Вы находитесь на странице: 1из 27

MethodsofDelayAnalysis

RequirementsandDevelopments

KatrinEnders
HillInternational,LondonUK
Frankfurt,29September2015
OVERVIEW

Overview DefinitionForensicScheduleAnalysis

Approach DelayAnalysisMethodologiespro&cons

Findings Choosingamethodology,FactisKing,Guidance

Conclusions

2
OVERVIEW DEFINITION

BewarethedarkartswasthesageadviceofAlbus
DumbledoretotheyoungHarryPotter.Besidesbuddingwizards,
constructionclients(attheprojectordisputeresolutionstages),
contractorsandlawyerswouldbeequallywellservedbythis
advicewhenitcomestothedifficultsubjectofdelay
analysis"...delayanalysis likeLordVoldamort,comesinmany
guises anditseemsthereisaspellforeverycircumstance.What
wouldyoulikeconjurederrproven,sir?Letmejustmixup
somefragnets,lags,eyeofnewtandheypresto!

(cited: BEWARE THE DARK ARTS! DELAY ANALYSIS AND THE PROBLEMS WITH RELIANCE ON TECHNOLOGY, David Barry, 2009 )
3
OVERVIEW DEFINITION

FORENSICSCHEDULEANALYSIS
referstothestudyandinvestigationofeventsusingCPM orother
recognizedschedulecalculationmethodsforpotentialuseinalegal
proceeding.

thestudyofhowactualeventsinteractedinthecontextofa
complexmodelforthepurposeofunderstandingthesignificanceofa
specificdeviationorseriesofdeviationsfromsomebaselinemodeland
theirroleindeterminingthesequenceoftaskswithinthecomplex
network.
(cited:AACEInternationalRecommendedPracticeNo.29R03FORENSICSCHEDULEANALYSISTCM Framework)

4
APPROACH

Overview DefinitionForensicScheduleAnalysisandNomenclature

Approach DelayAnalysisMethodologiespro&cons

Findings Choosingamethodology,FactisKing,Guidance

Conclusions

5
APPROACH DELAYANALYSISMETHODOLOGIES

RetrospectiveAnalyses ProspectiveAnalyses

LOOKING BACK LOOKING FORWARD

AsplannedversusAsbuilt TimeImpactAnalysis
AsBuiltButFor ImpactedAsplanned

TWO
Types

FOUR
Categories*

* See for example the Society of Construction Law Protocol on Delay and Disruption, or Association for the Advancement of Cost Engineering Recommended Practice No.29R-03
Forensic Schedule Analysis 6
APPROACH ASPLANNEDVS ASBUILT(APAB)

isthemostbasicmethodofanalysis
isobservational nochangesaremadetotheprogramme
straightforwardcomparisonbetweentheplanned vstheactual
performanceofthework
canonlybecarriedoutretrospectively(requiresasbuiltprogramme/orat
leasttheoverallasbuiltcompletiondate)

Strengths Weakness
isverysimpleandtherefore Staticcriticalpath
easytounderstand failstofulfilthefundamental
canbeperformedwith requirementtodemonstratethe
rudimentarybasedata(e.g. causallinkbetweenadelayeventand
whendetailandlogicoftheas itsallegedeffect
plannedprogrammeisunavailable, doesnotdealadequatelywith
andno detailedprogressrecords concurrentdelay
otherthantheoverallasbuilt
programmeareavailable)
7
APPROACH ASPLANNEDVS ASBUILT(APAB)

CompareAsPlannedvsAsBuilt

Activities Timescale
PlannedCP Contractual Actual
Completion Completion
AsbuiltCP Date
Date

(delays)

Claim
(delaysanddisruptions)
APPROACH IMPACTEDASPLANNED(IAP)

isaprospective methodology
delayeffectismeasuredbyimposingeventsonamodeloftheoriginal
programme(Baseline)
doesnotrelyonanyactualprogressthathasbeenmade
requiresarobustandreliableoriginalprogrammethatreflectsthe
indentedsequenceandtheScopeofWork

Strengths Weakness
relativelysimpletocarryoutand cannotbeusedforcomplexprojects
tounderstand usedtoquantifypotentialdelaysrather
No asbuiltrequired(likelychoice andactual
whenplannedprogrammeisavailable, concurrentdelayseasilyoverlooked
nosignificantchangesinthesequence assumesthatthebaselinewas
duringtheprojectexecution,few achievable
delayingevents,andwhenthereis
doesnottakeactualprogress/resources
littleornoprogressrecords)
intoaccount
notreliableindisputeresolution
9
APPROACH IMPACTEDASPLANNED(IAP)

Activities Timescale

Event
Claim
Event

Event

Event
Event

Event

10
APPROACH TIMEIMPACTANALYSIS(TIA)
prospective anddynamicmethod butcanbeappliedretrospectively
takesaccountofprogressandtiming ofdelayeventsontheWorks
requiresreliableasbuiltdatatoupdatetheprogramme(hence,ifdetailedand
regularprogressdataisnotavailablethenthismethodcannotbeused)
a reliablebaselineprogrammeisessential(ideallyreflectstheexecutionofthe
plannedprojectusingsoundconstructionlogic)
oftenundertakenintimeslices(windows)

Strengths Weakness
hasaproventrackrecordin timeconsuming(todeterminethefactual
forensicapplication backgroundandcorrectlogicassociated
preferredmethodoftheSCL withprogressrecordsanddelayevents)
Protocol requires considerabledegreeof
basedonadynamicandchanging expertiseandtechnicalknowledge
criticalpath hence,difficulttocommunicate,highly
demonstrates causeandeffect complex
11
APPROACH TIMEIMPACTANALYSIS(TIA)

Activities Timescale
Dateof Project
Event Completion
Activity1 DelaytoProject
Activity2 Completion
Activity3
DelayEvent

Progressbehind
onthisactivity. DelaytoProject
Completion(2)
Delay(1)causedbypoorprogress
Delay(2)causedbyevent
Claim=differencebetweenD(1)andD(2)
12
APPROACH ASBUILTBUTFOR(ABBF)
retrospectivemethodalsoknownasCollapsedAsbuilt(CAB)
reliesonadetailedreconstructionoftheasbuiltprogramme
normallyrestrictedtoaftertheeventanalysesinforensicwork
doeshavealimitedprospectivecapability(canbeusedtodemonstratetheeffect
ofadelayonthecompletedpartofanincompleteproject)
hasbeenproventobereliableindisputeresolution/claims
Ifdoneproperlycandemonstrateseffectandcause/takesaccountof
concurrence
Strengths Weakness
greateststrengthforforensicwork complicatedmethodhence,difficultto
isthatitisfactbased(basedonas executeandtoexplain
build) difficulttoestablishadynamicasbuilt
notreliantuponanasplanned schedule(ascomplicatedtodetermineand
programme modellogic)
requiresdetailedasbuild/progress
records
13
APPROACH ASBUILTBUTFOR(ABBF)

IdentifyPlannedPeriod&Asbuilt

Planned Actual
Planned Completion Completion
period

Asbuilt

14
APPROACH ASBUILTBUTFOR(ABBF)

IdentifyDelays

Planned Actual
Planned Completion Completion
period

Asbuilt

15
APPROACH ASBUILTBUTFOR(ABBF)

Zerodelays

Planned Actual
Planned Completion Completion
period

Asbuilt

ActualCompletionbutfor
delays
16
APPROACH ASBUILTBUTFOR(ABBF)

QuantifyClaim
Extended
Completion
Contract
Contract Completion
period Actual
Completion
Asbuilt

Culpableornon Claim
claimabledelays period

ActualCompletion
butfordelays
17
APPROACH NOMENCLATURE
AACEI RP 29R-03: Forensic Schedule Analysis
Table 1 Nomenclature Correspondence

ADVANTGES & DISADVANTAGES


NOT PREFERENCE OR PREJUDICE!

18
FINDINGS

Overview DefinitionForensicScheduleAnalysisandNomenclature

Approach DelayAnalysisMethodologiespro&cons

Findings Choosingamethodology,FactisKing,Guidance

Conclusions

19
FINDINGS CHOOSINGAMETHODOLOGY

WhichMethodisappropriate,correct,sustainable?
Legal/Contractual
Whatdoesthejurisdiction/contractrequire?(e.g.Concurrency?LikelyorActualdelay
tocompletion?DelayAnalysisMethodSpecified?)

Whatinformationisavailable?
Planned,progress,asbuilt(Doesalackofinformationprecludetheuseofanyofthe
methods?)

TimeandMoney
Dotime/costconstraintseliminatecertainoptions?((Duringproject/AfterProject,
Recordkeeping;Staffavailable(Engineering/Management),Decisionmaking,Budget)

Otherissues:
Proportionality,Typeofproject,Whichparty,atwhatstageisthedispute?
20
FINDINGS FACTISKING

KeyFacts:
AtleastafteraneventdelaybecomesafactandtheOtherParty/theCourtsare
interestedinwhatactuallyhappenedratherthaninwhatcouldhavehappened.

Foraneventtoaffectthecompletiondateitmustfallonthecriticalpathofthe
project.

must considerallrelevantfactsandevidence regardlessofapositiveornegative


impactinrelationtotheissuesinquestion

DelayAnalysisshouldbebasedonacalculatedapproach itcannotbeimpressionistic
EffectandCausenotCauseandEffect

Aretherefacts/evidenceavailableandaccessibletoverifythecause?

21
FINDINGS GUIDANCE

RecommendGuidance:
AACEI RecommendedPractice(http://www.aacei.org/resources/ppg/)

SCL Protocol(http://www.scl.org.uk/resources)

22
CONCLUSIONS

Overview DefinitionForensicScheduleAnalysisandNomenclature

Approach DelayAnalysisMethodologiespro&cons

Findings Choosingamethodology,FactisKing,Guidance

Conclusions

23
CONCLUSIONS

Conclusions:
DelayAnalysiscomesinmanyguisesallwiththeir
advantagesanddisadvantages
Tochosethemostsuitablemethoddependsonthe
surroundingfactors
FactsandcommonsenseareKING

24
QUESTIONS

QUESTIONS PLEASE ?

Katrin Enders
Associate Director
Hill International (UK) Ltd
11 Pilgrim Street,
London EC4V 6RN
Office: +44 (0)207 618 1200/ 1262
Mobile: +44 (0)7850722796
www.hillintl.com
25
SERVICES

4900Employeesworldwide

100Officesin40countries

ConstructionClaims&ConsultingGroup

ProjectManagementGroup

NYSEGlobalMarket

Foundedin1976

Employers/Contractors
HillInternational(D)GmbH
Prinzregentenstrae2022
80538Mnchen
HillInternationalUK Munich@hillintl.com
London,HillInternationalUK,Ltd.
Dsseldorf,Germany
11PilgrimSt
Graf Adolf Platz15
London,
40213Dsseldorf
EC4V6RN
Duesseldorf@hillintl.com
UK
Tel:+44(0)2076181200 Hamburg,Germany
AmKaiserkai 1
(9 UK Locations)
20457Hamburg
SERVICES

ContractAnalysis/ Delay&Disruption
Drafting Analysis
TimeRiskManagement ExpertAdvisoryServices
ProcurementStrategy ExpertWitnessServices
ContractAdvisory ClaimsPreparation
StaffAugmentation Dispute Dispute ClaimsAnalysis
ContractWorkshops Avoidance Resolution
ProjectAudits

Seminars/
Claims
Coaching/
Consulting
InHouseSeminars Mentoring Compliance
OpenSeminars ToolsandTemplates
IndustryEvents Guidelines
Coaching/Mentoring Procedures&WorkFlows
Workshops Structures

Вам также может понравиться