Академический Документы
Профессиональный Документы
Культура Документы
However, Puzon failed to comply even after Had the appellant not been remiss in his
formal demand letters were sent to him. obligations as partner and as prime
contractor of the construction projects in
Thereafter, Puzon (as the primary contractor question as he was bound to perform
of the projects) wrote terminated the pursuant to the partnership and subcontract
subcontract agreement with the partnership agreements, and considering the fact that
to which he is also a partner. (November 27, the total contract amount of these two
1957) projects is P2,327,335.76, it is reasonable to
expect that the partnership would have
earned much more than the P334,255.61