Q.

3) An activity where the Architect may be paid on a per diem basis plus out-of-
pocket expenses such as travel, accommodations and subsistence, long-distance
telephone calls, secretarial service.

A. confer with prospective investors


B. data gathering
C. feasibility study
D. accounting
Q.4) Which group classification belongs projects involving extensive detail such
furniture design, built-in equipment, special fittings, screens, counters, interiors
and other detailed parts of appurtenances of buildings or structures and
landscaping designs?

A. Group 6
B. Group 7
C. Group 8
D. Group 9
Q.5) For a housing project exceeding 10 units, how much is the minimum fee
chargeable for each additional unit, excluding the fees for the first 10 units?

A. 20% of basic fee


B. 30% of basic fee
C. 40% of basic fee
D. 60% of basic fee
Q.6) How are projects classified in determining the basis for the Architect's Basic Fee?

A. material specifications
B. total floor area
C. degree of project complexity
D. structural components
Q.7) What is the minimum basic fee for public markets with a project construction cost
of P50M.

A. P 2.5 M
B. P 3M
C. P 3.5 M
D. P 4M
Q.8) Which work item is chargeable to the Owner and not included in the regular
scope of services?

A. miniature models of design studies


B. extra drafting of changes made by Owner
C. structural analysis
D. electrical load calculation
Q.9) A method of compensation frequently used where there is a continuing
relationship on a series of projects.:
A. multiple of direct personnel expense
B. percentage of construction cost
C. professional fee plus expenses
D. lump sum or fixed fee
Q.10) A method of compensation that is flexible, easy to apply and is related to the size
and the type of the project.

A. multiple of direct personnel expense


B. percentage of construction cost
C. professional fee plus expenses
D. lump sum or fixed fee
Q.11) The multiplier applied in the multiple of direct personnel expense depends on the
following except one:

A. complexity of project office set-up


B. office set-up
C. experience of the Architect
D. cost of transportation
Q.12) A method of selection for an Architect most often used by an individual person
undertaking a relatively small project

A. comparative selection
B. design competition
C. bidding
D. direct selection
Q.13) When the design of the Architect is used again to build a sixth structure without
amending the drawing and specifications, how much shall the Architect's fee be
computed?

A. 20% of basic fee


B. 30% of basic fee
C. 40% of basic fee
D. 60% of basic fee
Q.14) What is the minimum basic fee for publishing plants with a project construction
cost of P40M?

A. P 2.4 M
B. P 2.8M
C. P 3.2 M
D. P 3.6M
Q.15) Not a criteria for computing the Architect's compensation.

A. talent and skill


B. experience
C. personal relations
D. effort and time available
Q.16) Which component is not considered in the formulation of the Master
Development Plan under the Comprehensive Planning Services?

A. Site Development
B. Legal and Administrative
C. Economic
D. Transport
Q.17) The multiple of personnel direct expense is applicable only to what type of
work?.

A. research
B. creative work
C. government projects
D. ocular site inspection
Q.18) A method of compensation that represents a risk situation to the Architect since
his costs may exceed the agreed amount.

A. multiple of direct personnel expense


B. percentage of construction cost
C. professional fee plus expenses
D. lump sum or fixed fee
Q.19) Not included in the scope of services under Physical Planning.

A. environmental studies
B. impact analysis
C. examination of laws, ordinances, rules and regulations
D. engineering dawings and specifications
Q.20) A full-time construction inspector as deemed necessary shall be engaged and
paid for by the Owner and shall be under the technical control of whom?

A. Owner
B. Contractor
C. Architect
D. Construction Manager
Q.21) The method of compensation should not have the following characteristic.

A. fair to client and architect


B. easy to understand
C. not create legal problems
D. focus client's attention to price
Q.22) When the Architect as Environmental Planner is commissioned to do town and
regional planning or urban renewal projects, he performs the following except
one:

A. undertakes demographic analysis


B. prepares concept development plans
C. identifies social behavior and interaction
D. undertakes environmental impact assessment
Q.23) What is the minimum basic fee for public health centers with a project
construction cost of P50M or less?

A. 5%
B. 6%
C. 7%
D. 8%
Q.24) What is the minimum basic fee for museums with a project construction cost of
P100M?

A. 8%
B. 10%
C. 12%
D. 15%
Q.25) Most expensive and time-consuming method of selecting the Architect.

A. comparative selection
B. design competition
C. mixed method
D. direct selection