CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

1.00 ABRAZADERA PVC DE 1/2" X 4" S/. 3,600.00 S/. 3,600.00 S/. 3,600.00 S/. 3,600.00 S/. 1,800.00
2.00 ACCESORIOS DIVERSOS S/. 5,008.99 S/. 5,008.99 S/. 5,008.99 S/. 5,008.99 S/. 2,504.49
3.00 ACCESORIOS DIVERSOS PARA TANQUE ELEVADO S/. 1,500.00 S/. 1,500.00 S/. 3,000.00 S/. 3,000.00
4.00 ACCESORIOS PVC SAP (AGUA) S/. 470.00 S/. 470.00 S/. 470.00 S/. 470.00 S/. 235.00
5.00 ACERO CORRUGADO 0 3/8" S/. 2.79 S/. 2.79 S/. 5.59 S/. 5.59
6.00 ACERO DE REFUERZO FY=4200 GRADO 60 S/. 150,000.00 S/. 50,000.00 S/. 45,000.00 S/. 23,000.00 S/. 10,000.00
7.00 ADAPTADOR PVC SAP -FF DE 110 MM S/. 868.00 S/. 868.00 S/. 868.00 S/. 868.00 S/. 434.00
8.00 AFORADOR DE FIBRA DE VIDRIO
9.00 AGUA S/. 3,329.88 S/. 3,500.00 S/. 2,500.00 S/. 1,500.00 S/. 1,500.00
10.00 ALAMBRE NEGRO RECOCIDO # 16 S/. 1,000.00 S/. 3,000.00 S/. 3,000.00 S/. 3,000.00 S/. 4,000.00
11.00 ALAMBRE NEGRO RECOCIDO # 8 S/. 750.00 S/. 850.00 S/. 750.00 S/. 750.00 S/. 500.00
12.00 ANDAMIO DE MADERA S/. 104.14
13.00 ANDAMIO METAL TABLAS-ALQUILER S/. 78.25
14.00 ANGULO 1"x1"x1/8" x6m. AREQUIPA S/. 100.00 S/. 47.34
15.00 ANGULO 2"x2"x1/4" x6m. AREQUIPA S/. 104.40
16.00 ANGULO 3/4"x3/4"x1/8"x 6m. AREQUIPA S/. 40.04
17.00 ANILLO DE JEBE DE 110MM PARA AGUA C-7.5 S/. 2,877.39 S/. 2,877.39 S/. 2,877.39 S/. 2,877.39 S/. 1,438.69
18.00 ANILLO DE JEBE DE 200MM S/. 1,794.62 S/. 2,392.83 S/. 1,794.62 S/. 1,794.62 S/. 1,794.62
19.00 ANILLO DE JEBE DE 200MM PARA AGUA C-7.5 S/. 656.74 S/. 656.74 S/. 656.74 S/. 656.74 S/. 328.37
20.00 ANILLO DE JEBE DE 250MM S/. 23,972.54 S/. 25,534.08
21.00 ANILLO DE JEBE DE 300MM S/. 85.05 S/. 113.40 S/. 85.05 S/. 85.05 S/. 85.05
22.00 ANILLO DE JEBE A-10 DE 250MM S/. 41.82 S/. 55.76 S/. 41.82 S/. 41.82 S/. 41.82
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

23.00 ANILLO DE JEBE A-7.5 DE 110MM S/. 62.00 S/. 62.00 S/. 62.00 S/. 62.00 S/. 31.00
24.00 ARENA FINA S/. 100,000.00 S/. 50,000.00 S/. 45,000.00 S/. 45,000.00 S/. 2,790.68
25.00 ARENA GRUESA S/. 50,000.00 S/. 50,000.00 S/. 50,000.00 S/. 40,000.00 S/. 40,000.00
26.00 ARENADO,LABOR PINTADO TUBO FIERRO 16" S/. 707.00
27.00 ARENADO,LABOR PINTADO TUBO FIERRO 8" S/. 1,311.38
28.00 ASFALTO RC-250 S/. 10,000.00 S/. 3,000.00 S/. 3,000.00 S/. 1,604.86
29.00 BALDE PRUEBA-TAPON -ABRAZ. Y ACCESORIOS S/. 2,000.00 S/. 2,000.00 S/. 2,000.00 S/. 308.22
30.00 BARRENO DE PERFORACION DIFERENTES MEDIDA S/. 2,500.00 S/. 1,500.00
31.00 BOMBA DE AGUA 4 HP DE CAUDAL S/. 600.00 S/. 600.00 S/. 600.00 S/. 600.00
32.00 BOMBA PARA PRUEBA, 12 HP S/. 360.00
33.00 BRIDA ACERO P/SOLDAR-ROMPE AGUA DE 8" S/. 130.00
34.00 BRIDA DE ACERO P/ SOLDAR-EMPERNAR DE 8" S/. 1,000.00 S/. 560.00
35.00 CABLE TW # 10 AWG S/. 48.30
36.00 CABLE TW # 14 AWG 2.5 MM2 S/. 204.10
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

37.00 CABLE TW # 2 AWG - 35 MM2. S/. 10.00


38.00 CAJA CONCRETO SIMPLE DESAG. .3X.6 I/FLET S/. 80,000.00 S/. 35,000.00 S/. 30,000.00 S/. 5,000.00
39.00 CAJA DE CONCRETO P/MEDIDOR 1/2" - 3/4" S/. 24,000.00
40.00 CAJA OCTOGONAL GALV. 4" X 2 1/8 " S/. 16.00
41.00 CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 S/. 13.72
42.00 CAJA RECTANG GALV 4"X2 1/8" S/. 16.50
43.00 CAL HIDRATADA DE 30 Kg S/. 46.40
44.00 CAMION CISTERNA 4x2 (AGUA) 122 HP 1,500 S/. 2,500.00 S/. 2,500.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00
45.00 CAMION VOLQUETE 4x2 140-210 HP 6 M3. S/. 1,500.00 S/. 1,500.00 S/. 2,000.00 S/. 684.05
46.00 CAMION VOLQUETE 7 M3. S/. 1,500.00 S/. 1,500.00 S/. 5,000.00 S/. 5,000.00 S/. 1,179.00
47.00 CANASTILA ROSCADA DE BRONCE DE 12" S/. 357.75
48.00 CANASTILLA DE 8" S/. 90.00
49.00 CAPACITACION SOCIAL S/. 2,000.00 S/. 2,000.00 S/. 2,000.00 S/. 2,000.00
50.00 CAPATAZ S/. 35,000.00 S/. 20,000.00 S/. 20,000.00 S/. 20,000.00 S/. 5,000.00
51.00 CARGADOR RETROEXCAVADOR 62 HP 1 YD3 S/. 50,000.00 S/. 25,000.00 S/. 25,000.00 S/. 20,000.00 S/. 15,000.00
52.00 CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3 S/. 344.38
53.00 CARGADOR S/LLANTAS 125-155 HP 3 YD3. S/. 10,000.00 S/. 10,000.00 S/. 10,000.00 S/. 10,000.00
54.00 CARGADOR S/LLANTAS 80-95 HP 1.5-1.75 YD3 S/. 2,447.60
55.00 CASETA ADICIONAL TECHADA SEDAPAL S/. 4,732.00
56.00 CASETA DE BOMBEO C/EQUIPO S/. 20,000.00 S/. 15,000.00
57.00 CEMENTO PORTLAND TIPO I (42.5KG) S/. 68,000.00 S/. 20,000.00 S/. 20,000.00 S/. 5,000.00 S/. 7,756.29
58.00 CEMENTO PORTLAND TIPO I (EN FCA.)S-PUB S/. 558.33
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

59.00 CEMENTO PORTLAND TIPO V S/. 100,000.00 S/. 20,000.00 S/. 27,528.01
60.00 CINTA AISLANTE S/. 0.90
61.00 CINTA TEFLON S/. 240.00
62.00 CIZALLA P/FIERRO CONST. HASTA 1" S/. 250.00 S/. 250.00 S/. 250.00 S/. 100.12
63.00 CLAVOS Fo No C/C 3" S/. 32.00
64.00 CLAVOS Fo No C/C 3/4" S/. 842.00
65.00 CLAVOS PARA MADERA C/C 3" S/. 2,500.00 S/. 2,000.00 S/. 2,000.00 S/. 1,000.00
66.00 CLAVOS PARA MADERA C/C 3/4" S/. 104.73
67.00 COCINILLA A GAS I/ACCESORIOS/PLOMO S/. 17.15
68.00 CODO PVC SAP 110MM*22.5 S/. 780.00
69.00 CODO PVC SAP 110MM*90 S/. 1,000.00 S/. 1,000.00 S/. 1,000.00 S/. 640.00
70.00 CODO DE 900 SP PVC SAP P/AGUA DE 1/2" S/. 250.00 S/. 250.00 S/. 500.00 S/. 500.00 S/. 300.00
71.00 CODO DE ACERO DE 200MM S/. 340.00
72.00 CODO PVC SAP 110MM*45 S/. 260.00
73.00 CODO PVC SAP 200MM*90 S/. 1,295.00
74.00 COMPACTADOR VIBR. TIPO PLANCHA 4 HP S/. 552.00
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

75.00 COMPACTADOR VIBR. TIPO PLANCHA 7 HP S/. 250.00 S/. 500.00 S/. 200.00 S/. 5.39
76.00 COMPACTADOR VIBR. TIPO PLANCHA 8 HP S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 9,803.68
77.00 COMPRESORA NEUMATICA 196 HP 600-690 PCM S/. 2,500.00 S/. 1,000.00 S/. 1,000.00
78.00 COMPUERTA DE MADERA 0.30X0.40m S/. 100.00
79.00 CONEXION A CAJA PVC SAP 3/4" S/. 4.80
80.00 CONEXION A CAJA PVC SEL P/INS ELECT 5/8" S/. 50.00
81.00 CONEXIONES A CAJA PVC SEL 3/4"
82.00 CORDEL S/. 237.00
83.00 CORPORATION RT-NIPLE-TUERCA-EMPAQ. 1/2" S/. 6,850.00 S/. 5,000.00 S/. 1,000.00 S/. 200.00
84.00 CORTADORA DE CONCRETO 8HP S/. 58.72
85.00 COSTO ESTIMADO S/. 420.00
86.00 COSTO ESTIMADO PARA DIAGRAFIA S/. 4,144.00
87.00 CRUZ PVC SAP DE 110MM S/. 224.00 S/. 224.00 S/. 224.00 S/. 300.00 S/. 148.00
88.00 CRUZ PVC SAP DE 200MM S/. 500.00 S/. 500.00 S/. 416.00
89.00 CURVA LIVIANO PVC SEL P/INST. ELECT 1" S/. 2.60
90.00 CURVA LIVIANO PVC SEL P/INST. ELECT 5/8" S/. 3.00
91.00 CURVA PESADO PVC SAP P/INST. ELECT. 1" S/. 0.90
92.00 CURVA PVC 1/2" P/AGUA S/. 900.00
93.00 CURVAS PVC SEL 3/4" S/. 5.85
94.00 DISCO DE CORTE DIAMANTADO S/. 3,555.91
95.00 ELECTROBOMBA 25HP SUMERGIBL TUBULAR 6"MON S/. 20,000.00
96.00 ELECTROBOMBA 2HP SUMERGIBL TUBULAR 6"TRI S/. 8,657.17
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

97.00 ELECTROBOMBA 36HP SUMERGIBL TUBULAR 6"MON S/. 13,913.60 S/. 49,600.00 S/. 6,000.00 S/. 54.40
98.00 EMPAQUETADURA DE JEBE DE 8" S/. 384.00
99.00 ENCOFRADO METALICO S/. 882.37
100.00 EQUIPO DE CLORINACION S/. 3.21
101.00 EQUIPO DE CONTROL AUTOMATICO DE NIVEL
102.00 EQUIPO DE CONTROL AUTOMATICO ENCENDIDO + ESTABILIZADOR S/. 22,775.90
103.00 EQUIPO DE CORTE Y SOLDEO (OXI-ACET) S/. 20,000.00 S/. 20,000.00 S/. 21,921.28
104.00 EQUIPO IMPORTADO S/. 1,500.00 S/. 1,000.00 S/. 1,000.00 S/. 500.00
105.00 ESCALERA DE CARACON D=1.30M H=2.40M S/. 4,216.32
106.00 ESTACA DE MADERA S/. 8,090.16
107.00 ESTERA DE 2.00 X 3.00 M.
108.00 ESTIMADO S/. 185.00
109.00 FILTRO ESPECIA DE FGIMPORTADO S/. 5,000.00 S/. 10,000.00 S/. 10,000.00
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

110.00 FLETE TRANSPORTE LOCAL S/. 3,000.00 S/. 1,000.00 S/. 2,803.87
111.00 FLETE TUBERIA P.V.C. 1/2" - 1" S/. 120.00
112.00 GENERADOR DIESSEL 10 KW S/. 22,500.00
113.00 GRAVA PARA FILTRO DE 10-18MM S/. 2,000.00 S/. 2,000.00 S/. 2,006.96
114.00 GRAVILLA PARA PROTECCION DE MEDIDOR S/. 900.00
115.00 GRIFO CONTRA INCENDIO T/POSTE 2 BOCAS S/. 500.00 S/. 500.00 S/. 500.00
116.00 HIPOCLORITO DE CALCIO 70% S/. 450.00
117.00 HIPOCLORITO DE CALCIO AL 70% S/. 726.74 S/. 2,000.00 S/. 2,000.00
118.00 HORMIGON S/. 100.00 S/. 508.93
119.00 HORMIGON (PUESTO EN OBRA) S/. 389.04
120.00 IMPERMEAB.MORTERO/CONCRETO CHEMA 1 POLVO S/. 786.19
121.00 IMPERMEABILIZANTE S/. 78.79
122.00 IMPRIMANTE S/. 1,703.29
123.00 INODORO TQUE. BAJO NORMAL BLANCO C/A. S/. 65.00
124.00 INSTALACION PROVISIONAL DE AGUA Y DESAGU S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00
125.00 INSTALACIONES ELECTRICAS (ESTIMADO) Z.S. S/. 2,000.00 S/. 574.00
126.00 INTERRUPTOR SIMPLE BIPOLAR BAKELITA S/. 14.40
127.00 INTERRUPTOR TERMOMAGNETICO DE 3x60A S/. 70.00
128.00 INTERRUPTORES DE COMMUTACION S/. 75.00
129.00 LADRILLO CORRIENTE 6 x 12 x 24 CM S/. 1,000.00 S/. 1,000.00 S/. 46.00
130.00 LADRILLO CORRIENTE 6 x 12 x 24 CM S/. 229.85
131.00 LADRILLO KING KONG HECHO A MANO 10x14x24 CM S/. 446.78
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

132.00 LAVATORIO 23"X17" P/GRIF.4" BLANCO C/A S/. 85.00


133.00 LIMPIEZA Y DESFORESTACION S/. 3,000.00 S/. 3,000.00 S/. 3,000.00 S/. 3,000.00 S/. 1,000.00
134.00 LLAVE PASO RT-NIPLE-TUERCA-EMPAQ. 1/2" S/. 15,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00
135.00 LUBRICANTE S/. 5,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00 S/. 1,994.17
136.00 MADERA CEDRO DE PUCALLPA CEPILLADA S/. 18.82
137.00 MADERA EUCALIPTO TRATADA S/. 500.00 S/. 500.00 S/. 500.00 S/. 452.50
138.00 MADERA NACIONAL P/ENCOFRADO-CARP S/. 25,000.00 S/. 25,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00
139.00 MADERA TORNILLO CEPILLADA S/. 400.00 S/. 400.00 S/. 423.81
140.00 MADERA TORNILLO INC.CORTE P/ENCOFRADO S/. 15,000.00 S/. 15,000.00 S/. 10,000.00 S/. 10,000.00
141.00 MALLA CUADRADA CRIPADA GALVANIZADA # 10 S/. 4.75
142.00 MARCO F.FDO. DIAMETRO 0.60 M. S/. 20,000.00 S/. 20,000.00 S/. 10,000.00 S/. 3,400.00
143.00 MARCO Y TAPA TERMOPLASTICO P/MEDIDOR 1/2"-3/4" S/. 45,000.00 S/. 900.00
144.00 MATERIAL CLASIFICADO PARA BASE S/. 971.81
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

145.00 MATERIAL DE PRESTAMO-SELECCIONADO OBRA S/. 5,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00
146.00 MEDIDOR DE CAUDAL 1/2" S/. 15,000.00
147.00 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00
148.00 MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 S/. 500.00 S/. 1,200.00 S/. 1,000.00 S/. 1,000.00 S/. 1,000.00
149.00 MOLDE METALICO PARA BUZON S/. 500.00 S/. 200.00 S/. 200.00 S/. 200.00
150.00 MOTOBOMBA 10 HP 4" S/. 381.77
151.00 MOTOBOMBA 3.5 HP 2" S/. 500.00
152.00 MOTOBOMBA 3.5HP D=2" S/. 300.00 S/. 300.00 S/. 300.00 S/. 22.61
153.00 MOTOBOMBA 4" INCL. MANGUERA Y ACCS. S/. 1,000.00 S/. 1,000.00 S/. 2,500.00 S/. 1,500.00 S/. 1,000.00
154.00 MOTOSOLDADORA DE 250 AMP. S/. 350.00 S/. 500.00 S/. 250.00
155.00 MOVILIZACION Y DESMOVILIZACION S/. 3,654.26

S/. 764,446.20 S/. 598,265.37 S/. 492,303.19 S/. 413,844.49 S/. 269,234.22
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA: MEJORAMIENTO Y AMPLIACION INTEGRAL DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA LOCALIDAD DE OYOTUN-CHICLAYO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE OYOTUN
VALOR REFERENCIAL: S/. 9,997,833.45
PLAZO DE EJECUCION DE OBRA: 353 DIAS

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05

S/. 76,444.62 S/. 59,826.54 S/. 49,230.32 S/. 41,384.45 S/. 26,923.42
S/. 38,222.31 S/. 29,913.27 S/. 24,615.16 S/. 20,692.22 S/. 13,461.71
S/. 38,222.31 S/. 29,913.27 S/. 24,615.16 S/. 20,692.22 S/. 13,461.71
S/. 917,335.44 S/. 717,918.44 S/. 590,763.83 S/. 496,613.39 S/. 323,081.06
S/. 174,293.73 S/. 136,404.50 S/. 112,245.13 S/. 94,356.54 S/. 61,385.40
S/. 1,091,629.18 S/. 854,322.94 S/. 703,008.95 S/. 590,969.94 S/. 384,466.46
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 1,800.00 S/. 18,000.00 18,000.00


S/. 2,504.49 S/. 25,044.93 25,044.93
S/. 3,000.00 S/. 3,000.00 S/. 15,000.00 15,000.00
S/. 235.00 S/. 2,350.00 2,350.00
S/. 5.59 S/. 5.59 S/. 27.93 27.93
S/. 6,869.36 S/. 284,869.36 284,869.96
S/. 434.00 S/. 4,340.00 4,340.00
S/. 2,250.00 S/. 2,250.00 2,250.00
S/. 2,500.00 S/. 1,819.53 S/. 16,649.41 16,649.41
S/. 4,050.57 S/. 18,050.57 18,050.57
S/. 138.38 S/. 3,738.38 3,738.38
S/. 104.14 104.14
S/. 78.25 78.25
S/. 147.34 147.34
S/. 104.40 104.90
S/. 40.04 40.04
S/. 1,438.69 S/. 14,386.94 14,386.94
S/. 1,794.62 S/. 598.21 S/. 11,964.15 11,964.15
S/. 328.37 S/. 3,283.70 3,283.70
S/. 49,506.62 420.00
S/. 85.05 S/. 28.35 S/. 567.00 567.00
S/. 41.82 S/. 13.94 S/. 278.80 278.80
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 31.00 S/. 310.00 310.00


S/. 242,790.68 242,790.68
S/. 12,000.00 S/. 711.84 S/. 242,711.84 242,711.84
S/. 707.00 707.00
S/. 1,311.38 1,311.38
S/. 17,604.86 17,604.86
S/. 6,308.22 6,308.22
S/. 383.50 S/. 4,383.50 4,383.50
S/. 225.00 S/. 2,625.00 2,625.00
S/. 360.00 960.00
S/. 130.00 130.00
S/. 1,560.00 1,560.00
S/. 48.30 48.30
S/. 204.10 204.10
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 10.00 10.00


S/. 150,000.00 150,000.00
S/. 24,000.00 24,000.00
S/. 16.00 16.00
S/. 13.72 13.72
S/. 16.50 16.50
S/. 46.40 46.40
S/. 1,081.18 S/. 21,081.18 21,081.18
S/. 5,684.05 5,684.05
S/. 14,179.00 14,179.00
S/. 357.75 357.75
S/. 90.00 90.00
S/. 1,000.00 S/. 1,000.00 S/. 10,000.00 10,000.00
S/. 3,123.75 S/. 103,123.75 103,123.75
S/. 10,000.00 S/. 10,000.00 S/. 397.27 S/. 155,397.27 155,397.23
S/. 344.38 344.38
S/. 10,000.00 S/. 550.02 S/. 50,550.02 50,550.02
S/. 2,447.60 2,447.60
S/. 4,732.00 4,732.00
S/. 35,000.00 35,000.00
S/. 120,756.29 120,756.29
S/. 558.33 558.33
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 147,528.01 147,528.01


S/. 0.90 0.90
S/. 240.00 240.00
S/. 850.12 850.12
S/. 32.00 32.00
S/. 842.00 842.82
S/. 640.02 S/. 8,140.02 8,140.02
S/. 104.73 104.73
S/. 17.15 17.15
S/. 780.00 780.00
S/. 3,640.00 3,640.00
S/. 1,800.00 1,800.00
S/. 340.00 940.00
S/. 260.00 260.00
S/. 1,295.00 1,295.00
S/. 552.00 552.04
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 955.39 955.39


S/. 109,803.68 109,803.68
S/. 1,500.00 S/. 192.13 S/. 6,192.13 6,192.13
S/. 100.00 100.00
S/. 4.80 4.80
S/. 50.00 50.00
S/. 10.80 S/. 10.80 10.80
S/. 237.00 0.00
S/. 13,050.00 13,050.00
S/. 58.72 58.72
S/. 420.00 420.00
S/. 4,144.00 4,144.00
S/. 1,120.00 1,120.00
S/. 1,416.00 1,416.00
S/. 2.60 2.60
S/. 3.00 3.00
S/. 0.90 0.90
S/. 900.00 900.00
S/. 5.85 5.85
S/. 3,555.91 3,555.91
S/. 20,000.00 20,000.00
S/. 8,657.17 43,285.84
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 69,568.00 69,568.00


S/. 384.00 384.00
S/. 882.37 882.37
S/. 3.21 31,500.00
S/. 16,268.50 S/. 16,268.50 16,268.50
S/. 22,775.90 22,775.90
S/. 61,921.28 61,921.28
S/. 666.90 S/. 4,666.90 4,666.90
S/. 4,216.32 4,216.32
S/. 8,090.16 8,090.16
S/. 225.00 S/. 225.00 225.00
S/. 185.00 185.00
S/. 10,000.00 S/. 1,720.00 S/. 36,720.00 36,720.00
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 6,803.87 6,803.87


S/. 120.00 120.00
S/. 22,500.00 22,500.00
S/. 6,006.96 6,006.96
S/. 900.00 900.00
S/. 500.00 S/. 250.00 S/. 2,250.00 2,250.00
S/. 450.00 450.00
S/. 2,000.00 S/. 2,000.00 S/. 8,726.74 8,726.74
S/. 608.93 608.93
S/. 389.04 389.04
S/. 786.19 786.19
S/. 78.79 78.79
S/. 1,703.29 1,703.29
S/. 65.00 65.00
S/. 500.00 S/. 500.00 S/. 3,500.00 3,500.00
S/. 2,574.00 2,574.00
S/. 14.40 14.40
S/. 70.00 70.00
S/. 75.00 75.00
S/. 2,046.00 2,046.00
S/. 229.85 229.85
S/. 446.78 446.78
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 85.00 85.00


S/. 1,000.00 S/. 1,615.14 S/. 15,615.14 15,615.14
S/. 30,000.00 30,000.00
S/. 21,994.17 21,994.17
S/. 18.82 18.82
S/. 1,952.50 1,952.50
S/. 5,000.00 S/. 2,552.22 S/. 72,552.22 72,552.22
S/. 1,223.81 1,223.81
S/. 2,622.65 S/. 52,622.65 52,622.65
S/. 4.75 4.75
S/. 53,400.00 53,400.00
S/. 45,900.00 45,900.00
S/. 971.81 971.81
DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL

S/. 2,765.00 S/. 27,765.00 27,765.00


S/. 15,000.00 75,000.00
S/. 500.00 S/. 500.00 S/. 634.65 S/. 3,634.65 3,634.65
S/. 1,000.00 S/. 1,000.00 S/. 23.48 S/. 6,723.48 6,723.48
S/. 350.00 S/. 150.00 S/. 45.98 S/. 1,645.98 1,645.98
S/. 381.77 381.77
S/. 500.00 S/. 32.39 S/. 1,032.39 1,032.39
S/. 922.61 922.61
S/. 500.00 S/. 500.00 S/. 326.60 S/. 8,326.60 8,328.60
S/. 61.20 S/. 1,161.20 1,161.20
S/. 3,654.26 S/. 7,308.51 7,308.51

S/. 2,683,845.50 2,761,851.26


DE ADQUISICION DE MATERIALES

MESES
MES 06 MES 07 MES 08 SUMA PARCIAL
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

156.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 2,800.00


157.00 NIPLE PVC 7.5 X 3/4"-REEMP MEDIDOR 1/2" S/. 300.00 S/. 300.00 S/. 300.00 S/. 300.00 S/. 150.00 S/. 150.00 S/. 0.00
158.00 NIVEL S/. 139.63
159.00 NIVEL S/. 963.60 S/. 800.00 S/. 800.00 S/. 800.00 S/. 800.00 S/. 800.00 S/. 800.00
160.00 OCRE ROJO S/. 72.68
161.00 OFICIAL S/. 25,500.00 S/. 35,500.00 S/. 25,000.00 S/. 25,000.00 S/. 24,500.00 S/. 5,000.00 S/. 2,200.00
162.00 OPERADOR DE EQUIPO PESADO S/. 3,250.00 S/. 2,500.00 S/. 2,500.00 S/. 2,500.00 S/. 2,500.00 S/. 1,500.00 S/. 1,319.61
163.00 OPERARIO S/. 35,000.00 S/. 35,000.00 S/. 35,000.00 S/. 35,000.00 S/. 35,000.00 S/. 35,000.00 S/. 35,000.00
164.00 PEGAMENTO PARA PVC S/. 2,500.00 S/. 5,000.00 S/. 3,500.00 S/. 3,500.00 S/. 3,500.00 S/. 3,500.00 S/. 1,210.91
165.00 PEGAMENTO PARA PVC AGUA FORDUIT S/. 34.56 S/. 34.56
166.00 PEGAMENTO PARA PVC AGUA FORDUIT 1/4 GLN S/. 4,816.00
167.00 PEON S/. 175,000.00 S/. 190,000.00 S/. 195,000.00 S/. 187,500.00 S/. 198,000.00 S/. 200,000.00 S/. 165,000.00
168.00 PERFORISTA OFICIAL S/. 3,550.00 S/. 3,550.00 S/. 3,550.00 S/. 1,200.00 S/. 224.75
169.00 PERNOS 1 1/8" X 6" S/. 720.00
170.00 PERNOS HEXAGONALES DE 3/4" X 6" INC.TUER S/. 67.20
171.00 PIEDRA CHANCADA DE 1/2" S/. 12,000.00 S/. 15,000.00 S/. 4,500.00 S/. 1,200.00 S/. 42.84
172.00 PIEDRA CHANCADA DE 3/4" S/. 10,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,000.00 S/. 3,500.00 S/. 3,535.07 S/. 3,500.00
173.00 PIEDRA CHANCADA DE 3/4" S/. 15,000.00 S/. 5,000.00 S/. 5,000.00 S/. 2,500.00 S/. 1,000.00 S/. 459.11
174.00 PIEDRA GRANDE DE 8" S/. 179.58
175.00 PIEDRA MEDIANA DE 6" S/. 17.05
176.00 PINTURA AL OLEO MATE S/. 80.34
177.00 PINTURA AL TEMPLE SIMPLE S/. 3,000.00 S/. 1,000.00 S/. 500.00 S/. 597.77
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

178.00 PINTURA ANTICORROSIVA EPOX-USO NAVAL S/. 169.13


179.00 PINTURA ESMAL.METAL-MAD.ESMALTEX C/COLOR S/. 220.90
180.00 PINTURA ESMALTE SINTETICO S/. 54.61
181.00 PISON MANUAL S/. 1,200.00 S/. 1,200.00 S/. 1,200.00 S/. 1,200.00 S/. 1,200.00 S/. 1,200.00 S/. 1,200.00
182.00 PIZON MANUAL S/. 10,000.00 S/. 10,000.00 S/. 10,000.00 S/. 10,000.00 S/. 10,000.00 S/. 10,000.00 S/. 10,000.00
183.00 PLANCHA ACERO 1.6mm x 1.22m x 2.40m S/. 410.24
184.00 PLANTONES DE MOLLE Y EUCALIPTO S/. 1,200.00 S/. 725.00
185.00 PLATINA DE FIERRO 1/2" x 4" x 6m S/. 2.52
186.00 PLATINA DE FIERRO 1/4" x 1/2" x 6m S/. 0.80
187.00 PLATINA DE FIERRO 1/4" x 3" x 6m S/. 1.64
188.00 PLATINA DE FIERRO 1/4" x 4" x 6m S/. 1.54
189.00 PLATINA DE FIERRO 1/8" x 1 1/2" x 6m S/. 10.81
190.00 PLATINA DE FIERRO 1/8" x 1" x 6m S/. 0.63
191.00 PLATINAS DE 3/16" S/. 89.60
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

192.00 PLOMO ELECTROLITICO S/. 20.58


193.00 REDUCCION PVC SAP 200X110MM S/. 1,250.00 S/. 1,250.00 S/. 1,250.00 S/. 150.00 S/. 10.00
194.00 REGLA DE MADERA S/. 68.10
195.00 REGLA GRADUADA I/ACCESOR Y PINTURA S/. 50.00
196.00 RETROEXCAVADOR S/LLANTAS 58 HP 1 YD3. S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 10,000.00 S/. 3,561.28
197.00 RETROEXCAVADORA 225 H.P. S/. 6,514.56
198.00 RETROEXCAVADORA S/O 75-110 HP,.50-1.3Y3 S/. 5,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 25,000.00 S/. 20,000.00
199.00 RETROEXCAVADORA S/O 115-165 HP,.75-1.4Y3 S/. 3,233.42
200.00 RIPIO CORRIENTE S/. 39,690.02 S/. 15,000.00 S/. 15,000.00 S/. 15,000.00 S/. 15,000.00 S/. 15,000.00 S/. 15,000.00
201.00 RIPIO CORRIENTE S/. 2,878.20
202.00 RODILLO LISO VIBR MANUAL 10.8HP 0.8-1.1T S/. 348.66
203.00 RODILLO TANDEM ESTATI AUT 70-100HP 8-14T S/. 123.75
204.00 RODILLO TRES RUEDAS ESTATI 58.5HP 10-15T S/. 123.75
205.00 SEGURO PARA MEDIDOR S/. 9,000.00
206.00 SOLDADURA CELLOCORD P 3/16" S/. 128.84
207.00 SPOT LIGTH CROMADO S/. 24.00
208.00 TABLERO ARRANQ-PARAD 3M. INC.CABLES/CR4 S/. 20,000.00
209.00 TABLERO ELECTRICO GENERAL E.B./LP-32-92 S/. 5,000.00
210.00 TABLERO GABINETE METAL BARRA BRONCE 12 POLOS S/. 250.00
211.00 TALADRO CON BROCA S/. 45.00
212.00 TAPA CONCRETO ARMADO DESAG .3X.6 I/FLETE S/. 37,500.00
213.00 TAPA DE CONCRETO ARMADO PARA BUZON S/. 40,050.00
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

214.00 TAPA INSPECCION 0.60MX0.60M DE FG S/. 150.00


215.00 TAPON PVC 110MM SAP S/. 270.00
216.00 TEE 1 1/2"x1 1/2"x1/8" x6m. A. AREQUIPA S/. 29.38
217.00 TEE 1"x1"x1/8" x6m. A. AREQUIPA S/. 169.97
218.00 TEE 3/4"x3/4"x1/8" x6m. A. AREQUIPA S/. 65.06
219.00 TEE PVC SAP 110MM S/. 4,940.00
220.00 TEE PVC SAP 200MM S/. 10,000.00 S/. 5,000.00 S/. 5,000.00 S/. 5,800.00
221.00 TEODOLITO S/. 167.56
222.00 TEODOLITO S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 500.00 S/. 203.04
223.00 TIERRA DE CHACRA O VEGETAL S/. 48.00
224.00 TIZA S/. 34.92
225.00 TOMACORRIENTE DOBLE PLANO BAKELITA S/. 4.60
226.00 TOPOGRAFO S/. 2,000.00 S/. 2,000.00 S/. 2,000.00 S/. 2,000.00 S/. 1,000.00 S/. 1,000.00 S/. 697.78
227.00 TRANSFORMADOR 10 KVA S/. 14,000.00
228.00 TRANSICION Fo.Fo. MAZZA A-10 (C-150) 4" S/. 650.00
229.00 TRIPLAY DE 6 MM S/. 588.68
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

230.00 TUB. PVC SAP P/INST. ELECT. DE 1" S/. 5.00


231.00 TUB. PVC SEL P/INST. ELECT. DE 1" x 3m S/. 9.12
232.00 TUB. PVC SEL P/INST. ELECT. DE 5/8" S/. 70.00
233.00 TUB. PVC SEL P/INST. ELECT. DE 5/8" x 3m S/. 9.26
234.00 TUB.SCHELUDE 40 DE 16"(400MM) S/. 25,000.00 S/. 2,573.00
235.00 TUB.SCHELUDE 40 DE 8"(200MM) S/. 15,000.00 S/. 1,716.90
236.00 TUBERIA PVC 110MM CLASE 7.5 S/. 125,000.00 S/. 50,000.00 S/. 50,000.00 S/. 2,176.67
237.00 TUBERIA PVC 160MM CLASE 10 S/. 34,872.20
238.00 TUBERIA PVC 160MM UF SERIE 20 S/. 27,255.00
239.00 TUBERIA PVC 200MM CLASE 10 S/. 2,892.24
240.00 TUBERIA PVC 200MM CLASE 7.5 S/. 28,896.60 S/. 28,896.60 S/. 28,896.60 S/. 28,896.60 S/. 20,000.00 S/. 8,896.60
241.00 TUBERIA PVC 200MM UF SERIE 20 S/. 104,061.52 S/. 104,061.52 S/. 104,061.52 S/. 104,061.52 S/. 52,030.76 S/. 45,000.00 S/. 7,030.76
242.00 TUBERIA PVC 250MM CLASE 10 S/. 3,378.40 S/. 3,378.40 S/. 3,378.40 S/. 3,378.40 S/. 1,689.20 S/. 1,689.20
243.00 TUBERIA PVC 250mm serie 20 S/. 14,059.50
244.00 TUBERIA PVC 300mm serie 20 S/. 19,467.00
245.00 TUBERIA PVC 400mm CLASE 10 S/. 1,238.58
246.00 TUBERIA PVC SAP A-10 DE 1/2" S/. 5,000.00 S/. 4,000.00
247.00 TUBO CACHIMBA PVC 160MM S/. 19,500.00 S/. 19,500.00 S/. 19,500.00 S/. 19,500.00 S/. 9,750.00 S/. 9,750.00
248.00 TUBO FO.GALV.ST.ISO-I 1 1/2" S/. 216.09
249.00 TUBO FO.GALV.ST.ISO-I 1" S/. 171.50
250.00 TUBO FO.GALV.ST.ISO-I 2" S/. 163.17
251.00 TUBO Fo.GALV.ST.ISO-I 2"x3.3mm S/. 19.80
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

252.00 TUBO FO.GALV.ST.ISO-I 3/4" S/. 66.50


253.00 TUBO Fo.GALV.ST.ISO-I 4"x4.5mm S/. 5.60
254.00 TUBO PVC SEL (E/C) 3/4" X 3.00 M. S/. 26.25
255.00 UNION FLEXIBLE TIPO DRESSER DE 8" S/. 5,000.00 S/. 3,800.00
256.00 UNION PR PVC SAP P/AGUA DE 1/2" S/. 1,050.00
257.00 UNION PVC SEL 3/4" S/. 1.60
258.00 VALVULA DE BRONCE DE 110mm S/. 2,250.00
259.00 VALVULA DE COMPUERTA 110 MM MAZZA S/. 15,000.00 S/. 10,000.00 S/. 2,900.00
260.00 VALVULA DE COMPUERTA-BB 8" S/. 5,480.00
261.00 VARILLA DE COBRE DE 1/2" x 2.40m S/. 45.00
262.00 VERTEDERO SUTRO S/. 150.00
263.00 VIBRADOR DE 3/4" - 2" CONCRETO S/. 500.00 S/. 300.00 S/. 300.00 S/. 256.49 S/. 200.00 S/. 200.00
264.00 VIBRADOR DE CONCRETO 4 HP 2.40" S/. 100.00 S/. 100.00 S/. 100.00 S/. 100.00 S/. 54.71
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

265.00 VIDRIO TRANSPARENTE INCOLORO CRUDO MEDIODOBLE S/. 97.60


266.00 VOLQUETE DE 10 M3 S/. 27,001.04 S/. 27,001.04 S/. 27,001.04 S/. 27,001.04 S/. 20,000.00 S/. 7,001.04
267.00 VOLQUETE DE 4 M3 S/. 500.00 S/. 400.00 S/. 200.00 S/. 37.17
268.00 WINCHA S/. 2.16
269.00 WINCHE MANUAL S/. 24.26
270.00 YESO DE 28 Kg S/. 1.80
271.00 HERRAMIENTAS MANUALES S/. 16,167.97 S/. 16,167.97 S/. 16,167.97 S/. 16,167.97 S/. 10,000.00 S/. 6,167.97
117.00
118.00
119.00
120.00
121.00
122.00
123.00
124.00
125.00
126.00
127.00
128.00
129.00
130.00
131.00
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

132.00
133.00
134.00
135.00
136.00 COSTO DIRECTO
137.00 GASTOS GENERALES (10%)
138.00 UTILIDAD (5%) S/. 96,820.00
139.00 SUPERVISION DE OBRA (5%)
140.00 SUBTOTAL
141.00 IGV (19%)
142.00 COSTO TOTAL
143.00
144.00
CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

145.00
146.00 S/. 26,073.60
147.00
148.00
149.00
150.00 S/. 750.00
151.00
152.00 S/. 4,084.80
153.00 S/. 10,892.80
154.00 S/. 6,808.00
155.00 S/. 200.00

S/. 794,538.73 S/. 495,640.96 S/. 420,050.17 S/. 365,387.43


CALENDARIO DE ADQUISICION DE MATERIALES

OBRA:AMPLIACION Y MEJORAMIENTO SISTEMA DE AGUA POTABLE Y ALCANTARILLADO LOCALIDAD DE MOCHUMI


PROPIETARIO: MUNICIPALIDAD DISTRITAL DE MOCHUMI
VALOR REFERENCIAL: S/. 9,110,290.26
PLAZO DE EJECUCION DE OBRA: 240 DIAS CALENDARIO

MESES
Item Descripcin
MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07

S/. 79,453.87 S/. 49,564.10 S/. 42,005.02 S/. 36,538.74


S/. 39,726.94 S/. 24,782.05 S/. 21,002.51 S/. 18,269.37
S/. 39,726.94 S/. 24,782.05 S/. 21,002.51 S/. 18,269.37
S/. 953,446.47 S/. 594,769.15 S/. 504,060.20 S/. 438,464.92
S/. 181,154.83 S/. 113,006.14 S/. 95,771.44 S/. 83,308.33
S/. 1,134,601.30 S/. 707,775.29 S/. 599,831.64 S/. 521,773.25
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 2,800.00 S/. 5,600.00 5,600.00 S/. 70,956.00


S/. 0.00 S/. 1,500.00 1,500.00 S/. 79,791.79
S/. 139.63 139.63 S/. 45,576.89
S/. 800.00 S/. 6,563.60 6,563.60 S/. 26,899.80
S/. 72.68 72.68 S/. 461.83
S/. 530.25 S/. 143,230.25 143,230.25 S/. 1,284,460.43
S/. 1,000.00 S/. 17,069.61 17,069.81 S/. 64,391.03
S/. 19,526.75 S/. 264,526.75 264,526.75 S/. 800,493.25
S/. 22,710.91 22,710.91 S/. 118,244.96
S/. 69.12 142.31 S/. 54,597.26
S/. 4,816.00 S/. 9,632.00 630.00 S/. 31,275.14
S/. 118,943.52 S/. 1,429,443.52 1,429,443.52 S/. 4,288,809.98
S/. 12,074.75 12,074.65 S/. 36,626.90
S/. 720.00 720.00 S/. 2,771.02
S/. 67.20 67.20 S/. 685.30
S/. 32,742.84 32,742.84 S/. 98,519.64
S/. 3,500.00 S/. 39,035.07 39,035.07 S/. 160,438.03
S/. 28,959.11 28,959.11 S/. 122,942.78
S/. 179.58 179.58 S/. 10,563.84
S/. 17.05 17.05 S/. 99,659.39
S/. 80.34 80.34 S/. 2,118.02
S/. 12.18 S/. 5,109.95 5,109.95 S/. 16,343.25
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 169.13 169.13 S/. 1,615.39


S/. 220.90 220.90 S/. 729,213.74
S/. 54.61 54.61 S/. 728,479.35
S/. 363.68 S/. 8,763.68 8,763.68 S/. 28,593.04
S/. 9,172.72 S/. 79,172.72 79,172.72 S/. 241,634.30
S/. 410.24 410.84 S/. 54,228.90
S/. 1,925.00 1,925.00 S/. 24,883.66
S/. 2.52 2.52 S/. 13,343.06
S/. 0.80 0.80 S/. 8,063.40
S/. 1.64 1.64 S/. 1,871.92
S/. 1.54 1.54 S/. 582.62
S/. 10.81 10.81 S/. 4,901.43
S/. 0.63 0.63 S/. 336.79
S/. 89.60 89.60 S/. 1,072.10
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 20.58 20.58 S/. 283.74


S/. 3,910.00 3,910.00 S/. 461,923.00
S/. 68.10 68.10 S/. 72,398.30
S/. 50.00 50.00 S/. 393.00
S/. 138,561.28 138,561.28 S/. 415,921.00
S/. 6,514.56 6,514.56 S/. 19,790.18
S/. 2,706.16 S/. 152,706.16 152,706.16 S/. 458,455.68
S/. 3,233.42 3,233.42 S/. 73,142.80
S/. 129,690.02 129,690.02 S/. 406,322.21
S/. 2,878.20 2,878.20 S/. 51,372.60
S/. 348.66 348.66 S/. 2,321.23
S/. 123.75 123.75 S/. 844.25
S/. 123.75 123.75 S/. 30,575.25
S/. 9,000.00 9,000.00 S/. 336,576.25
S/. 128.84 128.84 S/. 466,784.29
S/. 24.00 24.00 S/. 1,312.14
S/. 20,000.00 20,000.00 S/. 211,858.06
S/. 5,000.00 5,000.00 S/. 22,551.80
S/. 250.00 250.00 S/. 15,156.00
S/. 45.00 45.00 S/. 105,346.00
S/. 37,500.00 37,500.00 S/. 474,980.87
S/. 40,050.00 40,050.00 S/. 122,037.99
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 150.00 150.00 S/. 443,248.03


S/. 270.00 270.00 S/. 1,027.70
S/. 29.38 29.38 S/. 1,024.14
S/. 169.97 169.97 S/. 3,277.27
S/. 65.06 65.06 S/. 509.18
S/. 4,940.00 4,940.00 S/. 17,565.82
S/. 25,800.00 25,800.00 S/. 102,040.06
S/. 167.56 167.56 S/. 1,037.87
S/. 2,703.04 2,703.04 S/. 8,382.57
S/. 48.00 48.00 S/. 2,707.00
S/. 34.92 34.92 S/. 11,248.76
S/. 4.60 4.60 S/. 5,638.80
S/. 10,697.78 10,697.78 S/. 33,939.34
S/. 14,000.00 14,000.00 S/. 43,007.00
S/. 650.00 650.00 S/. 6,063.00
S/. 588.68 588.68 S/. 3,651.08
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 5.00 5.00 S/. 3,111.17


S/. 9.12 9.12 S/. 329,669.40
S/. 70.00 70.00 S/. 19,018.39
S/. 9.26 9.26 S/. 560.78
S/. 27,573.00 27,573.00 S/. 82,967.40
S/. 16,716.90 16,716.90 S/. 50,535.70
S/. 227,176.67 227,176.67 S/. 681,798.41
S/. 34,872.20 94,872.20 S/. 165,327.60
S/. 27,255.00 27,255.00 S/. 121,153.00
S/. 2,892.24 2,892.24 S/. 9,091.88
S/. 144,482.98 144,482.98 S/. 434,948.95
S/. 520,307.59 520,307.59 S/. 1,573,595.77
S/. 16,892.00 16,892.00 S/. 54,278.00
S/. 14,059.50 14,059.50 S/. 46,669.50
S/. 19,467.00 19,467.00 S/. 58,652.80
S/. 1,238.58 1,238.58 S/. 3,969.74
S/. 9,000.00 9,000.00 S/. 27,248.70
S/. 97,500.00 97,500.00 S/. 295,447.00
S/. 216.09 216.09 S/. 913.82
S/. 171.50 171.50 S/. 11,431.23
S/. 163.17 163.17 S/. 60,739.51
S/. 19.80 19.80 S/. 60,910.58
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 66.50 66.50 S/. 209,155.50


S/. 5.60 5.60 S/. 1,421.80
S/. 26.25 26.25 S/. 2,979.86
S/. 8,800.00 8,800.00 S/. 58,161.42
S/. 1,050.00 1,050.00 S/. 52,211.50
S/. 1.60 1.60 S/. 68,589.50
S/. 2,250.00 2,250.00 S/. 192,771.84
S/. 27,900.00 27,900.00 S/. 97,959.70
S/. 5,480.00 5,480.00 S/. 29,348.96
S/. 45.00 45.00 S/. 24,666.48
S/. 150.00 150.00 S/. 1,387.00
S/. 1,756.49 1,756.49 S/. 6,087.47
S/. 454.71 454.71 S/. 111,788.13
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 97.60 97.60 S/. 20,969.41


S/. 135,005.21 135,005.21 S/. 405,641.63
S/. 1,137.17 1,137.17 S/. 71,178.51
S/. 2.16 2.16 S/. 18,295.36
S/. 24.26 24.26 S/. 3,041.78
S/. 1.80 1.80 S/. 7,025.40
S/. 80,839.86 80,839.86 S/. 244,140.58
S/. 26,297.22
S/. 1,944.79
S/. 1,286.12
S/. 4,197,176.79 S/. 4,199,655.36
S/. 357.37
S/. 5,231.87
S/. 6,959,028.05 S/. 6,959,346.05
S/. 10,624.00
S/. 7,847.00
S/. 169.20
S/. 337.00
S/. 353.00
S/. 6,267.00
S/. 819.55
S/. 1,471.34
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 387.00
S/. 46,978.42
S/. 90,134.00
S/. 66,117.51
S/. 192.46
S/. 5,994.50
S/. 96,820.00 S/. 411,434.66
S/. 0.00 S/. 3,810.43
S/. 0.00 S/. 158,007.95
S/. 0.00 S/. 155.25
S/. 0.00 S/. 160,342.00
S/. 0.00 S/. 137,843.00
S/. 0.00 S/. 3,059.43
ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 0.00 S/. 83,440.00


S/. 26,073.60 S/. 157,293.20
S/. 2,417.03 S/. 2,417.03 S/. 15,885.01
S/. 0.00 S/. 20,318.44
S/. 0.00 S/. 5,086.94
S/. 750.00 S/. 2,795.31
S/. 3,250.80 S/. 3,250.80 S/. 9,749.77
S/. 4,084.80 S/. 11,089.43
S/. 10,892.80 S/. 46,920.40
S/. 6,808.00 S/. 17,253.60
S/. 200.00 S/. 22,480.53

S/. 169,839.09 S/. 15,353,381.63 S/. 32,107,797.75


ADQUISICION DE MATERIALES

MESES
Parcial (S/.)
MES 08 SUMA PARCIAL

S/. 16,983.91 S/. 1,535,338.16 S/. 3,210,779.78


S/. 8,491.95 S/. 767,669.08 S/. 1,605,389.89
S/. 8,491.95 S/. 767,669.08 S/. 1,605,389.89
S/. 203,806.91 S/. 18,424,057.96 S/. 38,529,357.30
S/. 38,723.31 S/. 3,500,571.01 S/. 7,320,577.89
S/. 242,530.22 S/. 21,924,628.97 S/. 45,849,935.19