Академический Документы
Профессиональный Документы
Культура Документы
ISBN 978-0-7277-6129-3
Abstract
Providing parallel access into tunnels during its construction is a key factor for optimising
programme. However a tunnel is a linear work site where sharing of the space between
several contractors brings with it interfacing issues and associated risks that may in turn
negate the benefit gained from parallel working.
This paper considers the construction of station platform tunnels ahead of TBM constructed
tunnels to optimise the project construction programme. As a result the TBMs are required
to transit through the stations.
TBM transits can be summarised into three distinct phases; reception, transit and relaunch.
The paper discusses the requirements and considerations for each phase of the transit. It
looks at the designs of the reception and launch chambers. It discusses TBM transit
alignments and clash detection. The paper draws examples from the systems used for
transiting through bored tunnels stations with some comparison undertaken with a box
station.
1. Introduction
Metros are underground railways where the majority of its structures are tunnels. However
Metros are also comprised of other critical underground structures that allows it to function
as a commuter railway. They include stations, shafts, bifurcation caverns and cross over
tunnels. All these structures together with the running tunnels are constructed along a
common spine; which is the track alignment. The geometry of all these structures are very
different but they are all required to interface with one another seamlessly. It follows that the
method of constructing these various structures will also be different. The challenge on a
Metro project is therefore to coordinate the various construction methodologies where
possible in order to manage the interfaces, minimise programme risks and optimise access
in the underground space.
The excavation for the station platform tunnels can be undertaken either before or after a
TBM transits through the station. The question as to which transit strategy to adopt is
dependent on many considerations. Both strategies were used on Crossrail, with Contract
C305 and C310 TBMs transiting through completed station platform tunnels, whilst Contract
C300 TBMs bored pilot tunnels through the station alignment which were then expanded.
531
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
532
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
533
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
Shafts on the track alignment are located at Limmo Peninsula and Stepney Green Junction
where they were used to facilitate the launch and retrieval of the TBMs. In the permanent
condition they are provided for ventilation and emergency egress / access.
Bifurcations accommodate the merger or splitting of the eastbound and westbound tracks.
On Crossrail there is an underground bifurcation at Stepney Green junction where the north-
east and south-east spurs meet. Crossovers on the other hand allow trains to switch
between the eastbound and westbound tracks (and vice versa). There are two single
crossovers on Crossrail, one located in the western section at Fisher street and the other on
the central section immediately west of Whitechapel station. They are typically 125m long
but have variable cross sections to accommodate the double track configurations. The
maximum diameter of the caverns is 19m at the headwall.
The summary above provides an insight to the type of structures that can be found on the
track alignment and therefore along the running tunnel and TBM path. During the
construction of the running tunnels, there is continuous stream of traffic within the completed
sections of the tunnels for supplies, personnel and muck removal. There is no access to
other Contractors along the running tunnels, including segregated sections of the station
platform tunnels, during this time. It can therefore be appreciated how obtaining parallel
access into the underground space can provide programme advantages.
The paper now discusses the design and planning of the particular operation of transiting
TBMs through partially completed station platform tunnels. The two main risk are:
Insufficient space for the TBM to transit through the station tunnels
The station tunnels being constructed out of the permanent track alignment tolerance
534
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
All permanent works are referenced to Permanent Track Alignment. This is the most
important principle to maintain. It is also a reminder that a Metro is primarily a railway which
is contained within underground structures such as tunnels. The alignment of the
underground structures must respect and satisfy the requirements of the railway. To
achieve this, the Designer must understand the relationship and hierarchy between the
various alignments.
In a station, the primary relationship is between the track and the platform edge. Track
alignment in stations are normally straight and level, so the vertical and horizontal offset are
constant. The track alignment could be related to the platform tunnel alignment like the
running tunnel. However it should be noted that the cross sectional shapes of the station
tunnels can vary along with the length of the station platform. Therefore forming a direct
535
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
relationship between track and the station alignments in some areas is not straight forward.
Nevertheless keeping the track alignment visible as a primary reference is important
Track Alignment
Tunnel alignment related to track Station tunnel alignment Station tunnel alignment at fixed
by cant varies to accommodate offset to track but relationship is
TBM transit. The different from the station non
relationship with track public area
alignment is variable
The following section will provide some guidance for designing the TBM transit alignment. To
begin with the following design principles should be incorporated where possible:
The vertical offset between track level and TBM centreline should be kept constant.
Horizontal TBM transit alignment is straight at the reception and launch locations
The TBM transit slew is an S curves which should not bend the TBM in opposite
directions at any one time
By keeping the vertical offset constant, the transit alignment also preserves the vertical offset
from the track. This ensures the TBM and hence the PCC tunnels are constructed to the
permanent track alignment. The TBM transit alignment iterations are then simplified by
confining adjustments to the horizontal alignment only. It should be noted that this may not
be possible if the running tunnels are constructed before the station tunnels. Here the
vertical offset may need to be changed to position the running tunnel (pilot) at a particular
level to facilitate the subsequent enlargement of the station platform tunnel.
536
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
Receiving and launching the TBM on straight horizontal alignments helps control TBM drive
tolerance. Although arriving and launching on shallow curves was not an issue on C305,
having straights simplified detailing for items such as the TBM launch brackets, transit rails
and setting of station reception & launch chambers.
A horizontal S bend in the transit alignment is required to slew the TBM into and out of
the station platform from the reception and launch chambers. The S bend is made up of
three components comprising a curve, a straight and an opposite curve. The length of each
component was matched to the TBM shield geometry as follows:
The curves were designed with entry and exit transitions. With this S bend geometry the
TBM shield was not bent in opposite directions at any given time during the slewing. The
TBM mid shield articulation was not considered in the transit design although could have
been used if the tighter slew paths were required. Tighter radii and shorter lengths of curves
and straights could have been used, but this would potentially cause the TBM swept path
envelope to increase requiring larger diameter station tunnels. It should also be noted that
the curve radius can be limited by the space required to transit the gantries. There is a risk
that the bottom corners of the gantries frames clashing with the tunnel linings.
537
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
Fig 2.4 Damage to PCC Segments from Gantry Clash (picture not from C305)
The relationship of the TBM transit alignment can be related to the permanent track
alignment by simply defining the horizontal offsets from the point where the two alignments
depart. This relationship is essential for designing the station tunnels as it allows both the
permanent and temporary space proofing to be checked simultaneously.
Face pressure is lost as the TBM begins its breakthrough into a station. When the cutter
head daylights into the station, the annulus around the TBM shield is exposed to the
atmosphere and hydraulic support can no longer be maintained. If no provision is made for
alternative support, there will be a length of ground which is temporarily unsupported whilst
the full length of the TBM enters the reception chamber. Until the last permanent tunnel ring
538
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
is installed and sealed against the reception chamber, there remains a risk of the annulus
collapsing and the ground above settling.
PCC Ring
Fig 3.1 Potential Loss of Support around TBM Shield at Reception
The station reception chambers on C305 were SCL tunnels that extended from the station
platform tunnel. The reception chamber headwall / softeye is a balanced design that
provides temporary stability before TBM breakthrough but structural weakness during the
breakthrough. This was achieved by using a dome shaped headwall constructed of a thin
SCL shell which was stabilised by a foam concrete plug (C2 to C5 concrete) behind it. The
SCL headwall is fractured by the applying tensile splitting forces on the concrete through the
TBM disc cutters. This was typically 100kN per disc of which there were 22No. The foam
concrete was a means of controlling the break through to avoid collapse of the headwall.
Once the TBM cutter head was buried into the reception chambers headwall, risk of ground
movement ahead of the TBM face is prevented as the chamber provides a protective
canopy. In stations such as Canary Wharf where the breakthrough was directly into a box,
there was no ground ahead of the TBM face and hence no risk of ground collapse once the
TBM was in the station. Collapse of the annulus around the TBM shield is caused by high
pore pressures or flowing water which in turn destroys any temporary soil shear strength.
The hydraulic support in the annulus during the normal TBM operation can be maintained
after break through by providing seals inside the reception chamber. This can be achieved
by having:
Further annulus stability can be achieved by stabilising the ground immediately outside the
reception chamber headwall for a minimum length of the TBM shield. This would include the
use of:
a grouted canopy
depressurisation / dewatering of the ground
539
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
The minimum clear diameter for the reception chamber was 7380mm. This was based on:
Further allowances locally would be required for accommodating seals and tolerances for
constructing the reception chamber.
From the time the TBM engages the station headwall, the reception chamber area became
an exclusion zone. Dust suppression systems were provided at the headwall in the form of;
water cannons, water sprinklers and additional ventilation. Control systems for the dust
suppression and ground stabilisation were protected during TBM arrival by positioning the
equipment outside the TBM envelope. Typically a gap of 1m was provided between the
540
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
foam headwall (end of landing platform) and the beginning of the TBM transit rails. This gap
has several functions including acting as a debris moat, sump and a transition zone to
transfer the TBM on to the transit rails.
Fig 4.1 Example of Pinch Point where TBM Enters Larger Platform Tunnel
Once the TBM is in the main body of the station platform tunnels, there is little risk of clash.
The main consideration here is related to integration and logistic of the temporary works in
order to protect permanent works and optimise programme.
541
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
The Herrenknecht check was a review of the station temporary space proofing. It used the
TBM design transit alignment and a range of TBM envelopes which were checked against
the station 3D design models. However the station model initially, did not represent the
intermediate configuration during the TBM transit phase. The station models were modified
but specific details such as interface connections were difficult to model accurately. There
was still tremendous value in undertaking this 3D modelling as it provided an independent
check on the temporary space proofing, but more importantly a strong visual aid to focus
minds on the specific issues at pinch points.
The DSJV 3D check was undertaken using built survey information of the SCL tunnel linings.
With a clear understanding of where the pinch points were, targeted surveys and checks
could be undertaken. As discussed previously, understanding the track, station and transit
relationship here allowed the TBM envelope to be positioned correctly relative to the as built
station lining survey. Thereafter this could be evaluated for clash and adjustment identified
accordingly.
542
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
The majority of the TBM transit occurs through main length of the station platform. Once the
TBM has been slewed into the middle of the station platform tunnel and the transit alignment
set straight and level, the risk of the TBM shield clashing with the station lining is minimal.
Although there are still areas where particular clash checks are required including:
Fig 4.3 (a) Local Clash at Shaft Tunnel Interface (b) Detailed Setting Out for Shaft
Aperture
Whilst positioning the transit alignment in the middle of the platform tunnel may present the
lowest risk option for preventing clash, it may not necessarily be the optimum location when
considering provisions for:
The initial sections of the transit rails were adjustable so that it can be aligned with the final
position of the TBM shield when it breaks into the station. On C305 the adjustable transit
rails were formed of prefabricated 50 x 50 mm flat bars tack welded onto a hollow steel
sections filled with grout. These hollow steel section were welded onto a 12 mm plate with
links at 250 mm centres, then cast into reinforced concrete plinth. After TBM breakthrough
the tack welds could be removed to allow final adjustments to be made. The temporary
543
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
plinths were separated from the station lining with a debonding membrane but dowels were
provided at the interface to provide shear resistance.
Beyond the adjustable rails were the fixed transit rails which were formed of MRS 87A Rail
or an 80 x 30 mm flat bar welded onto the 12 mm plate. The 80 x 30mm flat bar was used
where clearance to the station tunnel lining was tight. All the transit rails were installed using
a jig that was set out to the TBM transit alignment.
Two jacking systems were used on C305 to advance the TBM across the station which
include using:
The first system of jacking off temporary invert ring (shove iron) was used in all the transits
apart from Canary Wharf station. This was a simple systems that placed two invert PCC
segments behind the TBM which provided a reaction point for the jacks to advance the
shield forward. The invert segments were supported off the station tunnel invert on timber
544
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
blocks positioned in between the transit rail plinths. These timber blocks were placed
adjacent to the transit rail plinths outside the envelope of the TBM shield. Once the TBM
shield had passed, the timber blocks were pulled into position by a system of ropes and
wedged under the PCC segment. These invert segments then provided the temporary
platform to support the TBM gantries and temporary railway as per the normal configuration
in the running tunnel. Where the station tunnel invert or shaft inverts were deep, additional
concrete was poured to build up a temporary invert. Where possible rectangular hollow
sections were incorporated so that telehandlers could be used to remove the temporary
invert after completion of the tunnelling works.
Fig 4.5 TBM Shoving Off Temporary Invert Segments During Transit
Fig 4.6 TBM Gantries Supported on Temporary Invert Segment During Transit
545
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
As a note, on C300 Western Running Tunnels, 1m long temporary segments where installed
through the station platform to match the maximum advance length of SCL excavation for
the subsequent enlargement of the station platform tunnels.
Planning the interface between the station and tunnelling works is important to allow both
programmes to be optimised. However the various underground spaces should always be
clear defined and controlled by the respective Principal Contractors. These work spaces
would have its own arrangement for welfare, access routes, entry and emergency egress.
The boundaries of the underground sites is dynamic so it was important that daily liaison
between the Contractors Person in Charge were undertaken to confirm changes to the
work areas and corresponding emergency arrangements. During tunnelling, the station
space where the temporary railway is located is under the control of the tunnelling
Contractor. No station works can be undertaken in this area until is it handed back to the
station Contractor. Where possible the aim was to have the structural lining completed in
the platform tunnels so that only internal works such as that for the platform structures and
track bed would need to be undertaken after the platform tunnel is handed back.
546
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
Temporary services are required through the station to support the TBM. Lighting was
positioned next to walkways by the transit rail plinths. Other services including pipework,
electrical cables, communications, muck conveyors and ventilation were fixed to the station
tunnel lining. Installation of the conveyors and ventilation bagging could not be undertaken
from the TBM gantries without additional provisions in the form of extension chains being
provided to account for the large diameter platform tunnels. Consideration could be given to
using steel frames erected around the TBM on which these services could supported,
keeping it independent of the station lining. Constraints such as temporary loads and drilling
depth into the station linings were defined in Interface Control Documents to allow the
tunnelling Contractor to design the temporary works whilst protecting the permanent works in
the station. Items of particular concern to the station was preventing damage to the
permanent structural lining and waterproofing membrane (if installed).
Upon breakthrough the ventilation through the completed tunnel needs to be preserved.
This could be provided by venting through the stations, but in the case of C305 the system
was sealed so that air circulation was contained within the running tunnels. This approach
therefore required bulkheads to be erected across station openings, such as adits and
shafts. In some cases where the station was not ready for TBM transit, temporary
bulkheads were erected across the platform tunnel itself.
547
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
the station permanent works. Apart from the interface with the station tunnel lining, the other
interface between the tunnel temporary railway is the platform structure and the track bed
concrete. Positioning of the temporary works would need to take into consideration position
of reinforcement, undertrack crossings, track drainage and so on. Furthermore the
construction of cast in items would require the works to be adopted by the permanent works
Designer who in doing so needs to ensure that track and platform setting out are preserved.
This is where maintaining an understanding between the permanent track alignment and the
other temporary alignments is key to ensuring the permanent railway requirements are
achieved.
Whilst undertaking tunnelling and station works in parallel may bring programme benefits to
the project, there must be a clear understanding of how the TBM will be retrieved at the end
of the drive. The construction of the platform structure in the station reduces the available
space if large TBM components have to be retrieved back through the station.
Consideration should then be given to the configuration of the temporary works such as the
use of steel vs concrete, insitu vs precast, in order to understand which approach optimises
the time required for temporary works removal and hand back of the station space.
700 700
A393 Mesh
Fig 4.9 Example of Integrating Temporary Railway Plinth into Station First Stage Concrete
transition the TBM from the platform tunnel back onto the design tunnel alignment
housing the launch brackets against which the permanent tunnel rings are
constructed
Sealing the tunnel allowing full face pressure to be established before break out
constructing the permanent connection between the Running tunnel and Station
Although the TBM can launch on a horizontal curve the preference is always to have a
straight alignment wherever possible. On C305 launch chambers were constructed at the
end of the bored stations for a length of the TBM shield plus 1m for a foam concrete plug.
Behind the shield a further length is required to accommodate the launch brackets and
548
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
provision for constructing the permanent connection between the PCC rings and the station
lining.
The minimum clear diameter for the launch chamber was 7280mm. This was based on:
PCC Ring
The diameter of the launch chamber is smaller than the reception chamber to minimise the
size of the annulus grouting required around the permanent rings. This is to ensure a seal
can be formed during the launch and the PCC rings are stabilised thereafter. On C305,
reaction brackets aligned with the 22No TBM RAMs, were bolted around the launch
chamber lining. Local thickening of the launch chamber lining was required to accommodate
these brackets and to dissipate the launch loads. The launch loads were typically 200T from
the dead weight of the TBM and a further 220T for the forced required to fracture the head
wall. Further allowance were made to account for unevenly distributed RAM loads. Each
launch bracket was made up of two steel components, a seat and a reaction frame, which
were assembled together once the TBM shield was in position.
549
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Crossrail Project: Infrastructure design and construction Volume 3
Fig 5.2 (a)Launch Brackets Seats (b) Fully Assembled Reaction Frames
A 250mm wide steel ring former was bolted to the first PCC ring which acted as a template
to aid assembly of the first permanent ring. As the PCC rings were built, a grout bag was
installed at the trailing edge of the first ring in the annulus. This was inflated which formed a
stop end against which the annulus could be backfilled. The annuls back fill within the
launch chamber was initially pea gravel which was then grouted once the TBM broke out
and tail skin grouting could begin. The configuration of the foam plug and the shape of
headwall had a bearing on how easy it was to breakout. The preference was:
No steel fibres in the headwall concrete to avoid concrete breaking into clumps
making it difficult to remove through the muck screw.
A benched rather than domed headwall to minimise concrete clumps during break
out.
550
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.
Chew, McIntyre and Cullen
6. Conclusion
Developing the relationship between the TBM
transit alignment and the track alignment is
key to ensuring the permanent works are not
compromised. The transit alignment should
be kept simple by maintaining the vertical
alignment at a constant offset from the
permanent track alignment thus confining to
design of the transit to the horizontal
alignment. Where possible, allow the TBM to
be received on a straight alignment. During
the transit avoid short S curves as this would
require the TBM to bend in opposite directions
simultaneously.
The TBM station transit can be described in three parts; reception, transit and launch. The
main risk during TBM reception is ground instability. The TBM face and annulus pressures
that are lost during entry can be mitigated by providing seals in the reception chamber and
undertaking ground stabilisation. During the TBM transit, areas of risk to TBM clash include
locations where the station cross section changes and where the TBM transit path slews
away from the track alignment. There are several ways of optimising the tunnelling and
station programmes such as integrating the tunnelling temporary works with the station
permanent works and using segregated work areas to allow parallel working to continue
safely. However this has to be balanced against the potential impact on access required for
other works such as TBM removal. Access into the underground space is always limited
and therefore the use of a simple light weight launching system was ideal.
C305 under took four TBM transit through stations and crossover chambers. A simple and
repeatable system was used which allowed all the transits to be completed without major
issues. Design, planning and execution of the works required extensive interfacing to
achieve a balanced outcome for all parties. Successful transits of the TBMs through the
stations was a key component for maintaining the critical path activity of constructing the
running tunnels.
551
Downloaded by [ University College London] on [24/11/16]. Copyright ICE Publishing, all rights reserved.