Академический Документы
Профессиональный Документы
Культура Документы
CONTENTS
2
API 570 - PIPING INSPECTOR COURSE
PROGRAM SCHEDULE
I DAY-l
Bench-mark Quiz
Introduction to API 570 certification
ASME B 31.3 Scope and applicability
~ervice/Fluid Classification
Joint Quality Factors
Allowable stresses
Design for Internal Pressure
Design of permanent blanks
Impact testing for Low temperature service
Acceptance of Impact test results
Welding requirements-Preheat Temperatures
PostWeldHeat Treatment
Hardness Testing after PWHT
Practice Questions on ASME B 31.3
I DAY-2
Scope
Pressure Temperature Ratings
Materials
Dimensions
System pressure Test
Practice Questions on ASME B 31.3 and B 16.5
I DAY-3.
I DAY-S.
I DAY-7.
API Authorized Piping Inspectors must have a broad knowledge base relating to maintenance, inspection, alteration and
repair of in-service metallic piping systems. The API Authorized Piping Inspector Certification Examination is designed
to determine if applicants have such knowledge.
The examination consists of two parts. The closed book part tests the candidate on knowledge and tasks requiring everyday
working knowledge of API Standard 570 and the applicable reference documents . The open book portion of the
examination requires the use of more detailed information that the inspector is expected to be able to find in the
documents, but would not normally be committed to memory.
A. API Publications:
( ... . :,
API Standard 570 - Inspection, Repair, Alteration, and Rerating ofIn-Service Piping Systems
API RP 571, Damage mechanisms Affecting Fixed equipment in the Refining Industry
API Recommended Practice 574 - Inspection Practices for Piping System Components
API Recommended Practice 578 - Material Verification Program for New and Existing Alloy Piping Systems
Note: Refer to the Publications Effectivity Sheet in the application package for a list of specific editions, addenda, and
supplements of the referenced publications that are effective for your examination date.
The following is the list of specific topics in which an API certified Piping Inspector should be knowledgeable.
A. Code calculation questions will be oriented toward existing in-service piping, not new piping. API Authorized Piping
Inspectors should be able to check and perform calculations relative to in-service deterioration, repairs, rerates, or
alterations, such as those included in the following eight categories.
Note: Candidates are expected to understand the SI units (metric system) and the US customary units (inches,
feet, PSI, etc.) and to use both system formulas.
The Inspector should be able to understand inspection data and determine the thickness measurement and visual
external inspection intervals.
The formulas for performing the above calculations and rules for setting the inspection intervals may be "closed-book"
during the exam.
The inspector should be able to determine the weld joint quality factor "Ej" of a longitudinal pipe weld joint. The
inspector should be able to determine:
Determining weld joint quality factor may be part of an internal pressure problem since the joint factor Ej is used in the
formulas for determining required thickness or internal design pressure.
a) The minimum required thickness or pressure design thickness of a straight pipe section for a intemal
pressure only (ASl\1E B31.3 ~ection 304.l.l and 304.1.2);
b) The minimum required thickness of a permanent blank for a given design pressure (ASME B31.3 Section
304.5.3);
c) The "MA WP" of corroded pipe, compensating for expected corrosion loss at the next inspection (API 570,
Par., 7.2)
The inspector should also be able to compensate for the corrosion allowance. (Add or subtract based on requirements
from the exam problem). .
4. PRESSURE TESTING
a) Demonstrate knowledge concerning hydrostatic leak testing (ASl\1E B31.3 Section 345.4)
b) Demonstrate knowledge concerning pneumatic leak testing (ASl\1E B31.3 Section 345.5)
c) Calculate a hydrostatic or pneumatic leak test pressure (ASl\1E B31.3 Sections 345.4, 345.5)
a) Determine the minimum metal temperature of a material, which is exempt from impact testing (ASME
B31.3, Section 323.2.2, Figure 323.2.2A & Table A-I).
b) Determine the minimum required charpy V-notch impact values of a given material. (ASME B31.3,
Section 323.3, Table 323.3.5)
The inspector should be able to determine which weld sizes require preheating and/or heat treatment. The inspector
also should be able to:
a) Determine what is the required or recommended preheat temperature (ASME B31.3, Section 330 & Table
330.1.1).
b) Determine the governing thickness, holding time, holding temperature, and maximum Brinell hardness for
heat treatment applications (ASME B31.3, Section 331 & Table 331.1.1).
7. THERMAL EXPANSION
The inspector should be able to determine the total thermal expansion of a material between temperatures (ASME
B31.3, Appendix C, Table C-l).
The inspector should be able to determine the minimum wall thickness and working pressure requirements for flanges.
The inspector should also be able to:
a) Determine the working pressure and minimum/maximum system hydrostatic test pressure for a flange of specified
material and temperature (ASME BI6.5, Par. 2.5 & Table lA & Tables 2-1.1 through 2-3.17).
b) Determine the minimum dimensions of a given flange (ASME B 16.5 Tables 7 through 22).
c) Determine maximum working pressure of a flange when given the design temperature, flange material and flange
class.
d) Determine maximum temperature of a flange when given the design pressure, flange material and flange class.
e) Determine most cost effective flange when given the design pressure, design temperature, and flange material.
B. The following are the ASME B31.3 code engineering requirements that are excluded from the examination and
that the API Authorized Piping Inspectors will NOT be expected to know for the purposes of certification testing.
1. 302 Design criteria - (All except for 302.3.3 Casting Quality Factor, E e, and 302.3.4, Weld Joint
Quality Factor, Ej )
2. 304.1.3 Straight Pipe Under External Pressure
3. 304.2 Curved and Mitered Segments of Pipe
4. 304.3 Branch Connections
5. 304.4 Closures
6. 304.5 Pressure Design of Flanges & Blanks (All except 304.5.3, Blanks)
7. 304.6 Reducers
8. 304.7 Pressure Design of Other Components
9. 315 Tubing Joints
10.316 Caulked Joints
11. 317 Soldered and Brazed Joints
12. 318 SpecialJoints
13.319.4 Flexibility Analysis
14.319.5 Reactions
15. 319.6 Calculation of Movements
16. 319.7 Means of Increasing Flexibility
17. 322.3 Instrument Piping
18. Chap. VII Nonmetallic Piping and Piping Lined With Nonmetals
19. Chap. VIII Piping for Category M Fluid Service
20. Chap. IX High Pressure Piping
21. App.B Stress Tables and Allowable Pressure Tables for Nonmetals
22. App. D Flexibility and Stress Intensification Factors
23. App.E Reference Standards
24. App. G Safeguarding
25. App. H Sample Calculations for Branch Reinforcement
26. App. J Nomenclature
27. App. K Allowable Stresses for High Pressure Piping
28. App. X Metallic Bellows Expansion Joints
29. App. Z Preparation of Technical Inquiries
The inspector should have the knowledge and skills required to review a Procedure Qualification Record and a Welding
Procedure Specification and to be able to determine the following:
a) Determine if procedure and qualification records are in compliance with applicable ASME Boiler and Pressure
Vessel Code and any additional requirements of API-570. The weld procedure review will include:
One Weld Procedure Specification (WPS); and
One Procedure Qualific(ltion Record (PQR). .
a) Determine if all required essentia:J and non-essential variables have been properly addressed. (Supplemental
essential variables will not be a part of the WPSIPQR)
b) Determine that the number and type of mechanical tests that are listed on PQR are the proper tests, and whether the
results are acceptable.
WELD PROCEDURE REVIEW MAY INCLUDE SMA W, GTAW, GMAW, OR SAW, WITH THE FOLLOWING
LIMITATIONS:
a) No more than one process will be included on a single WPS or PQR and the WPS to be reviewed will be supported
by a single PQR.
b) Filler metals will be limited to one-per-process for SMAW, GTAW, GMAW, or SAW
c) The PQR will be the supporting PQR for the WPS.
d) Base metals will be limited to PI, P3, P4, P5, and P8.
e) Dissimilar base metal joints, and dissimilar thicknesses of base metals will be excluded.
f) Special weld processes such as corrosion-resistant weld metal overlay, hard-facing overlay, and dissimilar metal
welds with buttering of ferritic member will be excluded.
g) For PI, P3; P4, and P5, for the purpose of the examination the lower transition temperature will be 1330 0 F and the
upper transformation temperature will be 1600ilp.
B. ASME B31.3
The inspector should be familiar with and understand the general rules for welding in ASME B31.3, Chapter V such as:
Note: "Editorial" and non-technical requirements for the welding subject matter, the candidate is to be tested on, are
excluded. This includes items such as the revision level of the WPS, company name, WPS number and date, and name
of testing lab. However, the API Authorized Piping Inspector should know that the PQR must be signed and dated.
D. The inspector shall be familiar with all the requirements of and information in API RP 577.
570_bokyev7-10-12_final.docx 5
III. NONDESTRUCTIVE EXAMINATION
NOTE: The examination will cover only the main body of each referenced Article, except as noted.
The inspector should be familiar with and understand the general rules for applying and using the liquid penetrant
method, including but not limited to the following:
G. Article 10, Leak Testing (Including Mandatory appendix 1 Bubble Test -Direct Pressure Technique):
The inspector should be familiar with and understand the general rules for applying and using the leak testing method
including, but not limited to the following:
H. Article 23, Ultrasonic Standards, Section SE-797 only - Standard practice for measuring thickness by manual ultrasonic
pulse-echo contact method:
The inspector should be familiar with and understand;
ASME B31.3: The inspector should be familiar with and understand the general rules for NDE (Chapter VI).
API Standard 570
The inspector should be familiar with and understand the general rules for NDE in API-570.
More information relative to each of the categories is contained in section "V. PRACTICAL KNOWLEDGE - SPECIFIC"
where each reference publication applicable for study for the examination has been listed with relevant topics that may
be covered on the examination.
API-570, Inspection, Repair, Alteration, and Rerating of In-Service Piping Systems - the entire document is
subject to testing
API RP 571, Damage mechanisms Affecting Fixed equipment in the Refining Industry
ATTN: Examination questions will be based on the following portions of the document only:
o Par. 3 - Definitions
o 4.2.7 - Brittle Fracture
o 4.2.9 - Thermal Fatigue
o 4.2.14 - ErosionlErosion Corrosion
o 4.2.16 - Mechanical Fatigue
o 4.2.17 - Vibration-Induced Fatigue
o 4.3.l - Galvanic Corrosion
o 4.3.2 - Atmospheric Corrosion
o 4.3.3 - Corrosion Under Insulation (CUI)
o 4.3.5 - Boiler Water Condensate Corrosion
o 4.3.7 - Flue Gas Dew Point Corrosion
o 4.3.8 - Microbiological Induced Corrosion (MlC)
o 4.3.9 - Soil Corrosion
o 4.4.2 - Sulfidation
o 4.5.l - Chloride Stress Corrosion Cracking (CI-SCC)
o 4.5.3 - Caustic Stress corrosion Cracking (Caustic Embrittlement)
o 5.1.3.1 - High Temperature Hydrogen Attack (HTTA)
API RP-574, Inspection of Piping, Tubing, Valves, and Fittings - the entire document is subject to testing
API RP 577, Welding Inspection and Metallurgy - the entire document is subject to testing
API Recommended Practice 578 - Material Verification program for New and Existing Alloy piping Systems
- the entire document is subject to testing
o Scope
o Pressure Temperature Ratings
o Markings
o Materials
o Dimensions
o Test
o Limiting Dimensions of Gaskets
o Methods for Establishing Pressure-Temperature Ratings
Please be advised that API and ASME documents and publications are copyrighted materials. Reproducing
these documents without API permission is illegal. If exam proctors determine that your documents are
illegal copies, the illegal documents will be confiscated from you prior to the exam.
API Standard 570, Piping Inspection Code: Inspection, Repair, Alteration, and Rerating ofIn-Service Piping
Systems, 3rd Edition, November 2009.
API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry,
2nd EDITION, April 2011.
ATTENTION: Only the following sections / mechanisms from RP 571 are included on the exam:
Section 3 - Terms (Definitions)
Mechanisms:
Par. 4.2.7 Brittle Fracture
4.2.9 Thermal Fatigue
4.2.14 ErosionlErosion Corrosion
4.2.16 Mechanical Fatigue
4.2 .17 Vibration-Induced Fatigue
4.3 .1 Galvanic Corrosion
4.3 .2 Atmospheric Corrosion
4.3 .3 Corrosion Under Insulation (CUI)
4.3.5 Boiler Water Condensate Corrosion
4.3 .7 Flue Gas Dew Point Corrosion
4.3.8 Microbiologically Induced Corrosion (MIC)
4.3.9 Soil Corrosion
4.4.2 Sulfidation
4.5 .1 Chloride Stress Corrosion Cracking (Cl-SCC)
4.5.3 Caustic Stress corrosion Cracking (Caustic Embrittlement)
5.1.3.1 High Temperature Hydrogen Attack (HTTA)
API Recommended Practice 574, Inspection Practices for Piping System Components, 3rd Edition, Nov. 2009.
API Recommended Practice 577, Welding Inspection and Metallurgy, 1st edition, October 2004.
(
API Recommended Practice 578, Material Verification Program for New and Existing Alloy Piping Systems, 2nd
Edition, March 2010.
American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, 2010 Edition, w/2011
Addendum, July 2011
i. Section V, Nondestructive Examination, Articles 1,2, 6, 7, 9, 10, and 23 (Section SE-797 only).
ii. Section IX, Welding and Brazing Qualifications, Welding only
Please ensure you obtain authorized documents from one of API's redistributors:
Techstreet: www.techstreet.com; Phone: 1-800-699-9277
ms Documents: www.global.ihs.com ; Phone: 1-800-854-7179
570- EffSheet2012-2013 - 072312
General Information and Qualification Requirements
1. Introduction
The American Petroleum Institute (API) initiated a Pressure Vessel Inspector Certification Program to
improve management control of process unit operation, repair, and maintenance; reduce the potential for
inspection delays resulting from regulatory requirements; and provide a continued high level of safety
through the use of inspectors specialized in process equipment. The program promotes self-regulation and
establishes a uniform national program that will assist state and local governments in pressure vessel
. regulations.
2. Qualification Requirements
Minimum
Education Experience
Required
ISkills
Supervision or performance of
BS or higher in
inspection activities as described in
engineering 11Y'" API 510
1. Successful completion of National Board of Boiler and Pressure Vessel Inspectors Commission
exam or Certificate of Competency.
Applicants who have successfully passed the written examination for the National Board of Boiler
and Pressure Vessel Inspectors are eligible for API 510 certification without taking API test. Please
fill out the application package for API 510 certification, including the Employment Reference Form,
and provide the appropriate documentation cited in the Application Form to confirm your
qualifications.
2. Written Examination under API Standard 510
If an applicant does not qualify under the National Board Commission, he/she must be certified by
written examination.
Examination Information
1. API examination consists of 150 multiple-choice questions with an open and closed book
sections. The examination is administered by participating members of the National
Board of Boiler and Pressure Vessel Inspectors and by the Professional Examination
Service (PES). Total length of examination is 8 hours. Individual jurisdictions may
charge a sitting fee to take the examination in their jurisdiction. Please contact the
jurisdiction you select for an exact amount. There is no additional sitting fee at the
locations where examination is administered by PES.
2. If you pass the examination, and all sections of your application are complete, you will be
certified and receive a wallet card and a certificate approximately 3 months after the
examination date.
3. API grants each applicant three consecutive attempts during the I8-month period to sit
and pass the test, starting with the first exam administration the applicant registers for. If
you fail the examination on your first attempt, you may retake it twice. If you fail to
appear for the test, it will still count as an official attempt.
4. If you do not pass the examination on the first attempt, you need to submit a $50.00
rescheduling fee. If you do not pass it on the second attempt, you must also submit an
updated Employment Reference form. If the candidate is unsuccessful on the third
attempt, a new application must be submitted with a new application fee.
5. Examination results will be mailed to you approximately 8 weeks after you have taken
the exam. DO NOT call API, PES, or your jurisdiction for examination results; these
results WILL NOT be given over the telephone.
o No.2 pencils;
o A non-programmable calculator (a calculator with only simple functions); .
o The applicable API and ASME reference publications. Please note: highlighting,
underlining, page tabs, and notes written in margins of the code books are
acceptable. However, loose pages inserted in the code books are not acceptable.
Note: API and ASME publications are copyrighted material. Photocopies of
( publications are not permitted at the exam;
o Your examination site confirmation letter;
o A picture ID (i.e. driver's license).
Step-by-step certification process
Please complete the following steps in order to get certified:
1. Check out minimum qualification requirements for your chosen certification program , and confirm
your eligibility for certification.
2. Review API's testing and certification policies.
3. Determine the most convenient location, test date and application deadline for your chosen
program .
4. Download the application for your program or request the application package to be sent to you via
mail.
5. Fill out your application completely.
6. Mail your application, supporting documentation and payment to API by the deadline indicated.
7. Download the Body of Knowledge for your chosen program .
8. Obtain necessary technical documents and publications. Effective publication dates are listed in the
application package.
9. Prepare for examination. Training programs are optional and not provided by API.
10. Take the examination.
510 examination sample items
SAMPLE API-510 Exam Items
The items below are examples of what an exam item might look like. If yOU have guestions about an item or
disagree with the answer. please email us at inspector@api.org and we will forward to one of our subject
matter experts.
Correct Answer: 4
Correct Answer: 3
Correct Answer: 1
Correct Answer: 4
E. A pressure vessel has been in service for 12 years and has a history
of corrosion over its service life. The original thickness was 1.9375
inches; the current thickness is 1.405 inches. What is the corrosion rate
for this vessel?
Correct Answer: 3
F. What can be done to extend the life of a vessel with a corroded area
in the shell plate 6 inches from the weld, a joint efficiency of less than 1,
and a corrosion thickness currently near the minimum required
thickness?
Correct Answer: 2
[M$fiI!Wi! ij f
Correct Answer: 2
1. The owner-user
2. The pressure vessel engineer
3. The National Board inspector
4. The vessel manufacturer
Correct Answer: 4
Correct Answer: 3
1. FCAW
2. GMAW
3.GTAW
4. SAW
API 570- PIPING INSPECTOR PREPARATORY COURSE
(VOLUME-I)
Part-2
INTRODUCTION
The APr Courses provide the participants the guidelines and methodology of
carrying out inspection of in-service" equipments. It also provides techniques
fI
for the assessment of the wear and tear of the equipments as well as to measure
de-gradation and damages caused to the process equipments due to the process
conditions.
COURSE OBJECTIVES
The majority of the classroom study will focus on the Body of Knowledge. The
goal, is to obtain a perfect score. Therefore please take your daily classroom
activity and assigned homework seriously.
The test is divided into two sections! a closed-book section and an open-book
section. The closed-book examination includes such questions which the
inspector is normally expected to know without referring the Codes! i.e.! the
questions are II awareness level questions. Whenever you find a very definitive
ll
information which is not short and crisp, (i.e., large paragraphs, several
,
(
No reference material of any kind will be permitted during the closed book
portion; some examining proctors may permit language translation dictionaries.
There will be some common knowledge mathematical questions on the practical
portion of the exam - remember to have your calculator available for this part of
the exam.
WEIGHTAGE OF MARKS
You have only a limited amount of time to study, so you need to invest your time
where you can get the MAXIMUM return! Approximately 50% of the test
questions are directly from API 570. So, that's your priority! For every hour spent
studying the other publications, spend 2 hours studying API 570.
There will be about 75 test questions directly from API 570 .This document is
about 40 pages, that averages almost 2 questions per page. The remaining 65
questions will come from the 600+ pages contained in the other documents.
That's only 1 question for every 10 pages.
Following distribution scheme will help the participant to decide how much
time he should spend for each document during preparation.
B. ASME Publications:
(VOLUME-I)
Part-3
1) GENERAL ASME Piping Codes give stipulations and guidelines for the
design, materials, manufacture and testing of pressure Piping.
These are issued by the American Society of Mechanical
Engineers, New York.
It is a LIVE code and is revised and updated periodically by
issuing new editions and addenda. It keeps pace with time and
is responsive to the questions from its users.
2) APPLICABILITY The editions and addenda become applicable after six months
from date of issue. However, for old contracts still in execution,
the old applicable edition and addenda are valid till the
completion of contract! up to start-up.
The codes specify the required N.D.T. and other inspections. They also specify accept /
reject criteria.
What is most important about the ASME Code is that they are user friendly, and keep
pace with changing technologies and new materials. No wonder - the users and the
Manufactures world over have adopted the ASME codes whole heartedly.
The participants are advised to refer the actual code clauses and extract information
from the latest codes applicable. ASME code is even evolving document and one has to
refer to the latest applicable edition and addenda.
The ASME 831 Code for Pressure Piping consists of a number of individually published
Sections.
Rules for each Section have been developed considering the need for application of
specific requirements for various types of pressure piping. Application considered for
e.ach Code Section inclu.de
831.1 Power piping: Piping typically found in electric power generating stations, in
industrial and institutional plants, geothermal heating systems, and central and district
heating and cooling systems;
831.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids:
transporting products which are predominately liquid between plants and terminals and
within terminals, pumping, and metering stations;
831.5 Refrigeration Piping: Piping for refrigerants and secondary coolants;
1.1 GENERAL
The Code sets forth engineering requirements deemed necessary for safe design
and construction of pressure piping.
1.2 SCOPE
Rules for the Process Piping Code Section B 31.3 have been developed
considering piping typically found in petroleum refineries; chemical,
pharmaceutical, textile, paper; semiconductor, and cryogenic plants; and related
processing plants storage facilities and terminals within the property limits. The
code is therefore often referred as Refineries and Plant piping code
1.3 DEFINITIONS
Normal Fluid Service Pertains to most piping covered by the Code and
includes piping not classified within the other fluid
services listed below [300.2].
Basic Quality Factors. The weld joint quality factors Ej tabulated in Table A-1 B
are basic factors for straight or spiral longitudinal welded joints for pressure-
containing components as shown in Table 302.3.4
Increased Quality Factors. Table 302.3.4 also indicates higher joint quality
factors which may be substituted for those in Table A-1 B for certain kinds of
welds if additional examination is performed beyond that required by the product
specification.
The factor shall be taken as 1.0 at temperatures of 510 deg C and below, and
0.5 at 815 deg C for all materials. The strength factor shall be interpolated for
intermediate values.
tm = t + c
For t < 0/6, the internal pressure design thickness for straight pipe shall
be not less than that calculated in accordance with Eq. (3a) :
PO
t =
2(SEW + PY)
To determine wall thickness and stiffening requirements for straight pipe under
external pressure, the procedure outlined in the BPV code, Section VIII Division
1, UG-28 through UG-30 shall be followed, using as the design length L, the
running centerline length between any two sections stiffened in accordance with
UG-29.
2.3.2 Blanks
The minimum required thickness of a permanent blank (representative
configurations shown in Fig. 304.5.3) shall be calculated in accordance
with Eq. (15)
=
.y
+C16SEW
where-
Generic Description
Materials considerations are specifically covered in 831.3 Chapter III, but there are also
material references in many other chapters. In fact, after stating the obvious in the first
sentences of Chapter III (that "limitations and required qualifications for materials are
based on their inherent properties") [323], 831.3 continues by referring back to 300(d) in
Chapter 1.
831.3 recognizes that material properties and behavior in service are temperature
dependent. A significant portion of b31.3 Chapter III deals with temperature limitations
for materials, in particular lower temperature limits where impact testing may apply. The
Code also imposes cautionary and restrictive temperature limits in Tables A-1 and A-2,
and requires designers to verify that materials are suitable for service throughout the
operating temperature range
Upper temperature limits for listed limited materials are the maximum temperatures for
which a stress value or rating is shown directly in or referenced by the Code. The Code
may also provide notes to the stress value tables, precautionary information in Appendix
F, and lor restrictions within the text of Code. For example, from Table A-1, the upper
temperature limit for ASTM A 106 Grade 8 pipe is 11 OOF even though there are two
notes pertaining to use of the material above 800F and 900F, respectively.
Lower temperature limits for materials are established as a means of controlling risk of
brittle fracture. Terms frequently used in lower temperature limit discussions include
notch sensitivity, impact testing, Charpy testing, and notch brittleness.
For must Code users, the basic question to be answered is: "Do I need to use impact
tested mater'ialsl,1,; answering the question can be complex and convoluted; however, the
basic steps to determining the answer are listed below and are discussed in detail in the
following paragraphs.
a. Select the design minimum temperature for the piping. This may involve process
engineering and or heat transfer specialists, and consideration of ambient
temperature effects.
b. Obtain the minimum permissible temperature for the proposed piping materials
according to 831.3 rules.
a. Follow the instructions of 831.3 to determine whether impact tests are required
(e.g., Table 323.2.2).
b. If impact tests are required, consult the additional requirements of 831.3 regarding
impact test methods and acceptance criteria.
For the convenience of users of the guide, several clauses and tables applicable to
831.3 impact testing requirement are listed in Table below.
Introduction
ASME 831.3 gives exhaustive requirements for the fabrication, assembly, and erection
of piping systems. These terms are defined by as follows.
c. Erection is the complete installation of a piping system in the locations and on the
supports designated by the engineering design, including any field assembly,
fabrication, examination, inspection, and testing of the system as required by the
code.
Welding
Although the qualification exemptions discussed above may be used, normally the
employer is required to conduct welding qualifications. 831.3 controls the details of
welding qualifications by referencing:
a. ASME Section IX[328.2.1 (a)],
b. Supplementary technical requirements
c. Requirements for qualification records
8y external reference to ASME Section IX, the 831.3 Code takes advantage of a general
working document governing welding qualifications for the entire ASME Code. Topics in
the following paragraphs, which address welding variables listed in ASME Section IX,
are indicated by the "QW" prefix to clause numbers.
Pre-heating:
a. 831.3 defines preheating as the application of heat to the base metal immediately
before or during a forming, welding, or cutting process [300.2]. This definition has a
slightly broader scope than the definition provided in ASME Section IX QW - 492.
831.3 also states that preheat is used, along with heat treatment to minimize the
detrimental effects of high temperature and severe thermal gradients inherent in
welding [330.1].
From a practical welding perspective, the method of heating is not generally an issue as
long as the correct preheat temperature is achieved, with the heat uniformly applied
throughout the full thickness and circumference of the joint. In some cases, the use of
oxyacetylene torches is prohibited by owner specifications due to the intensity of the
heat source and the risk of local damage to the base metal or weld metal if the heat is
concentrated at one location.
831.3 requires that the preheat temperature be checked to ensure that the temperature
specified by the WPS is obtained prior to and during welding
Heat treatment is used to minimize certain detrimental effects associated with welding,
bending and forming processes [331]. Depending on the nature of each process,
attendant high temperatures, severe thermal gradients, and/or severe metal forming.
operations (cold work) can result in dramatic loss of toughness, reduction of ductility,
increased hardness, and/or high residual stresses. In turn, these can lead to premature,
unexpected, and potentially catastrophic failures caused by brittle fracture, fatigue
cracking, stress corrosion cracking, and/or hydrogen embrittlement.
831.3 provides basic heat treatment practices suitable for most welding, bending, and
forming operations. One should confirm that proposed heat treatment cycles are capable
of satisfying maximum hardness restrictions. Confirmation would
Heat treatments listed in 831.3 table 331.1.1 are best described as stress relieving heat
treatments, since the primary purpose of the treatment is the reduction of residual
stresses due to welding, forming, or bending operations. Such treatment may also result
in improved ductility, lower hardness (note that 831.3 does impose some hardness
restrictions), better toughness, and reduced distortion during subsequent machining
operations ..
831.3 does not impose limitations on heating equipment and methods. It only indicates
that the heating method must provide the required metal temperature, metal temperature
uniformity, and temperature control, and then lists methods which may be used for
heating including furnace, local flame heating, electric resistance, electric induction, and
exothermic chemical reaction [ 331.1.4].
Heating methods used for heat treatment may be classified in terms of the facility used
for heat-treating and the energy source. Facilities can be discussed in terms of local heat
treatment and furnace heat treatment.
a. Local heat treatment involves the heating of a small band of metal. Normally the
band being heat-treated is stationary, but in some manufacturing operations, the
band moves. Examples of moving bands include in-line-tempering operations used
during manufacture of quenched and tempered pipe and local heating operations
used in the manufacture of induction bends.
b. Furnace heat treatment generally involves placing the item to be heat treated inside
a permanent furnace operated by a fabrication shop or commercial heat treater.
However, it is possible to construct temporary heat treatment facilities (e.g., at the
job site), which may range from simple ad hoc insulated box constructions to
complex portable furnaces.
831.3 does not impose restrictions on heating and cooling rates [331.1.4]. ASME .
Section VIII, Division 1, UCS-56 requirements are frequently applied, but there are
causes where insulation and coils are ripped off immediately after the soak period. In the
stress relieving business, time is money, especially if the heat treater is working by the
weld or lump sum. So, if heating and cooling rates need to be controlled, it should be
stated in specifications or other contract documents.
Hardness Tests [331.1.4]
Hardness tests of production welds and of hot bent and hot-formed piping are intended
to verify satisfactory heat treatment. Hardness limits apply to the weld and to the heat
affected zone (HAZ) tested as close as practicable to the edge of the weld.
a. Where a hardness limit is specified in Table 331.1.1, at least 10% of welds, hot
bends, and hot formed components in each furnace heat treated batch and 100% of
those locally heat treated shall be tested.
b. When dissimilar metals are joined by welding, the hardness limits specified for the
. base and welding materials in Table 331.1.1 shall be met for each material.
The code does not discuss many of the technical details necessary to give an accurate
and representative appraisal of production weld harness. Consequently, owner
specifications are recommended for guidance on applying this simple but often misused
and abused test method. Owner specifications should consider the size of hardness
indentations relative to the size of weld zones to be measured, surface preparation of
. the weld, methods for locating the zones of interest, and training requirements for
hardness testing personnel.
CHAPTER - 6 INSPECTION, TESTING
Inspection of Piping:
The code distinguishes between Examination (see para. 341) and Inspection. Inspection
applies to functions performed for the owner, by the owner's inspector or the inspector
delegate. References in this code to the "Inspector" are to the owner's inspector or the
inspector delegate.
It is owner's responsibility, exercised through the inspector, to verify that all required
examinations and testing have been completed and to inspect the piping to the extent
necessary to his satisfaction to confirm all applicable examinations required by code and
by the engineering Design.
The owner's Inspector shall be designated by the owner and shall be the owner, an
employee of the owner, an employee of an engineering or scientific organization,
or of a recognized insurance or inspection company acting as the owner's agent
The owner's Inspector shall have not less than 10 years experience in the design,
fabrication, or inspection of industrial pressure piping
It is a right of the inspector delegated by code that the inspector shall have access to
any place where work concerned with piping fabrication, installation is being performed.
This includes manufactures, fabrications, assembly, erection, examination and testing of
piping. He shall have right to audit any examination, examination methods, qualification
of personnel carrying examinations and review of records.
Inspector shall be the owner, employee of the owner, employee of the inspection
organization. Inspector shall not represent nor be the employee of piping manufacturer,
fabricator or erector.
Inspector shall have engineering degree and at least 5 years relevant experience.
Examination
Examination Requirements
Code has specified various minimum required examinations to be carried out for
checking of the quality achieved. Code also specifies acceptance criteria for all these
various examination results. Code suggests the remedies over the defects find outs and
specifies the repairs and re-examinations (double of the originally specified) of that
repaired component. Code has specified very systematic approach to carry out the
examinations so as to maintain the minimum expected quality.
Other examinations:
Not less than 5% of circumferential butt and miter groove weld shall be examined fully by
random radiography in accordance with para 344.5 or by random ultrasonic
examinations in accordance with para 344.6. Weld shall be selected in such a way that
each welder's production welding is covered. They shall be selected to maximize
coverage of intersections with the longitudinal joints. At least 38 mm (1 ~ in) of
longitudinal weld shall be examined.
After completion of construction in all aspects and before first run (commissioning) it is
mandatory to test the systems for design conditions. Code has made pressure test
mandatory for all piping installations with water. In case hydrates is not possible, one
can opt for pneumatic test.
Code has recommended test pressure as 1.5 times design pressure and also suggested
to use temperature correction factor. For pneumatic test the test pressu(e factor is 1.1
and temperature correction factor is optional for owner.
System shall be tested at least for 10 minutes at test temperature. No evidence of any
kind of leak shall be noticed. During pneumatic test code identifies the hazard involved in
the energy stored system and has suggested carrying out test stage wise.
The record of all tests, examinations and inspection shall be maintain for at least for five
years.
API 570- PIPING INSPECTOR PREPARATORY COURSE
(VOLUME-I)
Part-4
1
PIPING INSPECTION AS PER API 570.
1. INTRODUCTION TO API-570
1.1 SCOPE
1.1.1 Coverage
API 570 covers inspection, repair, alteration, and rerating procedures for metallic piping
systems that have been in service.
Repair ; The work necessary to restore a piping system to a condition suitable for safe
operation at the design condition.
1.1.2 LIMITATIONS:
API 570 shall not be used as a substitute for the original construction requirements
governing a piping system before it is placed in service.
a. API 570 applies to piping systems for process fluids, hydrocarbons, and
similar flammable or toxic fluid services.
The fluid services and classes of piping systems listed below are excluded from the specific
requirements of API 570 but may be included at the owner's or user's (owner/user's) option.
2
2. DEFINITIONS
The code, code section, or other recognized and generally accepted engineering
standard or practice to which the piping system was built or which is deemed by the
owner or user or the piping engineer to be most appropriate for the situation, including
but not limited to the latest edition of ASME B 31.3
a. The inspection organization of the jurisdiction in which the piping system is used.
Instrument and machinery piping, typically small-bore secondary process piping that can
be isolated from primary piping systems. Examples include flush lines, seal oil lines,
analyzer lines, balance lines, buffer gas lines, drains and vents.
2.5 CUI:
3
Components of a piping system that normally have no significant flow. Examples
include the following : blanked branches, lines with normally closed block valves, lines
with one end blanked, pressurized dummy support legs, stagnant control valve bypass
piping, spare pump piping, etc
2.7 DEFECT:
2.8 EXAMINER:
A point in the repair or alteration process beyond which work may not proceed until the
required inspection has been performed and documented.
2.10 IMPERFECTIONS:
Flaws or other discontinuities noted during inspection that may be subject to acceptance
criteria during an engineering and inspection analysis.
2.11 INDICATION:
Locations where relatively small quantities of materials are injected into process streams
to control chemistry or other process variables. Injection points do not include locations
where two process streams join.
2.13 IN-SERVICE:
Refers to piping systems that have been placed in operation, as opposed to new
construction prior to being placed in service.
2.14 INSPECTOR:
4
2.16 MAXIMUM ALLOWABLE WORKING PRESSURE (MAWP)
The maximum internal pressure permitted in the piping system for continued operation at
the most severe condition of coincident internal or external pressure and temperature
(maximum and minimum) expected during service. It is the same as the design
pressure, as defined in ASME B 31.3 and other code sections, and is subject to the
same rules relating to allowances for variations of pressure or temperature or both.
2.17 ON-STREAM:
A section of piping that has all points exposed to an environment of similar corrosivity
and that is of similar design conditions and construction material.
Process piping in normal, active service that cannot be valved off or, if it were valved off,
would significantly affect unit operability. Primary process piping normally includes all
process piping greater than NPS 2.
a. An owner or user of piping systems who repairs or alters his or her own
equipment in accordance with API 570.
b. A contractor whose qualifications are acceptable to the owner or user of piping
systems and who make~JepairsQralterations,in accordance with API 570. .
c. One who is authorized by, acceptable to, or otherwise not prohibited by the
jurisdiction and who makes repairs in accordance with API 570.
Small-bore (less than or equal to NPS 2) process piping downstream of normally closed
block valves.
An area in which external corrosion may occur on partially buried pipe. The zone of the
corrosion will vary depending on factors such as moisture, oxygen content of the soil,
and operating temperature. The zone generally is considered to be from 12 inches (305
5
mm) below to 6 inches (150 mm) above the soil surface. Pipe running parallel with the
soil surface that contacts the soil is included. .
2.24 SPOOL:
Repairs made to piping systems in order to restore sufficient integrity to continue safe
operation until permanent repairs can be scheduled and accomplished within a time
period acceptable to the inspector or piping engineer.
An area defined by a circle having a diameter not greater than 2 inches (50 mm) for a
line diameter not exceeding 10 inches (250 mm) or not greater than 3 inches (75 mm)
for larger lines. Thickness readings may be averaged within this area. A test point shall
be within a thickness measurement location.
2.29 WFMT:
6
3. INSPECTION AND TESTING PRACTICES
Expected type of degradation. ely areas affected i.e. identifying the most prone areas
and possible locations, Measurement of degradation i.e. quantifying the amount of
degradation.
2. PREPARATION:
Prior to actual inspection proper preparation and safety precautions are essential
particularly if components are to be inspected internally. This essentially involves
Isolating and segregating the piping system, installing blanks (blids) etc.
Removal of harmful liquids, gases, vapors, flushing out and purging to bring down
residual content to safe leveJs.
Obtain suitable permissions to work i.e. cold work permit (CWP), Hotwork Permits
(HWP) etc.
Each owner! user should provide specific attention to the need for inspection of piping
system that are susceptible to the following specific types & areas of deterioration:
a. Injection points.
b. Oeadlegs.
c. Corrosion under insulation ( CUI ).
d. Soil-to-air (S!A ) interfaces.
7
e. Services specific & localized corrosion.
f. Erosion &c orrosion/erosion.
g. Environmental cracking.
h. Corrosion beneath linings & deposits.
i. Fatigue cracking.
j. Creep cracking.
k. Brittle fracture.
I. Freeze damage.
3.1 Injection Points: Injection points are sometimes subject to accelerated or localized
corrosion.
When designating an injection point circuit for the purposes of inspection, the
recommended upstream limit of the injection point circuit is a minimum of 12 inches
(300) or three pipe diameters upstream of the injection point, whichever is greater. The
recommended downstream limit of the injection point circuit is the seconed change in
flow direction past the injection point, or 25 feet (7.6 m) beyond the first change in flow
direction, whichever is less. In some cases, it may be more appropriate to extend this
circuit to the next piece of pressure equipment.
The preferred methods of inspecting injection points are radiography and/or ultrasonics,
as appropriate, to establish the minimum thickness at each TML.
3.2 Oeadlegs : The corrosion rate in dead legs can vary significantly from the adjacent active
piping. The inspector should monitor wall thickness on selected dead legs, including both
the stagnant end and at the connection to an active line. In hot piping systems, the high-
point area may corrode due to convective currents set up in the deadlegs. Consideration
should be given to removing dead legs that serve no further process purpose.
3.3. Corrosion Under Insulation : External inspection of insulated piping systems should
include a review of the integrity of the insulation system for conditions that cold lead to
corrosion under insulation (CUI) and for signs of ongoing CUI. Sources of moisture may
include rain, water leaks, condensation and deluge systems. The most common forms of
CUI are localized corrosion of carbon steel and chloride stress corrosion cracking of
austenitic stainless steels.
3.4 Insulated Piping Systems Susceptible to CUI : Certain areas and types of piping
systems are potentially more susceptible to CUI, including the following:
8
e. Carbon steel piping systems, including those insulated for personnel protection,
operation between 25 F- 250 F (-4C-120 C).
f. Carbon steel piping systems that normally operate in-service above 250 F
(120C) but are in intermittent service.
g. Deadlegs and attachments that protrude from insulated piping and operate at a
different temperature than the operating temperature of the active line.
h. Austenitic stainless steel piping systems operating 1500 F- 400 F (65C-204C).
(These systems are susceptible to chloride cracking. )
i. Vibrating piping systems that have a tendency to inflict damage to insulation
jacketing providing a path for water ingress.
j. Steam traced piping systems that may experience tracing leaks, especially at
tubing fitting beneath the insulation.
k. Piping systems with deteriorated coatings and/or wrappings.
3.5 Soil-to-Air Interface: Soil-to-air (S/A) interfaces for buried piping without adequate
cathodic protection shall be included in scheduled external piping inspections.)
Thickness measurements and excavation may be required to assess whether the corrosion
is localized to the S/A interface or extends to the buried system.
Thickness readings at S/A interfaces may expose the metal and accelerate corrosion if
coatings and wrappings are not properly restored.
3.7 Service Specific & Localized Corrosion: Examples of Service Specific & Localized
Corrosion are::
Mixed grades of carbon steel piping in hot corrosive oil service (450 deg F [230
deg]C) or higher temperature & sulfur content in the oil greater than 0.5 percent by
weight.
Non silicon kiled steel pipe, such as A-53 & API 5L, may corrode at higher rates than
does silicon killed steel pipe, such as A-106 especially in high -temperature sulfidic
environments.
3.6 Erosion & corrosionl erosion: Erosion can be defined as the removal of surface
material by the action of numerous individual impacts of solid or liquid particles. It can
be characterized by grooves, rounded holes, waves, & vallys in a directional pattern.
Erosion usually occurs in areas of turbulent flow, such as at change of direction in a
piping system or downstream of control valves where vaporization may take place.
3.7 Erosion damage is usually increased in streams with large quantities of solid or liquid
particles flowing at high velocities. A combination of corrosion & erosion (
corrosion/erosion )results in significantly greater metal loss than can be expected from
corrosion occurs at high velocity & high turbulence areas.
9
3.9 Environmental Cracking: Piping system construction materials are normally selected
to resist the various forms of stress corrosion cracking (SCC). However, some piping
system may be susceptible to environmental cracking due to upset process conditions,
CUI unanticipated condensation, or exposure to wet hydrogen sulfide or carbonates.
10
4. SPECIFIC AREAS OF INSPECTION
The linings should be inspected for separation, breaks, holes, and blisters. If any of
these conditions are noted, it may be necessary to remove portions of the internal lining
to investigate the effectiveness of the lining and the. condition of the metal piping
beneath the lining.
Corrosion beneath refractory linings can result in separation and bulging of the
refractory. If bulging or separation of the refractory lining is detected, portions of the
refractory may be removed to permit inspection of the piping beneath the refractory.
Fatigue cracking of piping systems may result from excessive cyclic stresses that are
often well below the static yield strength of the material. Excessive piping system
vibration (such as machine or flow-induced vibrations) also can cause high-cycle fatigue
damage.
4:2.12 CREEPCRAGKING :
Carbon low-alloy, and other ferritic steels may be susceptible to brittle failure at or below
ambient temperatures. Brittle fracture usually is not a concern with relatively thinwall
piping. Most brittle fractures have occurred on the first application of a particular stress
11
level (that is, the first hydrotest or overload) unless critical defects are introduced during
service. The potential for a brittle failure shall be considered when rehydrotesting.
At subfreezing temperatures, water and aqueous solutions in piping systems may freeze
and cause failure because of the expansion of these materials. After unexpectedly
severe freezing weather, it is important to check for freeze damage to exposed piping
components before the system thaws. If rupture has occurred, leakage may be
temporarily prevented by the frozen fluid. Low points, riplegs, and deadlegs of piping
systems containing water should be carefully examined for damage.
Internal visual inspections are not normally performed on piping. When possible and
practical, internal visual inspections may be scheduled for systems such as large-
diameter transfer lines, ducts, or other large-diameter piping systems. Such inspections
are similar in nature to pressure vessel inspections and should be conducted with
methods and procedures similar to those outlined in API 510.
12
4.4 THICKNESS MEASUREMENT LOCATIONS :
Thickness measurement locations (TML's) are specific areas along the piping circuit where
inspections are to be made. The nature of the TML varies according to its location in the
piping system. The selection of TML's shall consider the potential for localized corrosion
and service-specific corrosion as described in 5.3
Ultrasonic thickness measuring instruments usually are the most accurate mean for
obtaining thickness measurements on installed pipe larger than NPS 1. Radiographic
profile techniques are preferred for pipe diameters of NPS 1 and smaller. Radiographic
profile techniques may be used for locating areas to be measured, particularly in insulted
systems or where non-uniform or localized corrosion is suspected.
When piping systems are out of service, thickness measurements may be taken through
openings using calipers. Calipers are useful in determining approximate thicknesses of
castings, forgings, and valve bodies, as well as pit depth approximations from CUI on
pipe.
Pit depth measuring devices also may be used to determine the depth of localized metal
loss.
Pressure tests are not normally conducted as part of a routine inspection. Exceptions to
this include requirements of local jurisdictions, after welded alterations or when specified
by the inspector or piping engineer. When they are conducted, pressure tests shall be
performed in accordance with the requirements of ASME B 31.3
Upon completion of the pressure test, pressure relief devices of the proper settings and
other appurtenanees removed or made iiloperable during the pressure test shall be
reinstalled or reactivated.
During repairs or alterations of low- to high alloy piping systems, the inspector shall
verify the installation of the correct new materials. At the discretion of the owner/user or
the inspector, this verification can be either by 100 percent checking or testing in certain
critical situations or by sampling a percentage of the materials.
Normally, thickness measurements are not routinely taken on valves in piping circuits.
The body of a valve is normally thicker than other piping components for design reasons.
13
Critical check valves should be visually and internally inspected to ensure that they will
stop flow reversals.
a. Checking to insure that the flapper is free to move, as required, without excessive
looseness from wear.
b. The flapper stop should not have excessive wear. This will minimize the likelihood
that the flapper will move past the top dead central position and remain in an open
position when the check valve is mounted in a vertical position.
c. The flapper nut should be secured to the flapper bolt to avoid backing off in service.
Inspection for piping weld quality is normally accomplished as a part of the requirements
for new construction, repairs, or alterations.
Fasteners should extend completely through their nuts. Any fastener failing to do so is
considered acceptably engaged if the lack of complete engagement is not more than
one thread.
14
5. FREQUENCY AND EXTENT OF INSPECTION
5.1 GENERAL:
The frequency and extent of inspection piping circuits depend on the forms of
degradation that can affect the piping and consequence of a piping failure.
5.2.1 CLASS 1 :
Services with the heist potential of resulting in an immediate emergency if a leak were to
occur are in Class 1. Such an emergency may be safety or environmental in nature.
Examples of Class1 piping include, following :
a. Pressurized services that may rapidly vaporize during release, creating vapors
that may collect and form an explosive mixture, such as C2, C3 and C4
( LPG) streams.
b. Hydrogen sulfide (greater than 3 percent weight) in a gaseous stream.
c. Anhydrous hydrogen chloride.
d. Hydrofluoric acid.
e. Piping over or adjacent to water and piping over public through ways.
5.2.2 CLASS 2 :
Services not included in other classes are in Class 2. This classification includes the
majority of unit process piping and selected off-site piping. Typical examples of these
services include those containing the following:
5.2.3 CLASS 3 :
Services that are flammable but do not significantly vaporize when they leak and are not
located in high activity areas are in Class 3.
15
5.3 INSPECTION INTERVALS :
External visual inspections, including inspections for corrosion under inSUlation (CUI),
should be conducted at maximum intervals listed in Table 6-1 to evaluate external
condition of paint and coating systems, to check for external corrosion, and to check for
other forms of deterioration.
Piping systems that are known to have a remaining life of over 10 years or that are
adequately protected against external corrosion need not be included for the NDE
inspection recommended in Table 6-2
Small bore piping (SBP) that is primary process piping should be inspected in
accordance with all the requirements of this document. .
16
TABLE 6-1 RECOMMENDED MAXIMUM INSPECTION INTERVALS
17
6. INSPECTION DATA EVALUATION
The dreaming life of the piping system shall be calculated from the following formula
tactual _ t minimum
Remaining life (years) = -----------------------------
Corrosion rate
[inches (mm) per year]
where:
t minimum = the minimum required thickness, in inches (mm) for the limiting
section or zone.
The long term (L.T.) corrosion rate of piping circuits shall be calculated from the
following formula :
The short term (S.T.) corrosion rate of piping circuits shall be calculated from the
following formula:
Long term and short term corrosion rates should be compared to see which results in the
shortest remaining life.
Corrosion rates shall be calculated on either a short term or a long term basis. For the
short term calculation, readings from the two most recent inspections shall be used. For
the long term calculation, wall thicknesses from the most recent and initial (or nominal)
inspections shall be used. In most cases, the higher of these two rates should be used
to estimate remaining life and so set the next inspection interval.
If calculations indicate that an inaccurate rate of corrosion has been assumed, the rate
to be used for the next period shall be adjusted to agree with the actual rate found.
18
6.2 MAXIMUM ALLOWABLE DWORKING PRESSURE DETERMINATION :
a. The maximum allowable working pressure (MAWP) for the continued use of
piping systems shall be established using the applicable code.
For unknown materials, computations may be made assuming the lowest grade material
and joint efficiency in the applicable code. When the MAWP is recalculated, the wall
thickness used in these computations shall be the actual thickness as determined by
inspection (see definition) minus twice the estimated corrosion loss before the date of
the next inspection.
The minimum required pipe wall thickness, or retirement thickness, shall be based on
pressure, mechanical, and structural considerations using the appropriate design
formulas and code allowable stress.
The owner/user shall maintain appropriate permanent and progressive records of each
piping system covered by API 570. These records shall contain pertinent data such as
piping system service; classification; identification numbers; inspection intervals; and
documents necessary to record the name of the individual performing the testing, the
date, the types of testing, the results of thickness measurements and other tests,
inspections, repairs (temporary and permanent), alterations, or rerating.
19
7. REPAIRS, ALTERATIONS, RERATING
The principles of ASME 831.3 or the code to which the piping system was built shall be
followed.
7.1.1 AUTHORIZATION
All repair and alteration work must be done by a repair organization as defined in
Section 3 and must be authorized by the inspector prior to its commencement.
Authorization for alteration work to a piping system may not be given without prior
consultation with, and approval by, the piping engineer. The inspector will designate any
inspection hold points required during the repair or alteration sequence. The inspector
may give prior general authorization for limited or routine repairs and procedures,
provided the inspector is satisfied with the competency of the repair organization.
7.1.2 APPROVAL:
Welding repairs of cracks that occurred in service should not be attempted without prior
consultation with the piping engineer in order to identify and correct the cause of the
cracking. Examples are cracks suspected of being caused by vibration, thermal cycling,
thermal expansion problems, and environmental cracking.
The inspector shall approve all repair and alteration work at designated hold points and
after the repairs and alterations have been satisfactorily completed in accordance with
the requirements of API 570
For temporary repairs, including on steam, a full encirclement welded split sleeve or
box type enclosure designed by the piping engineer may be applied over the damaged
or corroded area. Longitudinal cracks shall not be repaired in this manner unless the
piping engineer has determined that cracks would not be expected to propagate from
under the sleeve. In some cases, the piping engineer will need to consult with a
fracture analyst.
If the repair area is localized (for example, pitting or pinholes) and the specified
minimum yield strength (SMYS) of the pipe is not more than 40,000 psig (275,800
kPa), a temporary repair may be made by fillet welding a properly designed split
coupling or plate patch over the pitted area (See 7.2.3 for design considerations and
Appendix C for an example) The material for the repair shall match the base metal
unless approved by the piping engineer.
20
For minor leaks, properly designed enclosures may be welded over the leak while the
piping system is in service, provided the inspector is satisfied that adequate thickness
remains in the vicinity of the weld and the piping component can withstand welding
without the likelihood of further material damage, such as form caustic service.
Temporary repairs should be removed and replaced with a suitable permanent repair
at the next available maintenance opportunity. Temporary repairs may remain in place
for a longer period of time only if approved and documented by the piping engineer.
Corroded areas may be restored with weld metal deposited din accordance with 7.2
Surface irregularities and contamination shall be removed before welding. Appropriate
NDE methods shall be applied after completion of the weld.
If it is feasible to take the piping system out of service, the defective area may be
removed by cutting out a cylindrical section and replacing it with a piping component that
meets the applicable code.
Insert patches (flush patches) may be used to repair damaged or corroded areas if the
following requirements are met :
All repair and alteration welding shall be done in accordance with the principles of ASME
B 31.3 or the code to which the piping system was built.
21
7.2.2.1 PREHEATING:
Piping systems constructed of other steel initially requIring PWHT normally are
postweld heat treated if alterations or repairs involving pressure retaining welding are
performed. The use of the preheat alternative requires consultation with the piping
engineer who should consider the potential for environmental cracking and whether
the welding procedure will provide adequate toughness. Examples of situations where
this alternative could be considered include seal welds, weld metal buildup of thin
area, and welding support clips.
7.2.3 DESIGN:
7.2.4 MATERIALS:
The materials used in making repairs or alterations shall be of known weldable quality,
shall conform to the applicable code, and shall be compatible with the original materials.
For material verification requirements see 4.8
Acceptance of a welded repair or alteration shall include NDE in accordance with the
applicable code and the owner/user's specification, unless otherwise specified in API
570
After welding is completed, pressure test in accordance with 4.7 shall be performed if
practical and deemed necessary by the inspector. Pressure tests are normally required
after alterations and major repairs. When a pressure test is not necessary or practical,
NDE shall be utilized in lieu of a pressure test. Substituting special procedures for a
pressure test after an alteration or repair may b e done only after consultation with the
inspector and the piping engineer.
When it is not practical to perform a pressure test of a final closure weld that joins a new
or replacement section of piping to an existing system, all of the following requirements
shall be satisfied :
22
a. Any final closure butt-weld shall be of 100 percent radiographic quality;
OR angle beam ultrasonics flaw detection may be used, provided the appropriate
acceptance criteria have been established.
b. MT or PT shall be performed on the root pass and the completed weld for
butt-welds and on the completed weld for fillet welds.
7.3 RERATING
Rerating piping systems by changing the temperature rating or the MAWP may be
done only after all of the following requirements have been met :
b. All ratings shall be established in accordance with the requirements of the code to
which the piping system was built or by computation using the appropriate
methods in the latest edition of the applicable code.
c. Current inspection records verify that th~ piping system is satisfactory for the
proposed service conditions and that the appropriate corrosion allowance is
provided.
d. Rerated piping systems shall be leak tested in accordance with the code to which
the piping system was built or the latest edition of the applicable code for the new
service conditions, unless documented records indicate a previous leak test was
performed at greater than or equal to the test pressure for the new condition.
c. The piping system is checked to affirm that the required pressure relieving devices
are present, are set at the appropriate pressure, and have the appropriate
capacity at set pressure.
g. All piping components in the system (such as valves, flanges, bolts, gaskets,
packing, and expansion joints) are adequate for the new combination of pressure
and temperature.
23
8. INSPECTION OF BURIED PIPING
Inspection of buried process piping is different from other process piping inspection because
significant external deterioration can be caused by corrosive soil conditions.
Since the inspection is hindered by the inaccessibility of the affected areas of the piping, the
inspection of buried piping is treated in a separate section of API 570.
Indications of leaks in buried piping may include a change in the surface contour of the
ground, discoloration of the soil, softening of paving asphalt, pool formation, bubbling
water puddles, or noticeable odor. Surveying the route of buried piping is one method of
identifying problem areas.
The close interval potential survey performed at ground level over the buried pipe can be
used to locate active corrosion points on the pipe's surface.
Corrosion cells can form on both bare and coated pipe where the bare steel contacts the
soil. Since the potential at the area of corrosion will be measurably different from an
adjacent area on the pipe, the location of the corrosion activity can be determined by this
survey technique.
The pipe coating holiday survey can be used to locate coating defects on buried coated
pipes, and it can be used on newly constructed pipe systems to ensure that the coating
is intact and holiday free. More often it is used to evaluate coating serviceability for
buried piping that has been in service for an extended period of time.
Corrosion of bare or poorly coated piping is often caused by a mixture of different soils in
contact with the pipe surface. The corrosiveness of the soils can be determined by a
measurement of the soil resistivity.
Lower levels of resistivity are relatively more corrosive than higher levels, especially in
areas where the pipe is exposed to significant changers in soil resistivity.
24
8.1.6 Inspection Methods :
Several inspection methods are available. Some methods can indicate the external or
wall condition of the piping, whereas other methods indicate only the internal condition.
Examples are as follows :
o Video cameras. Television cameras are available that cana be inserted into
the piping. These cameras may provide visual inspection information on the
internal conditionof the line.
o Excavation. In many cases, the only available inspection method that can be
performed is unearthing the piping in order to visually inspect the external
condition of the piping and to evaluate its thickness and internal condition.
The owner/ user should, at approximately 6 month intervals survey the surface
conditions on and adjacent to each pipeline path.
A close interval potential survey on a cathodically protected line may be used to verify
that the buried piping has a protective potential throughout its length. For poorly coated
pipes where cathodic protection potentials are inconsistent, the survey may be
conducted at 5 year intervals for verification of continuous corrosion control.
The frequency of pipe coating holiday surveys is usually based on indications that other
forms of corrosion control are ineffective. For example, on a coated pipe where there is
gradual loss of cathodic protection potentials or an external corrosion leak occurs at a
coating defect, a pipe coating holiday survey may be used to evaluate the coating.
For piping buried in lengths greater than 100 feet ( 30 m ) and not cathodically protected,
evaluations of soil corrosivity should be performed at 5 year intervals. Soil resistivity
measurements may be used for relative classification of the soil corrosivity.
25
8.2.5 Cathodic Protection :
The external condition of buried piping that is not cathodically protected should be
determined by either pigging, which can measure wall thickness or by excavating
according to the frequency given in Table 9-1. Significant external corrosion detected by
pigging or by other means may require excavation and evaluation even if the piping is
cathodically protected.
An alternative or supplement t'O inspection is leak testing with liquid at a pressure atleast
10 percent greater than maximum operating pressure at intervals one-half the length of
those shown in Table 9-1 for piping not cathodically protected and at the same intervals
as shown in Table 9-1 for cathodically protected piping. The leak test should be
maintained for a period of 8 hours.
Four hours after the initial pressurization of the piping system, the pressure should be
noted and, if necessary, the line repressurized to original test pressure and isolated from
. the pressure source.
If, during the remainder of the test period, the pressure decreases more than 5 percent,
the piping should be visually inspected externally and! or inspected internally to find the
leak and assess the extent of corrosion. Sonic measurements may be helpful in locating
leaks during leak testing.
Other alternative .Ieak test methods involve acoustic emission examination and the
addition of a tracer fluid to the pressurized line ( such as helium or sulfur hexafloride). If
the tracer is added to the service fluid, the owner! user shall confirm suitability for
process and product.
26
8.3 REPAIRS TO BURIED PIPING SYSTEMS
Any coating removed for inspection shall be renewed and inspected appropriately.
In addition, coating repairs may be tested using a high voltage holiday detector. The detector
voltage shall be adjusted to the appropriate value for the coating material and thickness. Any
holidays found shall be repaired and retested.
If piping leaks are clamped and reburied, the location of the clamp shall be logged in the
inspection record and may be surface marked.
Both the marker and the record shall note the date of installation and the location of the
clamp. All clamps shall be considered temporary. The piping should be permanently
repaired at the first opportunity.
******
27
API 570- PIPING INSPECTOR PREPARATORY COURSE
(VOLUME-I)
Part-5
CODE CALCULATIONS
(Thickness Determination)
Exercise-I.
Determine the Pressure design thickness and minimum required thickness for a piping
with the following design conditions: Take W=l.
Exercise-I. (SOLUTION)
= 0.115 inch
Thus, Pressure Design thickness = 0.115 inch
Exercise-2.
Determine the Pressure design thickness and minimum required thickness fot a piping
with the following design conditions:
Exercise-2. (SOLUTION)
= 0.268 inch
Thus, Pressure Design thickness = 0.268 inch
Exercise-3.
Exercise-3. (SOLUTION)
Tm _ d ~ 3 P + C
- g 16 SE
P = 250psig
C = 0.625 inch
S = 16800 psig
E =1.0
Dg=8 inch
Exercise-4.
Q.l A Piping system is to be constructed using 12.7mm (0.50 inch) thick pipes.
Pipe specification is A 106 Grade A (de-oxidised). Design minimum
temperature is 0 deg.C ( 32 0 F). Will you require impact testing ,?-S per
ASME B 31.3?
Q.4 If all conditions in Q. 1 above are same except that we now use 30 mm
thick pipe. Will you specify impact test?
Q.5 Impact testing was conducted on A 106 Grade A pipes. Using 3 specimen.
Test impact values reported were:
Specimen 1: 16 ft Ib
Specimen 2: 15 ft Ib
Specimen 3: 11 ft Ib
Is impact test acceptable?
Exercise-4. (SOLUTION)
1) In this example Curve B will apply. Referring to Pig 323.2.2A, the point is
clearly above the curve, hence Impact Testing is not required.
2) Now the point lies clearly below the curve. Impact testing is required.
3) Now the point lies very close to the curve. Decision whether point is
above or below is difficult. Go to table 323.2.2A . We see that point will be
below the curve. Impact testing is required.
6) Not required. Go to Table A.1. This material can be used without impact
testing up to (_50 P).
0
CODE CALCULATIONS
( Pressure testing requirements)
Exercise-5.
4) First stage pressure for Pneumatic is smaller of 50% of test pro or 25 psi
= Smaller of 165/2 or 25 psi
= 25 psi.
Exercise-6.
Q.2. A 106 Gr B pipes, NPS 12, Sch 80 pipe welded to NPS 12 Sch 160 pipe
(Ambient temperature at plant site = -SOC)
Q.4 A 335 Grade P12 pipes NPS 10, Sch SO pipes welded to A 335 Grade P5
pipes NPS 10, Sch SO
CODE CALCULATIONS
( Pre-heating teperatures )
Exercise-:-6. ( SOLUTION)
1) Solution to Q.l
For AI06 Gr.B pipes P no. is 1
Tensile strength is 60000 psi
Thickness for NPS 10 sch 80 is 0.594 inch
From table 330.1.1 Preheat temp. = 50 deg F recommended
2) Solution to Q.2
4) For A 335 Gr.12 pipes P no. is 4. and For A 335 Gr.P5, the P no. is 5B
For P noA, Preheat temp= 300 deg F required
For P no.5B, Preheat temp= 350 deg F required
Use higher Preheat temp. = 350 deg F. Required.
CODE CALCULATIONS
( PWHT Requirments )
Exercise-7.
1) Solution to Q.l
2) Solution to Q.2
3) Solution to Q.3
Exercise-8.
1. Estimate the total length after heating if a 200 feet long, A 106 Gr.B pipe was
heated from 70 deg.F to 800 deg.F
3. What will be the total length after heating if a 280 feet long pipe was heated from
70 deg.F to 975 deg.F. Out of250 feet length, 150 feet was Carbon Steel and 130
feet was Austenitic Stainless steel ( 18Cr-8Ni)
CODE CALCULATIONS
( Thermal Expansion of Pipes)
Exercise-8.( SOLUTION)
2. Go to page 4 table A1. For material A182 Gr. F1, refer pressure-
temperature table number F2-1.5, page 122.
For 600deg. F and pressure = 600psi, Class 300 flange will be OK.
3. From table F2-1.7, page 123, A182 Gr. F2, Class 400 flange can be used
up to 940psi pressure for temperature of 400 deg. F.
4. From table F2-1.7, page 123, A182 Gr. F2, Class 400 flange can be used
up to 850 deg. F temperature for pressure of 650psi.
CODE CALCULATIONS
(Numerical Examples in API 570 Code)
Exercise"':9.
(A) Following information is available from Pipe data sheet & inspection
records for a classl Piping in service. The service in unchanged from 2002
& will continue.
Calculate following:
1. Long term corrosion rate
2. Short term corrosion rate
3. ,. What corrosion rate is to be considered of for Remaining life calculation?
4. Calculate Remaining Life.
5. What are nexfmaximum Thickness measurement & External inspection
intervals?
Exercise-9 (SOLUTION).
(Solution for A)
t initial = 1.2 inch (May 1992)
t previous = 1.05 inch (May 2002)
tactual = 0.9 inch (May 2007)
t required = 0.60 inch
= 1.2 -0.9
15
3) S.T. rate reflects current process used S.T. Corrosion rate (30 mpy)
for remaining life calculation.
4) Remaining life = (t actual- t required)/ Corrosion rate
0.9-0.60
0.030
10 years
s = 2 inches.
(VOLUME-I)
Part- 6
11 lYes
~
SMTS of base metal
Yes
E Hwas break ~I
weld metal
~No
Is the WPS supported by No Is unit stress 2:
PQR. Does WPS show No If--- 95%ofSMTS (QW -153)
---:l
reference No. of the J of base metal
supporting PQR
Yes I
1 Yes
Yes
No I Is bend test Qty, type
stated and correct I (QW - 451.1
Has PQR been revised ~
E ~Yes
lNa No
No
Is the result stated & OK I (QW -1 63)
I Is PQR signed and dated ~ {, Yes
lYes No Are result.s for tou)Fl (QW _ 17 2)
I test (If any) OK
Accept for C J,Yes
detailed Place WPS & PQR side by side
review
1
Go to tables as follows
T SMAW -QW253
SAW -QW254
No Check WPS/PQR for QW 402 to
QW 410 for the following
WPS: EV, NEV, PQR: EV,
Are the documents OK?
1
If the welder is to be qualified on the
~ basis ofPQR. Is his IdentifYing code.
Position of welding recorded on PQR.?
Accept
20 Welding DocUIllentation Forms Chapter 2
JOINTS (QW-402)
QW 483 (Back)
PQRNo.l'81 R/'l.oo+ /611
Tensile Test (QW150)
Ultimate Ultimate Type of
Specimen Total Load Unit Stress Failure &
No. Width Thickness Area lb psi Location
TeJ\si\~~1 I c'746 It
W,,-:l'-'l;'~
"\f\\S\ \e. Q;.I Q; '74 (/' . . . . . 'Bei.JE.- ii:fM
j .
GuidedBend Tests (QW160)
Type anel. Figure No. Result
Ftc~ r3J2Jl\~.~ . 1
.f~~ B~ ':J.
R.e6t-~~:1
R.';~t- ~-E.JII\! - l.
... I I
I
I I ......
..............
. "'j
I
I
I. I I
I
I
....
i I I
J i
Comments: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
..
Other Tests
T}~eofTest _______________________________________________
DepositAnalysis _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
Other _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. ________________________________
I.... f"11"
Welder'sName H::t\.)'
f',,,
~ v,'1"Ic..OY'. Clock No, Stamp No, N ! 2....
Tests conducted by: bJ A-l \ 0 l:-i p... L T i;. ST Laboratory Test No. H,. H I I" I
I
We certify that the statements in this record are correct and that the test welds were prepared, welded, and tested in
accordance with the requirements of Section IX of the ASME Code,
Manufacturer -r-=----------,.,.----'--'....q';;#'''-----
..., .J::>I\ V IDS ""1"11-\
Date 2.6-'2.-2007'". By xyz. CoRj?oRf\"TION
metail of record of tests are illustrati\'e only and may be modified to confonn to the t\ e and number of tests re uired by the Code.)
:'!I<~""'------
18 Welding Documentation Forms Chapter 2
QW-482 (Back)
'IN P!:I2.a of- } O:;",I!, 0
WPS No. f Rev.
j
.32..: ,
i
i
i I
!
1
i i
t
i I
I !
j i
,
i
PQRREVIEW:
1. Check P,F and A Nos ....... P NO.1 is OK, F No. should be 4 instead of 2,. A No.
OK
2. Bend tests specimen Nos. = 4 ... 0K, Test results also OK, but specimen tested
are wrong. They must be 4 side bendsfor Test coupon thickness=0.75 inch.
WPSREVIEW:
Check P.No , F No, A No. Change F No. to agree with PQR ( change F no. to 4)
Base metal thickness range shall be= 3/16 inch to 1112 inch.
Weld metal thickness range shall be = 0 to 1 112 inch.
Volume -1
PART 7
a. 40 psig
b. 20 psig
c. 25 psig
d. 80 psig
a. 450 psi
b. 476 psi
c. 330 psi
d. 375 psi
a. 349 psi
b. 396 psi
c. 408 psi
d. 330 psi
7. PWHT is required for all thicknesses of piping over 1/2 inch for which
a. P Nos. 1 and 2
b. PNos.1 and 3
c. PNos.2and3
d. P Nos. 4 and 5
8. Code B 31.3 recommends and mandates min, required pre-heat temp, for
welding of pipes. When do the recommendations become mandatory?
a. 10%
b. 15%
c. 121/2%
d. None of these
- .
11. NPS 12, Sch 80 and Sch 160 pipes (M.O.C = A 106 gr B) are to be used at -100 C.
Determine whether,
a. FCAW
b. GMAW
c. GTAW
d. SAW
ANSWERS
Q.NO. ANSWER
1 B
2 C
3 C
4 C
5 B
6 A
7 D
8 D
9 C
10 B
11 B
12 C
13 A
14 B
15 D
API 570 Preparatory training course
N ate: Choose only one alternative which you think is most appropriate.
a. An owner or user of piping systems who repairs or alters his or her own
equipment in accordance with API 570
b. A contractor whose qualifications are acceptable to the owner or user of
piping systems and who makes repairs or alterations according to API 570
c. One who is authorized by, acceptable to, or otherwise not prohibited by the
jurisdiction and who makes repairs or alterations according to API 570
d. All of the above
a. Any piping which is extra to the main piping run can be considered as
auxiliary piping.
b. Instrument and machinery piping, typically small bore secondary process
piping that can be isolated from primary piping system.
c. Any piping which is less than 1.0 inch N.B
d. All of the above
a. Before PWHT
b. After PWHT and before painting
c. After PWHT and painting
d. Anytime is okay
11. API 570 was developed for the petroleum refining and chemical process industries.
a. Piping system
b. Piping Spool
c. Piping Circuit
d. N one of the above
17. What is the minimum time that a leak test must be maintained as per B 31.3?
a. 60 minutes
b. 45 minutes
c. 30 minutes
d. 10 minutes
a. Three specimen
b. At least two specimen
c. Minimum three specimen
d. Maximum three specimen
ANSWER KEY
Q. ANS.
1 C
2 D
3 C
4 A
5 B
6 C
7 B
8 D
9 C
10 C
11 B
12 C
13 B
14 D
15 C
16 C
17 D
18 C
19 A
20 B
API 570 Preparatory training course
Note: Choose only one alternative which you think is most appropriate.
4. In the Barlow formula for determining pipe thickness, the term'S" stands for:
6: A 20' long carbon steel pipe is heated uniformly to 450 degrees F. from 70
degrees F. Determine it~ length after heating.
a. 20.052'
b. 20.263'
c. 20.210'
d. 20.250'
10. Environmental cracking of austenite stainless steels is caused many times by:
ANSWERS
Q.NO. ANSWER
1 A
2 A
3 D
4 C
5 D
6 A
7 C
8 A
9 D
10 C
API 570 Preparatory training course
Note: Choose only one alternative which you think is most appropriate.
a. API579
b. API570
c. API580
d. API574
6. "Pipe to soil potential survey" for poorly coated pipes (or where cathodic
protection is not reliable) should be conducted at intervals of:
a. Five years
b. Three years
c. Ten years
d. Six years
7. In pressure decay method for testing under ground pipe, the acceptance criteria
is that pressure decrease :
a. 150%
b. 50%
c. 110%
d. 125%
5. Marker chemical (tracer) is used for testing the underground pipes for the
purpose of:
7. The retirement thickness of valves and flanged fittings can be computed using
formula for pipes by using:
a. 5.0 years
b. 4.5 years
c. 6.0 years
d. Data is insufficient to calculate remaining life
I Thickness I I Year I
0.500 II 0
0.425 II 5
0.400 II 10
On the basis of the information above, the long-term corrosion rate for the
location is:
12. For thickness measurement of pipes NPSl and smaller. NDT technique
employed would be:
a. Ultrasonic teclmique
b. Radiographic profile technique
c. Anyone is OK
d. None are OK
13. If probable corrosion rates can not be determined on-stream determinations shall
be made approximately
a. 6 months of service
b. 3 months of service
c. 1 month of service
d. None of the above
15. For calculating MAWP of Piping Circuit which is put in service the
wall thickness used in computations is:
a. Actual thickness as determined by inspection.
b. Actual thickness minus the estimated corrosion loss before the
date of next inspection
c. Actual thickness minus twice the estimated corrosion loss before
the date of next inspection
d. None of the above
16. Table 6-2 of API 570 standard gives extent of CUI inspection following the visual
inspection, which is applicable to:
17. As per API 570 for .bolted flanged joints, bolts and nuts are considered as
acceptably engaged if the lack of complete engagement is:
a. 5
b. 10
c. 15
d. 3
ANSWERS
Q.NO. ANSWER
1 C
2 A
3 B
4 C
5 D
6 D
7 C
8 C
9 A
10 D
11 C
12 B
13 B
14 A
15 C
16 D
17 B
18 A
19 B
20 A
API 570 Preparatory training course
Note: Choose only one alternative which you think is most appropriate.
a) Piping Engineer
b) Inspector
c) Repair Organisation
d) Operating Personnel
3. Which of the following are some of the mandatory requirements for re-rating a
piping system?
a. Normally required
b. Not required at all
c. Depend on opinion of piping inspector
d. Only a" and c" above
/I /I
7. Which of the following are areas on piping systems which are susceptible to CUI
during the range of 25F to 250F:
8. Listed below are several examples of piping system. Which is class I piping
for flammable fluids?
9. Which of the following documents referenced in API 570 addresses hot tapping?
a. API 2201
b. API 574
c. ASMEB31 G
d. None of the above
10. The preferred method for inspecting piping coating is:
a. Changing the damaged flange to a new flange of same rating and material
b Alteration on piping changing a nozzle size from one not requiring
reinforcement pad to the one requiring reinforcement pad
c. For both a and b
d. For none of the above
13. For a project involving piping welding at site by 10 welders, (with only one
qualified welder) procedure and 9 welders were to be qualified. In this case,
. identify correct statement from the following:
a. 9 welders qualification must be performed before procedure
qualification.
b. 9 welders qualification should be performed after procedure
qualification is carried out using qualified welder.
c. Out of Welder qualification and procedure qualification, anything can
be performed before.
d. .Welder qualification and procedure qualification must be performed
simultaneously, without waiting for the test results.
a. Ductility of weld
b. Strength of weld
c. Soundness of weld
d. Both soundness and ductility of weld
16. According to ASME Sec. IX, a welder for SMAW can be qualified by following
minimum tests (for IG pipe position):
a. True
b. False
c. Depends on company policy
d. Depends on client of the company
20. When dial-type indicating and recording pressure gauges are used to
monitor leak testing, the maximum gauge range shall not exceed which
multiple of the expected test pressure?
a. 11/2 times
b. 21/2 times
c. 3 times
d. 4 times
21. A radiographic technique in which radiation passed through two walls and both the
walls are viewed on the same radiograph (double wall, double image - ellipse) the
limitation for the outside diameter is:
a. 3-1/2"
b. 2"
c. 4"
d. Any diameter possible
a. 5.0 years
b. 4.5 years
c. 6.0 years
d. None of above
23. Common locations which are susceptible to CUI on the insulated piping are:
24. The accuracy of magnetizing equipment that is equipped with an ammeter shall be
verified:
a. Each year
b. Each two years
c. When possible
d. Every 6 months
a. Radiography
b. Ultrasonic
c. Hardness survey
d. N one of above
30. In visual testing for qualifying the procedure, a defect of which minimum
width shall be used:
a. 1/16"
b. 1/8"
c. 1/32"
d. N one of the above
a. Annually
b. Six monthly
c. Once in 3 years
d. None of the above
32. The pressure gauges for leak testing shall be calibrated as an ASME Sec. V
requirement, at least:
33. It is decided to carryout a surface NDT for austenitic S.S. pipe welds. Choose the
best combination.
36. When a pressure test is not necessary or practical, what shall be utilised in
lieu of a pressure test?
a) PMI Testing
b) Non-destructive examination
c) Vacuum visual examination
d) Hammer Testing
a. Sub-surface cracks
b. Surface cracks
c. Both a and b
d.None of a or b
38. The pipe welding test position in which the pipe is horizontal and rotated so that
welding takes place at or near the top is designated as?
a. 2G
b. 5G
c. 3G
d. 1G
40. For thickness measurement of pipes NPS 1 and smaller, NDT technique
employed would be:
e. Ultrasonic technique
f. Radiographic profile technique
g. Anyone is okay.
h. None are okay.
41. API 578 requires at least _ _ _ _ electrodes to be PMI tested from each box.
a. One
b. Two
c. Minimum 10%
d. All
42. Which of the following make pipe system most susceptible to CUI?
a. Water only
b. Oil only
c. Water and aqueous solutions
d. None of the above
44. For calculating MA WP of Piping Circuit which is put in service the wall thickness
used in computations is:
45. When checking Titanium materials for cracks using PT methods only liquid
penetrants:
46. As per API 570 for bolted flanged joints, bolts and nuts are considered as acceptably
engaged if the lack of complete engagement is:
a. Safety
b. Reliability of operation
c. Regulatory requirements
d. All of above
48. For a typical "injection point pipe circuit" starts upstream of injection point
from a distance of
49. For MT examination by Prod technique the spacing between prods shall be between:
a. 4 inches to 12 inches
b. 4 inches to 10 inches
c. 3 inches to 10 inches
d. 3 inches to 8 inches
ANSWER KEY
Note: Choose only one alternative which you think is most appropriate.
a. After 8 years
b. After 5 years
c. After 10 years
d. None of the above
a. 0.20 inch
b. 0.28 inch
c. 0.12 inch
d. 0.16 inch
3. When will be the next inspection schedule from now on for external inspection for
. . Ql?
plpem ..
a. 10 years
b. 8 years
c. 5 years
d. none of the above
4. The pipe in Q.l above has an insulated area of 200 sq. ft., which is exposed to
susceptible temperature and mist spray of cooling tower. According to API 570, how
much of minimum area is recommended for NDT survey for CUI during external
inspection?
5. A PQR is to be qualified using 5/8 inch thick test coupon. It can qualify thickness:
a. 1/8// to 1-1/4//
b. 1/16/1 to 5/8/1
c. 1/16/1 to 1-1/4/1
d. None of the above
a. 5 min
b. 10 min
c. 7 min
d. 6 min
7. A radiograph was having density near the penetrameter equal to 3.0. Hence the
acceptable density range of the radiograph is:
a. 1.7 to 4
b. 2.55 to 3.9
c. 2.0 to 4.0
d. None of the above
8. For piping buried in soil with resistivity of 5000-ohm cm and not cathodically
protected, evaluations of pipe thickness should be performed at:
a. 10 year interval
b. 5 year interval
c. 3 year interval
d. None of the above
9. For a certain Natural gas piping system, which is in operation for 16 years, it is
estimated that it has remaining life of 12 years. Considering the stipulation of API
570, which of the following will determine maximum interval for next proposed
date for thickness measurement examination and visual examination?
11. You are planning for the Hydro-test of a piping with Hydro test pressure
40Kg/cm2g. The calibrated test gauges available with you are 0-50 Kg/cm2g, 0-100
Kg/cm2g, 1-150 Kg/cm2g and 0-200 Kg/cm2g. Which two gauges are acceptable for
this test?
12. What would you expect to happen if you were taking VT readings on piping
that was operated higher than 200 degrees F?
a. SetA
b. SetB
c. SetC
d. Set D
14. The document referenced in API 570 for determining "fitness for service" of piping
system is:
i. API 579
j. API 574
k. ASME B 31.1
1. None of the above
15. During impact testing of A 106 grB (Deoxidised) and A53 grB pipes (non-
deoxidised), following absorbed energy values in ft-Ib were observed:
18. When a PT test cannot be conducted between 10-52 degree C (50 degrees F - 125
degrees F) what must be done, as per ASME Sec. V?
19. A piping system isto be pneumatically pressure tested. Its Design Pressure is 160
psig. The first stage pressuration, the test pressure and inspection pressure
respectively will be:
20. Select suitable Hole type (source side) penetrameter for following weld joint:
a. No 20
b. No 25
c. No 30
d. None of the above
21. If type of penetrameter in above question is changed to wire type what shall be the
wire designation (wire decimeter in inch)?
e. 0.025 (No. 10)
f. 0.016 (No.8)
g. 0.032 (No. 11)
h. None of the above
22. For steel plates and welds to be checked by LPI, what shall be the penetration time
for penetrant?
23. After applying the developer the examiner checked four welds for surface defects
after following period, weld A - after 5 minute, weld B after 10 minutes, weld C was
checked after 30 minutes and welds Dafter 65 minutes. Which of the welds were
checked wrongly?
a. Weld A and B
b. Weld C and D
c. Weld D only
d. WeldA and D
24. In a certain PQR for SMAW, the electrodes used for all passes were of AWS
classification (E 7018). Corresponding WPS also showed filler materials as E
7018. Now the manufacturer proposes to change the filler material in WPS to
E 7015. Will you ask manufacturer to:
25. Actual thickness measured at a TML was 0.4 inch. The corrosion rate is 10 mpy.If
next planned thickness inspection is after 6 years, what thickness will be used for
MAWP calculation?
a. 0.4 inch
b. 0.34 inch
c. 0.28 inch
d. None of the above
26. Estimated rate of Sulphidation corrosion for a crude handing equipment due to
sulpher content of 0.5% (by weight) at 600 0F is 10 mpy. What will be the corrosion
rate if sulpher content is 1.0% by weight?
a. 10 mpy approximately
b. 12 mpy approximately
c. 15 mpy approximately
d. 20 mpy approximately
27. Suggest suitable construction materials for caustic service having 40% NaOH
concentration (by weight) operating at 240 0P
28. To avoid HTHA, sugge~t suitable materials of construction for hydrogen service
with partial pressure of hydrogen = 1500psi, and temperature = 800 0P
a. Carbon steel
b. 1.25 Cr - 0.5 Mo
c. 2.25 Cr - 1 Mo
d. 1 Cr - 0.5 Mo
30. While observing radiographic film for weld with SMAW process showed indication
of following description. "A localized darker density with fuzzy edges in the center
of the width of weld image." This indication most likely represents:
a. Excessive penetration
b. Lack of penetration
c. Cluster porosity
d. Burn through
API 570 Preparatory training course
Q.6 Table in Art. 6 of ASME Sec. V shows development time of 10 ririnutes for all
materials.
Answer:b
Answer:b
Answer: a
Answer: a
Q.ll Refer ASME Sec. V (Leak Testing - Art. 10). The range for pressure
gauges is:
Answer: c
Answer:b
Answer: a
12.5 + 13.5 + 12
Average for A106 grB = = 12.5 < 13
3
11 + 11.5 + 9
Average for A53 grB = = 10.5> 10 ft lb
3
Q.16 A 106 grC pipe belongs to P No.1 material. So it will qualify only P No.1 materials.
A lOS, A 516 gr60 and A516 gr70 are P No.1 materials.
Refer Table QW-422 from ASME Sec. IX.
Answer:b
Answer: a
Answer: a
Answer: c
Answer: b
Answer: d
Answer: d
Answer: d
Q.24 Refer ASMB Sec. IX - Table for F Nos.
B7018 and B70I8 are both F No. = 4
So same PQR is OK. Only revise WPS.
Answer:b
Q.25 Refer API 570 Page 7-2 for MAWP thickness used shall be Actual Thickness minus
twice the corrosion loss up to next inspection.
Answer: c
Answer is: B
Answer is: D
Answer is: C
Answer is: A
Answer is: D
API 570- PIPING INSPECTOR PREPARATORY COURSE
Volume -1
PART 8
1) API 570 covers inspection, rating, repair, and alteration procedures for metallic
and fiberglass reinforced plastic (FRP) piping systems and their associated
pressure relieving devices that have been placed in service.
2) The intent of this code is to specify the in-service inspection and condition-
monitoring program that is needed to determine the integrity of piping.
3) API 570 was developed for the petroleum refining and chemical process
industries but may be used, where practical, for any piping system.
4) API 570 shall not be used as a substitute for the original construction
requirements governing a piping system before it is placed in service;
5) API 570 shall not be used in conflict with any prevailing regulatory requirements.
Ifthe requirements ofthis code are more stringent than the regulatory
requirements, then the requirements ofthis code shall govern.
7) The fluid services and classes of piping systems listed below are optional with
regard to the requirements of API 570.
hazardous fluid services below threshold limits, as defined by jurisdictional
regulations;
water (including fire protection systems), steam, steam-condensate, boiler
feed water, and Category D fluid services, as defined in ASME B31.3.
Other classes of piping systems that are optional are those that are
exempted from the applicable process piping construction code.
API Publication SiD, Pressure Vessel Inspection Code: Maintenance Inspection, Rating,
Repair, and Alteration
API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the
Refining Industry
API Recommended Practice 574, Inspection Practices for Piping System Components
API Recommended Practice 578, Material Verification Program for New and Existing
Piping Systems
API Publication 2201, Safe Hot Tapping Practices in the Petroleum and Petrochemical
Industries
CHAPTER - 3. Terms, Definitions, Acronyms, and Abbreviations
1. alteration
A physical change in any component that has design implications affecting the
pressure containing capability or flexibility of a piping system beyond the scope of its
original design.
4. auxiliary piping
Instrument and machinery piping, typically small-bore secondary process piping that
can be isolated from primary piping systems.
6. corrosion barrier
The corrosion allowance in FRP equipment typically an interior layer which is
specified as necessary to provide the best overall resistance to chemical attack.
7. corrosion specialist
A person who is knowledgeable and experienced in the specific process chemistries,
corrosion degradation mechanisms, materials selection, corrosion mitigation
methods, corrosion monitoring techniques etc.
8. deadlegs
Components of a piping system that normally have no significant flow like bypass
piping, spare pump piping.
10. examiner
A person who assists the inspector by performing specific NDE on piping system
components but does not evaluate the results of those examinations in accordance
with API 570, unless specifically trained and authorized to do so by the owner or
user.
14. in service
Piping systems placed in operation (installed).
NOTE: Does not include piping systems that are still under construction or in
transport to the site prior to being placed in service or piping systems that have
been retired.
Piping systems that are not currently in operation due to an outage of the process,
turnaround, or other maintenance activity are still considered to be "in service./J
16. inspection
The externat internat or on-stream evaluation (or any combination of the three) of
piping condition conducted by the authorized inspector or his/her designee.
17. minimum required thickness
The thickness without corrosion allowance based on the appropriate design code
calculations that consider pressure, mechanical and structural loadings.
20. on-stream
A condition where in-service piping systems have not been prepared for an internal
inspection.
26. renewal
Activity that discards an existing component, fitting, or portion of a piping circuit and .
replaces it with new or existing spare materials of the same or better qualities as the
original piping components.
27. repair
The work necessary to restore a piping system to a condition suitable for safe
operation at the design conditions
29. rating
Calculations to establish pressures and temperatures appropriate for a piping
system, including design pressure/temperature, MAWP, structural minimums,
required thicknesses, etc.
30. rerating
A change in the design temperature, design pressure Qr the MAWP of a piping
system (sometimes called rating). A rerating may consist of an increase, a decrease,
or a combination of both.
MT magnetic-particle technique
1. An owner/user of piping systems shall bear ultimate responsibility for all aspects
covered in API 570
2. Moe
The owner/user is also responsible for implementing an effective MOe process that
will review and control changes to the process and to the hardware.
3. Piping Engineer
The piping engineer is responsible to the owner/user for activities involving design,
engineering review, analysis, or evaluation of piping systems covered by API 570.
4. Repair Organization
All repairs and alterations shall be performed by a repair organization. The repair
organization shall be responsible to the owner/user and shall provide the materials,
equipment, quality control, and workmanship necessary to repair the piping systems
in accordance with the requirements of API 570.
6. Examiners
The examiner shall perform the NDE in accordance with job requirements.
7. Other Personnel
Operating, maintenance, engineering or other personnel shall be responsible for
timely notification to the inspector or engineer of any issues that may affect piping
integrity or any unusual conditions that may develop (e.g. noises, leaks, vibration, etc.).
CHAPTER - 5. Inspection, Examination, and Pressure Testing Practices
5.2 RBI
RBI can be used to determine inspection intervals and the type and extent of
future inspection/examinations.
Probability Assessment
The probability assessment shall be in accordance with API 580 and shall be
based on all forms of damage that can be expected to affect equipment
Consequence Assessment
The consequence assessment shall consider the potential incidents that may
occur as a result of fluid release, the size of a potential release, and the type of a
potential release (includes explosion, fire, or toxic exposure.)
Piping Entry
Prior to entering large piping, the piping shall be isolated from all sources of
liquids, gases, vapors, electricity, and other sources of energy.
The piping system should be drained, purged, cleaned, ventilated, gas tested and
locked out/tagged out before it is entered.
Records Review
Before performing any of the required inspections, inspectors shall familiarize
themselves with prior history of the piping system for which they are responsible.
In particular, they should review the piping system's prior inspection results,
prior repairs, current inspection plan, and/or other similar service inspections.
On-stream Inspection
All on-stream inspections should be conducted by either an inspector or
examiner.
The inspector should consult with a corrosion specialist when the short-term
corrosion rate changes significantly from the previous identified rate to
determine the cause.
External piping inspections may be made when the piping system is in-service.
CUI Inspection
Inspection for CUI shall be considered for externally-insulated piping with
possibility of moisture ingress and susceptible temperature range {Carbon steel
piping operating between 10 OF (-12C} and 350 OF (175 C)}.
If CUI damage is found during spot checks, the inspector should inspect other
susceptible areas on the equipment.
Supplemental Inspection
Other Supplemental inspections may be scheduled as appropriate or necessary.
-~
Injection'Point Inspection
The recommended upstream limit ofthe injection point circuit is a minimum of
12 in. (300 mm) or three pipe diameters whichever is greater. The recommended
downstream limit the second change in flow direction, or 25 ft (7.6 m) beyond
the first change whichever is less.
The preferred methods of inspecting injection points are radiography and/or UT,
as appropriate
5.6 CMLs
CMLs are specific areas along the piping circuit where inspections are to be made.
Examples of different types of CMLs include locations for thickness
measurement, locations for stress cracking examinations, locations for CUI and
locations for high temperature hydrogen attack examinations.
CML Monitoring
Each piping system shall be monitored at CMLs.
Every CML should have one or more examination points identified by:
locations marked on un-insulated pipe using paint stencils, or stickers;
holes cut in the insulation and plugged with covers;
isometrics or documents showing CMLs
. Radiographic profile techniques are preferred for pipe diameters of NPS 1 and
smaller. Radiographic profile techniques may be used, in insulated systems or
where localized corrosion is suspected.
Lower pressure tests, which are used only for tightness of piping systems, may
be conducted at pressures designated by the owner/user.
Test Fluid
The test fluid should be water unless there is the possibility of damage due to
freezing. such case, another suitable nontoxic liquid may be used.
To minimize the risk of brittle fracture during a pressure test, the metal
temperature should be maintained at least 30 of (17C) above the MDMT for
piping that is more than 2 in. (5 cm) thick, and 10 of (6C) above the MDMT for
piping that have a thickness of 2 in. (5 cm) or less.
As alternative, each valve disk shall be held down by a suitably designed test
clamp.
The application of an additional load to the valve spring by turning the adjusting
screw is prohibited.
When valve body and/or closure pressure tests are performed after servicing,
they should be conduCted in accordance with API 598.
Critical check valves should be visually and internally inspected to ensure that
they will stop flow reversals.
Due to the different capabilities various NDE methods to find flaws, it is a good
practice to specify the types of NDE during original fabrication that the owner-
user plans to apply during in-service inspections.
The audit team should typically be from another owner/user plant site or from a
third party experienced in refining and/or petrochemical process plant
inspection
CHAPTER - 6. Interval/Frequency and Extent of Inspection
6.1 General
Scheduled inspections of Piping Systems shall be conducted on or before their
due date or be considered overdue for inspection.
Inspections that have been risk assessed and found to have acceptable risk for
an extension of the due date are not considered overdue until the end of the
documented extension period.
Piping Installation
Piping shall be inspected in accordance with code of construction requirements
at the time of installation.
The allowable service conditions and the inspection interval shall be established
for the new service.
When used to increase inspection interval limits or the extent of inspection, RBI
assessments shall be shall be reviewed and approved by a piping engineer and
authorized piping inspector at intervals not to exceed limits in Table 2, or more
often if warranted by process, equipment, or consequence changes.
Inspection Intervals
Class 1
Services with the highest potential of resulting in an immediate emergency if a
. leak were to occur are in Class 1.
Fluids that can rapidly vaporize during release, are class 1 ( such as C2, C3, and
C4 streams).
Fluids that rapidly vaporize are those with boiling temperatures below 50 OF
(10C)
Class 2
Services not included in other Classes are in Class 2. This classification includes
the majority of unit process piping
On-site hydrocarbon fluids tnat will slowly vaporize during release are class 2
Class 3
Hydrocarbon Fluids that do not significantly vaporize during release are class 3
Services that are potentially harmful but are located in remote areas may be
included in this class.
Class 4
Services that are essentially nonflammable and nontoxic are in Class 4, as are
most utility services. Inspection of Class 4 piping is optional.
Piping systems that are known to have a remaining life of over 10 years or that
are adequately protected against external corrosion ne'ed not be included for the
NDE inspection recommended in Table 3.
This sampling also shall include CMLs with the earliest renewal date as of the
previous inspection.
PRDs should be inspected, tested, and maintained in accordance with API 576 .
tactual- trequired
Rem ai n in g Iife (yea rs) = ------------------------------------------------------
corrosion rate [inches (mm) per year]
where,
tactual is the actual thickness, measured at the time of inspection.
trequired is the required thickness, at the same location as the tactual
The corrosion rates of piping circuits shall be calculated from the following formula:
tinitial- tactual
Corrosioon rate (LT) = ---------------------------------------------------------
time (years) between tinitial and tactual
The 5T corrosion rate of piping circuits shall be calculated from the following formula:
tprevious - tactual
Corrosioon rate (5T) = --------------------------------------------------------------
time (years) between tprevious and tactual
where
tinitial is the thickness, at initial installation
. tprevious is the thickness, at the same location as tactual measured during previous
inspection.
For new piping systems and piping systems for which service conditions are
being changed, one of the following methods shall be employed to determine
the rate of corrosion
o A corrosion rate for a piping circuit may be calculated from data collected
by the owner/user on piping systems of similar service an~ comparable
operating conditions.
o If data for the same or similar service are not available, a corrosion rate
from the published data on piping systems in comparable service.
For unknown materials, computations may be made assuming the lowest grade
material and joint efficiency in the applicable code.
When the MAWP is recalculated, the wall thickness used in these computations
shall be the actual thickness determined by inspection minus twice the
estimated corrosion loss before the date of the next inspection
Piping system owners and users shall maintain permanent and progressive
records of their piping systems and pressure-relieving devices. Permanent
records will be maintained throughout the service life of each piping system.
Any piping circuit not inspected within the established interval is considered
overdue for inspection,
Temporary extensions of piping inspection due dates and shall not be considered
inspection interval revisions.
8.1.2 Authorization
All repair and alteration work shall be authorized by the inspector prior to its
commencement. Authorization for alteration work may not be given without
prior consultation with, and" approval by, the piping engineer.
The inspector will designate any inspection hold points required during the
repair or alteration sequence.
The inspector may give prior general authorization for limited or routine repairs
and procedures, provided the inspector is satisfied with the competency of the
repair organization.
Approval
All proposed methods of execution of repair and alteration work, materials,
welding procedures, examination, and testing shall be approved by the inspector
or by the piping engineer, as appropriate.
The inspector shall approve all repair and alteration work at deSignated hold
points and after the repairs and alterations have been satisfactorily completed.
For temporary repairs, a full encirclement sleeve may be applied over the
damaged or area ..
If the repair area is localized and the specified minimum yield strength of the
pipe is not more than 40,000 psi a temporary repair may be made by fillet
welding a split coupling or plate patch over the pitted area.
d= 4 vRT
where,
d = the minimum distance between the adjacent fillet weld attachments,
R = the inside radius
t =the minimum required thickness of the fillet welded patch
Temporary repairs may remain in place for if approved by the piping engineer.
Permanent Repairs
Repairs may be made by preparing a welding groove to remove the defect and
then filling the groove with weld metal
The defective area may be removed by cutting out a cylindrical section and
replacing it with a piping component
Insert patches (flush patches) may be used to repair damaged or corroded areas
if the following requirements are met:
o Full-penetration groove welds are provided.
o For Class 1 and Class 2 piping systems, the. welds shall be 100 percent
radiographed or ultrasonically tested.
o Patches may be any shape but shall have rounded corners 1 inch radius
The bolted clamp, nonmetallic composite wrap, metallic and epoxy wraps, are
considered as non-welded temporary repairs. These can be installed on-stream.
The repair organization shall use welders and welding procedures qualified in
accordance with the code to which the piping was built.
o Pressure tests are normally required after alterations and major repairs
Rerating:
The close-interval potential survey is performed at ground level over the buried
pipe to locate active corrosion of pipe's surface. For poorly coated pipes where
cathodic protection potentials are inconsistent, this survey is conducted at 5-
year intervals
The pipe coating holiday survey can be used to locate coating defects on buried
coated pipes
For piping buried in lengths greater than 100 feet (30 m) and not cathodically
protected, evaluations of soil corrosivity should be performed at 5-year intervals
Inspection Methods
Intelligent pigging. This method involves the movement of a device (pig) through the.
Five diameter bends are usually required since standard 90-degree elbows may not
pass a pig.
Video cameras. Television cameras are available that can be inserted into the piping.
These cameras may provide visual inspection information on the internal condition
of the line.
Excavation. In many cases, the only available inspection method that can be
performed is unearthing the piping in order to visually inspect the external condition
of the piping
The external condition of buried piping that is not cathodically protected should be
determined by either pigging, which can measure wall thickness, or by excavating
according to the frequency given in Table at the end (Table 9-1).
Leak Testing:
As alternative or supplement to inspection is leak testing with liquid at a
pressure at least 10 percent greater than maximum operating pressure
Intervals for above test are: one-half the length of those shown in Table 9-1 for
piping not cathodically protected and at the same intervals as shown in Table 9-1
for cathodically protected piping.
The leak test should be maintained for a period of 8 hours. Four hours after the
initial pressurizationof the piping system, the pressure should be noted and, if
necessary,the line repressurized to original test pressure and isolated from the
pressure source. If, during the remainder of the test period, the pressure
decreases more than 5 percent, the piping should be visually inspected to find
the leak and assess the extent of corrosion.
If piping leaks are clamped and reburied, the location of the clamp shall be
logged in the inspection record (with the date of installation) also be surface
marked.
Inspector Certification
An API 570 inspector certification will be issued when an applicant has successfully
passed the API 570 certification exam and satisfies at least one of the following:
Recertification
o Recertification is required three years from the date of issuance of the
API 570 authorized piping inspector certificate. Recertification by written
examination will be required for authorized piping inspectors who have
not been actively engaged
8. It can not be used for lower temperature (if double line is to the left)
or higher temperature (if double line is to the right).
9. Table A-1 B of B 31.3 Code gives weld joint quality factor for
manufactured pipes. The factor can be increased for Electric
Fusion welded pipes by conducting additional radiography (spot or
full) as per Table 302.3.4.
2(8EW + PY)
11. The thickness calculated shall be corrected for 12.5% negative mill
tolerance.
3P
---+C
16 SE
Where, dg::::: gasket inside diameter
20. For joining unequal schedule pipe, tapering or step-slot shall be made
inside thicker pipe for weld fit-up.
21. For fillet weld, the throat of fillet weld is calculated as throat =0.707 size of
weld.
26. PWHT Table (331.1.1) gives temperature range, minimum holding time
and maximum hardness values.
27. PWHT conducted properly should reduce the hardness in weld and HAZ.
Code gives the maximum Brinell Hardness Values after PWHT .
29.AII NDT (PT, RT, MT, VT, UT) shall be carried out according to
ASME Sec. V.
31.lf two values are separated, by 'and' lower value becomes the acceptance
limit. If two values are separated by 'or' then higher value becomes the
acceptance lim it.
33. After fabrication and inspection of piping, but before first operation,
hydrostatic pressure test shall be carried out on completed piping.
37 . Stress Rat 10 = -
Stress at test temperature (Ambient)
-----=-----'------'--
Stress at design temperature
40.ln pneumatic leak test, final inspection pressure for leak check is Design
Pressure of the Piping System.
41. For category D fluids the leak testing at operating pressure can be
performed with the product itself directly.
43. For hydro testing water should be used as testing medium but other
non toxic liquid may be used if water is not suitable due to
possibility of freezing or due to process reasons.
44. For pneumatic testing preferred medium is air but other non-toxic
gases also may be used
45. The inspection procedure records shall be retained for at least 5
years.
1. 8 16.5 Covers Flanges and flanged fittings with rating class designation 150.
300,400,600,900, 1500, and 2500 in sizes NPS 1/2 through NPS 24
3. The System Hydrostatic Test pressure for flanges and flanged fittings is 1.5
times the pressure rating at 100 deg. F rounded to higher 25 psi.
4. For finding out the required flange class as per 816.5, first find out which table
(Pressure - Temperature rating table) to refer for that material. Flange rating
then can be read out from that table for given condition of design pressure and
design temperature.
5. Flanges are not required to be pressure tested. Each flanged fitting shall be
given a shell pressure test
6. The shell pressure test for flanged fittings shall be at a pressure no less than
1.5 times the 38C (100F) pressure rating rounded off to the next higher 1 bar
(25 psi) increment.
7. Flanged fittings shall be pressure tested for leak tightness using water. Other
test fluids may also be used if required. The test duration shall be:
Size Duration, sec
< NPS 2 60
NPS 21/2 to NPS 8 120
~NPS10 180
IMPORTANT SUMMARY POINTS
5. Bend test (It may be Face bend, root bend or side bend) is
passed if test specimen does not show open discontinuity more
than 1/8 inch. (3 mm.) (QW 163).
10. For P & R test to pass it shall pars 2 tension tests and 4 bend
tests (QW 202).
11. Bend tests are 2 face Bend and 2 Root bends for coupon
thickness less than 3/4" (19 mm) and 4 side bend tests if
thickness is equal to greater than 3/4" (QW 451)
12. P Q R should also list P. No. (for parent metal) F.No. (for filler
metal) and A-No. (for weld metal) [QW-422, QW-432, QW-442].
A. General:
1. ASME Sec. V. gives methods and requirements for conducting
NOT. It becomes applicable only if referred by the other
referencing codes.
B. RT Examination:
3. For RT Examination, either hole type or wire type 101 shall be
used.
5. Density limitation:
8. Hole 101 may be placed on or near the weld. Wire IQI is placed
on the weld with wires perpendicular to the weld axis.
C. PT Examination.
Water washable
Post Emulsifying.
Solvent Removable.
This results in total 6 techniques.
D. MT Examination:
16. The Magnetic Particle Examination can be performed on
Ferromagnetic materials for finding surface and near surface
defects.
Drug or wet Iron powder and visible, or fluorescent powder is
used.
18. Yoke technique is suitable for surface defects only and can use
A.C., D.C. or permanent magnet.
E. UT Examination:
23. Pulse - Echo contact method is used for finding thickness and
laminations.
26. Dual Search units are also used using two crystals one for
sending pulse and other for receiving echo. On smaller
thickness this method results in vee-error which needs
correction.
1. The two most common carbon steel piping materials used in the
petrochemical industry are ASTM A53 and A 106.
2. A gate valve consists of a body that contains a gate that interrupts flow.
The gate valve is normally used in fully open or fully closed position.
3. Full ported gate valves shall be used on the pipelines which are to be
pigged.
10. Proper Inspection leads to safety, continuity and reliability of the plant.
12. Radiography has advantage of permanent record in the forrn of film. It can
be employed to check the thickness while insulation is intact.
13. Hotspots shall be inspected for oxidation loss and reduction of thickness.
Possibility of creep damage can be present if temperature during the
exposure was more than 800 deg. F.
14. Hammer Testing is used to locate thin spots by striking the hammer and
listening for the ringing sound by an experienced person.
15. Hammer testing shall not be performed on cast iron pipes, glass lined
pipes and stress relieved pipes. Hammer used shall be 1 lb. brass
hammer.
17. Valves have complex shapes and also subject to closing stresses. These
stresses are difficult to calculate. Therefore, the thickness of valves and
flanged fittings is substantially greater than that of a simple cylinder.
18. Minimum valve wall thickness is 1.5 times (1.35 times for Class 4500) the
thickness of a simple cylinder designed for a stress of 7000 psi for valve
Classes 150-2500.
19. The formula for calculating the retirement thickness of pipe can be
adapted for valves and flanged fittings by using the factor of 1.5 and the
allowable stress for the material specified in ASME 831.3.
29. The HIC cracks formed within HAZ will propagate rapidly
in perpendicular to surface due to loss of ductility to HAZ and
due to stress this is called SOHIC.
30. The Sulphide formed during the wet H2S exposure (Fe+
H 2S - FeS -+2H) causes cracking under combined action of
Sulphide and stress (which is caused due to internal pressure
in vessel) leading to SSC.
9. The HAZ is that portion of the base metal (adjacent to the weld)
that has not been melted but whose mechanical properties or
microstructure is altered due to heat of welding. For carbon
steels HAZ includes the regions heated to greater than 1350 F
(700 C).
14. Simplest wel~bility tests are the strength and ductility test of
weld.
15. For qualifying welder on "GMAW - S" process bend tests shall
be used instead of Radiography.
IMPORTANT SUMMARY POINTS
4. Inspection lot means materials of the same type from a common source
from which a sample is to be drawn for examination. An inspection lot
does not include items from more than one heat.
5. When welding is conducted, one electrode or wire sample from each lot or
package of alloy weldrod,s.hould be positively identified.
6. Longitudinally welded alloy pipe and fittings should receive random PMI
testing verification of the base metal and weld metal.
10. When PMI testing is conducted on new or existing piping systems, records
of the results should be kept as long as the piping system exists in its
original location.
API 570- PIPING INSPECTOR PREPARATORY COURSE
(VOLUME-I)
Part-9
Additional Information
pg.l
I
U!$ 3Ull !Mill
uoo ~2,ta 1I11111
UOO ~,;!!I -'1_
.Me?5 OO::t3 II;.
1.11. 7U3 nl1tl
JAOO
~,1I(Ij)
~AOO U'~
r
F
F,
MliJlIl OIM ~
'CII!lM tUM ~
_00
461JO tHea b'.l!
me U$
~oo &,;!!I
II,;!!!
7,12
7,112
7,12
"~,lO
~
tiUII
-
~ (!,311
1I~12
$,:$11
1,92
Uri
1,12 os,,"(J
~r+Hloo . .1IiI
~!l" J ,i.MlIlll. tlfllJO
CHARTS AND TABLES
Bend I
Nominal
Size
Weight
Designation
Aver- Mini-
age mum Inside
I
Cross-
Sectional :\lomcnt
1
Sec-
tioll
II Ch~r,,:('- Radiu
j of'
o
Weight of
- - - 1 - - - 1 - - - - - - - - - - ..---+1---1---1. - - - 1- - - - -
I
Std. 40
5S' 0.065
lOS 0.109
40S 0.140
0.057
0.095
0.123
1.530
1.442
1.380
0.33
0.53
0.67
0.104
0.161
0.195
0.125
0.193
0.235
1.23
2.17
2.91
II 0.56
0.55
0.54
1.11
1.81
2.27
0.80
0.71
0.65
1;"'("
1.660 XS 80 80S 0.191 0.167 1.278 0.88 0.242 0.291 4.25 0.52 3.00 0.56
160 0.250 0.219 1.160 1.11 0.284 0.342 6.04 0.51 3.76 0.46
XXS 0.382 0.334 0.896 1.53 0.341 0.411 11.2 0.47 5.22 0.27
5f: 0.065 0.057 1.770 0.38 0.158 0.16t) 0.927 0.f5 1.27 1.07
IDS 0.109 0.095 1.682 0.61 0.24.7 0.2GO 1.63 0.63 2.0'! 0.96
:::~
Std. 40 401.' 0.145 0.127 1.610 O.SO 0.310 0.326 0.t)2 2.72 0.88
1%"
1.900 XS 80 80:::., 0.200 0.175 1.500 1.07 0.3\11 0.412 0.61 3.63 0.77
I
II
160 0.281 0.246 1.338 1,43 0.183 0.508 5.15 0.58 4.87 0.t)1
I":XS 0.400 0.350 LIDO 1.8[1 O.MS 0.5')8 8.53 0.41
I
0.55 0.41
-'-1, 5~ 00t)5 2.245 0.47 0.31D 0.205 0.5S5 082 I UiQ 1.72
10SI O.lO' 2.157 n.7S 0.499 0.420 1.02 0.80 2.61 L5S
2"
2.375
IStd. 4.0 408, 0.154
I
2.037 1.07 O.(itlG o "j>:a 1.50 I 0.79 3.65 1.45
I
I X'" SO SOS! 0.218 1.939 1.18 0.868 0.731 225 0.77 5.02
'X~:
1.28
160 I O.3~3 1.68'1 2.1P l.ll) 0.97\) 8.\1\' f 0.73 7A5 0.97
- - - - Ii
I 0.4:3Ii 1..503 2.Gii 1.31 1.10 5.57 I 0.70 n.03 0.77
IISt.(1. 40
.jS, 0083
10:3' 0.120
40::;1 0.203
2.70~
2.n:35 ,
2.4G!1
0.73
1.01
1.70
0.710
0.\188
1.53
0.494
0.1587
1.0:)
~:;~~,
1.37
II
0.(11)
0.\18
O.n,]
2.413
....D .]","'".:)
5.7\1
2 ..50
2.36
2.0S
'J~r
2.1.,~" .
2 ._{O i x S SO 80;;;1 0
'I 0:3;~
g-- I ., 2.323 1.93 1.34 0.02 7.t1G 1.84
1. ...'0 ,I
1
160 2.125 2.95 2.35 1,(H 2.SS 0.89 10.0 1.54
Ixxs 0.552 1.771 i 4.03 2.87 2.00 j 0.84 13.7 1.07
;~;
'''1
----I
1
5S1 0.083 3.334 0.89 1.30 0.741 1.21 3.7S
Std. 4.0
lOS' 0.120
40s1 0.215
.3.260
3.0c18
1.27
2.23
1.82
3.02
1.04
L72 0.%1
['
1.20
l.lLi 7.58
I 3.61
3.20
3"
3.500 XS so
160
80S 0.300
0.438
2.900
2.024
3.02
4.21
3.flO
5.04
2.2:3
2.88
1A1
2.21 1.14
1.0:1 I
10.;3
IL3
I V~Hi
2.:34
xxs 0.600 2.300 5.47 5.90 3.13 3.42 1.05 18.0 l.80
----
I 580 0.083 0.073 3.834 1.02 Ult) 0.U80 0.2(\0 1.39 3.47 5.00
lOS 0.12v 0.105 a.760 lAo 2.76 1.38 0.3Sa 1.37 4.!l7 4.81
3Y2" Stu. 40 408 0.226 O.lns 3.548 2.68' 4.79 2.39 0.71i2 1.:31 fLU 4.213
4.000 XS 80 808 0.318 0.278 3.364 3.G8 6.28 3.14 1.13 1.31 12 ..5 :3.8.'>
XXS 0.G3G 0.557 2.728 6.72 ti.85 4.(J;i ~.70 1.21 22.n 2.53
11.7
-1.27 O.(':3;~
1.27
J..JS
US
15.0
19.0
I 4.98
4.47
120 O.1=3S .>-t'2i 5.59 5.18
xxs
l()O I 0.;;:31 (I.-llif) :H38 (Uj2 ]:U 5.nO 1.C02 IA2 22 ..'i 4.02
inches
Ie = 'J/gt)
iuehe, I inches inches square ineh,,> i iIl('hcs 4 inches IHlidiu~
J ft iuc'hes w" lC u
D
1------1
t 1m d I .\ ' ---- ----
Z } , I? Tq lb per ft
Ib per ft.
____ 1_ _ _ _.1 _ _ __
5E, 0.109 0.095 5.345' 1.87 G.95 2.50 0.176 U)3 6.35 9.73
lOS 0.134 0.117 5.295 2.29 8,43 3.03 0.218 1.(12 7.77 9.53
Std, 40 40S 0.258 0.226 5.047 4.30 15,2 5.45 0.440 1.88 14.6 8.66
5" XS 80 80S 0.375 0.328 4.813 6.11 20.7 7.43 0.66Cl 1.84 20.8 7.88
5,563
120 0.500 0.438 4.563 7.95 25.7 9.25 0.936 1.80 27.0 7.09
160 0.(;25 0.547 4.313 9.70 30.0 10.8 1.23 L76 33.0 6.33
xxs 0.750 0.E55 4.063 11.3 33.6 12.1 1.55 1.72 38.6 5.62
51" 0.109 0.095 6.407 2.23 11.9 3.58 0.123 2.30 5.37 14.0
10:3! 0.134 0.117 6.357 2.73 14.4 4.35 0.153 2.30 9.29 13.7
Std. 40
(ll' I XS SO
40s1 0.280
80s1 0.432
0.245
0.378
6.065
5,761
5.58
8.40
28.1
40.5
8.50
12.2
0.334
0 ..')41
2.25
2.20
19.0
28.6
12.5
11.3
Ii 0.~li2 I 0.402
(td2.=) I
J20 5.501 I 10.7 49.6 15.0 0.735 2.15 36.4 10.3
. Ixxs HiO
i
0.d8
0.86'!
0.628
0.756
5.189 13.3
15.!}
5(1.0
66,3
17.8
20.0
0.~!8S
1.25
2.10
2.06
45.3
53.2
H.16
8.14
-._ .. --I 4. 897 1
;';'", 1
30 ! 0.277 0.242 I I 8.071 7.20 63.4 14.7 (Ll nl 2.% 24.7 22,2
,:3t(~.~ 40 .10.,,1 0.322 I 0.2821 7.\l81 8AO 72.5 16.8 0.224 2.\11 28.G 21.7
I .\:-'
,"0
<'n
Ov I.)
I 0.400
"0)1 r'.1.0-00.
0 ..
! 0.355
0 4~S I
."
7.813
7.(i25 1
10.5
12.S
88.8
lOG
20.G
24.5
O.2S!-I
0.3(i4
2.n
2.8S
35.6
43.4
20.S
HJ.8
I 100 I 0.5:13 0.519 I 7.439 15.0
I 121 28.1 O.H1 2.55 50.U 18.8
xs 60 80:01 0.500 0.438 I 9.750 1(",,] 212 39.1 0.228 3.fi3 54.7 32.3
10" so 0.593 0.519 ~1.5G4 18.0 245 '15.5 0.27G 3.fjO 64.3 31.1
lO.7S0 0.625 I 0.547 9.500 10.9 256 47.6 0.2\13 3 ..Sf! 67.5 30.7
100 0.718 0.628 9.314 22.li 286 53.2 0.342 3.56 76.9 2\).5
0.750 0.655 9.250 23.6 296 55.1 0.360 3.55 80.1 2\).1
120 0.8:~ I 0.~~8 9.0(\4 I 2\. 2 324 (;0.3 OA12 3 ..52 SQ.2 27.\1
0.8i0 O.,{.G !l.OOO I 27.1 33:3 1;2.0 OA:,1 :~.51 n2.3 27.~
I, 11(1
WO
I0.(\81 8.500
8.750 I
1.000
1.12ii
I n.Ri.,S ::lA7 3tU;
310
3li8
3fJU
(;8,4
74.3
0.505
O.:3S3 3A~1
104
lHi
2G.0
24.0
-_. --_--------__"_----__-_._-------_._P. __._---.. ______ .. __ .. _. _____ _
pg.4
CHARTS AND TABLES
C""'''_I'"~'''
SC\,-
Size Designation age mum Inside Moment
Sectional tion
Ontside and/or 'Yall Wall Diam- of teristic GO
Metal lIlod-
Diam- Schedule Thirk- Thick- e(er Inertia per C ni t '~'ra- Pipe Water
Area ulnE Bend tlon
eter Number ne::;$ neg..;::
(= Yat)
inche..c;
D
Iinc~les inches inches
t.m d
II square inches
A
inches'
I
inches'
Z
Radius
lift
h/R
inches Wp lL'",
r. lb per ft lb per ft
------ ---
5S 0.165
lOS O.ISO
0.144
0.158
12.420
12.390
I 6.52
7.11
129
141
20.3
22.0
0.050
0.055
4.45 19.6 52.5
4.44 24.2 52.2
20 0.250 0.219 12.250 1 9.82 192 30.0 0.077 4.42 33.4 51.1
30 0.330 0.289 12.090 12.9 249 39.0 0.103 4.39 43.8 49.7
Std. 4013 0.375 0.328 12.000 14.6 279 43.8 0.118 4.38 49.6 49.0
40 0.406 0.355 11.9381 15.7 300 47.1 0.128 4.37 53.5 48.5
12/1 XS 80S 0.500 0,438 11.750 I 19.2 362 56.7 0.160 4.33 65.4 47.0
12.750 60 0.5li2 0,492 11.626 i 21.5 401 62.8 0.182 4.31 73.2 46.0
80
0.025
0.687
0.547
0.601
11.500
11.376
I 23.8
26.0
439
475
68.8 0.204 4.29 80.9 45.0
74.5 0.227 4.27 88.5 44.0
0.750 0.655 11.2.';0 1 2S.3 511 80.2 0.250 4.2.'i 96.2 43.0
100 0.843 I 0.738 11.064 31.5 5G2 88.1 0.28b I 4.22 107 41.6
I
0.875 0.76G ll.ooe ! 32.n 579 ~0.8 0.2)18 I 4.21 III 41.1
I 120 1.000 0.87.5 10.750 ! 3G.9 642 I 101 0.348 4.17 125 39.3
140 I i
J.l25 0.983 10.500 ! 41.1 701 110 00400 4.13 140 37.5
160 11.313 11.14(1 10.126 i ,),7.1 781 123 OASI 4.07 160 34.9
---- !
10 I 0.2.10 I 0.21 ~ 13.500 I 10.S 255 3il.5 0.004 4.S6 36.7 62.0
20 I 0.312 I 0.273 13.:375 I 13.4 315 4.'i.0 0.080 4.8,), 45.7 60.6
Std. 30
40
I 0375
! 0.438
I 0328
0.382
13.2;;0
13. 12.j
I IG.l
IS.7
373
42[1
.53.3
lol,4
0.007
0.114
4.82
4.80
M.6
63.4
59.7
58.6
I1 13.000 I
I
I XS 0.500 0.438 21.2 4S4 !lll.1 0.132 4.78 72.1 57.5
!
60 I 0.5i13 . 0.519 . 12.S14 I 25.0 5H2 80.3 0.158 4.74 84.9 55.9
11'1
1 0.~:5
0.517 12.750 I 2G.3 5S9 SU 0.168 4.73 Sll.3 55.3
14.000 SO 0.150 0.656 12.500 I 31.2 GS7 I \18.2 0.205 4.69 I ]23
106 53.1
1 0.875 O.7Gn 12.250 I 36.1 781
I
112 0.244 1.6.5 51.1
100 I 0.\137 0.820 12.125 I 38.4 825 118 0.264 4.63 131 50.0
120
1
i 1.093
I 0.956 H.3 930 133 151 47.5
11. 814 4.58
1 0. 315 1
140
11.2.'iO l.Ofl4 11.500 I 50.1 1030 147 0.369 4.53 170 45.0
100 1.406 1.230 55.6 1120 100 0..126 4.48 189 42.6
--- 11.1 88 1
10
I 0.312
0.250
0.219 15.500 12.4 384 48.0 0.048 --~
a.DI 42.1 81.7
20 0.273 15.376 15,4 474 59.3 O.OGI .5.55 52.3 80.5
Std. 30 0.375 0.328 15.250 18,4 562 70.3 0.074 5.53 52.6 79.1
XS 40 I 0.500 0.438 15.000 24.4 732 91.5 0.100 5..i8 82.8 76.5
0.625 0.547 14.750 30.2 894 112 0.127 5.44 103 74.1
lu"
GO I 0656
0.750
0.574
I 0.655
14.688
14.500
31.6
35 9
933
1050
117 0.134
0.155
5,43
5.10
108
122
73.4
71.5
!Ii 000 fA) , n 84B 1 0.73S 11314 I 40.1 l](iO 131
Wi 0.1711 ~.37 ]30 G9.7
I I O.Si.; /
I
J
070\i 14 2.;0 I 41l; , 11\;0 14\1 0.18i 5.36 141 on.l
HlO I 1 (nJ 0 (02 13 ~138 I ~S 5 11:r,0 J7l 0.221 5.29 W,) GO.I
I"~"~
.. I
J 10
I, 'W
Il.l(:~
._ (:) '0"
IlLl
1.258
'"1).n[J"'l
- -,
J3 121 II .")U.(l
I';"S
I J[,110
J7CO
] (I;')
220
0.2118
0.325
0.2;)
c
').li
,~
102
221
02.t)
,S~.6
--
11,0 J.Gr.;)
------- ---- - - - - - - - - - - -
1.:3(14 12.814 72.1
I lSr'O I 237 ---- -------.-----------
fl.l2 0.3(18
...
55.!l 215
.Po' J
IMPACT TESTING
pg.6
PIPE REPAIR CLAMPS FOR EMERGENCY REPAIR
pg.7
Studs & nuts / Test ports
in position
End sealing
mechanism
H75016/2 P
H75016,,2P
pg.8
API 570- PIPING INSPECTOR PREPARATORY COURSE
(VOLUME-I)
Part-10
1. API 570 covers inspection, rating, repair, and alteration procedures for which of the
following that have been placed in service
a. Metallic piping systems
b. Fiberglass reinforced plastic (FRP)
c. Associated pressure relieving devices
d. All of above
3. The intent of API 570 code is to specify -------------- that is needed to determine the
integrity of piping.
a. The in-service inspection program
b. Condition-monitoringprDgramfor in service piping.
c. Both the inspection and condition-monitoring program for in service piping.
d. The condition-monitoring program for both New and in service piping
6. According to API 570, the Piping systems that are exempted from the applicable
process piping construction code are ----------- in scope of API 570 code
a. Included
b. Excluded
c. Optional
d. API 570 is silent on this aspect
7. API 570 inspection code recognizes Fitness-For-Service concepts (API 579) for
evaluating in-service damage of:
a. Pressure containing parts as well as non-pressure parts
b. Pressure containing parts
c. Non-pressure parts
d. Use of API 579 is not recognized by API 570
1. Which of the following document is referenced in API 570 for: Material Verification
Program for New and Existing Piping Systems
3. Which of the following document is referenced in API 570 for: Risk-based Inspection
4. Which of the following document is referenced in API 570 for: Safe Hot Tapping
Practices in the Petroleum and Petrochemical Industries
2. Designated areas on piping systems where periodic examinations are conducted are
called.
a. Corrosion specialist
b. Corrosion Expert
c. Corrosion Engineer
d. Piping Engineer
a. Non-specific
b. Imprecise
c. General
d. Acceptable
6. Which of the following piping can be called as "in service Piping systems".
a. Metallic equipment
b. FRP equipment
c. Any non-metallic equipment
d: None of these
a. Supplants
b. Assists
c. Supervises
d. Directs
a. Major alteration
b. Major repairs
c. Routine repairs
d. Routine alterations
a. PWHT required
b. Required inspection
c. RT required
d. Ultrasonic testing
15. Calculations to establish pressures and temperatures appropriate for a piping system,
including design pressure/temperature, MAWP, structural minimums, required
thicknesses, etc. are called
a. Re-rating
b. Derating
c. Rating
d. Changed rating
a. Indication
b. Imperfection
c. Breach
d. Division
a. management of corrosion
b. measurement of corrosion
c. management of change
d. measurement of condition
1. Who shall be responsible to the owner-user for determining that the requirements of
API 570 for inspection, examination, and testing are met.
a. Inspector
b. Repair Organisation
c. Operating Personnel
d. Piping Engineer
2. Who is responsible for implementing an effective MOC process that will review and
control changes to the process and to the hardware.
3. Who bears overall responsibility for the control of piping system inspection programs,
inspection frequencies and maintenance of piping?
4. As per API 570, an authorized piping inspector shall have certain qualifications.
Which ofthe following is not acceptable qualification to become API 570 inspector.
d. Degree in engineering plus one year experience in the design, construction, repair,
operation, or inspection of piping systems.
11
Ans: c. API 570 Annex A
a. 10 % of time
b, 20 % of time
c. 25 % of time
d. 50 % of time
a. Six years
b. Three years
c. Five years
d. Ten years
12
QUESTIONS FROM CHAPTER-5
a. The inspector
b. The inspector and/or engineer
c. The engineer
d. None of above
2. A corrosion specialist should be consulted when developing the inspection plan for
piping systems:
a. Inspection intervals
b. The type and extent of future inspection/examinations.
c. Both a and b
d. None of above
13
5. In RBI assessment includes systematic evaluation of probability of piping failure and
the associated consequence of failure. Consequence assessment shall consider In
assessing
6. When RBI assessments are used to set equipment inspection intervals, the assessment
shall be updated after
7. Safety precautions shall be included when preparing piping systems for inspection and
maintenance activities. One such organization issuing safety Regulations is "OSHA",
which means
8. Prior to entering large piping, the piping system shall be isolated from all sources of
liquids, gases, vapors. The piping system should be-------------- (Choose correct
Sequence from following)
14
d. Drained, purged, cleaned, ventilated, gas tested before it is entered.
9. Before performing any of the required inspections on piping system, inspectors should
reVIew:
a. The piping system's prior inspection results, prior repairs, current inspection plan
b. The piping system's Design calculations and drawings
c. The piping system's drawings and current inspection plan
d. The piping system's Stress analysis, flexibility calculations and inspection plan
a. Fatigue cracking
b. Caustic stress corrosion cracking
c. Hydrogen induced cracking
d. Chloride stress corrosion cracking
11. Which of the following can result in General and local metal loss
a. Graphitization
b. Temper embrittlement
c. Sulfidation
d. a and b
12. As per API 570, When possible and practical, internal visual inspections may be
scheduled for systems such as large-diameter piping systems. Such inspections should
be conducted with-----------
15
13. According to API 570, all on-stream inspections should be conducted by
14. According to API 570, thickness measurements on piping systems are normally taken
while the piping is:
a. On-stream
b. Not in operation
c. Under maintenance
d. Empty and cleaned
15. What inspector should do when the short-term corrosion rate changes significantly
from the previous identified rate to determine the cause
16
16. An inspection performed to determine the condition of the piping insulation system,
painting, and coating systems, and associated hardware; and to check for signs of
misaligmnent, vibration, and leakage is called-------------
17. According to API 570, some welds in a piping system that has been subjected to
radiography according to ASME B31.3:
a. Will meet random radiograph requirements and will perform satisfactorily in-
service without a hydrotest
b. Will not meet random radiograph requirements, and will not perform
satisfactorily in-service even though hydrotested.
c. Will meet random radiograph requirements, and will not perform satisfactorily in-
service after a hydrotest
d. Will not meet random radiograph requirements, but will still perform
satisfactorily in-service after being hydro tested.
18. The periodic external inspection should normally be conducted by the inspector, but
may be conducted by----------------when acceptable to the inspector
19. For Carbon Steel piping Inspection for CUI shall be considered for externally-
insulated piping with possibility of moisture ingress and susceptible temperature
range, which is-------------
a. Between 10 OF (-12C) and 350 OF (175 C).
b. Between 25 OF (-4 C) and 250 OF (120 C).
c. Between 32 OF (0 C) and 212 OF (100C).
d. Between 10 OF (-12C) and 250 OF (120 C).
17
Ans: a API 570 Para 5.5.4
21. The recommended downstream limit ofthe injection point circuit is .................. .
22. During periodic scheduled inspections; more extensive inspection should be applied
to an area beginning ---------------------- upstream and continuing for at least --------
-----downstream of the injection point.
23. The preferred methods of inspecting injection points to establish the minimum
thickness at each TML are--------------
18
c. Eddy current and UT
d. Radiography and/or UT
24. For thickness measurements on pipe diameters ofNPS 1 and smaller, preferred
technique is:.
a. Always
b. Not normally
c. Never
d. Usually
26. When a pressure test is required on in-service piping it -------------any heat treatment.
27. When a pressure test is required on in-service piping, API 570 has cautioned
the owner/user is to avoid --------------for the material at test temperature
19
28. To minimize the risk ofbritile fracture during a pressure test, the metal temperature
should be maintained at least --------- above the MDMT for piping that is more than
2 in. (5 cm) thick, and ------- above the MDMT for piping that have a thickness of2
in. (5 cm) or less.
29. According to API 570, when a pressure test is not performed after a major repair or
alteration acceptable alternative is:.
30. Substituting NDE procedures for a pressure test after an alteration is allowed only
after --------------- the substitution.
31. PMI testing can be accomplished by the ---------------with the use of suitable
methods as described in API 578.
a. Inspector
b. Examiner
c. Inspector and the examiner
d. Inspector or the examiner
20
32. Nonnally, thickness measurements -------------- on valves during scheduled
inspections.
34. The audit team should typically be from ------------------ experienced in refining
and/or petrochemical process plant inspection
21
QUESTIONS FROM CHAPTER-6
a. Increase
b. Decrease
c. Increase or decrease
d. None of these
a. Piping engineer
b. Owner-user or the inspector
c. Chemical Engineer
d. Piping engineer and the jurisdiction
4. Of the four classification of piping systems, which includes the majority of unit
processes and selected off-site piping?
a. Class 3
b. Class 4
c. Class 1
d. Class 2
22
5. Class 3 piping is described as being in services:
6. The appropriate inspection shall provide the information necessary to determine that
Piping is safe to operate until--------------.
8. Table 2 of API 570 contains recommended maximum inspection intervals for Classes
1,2 and 3 of piping services. Maximum intervals for Class 4 piping are ------------------
23
a. Optional.
b. Same as class 3
c. Same as class 1
d. Same as class 2
9. Piping systems that are known to have a remaining life of over years or
that are protected against external corrosion need not have insulation removed for the
periodic external inspection.
a. 10
b. 15
c. 5
d. 20
10. If Piping Service is Changed then-------------shall be established for the new service.
11. As per API 570, Services with the ------------------------ are in Class 1.
24
a. Fluids that can rapidly vaporize during release, are class l.
b. On-site hydrocarbon fluids that will slowly vaporize during release
are class 2
c. Hydrocarbon Fluids that do not significantly vaporize during release
are class 3
d. All of above
a. Services that are essentially nonflammable but may be toxic are in Class
4,
b. Services that are essentially flammable and nontoxic are in Class 4,
c. Services that are essentially nonflammable and nontoxic are in Class 4,
d. Services that are essentially flammable and toxic are in Class 4,
a. API 579
b. API 578
c. API 577
d. API 576
15. As per API 570 , test and inspection intervals for pressure-relieving devices in typical
process services should not exceed:
25
QUESTIONS FROM CHAPTER-7
1. If LT and ST corrosion rates are showing different values, The authorized inspector,
in consultation with a corrosion specialist, shall select the corrosion rate that-------------
2. You have a new piping system that has just been installed. It is completely new and no
information exists to establish a corrosion rate. Also, infOlmation is no available on a
similar system. You decide to put the system in service and NDT it later to determine
the corrosion rate. How long do you allow the system to stay in service before you
take your first thickness readings?
a. 1 month
b. 3 months
c. 6 months
d. 12 months
3. When the MAWP is recalculated, the wall thickness used in these computations
shall be the actual thickness determined by inspection--~---------------
a. Minus the estimated corrosion loss before the date of the next
inspection
b. Plus the estimated corrosion loss before the date of the next inspection
c. Minus twice the estimated corrosion loss before the date of the next
inspection
d. Plus twice the estimated corrosion loss before the date of the next
inspection
4. Inspection deferral is appropriate when the piping circuit's current interval is still
considered to be correct given the available data but an extension of the inspection date
based on --------------
26
a. A documented stress analysis process is acceptable to the inspector
b. A documented risk analysis process is acceptable to the inspector
c. A documented flexibility analysis process is acceptable to the inspector
d. A documented both sress and flexibility analysis process is acceptable to
the inspector
a. The lowest grade material and joint efficiency in the applicable code
may be assumed for calculations.
b. Samples must be taken from the piping and testing for maximum
tensile stress and yield strength will determine the allowable stress to
be used.
c. The piping made of the unknown material must be removed from
service and current piping of known material must be installed.
d. The piping of unknown material may be subjected to a hydrostatic
stress tests while having strain gages on it to determine its yield
strength and thus allowable stress.
6. As per API 570, Piping system and pressure-relieving device records shall contain
four types of information pertinent to mechanical integrity. Which ofthe following
is NOT part of these records.
27
b) Inspector
c) Piping system owners and users
d) Jurisdiction
e) Examiner
28
QUESTIONS FROM CHAPTER-8
1. When making repairs and alterations to piping systems, the principles of ---------------
-------- shall be followed:
a. ASME B31.3
b. Code to which the piping system was built
c. Orb.
d. ASME B&PV Code
2. Repair and alteration work must be done by a repair organisation as defined in API
570 and must be authorised by the prior to its commencement:
a. Jurisdiction
b. Inspector
c. Owner-user
d. Examiner
a. Alteration work
b. Repair work
c. Any repair as well as alteration work
d. Replacement of any piping component
4. What type of repairs and procedures may the inspector give prior general
authorisation to continue (provided the inspector is satisfied with the competency
ofthe repair organisaton)?
29
c. Alterations and re-ratings .
d. Minor re-ratings and alterations
a. Owner-user
b. Jurisdiction
c. Examiner
d. Analyst
a. Examiner
h. piping engineer
c. Inspector
d. Corrosion engineer
30
7. What type of defect, should not be repaired by a full encirclement welded split
sleeve?
a. A longitudinal check
b. A circumferential crack
c. Pits that are one half through wall
d. General corrosion in the longitudinal direction.
8. If a repair area is localised (for example, pitting or pin-holes) and the specified
minimum yield strength (SMYS) of the pipe is not more than psi, a
temporary repair may be made by fillet welding a properly designed plate patch over
the pitted area:
a. 30,000 psi
b. 55,000 psi
c. 40,000 psi
d. 36,000 psi
9. Insert patches (flush patches) may be used to make permanent repairs. One of the
condition for making these is that :
31
10. Insert patches may be used to repair damaged or corroded areas of pipe if several
requirements are met. One of these is that an insert patch shall have rounded
comers with minimum radii.
a. 0.375"
b. 0.50"
c. 0.75"
d. 1"
13. For carrying out repairs by welding qualified welding procedures and welders have
to be used. Who ------------------shall maintain records of welding procedures and
welder performance qualifications.
a. Repair organization
b. Inspector
c. Owner-user
d. Examiner
32
14. The records of welding procedures and welder performance qualifications shall be
available to the inspector:
a. 150
b. 200
c. 300
d. 350
a. An engineer
b. The inspector
c. The piping engineer
d. The repair organisation
33
18. As per API 570, pressure tests normally required----------
19. When a pressure test is not necessary or practical, NDE shall be utilized in lieu of a
pressure test after consultation with --------------------
a. The inspector
b. Piping engineer.
c. The inspector and the piping engineer.
d. Corrosion specialist.
20. As per API 570, Rerating of piping systems can be done under certain conditions
which of the following is/are such conditionls for perfortning Rerating
21. As per API 570, Rerating of piping systems can be done under certain conditions
which ofthe following is/are such conditionls for performing Rerating
a. Rerated piping systems shall be leak tested unless a previous leak test was
done at greater than or equal to the test pressure for the new condition.
b. Full radiography of all butt welds must be performed.
c. PMI testing of piping systems shall be done
d. A and C above
34
QUESTIONS FROM CHAPTER-9
a. 3-Itlonth intervals
b. 6-month intervals
c. Once a year
d. Once every 3 years
2. Corrosion cells can form on Buried pipes (both bare and coated pipe) where bare steel
contacts the soil. How can these cells be detected ?
3. A pipe coating holiday survey is used to locate coating defects on coated pipes. More
often, it is used on buried pipeto--------------
35
Ans: a API 570 Para 9.2.6
a. Holiday detector
b. Intelligent pigging.
c. Boroscopes.
d. Wenner Four-Pin Method
6. For piping buried in lengths greater than 100 feet (30 m)and not cathodically
protected, evaluations of soil corrosivity should be performed at ---------
7. How often should poorly coated pipes withinconsistent cathodic protection potentials
have a pipe-to-soil potential survey made?
a. Yearly
b. Every 2 years
c. Every 3 years
d. Every 5 years
36
d. Only on small bore piping
a. Cathodically protected
b. Not painted and not cathodically protected
c. Painted and cathodically protected
d. Not cathodically protected
10. An alternative or supplement to inspection of buried piping is leak testing with liquid
at a pressure at least % greater than the maximum operating pressure
a. 5
b. 25
c. 10
d. 50
11. In a certain leak test for a buried piping system, specified Leak test pressure was 200
psi and piping was pressurized to this pressure. Four hours after the initial
pressurization of the piping system, the pressure dropped to 285 psi . As per API
570, What should be done?
37
Ans: c API 570 Para 9.3.7
12. If buried piping leaks are repaired by putting clamps and reburied What shall be done
as per API 570:
38
Practice questions API-570 course
1) A 18" O.D. pipe has a corroded area on it. What is the maximum size of a fillet
patch that may be used to repair the corroded area?
a. 3.5"
b. 9"
c. 6"
d. 6.5"
2) A 10' long carbon steel pipe is welded to a 10 '1ong 18-8 stainless pipe and is
heated uniformly to 475 degrees F from 70 degrees F. Determine its total
length after heating
a. 20.067'
b. 20.156'
c. 20.234'
d. 20.095'
3) A seamless NPS 10 pipe, ASTM A106 Grade B material operates at 750 psi
and 700 degrees F maximum. Considering only pressure design thickness,
what minimum thickness is required?
a. 0.244"
b. 0.200"
c. 0.282"
d. 0.173"
4) A seamless NPS 6, ASTM A106 Grade A pipe operates at 300 degrees F and
765 psi. The allowable stress is 16,000 psi. Using the Barlow equation,
determine the retirement thickness for these conditions
a. 0.446"
b. 0.332"
c. 0.231"
d. 0.158"
5) A seamless NPS 10 pipe, ASTM A106 Grade B material, operates at 750 psi
and 700 degrees F (maximum). The thickness of the pipe as determined by the
last inspection is 0.30". The pipe has been in service for 10 years. The original
39
thickness (measured when installed) was 0.365 11 Two years previous to the
0.30 11 measurement the thickness of the pipe was measured to be 0.3r.
Determine the greatest corrosion rate i.e. short or long term
40
Practice questions API-570 course
41
Practice Questions API-570 course
ASME B 31.3 PROCESS PIPING
Closed Book
Q1) Piping code to be adopted for process piping within a large fertilizer
factory will be:
Q2) Most of the fluids normally covered by B 31.3 code falls under
Category
a. Category M
b. Category K
c. Category D
d. Normal
Q3) The term 'Y' in pipe thickness formula in B 31.3 represents numerical
factor of value.
Q4) Impact test is to be conducted with how many specimen for applying
acceptance criteria of ASME B 31.3
Q5) ASME B31.3 applies to piping for all fluids except for which of the
below?
42
Q6) As per ASME 31.3, the increased quality factors by conducting
additional NDT is permitted for:
a. ERWpipes
b. Seamless pipes
c. Electric fusion welded pipes
d. All types of pipes
Q9) ASME B 31.3 code is meant for new piping installations in:
43
Q11) The requirements of the latest edition of ASME Code Section B 31.3 and
any subsequent Addenda become effective:
a. D
b. C
c. M
d. N
Q13) A fluid service in which the potential for personnel exposure is judged to
be significant and in which a single exposure to a very small quantity of a
toxic fluid, caused by leakage, can produce serious irreversible harm to
persons on breathing or bodily contact, even when prompt restorative
measures are taken is known as a category fluid.
a. D
b. M
c. H
d. N
a. Tack weld
b. Seal weld
c. Fillet weld
d. Butt weld
Q15) In the equation tm = t + c, pick the correct definition of the value "tll.
44
a. Minimum required thickness, including mechanical,
corrosion, & erosion allowances
b. Pressure design thickness, as calculated for internal
pressure.
c. Nominal wall thickness (As per purchase
specification)
d. Minimum design temperature of the pipe
Q17) The pre-heat zone shall extend at least -----inch beyond the edge of the
weld.
a) Above
b) Below
c) On or above
d) On or below
45
b) Curve A material is most brittle
c) Curve D material is most brittle
d) Curve B material is most brittle
Q21) As per ASME B 31.3,the code used for Qualification of Welding Procedure
and welders is:
a) ASME Sec. IX
b) API 1104
c) Anyone of a or b above may be used.
d) Both a and b above must be used
a. Three specimen
b. At least two specimen
c. Minimum three specimen
d. Maximum three specimen
a. Pipethk~r
b. Pipethk~%11
c. Ambient temp is less than OoC
d. None of above
Q25) If Two pipes different pre-heat requirements say tl and tz are to be welded,
the pre- heat for their joining shall be
46
b. Lower of tOl and t02
c. Average of tOl and t02
d. None of above
Q26) To have a safe Pressure Test of Piping which type of test will you
recommend?
a) Hydrostatic
b) Pneumatic
c) Either a or b both are equally safe.
d) Code does not accept a or b
Q28) What is the only category fluid service that may be subject to an initial
service leak test?
a) Category M
b) Category D
c) Category N
d) Category K
Q29) What will be Hydrotest pressure for a piping system with design pr = 100
psig, and safe stress at design condition is 18,000 psi while safe stress at test
condition (ambient) is 19,800 psi?
a. 150 psig
b. 130 psig
c. 165 psig
d. N one of above
a. 40 psig
b. 20 psig
c. 25 psig
d. 80 psig
47
Q31) For pressure testing of piping systems, which of the following
statement(s) are correct?
Q32) According to ASME B 31.3 ,In case of fabricated piping Pressure test is
conducted
Q33) What is the minimum time that a leak test must be maintained as per B
31.3?
a. 60 minutes
b. 45 minutes
c. 30 minutes
d. 10 minutes
a. 10 years
b. 8 years
c. 6 years
d. 4 years
48
Q35) After PWHT, the hardness of weld and Heat affected Zone will generally -
a. Increase
b. May increase or reduce.
c. Remain unaffected.
d. Reduce.
49
Practice Questions API -570 course
ASME B 31.3 PROCESS PIPING
Closed Book- Answer Key
Q.NO. ANSWER
1 B
2 D
3 C
4 A
5 A
6 C
7 C
8 B
9 B
10 B
11 C
12 A
13 B
14 B
15 B
16 D
17 a
18 a
19 b
.- -
20 d
21 b
22 c
23 b
24 d
25 a
26 a
27 a
28 b
29 d
30 b
31 c
32 b
33 d
34 a
35 d
50
Practice questions API-570 course
ASME B 31.3 PROCESS PIPING
Open Book
Ql) What is the longitudinal weld joint factor, Ej, for API 5L ERW (Electric
Resistance Welded) pipe?
a. 1.00
b. 0.95
c. 0.S5
d. 0.60
Q2) "S" is defined as the stress value for material from Table A-l of ASME
B31.3. Pick the value of "S" when the material is ASTM A335 Grade P5 and
the temperature is 950 degrees F.
a. llAOO psi
b. 10,600 psi
c. S,OOO psi
d. .20,00 psi
Q3) Select appropriate Y factor for Austenitic Stainless Steel pipes for Design
temperature of 630 deg. C.
Q4) A Water piping with Design Pressure=lS0 psig and Design temperature=-
10 deg. F, will be classified as Fluid Service
Q5) If Design temperature in above question is changed to -30 deg.F what will
be the fluid service.
Q6) Water piping with Design Pressure=130 psig and Design temperature= -10
deg. F, will be classified as Fluid Service
51
a.D. b.M c. High Pressure d. Normal
Q7) NPS 12, Sch 80 and Sch 160 pipes (M.O.C = A 106 gr B) are to be used at (-100 C)
Determine whether,
Q9) A flat plate (without joints) is used as permanent blank for flanged point
with gasket I.D = 200 mmDesign pro = 200 psi and safe stress value for plate
; ,i
is 18,000 psi, for given temperature of 2500 C What shall be the minimum
blank thickness from given options? Corrosion allowance is Nil code of
construction B 31.3.
a.8mm
b. 10mm
c. 12mm
d. 14mm
52
Joint 3: P No.3, thk = 20 mm, Hardness = 228 HB
Your assessment is:
a) All joints are okay as per ASME B 31.3
b) Joint 2, and 3 are okay, joint 1 not okay
c) Only joint 1 is okay. Joint 2, and 3 are not
d) None of the above are correct answers.
Qll) An ASTM A53 Grade B pipe with a maximum wall thickness of 0.75/1 is
being considered for use in a cold service. What minimum temperature can it
be used and not have an impact test?
a. +20 degrees F
b. +15 degrees F
c. +10 degrees F
d. 0 degrees F
Q12) PWHT is required for all SMTS of piping over 1/2 inch for which of the
following materials?
a. P Nos. 1 and 2
b. P Nos. 1 and 3
c. PNos.2and3
d. PNos.4and5
Q13) A piping system has design pressure=200psig. The piping material has
allowable stress at design temperature=16000psi. It has allowable stress at test
temperature=17600 psi. Its minimum Hydro test pressure will be
a 300 psi b. 330 psi c.260 psi d. 220 psi.
53
b) Reject
c) Accept only if it is Stainless steel pipe
d) Reject only if it is Stainless steel pipe
Q16) A radiograph taken on Girth weld of 12 mrn thick piping in Severe Cyclic
condition shows a slag inclusion of length= 8 mrn . Is the slag length
acceptable as per ASME B 31.3?
a. Accept
b. Reject
c. Accept only if it is Stainless steel pipe
d. Reject only if it is Stainless steel pipe
Q17) PWHT is required for all SMTS of piping over % inch for
which of the following materials?
a. PNos.1 and 2
b. P Nos. 1 and 3
c. P Nos. 2 and 3
d. PNos.4and5
Q18) Piping system has design pressure=150 psig. Its Pneumatic test pressure
. will be
Q20) ASME B 16.5 permits pipe flanges made from plates for which of the
following type?
a. Slip on type
b. Weld neck type
c. Blind flanges
d. None of above
Q21) Suitable Class for pipe flanges (AI05) for Design pr = 400 psi, design
temp = 4000F will be:
a) Class 600
b) Class 300
c) Class 400
54
d) None of the above
Q22) What will be the System Hydrostatic Test pressure for above flange.
a. 300psig
b. 1000psig
c. 1100psig
d. 1125 psig
Q23) A carbon steel ASTM A 106 Grade B material is being impact tested.
What is the minimum average energy requirement for this material
(average for 3 specimens-fully deoxidized steel)?
a. 7 ft-lbs
b. 10 ft-lbs
c. 13 ft-lbs
d. 15 ft-lbs
Q24) Where the design temperature of the system is the same as the
hydrostatic test temperature, the hydrostatic test pressure shall not be
less than: (Yield stress during hydrotest is not governing factor.)
Q25) A NPS 10 pipe made from ASTM A53 Grade B carbon steel is to be
checked for thickness (t). The pipe operates at 975 degrees F. Determine the
coefficient Y.
a. 0.4
b. 0.5
c. 0.6
. d. 0.7
Q26) You have a fluid that does not operate at high pressure. The fluid is not
toxic. The fluid is not flammable. Exposure to the fluid will not cause damage
to human tissue. The design gage pressure is 120 psi and the operating
temperature is 1000F. What category fluid service would you design?
55
c. Category M fluid service
d. High pressure fluid service
Q27) If a pneumatic Pressure test test is used, the test pressure shall be
_ _ _ _ % of design pressure.
a. 50
b. 150
c. 125
d. 110
a. 5
b. 10
c. 15
d. 20
56
Practice questions API-570 course
ASME B31.3 PROCESS PIPING COURSE
Open Book Answer Key.
Q.NO. ANSWER
1 c
2 c
3 d
4 d
5 d
6 a
7 b
8 a
9 b
10 d
11 b
12 d
. 13 b
14 b
15 a
16 b
17 b
18 c
19 a
20 c
21 b
22 d
23 c
24 d
25 b
26 b
27 d
28 b
29 b
57
Practice questions API-570 course
API-578 recommended practice
CLOSED BOOK
Ql) API 578 provides guidelines for a quality assurance system to verify:
a all metals.
b. all alloy materials.
c. non-ferrous materials.
d. For Carbon steels
Q3) Who has the responsibility to verify that the material verification program
is properly implemented?
a. Authorized inspector
b. Owner/User
c. Repair organization
d. Engineering organization
Q6) Who has the responsibility to determine the extent of PMI testing required
on existing piping systems?
58
a. Authorized inspector
b. Owner/User
c. Repair organization
d. Engineering organization
Q7) PMI tools that use X-Ray fluorescence can not detect:
a. carbon content.
b. chrome content.
c. iron content.
d. molybdenum content.
59
Practice questions API-570 course
Api-578 recommended practice
1 b
2 d
3 b
4 c
5 a
6 b
7 a
8 c
60
Practice questions API-570 course
ASME B 16.5
PRACTICE QUESTIONS - OPEN BOOK
a. 170
b.290
c. 300
d. 400
a. 1000 0 F
b. 1300 0 F
c. 1180 0 F
d. 2000 0 F
a. 1125 psig
b. 450 psig
c. 1000 psig
d. None of the above
a. 2250 psi
b. 1500 psi
c. 1000 psi
d. None of the above
61
Practice questions API-570 course
ASME B 16.5
1. b
2. a
3. a
4. a
62
API 570 CERTIFICATION PREPARATORY COURSE
Practice Questions. ( Closed Book)
ASME Sec. V
a. Carbon steels
b. Ferritic stainless steels
c. Austenitic stainless steels
d. None of the above
3. The scope of the ASME Boiler and Pressure Vessel, Code, Section V includes:
63
4. For Ammeter calibration for Magnetising equipment, The allowable tolarence
is:
a. . 5%
a. + 10 %
b. + 15 %
d. . 20
a. Qualification of personnel
b. Calibration of NDE equipments
c. Correct procedure for NDE
d. All of the above
64
7. Describe how a liquid penetrant examination should be performed in order to
detect discontinuities, which are open to the surface :-
(a) clean the part, apply the developer, apply the penetrant, remove excess
penetrant, inspect the part, clean the part;
(b) clean the part, apply the penetrant, remove excess penetrant, apply the
developer, inspect the part, clean the part;
(c) clean the part, apply the developer, apply the penetrant, inspect the part,
remove excess penetrant, clean the part;
(d) clean the part, apply the developer, apply the penetrant, inspect the part,
clean the part.
8. When reviewing a radiograph, a light image of the letter B can be seen on the
film
65
a. Each year
b. Each two years
c, When possible
d. Every 6 months
11. For MT examination by Prod technique the spacing between prods shall be
between
a. 4 inch to 12 inch
b. 4 inch to 10 inch
c. 3 inch to 10 inch
d. 3 inch to 8 inch
13. What is the difference between an inspection and an examination per Section V of
the ASME Code?
a. Inspection performed AI
b. Examination performed by manufacturer's personnel
c. There is no difference between the two
d. Both a and b, above
66
Ans. d ... Ref. ASME V . T-170
14. In pulse -echo contact method, When does a considerable Vee - error will result
while measuring thickness?
15. In pulse -echo contact method which disply of UT results is recommended when
reflecting surface is rough.
a. CRT display
b. Direct Digital display
c. Any of a or b are OK
d. UT is prohibited when reflecting surface is rough
67
API 570 CERTIFICATION PREPARATORY COURSE
Practice Questions. ( Closed Book)
ASME Sec. IX
(a) that portion of the base metal which has not been melted;
(b) whose mechanical properties or micro structures have been altered by the heat of
welding;
(c) is least likely to contain discontinuities;
(d) both (a) and (b) above.
3. A welder may deviate from the parameters specified in WPS if they are nonessential
variables :-
68
(c) No;
(d) Nonessential variables only apply to PQRs
1. A welder is a qualified welder but gives consistently defective weld. What will be
your action as a Quality Control Manager?
5. Tensile test was carried out for qualifying a welding procedure (PQR). The specified
minimum tensile strength of the base metal is 70,000 psi. If the test specimen
breaks in parent metal (outside weld and fusion zone) and the tensile strength
calculated is 68,000 psi.
6. A weld procedure is qualified in 1G position. This procedure can be used for welding
in positions
a. 1G
b. 2G
c. 4G
69
d. all of the above
6"
12"
15"
d. Radiography can not be used for welder qualification
Ans a. REF: Section IX, QW- 302.2
9. When a tensile specimen breaks in the base metal outside of the weld
or fusion line, the strength recorded may be at most __ below the
specified tensile and be accepted.
A. 3.5%
B. 0.5%
C. 5%
D. All of the above
70
10. The basic purpose of testing a welder is to establish the welder's
a. Knowledge of welding requirements
b. Ability to deposit sound weld metal
c.. Mechanical ability to operate equipment
d.. General attitude toward welding inspectors
11. What is the number of transverse guided bend tests required for
Performance Qualification in a 6G position?
a. 2 b. 3 c. 4 d. 6
a. 3 months
b. 6 months
c. 9 months
d. 12 months
71
13. Groove weld test may be used for qualification of welders.
Which of the following shall be used for evaluation?
a. Only bend tests
b. Only radiography
c. Both radiography and bend tests
d. Either bend tests or radiography
72
API 570 CERTIFICATION PREPARATORY COURSE
Practice Questions. ( Open Book)
ASMESec. V
1. The recommended minimum development time allowed for a material made of high
temperature alloy is
a.5min
b. 10 min
c. 7 min
d. 60 min
2. What is the geometric unsharpness allowed as per code for a thickness of 2.0" (50.B
mm) as per code?
1. 0.020" ( 0.50Bmm)
2. 0.030" (.00.762mm)
3. 0.010 (O.254mm)
4. None of the above
3. For steel plates and welds to be checked by LPI, what shall be the penetration time
for Penetrant
73
d) 5 min for weld, 10 min for plate
4. A 1" thickness butt weld has 0.125" acceptable reinforcement was radiographed.
The applicable plate type penetrameter on (Film side) and essential hole shall be
a. ASME 30 - 2T
b. ASME 25 - 2T
c. ASME 20 - 2T
d. ASME 30 - 4T
5. What weight shall be used to check adequacy of lifting power of a permanent magnet yoke. ?
a. Annually
b. Every 90 days
c. Whenever it is turned on
d. As required by the Examiner
a. 48 mm
74
b. 47mm
c. 53mm
d. 52mm
9. What wire No. shall make image on the film If type of penetrameter ,is wire type which
was put source side . Nominal single wall thickness is 0.875 inch and
permissible reiforcement is 0.125 inch. (wire decimeter in inch)
a. A and B
b. Band C
c. C and 0
d. Aand 0
75
API 570 CERTIFICATION PREPARATORY COURSE
Practice Questions. ( Open Book)
ASME Sec. IX
2. In a certain PQR for SMAW, the electrodes used for all passes were of AWS
classification (E 7018). Corresponding WPS also showed filler materials as E
7018. Now the manufacturer proposes to change the filler material in WPS to E
7015. Will you ask manufacturer to:
76
for approval
3. What positions are necessary to qualify a welder for all position pipe
welding?
E. 3G and 4G
F. 2G and 5G
G. 3G and 1G
H. 4G and 5G
a 50F
b. 100F
c. 125F
d. 150F
1. Hardness
2. Composition, weldability & mechanical properties
3. Ductility only
4. None of the above
77
6. A groove weld was made with 1 %" thickness plate with SMAW process for PQR
Qualification and the test were found acceptable. This PQR can be used up to a
maximum weld thickness of:
1. 1 %"
2. 2.5"
3. 8"
4. None of the above
(a) F, V;
(b) F only;
(c) F, V, 0;
(d) ALL
(a) 3Gand1G
(b)1Gonly
(c) None. Procedure does not qualify performane. (d) must requalify ( d) All
positions
9. A welding procedure qualified on % inch thick plate can be used to weld groove welds
in materials from to :-
78
(c) 3/8 to 3/4; (d) 1/16to 1/2.
a 1,
b 2,
c 4,
d 5.
79
API 570 CERTIFICATION PREPARATORY COURSE
Practice Questions. ( Closed Book)
QUESTIONS ON API RECOMMENDED PRACTICES
0.1 Temper embrittlement typically takes place with which of the following materials:
0.2 Brittle fracture typically takes place with which of the following materials:
80
0.4 Erosion/Corrosion can be controlled by :
a. Mechanical fatigue.
b. Creep failure.
c. Stress corrosion cracks.
d. Hydrogen induced cracks.
81
Ans: d Reference: API RP 571 4.3.4
0.8. The dissolved gases which cause Boiler water condensate corrosion are:
o. 9 What construction material will you suggest where you are expecting serious
Sulphidation problem.
0.10 Characteristic of Chloride SCC in Austenitic S.S. is: Cracks which are:
82
b. Hydrogen blistering may occur on 1.0, 0.0, or any where within wall thickness of
the pressure vessel.
c. High hardness & High strength steels are more likely to undergo damage due to
wet H2 S compared to low strength/low hardness steels
d. All of the above are correct statements
83
QUESTIONS ON API RECOMMENDED PRACTICES
a Recordable indication
b Reportable indication
c both a and b
d None of above
84
4. A sub -surface terrace and step-like crack with basic orientation parallel to the
base metal surface caused by tensile stresses normal to thickness direction is
called
a. Lamination
b. Step-wise cracking
c. Lamellar tearing
d. Stress corrosion crack
a. SMAW
b. c and d below
c GTAW
d GMAW
a. Radiography only
b. Bend tests only
c. Either radiography or bend tests
d. Both Radiography and bend tests
a. within 6" - 24" with angle less than 30 with the surface
b. within 6"- 24"with angle not less than 30 with surface
c. within 24" with angle less than 30
85
d. beyond 24"with angle not less than 30
a. Preheating only
b. Pre-heating & PWHT
c. No pre- heating or PWHT
d. PWHTonly
86
Ans: a Reference: API RP577
12. A method to assure that PWHT on the welds was performed satisfactorily is
to perform which of the following after PWHT
13. Among the following Welding processes, identify the one that has highest
me;tal deposition rate
a. all of below.
b. GTAWfoliowed by SMAW
c. GMAW
d. SAW
14. A welding process which allows welding to be done without adding filler
metal is
a. SMAw
b. GTAW
c. GMAW
d. FCAW
87
b. Susceptibility of Hydrogen assisted Cracking decreases
c. Tensile Strength of the weld decreases
d. All of above"
88