Академический Документы
Профессиональный Документы
Культура Документы
Ministry of Railways
January 2004
1. Introduction 1 of 12
2. Objectives 1 of 12
3. History of Bridge 1 of 12
4. Test Conducted & Parameter Observed 2 of 12
5. Analysis of Data 4 of 12
6. Conclusion 8 of 12
7. Recommendation 9 of 12
8. Acknowledgement 11 of 12
9. References 12 of 12
10. Annexure I (Table 1 to 9 ) 1-10 of 10
11. Annexure II 1 of 1
12. Annexure III 1 of 1
13. Annexure IV 1 of 1
14. Annexure V 1 of 1
15. Annexure VI 1 of 1
16. Annexure VII 1 of 1
17. Annexure VIII 1 of 1
18. Annexure IX ( Figure 1 to 11 ) 1-11 of 11
NON-DESTRUCTIVE TESTING OF BRIDGES No. 355,366,388 &
390 ON MUMBAI DIVISION OF WESTERN RAILWAY
1.0 INTRODUCTION
1.1 The study was undertaken as per advise of CE (Gen.) W. Rly. vide letter
No. DO No. W/65/20 Vol.-IV (W3) dated 14/08/03.
1.2 With reference the to above letter, there were eight bridges for testing. Out
of these, four bridges were having exposed reinforcement. In other four
bridges, no symptoms of corrosion from out side was visible. RDSO
selected the four bridges for testing purpose. Bridges no. 388 & 390 were
having exposed reinforcement and bridges no. 355 & 366 were not having
exposed reinforcement.
2.0 OBJECTIVES
The bridge is 100 years old. The up line girder was replaced by RCC slab
on 31.05.96. According to bridge register (ADEN Surat), slab condition
from 1996 to till date is good.
No speed restriction has been imposed on this bridge. The up line bridge
is RCC slab & the Dn. line is Steel (I-girder). Only up line bridge was
tested.
4.1 Bridge No. 355 up (refer Annexure IX, fig. No. 5):-
4.3 Bridge No. 388 (refer Annexure IX, fig. No. 9 & 10)
4.4 Bridge No. 390 (refer Annexure IX, fig. No. 11):-
Note :- Due to the high level of water in canal and lack of proper testing
arrangements like erection of observation platform by railway, it was not
possible to test and inspect the bottom surface of the slab. Observations
were recorded on the east face of the slab only.
(b) Quality of Concrete:- The recorded pulse velocity values at three test
locations are 4220 m/s, 4370 m/s and 4330m/s . Average pulse velocity of
three measurements is 4306 m/s (refer Annexure I, table No.1). The pulse
velocity indicates good quality of concrete. The measurements are
recorded by semi-direct measurement method.
(b) Quality of Concrete:- The recorded pulse velocity values at three test
locations are 3250m/s, 3200m/s, and 1670m/s. Average pulse velocity of
three measurements is 2706 m/s (refer Annexure I, table No.6). The
measured pulse velocity indicates medium and doubtful quality of
concrete. The measurements are recorded by semi-direct method.
Based on observed data (refer Annexure I, table No.1 & Annexure-II, III),
the quality of concrete is good. The high values of concrete resistivity
indicate no risk of reinforcement corrosion. The measured values of
concrete cover almost match with the drawing values, so no remedial
measures are required at this stage.
The observed pulse velocity values (refer Annexure I, table No.2 &
Annexure-IV,V) confirm, good quality of concrete also the resistivity
values obtained indicate that reinforcement corrosion is not occurring at
this stage. The observed values indicate low concrete cover which may
increase risk of reinforcement corrosion in future. Since the structural
drawings of the bridge are not available, the theoretical values can not be
compared with measured values. However the actual cover recorded is
not sufficient for this region, from durability point of view.
The observed values indicate low concrete cover which may increase risk
of reinforcement corrosion in future. Since the structural drawings of the
bridge structure are not available, the theoretical values could not be
compared with measured values.
The resistivity & potentials measurements (refer Annexure VIII & Annexure
I, table No.8) obtained confirm no reinforcement corrosion but during the
visual inspection, spalling of concrete and signs of rusting of reinforcement
were clearly visible at many locations. The exposed reinforcement at
number of locations was found covered with corrosive layer and had
become brittle. The resistivity & electric potentials values are affected
largely due to unsaturation of structure & non-continuity of reinforcement
bars. Which was quite possible at the tested location, therefore these
results are to be ignored.
7.0 RECOMMENDATION
Low pulse velocity values recorded indicate towards the poor quality of
concrete and also the cover thickness provided is inadequate. These two
factors are mainly responsible for rebar corrosion, which is quite evident
during visual inspection. The concrete quality as well as the cover
thickness is required to be upgraded by adopting suitable measures.
This report is based on the field tests and investigation carried out
by the following team of RDSO research staff under the guidance of Shri
S.C.Gupta Director Bridges and Structures (Testing) RDSO LUCKNOW.
1. J.P.Meena SRE
2. A.K.Chakarborty JRE-I
3. Basudev Kumar JRE-I
4. R.R.Sinha JRE-I
1. ADEN Surat
2. PWI Navsari
9.0 REFERENCE :
Table No.1
Bridge No.-355
Location: - Pulse velocity taken at the center of the top face of the first slab from
western end.
Table No. 2
Bridge No.-366
Location: Pulse velocity taken at the web of the second T- beam from east side.
Table No. 3
Bridge No.-388
Location: - Pulse velocity taken at the bottom of the floor of the box from east
face on second span from Mumbai end.
Table No. 4
Bridge No.-388
Location: - Pulse velocity taken at the bottom of the floor of the box on second
span from west face of Mumbai end.
Table No. 5
Bridge No.-388
Location: - Pulse velocity taken at the bottom of the floor of the box from east
face of UP line on first span from Mumbai end.
Table No. 6
Bridge No.-390
Table No.9
This is the mostly used combined method in field. Both the methods are easy to
perform at site and one can collect large number of data in small interval of time.
This is the most economical combination. The pulse velocity and rebound
number can be combined to obtain multiple linear regression equation with
compressive strength as dependent variable in the form of
Log S = AV + BR C
By putting the values of S, V and R in the above equation and solving the three
equations we get the values of constants A, B and C as follows
A = 0.0000049
B = 0.0283
C = 0.491
Keeping the value of constants A, B and C as above in the original equation and
putting the value of R and V as collected from the field, we get the value of
theoritical compressive strength of the concrete.
Table No.9 (Contd.)
Bridge No.-355
Location: - Reading are taken at the center of the top face of the first slab from
west side on UP line.
MAX: 99kcm
Bridge No.-355
Location: - Reading are taken at the center of the side face of the first slab from
west side on UP line.
88 83 79 83 86 53 57 57 41 52
_
No. of observation: 10
MAX: 88kcm
Bridge No.-366
Location: - Reading are taken on the web of second T- beam from east face.
99 99 99 99 88 99 74
_
No. of observation: 7
MAX: 99kcm
Bridge No.-366
Location: - Readings are taken at center of the web from bottom side of second
T- beam from east face.
69 91 99 99 99 99 99
_
No. of observation: 7
MAX: 99kcm
Bridge No.-388
Location: - Readings are taken from bottom side at second span from west Side.
22 27 24 25
_
No. of observation:
MAX: 27kcm
Bridge No.-388
Location: - Readings are taken from bottom side at first span from east side.
25 77 73 36 34
No. of observation: 5
MAX: 77kcm
Bridge No.-390
85 70 99 99 77 99 99
62 69 69 55 63 77 43
_
No. of observation: 14
MAX: 99kcm