Вы находитесь на странице: 1из 8

S U B S T A T I O N S

20 kV, so that four different HV/MV net-

Comparison of works are evaluated. The comparison is


based on the life-cycle costs of the differ-

GIS and AIS ent supply concepts.

systems for urban Design of the AIS/GIS network


variants

supply networks High-voltage network


The best locations for the HV injections
into the distribution network depend to a
Studies carried out by ABB show that for urban supply networks the com- large extent on the technology (AIS or GIS)
bination of HV gas-insulated switchgear (GIS) and HV cable has important chosen for the HV system. Sites which are
advantages over systems with air-insulated switchgear (AIS) and overhead large enough for AIS substations are sel-
lines. Due to their compactness and flexibility, GIS substations can be lo- dom available, and when they are their
cated close to load centers, allowing a much more efficient configuration cost is extremely high. But it is not just the
for both the HV system and the MV distribution network. The saving in in- smaller size of the site that makes GIS the
vestment and operating costs more than compensates for the higher cost lower-cost option: GIS is also the more
of the GIS and cables. Benefits include higher reliability and the option of economic alternative when expanding or
integrating a complete GIS substation in an existing building, eg when replacing existing substations. An inner-
extra site area is not available. city site that has been used previously for
an AIS installation can be sold or rented

B esides the vital role they play in mod-


ern market economies, electricity supply
parison does not take into account the
fact that by locating a GIS transformer
out and the income used to help finance
the new substation. The compactness of
GIS enables an HV transformer substation
systems also have a large impact on the substation close to the load centers a far to be fully integrated in an existing build-
environment, making them subject to more efficient network structure is ob- ing, which may only have to be made
changes in social paradigms. It is in part tained at both the HV and the MV distribu- higher or have a basement added.
due to this that the medium-voltage sys- tion level. As a result, the investment and The issue of space extends beyond the
tems supplying power to urban areas are operating costs are reduced. transformer substations to the high-volt-
designed today almost entirely as cable To quantify the respective impact of AIS age connections. Overhead lines are
networks with indoor switching stations. and GIS technology at the HV and the MV today practically no-go as an option for
Besides its reduced visual intrusion on levels of an urban supply system, a look is inner-city areas. And even where rights-of-
everyday life, gas-insulated switchgear taken in the following at an existing net- way are available, these can often be util-
(GIS) also offers operators of high-voltage work with a maximum load of 120 MW. ized more economically in other ways.
supply systems reliable and flexible so- The MV network is optimized for each of Typical complaints about overhead lines
lutions in areas where load densities are the HV variants (GIS and AIS), in each case are that they are unsightly and generate
high and substation sites have to be kept for distribution voltages of 10 kV and electromagnetic fields, the effects of which
small. Urban supply systems combining are subject to constant and intensive pub-
GIS technology and HV cable are safe, re- lic debate.
liable and environmentally benign 1 . Modern-day HV cable not only offers a
A direct comparison of the component high level of reliability but also some tech-
Werner Zimmermann
investment for identical switchgear con- nical benefits for overhead line connec-
Andr Osterholt
figurations suggests that the GIS variant is Dr. Jrgen Backes tions. Given these advantages, there is
more costly than the air-insulated switch- ABB Calor Emag Schaltanlagen AG today no realistic alternative to HV cables
gear (AIS) solution. However, such a com- for electric supplies in urban areas.

ABB Review 2/1999 19


S U B S T A T I O N S

Use of ABB gas-insulated switchgear allowed the 132-kV transformer substation Barbaa in the center 1
of Orense, Spain, to be constructed underground and a park built over it which harmonizes with the surroundings.
The sound of the waterfall, which acts as a heat-exchanger, hides the noise made by the fans.

GIS
The GIS variant 2 considered in the study
4.5 km
consists of three HV transformer sub-

2.7 km stations located in the center of a city. The


connection to the surrounding 110-kV net-
work is provided by three cables run from
TS1
the nearest HV substation to the main
substation of the urban HV network. This

63 MVA main substation is configured as a double


busbar system, allowing maintenance to
be carried out on one busbar without hav-

3.7 km ing to de-energize the complete station.


The remaining substations in the HV cable
TS3 TS2
ring, which are also located in the city
center, are H-type transformer substations
with a bus-tie. They also allow mainte-
nance and repairs within the gas compart-

33.1 MVA
27.8 MVA
GIS variant of the 110-kV 2
4.1 km network

TS1, 2, 3 Transformer substations


1, 2, 3

20 ABB Review 2/1999


S U B S T A T I O N S

ment on one half of the busbar while the


3 km
other half remains in operation.
4.2 km
AIS
In the AIS variant 3 there is an overhead
line loop around the supply region, the TS1
right half of which consists of double lines
(due to the load flows). As in the GIS vari-
30.3 MVA
ant, the main HV substation consists of a
double busbar system, the remaining HV
transformer substations having H-type
5.6 km
configurations. Transformer substation
1.6 km
TS2 has a double-T connection to the TS2
SS1
double overhead line, substation TS3 1 km
SS2 2 km
being looped into the single line on the
TS3
left-hand side. Due to the larger space
required, the transformer substations are
1 km
located in the less densely populated
outer regions of the city.
Double lines connect the outer ring to 33.2 MVA
28.1 MVA TS4
the transformer substations, ie there are
two circuits on the same poles. This solu-
tion allows efficient utilization of the avail-
able space. However, it also reduces the
reliability of the HV supply as both circuits
can trip for the same reason (common 35 MVA
8.6 km
11.6 km
mode failure, eg due to back-flashover
from the earth wire to both circuits caused
by lightning striking the earth wire or con-
AIS variant of the 110-kV network 3
tact with trees).
TS1, 2, 3, 4 Transformer substations 1, 2, 3
SS1 ,2 Satellite stations 1, 2
Medium-voltage network
A comparison of the GIS and the AIS vari-
ants based only on the differences in the siderably influence operation of the net- Use of standard components:
HV network is too limited, since the lo- work. Each utility therefore has its own XLPE MV cables with an Al cross-
cations of the HV transformer substations planning rules, according to which the net- section of 150 mm2 (distribution
are of decisive importance and exert a work configuration is adapted to custom- cables) and 240 mm2 (transmission
large influence on the structure of the MV ers requirements and to the geographic cables)
network. The study therefore takes the locations of the MV loads. 110-kV/MV transformers with a
load situation in an actual urban network, rated power of 31.5/40 MVA
including the load values and the geo- Planning rules Open-loop topology for the distribution
graphical location of the MV transformer The technical constraints for each network network. The distribution cables start
substations, as its starting point 4 . variant are the allowed voltage band and from the MV busbar of the HV/MV
Radial operation of an MV network the limits for the short-circuit power, which transformer substations, run between
results in a large number of possible net- are dictated by the rating of the switch- customers substations and are looped
work concepts. Besides differing in terms gear. There are also some design rules to back to the MV busbar of the same HV
of their initial capital costs, they also con- be formulated: transformer substation. During normal

ABB Review 2/1999 21


S U B S T A T I O N S

operation one of the cables in this ring substation) does not load any cable be- required power transmission capability of
remains open to provide simple pro- yond 120 % of its capacity. The maxi- the MV network, allowing an additional
tection. Each HV/MV transformer mum load of 5.2 MVA per cable at 10 saving due to the smaller MV cable cross-
substation has its own back-up trans- kV (10.2 MVA at 20 kV) at the beginning sections required. And thirdly, trans-
former, allowing maintenance to be of the planning period takes into ac- mission losses are avoided. The reduction
carried out on a transformer without count the reduced ampacity for cables in operating costs due to this third advan-
having to operate switches in the MV bundled in the same cable trench close tage is especially evident at low distribu-
network. to the transformer as well as a margin tion voltages.
Maximum of 14 customer substations for load growth during the planning These general effects are also reflected
in a loop. This limits the number of cus- period. in the results obtained with the described
tomers whose power supply would be network solutions. The MV network receiv-
interrupted in the event of an MV net- Planning results ing power from the GIS substations con-
work failure, as only the feeder con- The inherent flexibility of GIS allows sists of radially operated (open) loops, all
nected to the HV/MV station busbar is planners to place the injection points of which are fed from the MV busbars of
equipped with overcurrent protection close to the load centers 5 . The first the HV substations.
and a circuit-breaker. effect of this is on the number of loads The peripheral locations of the trans-
Normal loading of the feeder cables, so considered an optimum for each HV sub- former substations in the AIS variant make
that a worst-case cable failure (feeder station, and thus on its installed trans- additional satellite stations necessary 6 .
failure close to the HV/MV transformer former capacity. Secondly, it reduces the These have remote MV busbars, fed by
the HV transformer substations via several
parallel and selectively protected trans-

Distribution and load rating of MV transformer substations taken 4 mission cables. Their reliability is com-
as a starting point for the GIS/AIS system comparison parable with the reliability of the MV bus-
bar of the HV transformer substations, but
they call for extra capital investment and
6.2 MW 1.9 MW 0.4 MW 0.2 MW
cause additional losses. The AIS variant
with a voltage of 10 kV requires 6 parallel

1.4 MW 2.7 MW 10 MW 11.3 MW 7.4 MW 3.1 MW 0.9 MW cables from the HV injection to the satel-
lite station, the 20-kV variant requiring 4
cables. These satellite busbars, like the

5.5 MW 4.9 MW 11.3 MW 19.7 MW 7.1 MW 6.7 MW 4.5 MW MV busbars of the HV substations, supply
power to the MV substations via open
loops.
1.3 MW 3.6 MW 4.2 MW 7.4 MW 3.9 MW 8.4 MW 1.5 MW

GIS/AIS cost comparison


1.7 MW 7.7 MW 6.1 MW 2.3 MW 1.1 MW 7 and 8 compare the respective cost of
the AIS and the GIS variant (the figures for
the different components and external ser-
1.5 MW 2.9 MW 1.8 MW 3.5 MW 0.3 MW vices apply to the German market). An in-
terest rate of 8 % and an inflation of 3 %
were assumed for the calculation of the
0.5 MW 0.9 MW 0.8 MW 0.5 MW cash values. A load growth of 1.5 % per
year (linear) was set and the cash value
calculated for a planning horizon of 10

0 1.0 km years. It should be noted that planning


times of 20 years and more, which have

22 ABB Review 2/1999


S U B S T A T I O N S

TS1 TS2

TS1
TS2

TS4

TS3
TS3

Topology of the GIS variant with injection points 5 Topology of the AIS variant with peripheral 6
close to the load centers (distribution voltage 20 kV) transformer substations and additional satellite
stations (distribution voltage 20 kV)
TS1, 2, 3 Transformer substations 1, 2, 3
TS1, 2, 3, 4 Transformer substations 1, 2, 3, 4

often been used in the past to evaluate dif- transformers results from the different operation, so that only a single additional
ferent variants, are not realistic in todays number of transformers in the two vari- unit is necessary for back-up. The AIS
rapidly changing market environment. ants. In the case of GIS, two transformers variant requires a dedicated back-up unit
The first cost to be considered in the are required at substation TS1 for normal for the transformer in each HV substation.
comparison is that of the HV switchgear
installations. This is significantly higher for
the GIS than for the AIS solution. However, Comparison of the cost of the GIS and AIS variants (cash value over 7
the difference in system costs is smaller a period of 10 years)
than the difference in component (eg,
CVrel Relative cash value
switchbay) costs. This is because the in-
herent flexibility of the GIS/cable topology 45

allows the HV network to be configured % AIS ( 20kV )

more efficiently, leading to a smaller 35 AIS ( 10kV )


number of HV substations (3 for GIS, 4 for 30 GIS ( 20kV )
AIS) and also switchbays per HV trans- 25 GIS ( 10kV )
former substation. 20
A look at the cost of the 110-kV con- 15
CV rel
nections shows a similar picture. Although 10
the cable length in the GIS variant is much 5
shorter than the length of the overhead 0
Maintenance /
Lines / cables

Transformers

construction

Interruption
Switchgear

Switchgear

lines with AIS, the capital cost of the


Losses
110 kV

110 kV

110 kV

Cables

repairs
Land /

costs
I&C
MV

MV

equipment and civil works are higher in


the case of GIS.
The difference in the cost of the 110-kV

ABB Review 2/1999 23


S U B S T A T I O N S

GIS. It is costs such as these that under-


100
score how much the results depend on the
%
90 basic assumptions of the comparison, eg
the interest rate and the planning horizon.
80
As regards the losses, the short planning
70
horizon chosen for this comparison results
60 in the saving due to GIS being underesti-

50 mated.
When state-of-the-art AIS and GIS
CV rel 40
components are used, the cost of their
30 maintenance and inspection will be a mini-

20 mum. As the comparison shows, the


maintenance costs have no impact on the
10
variant ranking. The GIS variant exhibits
0 the lower costs as it needs fewer inspec-
AIS ( 20kV ) AIS ( 10kV ) GIS ( 20kV ) GIS ( 10kV )
tions per switchbay (GIS once every
8 years, AIS once every 5 years), of which
Comparison of life-cycle costs with GIS and AIS 8
(cash value over a period of 10 years) it also has fewer.
The final factor in the comparison is the
CVrel Relative cash value
cost of supply interruptions, ie the costs at
110-kV switchgear MV switchgear Land/construction the load end resulting from interrupted
service. Although it is the customer who
110-kV lines/cables MV cables Losses
foots the bill, these costs enable the non-
110-kV transformers I&C Maintenance/repairs
reliability of the network to be defined in
monetary terms.
Significant differences also exist be-
Another factor that speaks for the GIS tion, control and instrumentation) for the tween the 10-kV and the 20-kV MV supply.
variant is the cost of the MV switchgear in- GIS variant. A 20-kV network can, roughly speaking,
stallations. The difference here is due to In addition, the cost of the land, foun- transfer twice as much power as a 10-kV
the additional switchgear panels needed dations and buildings is lower for the GIS network over the same cable cross-
for the satellite stations in the AIS con- variant. This is due to the smaller space section. This either reduces the invest-
figuration. required, which can even compensate for ment in primary equipment (due to the
The cost of the MV cables is extraordi- the higher cost of land in the inner city. smaller number of MV cables) or leads to
narily high for both variants (about 40 % of Also, the GIS substation can be integrated lower losses for the same cable cross-
the life-cycle costs/cash value). Their in the basement of an existing building, section.
absolute value as well as the difference thus providing the required space without This effect is relativized in actual
between AIS/GIS shows how important it having to add to the footprint. Since this planning. The maximum number of MV
is to compare complete supply concepts solution is still unusual in Germany, it has substations supplied by the same cable in
rather than just the HV substations if not been considered in the comparison. In high load density areas is limited not only
results are to be reliable and realistic: HV South-East Asia and other regions, util- by the ampacity of the feeder cables but
injection close to the load centers reduces ities often take advantage of this option in also by the need to keep the number of
the MV network costs significantly. order to install HV stations in highly popu- customers affected by a single failure as
The smaller number of HV substations, lated load centers. low as possible. Another constraint is due
the absence of remotely controlled MV The difference in the cash value of the to the open-loop topology: the MV sub-
satellite stations and the reduced number losses quantifies the additional trans- stations must be assigned to two half-
of HV connections also reduce the cost of mission loads in the MV network. A saving loops, each of which starts at the HV
the secondary equipment (ie, for protec- of approximately 25 % is possible with substation busbar and is linked to the

24 ABB Review 2/1999


S U B S T A T I O N S

other via a disconnect point in the net-


work. 0.035

The cost comparison of the GIS and GIS


0.030
the AIS variant in the case of the 20-kV AIS
network shows reduced differences in 0.025
losses and in the investment in MV cable.
However, the costs are still significantly 0.020

(approx 4 %) higher for the AIS variant.


0.015
The direct comparison of the 20-kV
and 10-kV variants for similar HV tech- 0.010
nologies shows an advantage for the IF
20-kV solution. This result is plausible 0.005

and in line with actual planning experi-


ence. TS1 SS1 TS2 SS2 TS3 TS4

Interruption frequencies (IF) at the MV busbars of the HV substation 9


Reliability
TS1, 2, 3, 4 Transformer substations 1, 2, 3, 4
of the AIS/GIS variants SS1, 2 Satellite stations 1, 2
A reliable electric supply is especially im-
portant in urban networks where load den-
sities are high and users are sensitive to of cables. Overhead lines exhibit high cables. The high value for the outage rate
interruptions. The outage and reclosure outage rates but short outage times. To is a pessimistic estimate in which the ma-
behaviour is an area in which there is keep overhead line systems compact, jority of the faults are assumed to be
a fundamental difference between the parallel circuits are run on the same caused by external cable damage. A relia-
GIS/cable and the AIS/overhead line sol- pylons. As mentioned before, a single bility calculation was performed to quantify
utions, at least as far as the main power event can therefore lead to common mode the differences between the 10-kV vari-
users are concerned. failures in which several circuits are ants of the AIS/GIS concepts. The calcu-
110-kV cable faults are rare, being due tripped. This aspect is important and has lation simulates relevant component failure
in most cases to accidental damage dur- to be considered in every reliability com- modes and evaluates and quantifies the
ing construction work. Since HV cables parison. consequences for the customers. The
are buried deeper than MV cables, the Table 1 shows the values used in the component behaviour is derived from sta-
latter, which are laid above them, give reliability calculations for the HV lines/ tistics about failures in the past.
them a certain degree of protection. If the
HV cable itself is not sufficiently robust (eg,
protected by a surrounding steel tube, as
Table 1:
in the case of pipeline compression cable) Reliability data for cables and overhead lines (110 kV)
concrete ducts can be used to provide the
Outage1) rate per Repair duration
necessary shielding. This minimizes the year and 100 km (h)
failure rate even in supply regions in which
Overhead short 0.21 1
large-scale construction work is carried
HV line
out. (1 circuit) long 0.04 20.5
Besides their cost, the main drawback
Overhead HV line 0.15 2.7
of HV cables is the long time needed for (common mode)
their repair, as HV cables are typically
HV cables short 0.35 3.4
spliced by the suppliers staff. long 0.35 298
The characteristic behaviour of over-
1) Independent, stochastic outages
head lines is somewhat different to that

ABB Review 2/1999 25


S U B S T A T I O N S

Conclusions
140
Although the GIS solution appears initially
GIS to be the more costly, its flexibility allows
120
AIS
the HV transformer substations to be sited
100 in optimum locations. The number of injec-
tions from the HV system can be opti-
80
mized and the transmission load of the MV

60 network reduced. This leads to a signifi-


cant saving in investment as well as oper-
40 ating costs which more than compensates
n for the additional cost of the GIS and HV
20
cables.
0 Another advantage of the GIS/cable
0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22 0.24
combination is that it offers better reliabil-
IF
ity than the AIS/overhead line solution.
Major customers linked to the HV sub-
Interruption frequency distribution, as experienced by customers 10
station via parallel MV cables also
n Number of MV nodes experience this in everyday operation.
IF Range of interruption frequencies (per year, upper value)
And being inherent advantages of the
GIS/cable variant, these benefits cost the
The results of the calculation are shown multiple cable failure will affect the satellite network operator nothing.
in 9 . It is evident that the interruption supply as long as the protection devices GIS technology also offers further
rates are much lower for the GIS/cable work correctly. benefits which are harder to quantify but
variant, although high failure rates for the As shown in 10 , there are no significant which can be decisive for the realization of
HV cables have been assumed. The effect differences between the AIS and the GIS a project. One example is the option of
on the reliability is felt at the MV busbars variant within the MV network. complete integration of a GIS substation in
of the HV transformer. The reason lies in the radial operation of an existing building when no extra site
The values for GIS are of the order of the MV loops. Every fault leads to the at- area is available. Summing up, GIS is a
0.01 per year, ie one interruption every 100 tached feeder tripping and interrupting the cost-efficient, flexible and reliable solution
years. The interruption frequencies for the supply to all customers in the same half- for supply systems in regions with high
AIS substations TS1 and TS4 are of the loop. This interruption of service is usually load densities.
same magnitude, but TS3 and especially ended by (manual or remotely controlled)
TS2 are more frequently affected (by a fac- switching. The large number of events in
tor of 3 to 4). The reason is the loop-in via the MV network compared with those in
a double overhead line, which has been the 110-kV system dictates the inter-
assumed in both cases, and in addition for ruption behaviour and ensures com- Authors
TS2 the double-T connection to the sur- parative reliability at all customer nodes. Werner Zimmermann
rounding ring (also a double overhead This effect is underscored by the com- Andr Osterholt
line). parable interruption costs for AIS and GIS Dr. Jrgen Backes
The values for the satellite stations re- 7. ABB Calor Emag Schaltanlagen AG
ceiving power from TS1 and TS2 are the In cases where a special-tariff custom- Kfertaler Str. 250
same as for the MV busbars of the HV er is connected to the HV transformer sub- D-68167 Mannheim
transformer substations. This is plausible station via parallel cables, the reliability of Germany
because of the selective protection pro- the HV substation is passed on to the cus- E-mail:
vided for the parallel transmission cables tomer, who also benefits in this way from werner.zimmermann@deace.mail.abb.de
between the transformer substations and the GIS solution. andre.osterholt@deace.mail.abb.de
the satellite stations; neither a single nor juergen.backes@deace.mail.abb.de

26 ABB Review 2/1999

Вам также может понравиться