Вы находитесь на странице: 1из 5

NASCC Steel Conference

February 10, 2006

STRUCTURAL STEEL VS REINFORCED


CONCRETE
By

Terry C. Pursley Project Director for Alberici Constructors Inc.

Terry C. Pursley has been working in the general construction industry for over 33 years on a wide range of project
types. A few of the major projects he has worked on include;

- A $200 million Milorganite producing facility in Milwaukee, Wisconsin incorporating both structural steel
framing and reinforced concrete floor slabs and shear walls.

- A $150 Million high rise luxury hotel and convention center complex in downtown St. Louis incorporating
tunnel form concrete erection for the superstructure of the Hotel and Structural steel framing for the
associated convention center.

- A $100 Million structural and architectural project for the sports arena in St. Louis (Home of the St. Louis
Rams) incorporating both pre-cast and cast-in-place concrete, and major long span roof trusses.

Terry has worked for Alberici Constructors Inc. out of St. Louis, Missouri since 1984. Prior to working with
Alberici, Terry worked as a project manager for a slip form concrete contractor in Minneapolis MN, and also spent
eight (8) years working with various design teams of Bechtel Power Corporation in their San Francisco office.

The vast majority of Terrys experience has centered on concrete and structural steel construction and their related
interface issues with architectural, mechanical and electrical disciplines and gives him a unique perspective on the
opportunities each type of construction brings to the project site.
NASCC Steel Conference
February 10, 2006

STRUCTURAL STEEL VS REINFORCED


CONCRETE
By

Terry C. Pursley Project Director for Alberici Constructors Inc.

During the course of my construction career I


have had the opportunity to work with many To form, set rebar, and place concrete you
excellent design firms and clients on a multitude generally need:
of high profile projects involving the use of both
structural steel and reinforced concrete elements. A. Carpenters
Throughout this period I have found structural B. Laborers
steel to offer more cost and schedule benefits to C. Ironworkers
the construction team over similar benefits D. Operating Engineers
offered by reinforced concrete construction with E. Cement Finishers, and you may need
respect to the erection of structural elements. F. Electricians and
G. Plumbers/Pipefitters for embedded
In most, if not all, of my projects Form vs work.
Function has been the governing criteria used
by most designers and clients in determining the Even in areas where jurisdictional issues are
use of structural steel or reinforced concrete minimized, the fact still remains that to produce
components. Normally, as constructors, we have a structural element on the job site, there are
had little or no say over what building materials more individual functions to be performed for
are selected by the design team. However, reinforced concrete than the erection of structural
advancements in the construction industry and steel. The more functions required, the more
design techniques have clouded this historical likely the chance for problems and increased
view and we are seeing more choices becoming costs. I therefore prefer structural steel erection
available for the use of either structural steel or as a means of reducing various risk factors.
reinforced concrete members in the construction
of multiple building types. Now back to the Four (4) basic advantages of
structural steel over reinforced concrete that I
I find structural steel has the following mentioned earlier.
advantages over reinforced concrete
construction: ADVANTAGES

1. Safety SAFETY:
2. Quality Control
3. Flexibility Of the advantages listed, I consider safety to be
4. Cost risk exposure the highest priority.

Ill discuss each item individually but before I do Historically, structural steel erection has been a
let me discuss one over-riding issue I find to be high risk endeavor. It would therefore appear
an advantage of structural steel and affects all structural steel erection would not have a safety
four of the items I have listed above. advantage over reinforced concrete work, but my
experience indicates we need to look more
Structural steel requires fewer closely at this aspect.
construction trade type personnel to erect
than does reinforced concrete. With structural steel erection, the industry
standards for 100% tie-off and the use of aerial
To erect structural steel you generally need: lifts to make connections has allowed us to make
significant strides in protecting our steel erection
A. Ironworkers and crews from life threatening falls. In addition, the
B. Operating Engineers personnel mix of a steel erection crew tends to
NASCC Steel Conference
February 10, 2006

remain stable with not a lot of different acceptable on structural steel than repairs to
personnel changes. This stability allows more concrete work.
focused on-site training and planning to be
shared with the crew. A stable crew allows FLEXIBILITY:
better monitoring of their safety performance and
tends to increase self-policing by crew This may seem to be an odd advantage, but
members to avoid unsafe practices. often, during the course of construction, the
client or designer wants to make a change in the
With reinforced concrete placement, a stable structure. I have found almost invariably such
crew mix is not nearly as assured as it is with modifications to a structural steel frame are
structural steel erection. You may have a stable easier to accommodate and less costly to
formwork crew, a stable reinforcing steel crew implement than similar changes to a reinforced
and a stable placement crew, but often times concrete structure.
these crews are not working together on a day in
and day out basis. In addition, various crew Platform and stairway modifications are both
members may not be needed on each concrete prime examples we often have to accommodate
placement, and thus there is less of a chance for and it has been my experience modifications of
the entire crew to receive consistent training and these elements on a structural steel frame are
far less of a chance for the crew members to much easier to accommodate than similar
develop a self-policing attitude. modifications upon a reinforced concrete frame,
especially if additional shoring is required.
My experience indicates there are more Doctor
Case injuries on concrete placements due to the COST RISK EXPOSURE:
multiple work crews being used. Concrete
related injuries may not tend to be as severe as a This item highlights my Stable Crew issue.
structural steel fall, but the impact upon the When you have one similar skill set of
project schedule for the multiple Doctor case personnel performing steel erection, your ability
injuries is as great or more so with the reinforced to manage that one skill set is much easier than
concrete work as compared to structural steel with the multiple personnel skill sets needed for
erection. reinforced concrete steel work.

QUALITY CONTROL: Off-site fabrication risk with structural steel is


much less than reinforced concrete on-site
Controlling the quality of the structural steel fabrication since it is accomplished in a more
fabrication is much easier and more reliable than controlled environment. Reinforced concrete
controlling the quality of reinforced concrete fabrication is performed in the field with all the
work fabrication on the site. normal risk factors and variables associated with
on-site work.
Structural steel fabrication is normally
performed in a controlled environment in a Erection of the structural steel is again
fabrication facility, with a consistent work force, accomplished by a more stable crew and unlike
and readily inspected by third parties; whereas, concrete doesnt have to wait a certain number of
inspection of the on-site reinforced steel concrete cure days before you can build upon it. You
fabrication work is subject to all of the can move forward with much more control of the
conditions one runs into on the site. Bad process and therefore at a less cost risk.
weather, poor shop drawings, numerous people
involved in multiple tasks, and inspectors being All these factors come into play when
spread too thin to inspect all items closely. contractors price their work and apply
contingency or profit/risk money to their bids.
Inspection of the structural steel field erection Coincidently, in my opinion there is much less
can be readily performed and is normally not a risk to the job progress from issues that may
last minute item, which is often the case with arise with structural steel than may occur with
reinforced concrete placement. reinforced concrete work.

Good quality repair work on structural steel


components is normally much easier to perform
than on concrete structural components and the
finished repair work is normally more visually
NASCC Steel Conference
February 10, 2006

DISADVANTAGES: While fireproofing may be considered an


architectural feature, its direct impact is to the
I would be remiss, if I did not point out three structural steel and the estimators, fabricators,
problem areas with structural steel construction erectors, and fireproofing applicators need a
over that experienced with reinforced concrete clear description on the structural drawings so
work. These are: confusion is minimized and costs are lowered.

1. Painting structural steel MOMENT CONNECTIONS:


2. Fireproofing structural steel, and
3. Moment connections Moment connections are costly and time
consuming and to the extent possible they should
PAINTING; be eliminated or minimized. Sometimes, the
Form vs Function issues dictate the need for
Poor surface preparation and poor prime painting major and multiple moment connections and thus
of structural steel has been and continues to be a they must be provided, but where possible, such
problem. In theory it should not be, but there are connections should be designed so they can
still too many people who fail, intentionally or performed in the fabrication facility with their
inadvertently, to perform this task well. A good tighter controls. Where this is not possible the
surface prep and prime painting performance is use of bolted moment connections should be
invaluable to a project. Poor surface prep and considered. When field performed welded
prime painting has cost fabricators, contractors moment connections must be used it is critically
and clients significantly more money and important to ensure the craft person(s)
headaches than it should. Continuous performing the welds are well qualified and
improvement is needed in this aspect. tested for the particular procedure. In addition
testing agencies must be provided timely access
FIREPROOFING: to these joints so as to not impact the schedule.

Fireproofing is a big mess, a coordination CONCLUSION:


problem, and a schedule issue that reinforced
concrete does not share. The impact of When the Form vs Function criteria allows a
Fireproofing can be minimized; however, by choice of structural steel versus reinforced
working with the designers to limit the need for concrete construction, I believe the choice of
fireproofing, making sure adequate time is structural steel is the easy choice from a general
allowed in the schedule for this activity to take contractors point of view. When selected in
place, and using a quality fireproofing coordination with a quality fabricator, structural
subcontractor to perform the work are activities steel construction provides a safe environment,
that will minimize the impact of this aspect. tighter quality control, more flexibility, and
Fireproofing installation is no place to cut reduces risk to the bottom line. Concerns with
corners because it never pays to give this item painting, fireproofing and moment connections
less attention than it deserves. I also recommend need to be recognized, but these items can be
fireproofing should be clearly called out on the managed and in my opinion are lesser risk
structural drawings rather than hiding it in the factors than various risks that occur with
specifications and/or architectural drawings. reinforced concrete
NASCC Steel Conference NASCC Steel Conference
February 10, 2006 February 10, 2006

STRUCTURAL STEEL VS REINFORCED CONCRETE STRUCTURAL STEEL VS REINFORCED CONCRETE

ADVANTAGES
STABLE CREW
SAFETY

QUALITY CONTROL
Structural steel requires fewer construction trade type
personnel to erect than does reinforced concrete. FLEXIBILITY

COST RISK EXPOSURE

NASCC Steel Conference NASCC Steel Conference


February 10, 2006 February 10, 2006

STRUCTURAL STEEL VS REINFORCED CONCRETE STRUCTURAL STEEL VS REINFORCED CONCRETE

DISADVANTAGES CONCLUSION
PAINTNG

FIREPROOFING
When selected in coordination with a quality fabricator, structural
steel construction provides a safe environment, tighter quality
MOMMENT CONNECTIONS control, more flexibility, and reduces risk to the bottom Line.

Вам также может понравиться