Вы находитесь на странице: 1из 54

10

Surface Mining

INTRODUCTION 60 ft) in the last 35 years and will continue to increase.


In Chapter 2, we saw that surface mining continues Highwalls up to a maximum height of 55 m (180 ft)
to capture a greater share of the US market because are being mined with the extremely large equipment.
of cost advantages, with the result that today about However, as the large reserves of thick, shallow coal
55% of the coal produced is surface-mined. Since 124 in the West are mined, this figure will not continue
Gt (137 billion) of the 394 Gt (434 billion tons) of to increase dramatically. Furthermore, the extremely
the demonstrated coal reserve base are strippable, and large stripping equipment to handle very large overbur-
much of it is low sulfur, this trend to strip mining is den thickness is no longer being manufactured. Multi-
expected to continue until perhaps as much as 65% ple, moderate-sized equipment is being used instead.
of the total US production is surface-mined. Therefore, Another trend noted is toward larger surface mines.
although the emphasis of this textbook is on under- From a maximum size of 2.7 Mt (3 million tons) pro-
ground mining methods, it would not be complete duced per year in the early 1960s, today's largest mines
without a brief treatment of strip mining. exceed 9 Mt (10 million tons) annually and production
For the purposes of discussing the mining methods from even larger open pit operations is being planned.
employed in surface mining, the US is divided into This trend is expected to continue.
fOUT distinct regions whose geology. climatic, and topo- UNIT OPERATIONS
graphic conditions fall into logical groupings that call
Surface coal mining, with the exception of anthra-
for different mining practices, Fig. I (Skelly and Loy, cite mining, generally has been limited to a simple
1975):
strip mining method, but today a variety of surface
Region I: Eastern Kentucky, West Virginia, Ten- methods are practiced. primarily to meet the more
nessee, and Virginia are characterized by steep slopes stringent environmental requirements. However, strip
and contour mining along the outcrops of coal. mining continues to dominate and will be given greatest
Region II: Pennsylvania, Maryland, Alabama, and emphasis here.
Southeastern Ohio have rolling terrain with modified- Strip mining is similar to the furrowing operation
area and multiple-cut contour mining. of the farmer when he plows. In essence, overburden
Region III : The northwest portion of the Ohio coal is removed. and after the first cut. it is side-cast into
field, the western Kentucky field, and all of Indiana, the previously mined area. The coal is then removed
Illinois, Arkansas, Missouri, Oklahoma, Kansas, and and another cut or strip is taken, overburden being
Iowa have generally Hat to slightly rolling terrain lead- side-casted into the previously mined area, Fig. 2, until
ing to box-cut-area or modified-area mining tech- the overburden technological (equipment) limit, the
niques; a wide spectrum of equipment is employed, property line itself, or an economic limit has been
but draglines and shovels dominate the stripping opera- reached, whichever comes first. In the most traditional
tions. cases, no overburden is hauled and little or no rehan-
Region IV: Arizona, Colorado, Montana, New dling of the overburden occurs. The unit operations
Mexico, North Dakota, and Wyoming contain the larg- of drilling, blasting, overburden stripping, coal loading,
est portion of coal reserves in the nation, if not the coal haulage, and reclamation involved in Fig. 2 will
world. Since the topography varies from typical Great be discussed briefly.
Plains to Rocky Mountain terrain with extremely thick
seams that may be multiple and dipping, basic stripping Drilling
operations are performed by a wide range of equipment The overburden over most coal seams consists of
for area mining and projected open pit mining. sufficient consolidated material to require blasting be-
The growth patterns for these regions are varied: fore it can be removed by excavating (stripping) equip-
on a percentage basis, Regions I and II are declining ment. Even where it is technically feasible for a strip-
in importance, Region III remains stable, while Region ping machine to load the overburden without blasting,
IV continues a rapid growth rate. With the application the overall economics may still favor drilling and blast-
of large stripping equipment, the average thickness of ing because the stripping cycle is speeded up when
overburden has increased from 9.1 to 18.3 m (30 to well-fragmented materials are handled, and also equip-
286 COAL MINING TECHNOLOGY

REGION I
REGION II

LEGEND

Fig. 1. Regional classification for


surface mining purposes (Skelly
and Loy, 1975). REGION rsz REGION ill

ment maintenance will be much lower. Therefore, a tage for horizontal drilling. Unfortunately, as the over-
working bench will be bulldozed on the high wall for burden thickness increases above 15.2 m (50 ft), single
positioning the drills so that a blasting hole pattern horizontal holes near the coal seam are inadequate
can be drilled. to pull (fracture) the overburden, especially if more
When shallower overburdens were mined, e.g., up massive rock is contained higher within the overbur-
to 15 m (50 ft), horizontal drilling was a common den. Also, the large explosive charge necessary to blast
practice, Fig. 3A. A drill, usually an auger type, was high overburden depths could cause shattering of the
located in the pit, and long horizontal holes were coal seam itself and loss of coal during excavation.
drilled approximately 0.3 to 0.6 m (I to 2 ft) above Use of upwardly inclined holes in addition to the hori-
the coal seam. Several advantages accrued from hori- zontal holes helps pull thicker overburden, although
zontal drilling when compared to vertical drilling, Figs. a limit is soon reached, Fig. 3B.
2 and 3C. Since softer shale materials normally occur Therefore, as thicker overburden is mined, it be-
on top of the coal seam, an auger drill can be used comes necessary to go to vertical drilling, Figs. 3C
with high penetration rates at lower bit costs. Further- and 2. The emplacement of a more powerful explosive
more, since the force of the explosion in a horizontal becomes possible in the stronger strata requiring it,
hole is directed perpendicular to the weaker bedding providing deck loading. Now, however, since the strati-
planes. the coal is shot with the grain, so to speak, graphic column above the seam will probably consist
and less drill footage is required per unit volume, up of massive sandstone and limestone, an auger drill is
to one-half less as compared to vertical drilling. Thus unsuitable, and another method of drilling becomes
less explosives and/or larger hole spacing can be used. necessary. Thus today the roller-bit type of rotary-per-
Also, no special preparation of the bench is required cussion drill, with compressed air for flushing the cut-
for the drill to operate and it can tram faster in the tings, is used almost exclusively for drilling vertical
pit. All of these factors provide a favorable cost advan- blast holes, Fig. 4. A smoother bore is produced for
SURFACE MINING 287

I ~ STR IP BENCH
V'A - -
:
SEAM

-
-
,~
-,
..., .. , -
-
- - , - Fig. 2. Typical area mining shovel strip-
-- ( -
ping operation.

ease of handling explosives, cuttings are available for


stemming, and less bit wandering occurs, resulting in
A. lower overall costs. The drill consists of rollers, usually
- 50'
three, equipped with bearings that permit them to ro-
DRILL HOLE tate independently as the drill stem is rotated with
-!........----- an applied thrust. Various teeth configurations are
available from long pointed teeth for softer rocks to
1*--40-60'--1 buttons of hard alloyed materials for the very hard
cutting. While diesel-electric power is employed for
the smaller units, high-speed heavy-duty electric drill-
ing equipment is utilized for the larger bit configura-
B. tions.
50-100' Another advantage of vertical drilling is that holes
may be drilled as far ahead of actual mining as desired
to take advantage of weather conditions, since an ex-
posed high wall is not necessary as it is in horizontal
r- 40 - 60 ' ----I drilling. Also, buffer shooting may be employed, i.e.,
shooting a row of holes with the previously blasted
row of holes along side of the highwall remaining un -
spoiled to provide total constraint. This improves frag-
I mentation, reduces air vibrations, and minimizes the
c. I scattering of overburden materials into the pit, thus
I
I +50 assisting the subsequent spoiling operation.
I The economics of drilling with the larger bit are
I fascinating. As bits increased in diameter, larger bear-
I
ings were provided for the roller bits which improved
r- 40 - 60'----1
bit life. Also, the larger hole permitted greater thrust
on the larger drill stem which increased penetration
Fig. 3. Va rious surface mining drilling techniques: (A) rates. The result was that a bit with a diameter of
horizontal, (B) inclined-horizontal, and (C) vertical. \8.7 em (7Va-in.) typically had a penetration rate of
288 COAL MINING TECHNOLOGY

Fig. 4. Roller bits used in strip mining. (courtesy Hughes Tool Co.). Left, soft formation bit.

21 m / h (70 fph) in average sedimentary rock which larger hole permits a greater concentration of explo-
permitted 5826 m' (7620 cu yds) of material per shift sives which makes a greater spacing between holes
to be prepared at a cost of l.32 per cubic yard with possible. The spacing of holes will be dependent upon
a bit life of 1829 m (6000 ft). Later, 38-cm (15in.) the strength of the material being blasted, the explo-
diam bits provided drilling rates of 33m/h (110 fph), sives used, and other factors. However, typical powder
permitting 38,439 m' (50,274 cu yds) of material to factors are from 0.3 to l.0. Powder factor is defined
be prepared per shift at a cost of 0.42 per cubic yard as the weight (lb) of the explosives used for each cubic
with a bit life of 3048 m (10,000 ft). Obviously, the yard of material blasted. Typically, 38-cm (15-in.) diam
SURFACE MINING 289

Fig. 4. Roller bits for medium soft to very hard formations.

holes might be spaced II x II m (35 x 35 ft) while ated, decompose at very high detonation velocities.
18 em (7-in.) diam holes might utilize a 4.6 x 4.6 m Most, but not all, dynamites contain nitroglycerin as
(15 x 15 ft) pattern. the explosive compound. However, dynamites have
largely given way to commercial blasting agents which
Blasting are cap-insensitive chemical compositions or mixtures
The earliest explosives used in surface mining were which contain no explosive ingredient and which can
dynamites. cap-sensitive chemical mixtures containing be made to detonate when initiated with a high-
an explosive compound, which, when properly initi- strength explosive primer. Of the many advantages
290 COAL MINING TECHNOLOGY

offered by these non-nitroglycerin compositions or creased, the explosive usually produces a greater shat-
mixtures, safety in handling. use. and cost undoubtedl y tering effect in hard materials. Strength and density
are the most important. also influence shattering action, so that all three prop-
Most of the properties presently used to character- erties must be considered in the final selection of an
ize explosives and blasting agents initially were devised explosive.
for dynamites and other high explosives. These proper- 5) Water Resistance. Higb explosives differ widely
ties have been modified and otherwise adapted for use in their ability to resist the effects of water. The gelatin
with other commercial explosives and blasting agents dynamites are the best in this respect. Some of the
as detailed here (Woodruff, 1966). higher-density ammonia dynamites possess good water
1) Strength. Strength refers to the energy content resistance, while the low-density ammonia dynamites
of an explosive which, in turn, contributes to the force and permissibles have little or no water resistance. Dy-
and power it develops and the work it is capable of namites which are penetrated by water first have their
doing. The strength rating of a straight dynamite desig- efficiency impaired and then, on prolonged exposure,
nates the percentage by weight of nitroglycerin in the may be desensitized to a point where they will not
formula; a 40% straight dynamite will contain 40% detonate. Therefore, when water is encountered in
nitroglycerin, a 60% grade will contain 60%, etc. In blasting, an explosive with at least sotne water resis-
other types of dynamite, the portion of nitroglycerin tance is necessary. For optimum reliability. it is desira-
is reduced and other strength-imparting ingredients, ble to incorporate water resistance or water tolerance
such as ammonium nitrate, are substituted. The total into the explosives or blasting agent formulation and
energy value of an explosive can be meaningless. The not depend upon the package alone to protect it.
energy must be available in time to do useful work. 6) Freezing Resistance. Most commercial dyna-
Velocity and density also are very important factors mites are resistant to freezing. Normally, they will not
in determining blast performance. The best explosive freeze under ordinary exposure to the lowest atmo-
for a given operation is not necessarily the one with spheric temperatures generally encountered in this
the highest strength, density, and velocity; it is the country. With the exception of water-containing prod-
one with the combination of strength, density, and ucts, all blasting agents and non-nitroglycerin explo-
velocity that will give the type of blast results desired. sives do not freeze under conditions normally encoun-
2) Density. Dynamite density is conveniently ex- tered in the field.
pressed by the number of 3.2 x 20-cm (l Iii x 8-in.) 7) Inflammability. This property refers to the ease
cartridges contained in a 23 kg (50-lb) case. The pur- with which an explosive or blasting agent can be ig-
pose of density variations in explosives is to enable nited. In the case of dynamites, this ranges from some
the blaster to concentrate or distribute charges at will. types that ignite readily and burn violently, to others
In producing lump coal, it is frequently advantageous that will not support combustion unless an outside
to string out the charge with low-density grades. In source of flame is continuously applied.
strip mining, the high-density explosive is sometimes 8) Fumes. Various gases, called fumes, both poi-
used in the bottom of the hole or in massive intervening sonous and nonpoisonous are produced from the deto-
strata where the work to be done is greatest, and the nation of commercial explosives and blasting agents.
bulkier one is used in other places in the hole where Both the nature and total quantity of poisonous gases
very little energy is ordinarily required. produced vary among the different types and grades
3) Sensitiveness. Sensitiveness of an explosive or of explosives, and may also vary according to condi-
blasting agent is a measure of its propagating ability. tions of use. For work in the open, fumes usually cause
Sensitiveness of dynamite is measured by the distance, no concern, but, for underground work, they require
in inches, over which one half of a 3.2 x 20-cm (\ '4 that careful consideration be given to the choice of
x 8-in.) cartridge will propagate to another half of a the explosive, the amount of it to be used, the condi-
3.2 x 20-cm (1'4 x 8-in.) cartridge when both halves, tions of blasting and, most important, ventilation.
with the cut ends facing. are enclosed in a paper tube 9) Sensitivity. This property frequently is confused
and shot unconfined. Dynamites must be sensitive with sensitiveness. Sensitiveness is a measure of the
enough to insur~ detonation for the entire length of explosives' propagating ability. Sensitivity is the mea-
the charge. For this reason, sensitiveness is especially sure of its ease of initiation.
critical in small-diameter holes in a 2.5 to 3.8-cm (\ In Fig. 5, the explosives are listed in such a manner
to 1\-2 -in.) range. However, dynamites normally must that an increase in the properties enumerated results
not be so sensitive that they will propagate from one upward and to the right. For example, nitroglycerin,
hole to another and not permit sequential firing with normally an ingredient in an explosive, when available
delays. alone has very high strength, density, sensitiveness,
4) Velocity. Velocity is a measure of the speed at velocity, water resistance, freezing resistance, inflam-
which the detonation wave travels through a column mability, fumes and sensitivity while a permissible ex-
of an explosive. Unless otherwise stated, velocity data plosive, at the other end of the spectrum, possesses
refer to a 3.2-cm (1 '4-in.) diameter column. Dynamites the least degree of these characteristics. A permissible
range in velocity from about 219 mls (4000 fps) to explosive is a specially formulated mixture for use in
about 7010 mls (23,000 fps). As the velocity is in- underground coal mines that has additives that sup-
SURFACE MINING 291
D E FLAGRATORS~'~---------------------'. DETONATORS
NON - COMBUSTI BLES COMBUSTIB L E EXPLOSIVE BASES
AIR BLACK POWDER I AMMONIUM NITRAT E I NITROG LYC ERIN E

!
I AIRDOXI
JUDSON I
POWDERI
IGUNCOTTON

60% i
r-Y
90%

IPEL L ETI H2 O ISTRAIGHT BL ASTING


~
DYNAMITE GELAT IN
I. STR ENGTH GREATER

t !
H
2. DE T. VEL. /
3. WATER INS.
4.FR. RES./" FUEL ..... TNT SLURRyl No N0 3 GEL ATIN
5. FUMES C DYNAMIT E
ANTIACID I
6.D E NSITY l L
IAN-FOI
7. SENSITIVITY
l
/'
LESSE R
8.INF L .
.1 AMMONIUM
"I GELATINS

INGREDIENTS TO REDUC E: IAMMONIUM I


I. L E NGTH OF T IME DYNAMIT E
AMMONIA
OF FLAME NITRATE
2. T EMPERATURE OF FLAM E EXP L OSIVES
3. DENSITY
4. AFTERG L OW PERMISSIBLES:

Fig. 5. Explosives blasting chart.

press the intensity and duration of the flames and mini- In spite of its high velocity and fracture potential
mize afterglow. In short, it will not initiate an explosive on explosion, primacord is relatively insensitive to
mixture of gas when shot in confined and approved sparks, friction, or ordinary shock, and, consequently,
manner. As ammonium nitrate is substituted for nitro- is relatively safe to handle and use on the job. So
glycerin, the mixture shows less resemblance to nitro- far as can be determined, primacord has never been
glycerin and more to a permissible explosive. Thus, responsible for an accidental explosion on blasting op-
various formulations are possible during mixing. erations in spite of having been subjected to all manner
Free-running ammonium nitrate prills (94%) with of abuse in such work. Primacord for commercial blast-
fuel oil (6%) is the most commonly employed explosive ing is normally supplied in four different types: (1)
in surface mining. Its main disadvantage is its lack reinforced, which has an inner plastic jacket with an
of water resistance, although plastic liners can be used outer covering of textiles and wax finish; (2) plastic
in boreholes or the explosive can be packaged in a reinforced, which has an added covering of textiles
water-tight wrapping. The commercial blasting agents plus waterproofing material followed by an outer cov-
are detonated using special cast primers which are usu- ering of tough plastic; (3) plastic-wire-countered,
ally initiated by primacord down lines that in turn which is similar to plastic reinforced but is further
are ignited by blasting caps, Fig. 6. Primacord is a strengthened by a countering of steel wires under the
detonating fuse having a high explosive core of penta- outer plastic jacket; and (4) E-Cord, which is essen-
erythritol tetranitrate (PETN). It has a very high veloc- tially identical to reinforced except for a reduced explo-
ity of detonation, exploding at about 6401 mls (21,000 sive core load.
fps). It also has good tensile strength and is light in Although free running blasting agents generally are
weight and flexible, making it easy to handle and con- lower in density than cartridge or canned products
nect. While the explosive core is protected against pen- and therefore have lower bulk strength, the fact that
etration of water or oil, straight (unknotted) lengths they fill the hole completely results in acceptable bore-
will reliably detonate even when the core is wet if hole loading. This, together with the fact that the blast-
initiated from the dry end or from the wet end with ing agent is coupled to the borehole wall, results in
a suitable booster. The energy of the primacord explo- an acceptable level of performance under ordinary con-
sion is sufficient to detonate high explosives lying ditions. Its main advantage. in addition to its safety
alongside it in a borehole. If it is attached to the first in handling, is its economy: it costs approximately 15
cartridge loaded into the hole, it acts as a priming per pound compared to 45 per pound for a 40%
agent throughout the entire length of the column of dynamite. For average sedimentary rock overlying a
explosives. coal seam, a powder factor of 0.3 to 1.0 Ib of ammo-

l
292 COAL MINING TECHNOLOGY
.-BLASTING CAPS Pit

DETONATING FUSE
Inst 9msec 17 msec 17 msec
P---.r.~~r---~--~--*--o

~Io.;.r--~;TEMMING 9msec 21ft-24ft


Shot bonk 9msec + 17 msec 17 msec

~ 26ft-28ft I-
IMER 9msec 17 msec 17 msec

Fig. 6. Singlehole charge (left) and plan of blasting pattern employing delays

.-
(right).
,., .,., IGr-A,N-FO
'" N operates in the pit, Fig. 2; the dragli~e operates on
the overburden beside the pit, Fig. 7. The fragmented
material in the pit and in the overburden is scooped
up and discharged (spoiled) at the side of the pit oppo-
site the high wall, building up by this process a mound
of loose material in hedge rows which are collectively
called the spoil bank. The excavating machines remove
all of the fragmented overburden material down to
the top of the coal seam.
In addition to the shovel and the dragline, the
bucket-wheel excavator (BWE), a machine used exten-
nium nitrate (ANFO) will be required for each cubic sively in Europe and much of the rest of the world,
yard of material blasted. is being employed in a few American coal mines. This
In order to secure higher density, higher bulk machine has several excavating buckets mounted on
strength, and a higher degree of water resistance, slurry a revolving wheel structure, like a water wheel, fixed
explosives have been employed. They include mixtures at the end of a long, bridgelike boom. Normally, this
of water and ammonium nitrate and can also include machine is utilized in tandem with another excavator,
aluminum (AI) and TNT. In fact, one of the largest Fig. 8. In a few mines where the overburden is thin,
explosives manufacturers is switching almost entirely conditions are such that the overburden may be re-
to water gels. To increase its bulk strength 175%, 15% moved by bulldozers, scrapers, and front-end loaders,
aluminum flakes are added to the ANFO mixture. By which are lower in initial cost, more economical to
adding 20% TNT to the mixture and making a slurry operate, and more flexible in the disposal of the spoil.
of it, the bulk strength is increased 151 %. Finally, This last attribute, and its importance in more stringent
by utilizing 25% TNT, 15% Al with a slurry mixture, reclamation requirements, make these latter machines
bulk strength is increased 264%. more applicable in surface mining.
Fig. 6A is a single-hole explosive arrangement Since the stripping equipment normally represents
while Fig. 6B shows a multiple-hole pattern. In each the highest capital cost item, its selection is the most
situation, two primacord down lines are employed for important decision to be made in selecting the strip
added reliability with dual blasting caps used for the mining system. After this choice is made, the other
same purpose. Special primers are normally used with equipment is matched to it. The selection of the over-
the primacord for igniting the ammonium nitrate. Mil- burden excavators will be treated in greater detail in
lisecond delay elements permit delays between rows a subsequent section. Here, however, the unit opera-
of holes as well as individual holes if desired. This tions will continue to be described in order.
reduces vibration and noise and improves fragmenta-
tion. Coal Loading
The coal exposed by the overburden excavator is
Overburden Excavation generally removed by power shovels, or, increasingly,
The blasting operation causes some of the ove rbur- by rubber-tired, front-end loaders, depending upon the
den material to fall into the pit; most of it, however, conditions at the mine site. Until recent years. the
is retained in the highwall area as a fragmented struc- vast majority of mining shovels produced were of 6.1
ture which can be excavated with relative ease. Two to 9.2-m 3 (8 to 12-cu-yd) capacity. There was little
types of machines are in most common use for this demand for larger shovels since the haulage units
type of excavation operation in American surface served were rather limited in size. But when haulage
mines: the power shovel and the dragline. The shovel units became increasingly larger, for instance the 154-t
SURFACE MINING 293

Fig. 7. Typical area mining dragline stripping operation.

/- ---{l-+-- STRI PPI NG


SHOVEL

COAL
LOADER

60'
100'
40'
1
Fig. 8. Pit layout for wheel excavator and
1-106~ 47 50'
shovel tandem operation.
294 COAL MINING TECHNOLOGY

Fig. 8A. Frontend loader used to load trucks (Deere & Co.).

(170-t) truck is one of the most popular sizes today. for stripping overburden, especially with the haul-type
the need for bigger shovels developed. Today, it is method, Figs. 8A and B.
the II to 20-m3 (15 to 26-cu-yd) machines that are Like the dozer from which it evolved, Fig. 14,
in demand. In any event, the shovel and trucks must the front-end loader is available on crawler tracks as
be matched so that the truck has a capacity in even well as rubber-tired wheels. During its evolution, there
multiples of the bucket size. Typically, the truck will has been a series of improvements extending the operat-
have a capacity of 5 to 10 dipper loads. ing capability of the machine: four-wheel drives, pow-
Another advantage of the larger shovel with its erful hydraulic action, and improved engines. The rub-
greater power is that it is more capable of digging ber-tired wheel loaders are generally preferred in all
the solid coal. However, some thicker or more compe but the most severe terrain and footing conditions.
tent coal seams will require drilling and blasting. Use They are available with both straight and articulated
of a mobile, rubber-tired, mounted auger drill to pro- frames. The larger units are generally articulated four-
duce a simple blasting pattern will usually suffice. wheel-drive loaders having the advantage in traction,
Where feasible, especially in thinner, less competent stability, and maneuverability, but their complexity
coal, the use of a rooter on a bulldozer frame will adds to capital and maintenance costs. By virtue of
provide a cost advantage over drilling and blasting. articulation, the front and rear wheels track in turn,
Fig. 9 shows a cross section of a loading shovel with giving the stability of a long wheel base and the maneu-
pertinent specifications for a wide range of models. verability of a short turning radius.
The front-end bucket loader is fast becoming popu- Front-end loaders can be competitive with loading
lar because of its ability to excavate, load, and carry shovels in loading coal directly off the seam, and have
material quickly and with unsurpassable maneuverabil- certain advantages and limitations. Some of the advan-
ity. It is used for loading coal into trucks and also tages of front-end loaders over shovels include: (I)

Fig. 88. Front-end loader removes over-


burden after blasting (Deere & Co.)
SURFACE MINING 295

i
D-----i
~-------H--~----~"--------B----~I
~I-------- F------~

E
~ r'~ ~

Ir-
) 0

L f1
~----- 1- - --1

..E
>< .E
,(
G:'
~ ..E
,(
~
c g c.=-
- ."- -...
@)
@>~
:5- @) ~
vi

- (U .:.
.J:::!.
~ ~
@)~
,,~

on ,:;
1: on~

...
.J:(.J
-~
" .: -'"
-.... -"e
C -.: ~

,,-
00'":,,,
"- .
"Ill
"-~

" .: ..s::: .~.


'iii
~
:.gZ
. .=
..s::: ''':''' on
::::1..1
:g..s::: .... ~~
.J: ~
"':'
"(l-
o .:
.c'1
'6 "u
.J:
""- _ E
"- ~ ;~
...~ e" . .= 'iii - 0.

.-.o..J:
.=
~'i'
.J:E EE .1::::: o~ "
. " - -"
> -
.: "- on-
~ ~ ...
~ " ... " ... on- o 1!
,,~

~'"

-. -. -..
~ bO"
Qi "0.E c." E
"0. E " ';:(E ~ E ~ E .J:~ ~
.8.
":;;
0
E ";;
"
cE . E'"
"
c~
"-
E"-
""
cE
E";;
"
cE .. +=i
c3E
'>< :;;
c3E
"
-"
"
.:
:.;:;
(.J_ . c3E:;:: ')(
"~E..
.- ' j(
:E~
~ t;
:3,~
C3~
"'C
0.>-
"-
c"
BE 1 108 23- 0 38- 9 15- 9 40-6 35- 3 46-3 31 - 5 16-3 17- 0 4
NW 1800 24- 5 34-8 37-1 56- 3 43-5 29-5 14- 2 16- 4 41f2
BE 150B 23- 9 41 - 3 16- 6 43- 0 38- 0 50- 0 33- 9 17- 0 18-3 41f2
P&H 1400 20-9 38-6 39-0 32-0 44-0 25- 7 16-0 16-6 4-5
P&H 1500 22-6 41-4 41 - 10 34-1 47-6 28-5 17-0 17-6 5
P&H 1600 23- 0 42-0 42-9 35- 7 48- 6 28-5 17-6 18- 0 6
MEC 4600 22-6 43-1 45-9 36-6 52- 0 35-10 24- 2 7
BE 190B 23- 9 41 - 3 16- 6 43- 0 38- 0 50- 0 33- 9 19- 0 19- 9 6%
M 151M 22- 3 41 - 6 16- 6 43- 6 35- 3 47- 3 20- 9 50- 9 34-3 17- 6 18-0 8
BE 195B 26- 3 46- 9 18- 9 48- 6 41 - 9 55-9 38-9 19-0 19-9 8
M 182M 29-6 50- 0 21-6 52-0 43-0 55-0 23-0 60-0 39-0 2 1- 6 23- 0 10
P&H 1900 27-0 50-0 52-9 42-6 57- 0 33- 0 2- 03 20- 9 10
BE 280B 28-6 53-6 21-0 54-3 47-6 62- 3 40- 6 21-0 21-6 10
M 185M 25- 3 48- 9 19- 9 49-6 40- 6 54- 3 24- 0 57- 6 40-3 20-6 23-0 12
P&H 2100B 28- 3 51 - 6 52- 6 44- 0 60-0 38- 9 21-9 23-0 12
M 191M 34-0 52-0 22- 3 54-9 51 - 3 54-9 26- 9 63-0 41-6 21-6 23- 0 12
P&H 2100BL 30-4 51 - 6 52- 6 46- 1 60-0 39- 9 24- 0 23- 0 13
M 191M(0) 46-3 66- 0 28-6 70-9 63-9 69-0 32-9 79- 0 50-3 21-6 26- 6 15
M 183(0) 41-3 56- 9 25-9 60-6 55-6 59-0 29-0 67- 9 44-6 22- 6 23- 0 16
BE 295B 31 - 6 53-3 24-9 55-0 49-0 63- 6 42- 6 23- 0 22- 9 18
P&H 2300 36- 6 55- 0 57- 0 54- 0 66- 6 46-6 26-0 24-6 20
M 251M 33- 9 64- 3 I 25- 0 I 65- 6 63- 3 67- 0 I 30- 6 I 73- 6 47- 0 I 27-6 I 30-0 25
Fig. 9. Load ing shovel models and specifications .
296 COAL MINING TECHNOLOGY
excellent mobility, (2) good blending capabilities, (3) conveyors, handling larger volume at lower operating
good backup and cleanup capabilities, (4) multi-func- cost will usually produce a more favorable overall cost
tionalism (loading coal, cleanup, road maintenance, compared to trucks.
stockpiling, etc.), and (5) low capital cost. The disad-
vantages include: (1) not as available as the shovel, Reclamation
(2) excessive tire wear in difficult digging, (3) high A tour through abandoned surface mines in Appa-
tire cost, (4) expected life half that of shovel, (5) inabil- lachia is not a pretty sight nor is it a situation that
ity to work high faces, (6) decrease in performance should continue to be condoned even if stringent legis-
with bad floor conditions, and (7) lower capacity for lation had not been enacted to prevent such future
digging so that coal must be shot harder. The early land degradation. In years past, when a surface-mined
front-end loaders had small buckets, usually 3.8 m3 coal deposit became exhausted or uneconomical to
(5 cu yd), but today the 7.6 and ll_m 3 (10 and 15- mine with the equipment available, it was abandoned,
cu-yd) buckets are most popular. leaving a barren, sawtooth, moon-type landscape of
spoil piles hostile to natural vegetation and generally
Coal Haulage unsuitable for any immediate land use. The industry
In the US, surface coal mine transportation out now accepts the premise that reclamation work, i.e.,
of the pit to the preparation plant or loading siding reclaiming the spoil area and reestablisHing permanent
is almost always accomplished by large off-highway vegetation, is an integral part of the surface mining
diesel-electric trucks. Labor costs are substantially re- operation. For quality results at an economical cost,
duced with the larger units which may be rear-dump reclamation cannot be an after-thought to the mining
or drop-bottom, tractor-trailer units. Rear-dump operation but instead must be an integral part of the
trucks are, for the most part, 32 to 77-t (35 to 85- total design. Presently, reclamation is required concur-
ton) capacity. Midwestern and eastern strip mines usu- rent with mining to minimize the problems of wind
ally employ the rear-dump unit because it maneuvers and water erosion as well as for aesthetic reasons.
well in compact pit operations and is built to cope While a variety of equipment may be used for reclama-
with steep ramps and sharp haulroad turns. But these tion purposes, the large bulldozer is the principal vehi-
qualities that make it a good hauler for compact, rough cle in use. Topsoil, where available, should be removed
pit work also limit the speed and distance it can travel. prior to mining and stored for subsequent reuse. It
Therefore in the West, where pits are larger, where is usually desirable to try to put back the overburden
ramps have gentle grades, and where haul distances in approximately the same stratigraphic column in
are long, the bottom dump is usually preferred primar- which it originally existed, paying particular attention
ily because of its lower initial cost. low maintenance to the burial of acidic materials. Drainage should be
cost, and very favorable ratio of material hauled for reestablished to keep the water off the coal seam to
a given horsepower design. Tractor-trailer, bottom- avoid acid contamination of the ground water. As the
dump units are usually 91 to 181-t (100 to 2oo-ton) various systems of surface mining are described, good
capaci ty. In short, they are the choice where traction reclamation features will be pointed out.
is not a problem.
Regardless of the size and type of truck utilized, OVERBURDEN STRIPPING EQUIPMENT
good road maintenance in the pit is very important The selection of the overburden stripping equip-
since haulage costs may comprise nearly half the cost ment is of vital importance in a mining operation. In
of producing a ton of coal, with tire costs the largest the past, the philosophy of brute strength was accepted
proportion of this cost. In addition to maintaining a as providing the most favorable economic choice with
good road base for minimum tire wear, minimizing the result that the primary stripping units became huge.
the dust formed by truck haulage is an important con- Up to a point, economics are in favor of the larger
sideration in hauling the coal off the mine site. Thus, unit. A specific example is shown in Table 1 which
good grading and wetting down with water trucks are compares the results of replacing a 10 m3 (l3-cu-yd)
necessary. In the pit, truck haulage is normally by a shovel in 1958. Even including the amortization of
circular route through transverse roads maintained the newer equipment, the overall cost of the larger
through the spoil every 457 to 610 m (1500 to 2000 shovel was lower because of the significantly lower
ft) apart. Where the bottom may present a problem operating cost. Furthermore, the coal reserve was sub-
for traction, it is a frequent practice in shovel stripping stantially increased because of the ability of the larger
to maintain a coal berm against the new high wall for newer unit to mine a thicker overburden.
truck transportation. This is not done very frequently However, not only do the very large units have
with draglines, however, since any berm left would high initial costs but they have also proved to lack
have to be overcast by the dragline. reliability. So it is not surprising that a point of dimin-
In European surface mines. mobile crushers in the ishing returns has set in. With an overburden that
pit and belt conveyors are in general use instead of ranges widely in thickness, say from 12 to 43 m (40
trucks and are receiving attention in this country as to 140 ft). it may not make economic sense to purchase
well. While the initial cost is much higher for belt a machine that is capable of handling 43 m (140 ft)
SURFACE MINING 297
Table 1. Cost Comparison Between 13 and 70- Power Shovel
Cu-Yd Shovels The power shovel, whether it is designed primarily
for stripping or loading, has its greatest application
Marion Marion in handling tight or poorly fractured overburden be-
5320 (1938) 5760 (1958)
cause of its crowding action which allows a higher
CapaCity, cu yd 13 cu 70 cu breakout force to be applied. As a result, a reduced
Boom length, It 95 140 amount of overburden preparation is required com-
Ave. burden, It 33.5 61 pared to the use of other equipment under these condi-
Rate, cu yd per hr 600 3250 tions. The power shovel can, however, be utilized to
Max. burden, It 48 66 handle loose material as well as rock, and blockier
Cost per cu yd, $ 0.0585 0.0485 material will have less overall effect on its ability to
load efficiently. Since it is designed with a solid connec-
Cost 5760 - $3,300,000 tor between the dipper and drive mechanism, positive
Amortize 15 rs
11 man. @ 720 hr per month control is always possible, and generally a higher
$27.78 per hr
y bucket-loading factor will result.
5760 cost ($0.0485) includes amortization; In shovel applications, cycle times are normally
5320 does not. low because most of the material loaded is confined
to an area directly in front of the unit and dumped
Metric equivalents: cu yd x 0.764 554 9
0 .3048 ~ m.
within a relatively short radius of the loading point.
While variable depending upon the unit, a complete
cycle for 90 dumping is generally 50 to 55 sec. Ordi-
of overburden when that portion of the deposit repre- narily, a shovel works from a position directly on top
sents only a small percentage of the property. It may of a coal deposit, eliminating the need for preparation
be better to purchase a smaller unit and do a certain of a working bench, Fig. 2. It is usually equipped with
amount of rehandling of material. Therefore, rather crawlers which are designed for rock wear and it has
than buying a single large machine that is probably the ability to load over a truck end. Low operator
a little too big for the job, it may be better to choose fatigue is also apparent in shovel operation.
a medium-size machine that can handle the task if The limiting factors of shovel usage include less
worked to its limits. Two smaller machines might also flexibility and maneuverability and slow tramming
prove a better choice. Thus, biggest is not always the rates. Bank or spoil slides as well as water seepage
best. into the pit will tend to impair the operation of a shovel.
Multiple machines for stripping might be used in The trend is toward units with greater versatflity in
tandem. Scrapers and bulldozers might remove high reach and digging depth, toward specialized bucket
spots and draglines and shovels then take care of the designs, and toward use of hydraulic power and con-
rest of the overburden. There are many possible combi- trol.
nations of stripping machines, as we will see. Tandem When the operating conditions are appropriate, a
operations might be very beneficial for subsequent rec- stripping shovel generally offers lower overall operating
lamation procedures since the spoil can be left in a costs than can be obtained with draglines or bucket-
less irregular contour with the more acid materials wheel excavators of comparable size. This is a conse-
buried. Also, multiple-seam mining may require a quence of a number of factors, including lower power
greater degree of flexibility in the equipment selected. requirement costs and lower wire-rope costs per cubic
Thus, there are many factors entering into the choice yard of dipper capacity, a higher availability factor,
of the stripping equipment such as: (I) the properties a lower level of bank preparation (e.g., blasting), and
and characteristics of the material to be mined, (2) a lower labor requirement. Also, the shovel normally
the desired production rate, and (3) the compatibility moves the overburden a shorter distance.
of the stripping machine to the overall mining and Currently, stripping shovels ranging from 19 to
mineral handling process (a mine without an integrated 13S-m3 (25 to IS0-cu-yd) capacities, with boom lengths
system will never develop into a truly efficient opera- of up to 72 m (235 ft) and handle lengths up to 43
tion). m (140 ft) are available. The larger units are capable
Therefore, since the stripping unit will usually be of mining an average overburden thickness of up to
the highest cost item, and is selected first with all other 30 m (100 ft). The price of a stripping shovel with a
equipment selected to match it, it requires special atten- 76-m 3 (IOO-cu-yd) dipper and 61-m (200-ft) boom, in-
tion. cluding shipment and erection costs, might run to $12
All strip mining equipment, whether primary or million. The market is highly competitive and pricing
supporting machinery, has certain specific applications is elastic. Some manufacturers, in fact, claim that they
and limitations which require discussion. It is intended lose money on shovels and that the tight pricing situa-
that this analysis will outline the most desirable fea- tion discourages innovation. Few, if any, of the very
tures of each piece of equipment as well as its draw- large stripping shovels have been constructed during
backs. the past ten years in the United States; they have been
298 COAL MINING TECHNOLOGY

I--~-=--=--=--_-_-_-_-_-_
-_-_L_-_ -J-----------_-_-_-_-_-----1-1:1

.-~~~----~~-- C ------~-dl

, I

1 - - - -- - - G -~~---__I'_I

K
F

"
0

g: :::'
~
.~ ::> u "~~

..., ..,-
~~
",.,
C ~ 00
$
.=- Ec C ~
.2~

@~ ~
..,~

: . ~c
"'" @;j!; g E ~ @).~ ~
,;
-'=~
~ 0. U
~

".;
-'.
""0
.~:z ~"
~~

E
~~

"
D.O.5 .ErJi
bO.: ~ C ..;t::
@i @~
." ""~-'"
E

~
0
:g .~ ."'
.- .
~
15
'*
bO. ~ ~
:g 'iii .-~ "~ :gi: .r:: " 'u
"~ ~-
~""
.S
o '
'0. ::: ,,", .:! ';
,,"" " .E. ~
'0
~
u ~ t!
"E ~

.au bil
0 """e "E
0.
E'"
~ 0
E",
~ 0 """
"" ~E
'ij ~
"" E ~ E
'ij
.J:= ~ 15~ ""'
~ . ,,-
~
0.
u
~

,,-'
..
o ~ o o ~
o 0_
of!
~ ~
"a- ,,0.

o 0 ~ ,,~
o E
,,~
o E "o . .::;; ~ 0
~
0
~
::;;
0;
"::;;0
E
0
0
'"
'0.. E
E ';;C
~
oE
~
'0.. E
E ')(
~
cE
~
~ t
-
.Eo >
~ t
->
.E 0
'ii'a.
EE
~
c"
~
'0.. E

cE
E')(
~ ~
:;::::;';(
-~
c3E
-
:.0:: 'i(

c3E
~
:;:: .2
-"
~
u"
~
o~

=~
:::J',
u"'
~~

ii
~

"'"'
c:
"
"".!!
~~
~b
"~
~"
"'~
~

C
~
0.
0.

BE 550B 45 68-0 100-3 43- 0 106-6 92-0 114- 0 66- 0 38-9 25


BE 550B 45 64-0 96-0 43-0 101-6 88-0 110-0 66-0 38-9 28
BE 1050B 45 76- 0 114- 6 48- 0 121 - 0 104- 0 131-6 75-6 43-11 40
BE 1050B 45 71-0 109-6 47-0 115-0 99-6 126-6 76-0 43- 11 45
BE 1850B 40 104-0 230-0 83-0 225-0 245-0 125-0 57-0 53-0 65
BE 1650B 47V2 106- 6 140- 0 69- 6 147-6 158- 0 97- 0 49-5 70
M 576 1 45 111-9 156-3 106-3 158-0 81-9 162-0 141- 3 158-6 88-9 173-0 95-3 50-0 39-0 75
BE 1650B 47112 96-0 127- 6 64-0 135-0 145- 0 84-0 49-5 75
M 5860 47 122-6 162-6 110- 3 167-0 88-3 169-6 152-9 165-0 95-6 181-3 99-3 58-2 44-0 80
M 586 1 46 133- 9 180- 0 123-6 184-0 92-6 189-0 163-6 182-0 99- 6 200- 9 115- 6 60-0 50-0 90
BE 1950B 49 134-0 185-0 104-0 193-9 207-6 113-6 68-6 58-0 100
BE 1850B 47h 101- 0 150-6 76-4 157-0 170-0 109- 0 57- 0 53-6 100
M 5900 47 143-6 195-6 127-6 200-9 104-6 203-6 176-9 199-0 112-6 216-3 126-3 65- 0 56-6V2 105
BE 3850B 50 150-0 210-0 108- 0 218- 0 232-0 135-0 73-8 63-0 125
BE 1950B 52 117- 6 151-6 83-6 163-0 172-0 96-6 63- 6 58- 0 130
BE 3850B 50 135-0 192-0 102-0 200-0 215-0 129-0 73-8 63-0 140
M 5960 45 125-0 181-0 118-0 184-0 95- 0 186-6 162- 0 185- 6 104-0 201 - 6 124-0 76-4 59- 0 150
M 6360 45 153- 0 211-6 133-6 217-9 113-6 219- 9 189-6 218-6 122-0 236-9 156-9 88-0 66- 6 180
Fig. 10. Stripping shovel models and specifications.

l
SURFACE MINING 299
limited generally to buckets of between 76 to 92-m' tub, its two pontoons retracted. When the machine
(100 to 120-cu-yd) capacities. must be moved, the pontoons, activated through a me-
Loading shovels play an important role in certain chanical (cam) or a hydraulic system capable of posi-
western strip mining because they not only dig and tioning them laterally from front to back as well as
load coal, but also strip off overburden. Dipper sizes vertically, are lowered in such a fashion that the sup-
for these shovels are usually between 7.6 and 19 m 3 port points fall somewhat behind the center of gravity
(10 and 25 cu yd), with the emphasis on the larger of the dragline. As the pontoons begin to lift the ma-
shovels since these machines may be called upon to chine, it moves forward, sliding or rolling depending
load higher overburdens. Thus, stripping with loading on the design of the particular walking system. By
shovels will offer advantages for western mining when: means of such a system, a large dragline can advance
I) Relatively thin overburden results in low strip- with steps of3.0 m (10 ft) or more. The walking mecha-
ping ratio (cubic yards of overburden per ton of coal) nism permits the dragline, no matter how ponderous
which does not require the higher stripping capacity it may be, to move in any direction with considerable
of an expensive dragline. precision, if not with any special grace.
2) Combinations of shovels and trucks need to A major advantage of the walking dragline, in addi-
quickly move the overburden farther than the reach tion to reduced maintenance and greater maneuverabil-
of any dragline. ity. is its extremely low bearing pressure. Even the
3) Multiple and dipping and sloping seam opera- largest machines exert a pressure on the ground of
tions lend themselves to a benched pit. only 125 kPa (19 psi) and smaller machines have a
4) Less blasting is required, thereby reducing bearing pressure of only 59.5 kPa (9.5 psi), making
shooting costs. them extremely suitable for soft or wet formations.
5) When shorter lead time for ordering equipment Also, the dragline can operate on the tops of spoil
is required, as well as a lower initial capital outlay. either as a primary stripping tool or for reclamation
Fig. 10 provides a representative list of stripping purposes. It is ideal for producing the initial or box
shovels available today with pertinent specifications cut in a stripping operation, a procedure that is almost
for them. impossible for a shovel.
The dragline can be effective in operations such
Dragline as building roads and ditches in addition to being able
The greatest assets of a dragline are inherent in to clean a rough coal seam for direct loading into trans-
the actual design of the machine. A greater reach and poration vehicles. Due to the design of the dragline,
dumping radius, which enable deeper overburden to bucket loading requires a high degree of operator skill,
be removed, coupled with ease of maneuverability are cycle times are generally high, and small amounts of
the major advantages of the dragline. Since the dragline load spillage frequently occur. The composition of the
normally operates on top of the overburden, certain overburden can cause material to adhere and build
problems such as bank slides, water runoff, and seepage up inside the bucket, decreasing its capacity and reduc-
are reduced or eliminated. Compensation for pitches ing the efficiency of the dragline, especially in wet or
and rolls in the mineral deposit can easily be made freezing conditions.
and, if necessary, the dragline may be used to chop Draglines, like shovels, have reached their physical
down a small proportion of the overburden to prepare limitations, the largest one being built with a 168-m3
a working bench. Although it deviates from standard (220-cu-yd) bucket. However, because of its newer de-
operating procedure, this method can be used to advan- sign and introduction of new components, it has not
tage under certain circumstances. For these reasons, had the reliability and performance necessary to en-
dragline stripping is expected to account for about 80% courage others to be built. The largest draglines being
of the total western surface coal production in the built today utilize buckets with capacities from 76 to
foreseeable future. 115 m 3 (100 to 150 cu yd). Fig. II provides a represen-
A highly important difference between draglines tative listing of draglines with pertinent dimensions.
and stripping shovels is the method of locomotion.
The shovel moves on massive crawlers in the manner The Bucket Wheel Excavator
of a bulldozer or military tank . Turning is accom- There are approximately to bucket wheel excava-
plished by powering the crawlers on only one side of tors operating in the US, most of them in Illinois.
the machine, thereby causing it to skid or slew about Bucket wheel excavators are among the largest, most
the center of the crawler on the unpowered side. The complicated, and, under favorable circumstances, most
dragline moves by walking on a pair of retractable productive excavating machines used in surface min-
pontoons which, when extended, are capable of lifting ing, Fig. 12. They effectively remove unconsolidated
the machine off the ground. A pontoon for a medium- overburden, such as earth, glacial till, clay, and soft
sized dragline [say, 57-m 3 (75-cu-yd)] can be 18 or shale, that does not require blasting.
21 m (60 or 70 ft) long by 3.0 to 4.6 m (10 to 15 ft) In a single continuous operation, a bucket wheel
wide. excavator (BWE) will excavate material from a high-
During excavating operations, the dragline rests wall on one side of a mine and deposit it as spoil at
on a large [up to 32 m (105 ft) in diam] ballast-filled the rate of 1147 to 1529 m3 /hr (1500 to 2000 cu yd
c

~------~ __~~B --------~ D

.- "">-
""
<Ii
"..
.-
'"00 . -""
.:

.
<Ii
"
'C
:;:
00
:;:
00
iii
'"00
iii :i-
..."
u

Qj
'"~
-<
oo~

.. "
c:
E
<I>

~
'C
~

00
c:
'c._
iii
'"
oo~
c:u
'0.-
Q.

"""ooe
c: ~
'So .
~
E
.!!!
"" ~

"'"~.
""'iii_c:
~

."c: ...
,,~

~
~
iii
'"
."c:"
,,~

~
-
'"
0
O~
-:>:
E'":'
'"
C
0
Q.

E~
.
Q.

""0 000 Eco E


=',
c tID .S: ~ .~
~

~.~ o0 ',c: 0-
.>!

:;: o "
CO""
,,~

e;: e;: is::: :S',


0;: (3::: u;: CO;:
o~
co;: ""
CO

M 7400 30 220 104-0 117-6 31 - 0 38- 0 4-4 7-3 9-14


P 732 30 173 64- 0 115-0 37-0 30- 10 5-4 10-0 13-19
M 7 500 30 209 84- 0 130-0 3 7-0 39- 0 4- 4 7-3 10- 20
BE 480WD 40 154 80-0 36-0 38-0 4-8 1/, 8-6 120 12- 18
BE 480W 40 154 80-0 36-0 38-0 4- 8 1/, 8- 6 120 12- 18
M 195M 43 98 63- 0 75- 0 26-6 5-9 10- 2 16-18
P 736 30 171 59- 0 115- 0 41-0 41 - 0 6-9 10-6 16-24
P 740 30 197 70-0 120-0 45-0 48- 8 7- 7 11-8 21 - 32
BE 800W 35 179 135-0 45-0 50-0 8-3 14-9 127 16- 26
BE 1260W 30 215 130-0 55-0 52-0 9-0 14-2 129 25-40
P 752 30 221 75-0 135- 0 56-0 57-0 7-8 12-0 36- 48
M 7820 30 262 112- 0 150- 0 50- 0 50- 0 7-4 13-6 35-45
BE 1300W 34 215 150- 0 50- 0 57- 0 9- 0 17- 2 148 42
M 7920 30 263 104-0 135- 0 52-0 66- 0 8- 7% 12- 3 1/4 40- 60
BE 1350W 38 241 150-0 52-0 66- 0 8- 6 15- 2 180 40- 50
BE 1370W 38 241 130-0 58-0 66-0 8-6 15-2 180 52
M 8000 32V, 299 136- 0 180-0 65- 0 66- 0 8-8 13- 9 45-65
P 757 30 259 95- 0 155-0 60-6 63- 0 9- 21/, 15- 0 45- 64
P 762 38 230 113- 0 70- 0 75- 0 75-0 9- 7 16- 0 62- 74
P 862 275 115- 0 165- 0 66- 0 63-0 10- 3 17- 5V, 55- 68
M 8050 33 290 135-0 200- 0 65- 0 66- 0 8-8 13-9 50-70
BE 1500W 38 241 115- 0 63- 6 68- 0 8-6 15-2 180 65
M 8200 37 282 137-0 150-0 58-0 68- 0 11 - 0 14- 10 60- 75
BE 2450W 38 249 130-0 63-6 69-0 8- 0 16- 0 185 75
M 8400 30V, 290 120- 0 200- 0 65-0 66-0 13-0 19-2 60-80
M 8750 37V, 246 132- 4 126- 6 75-0 77- 0 15- 10 21-4 80-115
BE 2560W 30 274 175-0 65- 0 80- 0 14-0 16-0 153 90
BE 2570W 30 283 165-0 74- 0 80- 0 14-0 16-0 158 115
M 8850 30 V, 340 146-0 180-0 80- 0 84- 0 13- 0 21-4 110- 140
M 8950 34 300 137-0 158- 0 80- 0 78- 0 16- 0 22- 0 140- 160
BE 4250W 38 302 185- 0 105-0 105-0 16- 7 24-0 214 220
(0) Diesel electric. All others electric.
Note: All dimensions based on largest bucket capacity available.

Fig. 11. Dragline models and specifications.


"

SURFACE MINING 301


is unique among excavating machines because it is de-
signed to operate continuously, in contrast to stripping
shovels and draglines, which operate cyclically. The
long stacker allows a much greater discharge radius
to be achieved while consuming less power per cubic
yard of materials removed compared to other equip-
ment.
There are many advantages to using BWE's:
I) For a given output, a BWE is actually smaller
than a dragline or shovel.
2) It is a continuous excavator and has no cycle
times.
3) It has lower instantaneous power requirements
and no shock loading.
4) It has a larger discharge radius and can be de-
signed to operate above or below the active mine level.
Specifications and Performance Data 5) It can load mined material efficiently onto a
variety of haulage modes, including truck, hydraulic,
General or belt conveyors.
Overall length (maximum) It 404 6) It can be designed to operate efficiently through
Roller circle diameter, ft 34 a wide range of mining heights.
Height of discharge pOint above coal, ft 144 7) It produces a smaller size consistency of mate-
Excavating range above coal (low), ft 40 rial. In coal, possibly only one further reduction would
(high), It 100 be required to produce a shippable product of 3.2 x
Digging Wheel
o cm (I \4 by 0 in.).
8) It can be designed with ground-bearing pres-
Diameter, ft 24 sures as low as 75.8 kPa (11 psi), but a reasonable
No. of buckets 9
Bucket capacity, cu yd 11/2 (bank measurement)
design is 137.9 kPa (20 psi). Its wheels produce more
Rpm (variable) normal 7 stable slopes and wider benches.
Swing speed at digging pOint, fpm 50-150 9) Close control of selective mining of interbedded
coal and small partings such as high- and low-sulfur
Belts horizons is possible.
Ladder belt width, in. 54 10) It has the flexibility to deliver the mined mate-
Ladder belt speed, fpm 900 rial above or below the working level.
Ladder conveyor length, It 91 II) There is little or no deadweight structure re-
Stacker belt wi<tth, in. 54 quired as counterweight because the stacker and drive
Stacker belt speed, fpm 1,000 are used, unless separate articulation is required.
Stacker conveyor length, It 326
Disadvantages of a BWE are:
Electric Power I) Its machinery is highly complicated and, there-
Motor generators, hp 2 @ 1000 each fore, has reduced availability.
Wheel drive motor, hp 250/500 2) It has less flexibility (due to lack of mobility).
Ladder belt drive motor, hp 187'/,/375 3) It cannot handle consolidated hard materials.
Ladder crowd drive motor, hp 100 4) It requires a large maintenance force and has
Stacker belt drive motors, hp 2 @ 250/500 high initial cost for a given production rate.
Swing drive motors, hp 2 @ 25150 5) The bucket configuration and wheel diameter
Propel drive motors, hp 4 @ 100 can cause problems in trying to follow the bottom of
Weight the coal seam, restricting the unit to mining thick coal
seams only. Thicknesses of coal would have to be at
Working weight without belts, Ib 3,200,000
least 0.7 times the diameter of the wheel.
Metric equivalents: ft x 0.3048 = m; cu yd x 0.764 554 6) In most instances, the great mass of support
9 = m3 ; fpm x 0.005 08 = m/s ; in. x 2.54 = em; in. X 25.4 equipment needed limits its use to thick seams only.
~ mm; hp X 746.0 ~ W; Ib X 0 .453 592 4 ~ kg. Fig. 8 shows the operation of BWE in a pit in
Fig. 12. Bucket-wheel excavator of Peabody Coal Co. at tandem with a shovel. Not only will the more compe-
River King mine, IL. tent rock in the lower portion of the overburden be
loaded with the shovel, but also since this is the portion
of the overburden that is apt to contain acidic materi-
per hr) up to 130 m (426 ft) away on the opposite als, it will be buried by the BWE so that the spoil is
side of the pit. In Germany, the largest such unit in placed back in its approximate original order. The ir-
the world, with a capacity of up to 9175 m 3 /hr (12,000 regular or hedgerow-type effect is also minimized with
ell yd per hr), operates in a brown coal operation. It subsequent reduction in reclamation costs.
302 COAL MINING TECHNOLOGY
The Tower Excavator are no longer produced, and mining firms would have
A method formerly used which may have applica- to show considerable interest in them to spur manufac-
tion in the future is a mining scheme employing a turers into building them. However, with ever-tighten-
tower excavator. This excavator has its greatest utiliza- ing legislation regarding land reclamation procedures
tion in conjunction with a shovel or other equipment in strip mining, this method may be feasible. A tandem
as a tandem operation. It can also be used where a operation that might be considered with a shovel is
dragline must cut a working bench prior to every move. shown in Fig. 13.
The tower excavator can cut the bench ahead of
the dragline or shovel and control the spoil dumping. Pan Scrapers
This has the effect of minimizing peaks and therefore, Pan scrapers have been the backbone of the heavy
minimizes the amount of leveling that must be done construction industry since their invention in the early
by bulldozers and allows a greater depth of mining. 1930s, and are finding wider application in the surface
An added advantage of this method is that the upper mining industry. As a result of the technological im-
strata can be placed over the spoil area to aid the provements during the past years, they can now be
reclamation plan and partially save the topsoils for used to remove moderately consolidated overburden
further use. The bucket size, however, limits the tower as well as various ores.
excavator's application. Furthermore, these excavators The scraper is an all-weather machine, noted for

Surfoce

Ope n
Tai l Bench Co. Heo d

_ ~~h woll_

T owe r
Spo il

Exposed Coal Seam


Spoi I

Pl an View

T owe r
Spo il

/
Tail Head
Tower Tower

Shovel Spoil

Se c ti o n V iew
Fig. 13. Proposed tower excavator bench cutting tandem operation.
SURFACE MINING 303

Fig. 14. Bulldozer removing overburden from a coal seam (John Deere & Co.).

its mobility and versatility. With the advent of state Bulldozers


laws requiring segregation and replacement of topsoil Bulldozers have become the workhorses of the sur~
at surface mine sites, the scraper has found a new face mine, especially in the mountainous terrain typical
home in coal operations. It is expected that stripping of the Appalachian area, and they are being used suc-
(in conjunction with draglines) and reclamation will cessfully for clearing terrain, constructing haul roads,
be the areas of greatest usage for scrapers, whether leveling benches for excavating equipment, tipping
in the east, midwest or west. overburden, and hauling for reclamation work, Figs.
Scrapers are limited in application mainly by high 14 and 15.
maintenance requirements when used in massive rock Both tracktype and wheel-type tractors are being
such as sandstone and deep overburden, and also by employed. In fact, the track-type tractor and the rub-
the high cost encountered for uphill dozing of material. ber-tired front-end loader are being employed at almost
The scraper's primary disadvantage is that its economic all mines in the Appalachian area, regardless of the
efficiency is seriously compromised where the material other equipment available in the mining industry.
to be moved is blocky. Manufacturers, however, have The track ~ type tractor is unmatched in its ability
been designing units capable of loading rocks to 61 to negotiate steep grades and to work in loose or muddy
cm (24 in.) in size. Unconsolidated material and such
rocks as friable shale and coal are, of course, the most
amenable to scraping, and are less costly in terms of
the maintenance, downtime, and tire wear they cause.
When used for reclaiming, scrapers are able to re-
load the stripped overburden material, such as topsoil
and subsoil previously stockpiled, haul it back to the
reclamation site, and replace it relatively evenly over
spoil material. If the various soils have been stockpiled
separately, scrapers can recreate the natural soil layer
sequence that existed over the coal prior to mining.
Pan scrapers are either track- or rubber-tire-pro-
pelled units. Track units are used f9r slow shQrt-range
haulage applications of 305 to 457 m (1000 to 1500
ft) where traction is a problem. In much wider use
are the pneumatic tire-mounted units for high-speed,
long~distance haulage under more favorable footing.
A bulldozer is normally used to push-assist scraper Fig. 15. Bulldozer preparing haul road in a strip pit (John
loading. Deere & Co.).
304 COAL MINING TECHNOLOGY

Fig. 16. Hydraulic excavator stripping last


3.6-m of a 9.1-m (12-ft of a 30-ft) over-
burden (John Deere & Co.).

ground. However, it is limited in top speed to a range tions as primary stripping machines but can be found
of 8.1 to 16 km/h (S to 10 mph), which makes it in all pits as service machines.
uneconomical for production earthmoving over haul The companion to the bulldozer, the front-end
distances of much over 91 m (300 ft). On the other loader, was discussed under "Coal Loading." It is quite
hand, wheel bulldozers have an advantage in speed heavily used in Appalachia as a primary stripping tool
[32 to 48 km/h (20 to 30 mph)] and maneuverability, as we will see in the section on mining methods.
but require more solid and level working bases. These
machines have been used mainly for cleanup opera- Hydraulic Excavators
tions, stockpiling, and moving unconsolidated materi- A relatively newcomer as a stripping unit is the
als. They are used only in the relatively small opera- hydraulic excavator, Fig. 16. Its unique application

Fig. 17. Excavator removing overburden on same base level (Caterpillar).


SURFACE MINING 305

Fig. 18. Excavator loading truck (Caterpillar).

of power, bucket agility, speed, and ease of operations how high an overburden can be mined and how far
exceeds conventional rope shovels in many instances. and high the spoil can be emplaced, establishing the
Because of the unique 3point articulation by hydraulic technological strip ratio (SR). Reach thus enters into
load application, a high penetration force allows the both the technological and economic limitations of the
digging of hard limestone and other rocks without strip pit. The bucket capacity determines the pro-
preparation. Together with reduced capital costs, it ductivity of the machine and thus directly affects the
can bring about significant cost reductions. economic feasibility of an operation. Actually, the
It is equally adept at cutting below the bench as reach and capacity of a given machine are closely re-
with a dragline, Fig. 16, on the same bench, Fig. 17, lated. The product of reach and capacity represents
or for loading of coal, Fig. 18. In the latter case, the an overhanging load which must be adequately sup-
excellent control of the bucket permits good coal clean- ported by the main structural frame of the machine.
ing. It is being increasingly used in overburdens up Therefore, for a given main frame structural unit, the
to 9.1 m (30 ft), especially with the various hauling reach and capacity should be inversely proportional,
techniques or in tandem with bulldozers, or other i.e., one can easily be increased by an appropriate re-
equipment. In Fig. 16 the excavator is taking out the duction of the other.
last of the overburden and passing the spoil to a shovel
further up the slope. MUF Concept
Together with bulldozers and front-end loaders, The maximum usefulness factor (MUF) is the term
the hydraulic excavator finds increasing use in lower used to express the relationship between machine struc-
overburden heights and where limited capital is avail- tural weight and its ability to do work (capacity multi-
able in smaller operations. plied by reach). The MUF is defined as the product
STRIP EQUIPMENT SELECTION AND of the nominal dipper or bucket size in cubic yards
times a functional dumping reach in feet. To gain maxi-
PIT DESIGN mum advantage in constructing shovel-operation spoil
It would be impossible to analyze the selection of piles, the shovel is positioned so that its tracks adjacent
all types of stripping equipment with any degree of to the spoil are as close as possible to the coal deposit
comprehensiveness in this limited treatment of surface rib. A vertical plane passing through the deposit rib
mining. However, since shovels and draglines are used would contain the dot shown above the outside crawl-
in a majority of the strip pits. a more comprehensive ers in Fig. 19. By measuring horizontally from the
treatment of these two pieces of equipment will be outermost edge of the crawlers to the dipper discharge
given here. point, the dumping reach, 's. is established. The maxi-
In designing a strip mine operation, the reach of mum usefulness factor can then be determined in terms
the machine and its capacity are the two most impor- of cubic yards multiplied by feet. For a shovel pit
tant factors to be considered. The reach determines design, both the maximum reach and maximum dump-
306 COAL MINING TECHNOLOGY

h A, H

8
dotum

r--- w ---l b >.1- -


Fig. 19. Shovel pit without coal fender (Woodruff, 1966).
ing height of the stripping unit are critical factors. If shown by the dot above the high wall edge in Fig. 21
the gross machine weight for various stripping shovels is established. Measuring horizontally from the point
is plotted against the maximum usefulness factor for described to the dumping point gives a moment arm
each shovel, the curve appears to follow a generally rd fo( the dragline. The nominal bucket capacity in
straight line regardless of manufacture or size range cubic ' yards multiplied by the arm, rd, determines the
of machine. It has been determined that each MUF maximum usefulness factor for each dragline.
unit requires 338 kg (745Ib) gross weight in the shovel, As with shovels, the dragline gross machine weights
Fig. 20. plotted against the maximum usefulness factors for
Like the shovel, the dragline's ability to handle existing dragline models closely follow a straight line,
deep overburden is normally limited by its ability to Fig. 208. Draglines require 261 kg (575 Ib) of gross
dispose of the spoil. Because this machine usually machine weight for each MUF. Since the cost of mining
works from the overburden surface of a cut or from machines is directly related to weight, the dragline
a bench floor slightly below the surrounding land sur will cost less than the shovel for each unit capability
face, its dumping height usually is not an influencing of work.
factor. For the type of operation described, the dump One useful application of MUF is in comparing
ing reach, rd , in Fig. 21 is the controlling factor. machines such as the Gem of Egypt and the Silver
Walking draglines are mounted on circular bases Spade which operate in the same general area in south-
called tubs. With the diameter of the tub (E in Fig. eastern Ohio. These machines are almost identical in
II), plus a safety margin of onefourth the diameter design (BE 1950B in Fig. 10) and their MUF's are
of the tub between the top edge of the old high wall nearly equal except that the Gem of Egypt is equipped
and the closest point of the tub, a moment center as with a 52m (170 ft) boom and a 99m3 (130 cu yd)
,-

f I I
2 1/
/
6
~(~
S.'I___~
.
0 5

3_ /
~

- f7 4
9
" /G
(b Nott :

g <."l'/ lope of A:.\]S


';i ~z 8~1/467
6 " 11.".. I
Slo p. 01

41--
/ Stopt 01 curve= 1' 745
2f-tt; _.
1/ II
2[7 ''1/ Fig. 20. MUF numbers as a function of
(I() (I<f) t/(X1IIO') machine weight for shovels and draglines
(Woodruff, 1966). A, left, shovels; B,
2 6 8 10
Gross mochine: wpight (lb.) " 2
Gross machine _i!Jl'l1 (lb.)
3
right, draglines.
SURFACE MINING 307

Rd~
I J5E I

datum
Fig. 21. Dragline pit (Woodruff,
I- w 1966).

dipper, designed to handle thin overburden in rela- than the minimum required for clearance. Actually,
tively flat terrain; the Silve, Spade is equipped with a for the larger stripping shovels, a bulldozer will work
61 -m (200 ft) boom, and a SO-m' (105 cu yd) dipper in con junction with the shovel for cleanup, pushing
and is designed to handle deep overburden in hilly the material into the active highwall face for the shovel
terrain. Similarly, the MUF can be used for the drag- to pick up and thus speeding up the shovel operation
line specifications in Fig. 11. It will be noted that a by allowing fuller buckets to be loaded more quickly
range of bucket sizes are shown for many models. The and keeping the swing cycle closer to 90 0 rather than
structural dimensions given in Fig. 11 are for the larg- IS0, which also speeds up the loading cycle. The 53
est size bucket. The reach for a smaller bucket size ft represents an absolute clearance minimum and thus
can easily be calculated using the MUF concept. For a 550B will usually have a minimum pit width of 15
example, " X D, = MUF = '2 X D 2 to 20% more so that at least an 18-m (60 ft) width
will be chosen for the machine. However, pit widths
Designing the Pit of 21 to 24 m (70 to 80 ft) are very common for this
With the aid of Fig. 19, a shovel pit can be designed machine.
for a given stripping shovel model. First the pit width Looking at Fig. 19, it is possible to determine how
must be selected. This is a function of many factors, much overburden can be placed in the spoil area given
but above all it must be able to accommodate the opera- the machine's physical parameters. From this figure,
tion of the stripping shovel in the pit itself. Therefore, the area of the spoil (A,) can be calculated considering
there will be a minimum pit width in which the shovel the maximum dumping height (h), the pit width (W),
will have sufficient clearance to operate. By using Figs. angle of spoil (0), and the pit geometry:
10 and 19, the selection of a minimum pit width is
possible. While the wider the pit usually the more effec-
tive the operation, the pit cannot be so wide that the
A,=(h- ~ tano)w+ ~ (~ tan II)
overburden cannot be put away in the spoil bank with- W' W'
out recasting. Thus the minimum and maximum pit A = Wh--tanO+-tanO
, 2 4
widths for a given shovel operation can be easily deter-
mined. By looking at the shovel parameters in Fig. W'
A, = Wh--tanO
4 (I)
10 and keeping in mind the operational position of
the shovel in Figs. 2 and 19, it should be apparent
that for the rear end of the cab to clear the highwall The spoil pile is equal in area to the area of the overbur-
during the dumping cycle, a minimum pit width equal den cut plus an additional value due to swell (S). The
to at least l-2 N + 0 of the machine will be required. swell factor (S) is defined as the additional volume
As an example, the BE 550B shovel [19 m' (25 cu (area) expansion of the in situ bank material in the
yd)] would require a minimum pit width of 3S.75/2 + loose state. Thus in terms of the bank cut area (A,)
33.5 = 19.37 + 33.5 = 53 ft. However, for cleanup and allowing for the swell, the spoil area can be calcu-
with the shovel, when the boom is perpendicular to lated:
the high wall, the maximum clean-up radius will be
M + N/2 in Fig. 10. For the 550B, this would be (2)
66 + 38.75/2 = 66 + 19 = 85 ft, considerably more
308 COAL MINING TECHNOLOGY
The cut area (A,) is calculated from the pit width
(W) and average overburden height (H): rd = cot 0[H( 1+ I~) + ~ tan 0]
A,= WH (3) +H cot cj>. (8) -
The simultaneous solution of Eqs. I, 2, and 3 gives:
Selecting Machine Capacity

(I + ~)WH = Wh - IV" tan 0 Having tentatively selected a stripp'ing machine


lDO 4 based on reach requirements. appropriate capacity
must also be attained. An estimated capacity table
(I +~)H= h - W tan 0 (4) should be set up as shown in the following example:
lDO 4
From Fig 19 it can be seen that the reach of the shovel Buckel size, ell yd 8
(r,) can be calculated from the spoil angle of repose Buckel fill factor 80%
(0) and the spoil dumping height (h): Buckel load, bank Cll yd 0.88
Cycle time, sec 56
rs = h cot 8 (5) Passes per hours 64
Theoretical bank Cll yd/hr 51Q
Substituting for h in Eq. 4 from Eq. 5 yields: Monthly operating hours 720
Theoretical bank Cll yd/month 36,8008
r,- - t a
S- ) H = - - WnO Monthly operating factor 85%
( 1 +IDO cot 0 4 Bank Cll yd/month o utput 31,2008

Rearranging to solve for H yields:


An explanation of each item follows:
r, W Shovels are designated by dipper size (D) while
----tanO
cot 0 4 draglin es are designated by bucket size (B); in either
H (6)
S case, the size of the dipper or bucket is expressed in
1+ - cubic yards of level volume (loose) measure. In our
lDO
discussion, Band D will be used interchangeably. In
Thus for a given machine size, considering the mate- the calculation of overburden or spoil values, it is com-
rial-pit parameters, it is possible to determine the high- mon to employ the in-place or bank volume in cubic
wall limit of mining. A calculation of the technological yards. In the loading of a bucket, the swell factor will
strip limit is possible by calculating the weight of the result in less bank cubic yards than represented by
coal in tons in a unit length of cut and dividing it the actual volume of loose material in the bucket; on
into the overburden unit volume: the other hand, during loading of the bucket, less than
a full bucket of level measure may be loaded or actually
v.o:::l"o"f...:o,-,v-.:e:.:rb:.:u=f.::d",en,,-,,(c:.:u,-,y"d",)
SR=- a surcharge load may be produced. The shovel is apt
tonnage of coal (tons) to have a surcharge value whereas the dragline will
WH X I ft ~27 usually have a tendency to less than a full bucket mea-
tW X I X 85+2000 sure, although operator skill will affect the fillability
of both. The influence of these two factors is expressed
where t is thickness of the coal seam, 85 Ib is the
in the bucket-fill factor which gives the percentage
average weight of a cubic foot of coal, and dividing
of the level bucket capacity expressed in bank yards
by 2000 Ib gives tonnage.
actually loaded per cycle. Typical fill factors are found
Some typical ranges for the parameters listed in
to be 80 to 95%; our example utilizes an 80% fill
the equations for sedimentary strata overlying coal
factor so the bucket load expressed in bank cubic yards
seams are: e,
angle of repose, 33 to 38 0 ; <1>, highwall
will be 0.8B.
angle, 60 to 90 0 , depending upon the competency
0
Cycle time refers to the time required between the
of the material; and S, swell factor, 25 to 35%.
commencing of dumping the bucket on the spoil until
A view of Fig. 21 reveals that Eqs. I to 4, derived
dumping commences again for the subsequent load,
for the shovel pit, hold equally well for the dragline
thus including one complete cycle of operation. Typical
pit because the geometry for the spoil and cut area
shovel cycles may vary from 40 to 58 sec while drag-
are identical. Rearranging Eq. 6 gives the shovel reach
lines will usually take 58 to 68 sec. In our example,
in terms of the other parameters:
a 56-sec cycle is taken. Dividing 56 into the 36DO sec
r, = cot 0[(1 + I~)H + ~ tan 0) ] (7)
available in an hour gives the passes per hour (64).
Multiplying the passes per hour by line 3, bucket load
in bank cu yd, 64 (0.8B) = 51B (line 6).
Looking at Fig. 21, it should be apparent that the Large stripping units are scheduled to operate more
dragline reach (rd) will be equal to the shovel reach continuously than any other mining equipment, so it
(r,) plus an additional amount equal to the horizontal is not uncommon to see them scheduled for 720 hr
projection of the high wall slope: (in our example) out of a total possible number of
rd = r, + H cot cj> 730 hr per month. However, any number less than
SURFACE MINING 309
this may be used according to the working schedule. alone (1), the BE 480W dragline in tandem (2) and
Multiplying theoretical bank cubic yards per hour the dragline used for stripping alone (3) provides the
(5IB) by the monthly operating hours (720) gives a following outputs in cubic yards per month.
theoretical bank cubic yards per month (36,800B).
During the scheduled hours, however, there will be
machine maintenance delays and other delays such BE 480 W BE 480W
182 M dragline dragline
as stopping for lunch and waiting for blasting or power shovel in tandem used alone
outages. These are lumped together as the monthly (1) (2) (3)
operating factor. Well-run mining operations can Dipper size, cu yd 10 15 15
achieve monthly operating factors between 80 and Dipper fill factor 0.85 0.8 0.8
90%; our example utilizes 85%. Therefore, in our ex- Dipper load, bank cu yd 8.5 12 12
ample, multiplying the theoretical bank cubic yards Cycle time, sec 50 59 59
Passes per hr 72 61.017 61.017
per month (36,800B) by the monthly operating factor Theor. bank cu yd per hr 612 732.2 732.2
(0.85) gives the actual bank cubic-yard per month out- Monthly oper. hr 336 576 720
put that can be expected given the assumed conditions Theor. bank cu yd per
(31 ,200B). Depending upon the amount of overburden month 205,632 421 ,747 527, 184
Monthly oper. factor -0.7 0.75 0.75
that must be moved to achieve the desired production, Bank cu yd per month 143,942 316,310 395,388
the bucket size needed is easily calculated. Of course,
suitable time studies will provide more accurate factors
for a specific operation than those given here. Entering Fig. 9 to obtain specifications for a 182M
An example will illustrate the use of the preceding shovel operating alone ( 1) reveals a clearance radius
information: of 23 ft (K) and a width across the crawlers of 21.5
I) A second-hand, 182M loading shovel with a ft (J). Based on clearance the minimum pit width
7.6-m' (10 cu yd) bucket is to be used for both overbur- would have to be:
den stripping and loading of a l.2-m (4 ft) thick seam
that outcrops with 0.6 m (2 ft) of cover and then ex- J 21.6
tends into a gentle hill that has a slope of 0.3 m in K +"2 = 23.0 + - 2- = 23.0 + 10.8 = 33.8 fl. (9)
3.0 m (1 ft in 10 ft). The shovel will be scheduled
for stripping 336 hr per month and has the following But based on a maximum cleanup radius of 39 ft (1),
characteristics: dipper factor, 85%; cycle time, 50 sec; the following cleanup width is required:
70% monthly operating factor. The overburden has
a swell factor of 30%, the highwall angle is 74 with J
the hori zontal while the spoil pile angle of repose is 1+"2 = 39.0 + 10.8 = 49.8 fl.
37. Calculate the number of cuts to the technological
limit, the monthly production of coal in the last cut, Therefore, choose W = 50 ft.
and the strip ratio. Check digging reach:
2) Having determined that the strip ratio for the
shovel is far below the economic strip ratio, a BE 480 J
W dragline equipped with a 12-m' (15 cu yd) bucket D +"2 = 52 + 10.8 = 62.8 fl.
is purchased for use in tandem with the shovel. For
a dragline with the following characteristics: dipper Next, dumping reach, 's. must be determined. This
factor, 80%; cycle time, 59 sec; and a monthly operat- is detennined using the tables and a suitable sketch
ing factor of 75%, determine the following if the drag- to scale. From Fig. 9 two points are available in the
line is scheduled for 576 hr of operation per month circular dumping cycle. from column A and Band
and all the factors remain the same as in (1): column C and D. Plotting these two points and inter-
a) Number of additional cuts possible for complete connecting them by a straight line gives the dumping
operation. reach, r" where the line crosses the profile of the spoil
b) Division of highwaU between shovel and drag- pile [12 m (40 ft)l:
line for complete operation.
c) Strip ratio in last cuI.
d) Monthly production in last cut.
,,
3) Finally, deciding that the tandem operation is /
unduly constraining and that the use of the shovel ,/
for both stripping and loading of coal is less than ideal, ' -~"'\r./
the dragline is scheduled 720 hr a month for stripping
and the shovel is used only for loading coal. Determine:
a) Maximum technological limit for dragline.
b) Strip ratio in the last cut. ,,
c) Monthly production in last cut. /
/
/
Setting up the capacity tables for the 182M shovel
310 COAL MINING TECHNOLOGY
The number of possible cuts are next determined. r18B18 ~ r'5B15 ~ 127(18) ~ 15r,5.
To do this, the average high wall depth of the last cut
Therefore
to be mined must be determined from Eq. 6:
127(\ 8)
W 152.4 ft.
r/ cot IJ - 4 tan IJ
T15 =
IS
H Utilizing Eq. 8, but remembering the adjacent cut area
1 + S/ IOO
must be left open for the shovel spoil:
50
~ 4O/cot 37 - - tan 37
4 152.4 ~ H cot 74 + cot 37 [( 1 + 13~) H
1+30/100
30.14 - 9.42 50 ] + 50
::..::.c..,-,----,-,-= ~ 15.94 ft. (10) +4tan37
\.3
152.4 = 0.2867 H + 1.7251H + 12.5 + 50
The following sketch reveals that only three cuts H ~ 44.7 ft.
can be mined since the average highwall in the fourth
cut would be in excess of 15.94 ft: From the sketch below, it is apparent that nine
cuts can be taken (six additional) since the average
overburden height in the 9th cut (44.5 ft) will be less
than the 44.7 ft calculated to be possible:
CD :
2~

0
Therefore, three cuts are possible and the volume of


overburden per linear foot in the last cut can be calcu- 8.2
lated:
cuyd
linear ft
14.5 X SOX 1ft
27 cu ft/cu yd
17 22 27 32 37 42 44. 5: 47
I
~
eli yd overburden
"-----...
~ 26.85 (last or 3rd cut). Calculating the volume of overburden in the last cut
linear ft as before:
The coal tonnage per linear foot in the last or 3rd cu yd OB 44.5' X 50' X I'
cut can also be calculated: 82.41 cu yd
linear ft 27 cu ftf cu yd
4 X 50 X I X 85 Ib/cu ft
-'----'.-'----"-==....:..::'-'-' ~ 8.5 tons per linear ft. 82.41
2000 Ib/ton therefore, the strip ratio = - - ~ 9.7
8.5
Having calculated these, the strip ratio can then be
obtained: To determine the proportion of the high wall each ma-
chine must mine:
Strip ratio (SR) ~ ====-'-=
overburden vol
coal tonnage
26.85 _
---3.1.
8.5
6
shovel - 143,942
dragline - 316,3 10
Finally, the monthly production of coal in the last total - 460,252 cu yd per month
cut will be:
shovel: 143,942 (44.5) ~ 13.92 ft
143,942 460,252
45,551.2 tons.
3.16 316,310 30.58 ft
To solve for part (2), entering Fig. II , it can be dragline: 460,252 (44.5) ~ 44.50 ft check
seen that the dumping radius of a BE 480W dragline
(column B) is 154 ft for a bucket size of 18 cu yd, monthly production of coal in the last cut = 46~:~52
since all structural dimensions in the table coincide ~ 47,449 tons.
with the largest bucket size listed. The reach of the
dragline is always calculated by multiplying the tub (3) To find the number of cuts that the dragline
diameter (column E) by 0.75 and deducting the prod- can mine alone, apply Eq. 10:
uct from the dragline dumping radius; thus:
152.4 ~ 0.2867H + 1.7251H + 12.5
r'8 = 154 - 0.75(36) ~ 154 - 27 ~ 127 ft. 139.9
H=-- ~69.6ft
Remembering the MUF concept: 2.01
SURFACE MINING 311
midpoint of the 13th cut = 64.5 ft
midpoint of the 14th cut = 69.5 ft
therefore, 14 cuts are possible.
cu yd OB 69.5' x 50' x I'
---:---= 128.7 cu yd
linear ft 27 cu ftlcu yd'
therefore, the strip ratio is 15.14
monthly production of coal in the last cut = 3i~:~!8
= 26,115 tons
MINING METHODS A. Typical contour strip method.

Mining methods are patterned to the natural condi -


tions that exist in a region. Topography, type of over-
burden, and climate are some of the more important diameter= 2/3 X Coal sea
of these conditions. Since these vary from region to
region, it is to be expected that the method of mining
will vary as well. Also, however, systems evolve as a
tradition in a region. Therefore, the logical classifica- ft fo 150 ft
tion of mining is on the basis of region (Skelly and Longitudinal section of on auge r ho le
Loy, 1975).

Region I
Note: Unm ined cool is left around holes
Natural Conditions: This bituminous coal region and wasted.
in the eastern US is a major, elongated depositional
basin containing a series of local, parallel, northeast-
southwest trending synclinal basins, occasionally offset
by faulting, Fig. l. Erosion of sedimentary strata by
dissecting streams has produced a series of steeply slop-
ing valleys and ridges. Overburden consists of shales Spacing of auger holes dr ill ed from the highwall
and blocky sandstones, many of which are acidic. Sur-
B. Coal losses from auger mining.
face mines are stripped, on the average, of 17 m (55
ft) of overburden, ranging from zero outcrop up to a Fig. 22. Typical contour strip mining, A, showing augering
maximum 30 m (100 ft). of highwall, B (Skelly and Loy, 1975).
Many thinly bedded coals exist in this region, re-
flecting a static depositional environment. However, sive casting is commonly employed in which holes are
seam thicknesses are variable, and most of the impor- drilled on close spacing and heavily charged to heave
tant seams contain shale particles. Climatic conditions as much as 50% of the material out of the pit and
vary considerably with the greatest seasonal variation down the slope. Since the overburden contains highly
in West Virginia, going from an average minimum toxic materials, severe environmental mine drainage
temperature of -6.7C (20F) in the winter to an aver- problems are created; mudslides and other erosion pro-
age summer temperature of 29.4C (85 F). Precipita- duced are not conducive to establishing vegetation on
tion is substantial, the annual average being between the slopes. The unstable highwall that is left behind
91 and 127 cm (36 and 50 in.). creates further erosion and ponution problems. There-
Conventional Contour Strip Mining: Region I has fore, because of the severe environmental degradation
been characterized throughout the years by its wide- resulting from this method, both temporarily and per-
spread use of contour strip mining, Fig. 22A. In con- manently, it has been outlawed in virtually all states
tour stripping, an initial cut is established along the and will have little future application. It is listed here
hillside at the point where the coal outcrops. Successive for background information only.
cuts are made into the hill, discontinuing the operation Contour stripping primarily utilizes the unit opera-
at a specific stripping ratio, either economic or techno- tions of clearing and grubbing, overburden prepara-
logical. Depending on thickness, continuity, slope, and tion, overburden removal , coal loading, coal hauling,
quality of the coal seam, type and conditions of over- augering, regrading and back filling, and revegetation.
burden, size of mine area, and the return per ton of Only those aspects of contour stripping that are pecu-
coal mined, this ratio can be as much as 30: I and liar to it will be discussed here, and then only briefly.
still provide a profitable operation using this mining The proposed affected area is usually cleared of
technique. vegetation by timbering and/or removal with dozers.
Contour stripping affects a large area, especially Dozers push this material downslope to the projected
on the downslope side. Not only is the overburden toe of the spoil pile to create a brush dam which helps
indiscriminately cast over the side of the hill but explo- to establish the spoil bank of dirt and sediment. This
312 COAL MINING TECHNOLOGY
unit operation is not always necessary, and in some coordination and scheduling of the various procedures
instances it is eliminated and all vegetation is simply included in the haul back method in order to eliminate
buried in the spoil during overburden removal. The production delays. Spoil material generated by the ini-
overburden is prepared by either drilling and blasting tial benching-down process is loaded and hauled to
with ANFO or by ripping. Both bulldozers and front- a previously determined storage area with segregation
end loaders are used for stripping. Coal loading usually and burial of blackish shale, waste coal, and toxic and
is accomplished by the same loader used in the strip- other acid-producing materials which are not condu-
ping process. However, when the coal is too hard or cive to revegetation. Remaining overburden is carefully
too thick for effective front-end loader use, shovels and precisely blasted using specialized techniques such
are employed as a substitute provided the underclay as deck loading, which would permit a subsequent inte-
can support them. The coal is either ripped or blasted rior cut, as well as prevent formation of an uncon-
prior to haulage with small-capacity 14 to 27 t (15 trolled outcrop area.
to 30 ton), on-the-road-type trucks, usually end-dump. Excavation, haulage, and deposition of overburden
Usually, when the maximum strip ratio has been is conducted parallel to the crop line following blasting.
reached, the highwall will be auger-mined, Fig. 22. All movement of overburden is toward the mined-out
Augering is done by drilling horizontal holes into the area, thereby precluding possibilities of baving uncon-
seam. While holes up to 61 m (200 ft) deep can be trolled spillage on the outslopes. Spoils are segregated
drilled sometimes, the auger either sags and thus pene- on emplacement and regraded and revegetated as soon
trates the bottom or wanders laterally into adjacent as possible. Concurrent reclamation associated with
holes, thus resulting in shorter holes. While augering lateral movement allows for immediate revegetation
can provide cheap coal, it provides poor recovery, Fig. and spoil stabilization, further enhancing its value as
228 and can result in severe water pollution problems, an environmentally sound method of mining.
especially if the holes penetrate abandoned under- Three basic combinations of stripping equipment
ground mines. are usually employed with the haulback technique, Fig.
In summary, regrading, back filling, and revegeta- 23: (A) front-end-Ioader truck, (B) scrapers, and (C)
tion are difficult if not impossible with contour strip- combination of both. Two loaders and two to four
ping, at least at reasonable cost. While the technique trucks can work very effectively in the pit, providing
can produce cheap coal, it does not require any compli- high production. Dozers assist by pushing overburden
cated or time-consuming mine preplanning, and re- down to the loader for easy digging and loading. Other
quires less capital expenditure for equipment and sup- services such as construction of ramps and haul roads
plies, it has obvious environmental disadvantages are performed by the dozer. A great deal of flexibility
which preclude its use for the future. is possible with the use of trucks with controlled depo-
Lateral Movement or Hauiback Method: This sition and segregation of spoil material possible without
newly developed mining method, Fig. 23, was initiated interfering with augering, reclamation, or auxiliary op-
as a means of eliminating one of the critical factors erations.
inhibiting achievement of effective and productive rec- Stripping shovels are rarely used to load overbur-
lamation in the hills and mountains of Region 1- den because of their lack of mobility and maneuverabil-
problematic outslope spillage. Selection of an adjacent ity, although they do have an advantage over the front-
hollow valley or low area for initial overburden dis- end loader where poor overburden footing is obtained
posal is the first consideration for beginning the opera- and thus digging is difficult. However, large front-end
tion. This phase is essential to eliminate indiscriminate loaders are the rule with shovels being used only be-
casting of first-cut material over the bench. If a hollow cause they are available.
is utilized, then extensive preplanning for the construc- The loader-truck combination provides the follow-
tion of underdrains and terracing must be imple- ing advantages: (I) ultimate placement and distribution
mented. In addition, this head-of-hollow fill can be of spoil; (2) under good conditions, production can
utilized in conjunction with appropriately sloping ac- easily be increased by simply adding a truck; (3) a
cess roads to form a conveyance system for mine water wide variation in overburden can be handled. Disad-
and surface runoff. Water can be diverted and chan- vantages are: (1) increasing the number of trucks cre-
neled into rock drains, preventing its contact with spoil ates congestion and slowdowns; (2) it is difficult to
material and providing effective erosion controL The match loader-trucks for maximum production; (3)
next step entails construction of the haul road on or good timing and planning are essential; and (4) spoil
below the predicted coal seam cropline. In addition deposition is intermittent by truck-loading, dumping,
to serving as an integral component in the removal and backing.
of overburden, this roadway, situated on the crop Since scrapers can dig their own loads, transport
bench, can aid in prevention of water, rock, and over- them at speeds up to 56 kmlh (35 mph), and spread
burden spillage downslope. and compact them in the dumping area, these machines
A great deal of preplanning is involved in the next offer good cost advantages over truck hauls on the
step: benching down by blasting overburden at the short distances associated with the haul back technique.
point calculated to be the highwalllimit. An important Two to three scrapers supported by a ripper-dozer can
factor here is the bench width required to allow efficient provide effective one-step loading and hauling in the
SURFACE MINING 313

A. Typical truck haulback method.

B. Typical scraper haulback method.

C. Typical truck and scraper haulback method.


Fig. 23. Typical haulback or lateral movement methods (Skelly and Loy, 1975).
314 COAL MINING TECHNOLOGY

haulback technique. Advantages of the technique are: clude water diversion, acid neutralization, and con-
(I) less equipment is needed in the pit since scrapers struction of sediment basins.
are usually self-loading and can build and maintain Since an ounce of prevention is worth a pound
their own roads; (2) no time is lost loading and dump- of cure according to the old adage, the key to pollution
ing, compaction is achieved, and there is less delay control is to reduce the need for treatment to a mini-
in production if a machine breaks down; (3) greater mum. By using water diversion systems (ditches,
production per hour on short hauls with better regrad- flumes, pipes, trench basins, and dikes), water can be
ing and compacting results in less subsequent reclama- kept from contact with acid-producing materials and
tion work; and (4) steep grades are easily handled. from picking up of sediments from disturbed areas,
The main disadvantage is that hard, blocky overburden Fig. 24. A diversion ditch along the top of the high wall
can not be handled as easily as with loaders and trucks. is standard practice, except when accompanied by a
A combination of the foregoing techniques is ideal haul road, Fig. 23C, which then substitutes as a diver-
with the scrapers removing the less consolidated mate- sion ditch. The edge of the haul road along the outcrop
rial near the surface while the loader-trucks handle bench is also used to collect surface drainage which
the blockier material over the coal. Scrapers can be is directed to a sump. Techniques of neutralization
routed along the top of the high wall, Fig. 23C, mini- and sedimentation control are similar. in all mining
mizing pit congestion, and can spread the overburden methods in this region and Fig. 24 shows how this
without the use of a dozer. On the other hand, loader is accomplished. Neutralization is obtained by using
trucks can be assigned to handle the overburden near lime and soda ash treatment. Treatment equipment
the seam, which is more toxic and blocky, and can is simple and mobile, with the size of equipment de-
avoid tramming steep grades for which they are not pending upon water flow and quality.
well suited. Mountaintop Removal and Valley Fill: This is a
The coal is generally ripped by the dozer available new method of mining developed in Region I which
and loaded by the same front-end loaders used in over- is not extensively used. It makes possible nearly 100%
burden handling. It should be apparent that the mobil- recovery of a coal seam in very hilly and mountainous
ity and flexibility of front-end loaders for overburden areas using the same equipment employed in contour
and coal handling, and their suitability for narrow pits mining. The first cut is executed in a box-cut manner
and steep slopes make them a favorite in Region I. across the ridge, isolating an undisturbed coal and
The following substantial advantages can be ex- overburden barrier of at least 4.6 m (15 ft) on the
pected with the lateral movement technique compared outslope, Fig. 2SA. This barrier serves as a natural
to conventional contour mining: (1) there are minimal seal along the outcrop to retain surface and mine water
erosion and landslide problems with the elimination during the actual mining process; later it provides sup-
of outslope spoil; (2) highwalls are eliminated; (3) seg- port for the back-filled overburden and helps confine
regation of the overburden results in better revegetation ground water within the regraded spoil. The overbur-
and less acid mine drainage; (4) concurrent reclamation den excavated during this first cut is placed in a valley
minimizes environmental problems; (5) there is mini- or head-of-hollow fill. After the initial cut and removal
mal disturbance of adjacent land; (6) disturbed land of the coal, mining proceeds in a series of cuts, parallel
area is reduced (50%), as are subsequent back filling to the first and adjacent to one another with concurrent
and revegetation costs; (7) ultimate control of back reclamation. Spoil from each new cut is placed in the
filling is possible; (8) the mining of coal seams on ex- adjacent excavated cut and in valley fills, until the
tremely steep slopes is possible; (9) the reclaimed land entire mountaintop has been removed.
has excellent recreational and wildlife land-use poten- Valley or head-of-hollow fill is a technique most
tial; and (10) overburden need be handled only once. frequently employed with mountaintop removal. Such
The disadvantages of the lateral movement include hollows must be free of underground mine openings
the following: (I) there are higher initial capital costs and natural springs, with vegetation removed and rock
for additional equipment and decreased rate of produc- drains constructed where natural drainage previously
tion produces an approximate 30% increase in overall existed, Fig. 2SB. This artificial drainage system pro-
production costs; (2) extensive premining planning is vides a continuous water conveyance permitting
necessary to properly schedule and execute the various ground water and natural drainage to percolate
phases without delays; (3) the critical drilling and blast- through the fill without saturating it, thus greatly re-
ing required to control overburden is time consuming; ducing landslide and erosion problems.
and (4) the availability of storage area for excess over- After mining is completed, previously rugged
burden and other considerations of overburden quality mountaintops are transformed into level land which
and strip ratios may not be favorable. may be scarce and thus very valuable. Advantages of
Pollution Control: Since the coal seams in Region this technique include the following: (1) coal can be
I contain considerable pyrites, water pollution is a con- mined where underground or other surface methods
siderable threat. Proper design, construction, and would not be feasible; (2) total resource recovery is
maintenance of pollution control facilities can alleviate possible; (3) valuable level land becomes available for
these threats, and maintain acceptable water quality agricultural, recreational, home, commercial, and in-
in streams. Common control techniques applied in- dustrial development; (4) steep unconsolidated out-
SURFACE MINING 315

~'C? _

La nd ( '7' / /' '; /


/
', /' /
. ~ ,""- " /
Di ve r sion Dit ch .

Div ersi on Dit ch Neutral izat io n


Se ttli ng Basin
A. Typical contour strip method water handling system.

B. Typical truck haulback method water handling system.


Fig. 24. Typical drainage systems with surface mining (Skelly and Loy, 1975).

slopes of spoil are eliminated, reducing the erosion Like many new mining methods, improvement in
problems associated with them; (5) highwalls are com- techniques could result in greater cost reduction for
pletely eliminated; and (6) overburden can be easily the mountaintop removal method. Its future use will
segregated, reducing acid mine drainage and facilitat- be influenced by changing laws, environmental con-
ing revegetation. cerns, and public opinion on the aesthetic values of
Disadvantages associated with the technique in- the method.
clude: (l) there are increased capital costs for addi-
tional equipment; (2) extensive premine planning is Region II
required to maximize productivity and minimize costs; Natllral Conditions: While Pennsylvania, Mary-
(3) planning and proper construction of valley fills are land, and southern Ohio are disconnected from Ala-
time-consuming and costly; and (4) valleys are not bama in this region, Fig. IB, they are similar, represent-
always available for filL ing the edges of the Appalachian Mountain chain.
01

316 COAL MINING TECHNOLOGY

A. Typical mountaintop removal-valley fill method.

Origino I ground SUI' fa'ce -____

H i ghwal l--~2=

Fil l
Lafera l

Roc k- f illed natural dra inway

R Cross section 01 typical head-aI-hollow lilL


Fig. 25, Mountaintop removal (Skelley and Loy, 1975),

Therefore, while they resemble Region I to some de- tour stripping in Alabama, modified block cut in Penn-
gree, the topography is generally less steep and the sylvania, dragline and shovel usage in box cut contour
terrain more rolling, although the variation can be mining and modified area mining, and dozers and load-
great, from relatively flat in Ohio and southern Ala- ers in small mines. The more popular methods in this
bama to quite rugged in the mountain ridges of central region will be described. To some extent, mining in
Pennsylvania and Maryland, While the seams are rela- a more level topograpby here is similar to that in Re-
tively flat and continuous, in some local areas, they gion III, but methods peculiar to such conditions will
may dip up to 30 and some faulting may be encoun- be deferred generally to the discussion of mining meth-
tered. As many as 40 minable seams occur in Pennsyl- ods in Region III. Also, since conventional contour
vania and Maryland with overburden commonly con- stripping as described in Fig, 22 in Region I is presently
sisting of sedimentary clays, sandstones, and shales permitted by law only in Alabama, and even here is
with some massive stone. probably on its way out under the new federal regula-
While the mining methods in Region II are similar tions, no further treatment of this method will be pro-
to those in Region I to a considerable degree, the vided,
greater variation in topography results in a greater Box-Cut Contour Mining: While this method pro-
variation of methods. These include conventional con- vides for spoiling overburden on the outslopes, Fig,
SURFACE MINING 317

Fig. 26. Typical boxcut contour method (Skelly and Loy. 1975).

26, important differences from conventional contour permit area as possible, leaving a 7.6-m (25 ft) wide,
stripping result in better environmental control, al- low-wall barrier, with spoil being compacted, graded,
though problems will exist. A major difference is that and temporarily seeded on the outslope. Coal from
a coal barrier 4.6 to 7.6 m (15 to 25 ft) thick must this initial cut is removed, after which overburden from
be left at the outcrop, depending upon the state law. cut No.2 (approximately one-third to one-half as long
This barrier confines the water to the pit and prevents as the initial cut) is placed in cut No. 1. When cut
its flow through the spoil area which would result in No.2 coal is exposed and ready for loading, stripping
landslides and acid drainage problems. Also, equip- of cut No. 3 begins and continues through No. 2'5
ment differs, draglines and shovels being much more loading cycle, with the spoil placed in the remaining
adaptable to providing the required coal barrier rather portion of the initial cut. Regrading and revegetation
than dozers and front-end loaders. While this method of the first cut is then accomplished. Overburden from
will also be obsolete soon, it is briefly described. cut No.4 is placed in cut No.2 after the coal is totally
Blasting Ihust be carefully controlled to avoid frac- exposed in cut No.3, then No.5 overburden is removed
turing the low-wall barrier, with dozer ripping substi- to No.3, No.6 to No.4, etc., until completion. Recla-
tuted whenever possible. A typical two-cut sequence mation grading is conducted as the final load of spoil
is shown in Fig. 27. The upper material in the cut is pushed into a mined-out cut, with revegetation of
next to the final high wall is cast on the outslope as the graded blocks occurring as soon as weather per-
shown, graded, and revegetated as the first step. This mits. Successive cuts become smaller as mining contin-
material is probably more conducive to revegetation ues, thus minimizing the amount of overburden that
and less likely to contain acid-bearing materials. In must be hauled to fill the final pit. The first cut spoil
the second step, the material in the lower part of this stored on the outslope is back filled into the pit gradu-
cut is cast on to the coal berm, uncovering the coal ally so that, when mining is completed, virtually the
in the first cut which can subsequently be mined. From original contour of the slope is achieved with minimal
this point on, parallel cuts can be taken into the hillside, environmental degradation. At some sites, cut se-
casting overburden into the previously mined area until quences proceed in one direction only, although this
some practical strip limit is reached. Steps 3 and 4 does not allow continuous coal loading and therefore
in Fig. 27 show how the pit is completed for two cuts is not as efficient.
only. As can be seen, part of the coal covered in the Dozers remove the topsoil on moderate slopes by
second step is uncovered and mined with the excess pushing it uphill and storing it on the top of the ex-
spoil from the second pit that is left after spoil has pected high wall, but on steeper terrain topsoil is stored
been piled against the highwall (3rd step) being placed on the lower wall barrier until reclamation. Scrapers
back into the pit, (4th step). are generally not used in this technique. Bulldozers
While the carefully placed materials on the down- and front-end loaders move overburden in a load-and-
slope create fewer environmental problems than con- carry operation by simply pushing and carrying mate-
ventional contour stripping, such problems do occur rial to the adjacent vacant block. Spoil segregation is
with any downslope disposal technique. Thus this is simple, with blocky acid material buried at the base
proving to be an unacceptable practice, too. of the high wall. Usually two dozers and two loaders
Modified Block-Cut Mining: The contour mining will operate at a given site. As the coal becomes ex-
method known as modified block-cut mining or simply posed, one of the loaders remains behind to load coal
block cut reduces spoil spillage on the outslopes, and while the rest of the fleet uncovers the next block. If
creates few environmental disturbances, Fig. 28. This the coal must be fractured before loading, one of the
technique is quite similar to the haul-back method since dozers will be used to rip it. End-dump highway trucks
all the spoil, except for the initial cut, is moved laterally with capacities of 18 to 27 t (20 to 30 tons) are used
along the bench after the topsoil has been removed for haulage; frequently they are contracted.
and stored, either on the high wall or at the outcrop. Since overburden removal and back filling are inte-
Initially, a box or block cut is excavated to the limiting gral parts of the operation, the only extra reclamation
high-wall height as close to the center of the mining procedure required is replacement of the topsoil by a
...'"
co
PROCEDURE PROCEDURE
I. Clear 8 grub from poinl A 10 point B. I. Compacl suilable spoil into and above
2. Make cui ACD. auger holes ( if appl icable ).
3. Place spoil from ACD onlo DE B.
....-Diversion Ditch 4. Eslablish rood at point E on fi ll bench. 2. Push sp oil aga insl highwall and uncover
5. Solid bench - poinl C to poinl D. Di vers ion Di lch Excess Spoil coal in 2nd pit. Slack any excess
6. Fill bench - point C 10 poinl D. from belween rood and pit.
~:)r-Highwall
2nd Pi 3.Leave 01 least 1511. barrier.
7. Vegetate outslope spo il.
4. Pick up cool.

Original Ground Surface Original Ground Surfac e - - -


1st Step 3 rd Step

PROCEDURE PROC EDURE


Diver sion Dilch I. Remove and stock spoil from lsi pit. I. Push spoi l inlo 2nd pit.
Spoil from Pil width is 1/3 of l ot al bench-(solid 2.Slope bench 10 specified grade.
1st pil bench plus f ill bench). Diversion Ditch 3.AI leasl 15 11. of barr ier is left inlact.
==..-Hlghwall 2. Pick up cool. 4.Road on edge of fil l bench is not disturbed.
3. Auger if permilled . Highwall Low - wa ll
., . . :.)Road Borr ier Reverse Terrace Slope
Rood

Original Ground Su rfa ce/


Cool Seam
2nd Step Original Ground Surface
4 th ,Step

Fig. 27. Typica l boxcut (two cuts) method (Skelly and Loy, 1975).

J ) j ) )
SURFACE MINING 319

------- -----
- - - - - - - _ _ _ _ _ _ 0.
---- - -

-. .,......
-.

151 Slep

2nd Slep
Fig. 28. Typi cal modified block-cut method. Top, first step; bottom, second step (Skelly
and Loy, 1975).

dozer either by pushing it upslope or downslope to capital investment is required since as few as two ma-
cover the affected area. Revegetation should be easily chines may be used; (4) land slides are eliminated;
established after reclamation is completed, creating an (5) acid formation is retarded since toxic materials
environmentally sound area. Advantages accruing are immediately buried; (6) highwalls are eliminated;
from this technique include the following: (I) aestheti- (7) fast reclamation is accomplished; (8) there is mini-
cally pleasing results are achieved with excellent com- mum erosion; (9) multi-seam mining is practical; and
plete reclamation of the affected area and no distur- (10) the disturbed area is minimized. Some disadvan-
bance to adjacent land above and below the permit; tages are: (I) small total coal production per year is
(2) no double handling of spoil is required; (3) low achieved and the method limited to small operations,
320 COAL MINING TECHNOLOGY

~~.-.c:::::::'~~ -=-::~~-:._:::.>
~~~--.

Fig. 29. Typical modified area mining method (Skelly and Loy, 1975).

although high tons per man hour are possible; (2) Pollution Control: As can be seen in Fig. 30, the
proper planning, design, and scheduling are necessary; use of diversion ditches, sediment retention structures,
and (3) good location is needed for initial fill. and neutralization facilities in this region are similar
Modified Area Mining: While this technique re- to that in Region I. Pit collection sumps are excavated
sembles the mountaintop removal method of Region in the strata beneath the coal seam at the lowest point
I, inasmuch as hilltop or ridge removal is accom- in the pit to collect ground water and/or surface runoff
plished, it is practiced in rolling terrain rather than which is automatically pumped via pipeline to neutral-
on steeply sloping mountains, Fig. 29. It is especially ization and sedimentation facilities.
adaptable to abandoned contour strippings that previ- Block-Area Mining: Block-area mining is a com-
ously had reached the upper economic strip ratio. Not promise between modified block-cut mining and modi-
only are these orphan strip pits reclaimed, but the fied area mining inasmuch as it employs the equipment
abandoned benches provide excellent storage areas for used in the former but applies to natural conditions
initial box-cut spoil. more common to the latter. It utilizes dozers and front-
First- and second-cut topsoil is removed by pan end loaders in overburdens of up to a maximum of
scrapers and stored on stockpiles for final cut reclama- 12 m (40 ft), Fig. 30. An initial block cut (No.1 in
tion. Topsoil from third and successive cuts is removed Fig. 31A) is established by dozing or carrying the over-
and placed directly on regraded spoil areas, thereby burden material to a temporary storage area adjacent
combining topsoil segregation and reclamation in a to the cut, Fig. 3lB, burying toxic materials. Similar
single operation. Initial box cuts are made near the cuts are made in sections 2, 3, 4, 5, 6, etc., along
point of a ridge or hill, or wherever first-cut spoil can the direction normal to mine development. After the
be stored with minimal environmental effects. Drag- coal is loaded, which is done immediately after the
lines or shovels ranging in size up to 34 m' (45 cu blocks are exposed, the overburden from successive
yds) are the primary stripping machines, but draglines cuts 7, 8, 9, 10, etc., is pushed into the mined-out
are more common since they can dig through hills area, with reclamation being accomplished concur-
and more easily spoil the material with their larger rently. Variations in cut sequence can be many; one
casting radius as well as provide better segregation alternate scheme is shown by the numbers in pa-
of spoil material. The spoil banks left will resemble rentheses in Fig. 3lA.
those encountered in the larger area strip mines to The advantages of block-area mining include: (I)
be described in Region III. it makes recovery of very thin seams economical; (2)
Advantages of modified area mining include: ( I) reduction of pollution potential by burial of toxic mate-
nearly 100% of the coal is recovered; (2) segregation rial, concurrent regrading, and reclamation are accom-
and burial of toxic overburden material is easily accom- plished; (3) minimal capital outlay for equipment is
plished with the draglines normally used; (3) there required; (4) production costs are low; (5) original con-
are the side benefits of reclaiming abandoned pits; (4) tour is easily obtained; and (6) breakdown of one ma-
reclamation is carried on concurrently with mining; chine cannot stop operations. Disadvantages include:
(5) regrading is done to nearly original contour; and (I) storage of initial block cuts until back filling of
(6) there is high production protential. Disadvantages final pits could be a problem, and (2) depending upon
include: (I) the initial cut must be stored for future the block sequence used, water handling and coal haul-
use, and (2) complete disruption of hilltop rock strata ing routes could also become problems.
can affect ground-water movement. Southeastern Ohio: While classified in Region II,
SURFACE MINING 321

A.

B.
Fig. 30. Typical drainage systems (Skelly and Loy, 1975).

this area is less hilly than most of the remainder of bags of ammonium nitrate of 36 kg (80 Ib) each and
the region but is not as ftat as Region III. Unlike fuel oil are loaded into each hole and detonated with
other areas in Region II, it utilizes very large shovels dynamite. Usually three rows of holes are shot at once,
and also is the location of the largest dragline in opera- using delays between each row to assure good fractur-
tion in the world. Contour mining is generally the ing of the overburden. The coal is not blasted.
rule here, with mining to depths of 55 m (180 ft) in The mining cycle is initiated by using the shovel
a variety of tract sizes. The following two case studies to remove overburden to a depth of 38 m (125 ft),
are examples of representative mining in this area. exposing the coal seam and establishing a pit width
In the first mine, a Bucyrus-Erie 1950-B stripping of approximately 55 m (180 ft) by following the contour
shovel (Silver Spade) with a capacity of 80 m' (105 or outcrop line. The seam being mined is the Sewickley
cu yds) and equipped with a 61-m (200-ft) boom is No.9 which is 114 cm (45 in.) thick. A Bucyrus-Erie
employed as a primary stripping machine, Fig. 32. 120 loading shovel of 7-m' (9 cu yd) capacity follows
The overburden is prepared using a Bucyrus-Erie 61R the stripping shovel and removes a 16-m (54 ft) cut
rotary roller bit drill, and 39-cm (15\.2-in.) diam holes of coal from the side of the pit nearest the spoil. Fig.
are drilled to within 1.5 m (5 ft) of the coal seam on 32 shows both plan and section views of the pit. Four
a spacing of 15 x 18 m (50 x 60 ft). From 30 to 33 lOO-lon K . W. Dart trucks operating on the exposed
322 COAL MINING TECHNOLOGY
Spoil from storag e area placed in finol cu ts olong th is face

9 -Ind icates seq uence of block cu ts


(Ill -Ind icates alt ernate sequence of block cu ts
A. Cut pattern sequences.

B. System overview.
Fig. 31. Typical blockarea mining method (Skelly and Loy, 1975).

seam are spotted for loading, and haul approximately of 1.5 to 3.0 m (5 to 10 ft) above the coal seam. Both
four miles to a preparation plant. ends of the pit are filled in to hasten and purify seepage
On the second and successive cuts, the stripping because the spoil in this area has a high limestone
shovel operates from the exposed coal seam and re- content. In essence, this method provides a sizable arti-
moves a 18m (60 ft) overburden cut, casting the spoil ficiallake in the final pit. This lake affords many possi
into the 16m (54 ft) cut where the exposed coal has bilities for mUltiple land use, but high walls may have
previously been loaded out. The cycle is then repeated to be eliminated in the Future. Planting of trees such
for each cut. Two Caterpillar 0-9 dozers are assigned as black locust, pine, poplar, and maples, or of legumes
to the pit for use in cleanup ahead of the stripping such as crown vetch follows the leveling process.
shovel and for high wall preparation prior to drilling The 168-m3 (220 cu yd) Bucyrus-Erie 4250-W drag-
and blasting. Stripping operations are conducted three line (Big Muskie) is employed in a nearby mine to
shifts a day, seven days a week, while coal loading remove up to 56 m (185 ft) of overburden consisting
normally occurs on two shifts a day, five days a week. mainly of shales, mudstones, lime rock, and sand-
The stripping ratio is approximately 20: 1 and the an- stones, Fig. 33. A BucyrusErie 61R rotary drill is
nual coal production is about 1.4 mt (1 V, million tons). also used for overburden preparation at this mine, drill-
Reclamation is started after coal removal, using ing on a 9.1 X 9.1-m (30 X 30-ft) grid. Ammonium
large bulldozers to grade the spoil to a gently rolling nitrate and fuel oil are bulk-loaded into the holes and
contour. The final-cut high wall is filled to a minimum some 1.4 to 5.0 tons (IV, to 5V, tons) are required
SURFACE MINING 323

5 ~,e Open
C.t

I
I
High I
Exposed
Wall
Sewickly No. 9
Coal
I
I

Pion View

12S'

Spoil

120' _ _ ~'-lr-S4'-1
Section View
Fig, 32. Plan and section views of a BucyrusErie 1950B pit (Stefanko, Ramani, and
Ferko, 1973).
per hole in order to maintain a one-ta-one blasting ing the I 22-cm (48-in.) thick No.9 Meigs Creek seam.
ratio, depending on the nature of the overburden and A 190-B Bucyrus-Erie II-m' (14 cu yd) loading shovel
depth of the hole. Bagged ammonium nitrate is used follows the dragline and removes the entire 53 m (175
only in wet holes. The coal is not blasted. ft) of exposed coal from the pit, loading a fieet of
The mining cycle can be referred to as contour four to six K. W. Dart 108-t (120-ton) trucks which
mining and is similar to the method previously dis- haul approximately 6.4 km (4 miles) to the railhead
cussed except that the dragline operates from the high- of a private automatic railroad. The mining cycle is
wall. The cycle begins as the dragline establishes a then repeated by the dragline exposing another 53-m
53-m (175ft) wide pit while following the contour of (I 75-ft) width of coal, casting the spoil into the previ-
the hillside. The spoil is cast along the crop line, expos- ously loaded cut.
324 COAL MINING TECHNOLOGY

Surface
Open Cut

High-
Wall
Exposed
No.9
Meig s Creck
Seam

PIon View

Surface

1
120-130'

Spoil

L 42-47" 1.....- - 175' 175 '

Section View

Fig, 33, Pit layout at Bucyrus-Erie 4250-W operation (Stefanko, Ramani, and Ferko,
1973)_
Stripping operations are conducted throughout the average swing time per second per operator to be from
year, three shifts a day, and coal loading is completed 71 to 82 sec for an overall average for all operators
in two shifts a day, five days a week_ Annual coal of 77 sec per swing_ The dragline operates at 13 800
production is approximately 1.4 mt (I" million tons) Y stepped down from 69 000 Y, while the loading
from the dragline pit with a stripping ratio of nearly shovel and drill require 4160 Y_
20: 1. The performance of this equipment, when first
erected, was studied closely, and considerable delay Region III
time occurred because of problems in the new design. Regional Characteristics: This midwest region can
While these have been largely worked out, this equip- be further subdivided into two distinct subregions be-
ment still does not attain the efficiency of older smaller cause of basic differences in climate and coal character-
units, Studying four different operators showed the istics. The eastern portion of the region which includes
SURFACE MINING 325

Fig. 34. Typical dragline in operation.

Ohio. western Kentucky. Indiana. and Illinois, has allel opening is made, placing overburden into the pre-
most of the region's (and the country's) known bitumi ceding mined-out area. Mining proceeds parallel cut
nous reserves, while the western portion, comprised by parallel cut, similar to Figs. 2 and 7, until all reserves
of Iowa, Missouri, Kansas, Arkansas, and Oklahoma, in the area are mined. In the past, miles of hedge-
has both bituminous and lignite reserves. While the row-type spoil banks would be visible after mining.
topography of the entire region consists of gently roll- Today, however, state laws require a minimum amount
ing hills and very flat plains, and is largely farmland, of unreclaimed spoil banks, so reclamation proceeds
it varies from very fertile in the north and east to concurrently with mining.
relatively poor toward the southwest. Generally, thin- So far, we have considered only single coal s~ams,
ner, poorer quality, and shallower seams amenable to although there are many properties where more than
smaller surface operations occur in the western portion one seam will be worked at one time. For such multi-
of the region while higher quality, thicker coal seams, seam operations, the versatility of the dragline for over-
amenable to both surface and deep mining occur in burden removal is especially important, Fig. 34. The
the eastern portion of the region. Table 7 in chapter following example shows this versatility.
two shows that half of the eight largest mines in the At this mine, Fig. 35, the overburden consists of
US are surface operations in the eastern part of this clays, sandstones, and shales and requires drilling and
region (Illinois and western Kentucky). Some of the blasting before stripping can be initiated. The topogra-
largest shovels and almost all of the bucket-wheel exca- phy of the area can best be described as flat with a
vators operate in Illinois. few gently rolling areas. A Bucyrus-Erie 61R rotary
Area Mining: The contiguous seams underlying the drill is used to prepare the overburden and holes are
levelland in this area lend themselves to the widespread spaced on a grid of 9.1 X 10 m (30 X 34 ft). A 6.1
lise of the area mining method. A wide spectrum of to 9.I -m (20 to 30-ft) thick shale parting located be-
equipment is employed, in various combinations, al- tween the Illinois No. 7 and No. 6 seams is drilled
though the basic stripping operations are performed with a Marion Mark II drill on a spacing of 9.1 X
by large draglines or strip shovels. Generally, in areas 8.2 m (30 X 27 ft). Ammonium nitrate and fuel oil
where coals lie within 12 to IS m (40 to 50 ft) of are used to blast both the overburden and parting.
the surface, stripping shovels are used because of their No blasting of the coal is required.
faster mining cycle, while thicker overburden [46 m A Marion 8900 dragline with a Ill-m' (l45-cu-
(ISO ft) in some cases] necessitates the use of draglines, yd) bucket and a 61-m (250-ft) boom removes 18 to
or bucket-wheel excavators are used in tandem with 21 m (60 to 70 ft) of overburden and the shale parting
either shovels or draglines. With the high overburden- between the seams. The dragline works from a 7.6-
to-coal ratios and fiat terrain, capacities of stripping m (25-ft) bench, 48 m (158 ft) in width at the top of
equipment begin at 27 m' (35 cu yd) and range up- the high wall. The bench is cut by the dragline before
wards. it moves ahead and approximately 2.4 m (8 ft) of shale
Since outcrops are not common, mining usually is placed on the bench to form a solid surface for
begins with an initial rectangular opening or box cut, the machine to operate from and move on. Although
overburden being cast to one side of the cut. After this bench-cutting operation (chopping down) is not
removing exposed coal from this cut, an adjoining par- the most efficient use of a dragline, in this situation
326 COAL MINING TECHNOLOGY

Surface Open cut Drag-


line
Surface Parting
Highwall Dragline

Exposed
Illinois
No. 7
~~~~~~~~~~Road
Highwall

Exposed
Leveled
Spoil
on

Seam Illinois
No.6 Seam
Plan View
Plan View

Surface

Spoil
.L~~\-----t1::::::::::::.-r"'"
20-30ft
lr--~7~2~in-.~N~o.~6-S~e-o-m~--~-----------
Section View Section View
A. B.
Fig. 35. Development of a dragline in a multi-seam operation (Stefanko, Ramani, and Ferko, 1973). (A) Views of
the initial pit with the No.2 seam exposed. (8) Dragline positioned on leveled spoil removing parting.

it appears more feasible than procuring another strip- Region III, and specifically the state of Illinois,
ping machine and using a tandem mining cycle. The is the home of the bucket-wheel excavator. Fig. 9
dragline then exposes a 46-m (150-ft) width of coal showed the plan of operation of a shovel in tandem
in the 122-cm (48-in) thick No.7 seam, casting the with a bucket-wheel excavator. Fig. 36 is a picture
overburden along the crop line for approximately 305 of what such a pit might look like. However, there
m (1000 ft) of pit length. Fig. 35A shows the pit initially are other combinations of equipment that call be used
with the No.7 seam exposed for loading. A Marion in tandem with the excavator. Fig. 37 shows the plan
151 loading shovel of 7.6-m' (IO-cu-yd) capacity fol- of operation of a dragline in conjunction with the exca-
lows the dragline and loads the entire pit width. Three vator, while Fig. 38 is a picture of such an operation.
109-t (120-ton) K . W. Dart trucks haul approximately The strata above the coal seam at this operation
3.5 km (2.2 miles) to a railheading where the coal is consists of clays, gravel, and medium-hard shales. The
transferred to a private railroad and hauled 22 km topography at this Illinois mine is generally fiat, and
(14 miles) to the preparation plant. a Krupp No. 1185 bucket-wheel excavator teams with
After completing about 305 m (1000 ft) of cut, a Marion 7800 23-m' (30-cu-yd) dragline to remove
the dragline moves to the spoil area, which has previ- some 26 m (85 ft) of overburden. Drilling and blasting
ously been leveled by bulldozers, and digs the remain- are required in that section of the highwall which is
ing parting to expose the 183-cm (72-in.) thick No. removed by the dragline. A Robbins R. R. 10 vertical
6 seam. Fig. 358 shows the dragline operating from drill bores 27-cm (lOo/8-in.) diameter holes II to 12
the leveled spoil. Again the loading shovel trails the m (38 to 40 ft) deep on approximately a 9.I-m (30-
dragline and loads the lower coal seam from the entire ft) square grid. Two 23 kg (50 Ib) bags of ammonium
pit width. The dragline then moves to the high wall, nitrate and fuel oil are usually loaded in each hole
and the cycle is repeated over the entire 2.0 km (I \4 and detonated by a 0.4-kg (I-lb.) cast primer and pri-
miles) of pit length, casting the spoil into the previous macord.
cut. In this method, spoil leveling is done immediately The mining cycle is initiated by the bucket-wheel
after the dragline moves on, and reclamation can be excavator as it cuts a bench 9. 1 to 20 m (30 to 65
almost concurrent. ft) deep and 27 m (90 ft) wide in the high wall, which
327

Fig. 36. Pit laout of a typical bucket-


wheel excavator and stripping shovel tan
dem operation (Stefanko, Ramani, and
Ferko, 1973).

Dragline Spoi l Open Cut


Working
Be nch

Bucket Wheel
Excavator
Cut

Plan View

:~==::==~====~====~~~:S'1~~~~~~~~
--7 Surface
,

9oft-l1
'30-65 ft
BWE
Spoil

10-55fl
Dragline
Spoil
--~--~----~--~--------~
t--90 11---1--90 fl -1 36 in.
Seclion View
Fig. 37. Pit configuration for a bucket-wheel excavator and dragline tandem operation
(Stefanko, Ramani, and Ferko, 1973).
328 COAL MINING TECHNOLOGY

Fig. 38. Bucket-wheel excavator and dragline in a tandem operation.

is generally unconsolidated to that depth. The Marion due to maintenance requirements, the bucket-wheel
7800 dragline follows the wheel excavator on the was able to nearly double the production of the drag-
bench, removing the remaining 3.0 to 17 m (10 to line.
55 ft) of medium-hard shales, exposing the 91-cm (36-
in) thick Illinois No. 2 seam for the entire 2.4 km
(1\6 miles) of pit. Fig. 37 shows the pit at this stage. Table 2 , Data Comparing a Wheel Excavator With
A Marion 4121 4.6-m 3 (6-cu-yd) loading shovel follows a Dragline over a Six-Month Period
on the exposed seam, loading coal from the entire 27 Marion 7800 Krupp wheel
m (90 ft) of pit width. Four 91-t (lOO-ton) K. W. Equipment dragline excavator
Dart trucks haul 5.6 to 10 km (3\6 to 6 miles) to
the tipple. At the end of the cut, the dragline fills in Bucket capacity, cu yd 30 28
the end of the pit which has already been loaded out Downtime, hr
and moves to this fill area, allowing the wheel excavator Power 27.45 6.55
to pass in order to start the following cut. Cable 24.25 4.35
On the second and successive cuts, the bucket- Other electrical 34.55 30.58
Wire rope 30.20
wheel excavator again digs a working bench, dumping Bucket 27.50 226.33
the spoil on top of the overburden cast by the dragline Mechanical 266.05 577.23
on the previous cut. Reclamation is somewhat easier Oil and grease 77.10
with this system as the upper soils are placed on top General repairs 445.00 1120.51
of the dragline spoil by the excavator and plant growth Belt 161.20
is relatively easy to establish. The cycle is then repeated Hopper 33.15
throughout the length of the property. At this opera- Clean machine 1.55
tion, water which lies above the coal seam creates a Miscellaneous 52.50 4.09
problem with the sandy upper high wall and continuous Lunch 71.45 1.30
pumping is required. Therefore the matching of the Blasting 1.05
Road building 6.00
bucket wheel and dragline moves becomes critical. The Clean pit 31.40
distance between the bucket wheel and dragline must Rehandle 7.25
be closely maintained. Stripping is a 24-hr-a-day, year- Deadheading 29.40 36.04
round operation, while loading is generally completed Wait on dozers 22.40 0.16
in one shift per day. Yearly production is generally Wait on loader 3.30 0.42
around 817,020 t (900,000 tons). Other 3.60
Data comparing the bucket-wheel excavator with Total time lost, hr 1162.00 2241.91
the dragline on this operation over a six-month period Total time worked, hr 2771.40 1734.19
is interesting, Table 2. As can be seen from this table,
and what is rather typical of the bucket-wheel excava-
Percent time worked %
Percent time lost, %
70.46
29.54
56.38
43.62 1
Yardage 2,822,295 5,282,273
tor, is the large amount of downtime of the bucket-
wheel excavator compared to the dragline, 43.62 vs. Metric equivalents: yd x 0.9144 = m; cu yd x 0.764 554
29.64%. However, even with the excessive downtime 9 = m3.
SURFACE MINING 329

Fig. 39. A l07m 3 (l40-cu-yd) 3850-B shovel operating at the River King mine in southern Illinois.

Other tandem operations with bucket-wheel exca- to 8-cu-yd) capacities remove this coal by loading it
vators have been suggested, even the use of two or into nine 45-t (50-ton) trucks, and scrapers remove
more bucket wheels, each operating a parallel slice the parting uncovering the lower seam. A loading ma-
downward. chine is then assigned to operate on the lower seam,
The largest shovels made [up to 138 m' (180 cu working closely with scrapers and dozers to remove
yds)] operate in this region. Fig. 39 shows one such the parting. The operation at this stage resembles an
machine, a 107-cm' (l40-cu-yd) 3850-B shovel, in op- open pit operation with the upper seam worked as
eration at the River King mine of Peabody Coal Co. one bench and the lower seam as a second bench for
in southern Illinois. An interesting variation is the use the length of the cut. Once the cut is completed, an-
of a shovel equipped with a variable pitch dipper for other parallel cut will be taken as in a traditional strip-
a multi-seam operation, Fig. 40. ping operation.
Other Mining Methods: While rather straightfor- The gigantic earth-moving operation is dependent
ward area mining methods dominate Region III, modi- upon critical equipment timing. Scraper haul lengths
fications, possible substitutes, and unique operations are approximately 1067 m (3500 ft) with seam uncov-
exist. Some of these will be covered here. ered to depths of 66 m (215 ft). Reclamation is very
A unique mining operation employing five pan easy on this operation since scrapers can level the spoil
scrapers and five bulldozers as the major stripping and place surface materials back into their original
equipment for a multi-seam subbituminous operation position. The low initial equipment cost, flexibility of
is shown in Fig. 41. Pan scrapers remove the overbur- operation, low production cost, and minimal adverse
den above the upper seam exposing a coal width of environmental effects of this system make it attractive
91 to 122 m (300 to 400 ft) for a length of nearly where it can be used.
305 m (1000 ft). Diesel shovels of 3.1 to 6.1-m' (4 Since much of Region III is valuable farmland,
330 COAL MINING TECHNOLOGY
Bo tt om Seam of
Top Seom of
Coo I Removed l\. ,(
Coa l Removed

- Previous ::;;::::
:. C Spoil 7 ,
--

-~-=.---~.

800m - Digging

Plan View 2:>


~~~iflM~L~~= Shovel jJ
Coo l Sea m:
Fig. 40. Multi-seam stripping op-
eration with a shovel (Skelly and
Loy. 1975). Seclion View

the environmental impact of area mining, including (200 to 300 ft) of active spoil. Topsoil replacement
disturbance of ground-water flow, pollution, disruption and revegetation immediately follow the pull-back drag
of surface characteristics, and erosion and sedimenta- route. This pull-back reclamation methodology, com-
tion must be minimized by proper reclamation proce- bined with retreat mining techniques. would retain the
dures. For this reason, mining engineers are constantly high production advantages of large stripping equip-
looking for better ways to produce lower-cost coal in ment while at the same time minimizing environmental
a more environmentally acceptable manner. Unfortu- disturbances.
nately, while block-area stripping provides immediate
reclamation of disturbed areas quite effectively, it is Region IV
not applicable to large stripping machines with the Natural Conditions: Region IV extends from the
extremely high production levels possible with them. border of Canada on the north to the border with
Thus there is a greater attempt to use better reclama- Mexico on the south, and contains the nation's largest
tion procedures with the mOTe popular area mining coal reserves, Fig. l. Its topography varies from the
methods, and there is an interest in concurrent recla- typical Great Plains area to the Rocky Mountain ter-
mation methods in mines employing the large stripping rain. Much of it is semiarid with sagebrush and skimpy
machines. Fig. 42 shows the use of a pull-back dragline, grass the only cover, although areas on the western
maintaining reclamation grading within 61 to 91 m slope of the Rocky Mountains receive considerable pre-
SURFACE MINING 331

Open Cut

Highwall
Surface
Exposed Armstrong
Cool Seam

Plan View

Armstrong Seam

35-40 ft

50ft i--300-400ft 300-400ft--j


Monarch Fig. 41. Plan and section views of a unique
Complex (Skelly and Loy, 1975) multiple seam
Section View scraper operation.

cipitation, primarily in the form of snow in the winter. lie beneath less than 30 m (100 ft) of cover which is
Erosion by wind and water has occurred over the re- either glacial drift (northern part) or a fine-grained
gion for centuries, and flash floods continue to create clastic sediment (southwestern portion). Central Mon-
severe erosion problems. tana's coalfields consist of subbituminous, bituminous,
The reserves in this area range from the lignite and lignite coalbeds.
beds in North Dakota and Montana to the highly vola- Even though portions of Wyoming remain largely
tile bituminous coal in several other fields. While min- unexplored, the coal reserves are known to be enor-
ing in this region has not been extensive until recently, mous. Lignites, subbituminous, and bituminous coals
it is greatly accelerating and will undoubtedly provide are present; many of these are very thick and lie at
the nation's major production very shortly. Because shallow depths. In the northern part of the state, pres-
of the diversity of the region, descriptions are more ently the scene of the nation's greatest coal develop-
meaningful on a state or area basis. ment, surface mines tend to be very large.
The Black Mesa field in the four-corners area of Area Mining: Area mining of the lignite and subbi-
Arizona and New Mexico contains six bituminous coal tuminous coals in western North Dakota, eastern Mon-
seams ranging in thickness from 1.5 to 8.5 m (5 to tana. and northeastern Wyoming is similar to that in
28 ft); they are within 518 m (1700 ft) of the surface Region III. One basic difference is a much lower strip-
with a Btu content of 12,300 (13 kJ) or greater, ash ping ratio than encountered in the other regions, 1.0
of 9% or less, and a sulfur content ranging from 0.4% in portions of North Dakota and 4.0 in Montana and
to 0.9%. Mining has been extensively pursued in this Wyoming which reflects the combined benefits of shal-
field for the last ten years. low overburden and thick coal seams.
Colorado's eight major coal basins were formed Since much of the land underlain by coal in Region
under diverse geologic conditions that caused the beds IV is either farmland, pastureland, or semiarid waste-
to vary from flat-lying and slightly faulted to steeply land, little clearing and grubbing and virtually no tim-
pitching and extensively faulted . Here average bitumi- bering are required, but where necessary these are ac-
nous coal Btu value ranges from 13,300 to 14,500 (14 complished by dozers. Topsoil is minimal and even
to 15.3 kJ) and the sulfur content is less than 1%. where available does not provide good cover growth
Eastern Montana and western North Dakota share because of semiarid conditions. Overburden prepara-
the nation's largest lignite and subbituminous reserves tion is frequently not necessary because of the uncon-
in the Fort Union region. Virtually all of these reserves solidated overlying strata, but where needed it is ac-
332 COAL MINING TECHNOLOGY

" l :U

. '1~
-
Reclaimed Area .'

Fig. 42. Concurrent reciamation with a pull-back dragline (Skelly and Loy. 1975).

complished by vertical rotary or percussion drilling. greater, a greater variety of coal loading equipment
Area mining in Region IV, as in Region Ill, usually abounds: shovels, bucket-wheel excavators, front-end
begins with an initial box cut and proceeds parallel loaders, and self-loading scrapers. A discussion of rep-
cut by parallel cut as explained f',arlier until the reserves resentative mining methods for thick, dipping, and
are depleted. Although overburden removal is similar mUltiple seam operations will illustrate the use of the
in both regions, the equipment used in Region IV is equipment more clearly.
usually smaller than in Region III and scrapers are Multiple and Dipping Seams: Multiple and dipping
used more extensively. It is in the coal loading opera- seams require modifications of techniques previously
tion that differences from other regions occur. Since described or the application of entirely new techniques,
many of the coal seams are thick, the coal is usually an example of each of which will be shown. Fig. 43
shot and loaded in benches in an open-pit type of opera- shows a modification of the area mining techniques
tion. Since the volumes of coal loaded are so much for mining multiple seams that dip from the horizontal.

Fig. 43. Modified area mining of multiple dipping seams (Skelly and Loy, 1975).
SURFACE MINING 333

A. Mining method.

1==F;;~b;;,~~'~~_~lim~it~s of mining- - - - ., I

.!-O,ig ir,o l ground l in e 1

~-...J I
Overburde n
I

rec la mat ion grade li ne

B. Final pit configuration.


Fig. 44. Open pit operation of multiple dipping seams (Skelly and Loy, 1975).

Draglines with rather small buckets are used .as the ing coals permits additional recovery of lower seams.
primary stripping equipment with support from dozers This stripping cycle continues through all of the seams
and scrapers. As shown in Fig. 43, stripping follows at the site until the overall stripping ratio becomes
the coal down dip to increasingly greater depths until too great to permit continued economical operation.
an economic strip limit is achieved. Removed overbur- When mining has ceased, the pit will resemble the
den is cast on both sides of the cut, covering the previ- cross section shown in Fig. 44B: a series of benches
ously exposed high wall above the lower seam as well on the high side, a single nearly Hat incline representing
as beyond the economic strip limit of the coal seam the base of the lowest seam, and a very large spoil
being worked. This operation is repeated for each seam outside the pit. The volume of spoil will be so great
in ascending order. Since no overburden material is that it may not be economical to return it to the pit,
hauled, this is a strip rather than an open pit operation. and even if it were, it would be insufficient for regrading
Fig. 44 shows mining under similar natural condi- to original contour. Thus reclamation will consist pri-
tions but with utilization of an open-pit method of marily of high wall reduction and rounding of the spoil
operation. An open-pit operation is distinguished from pile. The advantage of this technique is that high pro-
a stripping operation by the fact that overburden is duction is achieved from a series of otherwise unmina-
hauled rather than merely cast. On this operation in ble coal seams. The primary disadvantage is that the
Wyoming, 13 coal seams ranging from 1.2 to 28 m pit will not be returned to original contour.
(4 to 93 ft) in thickness are mined. Since the coals For the extremely thick seams encountered in Re-
outcrop along the top of the ridge, the lower seam is gion IV, the open-pit method is especially appropriate,
mined first with progressive benching of overlying Fig. 45. Shovel-truck combinations or scrapers provide
seams as they are encountered. The removal of overly- good Hexibility and dependability for overburden re-
334 COAL MINING TECHNOLOGY

_..,..;_ -- .1

I' I

J
.A

Fig. 45. Typical open pit mining method, thick seam (Stefanko, Ramani, and Ferko, 1973).

maval. Overburden is returned to the mined-out pit more complex operations will have to be more exten-
after initial mining and later graded to a contour com- sive than it has been in the past. For this reason, com-
patible with the surrounding terrain. The coal thick- puters will be used increasingly to determine the opti-
ness usually necessitates a benching operation for re- mum moves of equipment based upon appropriate spoil
moval with loading shovels. volume calculations. For example in Fig. 46, sequenc-
There are many possible combinations of equip- ing of dragline moves for the mining of three seams
ment and techniques that are limited only by the min- is shown.
ing engineers' imagination and creativity. Up to now, The new Jacobs Ranch mine of Kerr-McGee Coal
existing equipment has had to be used for mining dip- Corp. near Gillette, Wy., is an interesting one. Three
ping and multiple seams, but in the future it is expected seams, the 1.5 to 3.8-m (5 to 12\2 ft) thick upper
that new equipment especially designed for such condi- Wyodak (UW), the 9.1 X 18.2-m (30 to 60 ft) thick
tions will be employed. In any event, planning of these lower Wyodak (LW , ), and the 1.2 to 2.6-m (4 to 8.5-

Fig. 46. Dragline sequencing in the mining of three seams (Chironis, 1978).
SURFACE MINING 335
CO HAUL ROAD EXPOSE D COAL

A. FIRST ST EP

CHAN\3ES DIREcTIONS
prrw;~"""=~==mi

B. SECOND STEP

HAUL ROADS
STRIPPED
FROM
ADJACENT
BLOCK

C. THIRD STEP
Fig. 47. Multi-seam open pit operation (Chircnis, 1978).

ft) thick lowest Wyodak (LW2 ) are mined. The UW the first year's peak of operation which began February
has an average overburden thickness of 37 m (120 1978 with a projection of 13. 15 mt/a (14.5 million
ft) and is separated from the LW , by 0.5 to 14 m tpy) by the mid-1980s.
(1.5 to 45 ft) of shale and sandstone while LW 2 is While the stripping plans are subject to change
separated from LW 1 by 0.3 to 2.0 m (1 to 6\6 ft) of as experience is gained in thick-seam mining, mining
shale. Three million tons (2.7 mt) are projected for is projected as shown in Fig. 47. Stripping begins with
336 COAL MINING TECHNOLOGY

2000 2000

1500 o 500 1000 1500


Sca Ie in feet

1000

500 , 500
'\,
\
Sea level \
\
\
-500 LEGEND \
- --- Fault \
\
-1000-- Coal seam

A. Typical cross section.

B. Principal underground mining method.


Fig. 48. Anthracite mining conditions (Chircnis, 1978).

the removal and storage of topsoil. Overburden re- cent or parallel to the previously mined pit ov~rburden
moval and deposition of the spoil in a valley adjacent and coal haulage routes also change; this is accom-
to the initial cut follows . Once a pit advances far plished by making a 90 turn and then advancing far
enough for equipment access and movement, overbur- enough (8) to achieve the width of the next pit; then
den will go directly from the pit to the backfill area another 90 turn is made (C). Once these steps have
where coal has been mined. In the standard pit ad- been accomplished, the standard mining cycle contin-
vance, shovels remove overburden in mUltiple 12-m ues.
(40-ft) benches, the number depending on overburden
thickness. Waste goes along the pit to the correspond- ANTHRACITE MINING
ing pit back-fill benches, and coal goes out on the oppo- The author's friends from eastern Pennsylvania
site side of the pit, Fig. 47 A. As a pit approaches would be sorely disappointed if no mention were made
the property line, mining direction reverses 180 0 adja- of anthracite mining. Several studies have been COD-
SURFACE MINING 337

A. Open pit arrangement.

B. Method of mining.
Fig. 49. Anthracite open pit operation of multiple seams (Chironis, 1978).

dueted recently concerning the possibilities of mining pendent operations; total underground mining produc-
anthracite by open-pit operations. The vast reserves tion is less than 907 kt (1 million tpy), annual tons.
found in the southern anthracite fields of eastern Penn- Thus surface mining is projected as a substitute for
sylvania have been badly folded and warped, and a this underground technique. Presently, the nearly S.4
typical cross section is shown in Fig. 48A. In the past, mt (6 million tons) of annual production is achieved
underground mining up the pitch employing the breast roughly in equal amounts by strip mining and recovery
and pillar technique has been prominent, Fig. 48B. of waste piles from past mining.
However, the danger from such mining, inability to A suggested open-pit mining method for mining
mechanize the operation. and the tremendous physical a dozen or more seams down to a depth of 244 m
exertion demanded of miners have made the technique (800 ft) is shown in Fig. 49A. Mining proceeds in a
largely obsolete today except for some very small inde- series of uniform production faces 12 to 15 m (40 to

l
338 COAL MINING TECHNOLOGY

Portable
S.... it chgear --"-..,.j~;o~~~ , ~

Fig. 50. Large area mine electrical system (Skelly and Loy, 1975).

50 ft) high by 30 to :'8 m (100 to 125 ft) wide in a als on either pole lines or ground cables from the main
direction perpendicular to the strike of the coalbeds overhead at line intervals of 366 to 457 m (1200 to
(from the left in Fig. 49A). Conventional loading shov- 1500 ft) to switch-houses near the highwall, Fig. 50.
els with a capacity of II to 19 m' (IS to 25 cu yds) The power is then further reduced and distributed to
are used to load 45 to 91-t (50 to 100-ton) rear-dump low-voltage equipment, such as highwall drills and coal
trucks. Back filling can occur simultaneously with min- loading shovels. Pumps and coal drills are fed from
ing, Fig. 49B. the secondary circuit which is a stepdown further. The
switchhouses and laterals are moved back as the pit
advances and a new main pole line is constructed an-
ELECTRICAL POWER other mile back as the pit approaches.
The optimum power distribution system should be Since stripping equipment capacity is generally over
designed to supply adequate electricity to all equipment 19 m' (25 cu yds), it requires distribution of voltages
without exceptional voltage drop at the ends of the of either 7200 or 13000 V. All heavy equipment con-
pit, provide maximum protection of personnel and verts the distribution system's alternating current to
equipment, and be portable for relocation. After the direct current via large motor generator sets located
voltage has been reduced at the main substation, the in the equipment housing. This permits the use of a
primary voltage on pole lines should be carried 1.6 large synchronous motor and conversion sets with the
km (1 mile) in advance of, and parallel to, the pit ease of control of motors that can only be achieved
on the high wall side. The usual practice is to run later- with d-c motors.

.~

Вам также может понравиться