Вы находитесь на странице: 1из 8

Project Management Glossary

T H E V O CA B UL A R Y OF A CH I E V E M E N T

R O N BL A CK

T H E M E N T O R G RO U P

W W W . RO N BL A CK . CO M

8 00 -3 81 -8 686
This glossary is an excerpt from Ron Blacks book,

The Complete Idiots Guide to


Project Management with Microsoft Project 2003,
which is available in bookstores January 2005.

For additional tools, checklists, forms, and articles,


or to subscribe to Rons free Productivity PowerTools e-zine,
go to www.ronblack.com.
1

G L O S S A R Y

activityAn element of work that must be side and activity durations are shown as a
accomplished to complete the project. Also horizontal bar scaled to the length of the
known as a task. activity. Also known as a Gantt chart.

activity duration estimatingEstimating baselineThe scheduled dates, durations,


the number of work periods needed to resources, and costs according to the
accomplish an activity. original plan, used to compare progress.

Activity-On-Arrow (AOA)A network baseline finish dateThe originally


diagramming method that uses arrows to scheduled finish date.
represent activities.
baseline start dateThe originally
Activity-On-Node (AON)A network scheduled start date.
diagramming method that uses nodes or
boxes to represent activities. Budget at Completion (BAC)The
planned total cost of the finished project.
Actual Cost of Work Performed
(ACWP)The total of all costs incurred Budgeted Cost of Work Performed
during a given time period. (BCWP)The total value of activities
actually completed within a given period
Actual Finish Date (AF)The date work according to the planned costs.
on an activity was completed.
Budgeted Cost of Work Scheduled
Actual Start Date (AS)The date work (BCWS)The total value of activities as
actually started on an activity. planned for a given period.

administrative closureFormally closing calendarThe methodology used to


the project in accordance with the schedule workdays, shifts, resources, tasks,
organizations documentation procedures. and the project as a whole. There are four
calendar types in Microsoft Project: base,
arrowThe link between tasks in a project, resource, and task.
network diagram that shows the sequence
of workflow. change in scopeA change in the goals
and objectives of the project after the
Arrow Diagramming Method (ADM)A project has been planned.
network diagramming method in which
activities are shown as arrows. chart of accountsAn accounting
numbering system used to relate project
as-of dateThe date the data was costs to the organizations financial control
collected. system.
backward passCalculating the late charterThe responsibilities and
finish dates and late start dates of activities authorities assigned to the project.
by adding the duration of the successor
task to the dependent task in a network contingenciesAn allowance set aside
diagram. for potential problems to mitigate risk.

bar chartA network diagram of activities


where the tasks are listed down the left

Ron Black, 2004 y WWW .RONBLACK.COM y RONBLACK@THEMENTORGROUP.COM y 800-381-8686


2

contingency planningA planning dummy activityA drafting convention


technique used to identify and mitigate used as a placeholder to show a logical
potential problems. relationship in a network diagram, but
where no duration is planned.
controlMeasuring, evaluating, and
taking action based on actual performance Duration (DU)The number of minutes,
compared to the planned performance. hours, weeks, or months required to
complete an activity or task.
cost estimatingEstimating the total
direct and indirect expenses required to Early Finish Date (EF)The earliest
achieve project activities. possible date an activity can be completed
based on the schedule.
Cost Performance Index (CPI)
Budgeted costs divided by actual costs Early Start Date (ES)The earliest
(BCWP/ACWP). Sometimes used to predict possible date an activity can start based on
the projects completed costs. the schedule.

Cost Variance (CV)The difference between Earned Value (EV)The total cost of
actual and estimated costs of an activity. work calculated by comparing planned
work for a period against actual work
crashingCompressing the projects accomplished.
schedule through extraordinary means.
Also known as expediting. effortThe amount of work units needed
to complete an activity.
critical activityAny activity that is part
of the longest sequence of tasks from estimateA forecast of cost or duration
project start to project end. If the for an activity.
completion of a critical activity is delayed,
the total duration of the project is delayed. Estimate at Completion (EAC)The
expected total cost of an activity or project
critical pathThe series of tasks in a when finished.
network diagram that requires the most
time to complete. Activities on the critical Estimate to Complete (ETC)The
path have zero slack or float. expected additional cost needed to
complete an activity or project.
Critical Path Method (CPM)A project
scheduling technique where the duration Event-on-NodeA network diagramming
of the longest complete series of tasks from technique in which activities are shown as
project start to project completion is used nodes or boxes and workflow logic is
to predict project duration. shown with arrows. The original Program
Evaluation and Review Technique used
Cross functional teamA workgroup event-on-node to diagram workflow.
that embodies diverse professions, skills, or
expertise. expeditingShortening the duration of a
task or project by any means available.
deliverableAny specific, measurable Usually increases costs. Also known as
project accomplishment or outcome. crashing.

dependencyTerm used to describe the fast trackingCompressing a projects


relationship between two or more activities schedule by running tasks in parallel that
or tasks. See logical relationship. are normally run in sequence, such as

Ron Black, 2004 y WWW .RONBLACK.COM y RONBLACK@THEMENTORGROUP.COM y 800-381-8686


3

beginning construction before design is leadDescribes the advance of a


complete. Usually increases risk. successor tasks start from its predecessors
start or finish. See also lag.
finish dateThe actual, planned,
estimated, early, or late date an activity is levelingThe process of effectively
to be completed. allocating resources to tasks.

Finish-to-Finish (FF)The workflow linkThe arrow that shows the logical


logic between two tasks in which the work sequence relationship between tasks.
dependent task may not finish until its
predecessor task is finished. logicThe workflow sequence.

Finish-to-Start (FS)The workflow logic logic diagramA projects network


between two tasks in which the dependent diagram.
task may not start until its predecessor task
is finished. logical relationshipThe workflow logic
between two project tasks or activities (the
floatThe amount of time a task may be predecessor and the dependent tasks)
delayed without pushing out the project described as a finish-to-start, finish-to-
finish date. Also called slack. finish, start-to-finish, or start-to-start
relationship. Also know as dependency.
forward passThe calculation of the
early start and early finish dates of all milestoneA point in the network
activities in the network diagram. diagram that shows significant
accomplishment.
Free Float (FF)The amount of time a
task can be delayed without pushing out monitoringCollecting progress
the start of any immediately following information for judging progress against
activities. Also called free slack. the plan.

Free SlackSee free float. network diagramA diagram showing


the workflow sequence of all tasks
Gantt ChartA network diagram of required to complete a project.
activities in which the tasks are listed down
the left side and durations are shown as a network logicThe workflow sequence
horizontal bar scaled to the length of the as shown by a network diagram.
activity.
network pathAny series of tasks in a
lagDescribes the delay of a successor network diagram.
task from its predecessors start or finish.
See also lead. overlapThe concurrent period of time
two or more parallel tasks share. See lead,
Late Finish Date (LF)The latest a task lag, and parallel task.
may finish without delaying the projects
finish date. noncritical taskAny task or activity that
does not fall on the longest (critical) path.
Late Start Date (LS)The latest a task
may begin without delaying the project Over-allocationThe condition having of
finish date. too much work for the available resource
capacity.

Ron Black, 2004 y WWW .RONBLACK.COM y RONBLACK@THEMENTORGROUP.COM y 800-381-8686


4

parallel taskA task undertaken during project managementThe process of


the same time period as another task. undertaking and completing a course of
action to meet the stated goals and
pathA series of activities in a network objectives of an endeavor.
diagram.
Project Manager (PM)The person
path floatSee float. responsible for planning and implementing
the project.
Percent Complete (PC)Estimate of
progress derived by comparing the amount Remaining Duration (RDU)The
of work completed with the amount of amount of time required to complete a
work planned for an activity or project. task.
PERT ChartA critical path scheduling Request for Proposal (RFP)A
method using an activity-on-node network solicitation for proposals from potential
diagram and the Program Evaluation and vendors for good or services.
Review Technique of weighted average
duration estimates. Request for Quotation (RFQ)A
solicitation for quotations from vendors for
phaseA major subunit of a projects goods or services.
work or set of project deliverables.
resource levelingApplying available
Planned Finish Date (PF)The resources to a project to determine task
scheduled finish date of the project. start and finish dates, project duration, and
resource utilization rates.
Planned Start Date (PS)The scheduled
start date of the project. resource planningEstimating the
people, equipment, and material resources
precedence relationshipThe required to complete a project.
description of two or more tasks workflow
sequence. resourcesAll the people, equipment,
materials, and money required to complete
predecessor activityThe task which a project.
immediately precedes the dependent task.
risk assessmentEvaluating potential
programA group of projects that are risks and their affect on the project.
related and managed in a cohesive way.
S-CurveThe graph of cumulative project
Program Evaluation and Review expenditures plotted against time.
Technique (PERT)A critical path
method of scheduling a project using the Schedule Performance Index (SPI)
weighted average method to estimate The work performed compared to the
durations. work scheduled (BCWP/BCWS).
projectThe implementation of a strategy Schedule Variance (SV)The actual
to create a specific, measurable outcome. versus the planned cost, duration, work, or
percentage complete of an activity.
project charterThe document that
authorizes a project manager to use the Scheduled Finish Date (SF)The date
organizations resources and outlines the the task was to be completed according to
intended outcomes of the project. the plan.

Ron Black, 2004 y WWW .RONBLACK.COM y RONBLACK@THEMENTORGROUP.COM y 800-381-8686


5

Scheduled Start Date (SS)The date the triple constraintsThe interrelationship


task was to be started according to the of a projects time, cost, and performance
plan. elements. Understanding their relative
importance facilitates decision making and
scopeThe description of the projects problem solving. Usually described as a
intended breadth and depth. driver, middle, and weak constraint.
scope changeAlterations in the projects Under-allocationThe condition having
goals or objectives at any time after the of too much resource capacity for the
project has been initiated. available work.
slackThe amount of time a task or path Work Breakdown Structure (WBS)
can slip without causing the project to The decomposition of the projects goals
finish late. See float. and objectives into increasingly detailed
units of work, eventually identifying all
slopeThe dependent variables that tasks that are essential to the projects
describe the change in cost and duration successful completion.
when expediting (crashing) a task. Used to
compare alternate methods and calculate Z
the total costs required to shorten a
projects duration. start dateThe actual, A B O U T R O N B L A C K

planned, early, late, or baseline date a task


is scheduled to start. Throughout 30 years of business leadership
experience, Ron has built a reputation for
Start-to-Finish (SF)The workflow logic delivering down-to-earth, results-proven
between two tasks where the dependent content in all he does. As a business
task may not finish until its predecessor consultant, author, and award-winning
task has started. speaker, he works with top managers who
want to move their organizations to new
Start-to-Start (SS)The workflow logic levels of performance and entrepreneurs
between two tasks where the dependent launching new products and services.
task may not start until its predecessor task
has started. P O P U L A R T O P I C S

successor activityThe activity that Project Management Fundamentals


follows a predecessor activity. The Elements of Success
target scheduleThe baseline schedule. Acrobatics for OverachieversThe Art
and Science of Managing Multiple Projects
Target Finish DateThe baseline date and Priorities
work is scheduled to finish.
Tools of Change: People and Process
Target Start DateThe baseline date the Essentials of Managing Change
work is scheduled to start.
Managing Projects the Easy Way with
taskAn element of work which must be Microsoft Project

accomplished to complete the project. Also


known as an activity. Creating an Environment for Project
SuccessExecutive Briefing
Total Float (TF)The amount of time a
task or path can be delayed without Building the Championship Team
delaying the completion of the project. Workshop for Leaders

Ron Black, 2004 y WWW .RONBLACK.COM y RONBLACK@THEMENTORGROUP.COM y 800-381-8686


Ron Black
The Mentor Group
www.ronblack.com
ronblack@thementorgroup.com
503-618-8703
800-381-8686 toll-free in USA

Вам также может понравиться