RESUMEN VALORIZACION No. 02 - 1 QUINCENA AGOSTO 2012


ADJUDICACION DIRECTA SELECTIVA N 06-2012-MDCN-T
OBRA: CONSTRUCCION Y EQUIPAMIENTO DEL LOCAL MULTIUSO EN EL COMIT 12 DE LA ASOCACION DE VIVIENDA 28 DE AGOSTO DEL DISTRITO DE CIUDAD NUEVA - TACNA - TACNA
ENTIDAD: MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA
CONTRATISTA: EDIFICACIONES DRYWALL S.A.C.
SUPERVISION: MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA
FECHA VALOR REFERENCIAL: MARZO 2012

MONTO ACUMULADO EN EL PRESENTE ACUMULADO SALDO


ITEM D E S C R I P C I O N CONTRATADO ANTERIOR MES ACTUAL POR VALORIZAR AVANCE
S/. S/. S/. S/. S/.

ITEM DESCRIPCION PARCIAL (S/)


1 ESTRUCTURAS 146,471.06 58,528.98 38,076.19 96,605.16 49,865.90 65.96%
2 ARQUITECTURA 154,555.51 9,509.76 0.00 9,509.76 145,045.75 6.15%
3 INSTALACIONES SANITARIAS 16,190.75 0.00 1,895.21 1,895.21 14,295.54 11.71%
4 INSTALACIONES ELECTRICAS 18,647.53 0.00 1,094.31 1,094.31 17,553.22 5.87%
5 EQUIPAMIENTO Y MOBILIARIO 46,775.00 0.00 0.00 0.00 46,775.00 0
COSTO DIRECTO 382,639.85 68,038.74 41,065.71 109,104.44 273,535.41 28.51%
GASTOS GENERALES 10% 38,263.99 6,803.87 4,106.57 10,910.44 27,353.54
UTILIDAD 10% 38,263.99 6,803.87 4,106.57 10,910.44 27,353.54
COSTO PARCIAL 459,167.82 81,646.48 49,278.85 130,925.33 328,242.49
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000
SUB-TOTAL 459,167.82 81,646.48 49,278.85 130,925.33 328,242.49
I.G.V 18% 82,650.21 14,696.37 8,870.19 23,566.56 59,083.65
TOTAL PRESUPUESTO 541,818.04 96,342.85 58,149.05 154,491.89 387,326.13 28.51%
146,471.06
154,555.51
16,190.75
18,647.53
46,775.00
382,639.85

541,818.03
R.U.C. N 20477865845

VALORIZACION N 02 - 1 QUINCENA - AGOSTO 2012


AMORTIZACION DEL ADELANTO EN EFECTIVO
Al 31 de Enero del 2009

C= Monto restante por valorizar (Antes de esta valorizacion) = 6,045,824.03


A= Adelanto en efectivo = 1,403,213.17
Ab = Amortizacion del adelanto en efectivo = 11,437.44
Po = Monto de la valorizacion correspondiente al mes = 49,278.85
Pr = Monto a valorizar = 37,841.41

1.- AMORTIZACION DEL ADELANTO EN EFECTIVO DIRECTO OTORGADO PARA EL MES( Ab )

Ab = (A / C) * Po

1,403,213.17
Ab = ----------------------------------- * 49,278.85 = 11,437.44
6,045,824.03

Ab = 11,437.44

2.- MONTO A VALORIZAR

Pr = Po - Ab
Pr = 49,278.85 - 11,437.44 = 37,841.41
Pr = 37,841.41

3.- CONTROL DE LA AMORTIZACION DEL ADELANTO EN EFECTIVO

DESCRIPCION SIN IGV IGV TOTAL INC. IGV

CONTRATO 7,016,065.87 1,333,052.52 8,349,118.38


ADELANTO EN EFECTIVO 1,403,213.17 266,610.50 1,669,823.68

VAL N MES MENSUAL

1 12/30/2008 0.00
2 12/31/2009 11,437.44
3
4
5

Total Amortizacion 11,437.44


Saldo Adelanto (SIN IGV) 1,391,775.74
CONTRATISTAS GENERALES

VALORIZACION N 02 - 1 QUINCENA - AGOSTO 2012

ADJUDICACION DIRECTA SELECTIVA N 06-2012-MDCN-T


OBRA: : CONSTRUCCION Y EQUIPAMIENTO DEL LOCAL MULTIUSO EN EL COMIT 12 DE LA ASOCIACION DE VIVIENDA 28 DE AGOSTO - CIUDAD NUEVA - TACNA
ENTIDAD: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA
CONTRATISTA: : EDIFICACIONES DRYWALL SAC
SUPERVISION: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA
FECHA VALOR REFERENCIAL: MARZO 2012

PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
146,471.06 0.00 58,528.98 0.00 38,076.19 0.00 96,605.16 66% 0.00 49,865.90
01 OBRAS PROVISIONALES 5,295.78 4,872.05 0.00 4,872.05 92% 423.73
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 2.40x3.60M. und 1.00 586.67 586.67 1.00 586.67 1.00 586.67 100% 0.00 0.00
01.02 CASETA DE GUARDIANIA, ALMACEN Y OFICINA PARA RESIDENCIA m2 50.00 66.02 3,301.00 50.00 3,301.00 50.00 3,301.00 100% 0.00 0.00
01.03 CERCO PROVISIONAL DE ESTERAS m 45.25 12.39 560.65 45.25 560.65 45.25 560.65 100% 0.00 0.00
01.04 TRANSPORTE DE EQUIPOS Y MATERIALES glb 1.00 847.46 847.46 0.50 423.73 0.50 423.73 50% 0.50 423.73
02 TRABAJOS PRELIMINARES 365.62 286.71 0.00 0.00 286.71 78% 0.00 78.91
02.01 LIMPIEZA DEL TERRENO MANUAL m2 156.25 0.32 50.00 156.25 50.00 156.25 50.00 100% 0.00 0.00
02.02 TRAZO, NIVELES Y REPLANTEO m2 156.25 1.01 157.81 156.25 157.81 156.25 157.81 100% 0.00 0.00
02.03 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m2 156.25 1.01 157.81 78.12 78.90 78.12 78.90 50% 78.13 78.91
03 MOVIMIENTO DE TIERRAS 10,258.74 8,971.64 409.01 0.00 9,380.65 91% 0.00 878.09
03.01 EXCAVACION DE ZANJAS P/CIMIENTOS CORRIDOS, VIGAS DE CIMENTACION Y ZAPATAS m3 137.87 30.56 4,213.31 137.87 4,213.31 137.87 4,213.31 100% 0.00 0.00
03.02 NIVELACION INTERIOR Y APISONADO MANUAL P/CIMIENTOS m2 69.15 2.40 165.96 69.15 165.96 69.15 165.96 100% 0.00 0.00
03.03 RELLENO COMPACTADO C/EQUIPO MATERIAL PROPIO m3 41.80 21.91 915.84 41.80 915.84 41.80 915.84 100% 0.00 0.00
03.04 NIVELACION Y APISONADO P/FALSO PISO C/COMPACTADORA MANUAL m2 128.75 3.66 471.23 17.00 62.22 111.75 409.01 128.75 471.23 100% 0.00 0.00
03.05 ACARREO DE MATERIAL EXCEDENTE m3 124.89 16.46 2,055.69 124.89 2,055.69 124.89 2,055.69 100% 0.00
03.06 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQ. m3 124.89 12.48 1,558.63 124.89 1,558.63 124.89 1,558.63 100% 0.00
03.07 TERRAPLEN P/PISOS E=0.10m. m2 128.75 6.82 878.08 0.00 0.00 0.00 0.00 0.00 0% 128.75 878.08
04 CONCRETO SIMPLE 12,527.89 9,258.93 0.00 0.00 9,258.93 74% 0.00 3,268.96
04.01 CONCRETO P/SOLADOS C:H 1:12 m3 21.74 150.62 3,274.48 21.74 3,274.48 0.00 21.74 3,274.48 100% 0.00 0.00
04.02 CIMIENTO CORRIDO 1:10+30% P.G. FC=100KG/CM2 m3 26.19 145.58 3,812.74 26.19 3,812.74 0.00 26.19 3,812.74 100% 0.00 0.00
04.03 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 48.05 29.70 1,427.09 48.05 1,427.09 0.00 48.05 1,427.09 100% 0.00 0.00
04.04 CONCRETO 1:8 + 25% P.M. PARA SOBRECIMIENTOS m3 3.60 206.84 744.62 3.60 744.62 0.00 3.60 744.62 100% 0.00 0.00
04.05 FALSO PISO MEZCLA 1:8 E=4 ACABADO FROTACHADO m2 128.75 25.39 3,268.96 0.00 0.00 0.00 0.00 0% 128.75 3,268.96
05 CONCRETO ARMADO 118,023.03 0.00 35,139.64 0.00 37,667.18 0.00 72,806.83 62% 0.00 45,216.20
05.01 ZAPATAS 7,017.93 7,017.94 0.00 0.00 7,017.93 100% 0.00 0.00
05.01.01 ZAPATAS CONCRETO fc = 210 kg/cm2 m3 17.78 288.16 5,123.48 17.78 5,123.48 0.00 17.78 5,123.48 100% 0.00 0.00
05.01.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 425.72 4.45 1,894.45 425.72 1,894.45 0.00 425.72 1,894.45 100% 0.00 0.00
05.02 VIGA DE CIMENTACION 8,628.60 8,628.60 0.00 0.00 8,628.60 100% 0.00 0.00
05.02.01 VIGAS DE CIMENTACION fc = 210 kg/cm2 m3 9.49 301.06 2,857.06 9.49 2,857.06 0.00 9.49 2,857.06 100% 0.00 0.00
05.02.02 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION m2 63.27 28.51 1,803.83 63.27 1,803.83 0.00 63.27 1,803.83 100% 0.00 0.00
05.02.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 891.62 4.45 3,967.71 891.62 3,967.71 0.00 891.62 3,967.71 100% 0.00 0.00
05.03 SOBRECIMIENTO ARMADO 4,238.12 4,238.11 0.00 0.00 4,238.11 100% 0.00 0.00
05.03.01 SOBRECIMIENTO ARMADO fc = 210 kg/cm2 m3 4.92 301.06 1,481.22 4.92 1,481.22 0.00 4.92 1,481.22 100% 0.00 0.00
05.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO ARMADO m2 65.56 28.51 1,869.12 65.56 1,869.12 0.00 65.56 1,869.12 100% 0.00 0.00
05.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 199.50 4.45 887.78 199.50 887.78 0.00 199.50 887.78 100% 0.00 0.00
05.04 COLUMNAS 26,502.86 13,437.13 5,877.97 0.00 19,315.10 73% 0.00 0.00
05.04.01 CONCRETO fc = 210 kg/cm2 P/COLUMNAS m3 15.54 353.51 5,493.55 3.97 1,403.43 8.02 2,834.00 11.99 4,237.44 77% 3.55 1,256.11
05.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 231.83 36.47 8,454.84 36.48 1,330.43 83.47 3,043.97 119.95 4,374.39 52% 111.89 4,080.45
05.04.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,821.23 4.45 12,554.47 2,405.23 10,703.27 0.00 2,405.23 10,703.27 85% 416.00 1,851.20
05.05 PLACAS 4,057.14 1,817.87 1,380.37 0.00 3,198.24 79% 0.00 0.00
05.05.01 CONCRETO fc = 210 kg/cm2 P/PLACAS m3 2.19 351.83 770.51 0.00 1.35 474.97 1.35 474.97 62% 0.84 295.54
PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS m2 29.20 50.30 1,468.76 0.00 18.00 905.40 18.00 905.40 62% 11.20 563.36
05.05.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 408.51 4.45 1,817.87 408.51 1,817.87 0.00 408.51 1,817.87 100% 0.00 0.00
05.06 VIGAS 28,565.64 0.00 0.00 13,296.40 0.00 13,296.40 47% 0.00 0.00
05.06.01 CONCRETO fc = 210 kg/cm2 P/VIGAS m3 24.84 321.50 7,986.06 0.00 11.14 3,580.87 11.14 3,580.87 45% 13.70 4,405.19
05.06.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 199.85 32.22 6,439.17 0.00 82.19 2,648.00 82.19 2,648.00 41% 117.67 3,791.17
05.06.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 3,177.62 4.45 14,140.41 0.00 1,588.21 7,067.53 1,588.21 7,067.53 50% 1,589.41 7,072.87
05.07 LOSAS ALIGERADAS 30,552.11 0.00 14,802.20 0.00 11,762.28 38% 0.00 0.00
05.07.01 CONCRETO fc = 210 kg/cm2 P/LOSAS ALIGERADAS m3 22.57 326.75 7,374.75 0.00 10.80 3,529.23 10.80 3,529.23 48% 11.77 3,845.52
05.07.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS m2 257.93 32.48 8,377.57 0.00 123.44 4,009.33 123.44 4,009.33 48% 134.49 4,368.24
05.07.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,898.31 4.45 8,447.48 0.00 949.15 4,223.72 949.15 4,223.72 50% 949.16 4,223.76
05.07.04 LADRILLO HUECO DE ARCILLA 15X30X30 cm. P/LOSA ALIGERADA und 2,146.05 2.96 6,352.31 0.00 1,027.00 3,039.92 1,027.00 2,310.24 36% 1,119.05 3,312.39
05.08 ESCALERAS 4,620.74 0.00 2,310.25 0.00 0.00 0% 0.00 0.00
05.08.01 CONCRETO fc = 210 kg/cm2 P/ESCALERAS m3 4.98 324.98 1,618.40 0.00 2.49 809.04 2.49 809.04 50% 2.49 809.36
05.08.02 ENCOFRADO Y DESENCOFRADO DE ESCALERA m2 27.35 38.57 1,054.89 0.00 13.68 527.48 13.68 527.48 50% 13.67 527.41
05.08.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 437.63 4.45 1,947.45 0.00 218.81 973.72 218.81 973.72 50% 218.82 973.73
05.09 MESON DE CONCRETO 855.87 0.00 0.00 0.00 0.00 0% 0.00 0.00
05.09.01 CONCRETO fc = 210 kg/cm2 P/MESA DE CONCRETO m3 0.95 294.56 279.83 0.00 0.00 0.00 0.00 0% 0.95 279.83
05.09.02 ENCOFRADO Y DESENCOFRADO EN MESON DE CONCRETO m2 9.86 32.48 320.25 0.00 0.00 0.00 0.00 0% 9.86 320.25
05.09.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 57.48 4.45 255.79 0.00 0.00 0.00 0.00 0% 57.48 255.79
05.10 PESTAA DE CONCRETO 2,984.02 0.00 0.00 0.00 0.00 0% 0.00 0.00
05.10.01 CONCRETO fc = 210 kg/cm2 P/PESTAA DE CONCRETO m3 1.68 319.67 537.05 0.00 0.00 0.00 0.00 0% 1.68 537.05
05.10.02 ENCOFRADO Y DESENCOFRADO EN PESTAA DE CONCRETO m2 37.01 32.48 1,202.08 0.00 0.00 0.00 0.00 0% 37.01 1,202.08
05.10.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 279.75 4.45 1,244.89 0.00 0.00 0.00 0.00 0% 279.75 1,244.89
COSTO DIRECTO 146,471.06 0.00 58,528.98 0.00 38,076.19 0.00 96,605.16 0.00 49,865.90
GASTOS GENERALES (10%) 14,647.11 0.00 5,852.90 3,807.62 9,660.52 4,986.60
UTILIDAD ( 10%) 14,647.11 0.00 5,852.90 3,807.62 9,660.52 4,986.60
------------------- ------------------- ------------------- -------------------
COSTO PARCIAL 175,765.28 0.00 70,234.78 45,691.44 115,926.21 59,839.10
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000 1.00000
SUB TOTAL 175,765.28 0.00 70,234.78 45,691.44 115,926.21 59,839.10
IGV (18%) 31,637.75 0.00 12,642.26 8,224.46 20,866.72 10,771.04
=============== =============== =============== ============
TOTAL 207,403.03 0.00 82,877.04 53,915.90 136,792.93 70,610.14
R.U.C. N 20520092197

VALORIZACION N 02 - 1 QUINCENA - AGOSTO 2012


ARQUITECTURA

ADJUDICACION DIRECTA SELECTIVA N 06-2012-MDCN-T


OBRA: : CONSTRUCCION Y EQUIPAMIENTO DEL LOCAL MULTIUSO EN EL COMIT 12 DE LA ASOCIACION DE VIVIENDA 28 DE AGOSTO - CIUDAD NUEVA - TACNA
ENTIDAD: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA
CONTRATI: EDIFICACIONES DRYWALL SAC
SUPERVIS : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA

PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
06 MUROS Y TABIQUES 18,640.78 0.00 9,509.76 51.02% 9,131.02
06.01 MURO DE LADRILLO DE ARCILLA 24x14x10cm. DE SOGA m2 327.31 55.26 18,087.15 167.14 9,236.16 0.00 167.14 9,236.16 51.06% 160.17 8,850.99
06.02 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS kg 161.88 3.42 553.63 80.00 273.60 0.00 80.00 273.60 49.42% 81.88 280.03
07 REVOQUES, ENLUCIDOS Y MOLDURAS 35,999.18 0.00 35,999.18
07.01 TARRAJEO RAYADO O PRIMARIO m2 77.29 23.98 1,853.41 77.29 1,853.41
07.02 TARRAJEO EN MURO INTERIOR Y EXTERIOR 1:5 m2 594.18 21.15 12,566.91 594.18 12,566.91
07.03 TARRAJEO EN VIGAS Y COLUMNAS 1:4 m2 385.90 24.02 9,269.32 385.90 9,269.32
07.04 VESTIDURA DE DERRAMES ANCHO 15CM. m 276.26 17.51 4,837.31 276.26 4,837.31
07.05 CIELO RASO CON MEZCLA C:A 1:5 m2 257.93 28.97 7,472.23 257.93 7,472.23
08 PISOS Y PAVIMENTOS 28,127.26 0.00 28,127.26
08.01 PISO DE CERAMICO 40x00cm. ANTIDESLIZANTE m2 296.24 58.05 17,196.73 296.24 17,196.73
08.02 CONTRAPISO DE 48MM m2 306.74 31.53 9,671.51 306.74 9,671.51
08.03 CANTONERA ESTRIADA DE ALUMINIO DE 6"x3/16" P/ESCALERA m 45.60 27.61 1,259.02 45.60 1,259.02
09 CONTRAZOCALOS 0.00 0.00 5,503.54
09.01 CONTRAZOCALO DE CERAMICA DE H=0.10M. m 159.20 34.57 5,503.54 159.20 5,503.54
10 ZOCALOS 0.00 0.00 4,078.59
10.01 ZOCALO DE CERAMICA 20x30cm. m2 77.29 52.77 4,078.59 77.29 4,078.59
11 CARPINTERIA DE MADERA 13,441.16 0.00 13,441.16
11.01 PUERTA DE MADERA CEDRO TIPO TABLERO m2 32.38 258.47 8,369.26 32.38 8,369.26
11.02 TABIQUERIA DE ALUMINIO C/MELAMINE 18MM m2 11.16 127.12 1,418.66 11.16 1,418.66
11.03 REPOSTERO DE MADERA CEDRO und 4.00 913.31 3,653.24 4.00 3,653.24
12 CARPINTERIA METALICA 17,621.44 0.00 17,621.44
12.01 PUERTA ENRROLLABLE und 1.00 1,506.53 1,506.53 1.00 1,506.53
12.02 COBERTURA METALICA TIPO 1 C/POLICARBONATO ALVEOLAR DE 6MM INC/INSTALACION m2 50.78 175.46 8,909.86 50.78 8,909.86
12.03 COBERTURA METALICA TIPO 2 C/POLICARBONATO ALVEOLAR DE 6MM INC/INSTALACION m2 5.88 148.31 872.06 5.88 872.06
12.04 BARANDA DE FG 1 1/2" PARA ESCALERA m 14.50 115.49 1,674.61 14.50 1,674.61
12.05 BARANDA DE FG 1 1/2" EN BALCON m 29.80 81.59 2,431.38 29.80 2,431.38
12.06 BARANDA DE FG 1 1/2" PARA AZOTEA m 22.60 98.54 2,227.00 22.60 2,227.00
13 CUBIERTAS 755.21 0.00 755.21
13.01 COBERTURA DE LADRILLO PASTELERO ASENTADO C/MEZCLA m2 16.50 41.12 678.48 16.50 678.48
13.02 IMPERMEABILIZACION DE COBERTURA DE LADRILLO PASTELERO m2 16.50 4.65 76.73 16.50 76.73
14 CERRAJERIA 1,159.74 0.00 1,159.74
14.01 CERRADURA TIPO PARCHE 03 GOLPES und 3.00 68.66 205.98 3.00 205.98
14.02 CERRADURA TIPO PERILLA und 12.00 46.09 553.08 12.00 553.08
14.03 BISAGRAS ALUMINIZADA DE 4"x4" pza 42.00 9.54 400.68 42.00 400.68
15 VIDRIOS, CRISTALES Y SIMILARES 15,772.96 0.00 15,772.96
15.01 VENTANA TIPO SISTEMA INC. COLOCACION m2 83.00 156.78 13,012.74 83.00 13,012.74
15.02 MAMPARA TIPO SISTEMA C/MARCO DE ALUMINIO INC. COLOCACION m2 13.86 199.15 2,760.22 13.86 2,760.22
16 PINTURAS 13,455.65 0.00 13,455.65
16.01 PINTURA LATEX SATINADO MURO INTERIOR Y EXTERIOR m2 594.18 9.22 5,478.34 594.18 5,478.34
16.02 PINTURA LATEX SATINADO COLUMNAS Y VIGAS m2 385.90 10.48 4,044.23 385.90 4,044.23
16.03 PINTURA LATEX SATINADO CIELORASO m2 257.93 11.12 2,868.18 257.93 2,868.18
16.04 PINTURA LACA PIROXILINA 2 MANOS EN PUERTAS Y VENTANAS m2 64.76 15.35 994.07 64.76 994.07
PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
16.05 PINTURA ANTICORR. Y ESMALTE 2 MANOS EN PUERTA METALICA m2 6.72 10.54 70.83 6.72 70.83
COSTO DIRECTO 154,555.51 9,509.76 0.00 9,509.76 145,045.76
GASTOS GENERALES (10%) 15,455.55 0.00 950.98 0.00 0.00 0.00 950.98 0.00 0.00 14,504.58
UTILIDAD ( 10%) 15,455.55 0.00 950.98 0.00 0.00 0.00 950.98 0.00 0.00 14,504.58
----------------- ----------------- ----------------- -----------------
COSTO PARCIAL 185,466.61 0.00 11,411.72 0.00 0.00 0.00 11,411.72 0.00 0.00 174,054.92
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000
SUB TOTAL 185466.61 0 11411.72 0 0 0 11411.72 0 0 174054.92
IGV (18%) 33383.99 0 2054.11 0 0.00 0.00 2054.11 0.00 0.00 31329.89
----------------- ----------------- ----------------- -----------------
218850.60 0.00 13465.83 0.00 0.00 0.00 13465.83 0.00 0.00 205384.81
TOTAL
18,640.78
154,555.51

218850.64
R.U.C. N 20520092197

VALORIZACION N 02 - 1 QUINCENA - AGOSTO 2012


INSTALACIONES SANITARIAS

ADJUDICACION DIRECTA SELECTIVA N 06-2012-MDCN-T


OBRA: : CONSTRUCCION Y EQUIPAMIENTO DEL LOCAL MULTIUSO EN EL COMIT 12 DE LA ASOCIACION DE VIVIENDA 28 DE AGOSTO - CIUDAD NUEVA - TACNA
ENTIDAD: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA
CONTRATISTA: : EDIFICACIONES DRYWALL SAC
SUPERVISION: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA

PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
0 17 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 5,203.45 0 5,203.45 5,203.45
0 17.01 TRABAJOS PRELIMINARES 9.04 0.00 0.00 9.04 9.04
0 17.01.01 TRAZO Y REPLANTEO C/EQUIPO m2 7.86 1.15 9.04 0 0 7.86 9.04 9.04
0 17.02 MOVIMIENTO DE TIERRAS 421.13 0 0.00 421.13 421.13
0 17.02.01 EXCAVACION DE ZANJA PARA RED DE AGUA FRIA m3 4.19 27.26 114.22 4.19 114.22 114.22
0 17.02.02 REFINE Y NIVELACION DE ZANJAS m 26.20 3.40 89.08 26.20 89.08 89.08
0 17.02.03 COLOCACION DE CAMA Y SOBRECAMA PARA RED DE AGUA FRIA m 26.20 3.60 94.32 26.20 94.32 94.32
0 17.02.04 RELLENO COMPACTADO C/EQUIPO MATERIAL PROPIO m3 3.14 23.02 72.28 3.14 72.28 72.28
0 17.02.05 ACARREO DE MATERIAL EXCEDENTE m3 1.36 16.46 22.39 1.36 22.39 22.39
0 17.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1.36 21.21 28.85 1.36 28.85 28.85
0 17.03 RED DE AGUA FRIA 4,773.27 4773.27 4,773.27
0 17.03.01 TUBERIA PVC CLASE A-10/AGUA POTABLE DE 3/4" m 48.30 12.00 579.60 48.30 579.60 579.60
0 17.03.02 TUBERIA PVC CLASE A-10/AGUA POTABLE DE 1/2" m 34.60 11.06 382.68 34.60 382.68 382.68
0 17.03.03 SALIDA DE AGUA FRIA C/TUBERIA PVC SAP 1/2" pto 18.00 83.72 1,506.96 0 0 0 0.00% 18.00 1506.96 1,506.96
0 17.03.04 VALVULA COMPUERTA DE BRONCE DE 3/4" und 4.00 78.95 315.80 0 0 0 0.00% 4.00 315.80 315.80
0 17.03.05 VALVULA COMPUERTA DE BRONCE DE 1/2" und 4.00 73.86 295.44 0 0 0 0.00% 4.00 295.44 295.44
0 17.03.06 VALVULA CHECK DE BRONCE DE 3/4" und 2.00 74.64 149.28 0 0 0 0.00% 2.00 149.28 149.28
0 17.03.07 TEE PVC SAP 3/4" und 4.00 20.04 80.16 0 0 0 0.00% 4.00 80.16 80.16
0 17.03.08 TEE PVC SAP 1/2" und 13.00 19.61 254.93 0 0 0 0.00% 13.00 254.93 254.93
0 17.03.09 CODO PVC SAP 3/4"x90 und 16.00 20.89 334.24 0 0 0 0.00% 16.00 334.24 334.24
0 17.03.10 CODO PVC SAP 1/2"x90 und 12.00 19.61 235.32 0.00% 12.00 235.32 235.32
0 17.03.11 REDUCCION DE PVC SAP C/R 3/4" A 1/2" C-10 und 5.00 24.25 121.25 0 0 0 0.00% 5.00 121.25 121.25
0 17.03.12 PRUEBA HIDRAULICA EN REDES DE AGUA glb 1.00 517.61 517.61 0 0 0 0.00% 1.00 517.61 517.61
0 18 SISTEMA DE DESAGUE 10,987.30 1895.211 0 1895.211 17.25% 0.00 9092.10 10,987.31
0 18.01 TRABAJOS PRELIMINARES 15.71 0 0 0 0.00% 0.00 15.71 15.71
0 18.01.01 TRAZO Y REPLANTEO C/EQUIPO m2 13.66 1.15 15.71 0 0 0 0.00% 13.66 15.71 15.71
0 18.02 MOVIMIENTO DE TIERRAS 580.67 0 0 0 0.00% 0.00 580.67 580.67
0 18.02.01 EXCAVACION DE ZANJA PARA RED DE DESAGUE m3 4.82 27.26 131.39 0.00% 4.82 131.39 131.39
0 18.02.02 REFINE Y NIVELACION DE ZANJAS m 34.45 3.40 117.13 0 0 0 0.00% 34.45 117.13 117.13
0 18.02.03 COLOCACION DE CAMA Y SOBRECAMA PARA RED DE DESAGUE m 34.45 3.60 124.02 0 0 0 0.00% 34.45 124.02 124.02
0 18.02.04 RELLENO COMPACTADO C/EQUIPO MATERIAL PROPIO m3 2.07 23.02 47.65 0 0 0 0.00% 2.07 47.65 47.65
0 18.02.05 ACARREO DE MATERIAL EXCEDENTE m3 4.26 16.46 70.12 0 0 0 0.00% 4.26 70.12 70.12
0 18.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 4.26 21.21 90.35 0 0 0 0.00% 4.26 90.35 90.35
0 18.03 RED DE DESAGUE 4,726.79 1895.21 0 0 0.00% 0.00 2831.58 2,831.58
0 18.03.01 SALIDA DESAGUE DE PVC-SAL 4" pto 6.00 60.89 365.34 3.00 182.67 3 182.67 50.00% 3.00 182.67 365.34
0 18.03.02 SALIDA DESAGUE DE PVC-SAL 2" pto 10.00 57.08 570.80 4.00 228.32 4 228.32 40.00% 6.00 342.48 570.80
0 18.03.03 CAJ DE REGISTRO 12" x 24" C/TAPA DE CONCRETO und 3.00 96.76 290.28 0 0 0 0.00% 3.00 290.28 290.28
0 18.03.04 TUBERIA PVC SAL P/DESAGUE 2" m 84.30 18.38 1,549.43 42.15 774.717 42.15 774.717 50.00% 42.15 11,793.50 12,568.21
0 18.03.05 TUBERIA PVC SAL P/DESAGUE 4" m 38.15 9.20 350.98 19.07 175.444 19.07 175.444 49.99% 19.08 175.536 350.98
0 18.03.06 SUMIDERO DE 2" und 10.00 61.80 618.00 3 185.4 3 185.4 30.00% 7.00 432.6 618.00
0 18.03.07 REGISTRO DE BRONCE ROSCADO DE 4" und 6.00 70.44 422.64 3 211.32 3 211.32 50.00% 3.00 211.32 422.64
0 18.03.08 SALIDA VENTILACION DE PVC-SAL 2" pto 6.00 68.67 412.02 2 137.34 2 137.34 33.33% 4.00 274.68 412.02
0 18.03.09 SOMBRERO DE VENTILACION 2" und 6.00 24.55 147.30 0 0 0 0.00% 6.00 147.3 147.30
PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
0 18.04 APARATOS Y ACCESORIOS SANITARIOS 4,370.31 0 0 0 0.00% 0.00 4370.31 4,370.31
0 18.04.01 INODORO TANQUE BAJO pza 6.00 214.63 1,287.78 0 0 0 0.00% 6.00 1287.78 1,287.78
0 18.04.02 LAVATORIO DE LOSA pza 6.00 198.01 1,188.06 0 0 0 0.00% 6.00 1188.06 1,188.06
0 18.04.03 LAVATORIO DE COCINA DE ACERO INOXIDABLE pza 1.00 186.59 186.59 0 0 0 0.00% 1.00 186.59 186.59
0 18.04.04 LAVADERO DE GRANITO DE 02 POZAS und 1.00 232.36 232.36 0 0 0 0.00% 1.00 232.36 232.36
0 18.04.05 URINARIO NACIONAL MODELO CADET und 2.00 159.29 318.58 0 0 0 0.00% 2.00 318.58 318.58
0 18.04.06 LLAVE CROMADA DE 1/2" P/LAVATORIO und 8.00 45.31 362.48 0 0 0 0.00% 8.00 362.48 362.48
0 18.04.07 LLAVE CROMADA DE 1/2" P/LAVADERO DE ACERO INOX. und 2.00 58.02 116.04 0 0 0 0.00% 2.00 116.04 116.04
0 18.04.08 PAPELERA DE LOSA und 6.00 35.68 214.08 0 0 0 0.00% 6.00 214.08 214.08
0 18.04.09 DISPENSADOR DE JABON LIQUIDO Y PAPEL HIGIENICO und 6.00 77.39 464.34 0 0 0 0.00% 6.00 464.34 464.34
0 18.05 VARIOS 1,293.83 0 0 0 0.00% 0.00 1293.83 1,293.83
0 18.05.01 PRUEBA HIDRAULICA EN REDES DE DESAGUE glb 1.00 517.61 517.61 0 0 0 0.00% 1.00 517.61 517.61
0 18.05.02 SUM. E INST. DE TANQUE ELEVADO DE POLIETILENO DE 1.00M3 INC. ACCESORIOS und 1.00 776.22 776.22
1.00 776.22 776.22
COSTO DIRECTO 16,190.75 1895.21 14295.55 16190.75
GASTOS GENERALES (10%) 1619.08 0 0 0 189.52 0 0 0 0 1429.55 1619.07
UTILIDAD ( 10%) 1619.08 0 0 0 189.52 0 0 0 0 1429.55 1619.07
0.00
COSTO PARCIAL 19,428.91 0.00 0.00 0.00 2,274.25 0.00 0.00 0.00 0.00 17,154.65 19428.90
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000
SUB TOTAL 19428.91 0 0 0 2274.25 0 0 0 0 17154.65 19428.90
IGV (18%) 3497.2 0 0 0 409.37 0 0 0 0 3087.84 3497.21
0.00
TOTAL 22926.11 0 0 0 2683.62 0 0 0 0 20242.49 22926.11
16,190.76
R.U.C. N 20520092197

VALORIZACION N 02 - 1 QUINCENA - AGOSTO 2012


INSTALACIONES ELECTRICAS

ADJUDICACION DIRECTA SELECTIVA N 06-2012-MDCN-T


OBRA: : CONSTRUCCION Y EQUIPAMIENTO DEL LOCAL MULTIUSO EN EL COMIT 12 DE LA ASOCIACION DE VIVIENDA 28 DE AGOSTO - CIUDAD NUEVA - TACNA
ENTIDAD: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA
CONTRATISTA: : EDIFICACIONES DRYWALL SAC
SUPERVISION: : MUNICIPALIDAD DISTRITAL DE CIUDAD NUEVA - TACNA

PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)
0 19 INSTALACIONES ELECTRICAS 17,207.03 0 17,207.03
0 19.01 TRABAJOS PRELIMINARES 3.02 0.00 0.00 0.00 0.00 0.00 3.02
0 19.01.01 TRAZO Y REPLANTEO C/EQUIPO m2 2.63 1.15 3.02 0 0 0 0.00% 2.63 3.02
0 19.02 MOVIMIENTO DE TIERRAS 192.88 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 192.88
0 19.02.01 EXCAVACION DE ZANJA PARA RED ELECTRICA m3 2.29 27.26 62.43 0 0 0 0.00% 2.29 62.43
0 19.02.02 REFINE Y NIVELACION DE ZANJAS m 7.50 3.40 25.50 0 0 0 0.00% 7.50 25.50
0 19.02.03 COLOCACION DE CAMA Y SOBRECAMA PARA RED ELECTRICA m 7.50 3.60 27.00 0 0 0 0.00% 7.50 27.00
0 19.02.04 RELLENO COMPACTADO C/EQUIPO MATERIAL PROPIO m3 1.03 23.02 23.71 0 0 0 0.00% 1.03 23.71
0 19.02.05 ACARREO DE MATERIAL EXCEDENTE m3 1.44 16.46 23.70 0 0 0 0.00% 1.44 23.70
0 19.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1.44 21.21 30.54 0 0 0 0.00% 1.44 30.54
0 19.03 RED DE ENERGIA ELECTRICA 4,140.71 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 4,140.71
0 19.03.01 TENDIDO DE CONDUCTOR ELECTRICO glb 1.00 1,990.77 1,990.77 0 0 0 0.00% 1.00 1,990.77
0 19.03.02 MEDIDOR ELECTRICO MONOFASICO und 1.00 862.46 862.46 1.00 862.46
0 19.03.03 TABLERO GENERAL TG 1-3x50, 2-2x40, 1-2x15 und 1.00 298.81 298.81 0 0 0 0.00% 1.00 298.81
0 19.03.04 TABLERO GENERAL TD-1 2-2x30, 2-2x25, 1-2x15 und 1.00 342.27 342.27 0 0 0 0.00% 1.00 342.27
0 19.03.05 TABLERO GENERAL TD-2 2-2x30, 2-2x25, 1-2x15 und 1.00 342.27 342.27 0 0 0 0.00% 1.00 342.27
0 19.03.06 TABLERO GENERAL TD-3 2-2x30, 1-2x25, 1-2x15 und 1.00 304.13 304.13 0 0 0 0.00% 1.00 304.13
0 19.04 INSTALACIONES ELECTRICAS 6,406.28 0.00 0.00 1,094.31 1,094.31 17.08% 0.00 5,311.97
0 19.04.01 SALIDA PARA CENTRO DE LUZ pto 49.00 52.11 2,553.39 21.00 1094.31 21 1094.31 42.86% 28.00 1,459.08
0 19.04.02 SALIDA PARA TOMACORRIENTE DOBLE pto 33.00 47.48 1,566.84 0 0 0 0.00% 33.00 1,566.84
0 19.04.03 SALIDA PARA INTERRUPTOR SIMPLE pto 29.00 52.94 1,535.26 0 0 0 0.00% 29.00 1,535.26
0 19.04.04 SALIDA PARA INTERRUPTOR TRIPLE pto 2.00 90.67 181.34 0.00 0.00 0.00% 2.00 181.34
0 19.04.05 POZO CONEXION A TIERRA und 1.00 569.45 569.45 0 0 0 0.00% 1.00 569.45
0 19.05 ARTEFACTOS 4,895.42 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 4,895.42
0 19.05.01 ARTEFACTO FLUORESCENTE DE 2x40 W und 18.00 118.79 2,138.22 0 0 0 0.00% 18.00 2,138.22
0 19.05.02 ARTEFACTO FLUORESCENTE CIRCULAR 1x32W und 17.00 98.42 1,673.14 0 0 0 0.00% 17.00 1,673.14
0 19.05.03 ARTEFACTO SPOT LIGHT und 6.00 104.09 624.54 0.00 0.00 0.00% 6.00 624.54
0 19.05.04 BRAQUETE REFLECTOR DE 32W und 8.00 57.44 459.52 0 0 0 0.00% 8.00 459.52
0 19.06 INSTALACIONES AUXILIARES 994.40 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 994.40
0 19.06.01 SALIDA PARA TIMBRE pto 2.00 276.21 552.42 0 0 0 0.00% 2.00 552.42
0 19.06.02 SALIDA PARA TELEFONO DIRECTO (SERVICIO PUBLICO) pto 2.00 72.75 145.50 0 0 0 0.00% 2.00 145.50
0 19.06.03 SALIDA PARA TELEVISION pto 4.00 74.12 296.48 0 0 0 0.00% 4.00 296.48
0 19.07 VARIOS 574.32 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 574.32
0 19.07.01 PRUEBA ELECTRICA glb 1.00 574.32 574.32 0.00 0.00 0.00% 1.00 574.32
0 20 VARIOS 593.04 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 593.04
0 20.01 LIMPIEZA FINAL DE OBRA m2 156.25 0.27 42.19 0 0 0 0.00% 156.25 42.19
0 20.02 PLACA RECORDATORIA und 1.00 550.85 550.85 0 0 0 0.00% 1.00 550.85
0 21 MITIGACION DE IMPACTO AMBIENTAL 847.46 0.00 0.00 0.00 0.00 0 0 0.00% 0.00 847.46
PRESUPUESTO ACUMULADO ANTERIOR EN EL MES ACUMULADO ACTUAL SALDO POR VALORIZAR

ITEM D E S C R I P C I O N UND PRECIO


PARCIAL MONTO MONTO MONTO MONTO
METRADO UNITARIO METRADO METRADO METRADO % AVANCE METRADO
(Soles) S/. S/. S/. S/.
(Soles)

0 21.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 847.46 847.46 0 0 0 0.00% 1.00 847.46
COSTO DIRECTO 18,647.53 1,094.31 1,094.31 17,553.22 17,553.22
GASTOS GENERALES (10%) 1864.75 0 0 0 109.43 0 109.43 0 1755.32
UTILIDAD ( 10%) 1864.75 0 0 0 109.43 0 109.43 0 1755.32

COSTO PARCIAL 22,377.03 0.00 0.00 0.00 1,313.17 0.00 1,313.17 0.00 21,063.86
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000
SUB TOTAL 22377.033 0 0 0 1313.17 0 1313.17 0 0 21063.8628
IGV (18%) 4027.87 0 0 0 236.37 0 236.37 0 0 3791.5

TOTAL 26404.90 0.00 0.00 0.00 1549.54 0.00 1549.54 0.00 0.00 24855.36 26404.90