Project applied under EGAT PPA Project applied under PEA PPA
NED’s (55 MW) has already 51 projects (7,674 MW) with SCOD
been approved and signed the 340 projects (1,604.7 MW) obtained the approval
PPA on March 2010 with PPA signed
1 project (30 MW) has already 60 projects (187.7 MW) were approved
been approved 114 projects (544.6 MW) is still under approval
7 projects (451 MW) are still process
under approval process
LAND - Securing 1,140 rai or 2 km2 land
option for project site with ~ 5 kWh / SQM /
day solar resource
1/3 1/3 1/3 PPA - 55 MW Net AC (signed with EGAT), &
8 MW (signed with PEA)
Adder – fully allocated for 55 MW and 8
MW
Financing – Signed with ADB (USD70
million and three domestic lenders – KBank,
73 MW 8 MW Bangkok Bank and Siam Commercial Bank
Solar Solar
Flat Panel Technology Supply &
Project Thailand Solar Project Construction Contract with SHARP &
ITD
Location Central Thailand (2hr drive from
BKK) EIA Report Completed. 4 public hearing
conducted with high acceptance level.
Capacity 73 MW DC (55 MW Net AC)
BoI Certificate Obtained with full
Off-take Non firm EGAT PPA with Adder
privilege includes foreign ownership and tax
Adder THB 8 / kWh for 10 year exemption.
Total Tariff USD 0.36 / kWh (on-p); USD 0.3 / CDM - Asiatica engaged as CDM advisor
kWh (off-p)
Overall view
• The result from 3 sources above is well correlated with
the onsite measurement
• When assessing irradiation data, it is recommended to
have a long term (10-20 y) to assess the variability of
the solar resource and to be able to have a reliable
average with a clear assessment of its variation
• IE have recommend to use the combination of
available resource as shown in table
• IE doesn’t mention onsite data due to a very short
term period, onsite just only indicative to reference
with other sources and collect for the future use.
“The weighted average result combines data sets consisting of 57 years of measurement, taking
into account the advantage of longer-term satellite data, which contribute to about 60% of the
final value, and terrestrial data ” 4
Land Area: 1100 rai or 172 ha
Csi TF
Panel area 1.49m2 1.42m2
Total panels 541,926 350,208
Total panel area 52ha 77ha
Panel rating 210W 128/135W
Total DC rating 73..54 73.16
Annual MWh AC 108,283 111,339
Technology Thin Film Polycrystalline
Resource Assumptions
Panel Tilt2 Degree 10 15
Technology Assumptions
Number of Panels / Dishes 541,926 270,400
Rated Capacity per Panel / Dish Watts DC 135 270
Temperature Coefficient % -0.24% -0.47%
Output Calculations
Solar Radiation to Hit Solar Farm kWh / day 3,988,695 2,727,777
Conversion Efficiency (to DC) % 9.50% 13.92%
Loss Assumptions
Efficiency Factor Adjusted for Temp 87.78%
Inverter Efficiency 97.00% 98.40%
Incident Irridation Loss 98.00% 99.00%
Loss Due to Dirt 98.00% 98.00%
PV Loss Due to Irradiance Deviation 99.00%
DC Wiring Loss 98.00% 98.98%
Module Array Mismatch Loss 96.50% 98.00%
AC Wiring Loss 99.92%
Transformer Loss 96.6% 97.71%
Total efficiency 80.57% 78.57%
Weighted Factor
Si 1 Si 2 TF CPV
10
• Solar Manufacturing Industry
• EPC contracting is a foreign concept
• When dealing with most manufacturers/ suppliers, it is
difficult to explain the rationale of an EPC contract
• Concept of 100% liability for the full contract price is a new
risk scenario
• Liquidated damages (LDs) for events of default is
problematic at best
• Warranty periods for suppliers tend to be fairly short, getting
them to accept 2 years minimum with another 4 or 5 years
latent defect liability is met with great resistance.
• Forming a Consortium
• Finding a partner that the manufacturer can trust
• Consortium leader? One with the highest value contract or
the one with most experience?
• Joint and several liabilities – can the manufacturer’s senior
management / shareholders commit to this?
• And what actually does it mean? (manufacturers very unclear
and distrustful)
• Splitting contracts into off-shore and on-shore contracts. Do
suppliers understand the tax implications of their contractual
arrangements?
• Negotiating a contract
• 400 page contract document not like a Purchase Order.