Abstract of Estimated Quantity

Site : Residential Building


Location : Katunje

Item No Description of Item Unit Quantity Rate Amount(Rs) Remarks

Work title : Civil Works


A. EARTH WORK
1 Earthwork excavation in soft soil in
trenches with a load and lift as per
Cuft 2,201.78 15.44 33,995.56
drowing, specification and instruction all
complete.

2
Earthwork in backfilling in 15 cm layer
including water sprinkle and mechanical
Cuft 1,651.34 22.10 36,494.58
compaction as per drawing specification
and instruction all complete

3 Earthwork in filling Cuft 962.18 22.10 21,264.08


B. BRICK MASONRY
1
Flat brick soling work as per specifocation
Sqft 1,116.62 78.77 87,956.46
and instruction all complete
2 Supplying and laying of first class
chimney made brick work and erection
brick masonry wall in cement sand mortar
Cuft
(1:6) including in true line and level and
curing etc as per specification and
instruction all complete.
For Substructure Cuft 473.01 432.83 204,734.90
For Superstructure Cuft 2,090.33 442.48 924,929.68
C. PCC WORK
1
Providing, mixing and laying PCC 1:3:6
(lean concrete) works in foundation with
proper compaction by needle vibrator and
Cuft 279.16 380.75 106,288.64
completion to perfect line, level and
finishing including curing as per drawing,
specification and instruction all complete.

2
Providing, mixing and laying PCC 1:1.5:3
(M20) for RCC works in column, slab,
beam etc. with proper compaction by
needle vibrator and completion to perfect Cuft 2,408.86 455.00 1,096,031.91
line, level and finishing including curing
as per drawing, specificationa and
instruction all complete.

Page 1
Item No Description of Item Unit Quantity Rate Amount(Rs) Remarks

3 Providing high strength defoRfted bars


(HYSD) of grade Fe 415 or approved
TMT reinforcement bars including
straightening, cutting, bending, placing in mt 6.224 116,609.00 725,716.22
position and binding by annealed wire as
per drawing, specification, and instruction
all complete.
4
Providing, fiting and fixing standard
formwork of good wooden planks/steel
plates including all necessary
steel/wooden props, bracing, wedges and Sqft 6,194.24 76.25 472,310.79
careful removable of foRftworks at
approved time as per drawing,
specification, and instruction all complete.

D. FLOORING WORKS
1 Providing and laying of glazed and non
glazed (non skiding) porcelian clay tiles in
floor and walls of approved colour and
size on kitchen,toilet and bathroom in 1:4 Sqft 345.47 248.34 85,794.91
cement sand mortar in true line and level
as per drawing, specification all
instruction all complete
2 50 mm Screeding works in floors in 1:2:4
cement sand mortar in true line and level
Sqft 2,303.17 60.36 139,019.50
as per drawing, specification all
instruction all complete

E. FINISHING WORK
1 Supplying and applying of 12.5mm thick
1:6 cement sand plaster on true line and
level including curing as per specification Sqft 10,067.44 40.00 402,697.63
and instruction all complete

5 Supplying, mixing and applying of 1:1


cement sand punning 3 mm thick work as
Sqft 2,303.17 18.24 42,009.87
per specification and instruction all
complete
F. WOOD WORK
1
Supplying, fixing and erection of sal wood
frame for door with steel holefast of
approved shape and size jamming on Cuft 43.74 5,400.98 236,220.23
wall by 1:2:4 PCC as per specification
and instruction all complete

Page 2
Item No Description of Item Unit Quantity Rate Amount(Rs) Remarks

2
Supplying, fixing and erection of sal wood
panelled door shutter with hinges, tower
bolts and handle of approved quality and Sqft 678.42 581.21 394,302.55
colour as per specification and instruction
all complete

G. METAL WORKS
1 Handrails for staircase Rft 35.00 950.00 33,250.00
H. COLOURING AND PAINTING
1
Providing and applying two or more coats
of first quality hundred percent acrylic
paint (Apex weatherproof external
emulsion or approved equivalent
manufactured by Asian Paints, Berger
Paints, or ICI, ) of approved shade and
pattern to the exterior walls of buildings
Sqft 10,067.44 35.00 352,360.43
etc., The rates shall include for scrapping
etc., washing the surface with water,
applying a coat of approved quality water
base cement primer, surface preparation,
scaffolding etc., all complete as per the
manufacturer's recommendations and as
approved by the Engineer.

J. MISCELLANEOUS WORK
Total of Civil Works: 5,395,377.94

Sanitary works @10% of Civil Works 539537.79415


Electrification works @8 % of Civil works 431630.23532
Total Cost Estimate 6,366,545.97

Page 3
MEASUREMENT SHEET

S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Sub Structure Works
1 Earthwork:
1.1 Earthwork in excavation
Footing F1 5 5 5 5.00 625 cft
Footing F2 1 6 6 5.00 180 cft
CF1 1 10.83 5 5.00 270.75 cft
CF2 1 15.5 5 5.00 387.5 cft
CF3 1 10.42 5.08 5.00 264.668 cft

1.2 Trench for Wall Footings:


Along Grid A ( 1-2), (2-4) 1 11.25 2 3.33 75 cft
Along Grid B (1-2), (2-4) 1 10.25 2 3.33 68.33333 cft
Along Grid C (1-2) 1 5.75 2 3.33 38.33333 cft
Along Grid D (1-2) 1 5.67 2 3.33 37.8 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 11.58 2 3.33 77.2 cft 2'9"+5'1"+3'9"
Along Grid 2 ( A-B), (B-C), (C-D) 1 8.17 2 3.33 54.46667 cft 1'4"+4'7"+2'3"
Along Grid 4 (A-B), (B-C) 1 5.08 2 3.33 33.86667 cft
Along Grid 3 (C-D) 1 1.33 2 3.33 8.866667 cft
Extra 1 24 3.33 80
2201.78 cft

Earthwork in backfilling 1 75% of total Earthwork approx deducting water tank 1651.34 cft

1.3 Earthfilling 1
Garage 1 9 9.29 1.50 125.415 cft
Bedroom 1 10.33 9.58 1.50 148.4421 cft
Kitchen 1 10.33 9.92 1.50 153.7104 cft
Toilet with corridor 1 13.33 9.58 1.50 191.5521 cft
Living room 1 9.5 12.5 1.50 178.125 cft
Staircase 1 11.33 8.83 1.50 150.0659 cft
Extra 1 9.91 1.50 14.865 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
962.18 cft

2 Flat Brick Soling


Footing (F1) 5 5 5 125 sft
Footing (F2) 1 6 6 36 sft
CF1 1 10.83 5 54.15 sft
CF2 1 15.5 5 77.5 sft
CF3 1 10.42 5.08 52.9336 sft

Trench for Wall Footings:


Along Grid A ( 1-2), (2-4) 1 11.25 2 22.5 sft
Along Grid B (1-2), (2-4) 1 10.25 2 20.5 sft
Along Grid C (1-2) 1 5.75 2 11.5 sft
Along Grid D (1-2) 1 5.67 2 11.34 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 11.58 2 23.16 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 8.17 2 16.34 sft
Along Grid 4 (A-B), (B-C) 1 5.08 2 10.16 sft
Extra 1 24 24 sft
Garage 1 9 9.29 83.61 sft
Bedroom 1 10.33 9.58 98.9614 sft
Kitchen 1 10.33 9.92 102.4736 sft
Toilet with corridor 1 13.33 9.58 127.7014 sft
Living room 1 9.5 12.5 118.75 sft
Staircase 1 11.33 8.83 100.0439 sft
1116.62 sft

3 3" thick PCC(1:3:6)


Footing (F1) 5 5 5 0.25 31.25 cft
Footing (F2) 1 6 6 0.25 9 cft
CF1 1 10.83 5 0.25 13.5375 cft
CF2 1 15.5 5 0.25 19.375 cft
CF3 1 10.42 5.08 0.25 13.2334 cft

Trench for Wall Footings: cft


Along Grid A ( 1-2), (2-4) 1 11.25 2 0.25 5.625 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid B (1-2), (2-4) 1 10.25 2 0.25 5.125 cft
Along Grid C (1-2) 1 5.75 2 0.25 2.875 cft
Along Grid D (1-2) 1 5.67 2 0.25 2.835 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 11.58 2 0.25 5.79 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 8.17 2 0.25 4.085 cft
Along Grid 4 (A-B), (B-C) 1 5.08 2 0.25 2.54 cft
Extra 1 24 0.25 6 cft
Garage 1 9 9.29 0.25 20.9025 cft
Bedroom 1 10.33 9.58 0.25 24.74035 cft
Kitchen 1 10.33 9.92 0.25 25.6184 cft
Toilet with corridor 1 13.33 9.58 0.25 31.92535 cft
Living room 1 9.5 12.5 0.25 29.6875 cft
Staircase 1 11.33 8.83 0.25 25.01098 cft
279.16 cft

4 Concreting work for RCC(1:1.5:3)


Upto Ground Floor
4.1 Footing vertical portion
Footing (F1) 5 5 5 0.67 83.33333 cft
Footing (F2) 1 6 6 0.67 24 cft
CF1 1 10.83 5 1.67 90.25 cft
CF2 1 15.5 5 1.67 129.1667 cft
CF3 1 10.42 5.08 1.67 88.22267 cft
Footing inclined portion
Footing (F1) 2 15.63 1.00 31.25 cft
Footing (F1a) 3 29.38 1.00 88.125 cft
Footing (F2) 1 21.13 1.00 21.125 cft
SB 1 38.916666667 1 1.67 64.99083 cft

4.2 Foundation Tie-Beam cft


Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.00 15.9375 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.00 15.9375 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.00 15.1875 cft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.00 10.7475 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.00 20.94 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.00 18.81 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid 3 (C-D) 1 7.25 0.75 1.00 5.4375 cft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.00 11.94 cft

4.3 Plinth Tie-Beam cft


Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.00 15.9375 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.00 15.9375 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.00 15.1875 cft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.00 10.7475 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.00 20.94 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.00 18.81 cft
Along Grid 3 (C-D) 1 7.25 0.75 1.00 5.4375 cft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.00 11.94 cft

4.4 BEAM
Beam ( First Floor) cft
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 16.45313 cft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.08 11.64313 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.08 22.685 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.08 20.3775 cft
Along Grid 3 (C-D) 1 7.25 0.75 1.08 5.890625 cft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 12.935 cft
Beam ( Second Floor)
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 16.45313 cft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.08 11.64313 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.08 22.685 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.08 20.3775 cft
Along Grid 3 (C-D) 1 7.25 0.75 1.08 5.890625 cft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 12.935 cft
Beam ( Top Floor)
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 17.26563 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 16.45313 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid 1 ( A-B), (B-C), (C-D) 1 18.17 0.75 1.08 14.76313 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 16.41 0.75 1.08 13.33313 cft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 12.935 cft
Extra 1 25.5 0.75 1.08 20.655 cft Cantilever Beam

4.5 Columns
Columns in Ground floor including
sub struct
12" x 9" columns 13 1 1 12.58 163.5833 cft 9'+3'7"
Column in First Floor
12" x 9" columns 13 1 1 9.00 117 cft
Column in Second Floor
12" x 9" columns 13 1 1 9.00 117 cft
Column in Top Floor
12" x 9" columns 10 1 1 9.00 90 cft

4.6 Slab All 1 2036 0.33 678.5733 cft


Staircase Void Deduction 1 199.6 0.33 -65.8812 cft

4.7 Staircase
Waist Slab 1 4 6.5 3.5 0.33 30.03 cft
Waist Slab 2 2 2 3.25 0.33 4.29 cft
Landing 1 2 8 4.16 0.33 21.9648 cft
Landing 2 4 3.5 3 0.33 13.86 cft
Steps 1 14 0.243 3.33 11.33125 cft
Steps 2 14 0.243 3.5 11.90972 cft
Steps 3 4 0.243 3.25 3.159722 cft

2408.86 cft

5 Flooring
All Floor
5.1 Screeding
Garage 4 9 9.29 334.44 sft
Bedroom 4 10.33 9.58 395.8456 sft
Kitchen 2 10.33 9.92 204.9472 sft
Toilet with corridor 3 13.33 9.58 383.1042 sft
Living room 4 9.5 12.5 475 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Staircase 4 11.33 8.83 400.1756 sft
Extra 1 109.7 109.66 sft Balcony & Projection

2303.17 sft

5.2 Punning
Garage 4 9 9.29 334.44 sft
Bedroom 4 10.33 9.58 395.8456 sft
Kitchen 2 10.33 9.92 204.9472 sft
Toilet with corridor 3 13.33 9.58 383.1042 sft
Living room 4 9.5 12.5 475 sft
Staircase 4 11.33 8.83 400.1756 sft
Extra 1 109.7 109.66 sft Balcony & Projection
2303.17 sft
5.3 Tile work
Kitchen Floor 1 10.33 9.92 102.4736 sft
Kitchen Wall 1 40.5 6.00 243 sft
345.47 sft

6 Formworks
6.1 Upto Ground Floor
Footing F1 5 5 5 0.67 66.66667 sft
Footing F2 1 6 6 0.67 16 sft
CF1 1 10.83 5 1.67 52.76667 sft
CF2 1 15.5 5 1.67 68.33333 sft
CF3 1 10.42 5.08 1.67 51.66667 sft
SB 1 38.916666667 1 1.67 133.3217 sft

6.2 Foundation Tie-Beam


Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.00 58.4375 sft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.00 58.4375 sft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.00 55.6875 sft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.00 39.4075 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.00 76.78 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.00 68.97 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid 3 (C-D) 1 7.25 0.75 1.00 19.9375 sft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.00 43.78 sft
6.3 Tie beam
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.00 58.4375 sft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.00 58.4375 sft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.00 55.6875 sft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.00 39.4075 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.00 76.78 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.00 68.97 sft
Along Grid 3 (C-D) 1 7.25 0.75 1.00 19.9375 sft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.00 43.78 sft
6.4 Beam ( First Floor)
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 59.0625 sft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.08 41.79583 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.08 81.43333 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.08 73.15 sft
Along Grid 3 (C-D) 1 7.25 0.75 1.08 21.14583 sft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 46.43333 sft
Beam ( Second Floor)
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 59.0625 sft
Along Grid D (1-2), (2-3) 1 14.33 0.75 1.08 41.79583 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 1.08 81.43333 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 1.08 73.15 sft
Along Grid 3 (C-D) 1 7.25 0.75 1.08 21.14583 sft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 46.43333 sft
Beam ( Top Floor)
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid B (1-2), (2-4) 1 21.25 0.75 1.08 61.97917 sft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 1.08 59.0625 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 18.17 0.75 1.08 52.99583 sft
Along Grid 2 ( A-B), (B-C), (C-D) 1 16.41 0.75 1.08 47.8625 sft
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 1.08 46.43333 sft
Extra 1 25.5 0.75 1.08 74.205 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark

6.5 Columns
Columns in Ground floor including
sub struct
12" x 9" columns 13 1 1 12.58 654.3333 sft
Column in First Floor
12" x 9" columns 13 1 1 9.00 468 sft
Column in Second Floor
12" x 9" columns 13 1 1 9.00 468 sft
Column in Top Floor
12" x 9" columns 10 1 1 9.00 360 sft

6.6 Slab 1 1836 1502.143 sft

6.7 Slab edge perimeter 1 340.08333333 0.33 112.2275 sft

6.8 Staircase
Waist Slab 1 4 6.5 3.5 22.75 sft
Waist Slab 2 2 2 3.25 6.5 sft
Landing 1 2 8 4.16 33.28 sft
Landing 2 4 3.5 3 10.5 sft
Steps 1 14 0.83 3.33 11.33125 sft
Steps 2 14 0.83 3.5 11.90972 sft
Steps 3 4 0.83 3.25 3.159722 sft

6194.24 sft

7 Brickwork
Brickwork In sub-Structure Works in
7.1
Cm (1:6)
Dwarf wall 9"
Along Grid A ( 1-2), (2-4) 1 21.25 0.75 3.83 61.04063 cft
Along Grid B (1-2), (2-4) 1 21.25 0.75 3.83 61.04063 cft
Along Grid C (1-2), (2-3), (3-4) 1 20.25 0.75 3.83 58.16813 cft
Along Grid D (1-2), (2-3) 1 14.33 0.75 3.83 41.16293 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 27.92 0.75 3.83 80.2002 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 25.08 0.75 3.83 72.0423 cft
Along Grid 3 (C-D) 1 7.25 0.75 3.83 20.82563 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid 4 (A-B), (B-C) 1 15.92 0.75 3.83 45.7302 cft
extra 1 11.42 0.75 3.83 32.80395 cft
473.01 cft
7.2 Brickworks in super structure
Along Grid A ( 1-2), (2-4) 1 63.75 0.75 8.67 414.5344 cft
Along Grid B (1-2), (2-4) 1 63.75 0.75 8.67 414.5344 cft
Along Grid C (1-2), (2-3), (3-4) 1 60.75 0.33 8.67 173.8118 cft
Along Grid D (1-2), (2-3) 1 28.66 0.75 8.67 186.3617 cft
Along Grid 1 ( A-B), (B-C), (C-D) 1 74.01 0.75 8.67 481.25 cft
Along Grid 2 ( A-B), (B-C), (C-D) 1 66.57 0.33 8.67 190.4634 cft
Along Grid 3 (C-D) 1 14.5 0.33 8.67 41.48595 cft
Along Grid 4 (A-B), (B-C) 1 47.76 0.75 8.67 310.5594 cft
extra 1 34.26 0.75 8.67 222.7757 cft

Deduction for opening


Along Grid 1 1 8.75 0.75 8.67 -56.8969 cft
Along Grid 2 1 7.8333333333 0.75 8.67 -50.9363 cft
Deduction for Doors and Windows
Main Door 1 3.5 0.75 7.00 -18.375 cft
Door 1 3.5 0.75 7.00 -18.375 cft
Door 1 10 3 0.33 7.00 -69.3 cft
Door 2 2 2.5 0.33 7.00 -11.55 cft
DW 1 7.4166666667 0.75 7.00 -38.9375 cft
Window (w) 3 6.1666666667 0.75 5.00 -69.375 cft
window 1 (W1) 7 6 0.75 5.00 -157.5 cft
Ventilation 5 3 0.75 2.00 -22.5 cft
7.4 Parapet wall
over all length 1 170 0.33 3.00 168.3 cft
2090.33 cft

8 Plasterworks
8.1 Outer walls
Along North wall 1 21.166666667 30.00 635 sft
Along North wall extra 1 10.75 21.00 225.75 sft
Along east Wall 1 17.25 21.00 362.25 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along South Wall 1 18.916666667 30.00 567.5 sft
Along West Wall 1 26.916666667 30.00 807.5 sft
Along east Wall extra 1 16.25 12.00 195 sft
Deduction for Doors and Windows
Opening (main entry) 1 8.75 8.67 -75.8625 sft
DW 1 7.4166666667 7.00 -51.9167 sft
D1 1 3 7.00 -21 sft
Window1 (w1) 7 6 5.00 -210 sft
2434.22 sft

8.2 Inner Walls


Along Grid A ( 1-2), (2-4) 1 63.75 8.67 552.7125 sft
Along Grid B (1-2), (2-4) 2 63.75 8.67 1105.425 sft
Along Grid C (1-2), (2-3), (3-4) 2 60.75 8.67 1053.405 sft
Along Grid D (1-2), (2-3) 1 28.66 8.67 248.4822 sft Column plaster
Along Grid 1 ( A-B), (B-C), (C-D) 1 74.01 8.67 641.6667 sft
Along Grid 2 ( A-B), (B-C), (C-D) 2 66.57 8.67 1154.324 sft
Along Grid 3 (C-D) 1 14.5 8.67 125.715 sft
Along Grid 4 (A-B), (B-C) 1 47.76 8.67 414.0792 sft
extra 1 34.26 8.67 297.0342 sft
parapet wall 1 170 8.67 1473.9 sft

Deduction for opening sft


Along Grid 1 1 8.75 8.67 -75.8625 sft
Along Grid 2 2 7.8333333333 8.67 -135.83 sft
sft
Deduction for Doors and Windows sft
Main Door 2 3.5 7 -49 sft
Door 2 3.5 7 -49 sft
Door 1 16 3 7 -336 sft
Door 2 4 2.5 7 -70 sft
sft
DW 1 7.4166666667 7 -51.9167 sft
Window (w) 3 6.1666666667 5 -92.5 sft
window 1 (W1) 7 6 5 -210 sft
Ventilation 5 3 2 -30 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark

5966.63 sft
8.3 Ceilings
Garage 3 9 9.29 250.83 sft area
Bedroom 3 10.33 9.58 296.8842 sft area
Kitchen 2 10.33 9.92 204.9472 sft area
Toilet with corridor 2 13.33 9.58 255.4028 sft area
Living room 3 9.5 12.5 356.25 sft
Staircase 1 11.33 8.83 100.0439 sft
Extra 1 90 90 sft Verranda
Slab Edge 1 340.08333333 0.33 112.2275 sft
1666.59 sft

9 Paintwork

9.1 Outer walls


Along North wall 1 21.166666667 30 635 sft
Along North wall extra 1 10.75 21 225.75 sft
Along east Wall 1 17.25 21 362.25 sft
Along South Wall 1 18.916666667 30 567.5 sft
Along West Wall 1 26.916666667 30 807.5 sft
Along east Wall extra 1 16.25 12 195 sft
Deduction for Doors and Windows
Opening (main entry) 1 8.75 8.67 -75.8625 sft
DW 1 7.4166666667 7 -51.9167 sft
D1 1 3 7 -21 sft
Window1 (w1) 7 6 5 -210 sft
2434.22 sft
9.2 Inner Walls
Along Grid A ( 1-2), (2-4) 1 63.75 8.67 552.7125 sft
Along Grid B (1-2), (2-4) 2 63.75 8.67 1105.425 sft
Along Grid C (1-2), (2-3), (3-4) 2 60.75 8.67 1053.405 sft
Along Grid D (1-2), (2-3) 1 28.66 8.67 248.4822 sft
Along Grid 1 ( A-B), (B-C), (C-D) 1 74.01 8.67 641.6667 sft
Along Grid 2 ( A-B), (B-C), (C-D) 2 66.57 8.67 1154.324 sft Column plaster
Along Grid 3 (C-D) 1 14.5 8.67 125.715 sft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Along Grid 4 (A-B), (B-C) 1 47.76 8.67 414.0792 sft
extra 1 34.26 8.67 297.0342 sft
parapet wall 1 170 8.67 1473.9

Deduction for opening sft


Along Grid 1 1 8.75 8.67 -75.8625 sft
Along Grid 2 2 7.8333333333 8.67 -135.83 sft
sft
Deduction for Doors and Windows sft
Main Door 2 0 3.5 0 7 -49 sft
Door 2 0 3.5 0 7 -49 sft
Door 1 16 0 3 0 7 -336 sft
Door 2 4 0 2.5 0 7 -70 sft

DW 1 0 7.4166666667 0 7 -51.9167 sft


Window (w) 3 0 6.1666666667 0 5 -92.5 sft
window 1 (W1) 7 0 6 0 5 -210 sft
Ventilation 5 0 3 0 2 -30 sft
5966.63 sft

9.3 Ceilings
Garage 3 9 9.29 250.83 sft
Bedroom 3 10.33 9.58 296.8842 sft
Kitchen 2 10.33 9.92 204.9472 sft
Toilet with corridor 2 13.33 9.58 255.4028 sft
Living room 3 9.5 12.5 356.25 sft
Staircase 1 11.33 8.83 100.0439 sft
Extra 1 90 90 sft
Slab Edge 1 340.08333333 0.33 112.2275 sft
1666.5856 sft

10 Woodwork
c
10.1 Framework
Main Door 1 17.5 0.25 0.33 1.44375 cft
Door 1 17.5 0.25 0.33 1.44375 cft
S.N. Description of work No. Area Length Breadth Height Quantity Total Unit Remark
Door 1 10 17 0.25 0.33 14.025 cft
Door 2 2 16.5 0.25 0.33 2.7225 cft

DW 1 21.42 0.25 0.33 1.76715 cft


Window (w) 3 22.24 0.25 0.33 5.5044 cft
window 1 (W1) 7 22 0.25 0.33 12.705 cft
Ventilation 5 10 0.25 0.33 4.125 cft
43.74 sft
10.2 Shutter work
Main Door 1 3.5 7 24.5 sft
Door 1 3.5 7 24.5 sft
Door 1 10 3 7 210 sft
Door 2 2 2.5 7 35 sft

DW 1 7.4166666667 7 51.91667 sft


Window (w) 3 6.1666666667 5 92.5 sft
window 1 (W1) 7 6 5 210 sft
Ventilation 5 3 2 30
678.42 sft

11 Rebar as per bar sechudle 6223.50 kg

12 Steel railing for staircase 1 35 35 35.00 rft

Rebar Works
Vol of % of
Items Concrete Steel Steel in KG
Footing 620.46 0.8 1104.177
Column 487.58 2 2169.258
Beam 591.58 1.25 1644.953
Slab 612.69 0.8 1090.347
staircase 96.55 1 214.765
2408.86 6223.501