 1795 1783 2651 2639
STR31 2717 140 96 2953 2673 2761 2481
STR31 2237 2 -408 1830 1827 2647 2644

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 97
Relazione illustrativa e di calcolo Progetto Definitivo

STR32 2718 161 27 2905 2583 2852 2530


STR32 2238 23 -478 1783 1736 2739 2692
QKE1 2473 247 205 2926 2431 2515 2020
QKE1 2115 -150 -461 1503 1804 2426 2726
QKE2 2487 259 171 2917 2399 2576 2057
QKE2 2129 -138 -496 1495 1771 2487 2763
QKE3 2395 418 405 3218 2381 2408 1571
QKE3 2193 -321 -661 1211 1853 2533 3175
QKE4 2409 430 370 3210 2349 2469 1608
QKE4 2208 -309 -696 1203 1821 2594 3212
STR1 3672 29 531 4233 4175 3170 3112
STR1 3025 -112 -225 2688 2912 3138 3362
STR2 3071 46 482 3599 3507 2635 2543
STR2 2424 -95 -275 2054 2244 2603 2793
STR3 3672 51 457 4180 4078 3266 3164
STR3 3025 -90 -299 2636 2815 3235 3414
STR4 3071 68 407 3546 3410 2731 2595
STR4 2423 -72 -349 2002 2147 2700 2845
STR5 3694 20 557 4271 4231 3156 3117
STR5 3046 -121 -199 2727 2968 3124 3366
STR6 3092 37 508 3637 3563 2621 2548
STR6 2445 -104 -249 2093 2300 2590 2797
STR7 3693 42 483 4219 4134 3252 3168
STR7 3046 -99 -273 2674 2871 3221 3418
STR8 3092 59 433 3584 3466 2718 2599
STR8 2444 -81 -323 2040 2203 2686 2849
STR9 3520 4 449 3973 3964 3075 3067
STR9 3040 -100 -112 2829 3028 3052 3252
STR10 3519 41 325 3885 3802 3236 3153
STR10 3040 -63 -236 2741 2867 3213 3338
STR11 2918 21 399 3338 3296 2541 2498
STR11 2439 -83 -161 2194 2360 2517 2683
STR12 2918 59 275 3251 3134 2701 2584
STR12 2438 -46 -285 2107 2198 2678 2769
STR13 3541 -5 475 4011 4020 3062 3071
STR13 3061 -109 -86 2867 3085 3038 3256
STR14 3540 32 351 3923 3859 3222 3157
STR14 3061 -72 -210 2780 2923 3199 3342
STR15 2939 12 425 3377 3352 2527 2502
STR15 2460 -92 -135 2233 2416 2503 2687
STR16 2939 50 301 3289 3190 2688 2588
STR16 2459 -55 -259 2145 2254 2664 2773
STR17 3513 15 415 3942 3913 3112 3083

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 98
Relazione illustrativa e di calcolo Progetto Definitivo

STR17 3033 -89 -145 2798 2977 3089 3268


STR18 3512 37 341 3890 3816 3208 3135
STR18 3033 -67 -220 2746 2880 3185 3319
STR19 2911 32 365 3308 3245 2577 2514
STR19 2431 -72 -195 2164 2309 2554 2699
STR20 2911 54 291 3256 3147 2674 2566
STR20 2431 -50 -269 2112 2212 2650 2750
STR21 3548 0 459 4006 4007 3089 3090
STR21 3068 -104 -102 2862 3071 3066 3275
STR22 3548 22 384 3954 3910 3185 3141
STR22 3068 -82 -176 2810 2974 3162 3326
STR23 2946 17 409 3372 3338 2554 2521
STR23 2467 -87 -151 2228 2403 2531 2706
STR24 2946 39 334 3320 3241 2651 2572
STR24 2466 -65 -226 2176 2306 2627 2757
STR25 3518 11 426 3954 3932 3103 3081
STR25 3038 -93 -135 2810 2997 3080 3266
STR26 3517 33 351 3902 3835 3200 3133
STR26 3038 -71 -209 2758 2900 3176 3318
STR27 3539 2 452 3993 3989 3089 3085
STR27 3059 -102 -109 2849 3053 3066 3270
STR28 3539 24 377 3940 3891 3186 3137
STR28 3059 -80 -183 2796 2956 3162 3322
STR29 2916 28 376 3320 3264 2568 2512
STR29 2227 -76 -184 1966 2118 2335 2487
STR30 2706 51 301 3058 2957 2455 2354
STR30 2226 -54 -259 1914 2021 2431 2539
STR31 2727 19 402 3149 3110 2345 2306
STR31 2248 -85 -158 2005 2174 2321 2491
STR32 2727 42 328 3096 3013 2441 2358
STR32 2248 -63 -233 1952 2077 2418 2543
QKE1 2454 179 367 3000 2642 2265 1907
QKE1 2174 -200 -290 1683 2084 2263 2664
QKE2 2468 173 386 3026 2681 2255 1910
QKE2 2189 -207 -272 1710 2123 2254 2667
QKE3 2411 358 620 3389 2673 2149 1433
QKE3 2216 -380 -543 1294 2054 2379 3139
QKE4 2426 352 638 3416 2712 2140 1436
QKE4 2231 -386 -524 1321 2093 2369 3142

La massima azione verticale di compressione registrata sul palo di 4271kN.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 99
Relazione illustrativa e di calcolo Progetto Definitivo

10.2.2 Momento agente sul palo


Va inoltre considerato il momento che si produce lungo al palo dovuto ad azioni agenti
ortogonali allasse del palo.
Nel caso di un palo flessibile, cio avente una lunghezza superiore alla lunghezza critica definita
2
E palo 7
come: l c = D il massimo momento prodotto dalla forza orizzontale H pari a
Gc (1 + 0.75 )
Hl l
M max = 0.1 c . Tale momento si produce in una sezione posta a c dalla testa del palo nel caso
4
di terreno omogeneo. Per quanto invece concerne la distribuzione dei momenti prodotti da una
coppia applicata in testa, si pu assumere una variazione lineare che si smorza in corrispondenza
di una sezione posta a una distanza pari alla lunghezza critica.
Se il palo ha lestremit impedita di ruotare, imponendo la condizione di rotazione nulla si pu
ottenere il massimo momento in testa:
0.375 Hl c
M inc = 0.5

2 2
E palo 7 31.5 10 3 7
lc = D = 1 . 2 = 9 .4 m
Gc (1 + 0.75 ) 20(1 + 0.75 0.2)
lc
G( z = )
Grado di eterogenit: = 4 =1
Gc
Reazioni esportate dal modello FEM alla base delle pile:
Joint OutputCase CaseType StepType F2 F3 M1 g1

Text Text Text Text KN KN KNm

1107 STR1 Combination Max 36 10 365 1.35


1107 STR1 Combination Min -978 -280 -13 1.35
1107 STR2 Combination Max 194 55 306 1.35
1107 STR2 Combination Min -821 -235 -72 1.35
1107 STR3 Combination Max -81 -23 408 1.35
1107 STR3 Combination Min -1095 -314 30 1.35
1107 STR4 Combination Max 76 22 350 1.35
1107 STR4 Combination Min -938 -269 -28 1.35
1107 STR5 Combination Max -57 -16 399 1.35
1107 STR5 Combination Min -1071 -307 21 1.35
1107 STR6 Combination Max 100 29 341 1.35
1107 STR6 Combination Min -914 -262 -37 1.35
1107 STR7 Combination Max -174 -50 443 1.35
1107 STR7 Combination Min -1189 -341 65 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 100
Relazione illustrativa e di calcolo Progetto Definitivo

1107 STR8 Combination Max -17 -5 384 1.35


1107 STR8 Combination Min -1031 -296 6 1.35
1107 STR9 Combination Max -19 -6 287 1.35
1107 STR9 Combination Min -771 -221 7 1.35
1107 STR10 Combination Max -214 -62 360 1.35
1107 STR10 Combination Min -966 -277 80 1.35
1107 STR11 Combination Max 138 40 229 1.35
1107 STR11 Combination Min -613 -176 -52 1.35
1107 STR12 Combination Max -57 -16 301 1.35
1107 STR12 Combination Min -808 -232 21 1.35
1107 STR13 Combination Max -112 -32 322 1.35
1107 STR13 Combination Min -864 -248 42 1.35
1107 STR14 Combination Max -308 -88 395 1.35
1107 STR14 Combination Min -1059 -304 115 1.35
1107 STR15 Combination Max 45 13 263 1.35
1107 STR15 Combination Min -706 -203 -17 1.35
1107 STR16 Combination Max -150 -43 336 1.35
1107 STR16 Combination Min -902 -259 56 1.35
1107 STR17 Combination Max -27 -8 290 1.35
1107 STR17 Combination Min -778 -223 10 1.35
1107 STR18 Combination Max -144 -41 334 1.35
1107 STR18 Combination Min -896 -257 54 1.35
1107 STR19 Combination Max 130 37 232 1.35
1107 STR19 Combination Min -621 -178 -49 1.35
1107 STR20 Combination Max 13 4 275 1.35
1107 STR20 Combination Min -738 -212 -5 1.35
1107 STR21 Combination Max -183 -52 348 1.35
1107 STR21 Combination Min -934 -268 68 1.35
1107 STR22 Combination Max -300 -86 392 1.35
1107 STR22 Combination Min -1051 -301 112 1.35
1107 STR23 Combination Max -25 -7 290 1.35
1107 STR23 Combination Min -776 -223 9 1.35
1107 STR24 Combination Max -142 -41 333 1.35
1107 STR24 Combination Min -894 -256 53 1.35
1107 STR25 Combination Max -73 -21 308 1.35
1107 STR25 Combination Min -825 -236 27 1.35
1107 STR26 Combination Max -191 -55 351 1.35
1107 STR26 Combination Min -942 -270 71 1.35
1107 STR27 Combination Max -167 -48 342 1.35
1107 STR27 Combination Min -918 -263 62 1.35
1107 STR28 Combination Max -284 -81 386 1.35
1107 STR28 Combination Min -1035 -297 106 1.35
1107 STR29 Combination Max 84 24 249 1.35
1107 STR29 Combination Min -667 -191 -31 1.00

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 101
Relazione illustrativa e di calcolo Progetto Definitivo

1107 STR30 Combination Max -33 -10 293 1.00


1107 STR30 Combination Min -785 -225 12 1.00
1107 STR31 Combination Max -9 -3 284 1.00
1107 STR31 Combination Min -761 -218 3 1.00
1107 STR32 Combination Max -126 -36 327 1.00
1107 STR32 Combination Min -878 -252 47 1.00
1107 QKE1 Combination Max 454 282 383 1.00
1107 QKE1 Combination Min -983 -434 -186 1.00
1107 QKE2 Combination Max 389 264 408 1.00
1107 QKE2 Combination Min -1048 -453 -162 1.00
1107 QKE3 Combination Max 909 579 557 1.00
1107 QKE3 Combination Min -1438 -731 -359 1.00
1107 QKE4 Combination Max 845 561 581 1.00
1107 QKE4 Combination Min -1503 -750 -335 1.00
1147 STR1 Combination Max 608 174 58 1.35
1147 STR1 Combination Min -156 -45 -227 1.35
1147 STR2 Combination Max 515 148 93 1.35
1147 STR2 Combination Min -250 -72 -192 1.35
1147 STR3 Combination Max 487 140 104 1.35
1147 STR3 Combination Min -278 -80 -182 1.35
1147 STR4 Combination Max 394 113 138 1.35
1147 STR4 Combination Min -371 -106 -147 1.35
1147 STR5 Combination Max 657 188 40 1.35
1147 STR5 Combination Min -107 -31 -245 1.35
1147 STR6 Combination Max 564 162 75 1.35
1147 STR6 Combination Min -201 -58 -210 1.35
1147 STR7 Combination Max 536 154 85 1.35
1147 STR7 Combination Min -229 -66 -200 1.35
1147 STR8 Combination Max 442 127 120 1.35
1147 STR8 Combination Min -322 -92 -165 1.35
1147 STR9 Combination Max 543 156 9 1.35
1147 STR9 Combination Min -23 -7 -203 1.35
1147 STR10 Combination Max 341 98 84 1.35
1147 STR10 Combination Min -225 -65 -127 1.35
1147 STR11 Combination Max 450 129 43 1.35
1147 STR11 Combination Min -116 -33 -168 1.35
1147 STR12 Combination Max 248 71 119 1.35
1147 STR12 Combination Min -319 -91 -92 1.35
1147 STR13 Combination Max 592 170 -10 1.35
1147 STR13 Combination Min 26 7 -221 1.35
1147 STR14 Combination Max 390 112 66 1.35
1147 STR14 Combination Min -176 -51 -145 1.35
1147 STR15 Combination Max 499 143 25 1.35
1147 STR15 Combination Min -68 -19 -186 1.35

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 102
Relazione illustrativa e di calcolo Progetto Definitivo

1147 STR16 Combination Max 297 85 101 1.35


1147 STR16 Combination Min -270 -77 -111 1.35
1147 STR17 Combination Max 487 140 30 1.35
1147 STR17 Combination Min -80 -23 -181 1.35
1147 STR18 Combination Max 365 105 75 1.35
1147 STR18 Combination Min -201 -58 -136 1.35
1147 STR19 Combination Max 393 113 65 1.35
1147 STR19 Combination Min -173 -50 -147 1.35
1147 STR20 Combination Max 272 78 110 1.35
1147 STR20 Combination Min -294 -84 -101 1.35
1147 STR21 Combination Max 568 163 -1 1.35
1147 STR21 Combination Min 2 0 -212 1.35
1147 STR22 Combination Max 447 128 45 1.35
1147 STR22 Combination Min -120 -34 -167 1.35
1147 STR23 Combination Max 475 136 34 1.35
1147 STR23 Combination Min -92 -26 -177 1.35
1147 STR24 Combination Max 353 101 79 1.35
1147 STR24 Combination Min -213 -61 -132 1.35
1147 STR25 Combination Max 506 145 22 1.35
1147 STR25 Combination Min -60 -17 -189 1.35
1147 STR26 Combination Max 385 110 68 1.35
1147 STR26 Combination Min -181 -52 -144 1.35
1147 STR27 Combination Max 555 159 4 1.35
1147 STR27 Combination Min -11 -3 -207 1.35
1147 STR28 Combination Max 434 124 49 1.35
1147 STR28 Combination Min -133 -38 -162 1.35
1147 STR29 Combination Max 413 118 57 1.35
1147 STR29 Combination Min -153 -44 -154 1.00
1147 STR30 Combination Max 292 84 102 1.00
1147 STR30 Combination Min -275 -79 -109 1.00
1147 STR31 Combination Max 462 132 39 1.00
1147 STR31 Combination Min -105 -30 -172 1.00
1147 STR32 Combination Max 340 98 84 1.00
1147 STR32 Combination Min -226 -65 -127 1.00
1147 QKE1 Combination Max 700 359 230 1.00
1147 QKE1 Combination Min -582 -325 -274 1.00
1147 QKE2 Combination Max 734 368 218 1.00
1147 QKE2 Combination Min -548 -315 -287 1.00
1147 QKE3 Combination Max 1185 673 417 1.00
1147 QKE3 Combination Min -1068 -639 -461 1.00
1147 QKE4 Combination Max 1219 683 404 1.00
1147 QKE4 Combination Min -1034 -630 -473 1.00

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 103
Relazione illustrativa e di calcolo Progetto Definitivo

Azioni orizzontali sul singolo palo:


Azione tagliante sul singolo palo

Azione di Forza trasv Azione di Azione di


Azione di taglio Load
taglio palo dovuta taglio in taglio in
dovuta a F3 combination
dovuta a F2 a M1 direz 2 tot direz 3 tot

T2 T3 FM1 T2tot T3tot

kN kN kN kN kN

5 1 14 9 15 STR1
-122 -35 -1 -122 -36 STR1
24 7 12 28 18 STR2
-103 -29 -3 -104 -32 STR2
-10 -3 16 -5 12 STR3
-137 -39 1 -137 -38 STR3
10 3 14 14 16 STR4
-117 -34 -1 -118 -35 STR4
-7 -2 16 -2 13 STR5
-134 -38 1 -134 -38 STR5
13 4 13 17 16 STR6
-114 -33 -1 -115 -34 STR6
-22 -6 17 -16 10 STR7
-149 -43 3 -148 -40 STR7
-2 -1 15 3 14 STR8
-129 -37 0 -129 -37 STR8
-2 -1 11 1 10 STR9
-96 -28 0 -96 -27 STR9
-27 -8 14 -22 6 STR10
-121 -35 3 -120 -32 STR10
17 5 9 20 13 STR11
-77 -22 -2 -77 -24 STR11
-7 -2 12 -3 9 STR12
-101 -29 1 -101 -28 STR12
-14 -4 13 -10 8 STR13
-108 -31 2 -107 -29 STR13
-38 -11 15 -33 4 STR14
-132 -38 4 -131 -34 STR14
6 2 10 9 11 STR15
-88 -25 -1 -89 -26 STR15
-19 -5 13 -15 7 STR16
-113 -32 2 -112 -30 STR16
-3 -1 11 0 10 STR17
-97 -28 0 -97 -28 STR17

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 104
Relazione illustrativa e di calcolo Progetto Definitivo

-18 -5 13 -14 7 STR18


-112 -32 2 -111 -30 STR18
16 5 9 19 13 STR19
-78 -22 -2 -78 -24 STR19
2 0 11 5 11 STR20
-92 -26 0 -92 -27 STR20
-23 -7 14 -18 6 STR21
-117 -33 3 -116 -31 STR21
-37 -11 15 -32 4 STR22
-131 -38 4 -130 -34 STR22
-3 -1 11 1 10 STR23
-97 -28 0 -97 -27 STR23
-18 -5 13 -14 7 STR24
-112 -32 2 -111 -30 STR24
-9 -3 12 -5 9 STR25
-103 -30 1 -103 -29 STR25
-24 -7 14 -19 6 STR26
-118 -34 3 -117 -31 STR26
-21 -6 13 -16 7 STR27
-115 -33 2 -114 -31 STR27
-35 -10 15 -31 4 STR28
-129 -37 4 -128 -33 STR28
10 3 10 14 12 STR29
-83 -24 -1 -84 -25 STR29
-4 -1 11 0 10 STR30
-98 -28 0 -98 -28 STR30
-1 0 11 2 10 STR31
-95 -27 0 -95 -27 STR31
-16 -5 13 -12 8 STR32
-110 -31 2 -109 -30 STR32
57 35 15 62 49 QKE1
-123 -54 -7 -125 -61 QKE1
49 33 16 54 48 QKE2
-131 -57 -6 -133 -63 QKE2
114 72 22 121 93 QKE3
-180 -91 -14 -184 -105 QKE3
106 70 23 113 92 QKE4
-188 -94 -13 -192 -106 QKE4
76 22 2 77 24 STR1
-20 -6 -9 -22 -14 STR1
64 18 4 66 22 STR2
-31 -9 -7 -34 -16 STR2
61 17 4 62 21 STR3

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 105
Relazione illustrativa e di calcolo Progetto Definitivo

-35 -10 -7 -37 -17 STR3


49 14 5 51 19 STR4
-46 -13 -6 -48 -19 STR4
82 24 2 83 25 STR5
-13 -4 -10 -17 -13 STR5
70 20 3 71 23 STR6
-25 -7 -8 -28 -15 STR6
67 19 3 68 22 STR7
-29 -8 -8 -31 -16 STR7
55 16 5 57 20 STR8
-40 -12 -6 -42 -18 STR8
68 19 0 68 20 STR9
-3 -1 -8 -5 -8 STR9
43 12 3 44 15 STR10
-28 -8 -5 -30 -13 STR10
56 16 2 57 18 STR11
-15 -4 -7 -17 -10 STR11
31 9 5 32 13 STR12
-40 -11 -4 -41 -15 STR12
74 21 0 74 21 STR13
3 1 -9 0 -7 STR13
49 14 3 50 16 STR14
-22 -6 -6 -24 -12 STR14
62 18 1 63 19 STR15
-8 -2 -7 -11 -9 STR15
37 11 4 38 14 STR16
-34 -10 -4 -35 -14 STR16
61 17 1 61 19 STR17
-10 -3 -7 -12 -10 STR17
46 13 3 47 16 STR18
-25 -7 -5 -27 -12 STR18
49 14 3 50 16 STR19
-22 -6 -6 -23 -12 STR19
34 10 4 35 14 STR20
-37 -11 -4 -38 -14 STR20
71 20 0 71 20 STR21
0 0 -8 -2 -8 STR21
56 16 2 56 18 STR22
-15 -4 -6 -17 -10 STR22
59 17 1 60 18 STR23
-11 -3 -7 -14 -10 STR23
44 13 3 45 16 STR24
-27 -8 -5 -28 -12 STR24

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 106
Relazione illustrativa e di calcolo Progetto Definitivo

63 18 1 64 19 STR25
-8 -2 -7 -10 -9 STR25
48 14 3 49 16 STR26
-23 -7 -6 -24 -12 STR26
69 20 0 69 20 STR27
-1 0 -8 -4 -8 STR27
54 16 2 55 17 STR28
-17 -5 -6 -19 -11 STR28
52 15 2 52 17 STR29
-19 -5 -6 -21 -11 STR29
36 10 4 38 14 STR30
-34 -10 -4 -36 -14 STR30
58 17 2 58 18 STR31
-13 -4 -7 -15 -10 STR31
43 12 3 44 15 STR32
-28 -8 -5 -30 -13 STR32
87 45 9 90 53 QKE1
-73 -41 -11 -76 -51 QKE1
92 46 8 94 54 QKE2
-69 -39 -11 -72 -50 QKE2
148 84 16 153 99 QKE3
-133 -80 -18 -139 -97 QKE3
152 85 16 158 100 QKE4
-129 -79 -18 -135 -96 QKE4

Forza orizzontale massima sul palo:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 107
Relazione illustrativa e di calcolo Progetto Definitivo

10.2.3 Verifica capacit portante palo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 108
Relazione illustrativa e di calcolo Progetto Definitivo

La massima azione verticale registrata sul palo di 4271kN.


Capacit portante a compressione del palo 1200mm L=25m: 4310.7kN
La verifica risulta soddisfatta.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 109
Relazione illustrativa e di calcolo Progetto Definitivo

10.2.4 Verifica strutturale palo D1200mm


Come specificato al punto 7.2.5 del DM2008 i pali in calcestruzzo devono essere armati per tutta
la lunghezza con unarea non inferiore allo 0.3% di quella del calcestruzzo.

DATI GENERALI DELLA SEZIONE

Calcestruzzo: Rck = 30.00 N/mmq

Sezione circolare. Raggio = 60.00 cm

Acciaio: fyk = 450.00 N/mmq

Ferro N. X (cm) Y (cm) Area (cmq)


1 60.0 115.0 2.01
2 79.9 111.3 2.01
3 97.1 100.6 2.01
4 109.2 84.5 2.01
5 114.8 65.1 2.01
6 112.9 44.9 2.01
7 103.9 26.9 2.01
8 89.0 13.2 2.01
9 70.1 5.9 2.01
10 49.9 5.9 2.01
11 31.0 13.2 2.01
12 16.1 26.9 2.01
13 7.1 44.9 2.01
14 5.2 65.1 2.01
15 10.8 84.5 2.01
16 22.9 100.6 2.01
17 40.1 111.3 2.01

Caratteristiche limite della sezione:


Nu [kN] Mxu [kN m] Myu [kN m]
Sezione completamente tesa -1337.5 0.0 0.0
Sezione completamente compressa 17313.9 0.0 0.0
Fibre inferiori tese 0.0 677.8 0.0
Fibre superiori tese 0.0 -673.9 0.0
Fibre di sinistra tese 0.0 0.0 675.0
Fibre di destra tese 0.0 0.0 -675.0

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 110
Relazione illustrativa e di calcolo Progetto Definitivo

VERIFICA AGLI STATI LIMITE ULTIMI

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Coef. sicurezza: Gamma

Soll.n. Nd Mxd Myd Nu Mxu Myu EpsC EpsA Gamma


1 0.0 279.1 177.6 0.0 568.5 361.8 -0.18 1.00 2.04 Ok
2 4271.0 279.1 177.6 4271.0 1742.9 1109.0 -0.35 0.49 6.25 Ok

11 VERIFICA SPALLE
La spinta che la terra produce su un muro di contenimento strettamente legata alla
deformabilit di questultimo. Una struttura rigida, incapace di subire deformazioni anche di
piccola entit subir una pressione pari ai carichi verticali moltiplicati per il coefficiente di spinta
a riposo k0. Se essa invece in grado di ruotare, traslare o deformarsi, la pressione sar legata al
coefficiente di spinta attiva ka.
Nel nostro caso per il calcolo del muro di spalla si andr a considerare la spinta a riposo.
Caratteristiche terreno:
rinterro a monte spalla con angolo di attrito assunto pari a 34:
K0 = 1-sin34=0.44; = 19 kN/m3
1 1
risultante spinta del terreno PA= k 0H 2 = 0.44 19 4.85 2 = 98.32kN / m
2 2
sovraccarico variabile a tergo del muro
Secondo quanto esposto al punto C5.1.3.3.7.1 della circolare 2 febbraio 2009 n.617
al fine del calcolo delle spalle, sul rilevato a tergo del muro si pu considerare
applicato lo schema di carico 1, in cui per semplicit, i carichi tandem possono essere
sostituiti da carichi uniformemente distribuiti equivalenti, applicati su una superficie
rettangolare larga 3m e lunga 2.2m.
In un rilevato correttamente consolidato, si pu assumere una diffusione del carico
con angolo di 30.
Sulla base di ci, considerando tale diffusione a 30 le dimensioni della superficie di
carico che si registrano a met altezza del paraghiaia (cio a 4.85/2=2.425m) di:
(3+1.4x2)=5.8m
(2.2+1.4)=3.6m
Risulta quindi che il sovraccarico variabile da considerare di
600/(5.8x3.6)=28.7kN/m2.
Da cui risulta che la spinta orizzontale dovuta a tale sovraccarico variabile pari a:
PQ= k 0 qH = 0.44 28.7 4.85 = 61.24kN / m

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 111
Relazione illustrativa e di calcolo Progetto Definitivo

11.1 Verifica fondazione spalla S01


Per le verifiche delle fondazioni della spalla fissa si utilizzato lapproccio 2, secondo cui si adotta una
sola combinazione di gruppi di coefficienti parziali: A1+M1+R3.

11.1.1 Azione verticale sul palo


Si analizza nel seguito il carico verticale massimo agente sui pali di fondazione della pila.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 112
Relazione illustrativa e di calcolo Progetto Definitivo

Reazioni esportate dal modello FEM alla base dellimpalcato:


Joint OutputCase CaseType StepType F1 F2 F3 M1 M2 M3

Text Text Text Text KN KN KN KN-m KN-m KN-m

102 STR1 Combination Max 0 -325 6337 642 -207 -2608


102 STR1 Combination Min 0 -325 6337 642 -207 -2608
102 STR2 Combination Max 0 -243 4788 515 -165 -2111
102 STR2 Combination Min 0 -243 4788 515 -165 -2111
102 STR3 Combination Max 0 -181 6327 153 -57 -1699
102 STR3 Combination Min 0 -181 6327 153 -57 -1699
102 STR4 Combination Max 0 -98 4779 26 -15 -1202
102 STR4 Combination Min 0 -98 4779 26 -15 -1202
102 STR5 Combination Max 0 -366 6410 650 -213 -3365
102 STR5 Combination Min 0 -366 6410 650 -213 -3365
102 STR6 Combination Max 0 -283 4862 523 -170 -2869
102 STR6 Combination Min 0 -283 4862 523 -170 -2869
102 STR7 Combination Max 0 -221 6401 161 -62 -2457
102 STR7 Combination Min 0 -221 6401 161 -62 -2457
102 STR8 Combination Max 0 -138 4852 34 -20 -1960
102 STR8 Combination Min 0 -138 4852 34 -20 -1960
102 STR9 Combination Max 0 -373 6340 805 -258 -2911
102 STR9 Combination Min 0 -373 6340 805 -258 -2911
102 STR10 Combination Max 0 -132 6324 -10 -7 -1396
102 STR10 Combination Min 0 -132 6324 -10 -7 -1396
102 STR11 Combination Max 0 -291 4791 679 -215 -2414
102 STR11 Combination Min 0 -291 4791 679 -215 -2414
102 STR12 Combination Max 0 -50 4776 -137 36 -899
102 STR12 Combination Min 0 -50 4776 -137 36 -899
102 STR13 Combination Max 0 -414 6413 813 -263 -3668
102 STR13 Combination Min 0 -414 6413 813 -263 -3668
102 STR14 Combination Max 0 -173 6398 -2 -12 -2154
102 STR14 Combination Min 0 -173 6398 -2 -12 -2154
102 STR15 Combination Max 0 -331 4865 686 -221 -3171

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 113
Relazione illustrativa e di calcolo Progetto Definitivo

102 STR15 Combination Min 0 -331 4865 686 -221 -3171


102 STR16 Combination Max 0 -90 4849 -129 31 -1657
102 STR16 Combination Min 0 -90 4849 -129 31 -1657
102 STR17 Combination Max 0 -312 6312 640 -206 -2355
102 STR17 Combination Min 0 -312 6312 640 -206 -2355
102 STR18 Combination Max 0 -167 6303 150 -55 -1447
102 STR18 Combination Min 0 -167 6303 150 -55 -1447
102 STR19 Combination Max 0 -229 4763 513 -163 -1858
102 STR19 Combination Min 0 -229 4763 513 -163 -1858
102 STR20 Combination Max 0 -85 4754 24 -13 -950
102 STR20 Combination Min 0 -85 4754 24 -13 -950
102 STR21 Combination Max 0 -379 6435 653 -214 -3618
102 STR21 Combination Min 0 -379 6435 653 -214 -3618
102 STR22 Combination Max 0 -234 6425 164 -64 -2709
102 STR22 Combination Min 0 -234 6425 164 -64 -2709
102 STR23 Combination Max 0 -296 4886 526 -172 -3121
102 STR23 Combination Min 0 -296 4886 526 -172 -3121
102 STR24 Combination Max 0 -152 4877 37 -21 -2212
102 STR24 Combination Min 0 -152 4877 37 -21 -2212
102 STR25 Combination Max -781 -335 6278 668 -20 -2635
102 STR25 Combination Min -781 -335 6278 668 -20 -2635
102 STR26 Combination Max -781 -190 6269 179 130 -1726
102 STR26 Combination Min -781 -190 6269 179 130 -1726
102 STR27 Combination Max -781 -375 6351 676 -26 -3393
102 STR27 Combination Min -781 -375 6351 676 -26 -3393
102 STR28 Combination Max -781 -231 6342 187 125 -2484
102 STR28 Combination Min -781 -231 6342 187 125 -2484
102 STR29 Combination Max -781 -252 4729 541 22 -2138
102 STR29 Combination Min -781 -252 4729 541 22 -2138
102 STR30 Combination Max -781 -108 4720 52 173 -1229
102 STR30 Combination Min -781 -108 4720 52 173 -1229
102 STR31 Combination Max -781 -293 4803 549 17 -2896
102 STR31 Combination Min -781 -293 4803 549 17 -2896
102 STR32 Combination Max -781 -148 4793 60 167 -1987
102 STR32 Combination Min -781 -148 4793 60 167 -1987
102 QKE1 Combination Max 3579 281 5436 1437 1043 626
102 QKE1 Combination Min -3579 -634 4153 -893 -1225 -4171
102 QKE2 Combination Max 3579 253 5487 1443 1040 100
102 QKE2 Combination Min -3579 -662 4204 -887 -1228 -4697
102 QKE3 Combination Max 1260 719 5048 2628 849 3725
102 QKE3 Combination Min -1260 -1072 4541 -2084 -1030 -7270
102 QKE4 Combination Max 1260 691 5099 2633 845 3199
102 QKE4 Combination Min -1260 -1100 4592 -2078 -1034 -7796

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 114
Relazione illustrativa e di calcolo Progetto Definitivo

Le precedenti reazioni si traducono nelle seguenti azioni sulla spalla:


OutputCase F1 F2 F3 M1 M2 M3

Text KN KN KN KN-m KN-m KN-m


STR1 0 325 -6337 -642 207 2608
STR1 0 325 -6337 -642 207 2608
STR2 0 243 -4788 -515 165 2111
STR2 0 243 -4788 -515 165 2111
STR3 0 181 -6327 -153 57 1699
STR3 0 181 -6327 -153 57 1699
STR4 0 98 -4779 -26 15 1202
STR4 0 98 -4779 -26 15 1202
STR5 0 366 -6410 -650 213 3365
STR5 0 366 -6410 -650 213 3365
STR6 0 283 -4862 -523 170 2869
STR6 0 283 -4862 -523 170 2869
STR7 0 221 -6401 -161 62 2457
STR7 0 221 -6401 -161 62 2457
STR8 0 138 -4852 -34 20 1960
STR8 0 138 -4852 -34 20 1960
STR9 0 373 -6340 -805 258 2911
STR9 0 373 -6340 -805 258 2911
STR10 0 132 -6324 10 7 1396
STR10 0 132 -6324 10 7 1396
STR11 0 291 -4791 -679 215 2414
STR11 0 291 -4791 -679 215 2414
STR12 0 50 -4776 137 -36 899
STR12 0 50 -4776 137 -36 899
STR13 0 414 -6413 -813 263 3668
STR13 0 414 -6413 -813 263 3668
STR14 0 173 -6398 2 12 2154
STR14 0 173 -6398 2 12 2154
STR15 0 331 -4865 -686 221 3171
STR15 0 331 -4865 -686 221 3171
STR16 0 90 -4849 129 -31 1657
STR16 0 90 -4849 129 -31 1657
STR17 0 312 -6312 -640 206 2355
STR17 0 312 -6312 -640 206 2355
STR18 0 167 -6303 -150 55 1447
STR18 0 167 -6303 -150 55 1447
STR19 0 229 -4763 -513 163 1858
STR19 0 229 -4763 -513 163 1858
STR20 0 85 -4754 -24 13 950

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 115
Relazione illustrativa e di calcolo Progetto Definitivo

STR20 0 85 -4754 -24 13 950


STR21 0 379 -6435 -653 214 3618
STR21 0 379 -6435 -653 214 3618
STR22 0 234 -6425 -164 64 2709
STR22 0 234 -6425 -164 64 2709
STR23 0 296 -4886 -526 172 3121
STR23 0 296 -4886 -526 172 3121
STR24 0 152 -4877 -37 21 2212
STR24 0 152 -4877 -37 21 2212
STR25 781 335 -6278 -668 20 2635
STR25 781 335 -6278 -668 20 2635
STR26 781 190 -6269 -179 -130 1726
STR26 781 190 -6269 -179 -130 1726
STR27 781 375 -6351 -676 26 3393
STR27 781 375 -6351 -676 26 3393
STR28 781 231 -6342 -187 -125 2484
STR28 781 231 -6342 -187 -125 2484
STR29 781 252 -4729 -541 -22 2138
STR29 781 252 -4729 -541 -22 2138
STR30 781 108 -4720 -52 -173 1229
STR30 781 108 -4720 -52 -173 1229
STR31 781 293 -4803 -549 -17 2896
STR31 781 293 -4803 -549 -17 2896
STR32 781 148 -4793 -60 -167 1987
STR32 781 148 -4793 -60 -167 1987
QKE1 -3579 -281 -5436 -1437 -1043 -626
QKE1 3579 634 -4153 893 1225 4171
QKE2 -3579 -253 -5487 -1443 -1040 -100
QKE2 3579 662 -4204 887 1228 4697
QKE3 -1260 -719 -5048 -2628 -849 -3725
QKE3 1260 1072 -4541 2084 1030 7270
QKE4 -1260 -691 -5099 -2633 -845 -3199
QKE4 1260 1100 -4592 2078 1034 7796

Le azioni totali agenti allintradosso della fondazione della spalla ricavate dalle azioni precedenti
e dalla spinta delle terre risultano:
OutputCase F1 F2 F3 M1 M2 M3

Text KN KN KN KN-m KN-m KN-m

STR1 216 325 -15008 -1553 7754 2608


STR1 216 325 -15008 -1553 7754 2608
STR2 216 243 -13460 -1195 7711 2111
STR2 216 243 -13460 -1195 7711 2111

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 116
Relazione illustrativa e di calcolo Progetto Definitivo

STR3 216 181 -14999 -659 7603 1699


STR3 216 181 -14999 -659 7603 1699
STR4 216 98 -13450 -301 7561 1202
STR4 216 98 -13450 -301 7561 1202
STR5 216 366 -15082 -1674 7759 3365
STR5 216 366 -15082 -1674 7759 3365
STR6 216 283 -13533 -1316 7716 2869
STR6 216 283 -13533 -1316 7716 2869
STR7 216 221 -15072 -780 7608 2457
STR7 216 221 -15072 -780 7608 2457
STR8 216 138 -13524 -422 7566 1960
STR8 216 138 -13524 -422 7566 1960
STR9 216 373 -15011 -1851 7804 2911
STR9 216 373 -15011 -1851 7804 2911
STR10 216 132 -14996 -361 7553 1396
STR10 216 132 -14996 -361 7553 1396
STR11 216 291 -13463 -1493 7761 2414
STR11 216 291 -13463 -1493 7761 2414
STR12 216 50 -13447 -3 7510 899
STR12 216 50 -13447 -3 7510 899
STR13 216 414 -15085 -1972 7809 3668
STR13 216 414 -15085 -1972 7809 3668
STR14 216 173 -15069 -481 7558 2154
STR14 216 173 -15069 -481 7558 2154
STR15 216 331 -13536 -1614 7767 3171
STR15 216 331 -13536 -1614 7767 3171
STR16 216 90 -13521 -124 7516 1657
STR16 216 90 -13521 -124 7516 1657
STR17 216 312 -14984 -1513 7752 2355
STR17 216 312 -14984 -1513 7752 2355
STR18 216 167 -14974 -618 7601 1447
STR18 216 167 -14974 -618 7601 1447
STR19 216 229 -13435 -1155 7710 1858
STR19 216 229 -13435 -1155 7710 1858
STR20 216 85 -13426 -260 7559 950
STR20 216 85 -13426 -260 7559 950
STR21 216 379 -15106 -1714 7760 3618
STR21 216 379 -15106 -1714 7760 3618
STR22 216 234 -15097 -820 7610 2709
STR22 216 234 -15097 -820 7610 2709
STR23 216 296 -13558 -1356 7718 3121
STR23 216 296 -13558 -1356 7718 3121
STR24 216 152 -13548 -462 7567 2212

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 117
Relazione illustrativa e di calcolo Progetto Definitivo

STR24 216 152 -13548 -462 7567 2212


STR25 997 335 -14949 -1606 9753 2635
STR25 997 335 -14949 -1606 9753 2635
STR26 997 190 -14940 -712 9602 1726
STR26 997 190 -14940 -712 9602 1726
STR27 997 375 -15023 -1727 9758 3393
STR27 997 375 -15023 -1727 9758 3393
STR28 997 231 -15014 -832 9607 2484
STR28 997 231 -15014 -832 9607 2484
STR29 997 252 -13401 -1248 9710 2138
STR29 941 252 -11153 -1248 9710 2138
STR30 941 108 -11143 -354 9560 1229
STR30 941 108 -11143 -354 9560 1229
STR31 941 293 -11226 -1369 9715 2896
STR31 941 293 -11226 -1369 9715 2896
STR32 941 148 -11217 -474 9565 1987
STR32 941 148 -11217 -474 9565 1987
QKE1 -3419 -281 -11859 -650 -3519 -626
QKE1 3739 634 -10577 -883 18793 4171
QKE2 -3419 -253 -11910 -733 -3516 -100
QKE2 3739 662 -10628 -967 18796 4697
QKE3 -1100 -719 -11471 -614 3170 -3725
QKE3 1420 1072 -10965 -918 12104 7270
QKE4 -1100 -691 -11523 -698 3173 -3199
QKE4 1420 1100 -11016 -1002 12107 7796

Azioni verticali sul singolo palo:


Azioni verticali sul singolo palo

Azione verticale Azione verticale Azione verticale


Load combination P1 P2 P3 P4
dovuta a F3 dovuta a M2 dovuta a M3

N3 FM2 FM1 tot++ tot-+ tot+- tot--

kN kN kN kN kN kN kN

STR1 -1501 517 -39 -1023 -2057 -945 -1979


STR1 -1501 517 -39 -1023 -2057 -945 -1979
STR2 -1346 514 -30 -862 -1890 -802 -1830
STR2 -1346 514 -30 -862 -1890 -802 -1830
STR3 -1500 507 -17 -1010 -2023 -976 -1990
STR3 -1500 507 -17 -1010 -2023 -976 -1990
STR4 -1345 504 -8 -849 -1857 -833 -1841
STR4 -1345 504 -8 -849 -1857 -833 -1841

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 118
Relazione illustrativa e di calcolo Progetto Definitivo

STR5 -1508 517 -42 -1033 -2068 -949 -1983


STR5 -1508 517 -42 -1033 -2068 -949 -1983
STR6 -1353 514 -33 -872 -1901 -806 -1835
STR6 -1353 514 -33 -872 -1901 -806 -1835
STR7 -1507 507 -20 -1020 -2034 -980 -1995
STR7 -1507 507 -20 -1020 -2034 -980 -1995
STR8 -1352 504 -11 -859 -1867 -837 -1846
STR8 -1352 504 -11 -859 -1867 -837 -1846
STR9 -1501 520 -47 -1028 -2068 -934 -1975
STR9 -1501 520 -47 -1028 -2068 -934 -1975
STR10 -1500 504 -9 -1005 -2012 -987 -1994
STR10 -1500 504 -9 -1005 -2012 -987 -1994
STR11 -1346 517 -38 -866 -1901 -791 -1826
STR11 -1346 517 -38 -866 -1901 -791 -1826
STR12 -1345 501 0 -844 -1845 -844 -1845
STR12 -1345 501 0 -844 -1845 -844 -1845
STR13 -1508 521 -50 -1038 -2079 -938 -1979
STR13 -1508 521 -50 -1038 -2079 -938 -1979
STR14 -1507 504 -12 -1015 -2023 -991 -1999
STR14 -1507 504 -12 -1015 -2023 -991 -1999
STR15 -1354 518 -41 -876 -1912 -795 -1831
STR15 -1354 518 -41 -876 -1912 -795 -1831
STR16 -1352 501 -3 -854 -1856 -848 -1850
STR16 -1352 501 -3 -854 -1856 -848 -1850
STR17 -1498 517 -38 -1020 -2053 -943 -1977
STR17 -1498 517 -38 -1020 -2053 -943 -1977
STR18 -1497 507 -16 -1006 -2020 -975 -1989
STR18 -1497 507 -16 -1006 -2020 -975 -1989
STR19 -1344 514 -29 -859 -1887 -800 -1828
STR19 -1344 514 -29 -859 -1887 -800 -1828
STR20 -1343 504 -7 -845 -1853 -832 -1840
STR20 -1343 504 -7 -845 -1853 -832 -1840
STR21 -1511 517 -43 -1036 -2071 -950 -1985
STR21 -1511 517 -43 -1036 -2071 -950 -1985
STR22 -1510 507 -21 -1023 -2038 -982 -1996
STR22 -1510 507 -21 -1023 -2038 -982 -1996
STR23 -1356 515 -34 -875 -1904 -807 -1836
STR23 -1356 515 -34 -875 -1904 -807 -1836
STR24 -1355 504 -12 -862 -1871 -839 -1848
STR24 -1355 504 -12 -862 -1871 -839 -1848
STR25 -1495 650 -40 -885 -2186 -804 -2105
STR25 -1495 650 -40 -885 -2186 -804 -2105
STR26 -1494 640 -18 -872 -2152 -836 -2116

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 119
Relazione illustrativa e di calcolo Progetto Definitivo

STR26 -1494 640 -18 -872 -2152 -836 -2116


STR27 -1502 651 -43 -895 -2196 -808 -2109
STR27 -1502 651 -43 -895 -2196 -808 -2109
STR28 -1501 640 -21 -882 -2163 -840 -2121
STR28 -1501 640 -21 -882 -2163 -840 -2121
STR29 -1340 647 -31 -724 -2019 -661 -1956
STR29 -1115 647 -31 -499 -1794 -436 -1731
STR30 -1114 637 -9 -486 -1761 -468 -1743
STR30 -1114 637 -9 -486 -1761 -468 -1743
STR31 -1123 648 -34 -509 -1805 -440 -1736
STR31 -1123 648 -34 -509 -1805 -440 -1736
STR32 -1122 638 -12 -496 -1771 -472 -1747
STR32 -1122 638 -12 -496 -1771 -472 -1747
QKE1 -1186 -235 -16 -1437 -968 -1404 -935
QKE1 -1058 1253 -22 173 -2333 217 -2288
QKE2 -1191 -234 -18 -1444 -975 -1407 -938
QKE2 -1063 1253 -24 166 -2340 215 -2292
QKE3 -1147 211 -15 -951 -1374 -920 -1343
QKE3 -1096 807 -23 -313 -1927 -266 -1880
QKE4 -1152 212 -18 -958 -1381 -923 -1346
QKE4 -1102 807 -25 -320 -1934 -269 -1883

La massima azione verticale di compressione registrata sul palo di 2340kN.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 120
Relazione illustrativa e di calcolo Progetto Definitivo

11.1.2 Momento agente sul palo


Va inoltre considerato il momento che si produce lungo al palo dovuto ad azioni agenti
ortogonali allasse del palo.
Nel caso di un palo flessibile, cio avente una lunghezza superiore alla lunghezza critica definita
2

E palo 7
come: l c = D il massimo momento prodotto dalla forza orizzontale H pari a
Gc (1 + 0.75 )
Hl l
M max = 0.1 c . Tale momento si produce in una sezione posta a c dalla testa del palo nel caso
4
di terreno omogeneo. Per quanto invece concerne la distribuzione dei momenti prodotti da una
coppia applicata in testa, si pu assumere una variazione lineare che si smorza in corrispondenza
di una sezione posta a una distanza pari alla lunghezza critica.
Se il palo ha lestremit impedita di ruotare, imponendo la condizione di rotazione nulla si pu
ottenere il massimo momento in testa:
0.375 Hl c
M inc = 0.5

2 2
E palo 7 31.5 10 3 7
lc = D = 1 = 7 .9 m
Gc (1 + 0.75 ) 20(1 + 0.75 0.2)
lc
G( z = )
Grado di eterogenit: = 4 =1
Gc
Azioni orizzontali sul singolo palo:
Azione tagliante sul singolo palo

Azione di Azione di Forza trasv Azione di Azione di


taglio taglio palo dovuta taglio in taglio in Load combination
dovuta a F1 dovuta a F2 a M3 direz 1 tot direz 2 tot

T1 T2 FM3 T1tot T2tot

kN kN kN kN kN

22 33 65 85 46 STR1
22 33 65 85 46 STR1
22 24 53 73 35 STR2
22 24 53 73 35 STR2
22 18 42 63 27 STR3
22 18 42 63 27 STR3
22 10 30 51 16 STR4
22 10 30 51 16 STR4

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 121
Relazione illustrativa e di calcolo Progetto Definitivo

22 37 84 104 54 STR5
22 37 84 104 54 STR5
22 28 72 92 43 STR6
22 28 72 92 43 STR6
22 22 61 82 35 STR7
22 22 61 82 35 STR7
22 14 49 70 24 STR8
22 14 49 70 24 STR8
22 37 73 93 52 STR9
22 37 73 93 52 STR9
22 13 35 56 20 STR10
22 13 35 56 20 STR10
22 29 60 81 42 STR11
22 29 60 81 42 STR11
22 5 22 44 10 STR12
22 5 22 44 10 STR12
22 41 92 111 60 STR13
22 41 92 111 60 STR13
22 17 54 74 28 STR14
22 17 54 74 28 STR14
22 33 79 99 50 STR15
22 33 79 99 50 STR15
22 9 41 62 18 STR16
22 9 41 62 18 STR16
22 31 59 79 43 STR17
22 31 59 79 43 STR17
22 17 36 57 24 STR18
22 17 36 57 24 STR18
22 23 46 67 33 STR19
22 23 46 67 33 STR19
22 8 24 45 13 STR20
22 8 24 45 13 STR20
22 38 90 110 57 STR21
22 38 90 110 57 STR21
22 23 68 88 38 STR22
22 23 68 88 38 STR22
22 30 78 98 46 STR23
22 30 78 98 46 STR23
22 15 55 76 27 STR24
22 15 55 76 27 STR24
100 33 66 164 47 STR25
100 33 66 164 47 STR25
100 19 43 142 28 STR26

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 122
Relazione illustrativa e di calcolo Progetto Definitivo

100 19 43 142 28 STR26


100 38 85 183 55 STR27
100 38 85 183 55 STR27
100 23 62 160 36 STR28
100 23 62 160 36 STR28
100 25 53 152 36 STR29
94 25 53 146 36 STR29
94 11 31 124 17 STR30
94 11 31 124 17 STR30
94 29 72 165 44 STR31
94 29 72 165 44 STR31
94 15 50 143 25 STR32
94 15 50 143 25 STR32
-342 -28 -16 -357 -31 QKE1
374 63 104 476 85 QKE1
-342 -25 -3 -344 -26 QKE2
374 66 117 489 91 QKE2
-110 -72 -93 -201 -91 QKE3
142 107 182 320 145 QKE3
-110 -69 -80 -188 -86 QKE4
142 110 195 333 151 QKE4

Forza orizzontale massima sul palo:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 123
Relazione illustrativa e di calcolo Progetto Definitivo

11.1.3 Verifica capacit portante palo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 124
Relazione illustrativa e di calcolo Progetto Definitivo

La massima azione verticale registrata sul palo di 2340kN.


Capacit portante a compressione del palo 1000mm L=20m: 2813kN
La verifica risulta soddisfatta.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 125
Relazione illustrativa e di calcolo Progetto Definitivo

11.1.4 Verifica strutturale palo D1000mm


Come specificato al punto 7.2.5 del DM2008 i pali in calcestruzzo devono essere armati per tutta
la lunghezza con unarea non inferiore allo 0.3% di quella del calcestruzzo.

DATI GENERALI DELLA SEZIONE

Calcestruzzo: Rck = 30.00 N/mmq

Sezione circolare. Raggio = 50.00 cm

Acciaio: fyk = 430.00 N/mmq

Ferro N. X (cm) Y (cm) Area (cmq)


1 50.0 95.0 2.54
2 63.3 93.0 2.54
3 75.3 87.2 2.54
4 85.2 78.1 2.54
5 91.9 66.4 2.54
6 94.9 53.4 2.54
7 93.9 40.0 2.54
8 89.0 27.5 2.54
9 80.6 17.0 2.54
10 69.5 9.5 2.54
11 56.7 5.5 2.54
12 43.3 5.5 2.54
13 30.5 9.5 2.54
14 19.4 17.0 2.54
15 11.0 27.5 2.54
16 6.1 40.0 2.54
17 5.1 53.4 2.54
18 8.1 66.4 2.54
19 14.8 78.1 2.54
20 24.7 87.2 2.54
21 36.7 93.0 2.54

Caratteristiche limite della sezione:


Nu [kN] Mxu [kN m] Myu [kN m]
Sezione completamente tesa -1998.1 0.0 0.0
Sezione completamente compressa 13048.5 0.0 0.0

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 126
Relazione illustrativa e di calcolo Progetto Definitivo

Fibre inferiori tese 0.0 799.7 0.0


Fibre superiori tese 0.0 -796.1 0.0
Fibre di sinistra tese 0.0 0.0 797.0
Fibre di destra tese 0.0 0.0 -797.0

VERIFICA AGLI STATI LIMITE ULTIMI

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Coef. sicurezza: Gamma

Soll.n. Nd Mxd Myd Nu Mxu Myu EpsC EpsA Gamma


1 2340.0 722.0 222.2 2340.0 1339.4 412.3 -0.35 0.56 1.86 Ok
2 0.0 722.0 222.2 0.0 764.3 235.3 -0.26 1.00 1.06 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 127
Relazione illustrativa e di calcolo Progetto Definitivo

11.2 Verifica fondazione spalla S02


Per le verifiche delle fondazioni della spalla mobile si utilizzato lapproccio 2, secondo cui si adotta una
sola combinazione di gruppi di coefficienti parziali: A1+M1+R3.

11.2.1 Azione verticale sul palo


Si analizza nel seguito il carico verticale massimo agente sui pali di fondazione della pila.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 128
Relazione illustrativa e di calcolo Progetto Definitivo

Reazioni esportate dal modello FEM alla base dellimpalcato:


Joint OutputCase CaseType StepType F1 F2 F3 M1 M2 M3

Text Text Text Text KN KN KN KN-m KN-m KN-m

103 STR1 Combination Max 0 -50 6263 361 -107 -18


103 STR1 Combination Min 0 -50 6263 361 -107 -18
103 STR2 Combination Max 0 -66 4718 340 -102 -24
103 STR2 Combination Min 0 -66 4718 340 -102 -24
103 STR3 Combination Max 0 68 6271 -21 11 24
103 STR3 Combination Min 0 68 6271 -21 11 24
103 STR4 Combination Max 0 52 4727 -41 16 19
103 STR4 Combination Min 0 52 4727 -41 16 19
103 STR5 Combination Max 0 -78 6334 521 -155 -28
103 STR5 Combination Min 0 -78 6334 521 -155 -28
103 STR6 Combination Max 0 -94 4790 501 -150 -34
103 STR6 Combination Min 0 -94 4790 501 -150 -34
103 STR7 Combination Max 0 39 6343 140 -37 14
103 STR7 Combination Min 0 39 6343 140 -37 14
103 STR8 Combination Max 0 23 4798 119 -33 8
103 STR8 Combination Min 0 23 4798 119 -33 8
103 STR9 Combination Max 0 -89 6260 488 -146 -32
103 STR9 Combination Min 0 -89 6260 488 -146 -32
103 STR10 Combination Max 0 107 6274 -148 50 38
103 STR10 Combination Min 0 107 6274 -148 50 38
103 STR11 Combination Max 0 -105 4715 468 -142 -38
103 STR11 Combination Min 0 -105 4715 468 -142 -38
103 STR12 Combination Max 0 91 4730 -169 55 33
103 STR12 Combination Min 0 91 4730 -169 55 33
103 STR13 Combination Max 0 -118 6331 649 -194 -42
103 STR13 Combination Min 0 -118 6331 649 -194 -42
103 STR14 Combination Max 0 78 6346 12 2 28
103 STR14 Combination Min 0 78 6346 12 2 28
103 STR15 Combination Max 0 -133 4787 628 -190 -48

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 129
Relazione illustrativa e di calcolo Progetto Definitivo

103 STR15 Combination Min 0 -133 4787 628 -190 -48


103 STR16 Combination Max 0 62 4801 -8 7 22
103 STR16 Combination Min 0 62 4801 -8 7 22
103 STR17 Combination Max 0 -41 6239 307 -91 -15
103 STR17 Combination Min 0 -41 6239 307 -91 -15
103 STR18 Combination Max 0 77 6247 -75 27 28
103 STR18 Combination Min 0 77 6247 -75 27 28
103 STR19 Combination Max 0 -56 4694 287 -86 -20
103 STR19 Combination Min 0 -56 4694 287 -86 -20
103 STR20 Combination Max 0 61 4703 -95 32 22
103 STR20 Combination Min 0 61 4703 -95 32 22
103 STR21 Combination Max 0 -88 6358 575 -171 -31
103 STR21 Combination Min 0 -88 6358 575 -171 -31
103 STR22 Combination Max 0 30 6367 193 -53 11
103 STR22 Combination Min 0 30 6367 193 -53 11
103 STR23 Combination Max 0 -104 4814 555 -167 -37
103 STR23 Combination Min 0 -104 4814 555 -167 -37
103 STR24 Combination Max 0 14 4822 173 -49 5
103 STR24 Combination Min 0 14 4822 173 -49 5
103 STR25 Combination Max 0 -53 6269 364 -108 -19
103 STR25 Combination Min 0 -53 6269 364 -108 -19
103 STR26 Combination Max 0 65 6277 -17 10 23
103 STR26 Combination Min 0 65 6277 -17 10 23
103 STR27 Combination Max 0 -81 6341 525 -156 -29
103 STR27 Combination Min 0 -81 6341 525 -156 -29
103 STR28 Combination Max 0 37 6349 143 -38 13
103 STR28 Combination Min 0 37 6349 143 -38 13
103 STR29 Combination Max 0 -69 4725 344 -104 -25
103 STR29 Combination Min 0 -69 4725 344 -104 -25
103 STR30 Combination Max 0 49 4733 -38 14 18
103 STR30 Combination Min 0 49 4733 -38 14 18
103 STR31 Combination Max 0 -97 4796 505 -152 -35
103 STR31 Combination Min 0 -97 4796 505 -152 -35
103 STR32 Combination Max 0 21 4805 123 -34 7
103 STR32 Combination Min 0 21 4805 123 -34 7
103 QKE1 Combination Max 0 363 5124 1129 242 130
103 QKE1 Combination Min 0 -386 4343 -780 -343 -138
103 QKE2 Combination Max 0 344 5174 1240 208 123
103 QKE2 Combination Min 0 -406 4393 -669 -377 -146
103 QKE3 Combination Max 0 796 4928 2182 573 285
103 QKE3 Combination Min 0 -818 4539 -1834 -675 -293
103 QKE4 Combination Max 0 776 4978 2294 540 278
103 QKE4 Combination Min 0 -838 4589 -1722 -708 -300

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 130
Relazione illustrativa e di calcolo Progetto Definitivo

Le precedenti reazioni si traducono nelle seguenti azioni sulla spalla:


OutputCase F1 F2 F3 M1 M2 M3

Text KN KN KN KN-m KN-m KN-m

STR1 0 50 -6263 -361 107 18


STR1 0 50 -6263 -361 107 18
STR2 0 66 -4718 -340 102 24
STR2 0 66 -4718 -340 102 24
STR3 0 -68 -6271 21 -11 -24
STR3 0 -68 -6271 21 -11 -24
STR4 0 -52 -4727 41 -16 -19
STR4 0 -52 -4727 41 -16 -19
STR5 0 78 -6334 -521 155 28
STR5 0 78 -6334 -521 155 28
STR6 0 94 -4790 -501 150 34
STR6 0 94 -4790 -501 150 34
STR7 0 -39 -6343 -140 37 -14
STR7 0 -39 -6343 -140 37 -14
STR8 0 -23 -4798 -119 33 -8
STR8 0 -23 -4798 -119 33 -8
STR9 0 89 -6260 -488 146 32
STR9 0 89 -6260 -488 146 32
STR10 0 -107 -6274 148 -50 -38
STR10 0 -107 -6274 148 -50 -38
STR11 0 105 -4715 -468 142 38
STR11 0 105 -4715 -468 142 38
STR12 0 -91 -4730 169 -55 -33
STR12 0 -91 -4730 169 -55 -33
STR13 0 118 -6331 -649 194 42
STR13 0 118 -6331 -649 194 42
STR14 0 -78 -6346 -12 -2 -28
STR14 0 -78 -6346 -12 -2 -28
STR15 0 133 -4787 -628 190 48
STR15 0 133 -4787 -628 190 48
STR16 0 -62 -4801 8 -7 -22
STR16 0 -62 -4801 8 -7 -22
STR17 0 41 -6239 -307 91 15
STR17 0 41 -6239 -307 91 15
STR18 0 -77 -6247 75 -27 -28
STR18 0 -77 -6247 75 -27 -28
STR19 0 56 -4694 -287 86 20
STR19 0 56 -4694 -287 86 20
STR20 0 -61 -4703 95 -32 -22

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 131
Relazione illustrativa e di calcolo Progetto Definitivo

STR20 0 -61 -4703 95 -32 -22


STR21 0 88 -6358 -575 171 31
STR21 0 88 -6358 -575 171 31
STR22 0 -30 -6367 -193 53 -11
STR22 0 -30 -6367 -193 53 -11
STR23 0 104 -4814 -555 167 37
STR23 0 104 -4814 -555 167 37
STR24 0 -14 -4822 -173 49 -5
STR24 0 -14 -4822 -173 49 -5
STR25 0 53 -6269 -364 108 19
STR25 0 53 -6269 -364 108 19
STR26 0 -65 -6277 17 -10 -23
STR26 0 -65 -6277 17 -10 -23
STR27 0 81 -6341 -525 156 29
STR27 0 81 -6341 -525 156 29
STR28 0 -37 -6349 -143 38 -13
STR28 0 -37 -6349 -143 38 -13
STR29 0 69 -4725 -344 104 25
STR29 0 69 -4725 -344 104 25
STR30 0 -49 -4733 38 -14 -18
STR30 0 -49 -4733 38 -14 -18
STR31 0 97 -4796 -505 152 35
STR31 0 97 -4796 -505 152 35
STR32 0 -21 -4805 -123 34 -7
STR32 0 -21 -4805 -123 34 -7
QKE1 0 -363 -5124 -1129 -242 -130
QKE1 0 386 -4343 780 343 138
QKE2 0 -344 -5174 -1240 -208 -123
QKE2 0 406 -4393 669 377 146
QKE3 0 -796 -4928 -2182 -573 -285
QKE3 0 818 -4539 1834 675 293
QKE4 0 -776 -4978 -2294 -540 -278
QKE4 0 838 -4589 1722 708 300

Le azioni totali agenti allintradosso della fondazione della spalla ricavate dalle azioni precedenti
e dalla spinta delle terre risultano:
OutputCase F1 F2 F3 M1 M2 M3

Text KN KN KN KN-m KN-m KN-m

STR1 -216 50 -14934 -501 -7439 18


STR1 -216 50 -14934 -501 -7439 18
STR2 -216 66 -13390 -525 -7444 24
STR2 -216 66 -13390 -525 -7444 24

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 132
Relazione illustrativa e di calcolo Progetto Definitivo

STR3 -216 -68 -14943 210 -7557 -24


STR3 -216 -68 -14943 210 -7557 -24
STR4 -216 -52 -13398 186 -7562 -19
STR4 -216 -52 -13398 186 -7562 -19
STR5 -216 78 -15006 -741 -7391 28
STR5 -216 78 -15006 -741 -7391 28
STR6 -216 94 -13462 -765 -7396 34
STR6 -216 94 -13462 -765 -7396 34
STR7 -216 -39 -15014 -30 -7509 -14
STR7 -216 -39 -15014 -30 -7509 -14
STR8 -216 -23 -13470 -54 -7513 -8
STR8 -216 -23 -13470 -54 -7513 -8
STR9 -216 89 -14931 -738 -7400 32
STR9 -216 89 -14931 -738 -7400 32
STR10 -216 -107 -14946 447 -7596 -38
STR10 -216 -107 -14946 447 -7596 -38
STR11 -216 105 -13387 -762 -7404 38
STR11 -216 105 -13387 -762 -7404 38
STR12 -216 -91 -13401 423 -7601 -33
STR12 -216 -91 -13401 423 -7601 -33
STR13 -216 118 -15003 -978 -7352 42
STR13 -216 118 -15003 -978 -7352 42
STR14 -216 -78 -15017 207 -7548 -28
STR14 -216 -78 -15017 207 -7548 -28
STR15 -216 133 -13459 -1002 -7356 48
STR15 -216 133 -13459 -1002 -7356 48
STR16 -216 -62 -13473 183 -7553 -22
STR16 -216 -62 -13473 183 -7553 -22
STR17 -216 41 -14910 -421 -7455 15
STR17 -216 41 -14910 -421 -7455 15
STR18 -216 -77 -14919 290 -7573 -28
STR18 -216 -77 -14919 290 -7573 -28
STR19 -216 56 -13366 -445 -7460 20
STR19 -216 56 -13366 -445 -7460 20
STR20 -216 -61 -13374 266 -7578 -22
STR20 -216 -61 -13374 266 -7578 -22
STR21 -216 88 -15030 -821 -7375 31
STR21 -216 88 -15030 -821 -7375 31
STR22 -216 -30 -15038 -110 -7493 -11
STR22 -216 -30 -15038 -110 -7493 -11
STR23 -216 104 -13485 -845 -7380 37
STR23 -216 104 -13485 -845 -7380 37
STR24 -216 -14 -13494 -134 -7497 -5

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 133
Relazione illustrativa e di calcolo Progetto Definitivo

STR24 -216 -14 -13494 -134 -7497 -5


STR25 -216 53 -14941 -512 -7438 19
STR25 -216 53 -14941 -512 -7438 19
STR26 -216 -65 -14949 199 -7556 -23
STR26 -216 -65 -14949 199 -7556 -23
STR27 -216 81 -15012 -752 -7390 29
STR27 -216 81 -15012 -752 -7390 29
STR28 -216 -37 -15021 -41 -7508 -13
STR28 -216 -37 -15021 -41 -7508 -13
STR29 -216 69 -13396 -536 -7442 25
STR29 -160 69 -11148 -536 -7442 25
STR30 -160 -49 -11156 175 -7560 -18
STR30 -160 -49 -11156 175 -7560 -18
STR31 -160 97 -11220 -776 -7394 35
STR31 -160 97 -11220 -776 -7394 35
STR32 -160 -21 -11228 -65 -7512 -7
STR32 -160 -21 -11228 -65 -7512 -7
QKE1 -160 -363 -11547 -111 -7788 -130
QKE1 -160 386 -10766 -301 -7203 138
QKE2 -160 -344 -11597 -278 -7754 -123
QKE2 -160 406 -10816 -468 -7169 146
QKE3 -160 -796 -11352 45 -8119 -285
QKE3 -160 818 -10962 -458 -6871 293
QKE4 -160 -776 -11401 -122 -8086 -278
QKE4 -160 838 -11012 -624 -6838 300

Azioni verticali sul singolo palo:


Azioni verticali sul singolo palo

Azione Azione Azione


Load
verticale verticale verticale P1 P2 P3 P4
combination
dovuta a F3 dovuta a M2 dovuta a M1

N3 FM2 FM1 tot++ tot-+ tot+- tot--


kN kN kN kN kN kN kN
STR1 -1493 -496 -13 -2002 -1010 -1977 -985
STR1 -1493 -496 -13 -2002 -1010 -1977 -985
STR2 -1339 -496 -13 -1848 -856 -1822 -830
STR2 -1339 -496 -13 -1848 -856 -1822 -830
STR3 -1494 -504 5 -1993 -985 -2003 -996
STR3 -1494 -504 5 -1993 -985 -2003 -996
STR4 -1340 -504 5 -1839 -831 -1849 -840

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 134
Relazione illustrativa e di calcolo Progetto Definitivo

STR4 -1340 -504 5 -1839 -831 -1849 -840


STR5 -1501 -493 -19 -2012 -1027 -1975 -989
STR5 -1501 -493 -19 -2012 -1027 -1975 -989
STR6 -1346 -493 -19 -1858 -872 -1820 -834
STR6 -1346 -493 -19 -1858 -872 -1820 -834
STR7 -1501 -501 -1 -2003 -1002 -2001 -1000
STR7 -1501 -501 -1 -2003 -1002 -2001 -1000
STR8 -1347 -501 -1 -1849 -847 -1847 -845
STR8 -1347 -501 -1 -1849 -847 -1847 -845
STR9 -1493 -493 -19 -2005 -1018 -1968 -981
STR9 -1493 -493 -19 -2005 -1018 -1968 -981
STR10 -1495 -506 11 -1990 -977 -2012 -999
STR10 -1495 -506 11 -1990 -977 -2012 -999
STR11 -1339 -494 -19 -1852 -864 -1813 -826
STR11 -1339 -494 -19 -1852 -864 -1813 -826
STR12 -1340 -507 11 -1836 -823 -1857 -844
STR12 -1340 -507 11 -1836 -823 -1857 -844
STR13 -1500 -490 -25 -2015 -1035 -1966 -986
STR13 -1500 -490 -25 -2015 -1035 -1966 -986
STR14 -1502 -503 5 -2000 -993 -2010 -1004
STR14 -1502 -503 5 -2000 -993 -2010 -1004
STR15 -1346 -490 -25 -1862 -881 -1811 -830
STR15 -1346 -490 -25 -1862 -881 -1811 -830
STR16 -1347 -504 5 -1846 -839 -1855 -848
STR16 -1347 -504 5 -1846 -839 -1855 -848
STR17 -1491 -497 -11 -1999 -1005 -1977 -983
STR17 -1491 -497 -11 -1999 -1005 -1977 -983
STR18 -1492 -505 7 -1989 -980 -2004 -994
STR18 -1492 -505 7 -1989 -980 -2004 -994
STR19 -1337 -497 -11 -1845 -850 -1823 -828
STR19 -1337 -497 -11 -1845 -850 -1823 -828
STR20 -1337 -505 7 -1836 -826 -1849 -839
STR20 -1337 -505 7 -1836 -826 -1849 -839
STR21 -1503 -492 -21 -2015 -1032 -1974 -991
STR21 -1503 -492 -21 -2015 -1032 -1974 -991
STR22 -1504 -500 -3 -2006 -1007 -2001 -1002
STR22 -1504 -500 -3 -2006 -1007 -2001 -1002
STR23 -1349 -492 -21 -1862 -878 -1819 -835
STR23 -1349 -492 -21 -1862 -878 -1819 -835
STR24 -1349 -500 -3 -1853 -853 -1846 -846
STR24 -1349 -500 -3 -1853 -853 -1846 -846
STR25 -1494 -496 -13 -2003 -1011 -1977 -985
STR25 -1494 -496 -13 -2003 -1011 -1977 -985

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 135
Relazione illustrativa e di calcolo Progetto Definitivo

STR26 -1495 -504 5 -1994 -986 -2004 -996


STR26 -1495 -504 5 -1994 -986 -2004 -996
STR27 -1501 -493 -19 -2013 -1028 -1975 -990
STR27 -1501 -493 -19 -2013 -1028 -1975 -990
STR28 -1502 -501 -1 -2004 -1003 -2002 -1001
STR28 -1502 -501 -1 -2004 -1003 -2002 -1001
STR29 -1340 -496 -14 -1849 -857 -1822 -830
STR29 -1115 -496 -14 -1624 -632 -1597 -605
STR30 -1116 -504 4 -1615 -607 -1624 -616
STR30 -1116 -504 4 -1615 -607 -1624 -616
STR31 -1122 -493 -20 -1634 -649 -1595 -609
STR31 -1122 -493 -20 -1634 -649 -1595 -609
STR32 -1123 -501 -2 -1625 -624 -1622 -620
STR32 -1123 -501 -2 -1625 -624 -1622 -620
QKE1 -1155 -519 -3 -1677 -638 -1671 -633
QKE1 -1077 -480 -8 -1564 -604 -1549 -589
QKE2 -1160 -517 -7 -1684 -650 -1670 -636
QKE2 -1082 -478 -12 -1571 -615 -1548 -592
QKE3 -1135 -541 1 -1675 -593 -1678 -595
QKE3 -1096 -458 -12 -1566 -650 -1543 -627
QKE4 -1140 -539 -3 -1682 -604 -1676 -598
QKE4 -1101 -456 -16 -1573 -661 -1541 -630

La massima azione verticale di compressione registrata sul palo di 2015kN.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 136
Relazione illustrativa e di calcolo Progetto Definitivo

11.2.2 Momento agente sul palo


Va inoltre considerato il momento che si produce lungo al palo dovuto ad azioni agenti
ortogonali allasse del palo.
Nel caso di un palo flessibile, cio avente una lunghezza superiore alla lunghezza critica definita
2

E palo 7
come: l c = D il massimo momento prodotto dalla forza orizzontale H pari a
Gc (1 + 0.75 )
Hl l
M max = 0.1 c . Tale momento si produce in una sezione posta a c dalla testa del palo nel caso
4
di terreno omogeneo. Per quanto invece concerne la distribuzione dei momenti prodotti da una
coppia applicata in testa, si pu assumere una variazione lineare che si smorza in corrispondenza
di una sezione posta a una distanza pari alla lunghezza critica.
Se il palo ha lestremit impedita di ruotare, imponendo la condizione di rotazione nulla si pu
ottenere il massimo momento in testa:
0.375 Hl c
M inc = 0.5

2 2
E palo 7 25 10 3 7
lc = D = 1 = 7.37 m
Gc (1 + 0.75 ) 20(1 + 0.75 0.2)
lc
G( z = )
Grado di eterogenit: = 4 =1
Gc
Azioni orizzontali sul singolo palo:
Azione tagliante sul singolo palo

Azione di Azione di Forza trasv Azione di Azione di


taglio taglio palo dovuta taglio in taglio in Load combination
dovuta a F1 dovuta a F2 a M3 direz 1 tot direz 2 tot

T1 T2 FM3 T1tot T2tot

kN kN kN kN kN

-22 5 0 -21 5 STR1


-22 5 0 -21 5 STR1
-22 7 1 -21 7 STR2
-22 7 1 -21 7 STR2
-22 -7 -1 -22 -7 STR3
-22 -7 -1 -22 -7 STR3
-22 -5 0 -22 -5 STR4
-22 -5 0 -22 -5 STR4

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 137
Relazione illustrativa e di calcolo Progetto Definitivo

-22 8 1 -21 8 STR5


-22 8 1 -21 8 STR5
-22 9 1 -21 10 STR6
-22 9 1 -21 10 STR6
-22 -4 0 -22 -4 STR7
-22 -4 0 -22 -4 STR7
-22 -2 0 -22 -2 STR8
-22 -2 0 -22 -2 STR8
-22 9 1 -21 9 STR9
-22 9 1 -21 9 STR9
-22 -11 -1 -23 -11 STR10
-22 -11 -1 -23 -11 STR10
-22 11 1 -21 11 STR11
-22 11 1 -21 11 STR11
-22 -9 -1 -22 -9 STR12
-22 -9 -1 -22 -9 STR12
-22 12 1 -21 12 STR13
-22 12 1 -21 12 STR13
-22 -8 -1 -22 -8 STR14
-22 -8 -1 -22 -8 STR14
-22 13 1 -20 14 STR15
-22 13 1 -20 14 STR15
-22 -6 -1 -22 -6 STR16
-22 -6 -1 -22 -6 STR16
-22 4 0 -21 4 STR17
-22 4 0 -21 4 STR17
-22 -8 -1 -22 -8 STR18
-22 -8 -1 -22 -8 STR18
-22 6 1 -21 6 STR19
-22 6 1 -21 6 STR19
-22 -6 -1 -22 -6 STR20
-22 -6 -1 -22 -6 STR20
-22 9 1 -21 9 STR21
-22 9 1 -21 9 STR21
-22 -3 0 -22 -3 STR22
-22 -3 0 -22 -3 STR22
-22 10 1 -21 11 STR23
-22 10 1 -21 11 STR23
-22 -1 0 -22 -1 STR24
-22 -1 0 -22 -1 STR24
-22 5 0 -21 5 STR25
-22 5 0 -21 5 STR25
-22 -6 -1 -22 -7 STR26

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 138
Relazione illustrativa e di calcolo Progetto Definitivo

-22 -6 -1 -22 -7 STR26


-22 8 1 -21 8 STR27
-22 8 1 -21 8 STR27
-22 -4 0 -22 -4 STR28
-22 -4 0 -22 -4 STR28
-22 7 1 -21 7 STR29
-16 7 1 -15 7 STR29
-16 -5 0 -16 -5 STR30
-16 -5 0 -16 -5 STR30
-16 10 1 -15 10 STR31
-16 10 1 -15 10 STR31
-16 -2 0 -16 -2 STR32
-16 -2 0 -16 -2 STR32
-16 -36 -3 -19 -37 QKE1
-16 39 3 -13 39 QKE1
-16 -34 -3 -19 -35 QKE2
-16 41 4 -12 41 QKE2
-16 -80 -7 -23 -81 QKE3
-16 82 7 -9 83 QKE3
-16 -78 -7 -23 -79 QKE4
-16 84 8 -9 85 QKE4

Forza orizzontale massima sul palo:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 139
Relazione illustrativa e di calcolo Progetto Definitivo

11.2.3 Verifica capacit portante palo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 140
Relazione illustrativa e di calcolo Progetto Definitivo

La massima azione verticale registrata sul palo di 2015kN.


Capacit portante a compressione del palo 1000mm L=20m: 2813kN
La verifica risulta soddisfatta.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 141
Relazione illustrativa e di calcolo Progetto Definitivo

11.2.4 Verifica strutturale palo D1000mm


Come specificato al punto 7.2.5 del DM2008 i pali in calcestruzzo devono essere armati per tutta
la lunghezza con unarea non inferiore allo 0.3% di quella del calcestruzzo.

DATI GENERALI DELLA SEZIONE

Calcestruzzo: Rck = 30.00 N/mmq

Sezione circolare. Raggio = 50.00 cm

Acciaio: fyk = 430.00 N/mmq

Ferro N. X (cm) Y (cm) Area (cmq)


1 50.0 95.0 2.01
2 67.2 91.6 2.01
3 81.8 81.8 2.01
4 91.6 67.2 2.01
5 95.0 50.0 2.01
6 91.6 32.8 2.01
7 81.8 18.2 2.01
8 67.2 8.4 2.01
9 50.0 5.0 2.01
10 32.8 8.4 2.01
11 18.2 18.2 2.01
12 8.4 32.8 2.01
13 5.0 50.0 2.01
14 8.4 67.2 2.01
15 18.2 81.8 2.01
16 32.8 91.6 2.01

Caratteristiche limite della sezione:


Nu [kN] Mxu [kN m] Myu [kN m]
Sezione completamente tesa -1202.9 0.0 0.0
Sezione completamente compressa 12253.2 0.0 0.0
Fibre inferiori tese 0.0 497.1 0.0
Fibre superiori tese 0.0 -497.1 0.0
Fibre di sinistra tese 0.0 0.0 497.1
Fibre di destra tese 0.0 0.0 -497.1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 142
Relazione illustrativa e di calcolo Progetto Definitivo

VERIFICA AGLI STATI LIMITE ULTIMI

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Coef. sicurezza: Gamma

Soll.n. Nd Mxd Myd Nu Mxu Myu EpsC EpsA Gamma


1 2015.0 12.8 126.0 2015.0 110.4 1091.2 -0.35 0.67 8.66 Ok
2 0.0 12.8 126.0 0.0 49.9 493.2 -0.21 1.00 3.91 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 143
Relazione illustrativa e di calcolo Progetto Definitivo

12 VERIFICA MURO NUOVA ROTONDA

RELAZIONE DI CALCOLO MURO DI SOSTEGNO


--------------------------------------

Descrizione dell'opera : muro in calcestruzzo armato.


Tipo di sovrastruttura : paramenti piani.
Tipo di fondazione : piana orizzontale.

DATI GEOMETRICI, DEI MATERIALI E DI CARICO

GEOMETRIA DELLA MENSOLA IN ELEVAZIONE:

Altezza paramento : 2.30 m


Spessore in sommit : 0.50 m
Spessore all'attacco fondazione : 0.50 m
Inclinazione paramento esterno : 0.00
Inclinazione paramento interno : 0.00

GEOMETRIA DEGLI ELEMENTI DI FONDAZIONE:

Lunghezza base di fondazione : 2.70 m


Lunghezza mensola a monte : 1.85 m
Altezza bordo libero mens. mon. : 0.50 m
Lunghezza mensola a valle : 0.35 m
Altezza bordo libero mens. val. : 0.50 m
Altezza rinterro per mens. val. : 1.10 m
Inclinazione base di fondazione : 0.00

MATERIALI UTILIZZATI PER LA STRUTTURA:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 144
Relazione illustrativa e di calcolo Progetto Definitivo

Peso specifico del muro : 25.000 kN/mc


Resistenza caratt.ca Cls -Rck- : 30.0 N/mmq
Acciaio per armature -Tipo- : B 450 C

CARATTERISTICHE GEOTECNICHE DEI TERRENI:

Terreno a valle del muro:


Peso specifico : 18.000 kN/mc
Angolo di attrito : 30.00
Angolo di attrito terra-muro : 20.00
Coesione : 0.000 kN/mq

Terreno di fondazione del muro:


Peso specifico : 18.000 kN/mc
Angolo di attrito : 30.00
Coesione : 0.000 kN/mq
Tensione limite del terreno : 236.900 kN/mq

Terreno a monte del muro:


Peso specifico : 18.000 kN/mc
Angolo di inclin.ne terrapieno : 0.00
Angolo di attrito : 30.00
Angolo di attrito terra-muro : 20.00
Coesione : 0.000 kN/mq

CARICHI AGENTI SULLA STRUTTURA:

Sovraccarichi uniformi del tipo permanente sul terreno:


Distribuito a valle del muro : 0.000 kN/mq
Distribuito a monte del muro : 0.000 kN/mq
Nastriforme a monte del muro : 0.000 kN/mq
Distanza nastro dal param. int. : 0.00 m
Larghezza del nastro : 0.00 m

Sovraccarichi uniformi del tipo variabile sul terreno:


Distribuito a valle del muro : 0.000 kN/mq
Distribuito a monte del muro : 20.000 kN/mq
Nastriforme a monte del muro : 0.000 kN/mq
Distanza nastro dal param. int. : 0.00 m
Larghezza del nastro : 0.00 m

Carichi applicati alla mensola in elevazione:


Legenda dei simboli usati in tabella:
Tipo: P = permanente; V = variabile
dy : Distanza dalla base della mensola del punto di applicazione
Fx : Forza lungo X (positiva da sinistra verso destra)
Fy : Forza lungo Y (positiva dall'alto verso il basso)
Mz : Coppia (positiva se oraria)
-----------------------------------------------------------------
| N. | Tipo | dy [m] | Fx [kN] | Fy [kN] | Mz [kNm] |
-----------------------------------------------------------------
| 1 | V | 2.30 | -20.00 | 0.00 | -30.60 |
-----------------------------------------------------------------

NORMATIVA

Le verifiche geotecniche e di resistenza vengono eseguite secondo i dettami


del D.M. 14 gennaio 2008 adottando l'approccio 1.
Vengono generate dodici combinazioni di carico statiche:
- quattro di equilirio di corpo rigido (EQU);
- quattro di tipo strutturale (STR);
- quattro di tipo geotecnico (GEO);
ottenute permutando i coefficienti parziali per le azioni permanenti e per
le azioni variabili.
Vengono inoltre generate quattro combinazioni di carico sismiche variando
i coefficienti parziali per i parametri geotecnici del terreno utilizzati
(M1 per le prime due ed M2 per le restanti) e variando la direzione della

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 145
Relazione illustrativa e di calcolo Progetto Definitivo

componente verticale dell'azione sismica (verso il basso e verso l'alto).

Parametri per la determinazione dei carichi derivanti da sisma:


Vita nominale -Vn- : 50
Tipo di costruzione :2
Classe d'uso : III
Coefficiente d'uso -Cu- : 2
Periodo di riferimento -Vr- : 100
Probabilit di superamento -Pver- : 10
Periodo di ritorno -Tr- : 949
Fatt. di amplificaz. spettrale massima -Fo- : 2.8000
Accelerazione orizzontale massima -ag- : 0.0669 g
Zona sismica :4
Categoria di sottosuolo :C
Coeff. di amplificazione stratigrafica -Ss- : 1.5000
Coefficienti di riduzione dell'accelerazione orizzontale massima
verifiche locali -Betam- : 1.0000
verifica di stabilit globale -Betas- : 0.2000
Categoria topografica : T1
Coeff. di amplificazione topografica -St- : 1.0000
Coefficienti sismici per le verifiche locali
orizzontale -kh- : 0.10035
verticale -kv- : 0.05018
Coefficienti sismici per la verifica di stabilit globale
orizzontale -kh- : 0.02007
verticale -kv- : 0.01004

Coefficienti parziali per le azioni:


-----------------------------------
| Verifica | gGmax | gGmin | gQ |
-----------------------------------
| STR (A1) | 1.30 | 1.00 | 1.50 |
| GEO (A2) | 1.00 | 1.00 | 1.30 |
| EQU | 1.10 | 0.90 | 1.50 |
------------------------------------

Coefficienti parziali per i parametri geotecnici:


---------------------------------------
| Verifica | gTan(Fi) | gC' | gGamma |
---------------------------------------
| (M1) | 1.00 | 1.00 | 1.00 |
| (M2) | 1.25 | 1.25 | 1.00 |
---------------------------------------

Coefficienti parziali per le azioni nelle combinazioni sismiche:


Carichi permanenti -gG- : 1.00
Carichi variabili -psi2i- : 0.60

Coefficienti per la determinazione delle masse sismiche:


Carichi permanenti -gG- : 1.00
Carichi variabili -psiEi- : 0.60

Coefficienti parziali per le verifiche:


-----------------------------------------------------
| Verifica | R1 | R2 | R3 |
-----------------------------------------------------
| Capacit portante fondazione | 1.00 | 1.00 | 1.40 |
| Scorrimento | 1.00 | 1.00 | 1.10 |
| Stabilit globale | - | 1.10 | - |
-----------------------------------------------------

Combinazioni:
----------------------------------------------------------------------
| CMB | Tipo | gG | gQ | gE(*) || gTan(Fi) | gC' | gGamma || R |
----------------------------------------------------------------------
| 1 | EQU | 1.10 | 1.50 | 0.00 || 1.25 | 1.25 | 1.00 || 1 |
| 2 | EQU | 1.10 | 0.00 | 0.00 || 1.25 | 1.25 | 1.00 || 1 |
| 3 | EQU | 0.90 | 1.50 | 0.00 || 1.25 | 1.25 | 1.00 || 1 |

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 146
Relazione illustrativa e di calcolo Progetto Definitivo

| 4 | EQU | 0.90 | 0.00 | 0.00 || 1.25 | 1.25 | 1.00 || 1 |


| 5 | STR | 1.30 | 1.50 | 0.00 || 1.00 | 1.00 | 1.00 || R1 |
| 6 | STR | 1.30 | 0.00 | 0.00 || 1.00 | 1.00 | 1.00 || R1 |
| 7 | STR | 1.00 | 1.50 | 0.00 || 1.00 | 1.00 | 1.00 || R1 |
| 8 | STR | 1.00 | 0.00 | 0.00 || 1.00 | 1.00 | 1.00 || R1 |
| 9 | GEO | 1.00 | 1.30 | 0.00 || 1.25 | 1.25 | 1.00 || R2 |
| 10 | GEO | 1.00 | 0.00 | 0.00 || 1.25 | 1.25 | 1.00 || R2 |
| 11 | GEO | 1.00 | 1.30 | 0.00 || 1.25 | 1.25 | 1.00 || R2 |
| 12 | GEO | 1.00 | 0.00 | 0.00 || 1.25 | 1.25 | 1.00 || R2 |
| 13 | SIS | 1.00 | 0.60 | 1.00+ || 1.00 | 1.00 | 1.00 || R1 |
| 14 | SIS | 1.00 | 0.60 | 1.00- || 1.00 | 1.00 | 1.00 || R1 |
| 15 | SIS | 1.00 | 0.60 | 1.00+ || 1.25 | 1.25 | 1.00 || R2 |
| 16 | SIS | 1.00 | 0.60 | 1.00- || 1.25 | 1.25 | 1.00 || R2 |
----------------------------------------------------------------------
(*) Il segno dopo il coefficiente parziale indica la direzione della
componente verticale dell'azione sismica: + significa verso il basso
e - significa verso l'alto.

VERIFICHE DI STABILITA' DEL MANUFATTO

Coefficienti parziali per i parametri geotecnici M1:


Coef. Spinta Attiva (Coulomb) K = 0.2973
Coef. Spinta Attiva Statica+Dinamica (Mononobe-Okabe):
componente verticale azione sismica agente verso l'alto K = 0.3703
componente verticale azione sismica agente verso il basso K = 0.3625
Coefficienti parziali per i parametri geotecnici M2:
Coef. Spinta Attiva (Coulomb) K = 0.3601
Coef. Spinta Attiva Statica+Dinamica (Mononobe-Okabe):
componente verticale azione sismica agente verso l'alto K = 0.4446
componente verticale azione sismica agente verso il basso K = 0.4355

Coefficienti parziali per i parametri geotecnici M1:


Coef. Spinta Passiva a valle (Coulomb) K = 6.1054
Coef. Spinta Passiva a valle Statica+Dinamica (Mononobe-Okabe):
componente verticale azione sismica agente verso l'alto K = 2.8108
componente verticale azione sismica agente verso il basso K = 2.8295
Coefficienti parziali per i parametri geotecnici M2:
Coef. Spinta Passiva a valle (Coulomb) K = 4.5446
Coef. Spinta Passiva a valle Statica+Dinamica (Mononobe-Okabe):
componente verticale azione sismica agente verso l'alto K = 2.2715
componente verticale azione sismica agente verso il basso K = 2.2887

Calcolo della SPINTA ATTIVA su un tratto di muro di larghezza 1 m.


Altezza di calcolo = 2.80 m

Combinazione 1
Componente X RISULTANTE = 54.685 kN
Componente Y RISULTANTE = 19.904 kN
Distanza Y dall'estremo della fondazione = 1.176 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 2
Componente X RISULTANTE = 26.262 kN
Componente Y RISULTANTE = 9.559 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 3
Componente X RISULTANTE = 49.910 kN
Componente Y RISULTANTE = 18.166 kN
Distanza Y dall'estremo della fondazione = 1.199 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 4
Componente X RISULTANTE = 21.487 kN
Componente Y RISULTANTE = 7.821 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 5
Componente X RISULTANTE = 49.096 kN

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 147
Relazione illustrativa e di calcolo Progetto Definitivo

Componente Y RISULTANTE = 17.869 kN


Distanza Y dall'estremo della fondazione = 1.156 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 6
Componente X RISULTANTE = 25.627 kN
Componente Y RISULTANTE = 9.328 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 7
Componente X RISULTANTE = 43.182 kN
Componente Y RISULTANTE = 15.717 kN
Distanza Y dall'estremo della fondazione = 1.187 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 8
Componente X RISULTANTE = 19.713 kN
Componente Y RISULTANTE = 7.175 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 9
Componente X RISULTANTE = 48.508 kN
Componente Y RISULTANTE = 17.655 kN
Distanza Y dall'estremo della fondazione = 1.170 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 10
Componente X RISULTANTE = 23.875 kN
Componente Y RISULTANTE = 8.690 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 11
Componente X RISULTANTE = 48.508 kN
Componente Y RISULTANTE = 17.655 kN
Distanza Y dall'estremo della fondazione = 1.170 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 12
Componente X RISULTANTE = 23.875 kN
Componente Y RISULTANTE = 8.690 kN
Distanza Y dall'estremo della fondazione = 0.933 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 13
Componente X RISULTANTE = 37.262 kN
Componente Y RISULTANTE = 13.562 kN
Distanza Y dall'estremo della fondazione = 1.153 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 14
Componente X RISULTANTE = 34.426 kN
Componente Y RISULTANTE = 12.530 kN
Distanza Y dall'estremo della fondazione = 1.133 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 15
Componente X RISULTANTE = 44.763 kN
Componente Y RISULTANTE = 16.292 kN
Distanza Y dall'estremo della fondazione = 1.151 m
Distanza X dall'estremo della fondazione = 0.850 m
Combinazione 16
Componente X RISULTANTE = 41.338 kN
Componente Y RISULTANTE = 15.046 kN
Distanza Y dall'estremo della fondazione = 1.130 m
Distanza X dall'estremo della fondazione = 0.850 m

Forze d'inerzia
Componente X forza d'inerzia = 16.185 kN
Distanza Y dall'estremo della fondazione = 1.515 m
Componente Y forza d'inerzia = 8.093 kN
Distanza X dall'estremo della fondazione = 1.477 m

VERIFICA RIBALTAMENTO:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 148
Relazione illustrativa e di calcolo Progetto Definitivo

Combinazione 3
Centro di rotazione: estremo della soletta di fondazione.

M peso muro = 56.250 1.005 = 56.531 kNm


M peso terreno a monte = 68.931 1.775 = 122.353 kNm
M peso terreno a valle = 3.402 0.175 = 0.595 kNm
M sovraccarichi a monte = 55.500 1.775 = 98.513 kNm
MOMENTO STABILIZZANTE = 277.992 kNm

M comp X SpintaTotale = -49.910 1.199 = -59.847 kNm


M comp Y SpintaTotale = 18.166 0.850 = 15.441 kNm
M carichi concentrati = -129.900 kNm
MOMENTO RIBALTANTE = -174.306 kNm

Coef. Sicurezza Ribaltamento -> 1.595


Mstab. / Mrib.

VERIFICA SCHIACCIAMENTO:

Combinazione 5
N Peso Proprio del muro = 81.250 kN
N Peso terreno a monte = 99.567 kN
N Peso terreno a valle = 4.914 kN
N Sovrac. unif. a monte = 55.500 kN
N comp X SpintaTotale = 0.000 kN
N comp Y SpintaTotale = 17.869 kN
Componente Normale TOTALE (Ntot) = 259.100 kN

Mtot = Mrib + Mstab = -171.485 + 357.760 = 186.275 kNm

Ascissa appl. Risultante (Mtot / Ntot) = 0.719 m


Eccentricit = 0.631 m
Punto di applicazione risultante ESTERNO al terzo medio
Ampiezza zona compressa (Bcomp) = 2.157 m
Sigma1 = 240.265 kN/mq
Sigma2 = 0.000 kN/mq
Sigma Limite (SigmaL) = 236.900 kN/mq

Coef. Sicurezza Schiacciamento -> 0.986


[SigmaL / R1] / SigmaMax

VERIFICA A TRASLAZIONE:

Combinazione 16
Coef. attrito (Tg(Fi)) = 0.46188
Componente verticale azione sismica agente verso l'alto.

Risultante normale al piano di fond. (Ntot) = 172.023 kN


Risultante tangenziale al piano di fond. (T) = 69.523 kN

Coef. Sicurezza Traslazione -> 1.143


[NtotTg(Fi) / R2] / T

PROGETTO DELLE ARMATURE DEL MANUFATTO

Metodo di verifica : Stato Limite Ultimo.


Verifica N/M: si visualizza il valore del rapporto Sd/Su
(Sd = sollecitazione di progetto, Su = sollecitazione ultima).
Verifica (25): si visualizza il valore del rapporto Nd/Nu,
dove Nu viene ottenuto con riduzione del 25% di fcd
(Nd = sollecitazione normale di progetto, Nu = sollecitazione normale ultima).
Entrambi i valori dei rapporti devono essere minori o uguali a 1 per verifica positiva.

Sollecitazioni sul muro:


calcolo delle sollecitazioni per un tratto di muro di larghezza 1 m.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 149
Relazione illustrativa e di calcolo Progetto Definitivo

Quote delle sezioni dallo spiccato di fondazione.

Sezione n. 1 (quota = 1.53 m) (OK)


Combinazione 7
N = 9.58 kN
T = 37.90 kN
M = 71.74 kNm
Armatura minima progetto:
Af = 7.70 cmq
Af'= 3.93 cmq
Verifica N/M: Sd/Su = 0.53530
Verifica (25): Nd/Nu = 0.00154
Asse neutro: x/d = 0.11230
Armatura effettiva:
Af = 1 14 / 20 = 7.70 cmq
Af'= 1 12 / 20 = 5.65 cmq
Verifica N/M: Sd/Su = 0.53548
Verifica (25): Nd/Nu = 0.00152
Asse neutro: x/d = 0.11230

Sezione n. 2 (quota = 0.77 m) (OK)


Combinazione 7
N = 19.17 kN
T = 48.76 kN
M = 104.77 kNm
Armatura minima progetto:
Af = 7.70 cmq
Af'= 3.93 cmq
Verifica N/M: Sd/Su = 0.77315
Verifica (25): Nd/Nu = 0.00308
Asse neutro: x/d = 0.11230
Armatura effettiva:
Af = 1 14 / 20 = 7.70 cmq
Af'= 1 12 / 20 = 5.65 cmq
Verifica N/M: Sd/Su = 0.77338
Verifica (25): Nd/Nu = 0.00305
Asse neutro: x/d = 0.11230

Sezione n. 3 (quota = 0.00 m) (OK)


Combinazione 5
N = 37.37 kN
T = 66.57 kN
M = 150.33 kNm
Armatura minima progetto:
Af = 8.84 cmq
Af'= 4.75 cmq
Verifica N/M: Sd/Su = 0.95692
Verifica (25): Nd/Nu = 0.00594
Asse neutro: x/d = 0.11882
Armatura effettiva:
Af = 1 16 / 20 = 10.05 cmq
Af'= 1 12 / 20 = 5.65 cmq
Verifica N/M: Sd/Su = 0.84543
Verifica (25): Nd/Nu = 0.00586
Asse neutro: x/d = 0.12641

Sezione d'incastro mensola di fondazione a valle (OK)


Lunghezza di calcolo mensola = 0.60 m
Combinazione 5
sigma1 terreno = 240.27 kN/mq
sigma terreno sez. incastro = 173.43 kN/mq
Peso CLS mensola = 5.69 kN
Peso concio di terreno = 4.91 kN
T = 113.51 kN
M pressione terreno = 39.24 kNm
M peso fondazione = -2.42 kNm
M peso terreno = -2.09 kNm

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 150
Relazione illustrativa e di calcolo Progetto Definitivo

M totale = 34.73 kNm


Armatura minima progetto:
Af = 7.70 cmq
Af'= 3.93 cmq
Verifica N/M: Sd/Su = 0.26692
Asse neutro: x/d = 0.11230
Armatura effettiva:
Af = 1 16 / 20 = 10.05 cmq
Af'= 1 16 / 20 = 10.05 cmq
Verifica N/M: Sd/Su = 0.20650
Asse neutro: x/d = 0.12424

Sezione d'incastro mensola di fondazione a monte (OK)


Lunghezza di calcolo mensola = 2.10 m
Combinazione 5
sigma2 = 0.00 kN/mq
sigma sez. incastro = 173.43 kN/mq
Peso CLS mensola = 30.06 kN
Peso concio di terreno = 99.57 kN
Peso sovraccarico = 55.50 kN
T = -50.14 kN
M pressione terreno = 70.05 kNm
M peso fondazione = -35.32 kNm
M peso terreno = -116.99 kNm
M peso sovraccarico = -65.21 kNm
M totale = -147.48 kNm
Armatura minima progetto:
Af = 8.84 cmq
Af'= 4.75 cmq
Verifica N/M: Sd/Su = 0.99191
Asse neutro: x/d = 0.11882
Armatura effettiva:
Af'= 1 16 / 20 = 10.05 cmq
Af = 1 16 / 20 = 10.05 cmq
Verifica N/M: Sd/Su = 0.87681
Asse neutro: x/d = 0.12424

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 151
Relazione illustrativa e di calcolo Progetto Definitivo

ALLEGATO A

Relazione illustrativa e di calcolo del ponte provvisorio in acciaio tipo Bailey e del
ponte tecnologico temporaneo piperack

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 1
Relazione illustrativa e di calcolo Progetto Definitivo

Indice

1 PREMESSA E DESCRIZIONE DELLE OPERE ...............................................................................................3

1.1 Ponte provvisorio in acciaio tipo Bailey................................................................................................3


1.1.1 Fasi costruttive .........................................................................................................................................................4

1.2 Ponte tecnologico temporaneo piperack................................................................................................4

2 PONTE PROVVISORIO IN ACCIAIO TIPO BAILEY ......................................................................................6

2.1 Analisi dei carichi..................................................................................................................................6


2.1.1 Peso proprio..............................................................................................................................................................6
2.1.2 Spinta delle terre e sovraccarico variabile a tergo della spalla .................................................................................6
2.1.3 Variabili....................................................................................................................................................................7
2.1.3.1 Definizione delle corsie convenzionali.....................................................................................................................7
2.1.3.2 Schemi di Carico ......................................................................................................................................................8
2.1.3.3 Categorie Stradali .....................................................................................................................................................8
2.1.3.4 Disposizione dei carichi mobili ................................................................................................................................8
2.1.4 Azione longitudinale di frenamento o di accelerazione: q3....................................................................................11

2.2 Combinazioni di carico........................................................................................................................11


2.3 Analisi azioni sui pali di fondazione ...................................................................................................14
2.3.1 Azione verticale sul palo ........................................................................................................................................14
2.3.2 Momento agente sul palo........................................................................................................................................14

2.4 Verifica capacit portante palo ............................................................................................................16


2.4.1 Verifica strutturale palo D1000mm ........................................................................................................................18

3 PONTE TECNOLOGICO TEMPORANEO PIPERACK...................................................................................20


3.1 Analisi dei carichi................................................................................................................................20
3.2 Modellazione agli elementi finiti (FEM).............................................................................................20
3.2.1 Caratteristiche programma di calcolo .....................................................................................................................20

3.3 Casi di carico .......................................................................................................................................22


3.4 Combinazioni di carico........................................................................................................................22
3.5 Verifiche allo SLU...............................................................................................................................23
3.6 Verifica degli appoggi .........................................................................................................................25

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 2
Relazione illustrativa e di calcolo Progetto Definitivo

1 PREMESSA E DESCRIZIONE DELLE OPERE

Oggetto della presente relazione sono le verifiche strutturali nellambito del progetto definitivo
di nuovi parcheggi a servizio del complesso monumentale della Reggia di Venaria e di un nuovo
ponte sul torrente Ceronda nel Comune di Venaria Reale.
Nello specifico viene analizzato il ponte provvisorio in acciaio tipo Bailey e il ponte tecnologico
temporaneo piperack, entrambi previsti nel progetto in oggetto.

1.1 Ponte provvisorio in acciaio tipo Bailey


Lopera, classificabile ai sensi del DM2008 come ponte di prima categoria, a campata unica
caratterizzata da una lunghezza complessiva di 45.72m pari a 15 moduli da 304.8m e da un
ingombro fuoritutto di 564.4cm, una distanza tra le travate di 385.9cm e una carreggiata di
larghezza 368.1cm.
Il piano carrabile anchesso previsto in acciaio.
Sono previsti due ponti Bailey affiancati, uno per senso di marcia, posti alla distanza di 106.7cm
dallingombro fuoritutto e di 130 tra le travate.
E prevista la realizzazione di due spalle da demolire a fine lavori, uniche per i due ponti sulle
due sponde del fiume, il tutto su fondazioni indirette. Sono infatti previsti pali di fondazione di
diametro 1000mm.
La quota di pelo libero dellacqua TR10 di 253.50m, il che considerando un franco di 50cm,
porta a considerare come quota minima di intradosso del ponte a 254.00m. Infatti da progetto, si
posizionato lintradosso del ponte alla quota assoluta di 254.00m.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 3
Relazione illustrativa e di calcolo Progetto Definitivo

In relazione alle caratteristiche geomeccaniche del sito si fatto riferimento alla


caratterizzazione geotecnica dei materiali a cura del Dott.Ing.Geol. Giuseppe Massone.

1.1.1 Fasi costruttive


Lintervento in oggetto prevede innanzitutto la costruzione del ponte provvisorio in acciaio tipo
Bailey e la conseguente deviazione del traffico su tale ponte.
La fase di montaggio propedeutica alla realizzazione del ponte definitivo consiste nella
predisposizione dellarea per il montaggio e il varo del ponte con gli accessi necessari. Si
procede poi alla realizzazione delle opere di fondazione (pali e spalla) e al varo del ponte
provvisorio. Una volta completata la spalla provvisoria vengono realizzate le rampe e i raccordi
necessari per laccesso al ponte provvisorio.
Completato e collaudato il ponte definitivo viene rimosso il ponte provvisorio, demolite le
strutture di fondazione e ripristinate le aree.

1.2 Ponte tecnologico temporaneo piperack


Lopera a campata unica caratterizzata da una lunghezza complessiva di 50m e da un ingombro
di 150x200cm adibito alla posa di tubazioni in fase temporanea. La struttura prevista
interamente in acciaio ed costituita da due correnti inferiori L180x180x15, due correnti
superiori L200x200x16, un controvento inferiore e uno superiore L180x180x15 e due
controventi laterali, uno per lato, L80x80x8.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 4
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 5
Relazione illustrativa e di calcolo Progetto Definitivo

2 PONTE PROVVISORIO IN ACCIAIO TIPO BAILEY

2.1 Analisi dei carichi


Le azioni considerate nella progettazione del ponte stradale in oggetto sono:
le azioni permanenti (pesi propri degli elementi strutturali (g1), i sovraccarichi permanenti (g2)
e le spinte delle terre-spinte idrauliche (g3))
le azioni variabili da traffico
lazione longitudinale di frenamento o di accelerazione (q3)

2.1.1 Peso proprio


Il peso proprio del ponte provvisorio tipo Bailey stato valutato pari a 900kN.

2.1.2 Spinta delle terre e sovraccarico variabile a tergo della spalla


La spinta che la terra produce su un muro di contenimento strettamente legata alla
deformabilit di questultimo. Una struttura rigida, incapace di subire deformazioni anche di
piccola entit subir una pressione pari ai carichi verticali moltiplicati per il coefficiente di spinta
a riposo K0. Se essa invece in grado di ruotare, traslare o deformarsi, la pressione sar legata al
coefficiente di spinta attiva Ka.
Nel nostro caso per il calcolo del muro di spalla si andr a considerare la spinta a riposo.
Caratteristiche terreno:
rinterro a monte spalla con angolo di attrito assunto pari a 34:
K0 = 1-sin34=0.44; = 19 kN/m3
1 1
risultante spinta del terreno PA= k 0H 2 = 0.44 19 2.35 2 = 23.08kN / m
2 2
sovraccarico variabile a tergo del muro:
Secondo quanto esposto al punto C5.1.3.3.7.1 della circolare 2 febbraio 2009 n.617
al fine del calcolo delle spalle sul rilevato a tergo del muro si pu considerare
appplicato lo schema di carico 1, in cui per semplicit, i carichi tandem possono
essere sostituiti da carichi uniformemente distribuiti equivalenti, applicati su una
superficie rettangolare larga 3m e lunga 2.2m.
In un rilevato correttamente consolidato, si pu assumere una diffusione del carico
con angolo di 30.
Sulla base di ci, considerando tale diffusione a 30 le dimensioni della superficie di
carico che si registrano a met altezza del paraghiaia (cio a 2.35/2=1.175m) di:
(3+1.01x2)=5.02m
(2.2+1.01x2)=4.22m

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 6
Relazione illustrativa e di calcolo Progetto Definitivo

Risulta quindi che il sovraccarico variabile da considerare di


600/(5.02x4.22)=28.3kN/m2.
Da cui risulta che la spinta orizzontale dovuta a tale sovraccarico variabile pari a:
PQ= k 0 qH = 0.44 28 2.35 = 29.26kN / m

2.1.3 Variabili
Si fa riferimento al D.M. 14.01.08 norme tecniche, di cui si riporta una breve sintesi.

2.1.3.1 Definizione delle corsie convenzionali


Le larghezze wl delle corsie
convenzionali su una carreggiata ed il
massimo numero (intero) possibile di tali
corsie su di essa sono indicati nel
prospetto seguente (Fig. 5.1.1 e Tab.
5.1.I).

Se non diversamente specificato, qualora la carreggiata di un impalcato da ponte sia divisa in due parti
separate da una zona spartitraffico centrale, si distinguono i casi seguenti:
a) se le parti sono separate da una barriera di sicurezza fissa, ciascuna parte, incluse tutte le corsie di
emergenza e le banchine, autonomamente divisa in corsie convenzionali.
b) se le parti sono separate da barriere di sicurezza mobili o da altro dispositivo di ritenuta, lintera
carreggiata, inclusa la zona spartitraffico centrale, divisa in corsie convenzionali.

La disposizione e la numerazione delle corsie va determinata in modo da indurre le pi sfavorevoli


condizioni di progetto. Per ogni singola verifica il numero di corsie da considerare caricate, la loro
disposizione sulla carreggiata e la loro numerazione vanno scelte in modo che gli effetti della
disposizione dei carichi risultino i pi sfavorevoli. La corsia che, caricata, d leffetto pi sfavorevole
numerata come corsia Numero 1; la corsia che d il successivo effetto pi sfavorevole numerata come
corsia Numero 2, ecc.
Quando la carreggiata costituita da due parti separate portate da uno stesso impalcato, le corsie sono
numerate considerando lintera carreggiata, cosicch vi solo una corsia 1, solo una corsia 2 ecc, che
possono appartenere alternativamente ad una delle due parti.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 7
Relazione illustrativa e di calcolo Progetto Definitivo

Quando la carreggiata consiste di due parti separate portate da due impalcati indipendenti, per il progetto
di ciascun impalcato si adottano numerazioni indipendenti. Quando, invece, gli impalcati indipendenti
sono portati da una singola pila o da una singola spalla, per il progetto della pila o della spalla si adotta
ununica numerazione per le due parti.
Per ciascuna singola verifica e per ciascuna corsia convenzionale, si applicano gli Schemi di Carico
definiti nel seguito per una lunghezza e per una disposizione longitudinale, tali da ottenere leffetto pi
sfavorevole.

2.1.3.2 Schemi di Carico


Le azioni variabili del traffico, comprensive degli effetti dinamici, sono definite dai seguenti Schemi di
Carico:
Schema di Carico 1: costituito da carichi concentrati su due assi in tandem, applicati su impronte di
pneumatico di forma quadrata e lato 0,40 m, e da carichi uniformemente distribuiti come mostrato in Fig.
5.1.2. Questo schema da assumere a riferimento sia per le verifiche globali, sia per le verifiche locali,
considerando un solo carico tandem per corsia, disposto in asse alla corsia stessa. Il carico tandem, se
presente, va considerato per intero.
Schema di Carico 2: costituito da un singolo asse applicato su specifiche impronte di pneumatico di
forma rettangolare, di larghezza 0,60 m ed altezza 0,35 m. Questo schema va considerato autonomamente
con asse longitudinale nella posizione pi gravosa ed da assumere a riferimento solo per verifiche locali.
Qualora sia pi gravoso si considerer il peso di una singola ruota di 200 kN.
Schema di Carico 3: costituito da un carico isolato da 150kN con impronta quadrata di lato 0,40m. Si
utilizza per verifiche locali su marciapiedi non protetti da sicurvia.
Schema di Carico 4: costituito da un carico isolato da 10 kN con impronta quadrata di lato 0,10m. Si
utilizza per verifiche locali su marciapiedi protetti da sicurvia e sulle passerelle pedonali.
Schema di Carico 5: costituito dalla folla compatta, agente con intensit nominale, comprensiva degli
effetti dinamici, di 5 kN/m2. Il valore di combinazione invece di 2,5 kN/m2. Il carico folla deve essere
applicato su tutte le zone significative della superficie di influenza, inclusa larea dello spartitraffico
centrale, ove rilevante.

2.1.3.3 Categorie Stradali


Limpalcato viene considerato di 1a Categoria: ponti per il transito dei carichi mobili sopra indicati con il
loro intero valore.

2.1.3.4 Disposizione dei carichi mobili


Il numero delle colonne di carichi mobili da considerare nel calcolo dei ponti di 1a e 2a Categoria quello
massimo compatibile con la larghezza della carreggiata, comprese le eventuali banchine di rispetto e per

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 8
Relazione illustrativa e di calcolo Progetto Definitivo

sosta di emergenza, nonch gli eventuali marciapiedi non protetti e di altezza inferiore a 20 cm, tenuto
conto che la larghezza di ingombro convenzionale stabilita per ciascuna colonna in 3,00 m.

In ogni caso il numero delle colonne non deve essere inferiore a 2, a meno che la larghezza della sede
stradale sia inferiore a 5,40 m. La disposizione dei carichi ed il numero delle colonne sulla carreggiata
saranno volta per volta quelli che determinano le condizioni pi sfavorevoli di sollecitazione per la
struttura, membratura o sezione considerata. Per i ponti di 1a Categoria si devono considerare,
compatibilmente con le larghezze precedentemente definite, le seguenti intensit dei carichi:

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 9
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 10
Relazione illustrativa e di calcolo Progetto Definitivo

2.1.4 Azione longitudinale di frenamento o di accelerazione: q3


La forza di frenamento o di accelerazione q3 funzione del carico verticale totale agente sulla corsia
convenzionale n. 1 ed uguale a

180 kN q3 = 0,6(2Q1k ) + 0,10q1k wl L 900 kN


La forza, applicata a livello della pavimentazione ed agente lungo lasse della corsia, assunta
uniformemente distribuita sulla lunghezza caricata e include gli effetti di interazione.
Lazione frenante massima complessiva vale:

q3 = 0,6(2300) + 0,1093 45.72m=360+133.65 = 483kN


Lazione di frenamento agisce al livello della pavimentazione stradale.

2.2 Combinazioni di carico


Si adotta lapproccio 2, secondo cui si adotta una sola combinazione di gruppi di coefficienti parziali:
A1+M1+R3.
Le combinazioni di carico da considerare per la normativa vigente sono le seguenti.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 11
Relazione illustrativa e di calcolo Progetto Definitivo

Ai fini della determinazione dei valori caratteristici delle azioni dovute al traffico, si considerano, le
combinazioni riportate in Tab. 5.1.IV.

La Tab. 5.1.V fornisce i valori dei coefficienti parziali delle azioni da assumere nellanalisi per la
determinazione degli effetti delle azioni nelle verifiche agli stati limite ultimi.
I valori dei coefficienti 0j, 1j e 2j per le diverse categorie di azioni sono riportati nella Tab.5.1.VI
delle norme tecniche.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 12
Relazione illustrativa e di calcolo Progetto Definitivo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 13
Relazione illustrativa e di calcolo Progetto Definitivo

Il dimensionamento delle fondazioni verr fatto considerando la disposizione pi gravosa dei carichi.

In particolare le combinazioni pi gravose prese in considerazione per le fondazioni sono quelle di


massimo carico verticale (esempio per la verifica alla capacit portante delle fondazioni) associate alle
massime forze orizzontali (spinta della terra).

2.3 Analisi azioni sui pali di fondazione

2.3.1 Azione verticale sul palo


Si analizza nel seguito il carico verticale massimo agente sulle spalle del ponte provvisorio tipo
Bailey previsto (le sollecitazioni si riferiscono ad uno dei ponti previsti):
Peso proprio ponte Bailey: 900x1.35=1215kN
Carico tandem per corsia tot: 600x1.35=810kN
Carico distribuito per corsia: 9x3x1.35=36.45kN/m
La reazione verticale su una spalla quindi pari a:
Peso proprio ponte Bailey: 1215/2=607.5kN
Carico tandem per corsia tot: 810/2=405kN
Carico distribuito per corsia: 36.45x45.72/2=833.25kN
Totale: 1845.5kN (reazione verticale su una spalla relativa ad uno dei due ponti previsti)
Supponendo di disporre in tutto 4 pali 1000 sotto ogni spalla, risulta che lazione verticale
agente su ogni palo pari a:
Peso proprio spalla: 1.2x1.2x25x1.35=48.6kN/m
Massima larghezza di competenza del palo: 3.81m
Carico verticale su ogni palo: 1845.5/2+48.6x3.81=1108kN

2.3.2 Momento agente sul palo


Momento agente alla testa del palo dovuto alla spinta del terreno a tergo della spalla e al
sovraccarico variabile ivi presente:
M=23.08x0.78x1.35+29.26x1.175x1.35=70.72kNm/m
Massima larghezza di competenza del palo: 3.81m
M=70.72x3.81=269.4kNm/m
Momento dovuto allazione di frenatura:
M=483x1.55x1.35=1011kNm/ponte
Il momento massimo totale agente alla testa del palo pari a: 269.4+1011/2=774.9kNm
Va inoltre considerato il momento che si produce lungo al palo dovuto ad azioni agenti
ortogonali allasse del palo.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 14
Relazione illustrativa e di calcolo Progetto Definitivo

Nel caso di un palo flessibile, cio avente una lunghezza superiore alla lunghezza critica definita
2
E palo 7
come: l c = D il massimo momento prodotto dalla forza orizzontale H pari a
Gc (1 + 0.75 )
Hl l
M max = 0.1 c . Tale momento si produce in una sezione posta a c dalla testa del palo nel caso
4
di terreno omogeneo. Per quanto invece concerne la distribuzione dei momenti prodotti da una
coppia applicata in testa, si pu assumere una variazione lineare che si smorza in corrispondenza
di una sezione posta a una distanza pari alla lunghezza critica.
2 2
E palo 7 25 10 3
7
lc = D = 1 = 7.37 m
Gc (1 + 0.75 ) 20(1 + 0.75 0.2)
lc
G( z = )
Grado di eterogenit: = 4 =1
Gc
Forza orizzontale massima sul palo: H=23.08x1.35+29.26x1.35+483x1.35/2=396.68kN
Hl c 396.68 7.37
M max = 0.1 = 0 .1 = 292.35kNm
1

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 15
Relazione illustrativa e di calcolo Progetto Definitivo

2.4 Verifica capacit portante palo

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 16
Relazione illustrativa e di calcolo Progetto Definitivo

Carico verticale massimo sul palo: 1108kN


Capacit portante a compressione del palo 1000mm L=13m: 1266kN
La verifica risulta soddisfatta.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 17
Relazione illustrativa e di calcolo Progetto Definitivo

2.4.1 Verifica strutturale palo D1000mm

DATI GENERALI DELLA SEZIONE

Calcestruzzo: Rck = 30.00 N/mmq

Sezione circolare. Raggio = 50.00 cm

Acciaio: fyk = 450.00 N/mmq

Ferro N. X (cm) Y (cm) Area (cmq)


1 50.0 94.0 3.14
2 69.1 89.6 3.14
3 84.4 77.4 3.14
4 92.9 59.8 3.14
5 92.9 40.2 3.14
6 84.4 22.6 3.14
7 69.1 10.4 3.14
8 50.0 6.0 3.14
9 30.9 10.4 3.14
10 15.6 22.6 3.14
11 7.1 40.2 3.14
12 7.1 59.8 3.14
13 15.6 77.4 3.14
14 30.9 89.6 3.14

Caratteristiche limite della sezione:


Nu [kN] Mxu [kN m] Myu [kN m]
Sezione completamente tesa -1721.0 0.0 0.0
Sezione completamente compressa 12815.8 0.0 0.0
Fibre inferiori tese 0.0 684.2 0.0
Fibre superiori tese 0.0 -684.2 0.0
Fibre di sinistra tese 0.0 0.0 687.5
Fibre di destra tese 0.0 0.0 -687.5

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 18
Relazione illustrativa e di calcolo Progetto Definitivo

VERIFICA AGLI STATI LIMITE ULTIMI

Note sulle unit di misura:


Sollecitazioni: M [kN m], N [kN]
Coef. sicurezza: Gamma

Soll.n. Nd Mxd Myd Nu Mxu Myu EpsC EpsA Gamma


1 1108.0 774.9 0.0 1108.0 1038.9 0.0 -0.35 0.89 1.34 Ok
2 1156.5 292.4 0.0 1156.5 1050.6 0.0 -0.35 0.87 3.59 Ok

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 19
Relazione illustrativa e di calcolo Progetto Definitivo

3 PONTE TECNOLOGICO TEMPORANEO PIPERACK

3.1 Analisi dei carichi


Le azioni considerate nella progettazione del ponte tecnologico in oggetto sono:
peso proprio: viene valutato in automatico nel modello di calcolo tenendo conto delle diverse
sezioni
Peso specifico utilizzato per lacciaio.: acc=78.5kN/m3
carico permanente distribuito: 2kN/m

3.2 Modellazione agli elementi finiti (FEM)

3.2.1 Caratteristiche programma di calcolo


Il programma impiegato nella modellazione il PROSAP vers. 2010-10-153 che implementa i
calcoli e le verifiche secondo il DM2008. Il programma costituisce linterfaccia input ed output
del solutore ALGOR16. La verifica della sicurezza degli elementi strutturali avviene con i
metodi della scienza delle costruzioni. Lanalisi strutturale condotta con il metodo degli
spostamenti per la valutazione dello stato tensodeformativo indotto da carichi statici. Lanalisi
strutturale viene effettuata con il metodo degli elementi finiti. Il metodo sopraindicato si basa
sulla schematizzazione della struttura in elementi connessi solo in corrispondenza di un numero
prefissato di punti denominati nodi. I nodi sono definiti dalle tre coordinate cartesiane in un
sistema di riferimento globale. Lanalisi strutturale condotta con il metodo dellanalisi modale
e dello spettro di risposta in termini di accelerazione per la valutazione dello stato
tensodeformativo indotto da carichi dinamici. Le incognite del problema (nellambito del metodo
degli spostamenti) sono le componenti di spostamento dei nodi riferite al sistema di riferimento
globale (traslazioni secondo X, Y, Z, rotazioni attorno X, Y, Z). La soluzione del problema si
ottiene con un sistema di equazioni algebriche lineari i cui termini noti sono costituiti dai carichi
agenti sulla struttura opportunamente concentrati ai nodi:
K * u = F dove K = matrice di rigidezza; u = vettore spostamenti nodali; F = vettore forze nodali
Dagli spostamenti ottenuti con la risoluzione del sistema vengono quindi dedotte le sollecitazioni
e/o le tensioni di ogni elemento, riferite generalmente ad una terna locale allelemento stesso. Il
sistema di riferimento utilizzato costituito da una terna cartesiana destrorsa XYZ. Si assume
lasse Z verticale ed orientato verso l'alto.
Gli elementi per la modellazione dello schema statico della struttura sono i seguenti:
Elemento tipo TRUSS (biella) Elemento tipo BEAM (trave)
Elemento tipo MEMBRANE (membrana) Elemento tipo PLATE (piastra-guscio)
Elemento tipo BOUNDARY (molla) Elemento tipo STIFFNESS(matrice di rigidezza)

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 20
Relazione illustrativa e di calcolo Progetto Definitivo

Vista 3D Modello FEM

Vista 3D Modello FEM

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 21
Relazione illustrativa e di calcolo Progetto Definitivo

3.3 Casi di carico


CDC Tipo Sigla Id
1 Ggk CDC=Ggk (peso proprio della struttura)
2 Gk CDC=G1k (permanente generico )

3.4 Combinazioni di carico


Le combinazioni di carico da considerare per la normativa vigente DM 2008 sono le seguenti.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 22
Relazione illustrativa e di calcolo Progetto Definitivo

3.5 Verifiche allo SLU

Sfruttamento %

Resistenza: fyd=355/1.05=338N/mm2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 23
Relazione illustrativa e di calcolo Progetto Definitivo

Snellezze 3-3

Snellezze 2-2

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 24
Relazione illustrativa e di calcolo Progetto Definitivo

3.6 Verifica degli appoggi

Su ogni sponda del fiume prevista la realizzazione di una fondazione 80x80cm su 4 micropali
della lunghezza di 13m adibiti a portare gli scarichi del ponte tecnologico provvisorio. La
massima reazione su ogni sponda in combinazione SLU pari a 286kN, il che significa 71.5kN
per ogni micropalo.

Accessibilit da Nord alla Reggia di Venaria Reale e nuovo ponte sul Torrente Ceronda 25

Вам также может понравиться