Вы находитесь на странице: 1из 7

PEER-R EV IEW ED

Reduced Validation Effort


Approaches Used and Lessons
Learned
Elaine Kelleher and Anne Greene

INTRODUCTION How can the validation process be streamlined in


This article summarizes useful approaches used order to avoid the same pit-falls in the next project?
to reduce validation effort and lessons learned in Criteria for measuring success were established based
the process of delivering a project. A case study is on a review of previous projects. The following key
presented illustrating the execution and delivery of variables must be controlled in order to streamline
validation projects. the validation effort:
The aim of every pharmaceutical company today Validation approach. The approach to be adopted
is to deliver a drug to the market as fast as possible must be defined, implemented, and supported at
without risk to the patient, while complying with the the initiation of the project.
requirements of regulatory bodies and current good Time. Adequate time must be allocated to ensure
manufacturing practices (CGMPs). In order for a that each stage of the project lifecycle is delivered
company to have a competitive advantage, companies on schedule.
must review their approaches to delivering projects Resources. Resource planning must be adequately
and find a shorter path to the end-goal. In the global performed at the initial stage of the project to sup-
pharmaceutical arena, timing is critical for success. port all validation phases of the project, depen-
It is with this in mind that industry and regulatory dent on the approach.
agencies have created project management, integrated C ost. The project must be sufficiently budgeted
commissioning and qualification (ICQ), risk man- from the onset of the project, while building in
agement, and science-based approaches based on contingency for potential issues.
process understanding. The challenge facing new and Quality. Quality must not be compromised based
existing companies is which approach to validation on progressive approaches adopted throughout
to take (i.e., the traditional approach or the more each phase of the project.
progressive approaches). If the latter option is taken
the company must be willing to change its mind-set The following case study links each one of these
and also be willing to justify and defend the progres- key factors into an overall validation project (i.e., the
sive approach to all auditing parties (e.g., regulatory qualification of a new sterile fill finish facility).
bodies, corporate, and customers).
CASE STUDY
BACKGROUND This case study reviews and discusses the beneficial
This article presents the experiences of the author in approaches implemented by the company to reduce
the execution and delivery of validation projects. The the validation effort. The lessons learned were cap-
execution of numerous projects led to the question: tured in order to avoid problems in future projects.

[
For more Author ABOUT THE AUTHORS
information, Elaine Kelleher is the Senior Validation Manager for the Sterile Fill Finish Facility at Elan in Athlone,
go to Ireland. She can be reached by e-mail at Elaine.Kelleher@elan.com. Anne Greene, Ph.D., is program
ivthome.com/ director for the MSc in Pharmaceutical Validation Technology program at the Dublin Institute of Tech-
bios nology. Anne can be reached by e-mail at anne.greene@dit.ie.

Journal of Validation T echnology [Autumn 2008] 77


PEER-R EV IEW ED

Figure 1: Overview of risk management approach.


minimal
Audits resulting in positive feedback and com-
Risk assessment
Hazards identified, risk estimated, ments that the company is compliant in all
decision re. risk acceptability made operations and up to date with current trends
in industry.
Risk management

Risk Contol The following are lessons learned and pitfalls to be


Periodic avoided with respect to managing risk:
Risk reduction or risk maintenance controls
review
initiated until risk is acceptable or D  o not implement a risk management program
adequately controlled without a thorough training program to teach
participants. Never assume that all personnel
Qualification and validation know how to use the risk assessment tools.
Requirements are determined and actioned Get senior management buy-in from the onset;
this establishes a basis of acceptance from all
departments.
Risk knowledge is communicated C onducting a risk assessment can be a daunting
task if the appropriate people are not participants.
Request vendor participation in risk assessments.
Approach 1: Risk Management This reduces the execution time based on the ven-
A risk management approach (see Figure 1) was under- dors expertise of the equipment/system.
taken during the project lifecycle specific to the quali- C ounteract, through training and mentoring, the
fication/validation activities. This approach included negativity that can arise from a lack of under-
the use of risk assessment tools (e.g., IMPACT) to standing of the process and the belief that risk
evaluate the impact of the system on product quality, assessments are additional phases in the lifecycle
to evaluate the criticality of the components of a direct of the project. If unchecked, this negativity can
impact system as they relate to product quality, and slow the process down and risk assessment is then
determine the level of qualification required. Fail- seen as a hindrance rather than an aid.
ure modes, effects, and criticality analysis (FMECA)
assessments were then conducted on all direct Approach 2: Integrated Commissioning
impact systems/equipment to identify potential and Qualification
failure modes, risks (i.e., consequences and effects) The ICQ approach adopted by the company allowed
associated with these potential failure modes and the installation qualification (IQ) to progress concur-
what controls should be put in place to reduce the risk. rently with the commissioning phase and the opera-
The assessments identified critical process parameters tional qualification (OQ) to progress concurrently
associated with the controls and recommended any with the site acceptance testing (SAT) phase. The IQ
specific qualification requirements. and OQ documents were independent documents
The following are some of the benefits of risk and the approach was such that the qualification was
management: a standalone documentation process independent of
A documented justification based on sound sci- any factory acceptance testing (FAT), commissioning
entific proof for not qualifying every piece of or SAT documentation. Figure 2 provides an overview
equipment, system, and component of the approach.
A reduction in the overall qualification testing The following are some of the benefits of ICQ:
A reduction in qualification testing due to sys- A reduction in the duplication of testing
tem/equipment changes Reduced execution time on site thereby reducing
A better understanding of the systems being quali- qualification costs
fied through the knowledge gained during the Through the witnessing of integrated OQ testing
execution of a risk assessment and the impact vendor expertise is passed on about the systems
of failures and equipment to validation personnel
Reassurance that all potential failures have been Agreement up front through the approval of the
identified and controlled and if a failure occurs validation project plan (VPP); therefore, no rule
in the future the risk to project quality will be changing during qualification.
78 Journal of Validation T echnology [Autumn 2008] iv thome.com
EL A INE KELLEHER A ND A NNE GR EENE

Figure 2: Overview of ICQ approach.

PO placed Mechanical Commissioning System


completion report handover
URS
approval
Design
phase
DQ
execution
Fabrication

FAT

Installation

Commissioning

IQ execution

SAT

OQ execution
PQ execution

In some instances, vendor participation once the lot of mechanical and software changes. These
vendor requirements are out-lined at the start of changes would have been eliminated if there had
the project. been more input from the system owners and
The following are lessons learned and pitfalls to be product development group at the early design
avoided in regards to ICQ: stage of the project.
Once the IQ starts, any change made during com- The framework required to support the ICQ
missioning may impact the IQ section already approach for the first time requires the commit-
executed, thereby causing more document genera- ment of resources into the early phases of the
tion to re-execute the impacted sections project, if not this leads to the late approval of
The reduction in the duplication of testing during documents resulting in delays in the execution of
the OQ phase reduces the number of production the IQ and a direct impact on the schedule.
runs performed on the equipment, which typi- C ompany personnel did not anticipate that ven-
cally give the systems a good shake-down. Due dors did not routinely utilize good documen-
to the reduced number of cycles, performance tation practices. Time delays were encountered
problems may be encountered during the cycle during execution because time was required to
development and performance qualification (PQ) train vendors to use good documentation prac-
phases when the vendors have left the site. tices that are required to support ICQ.
Because of the aggressiveness of the schedule, Observing vendor activities and witnessing ven-
vendors executed parallel qualifications, which dor testing was resource intensive.
resulted in the equipment not being available
to the operations group for familiarisation and Approach 3: Leveraging of Testing
training. When the equipment is made available Leveraging of vendor testing to support CGMP critical
to operating personnel, delays are encountered qualification protocols, with respect to the quali-
because of lack of experienced personnel operat- fication of aseptic processes, was through a wrap
ing the equipment and training. For future proj- around approach. A gap analysis was performed
ects, more operator involvement is recommended on the vendor qualification documentation for IQ/
during qualification. During the integrated OQ computer installation qualification (CIQ) and OQ/
and cycle development phases of the project it computer operational qualification (COQ) against
transpired that some of the systems did not sup- the minimum company test requirements for IQ/CIQ
port the process intended and that resulted in a and OQ/COQ as defined in the site validation master
Journal of Validation T echnology [Autumn 2008] 79
PEER-R EV IEW ED

plan (VMP). Any testing deficiencies were highlighted Validation Project Plan
and were captured in the amended vendors proto- Rather than the top-level VPP, which provides an
cols if part of the scope; otherwise, deficiencies were overview of the project, a more detailed VPP was
addressed in the company wrap around protocols. approved. Whenever disagreement arose on the
The concept of the wrap around protocol meant that approaches applied and decisions made, the VPP was
any commissioning and SAT vendor testing could be used to verify the approaches that all departments had
leveraged into the IQ/CIQ and OQ/COQ phases of agreed upon. Examples included the following: When
the qualification. In order for this approach to work, to perform and approve risk assessments; trying to
a very robust change request system was implement- force qualification of indirect/no impact systems; the
ed. Under this system, once IQ started, all changes stage at which standard operating procedures (SOPs),
were through the company project change control calibration system, and preventative maintenance
system. During qualification, if required, all vendors system had to be implemented in the project; and
captured their changes through the vendors own what testing the protocols captured.
change control system, but the same changes were
also captured through the company project change User Requirement Specification/Design
control system. Qualification
In an effort to reduce failures during the PQ phase In order to streamline the design phase of the proj-
of the protocol and to support the US Food and Drug ect, the document requirements were studied. In
Administrations aspiration of demonstrating process previous projects the user requirement system (URS)
control and process improvements, cycle development and design qualification (DQ) documents were
phases were executed prior to PQ for key systems. considered separate documents, but to streamline
The objective of cycle development was to conduct activities they were combined into a single URS/DQ
optimisation studies to determine the critical process document. This document, when implemented at
variables and how to control them within achievable the purchase requisition stage of the project, clearly
limits. Process set points were determined based on identified the companys expectations to the vendor
the equipment and process capability. The cycle devel- in the DQ phase.
opment phase identified and resolved potential pro-
cessing, equipment, sampling, and testing problems Integration of Protocols
before entering the PQ phases. Cycle development For the traditional approach to qualification of com-
protocols were approved to full GMP standards to puterised systems, separate CIQ and COQ protocol are
allow the leveraging of testing to support the PQ pro- executed causing double time spent in the drafting,
tocol. This approach reduced the duplication of tests review, and approval cycle. In order to reduce time,
used to develop the cycles specific to equipment by the company combined the CIQ protocol with the IQ
reducing the testing, reviewing, and approving burden protocols and the COQ with the OQ protocol, while
which in turn simplified the overall PQ process. still allowing parallel execution of the phases. To
Starting change requests at the commencement of further streamline the process the company combined
IQ tied the project up in a mountain of paperwork. the IQ and OQ protocols into a single IOQ document
This paperwork burden halted progression of commis- for less complex systems (e.g., freezers, cold-rooms,
sioning while validation and QA approval was sought heal sealers, balances, and filter integrity testers).
for changes on items that were critical (e.g., updating
specifications and drawings). The experience led Templates
management to accept one update at the end of com- The project team learned from previous projects that
missioning and as built checks of all specifications each protocol originator had their own interpretation
and drawings prior to handover. of what each protocol should contain. This led to
inconsistencies throughout qualification documenta-
Approach 4: Qualification Documentation tion covering very complex protocols to very vague
A good documentation management system is the protocols. The team generated protocol templates
foundation to support the approaches presented in specific to each phase of the qualification lifecycle.
an effort to reduce validation. The application of a On implementation of these templates, a review was
good documentation management system will in conducted to verify the reduction in time spent during
itself reduce the validation effort. protocol generation. The Table shows this reduction in
80 Journal of Validation T echnology [Autumn 2008] iv thome.com
EL A INE KELLEHER A ND A NNE GR EENE

effort and time for a typical OQ/COQ protocol for a Table: Reductions in time.
complex piece of equipment (e.g., filling machine). Prior to template Template implementation
Activity # of days # of days
SAP System Drafting 3 days 2 days
The systems, applications, and products in data pro- Review 5 days 2 days
cessing (SAP) system was utilised for the issuing of
Address comments 1 day 1 day
documentation numbers linked to an overall project
number and the tracking of these documents for full Review 2 days 0 days
traceability of the documents associated with quali- Approve 1 day 1 day
fication. A documentation controller was appointed Total 12 days 6 days
to monitor the validation module of the SAP system.
The duties of the controller included the following:
Issuing SAP numbers for master documents post execution.
Deviations and change requests By utilizing interim approvals and a QA approval
Issuing SAP numbers for protocols in execution to proceed to the next phase of qualification, all
L inking ownership of each document to the testing associated with each phase of the project
originator was completed to a very high standard and was
Updating the systems as to the status of each able to progress forward.
document (i.e., approved and archived) The following are lessons learned and pitfalls to
Recording the filed location of each approved be avoided:
document A lthough the qualification testing template system
Issuing a weekly status report on all documenta- reduced documentation time spent in the review
tion within the system. and approval phase of the project, the amount of
testing and the same sets of tests were being applied
This system reduced the time spent on admin- to simple equipment pieces as to complex systems/
istration of overall validation effort. Benefits also equipment. For future projects the company will
included prevention of unapproved documents being review the testing requirements to be applied to
misplaced; providing top-level visibility on the status simple versus complex systems/equipment from
of each document thus enabling the originator to take the perspective of nice to have versus a regula-
responsibility and advance the documents through tory requirement. The approved templates will be
the system as expediently as possible. used as a guide but will not dictate what testing is
otherwise more appropriate.
Approach 5: Qualification Testing By having the vendors execute most of the test-
The level of qualification testing performed on a direct ing, company operations personnel did not get
impact system/equipment was determined through much time to become familiar with the systems/
risk assessment. The tests to be performed at each of equipment and thus gain the important hands
the qualification phases were outlined in the approved on experience. As a result, time was lost because
templates that were created by the validation team. operators still needed the hands on time to learn
Based on the fact that an ICQ approach was used, the the operation of the equipment. In future proj-
majority of testing was executed by the vendors and ects, the company will use operators during the
witnessed by company personnel. ICQ approach allowing the operators to operate
The following are some of the benefits of the the systems/equipment while the vendors execute
approach: the testing.
Because vendors were executing the tests, trouble By witnessing the testing, the resource requirement
shooting time was greatly reduced because the doubled. On future projects, additional witness-
vendor was on hand to help solve the issues ing resources must be planned for at the start and
C ompany personnel witnessed all testing thus throughout the project.
achieving a high level of CGMP compliance. Because an engineering firm was contracted to
All documentation was completed and attached execute the project as far as the OQ stage, there was
at the time of testing which reduced the subse- a fear that once the project was handed over to the
quent effort of trying to locate documentation company to execute the PQ phase, operating prob-
Journal of Validation T echnology [Autumn 2008] 81
PEER-R EV IEW ED

Figure 3: Deviation/change request cover page.


Approach 6: Deviation And Change
Control Systems
DEVIATION/CHANGE REQUEST FORM The deviation/change request system is initiated once
Reference Number- 00000000001 all mechanical checks are complete and the IQ phase
commences. Any changes made to the equipment/
Form Issued By/Date: _________________________ system design or functionality from this point must
SECTION A be done formally through the project change request
system. At the start of the project the deviation and
Originator: Date of request: 10.07.2007
change request forms were two different forms. To
Document Name reduce the time spent in generating different forms
Document Section and getting two sets of approval signatures, the
team decided to link the two together into one form
Document Number
because, in the majority of cases, a change request was
Equipment/Area/Method ID
always linked to a deviation. The form contains an
Equipment/Area Number IMPACT assessment section to capture any qualifica-
tion impacts as a result of the change and the require-
SECTION B ments for re-qualification or requests for additional
Change request or deviation description and proposed action documentation or certification (see Figure 3).
Deviation Change request
Approach 7: Role Of Departments And
Test methodology Acceptance criteria (include any retest requirements)
External Contractors
In order for a validation project to be successful, the
responsibilities of each department and external con-
tractor must be adequately defined. Assumptions leave
gaps in responsibilities.
The following are lessons learned and pitfalls to
be avoided:
Specifically define the responsibilities of each
member of the validation project team. As the
lems could be encountered. To reduce this risk, schedule slips and the project becomes more
much of the performance testing was performed aggressive, a culture of shifting responsibilities
at the OQ stages for some systems/equipment and develops. This can be largely prevented by hav-
then repeated in PQ. This duplication of testing ing the responsibilities defined and approved up
added additional time to the schedule. front in the VPP.
If a deviation was raised and a test had to be repeat- Specifically identify vendor responsibilities
edregardless of the testthere was a requirement (e.g., documentation requirements and CGMP
to repeat it three times even if the initial test was requirements for vendor IQ/CIQ and OQ/COQ
to be performed only once particularly during execution). Obtain read and understood sig-
OQ/COQ testing. In future, the test failures will natures prior to procurement of equipment and
be informally risk assessed to determine the re-test systems.
procedure. This will be stated in the VPP. Specifically define the role of the quality assur-
For complex systems/equipment, cycle develop- ance (QA) department with respect to QA require-
ment was performed prior to PQ execution. After ments during the QA review and approval of the
successful cycle development and PQ executions validation documentation.
and release of the equipment into routine produc- Require QA attendance at the FATs as the FAT pro-
tion, failures were observed. Although exhaustive vides an excellent platform for personnel involved
testing was performed during cycle development, in the project to become more familiar with the
it demonstrates that for future projects additional equipment and systems.
time needs to be spent establishing the edge of Do not delegate responsibility of the schedule to
failure of cycles qualified in order to build safety the external contract group. Instead, appoint an
factors into operational parameters. independent scheduler who will produce a real-
82 Journal of Validation T echnology [Autumn 2008] iv thome.com
EL A INE KELLEHER A ND A NNE GR EENE

istic schedule that reflects the true time require- Compliance, 10(4): 12- 35, 2006.
ments of each task. 8. FDA, Pharmaceutical cGMPs for the 21st CenturyA Risk-
Based Approach, 2004. Available from http://www.fda.
CONCLUSIONS gov/. [25 June 2007].
The case study presented in this paper demonstrates 9. James, P., Integrated Validation: A Way of Streamlining
how the defined approaches, when appropriately Projects to Reduce Project Validation Time and Cost,
implemented, can reduce the overall validation effort Pharmaceutical Engineering, 18(1): 72-80, 1998. JVT
(i.e., time and thus cost), without sacrificing qual-
ity. Realistic budgeting for resources and scheduling ARTICLE ACRONYM LISTING
is a critical part of validation success. Progressive CGMP Current Good Manufacturing Practice
approaches to validation can considerably reduce the CIQ Computer Installation Qualification
validation effort. As P. James states in his article on COQ Computer Operation Qualification
integrated validation (9) validation can be carried CR Change request
out simply, efficiently, and logically in a planned and DQ Design Qualification
organised manner with predictable results. FAT Factory Acceptance Testing
FMECA Failure modes, effects and criticality analysis
ICQ Integrated Commissioning and Qualification
REFERENCES IOQ Installation Operational Qualification
1. FDA, Guidance for Industry, Sterile Drug Products Pro- IQ Installation Qualification
duced by Aseptic ProcessingCurrent Good Manufacturing ISPE International Society for Pharmaceutical
Practice, 2004, Available from http://www.fda.gov. Engineering
2. EU-GMP: Chapter 5Production, Rules and Guidance OQ Operational Qualification
for Pharmaceutical Manufacturers and Distributors, PQ Performance Qualification
2007. Available from http://www.mhra.gov.uk. QA Quality Assurance
3. EU-GMP: Annex 1Manufacture of Sterile Medicinal SAP Systems, Applications and Products in Data
Products, Rules and Guidance for Pharmaceutical Processing
Manufacturers and Distributors, 2007. Available from SAT Site Acceptance Testing
http://www.mhra.gov.uk. URS User Requirement Specification
4. EU-GMP: Annex 11Computerised Systems, Rules VMP Validation Mater Plan
and Guidance for Pharmaceutical Manufacturers and VPP Validation Project Plan
Distributors, 2007. Available from http://www.mhra.
gov.uk. ACKNOWLEDGMENTS
5. EU-GMP: Annex 15 Qualification and Validation. Elaine Kelleher thanks her lecturers and classmates
Rules and Guidance for Pharmaceutical Manufactur- in the MSc. in Pharmaceutical Validation Technology,
ers and Distributors 2007. Available from http://www. especially Dr. Anne Greene and Dr. Barry Hatt for
mhra.gov.uk. their guidance on this topic.
6. ISPE, Pharmaceutical Engineering Guides for New and She also thanks Alan MacNeice for his assistance
Renovated FacilitiesCommissioning and Qualification on this subject with respect to the ISPE and her col-
Volume 5, 2001. Available from http://www.ispe.org leagues and management team in lan for their
7. ODonnell, K. and Greene, A., A Risk Management input and support during her Masters Degree espe-
Solution Designed to Facilitate Risk-Based Qualifica- cially Paul Logue, Susan Neenan, Edward Balbirnie,
tion, Validation, and Change Control Activities with Eoghan Gallagher, Marcella OGorman and Caroline
GMP and Pharmaceutical Regulatory Compliance En- Dwyer.
vironments in the EU: Part I and Part II, Journal of GXP

Journal of Validation T echnology [Autumn 2008] 83

Вам также может понравиться