PRESUPUESTO GENERAL DEL PROYECTO

VALOR REFERENCIAL 2 (VR2)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

TITULO DE PRECIO COSTO


ITEM. UNID. METRADO SUB-TOTAL
PARTIDA UNITARIO PARCIAL

01.00.00 OBRAS PRELIMINARES


01.01.00 CARTEL DE OBRA PREFABRICADO UND 1.00 296.61 296.610 32,365.31
01.02.00 FLETE TERRESTRE GLB 1.00 32068.70 32068.697

02.00.00 RED DE COLECTORES


02.01.00 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL M2 3,823.38 1.12 4272.035
02.01.02 TRAZO Y REPLANTEO LINEAL ML 6,372.31 0.67 4282.395 8,554.43

02.02.00 MOVIMIENTO DE TIERRAS


02.02.01 EXCAVACION MANUAL MATERIAL SUELTO M3 5,406.19 9.31 50338.152
02.02.02 EXCAVACION MANUAL ROCA SUELTA M3 855.72 13.97 11951.627
02.02.03 REFINE Y NIVELACION DE ZANJA ML 6,372.31 0.56 3560.029
02.02.04 CAMA DE APOYO, e = 5 cm. M2 3,823.38 1.28 4886.222
02.02.05 RELLENO Y COMPACTACION DE ZANJA ML. 6,372.31 4.52 28783.385 99,519.41

02.03.00 INSTALACION DE TUBERIAS


02.03.01 INSTALACION DE TUBERIAS PVC 160 mm ISO 4435 ML 6,372.31 15.21 96950.940
02.03.02 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435 ML 0.00 22.08 0.000
02.03.03 PRUEBA HIDRAULICA ML 6,372.31 1.14 7280.511 104,231.45

03.00.00 LINEA EMISOR


03.01.00 LIMPIEZA DE TERRENO MANUAL M2 497.73 1.12 556.136
03.02.00 TRAZO Y REPLANTEO LINEAL ML 829.55 0.67 557.485
03.03.00 EXCAVACION MANUAL MATERIAL SUELTO M3 1,374.63 9.31 12799.419
03.04.00 EXCAVACION MANUAL ROCA SUELTA M3 312.46 13.97 4364.055
03.05.00 REFINE Y NIVELACION ZANJA ML 829.55 0.47 386.206
03.06.00 CAMA DE APOYO, e = 5 cm. M2 497.73 1.28 636.091
03.07.00 RELLENO Y COMPACTACION DE ZANJA ML 829.55 7.22 5988.726
03.08.00 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435 ML 829.55 21.80 18086.302
03.09.00 PRUEBA HIDRAULICA ML 829.55 1.14 947.781 44,322.20

04.00.00 CONSTRUCCION DE BUZONES


04.01.00 EXCAVACION MANUAL MATERIAL SUELTO M3 372.50 9.31 3468.391
04.02.00 EXCAVACION MANUAL ROCA SUELTA M3 69.27 13.97 967.510
04.03.00 BUZON TIPO I DIAM=1.20, H=1.20 a H=1.50 UND 100.00 556.37 55637.155
04.04.00 BUZON TIPO II DIAM=1.20, H=1.50 a H=2.00 UND 20.00 686.43 13728.547
04.05.00 BUZON TIPO III DIAM=1.20, H=2.00 a H=2.50 UND 8.00 817.29 6538.333
04.06.00 BUZON TIPO IV DIAM=1.20, H=2.50 a H=3.00 UND 5.00 968.72 4843.585
04.07.00 BUZON TIPO V DIAM=1.20, H=3.00 a H=3.50 UND 0.00 1288.73 0.000
04.08.00 BUZON TIPO VI DIAM=1.20, H=3.50 a H=4.00 UND 4.00 1345.26 5381.031
04.09.00 CONCRETO fc= 210 Kg/cm2 PARA PANTALLA DE BUZON CON CAIDA M3 0.65 270.50 175.282
04.10.00 ENCOFRADO Y DESENCOFRADO M2 6.12 18.67 114.256
04.11.00 ACERO DE REFUERZO KG 43.54 2.06 89.753
04.12.00 SUMINISTRO Y COLOCACION DE ACCESORIOS BUZON DE CAIDA UND 3.00 200.60 601.811 91,545.65

05.00.00 PLANTA DE TRATAMIENTO


05.01.00 CAMARA DE REJAS
05.01.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.85 9.31 35.848
05.01.02 SOLADO DE CONCRETO 1:10 e=10cm. M2 0.19 57.82 11.131
05.01.03 CONCRETO fc= 175 Kg/cm2 EN LOSAS M3 1.50 227.66 340.871
05.01.04 ENCOFRADO Y DESENCOFRADO M2 16.05 18.67 299.642
05.01.05 ACERO DE REFUERZO KG 2.41 2.06 4.964
05.01.06 REVESTIMIENTO CON MORTERO 1:5 M2 8.20 12.29 100.789
05.01.07 SUMISTRO Y COLOCACION DE REJILLA 1/4"x1/2"xL 1 1/4" M2 0.62 160.61 99.578 892.82

05.02.00 DESARENADOR
05.02.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.13 9.31 29.163
05.02.02 CONCRETO fc= 175 Kg/cm2 M3 1.52 227.66 346.165
05.02.03 ENCOFRADO Y DESENCOFRADO M2 17.76 18.01 319.827
05.02.04 ACERO DE REFUERZO KG 1.08 2.06 2.216
05.02.05 TARRAJEO DE MUROS CON MORTERO M2 7.92 10.43 82.573
PRESUPUESTO GENERAL DEL PROYECTO
VALOR REFERENCIAL 2 (VR2)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

TITULO DE PRECIO COSTO


ITEM. UNID. METRADO SUB-TOTAL
PARTIDA UNITARIO PARCIAL

05.02.06 SUMISTRO Y COLOCACION ACCESORIOSDE REJILLA 1/4"x1/2"xL 1 1/ UND 1.00 486.85 486.848
05.02.07 COMPUERTA METALICA 0.45 x 0.50 mts. x 3/16" UND 1.00 135.59 135.593 1,402.39

05.03.00 CAJA DE DISTRIBUCION


05.03.01 EXCAVACION MANUAL MATERIAL SUELTO M3 1.44 9.31 13.408
05.03.02 CONCRETO fc= 175 Kg/cm2 M3 0.49 227.66 112.467
05.03.03 ENCOFRADO Y DESENCOFRADO M2 7.48 18.67 139.646
05.03.04 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 5.50 10.43 57.343
05.03.05 COMPUERTA METALICA C/BORDES METALICOS UND 2.00 127.12 254.237 577.10

05.04.00 CAJA DE INSPECCION


05.04.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.60 9.31 33.520
05.04.02 CONCRETO fc= 175 Kg/cm2 EN MUROS M3 1.68 227.66 383.388
05.04.03 ENCOFRADO Y DESENCOFRADO M2 24.20 18.67 451.797
05.04.04 ACERO DE REFUERZO KG 24.44 2.06 50.392
05.04.05 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 38.40 10.43 400.355 1,319.45

05.05.00 TANQUE IMHOFF 02 UNIDADES


05.05.01 LIMPIEZA DE TERRENO MANUAL M2 228.00 1.12 254.754
05.05.02 TRAZO Y REPLANTEO M2 73.71 1.31 96.651
05.05.03 EXCAVACION MANUAL MATERIAL SUELTO M3 613.11 9.31 5708.771
05.05.04 RELLENO Y COMPACTADO DEL PISO M3 28.88 22.88 660.946
05.05.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 MTS M3 730.28 4.66 3399.892
05.05.06 CONCRETO fc= 210 Kg/cm2 M3 136.22 253.76 34566.921
05.05.07 CONCRETO fc= 175 Kg/cm2 M3 1.65 227.66 375.647
05.05.08 ENCOFRADO Y DESENCOFRADO MUROS REFORZADOS M2 984.72 19.42 19122.465
05.05.09 ACERO DE REFUERZO KG 11,272.99 2.06 23239.419
05.05.10 TARRAJEO CON IMPERMEABILIZANTE DE LOSA DE FONDO-PISO, C M2 954.16 31.99 30518.986
05.05.11 INSTALACION DE TUBERIA PVC 200 mm ISO 4435 ML 77.00 22.08 1700.282
05.05.12 SUMINISTRO Y COLOCACION DE TEE PVC 200 mm UND 6.00 87.28 523.664
05.05.13 SUMINISTRO Y COLOCACION DE CODO PVC 200 mm x 45 UND 14.00 83.55 1169.740
05.05.14 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 2.00 1300.26 2600.523
05.05.15 PASAMANO DE TUBO GALVANIZADO DE 2" ML 104.80 31.53 3304.807 127,243.47

05.06.00 FILTRO BIOLOGICO


05.06.01 EXCAVACION MANUAL MATERIAL SUELTO M3 592.20 9.31 5514.093
05.06.02 CONCRETO fc= 175 Kg/cm2 EN LOSAS M3 88.38 227.66 20120.462
05.06.03 ENCOFRADO Y DESENCOFRADO MUROS M2 487.52 18.01 8779.393
05.06.04 ACERO DE REFUERZO KG 3,196.34 2.06 6589.289
05.06.05 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 506.10 10.43 5276.560
05.06.06 TUBERIA PVC SAP CLASE 10; 3/4" ML 652.70 12.00 7833.772
05.06.07 VERTEDERO TRIANGULAR DE MADERA UND 62.00 39.15 2427.566
05.06.08 FILTRO DE GRAVA M3 286.75 48.30 13849.833 70,390.97

05.07.00 LECHOS DE SECADO 02 UNIDADES


05.07.01 LIMPIEZA DE TERRENO MANUAL M2 317.00 1.12 354.198
05.07.02 TRAZO Y REPLANTEO M2 234.00 0.43 101.479
05.07.03 EXCAVACION EN CONGLOMERADO M3 696.96 9.98 6953.072
05.07.04 RELLENO Y COMPACTADO DEL PISO M3 115.20 8.11 934.294
05.07.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 MTS M3 727.20 4.66 3385.552
05.07.06 NIVELACION Y COMPACTADO DEL LECHO M2 230.40 5.59 1287.180
05.07.07 CONCRETO fc= 175 Kg/cm2 DE MUROS M3 60.74 227.66 13828.599
05.07.08 ENCOFRADO Y DESENCOFRADO MUROS M2 516.90 18.01 9308.477
05.07.09 ACERO DE REFUERZO KG 1,133.85 2.06 2337.447
05.07.10 INSTALACION DE TUBERIA PVC - 8 ISO 4435 ML 86.00 22.08 1899.016
05.07.11 SUMINISTRO Y COLOCACION DE ACCESORIOS PVC UND 2.00 1072.02 2144.046
05.07.12 REJILLAS DE PROTECCION DE 1" x 1/8" UND 302.00 1.69 511.864
05.07.13 ARCILLA COMPACTADA e=10cms. M2 207.87 10.58 2200.048
05.07.14 RELLENO CON GRAVA GRUESA e=2" M3 10.39 48.30 502.003
05.07.15 RELLENO CON ARENA M3 41.57 42.77 1778.177 47,525.45

05.08.00 TUBERIA DE EVACUACION FINAL


PRESUPUESTO GENERAL DEL PROYECTO
VALOR REFERENCIAL 2 (VR2)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

TITULO DE PRECIO COSTO


ITEM. UNID. METRADO SUB-TOTAL
PARTIDA UNITARIO PARCIAL

05.08.01 EXCAVACION MANUAL MATERIAL SUELTO M3 115.20 9.31 1072.650


05.08.02 REFINE Y NIVELACION DE ZANJA ML 192.00 0.56 107.265
05.08.03 CAMA DE APOYO DE ARENA, e=5cms. M2 192.00 1.28 245.373
05.08.04 RELLENO COMPACTADO DE ZANJA ML 103.68 4.52 468.317
05.08.05 TUBERIA PVC SAL DE 4" ML 192.00 8.23 1580.579
05.08.06 SUMINISTRO Y COLOCACION DE CODO PVC 4" UND 4.00 8.47 33.898 3,508.08

06.00.00 CONEXIONES DOMICILIARIAS


06.01.00 EXCAVACION MANUAL MATERIAL SUELTO M3 1,284.48 9.31 11960.050
06.02.00 REFINE Y NIVELACION DE ZANJA ML 1,784.00 0.56 996.671
06.03.00 CAMA DE APOYO DE ARENA, e=5cms. M2 1,784.00 1.28 2279.923
06.04.00 RELLENO COMPACTADO DE ZANJA ML 1,284.48 4.52 5801.931
06.05.00 TUBERIA PVC SAL DE 4" ML 1,784.00 8.23 14686.216
06.06.00 CONEXIN DOMICILIARIA DE AGUA UND 446.00 25.33 11296.838
06.07.00 CAJA DE REGISTRO, TAPA DE 12"x 24" Y ACCESORIOS UND 446.00 139.36 62153.680 109,175.31

COSTO DIRECTO 742,573.500


GASTOS GENERALES (15% C.D.) 111,386.02

SUB-TOTAL 853,959.52
COSTO DIRECTO: EQ. + MAT. 459,424.92
I.G.V. (18% (EQ. + MAT.)) 82,696.49
TOTAL PRESUPUESTO 936,656.01

SON: NOVECIENTOS TREINTISEIS MIL SETECIENTOS VEINTE Y 55/100 NUEVOS SOLES


PRESUPUESTO GENERAL DEL PROYECTO
VALOR REFERENCIAL 1 (VR1)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

PRECIO COSTO
ITEM. TITULO DE PARTIDA UNID. METRADO SUB-TOTAL
UNITARIO PARCIAL

01.00.00 OBRAS PRELIMINARES


01.01.00 CARTEL DE OBRA PREFABRICADO UND 1.00 296.61 296.61 32,365.31
01.02.00 FLETE TERRESTRE GLB 1.00 32,068.70 32,068.70

02.00.00 RED DE COLECTORES


02.01.00 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL M2 3,823.38 1.12 4,272.04
02.01.02 TRAZO Y REPLANTEO LINEAL ML 6,372.31 0.67 4,282.40 8,554.43

02.02.00 MOVIMIENTO DE TIERRAS


02.02.01 EXCAVACION MANUAL MATERIAL SUELTO M3 5,406.19 9.31 50,338.15
02.02.02 EXCAVACION MANUAL ROCA SUELTA M3 855.72 13.97 11,951.63
02.02.03 REFINE Y NIVELACION DE ZANJA ML 6,372.31 0.56 3,560.03
02.02.04 CAMA DE APOYO, e = 5 cm. M2 3,823.38 1.28 4,886.22
02.02.05 RELLENO Y COMPACTACION DE ZANJA ML. 6,372.31 4.52 28,783.38 99,519.41

02.03.00 INSTALACION DE TUBERIAS


02.03.01 INSTALACION DE TUBERIAS PVC 160 mm ISO 4435 ML 6,372.31 15.21 96,950.94
02.03.02 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435 ML 0.00 22.08 0.00
02.03.03 PRUEBA HIDRAULICA ML 6,372.31 1.14 7,280.51 104,231.45

03.00.00 LINEA EMISOR


03.01.00 LIMPIEZA DE TERRENO MANUAL M2 497.73 1.12 556.14
03.02.00 TRAZO Y REPLANTEO LINEAL ML 829.55 0.67 557.48
03.03.00 EXCAVACION MANUAL MATERIAL SUELTO M3 1,374.63 9.31 12,799.42
03.04.00 EXCAVACION MANUAL ROCA SUELTA M3 312.46 13.97 4,364.06
03.05.00 REFINE Y NIVELACION ZANJA ML 829.55 0.47 386.21
03.06.00 CAMA DE APOYO, e = 5 cm. M2 497.73 1.28 636.09
03.07.00 RELLENO Y COMPACTACION DE ZANJA ML 829.55 7.22 5,988.73
03.08.00 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435 ML 829.55 21.80 18,086.30
03.09.00 PRUEBA HIDRAULICA ML 829.55 1.14 947.78 44,322.20

04.00.00 CONSTRUCCION DE BUZONES


04.01.00 EXCAVACION MANUAL MATERIAL SUELTO M3 372.50 9.31 3,468.39
04.02.00 EXCAVACION MANUAL ROCA SUELTA M3 69.27 13.97 967.51
04.03.00 BUZON TIPO I DIAM=1.20, H=1.20 a H=1.50 UND 100.00 556.37 55,637.16
04.04.00 BUZON TIPO II DIAM=1.20, H=1.50 a H=2.00 UND 20.00 686.43 13,728.55
04.05.00 BUZON TIPO III DIAM=1.20, H=2.00 a H=2.50 UND 8.00 817.29 6,538.33
04.06.00 BUZON TIPO IV DIAM=1.20, H=2.50 a H=3.00 UND 5.00 968.72 4,843.59
04.07.00 BUZON TIPO V DIAM=1.20, H=3.00 a H=3.50 UND 0.00 1,288.73 0.00
04.08.00 BUZON TIPO VI DIAM=1.20, H=3.50 a H=4.00 UND 4.00 1,345.26 5,381.03
04.09.00 CONCRETO fc= 210 Kg/cm2 PARA PANTALLA DE B M3 0.65 270.50 175.28
04.10.00 ENCOFRADO Y DESENCOFRADO M2 6.12 18.67 114.26
04.11.00 ACERO DE REFUERZO KG 43.54 2.06 89.75
04.12.00 SUMINISTRO Y COLOCACION DE ACCESORIOS BU UND 3.00 200.60 601.81 91,545.65

05.00.00 PLANTA DE TRATAMIENTO


05.01.00 CAMARA DE REJAS
05.01.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.85 9.31 35.85
05.01.02 SOLADO DE CONCRETO 1:10 e=10cm. M2 0.19 57.82 11.13
05.01.03 CONCRETO fc= 175 Kg/cm2 EN LOSAS M3 1.50 227.66 340.87
05.01.04 ENCOFRADO Y DESENCOFRADO M2 16.05 18.67 299.64
05.01.05 ACERO DE REFUERZO KG 2.41 2.06 4.96
05.01.06 REVESTIMIENTO CON MORTERO 1:5 M2 8.20 12.29 100.79
05.01.07 SUMISTRO Y COLOCACION DE REJILLA 1/4"x1/2"xL M2 0.62 160.61 99.58 892.82

05.02.00 DESARENADOR
05.02.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.13 9.31 29.16
05.02.02 CONCRETO fc= 175 Kg/cm2 M3 1.52 227.66 346.16
05.02.03 ENCOFRADO Y DESENCOFRADO M2 17.76 18.01 319.83
05.02.04 ACERO DE REFUERZO KG 1.08 2.06 2.22
05.02.05 TARRAJEO DE MUROS CON MORTERO M2 7.92 10.43 82.57
05.02.06 SUMISTRO Y COLOCACION ACCESORIOSDE REJILLA 1/ UND 1.00 486.85 486.85
PRESUPUESTO GENERAL DEL PROYECTO
VALOR REFERENCIAL 1 (VR1)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

PRECIO COSTO
ITEM. TITULO DE PARTIDA UNID. METRADO SUB-TOTAL
UNITARIO PARCIAL

05.02.07 COMPUERTA METALICA 0.45 x 0.50 mts. x 3/16" UND 1.00 135.59 135.59 1,402.39

05.03.00 CAJA DE DISTRIBUCION


05.03.01 EXCAVACION MANUAL MATERIAL SUELTO M3 1.44 9.31 13.41
05.03.02 CONCRETO fc= 175 Kg/cm2 M3 0.49 227.66 112.47
05.03.03 ENCOFRADO Y DESENCOFRADO M2 7.48 18.67 139.65
05.03.04 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 5.50 10.43 57.34
05.03.05 COMPUERTA METALICA C/BORDES METALICOS UND 2.00 127.12 254.24 577.10

05.04.00 CAJA DE INSPECCION


05.04.01 EXCAVACION MANUAL MATERIAL SUELTO M3 3.60 9.31 33.52
05.04.02 CONCRETO fc= 175 Kg/cm2 EN MUROS M3 1.68 227.66 383.39
05.04.03 ENCOFRADO Y DESENCOFRADO M2 24.20 18.67 451.80
05.04.04 ACERO DE REFUERZO KG 24.44 2.06 50.39
05.04.05 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 38.40 10.43 400.36 1,319.45

05.05.00 TANQUE IMHOFF 02 UNIDADES


05.05.01 LIMPIEZA DE TERRENO MANUAL M2 228.00 1.12 254.75
05.05.02 TRAZO Y REPLANTEO M2 73.71 1.31 96.65
05.05.03 EXCAVACION MANUAL MATERIAL SUELTO M3 613.11 9.31 5,708.77
05.05.04 RELLENO Y COMPACTADO DEL PISO M3 28.88 22.88 660.95
05.05.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30 M3 730.28 4.66 3,399.89
05.05.06 CONCRETO fc= 210 Kg/cm2 M3 136.22 253.76 34,566.92
05.05.07 CONCRETO fc= 175 Kg/cm2 M3 1.65 227.66 375.65
05.05.08 ENCOFRADO Y DESENCOFRADO MUROS REFORZA M2 984.72 19.42 19,122.46
05.05.09 ACERO DE REFUERZO KG 11,272.99 2.06 23,239.42
05.05.10 TARRAJEO CON IMPERMEABILIZANTE DE LOSA DE M2 954.16 31.99 30,518.99
05.05.11 INSTALACION DE TUBERIA PVC 200 mm ISO 4435 ML 77.00 22.08 1,700.28
05.05.12 SUMINISTRO Y COLOCACION DE TEE PVC 200 mm UND 6.00 87.28 523.66
05.05.13 SUMINISTRO Y COLOCACION DE CODO PVC 200 mm UND 14.00 83.55 1,169.74
05.05.14 SUMINISTRO Y COLOCACION DE ACCESORIOS UND 2.00 1,300.26 2,600.52
05.05.15 PASAMANO DE TUBO GALVANIZADO DE 2" ML 104.80 31.53 3,304.81 127,243.47

05.06.00 FILTRO BIOLOGICO


05.06.01 EXCAVACION MANUAL MATERIAL SUELTO M3 592.20 9.31 5,514.09
05.06.02 CONCRETO fc= 175 Kg/cm2 EN LOSAS M3 88.38 227.66 20,120.46
05.06.03 ENCOFRADO Y DESENCOFRADO MUROS M2 487.52 18.01 8,779.39
05.06.04 ACERO DE REFUERZO KG 3,196.34 2.06 6,589.29
05.06.05 TARRAJEO DE MUROS INTERIORES CON MORTERO M2 506.10 10.43 5,276.56
05.06.06 TUBERIA PVC SAP CLASE 10; 3/4" ML 652.70 12.00 7,833.77
05.06.07 VERTEDERO TRIANGULAR DE MADERA UND 62.00 39.15 2,427.57
05.06.08 FILTRO DE GRAVA M3 286.75 48.30 13,849.83 70,390.97

05.07.00 LECHOS DE SECADO 02 UNIDADES


05.07.01 LIMPIEZA DE TERRENO MANUAL M2 317.00 1.12 354.20
05.07.02 TRAZO Y REPLANTEO M2 234.00 0.43 101.48
05.07.03 EXCAVACION EN CONGLOMERADO M3 696.96 9.98 6,953.07
05.07.04 RELLENO Y COMPACTADO DEL PISO M3 115.20 8.11 934.29
05.07.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30 M3 727.20 4.66 3,385.55
05.07.06 NIVELACION Y COMPACTADO DEL LECHO M2 230.40 5.59 1,287.18
05.07.07 CONCRETO fc= 175 Kg/cm2 DE MUROS M3 60.74 227.66 13,828.60
05.07.08 ENCOFRADO Y DESENCOFRADO MUROS M2 516.90 18.01 9,308.48
05.07.09 ACERO DE REFUERZO KG 1,133.85 2.06 2,337.45
05.07.10 INSTALACION DE TUBERIA PVC - 8 ISO 4435 ML 86.00 22.08 1,899.02
05.07.11 SUMINISTRO Y COLOCACION DE ACCESORIOS PVC UND 2.00 1,072.02 2,144.05
05.07.12 REJILLAS DE PROTECCION DE 1" x 1/8" UND 302.00 1.69 511.86
05.07.13 ARCILLA COMPACTADA e=10cms. M2 207.87 10.58 2,200.05
05.07.14 RELLENO CON GRAVA GRUESA e=2" M3 10.39 48.30 502.00
05.07.15 RELLENO CON ARENA M3 41.57 42.77 1,778.18 47,525.45

05.08.00 TUBERIA DE EVACUACION FINAL


05.08.01 EXCAVACION MANUAL MATERIAL SUELTO M3 115.20 9.31 1,072.65
05.08.02 REFINE Y NIVELACION DE ZANJA ML 192.00 0.56 107.27
PRESUPUESTO GENERAL DEL PROYECTO
VALOR REFERENCIAL 1 (VR1)

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

PRECIO COSTO
ITEM. TITULO DE PARTIDA UNID. METRADO SUB-TOTAL
UNITARIO PARCIAL

05.08.03 CAMA DE APOYO DE ARENA, e=5cms. M2 192.00 1.28 245.37


05.08.04 RELLENO COMPACTADO DE ZANJA ML 103.68 4.52 468.32
05.08.05 TUBERIA PVC SAL DE 4" ML 192.00 8.23 1,580.58
05.08.06 SUMINISTRO Y COLOCACION DE CODO PVC 4" UND 4.00 8.47 33.90 3,508.08

06.00.00 CONEXIONES DOMICILIARIAS


06.01.00 EXCAVACION MANUAL MATERIAL SUELTO M3 1,284.48 9.31 11,960.05
06.02.00 REFINE Y NIVELACION DE ZANJA ML 1,784.00 0.56 996.67
06.03.00 CAMA DE APOYO DE ARENA, e=5cms. M2 1,784.00 1.28 2,279.92
06.04.00 RELLENO COMPACTADO DE ZANJA ML 1,284.48 4.52 5,801.93
06.05.00 TUBERIA PVC SAL DE 4" ML 1,784.00 8.23 14,686.22
06.06.00 CONEXIN DOMICILIARIA DE AGUA UND 446.00 25.33 11,296.84
06.07.00 CAJA DE REGISTRO, TAPA DE 12"x 24" Y ACCESORI UND 446.00 139.36 62,153.68 109,175.31

COSTO DIRECTO 742,573.50


GASTOS GENERALES (15% C.D.) 111,386.02
SUB-TOTAL (A) 853,959.52
UTILIDAD 74,257.35
SUB-TOTAL 928,216.87
COSTO DIRECTO: EQ. + MAT. 459,424.92
I.G.V. (18% (EQ. + MAT.)) 82,696.49
TOTAL PRESUPUESTO 1,010,913.36

SON: UN MILLON DIEZ MIL NOVECIENTOS OCHENTITRES Y 49/100 NUEVOS SOLES


RELACION DE INSUMOS

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA
Costo
COSTO
DESCRIPCION DE INSUMOS UNID. P.UNIT. CANT. TOTAL
PARCIAL

MANO DE OBRA
TOPOGRAFO H.H. 7.50 250.66 1879.99
OPERARIO H.H. 6.78 8322.30 56425.19
OFICIAL H.H. 5.08 3985.88 20248.28
PEON H.H. 3.39 60352.54 204595.12

EQUIPO
MIRAS Y JALONES H.M. 1.27 164.61 209.25
WINCHA DE ACERO H.M. 0.34 9.36 3.17
MEZCLADORA DE CONCRET DE 9 A 11 P3 H.M. 8.47 275.28 2332.92
EQUIPO DE SOLDAR H.M. 6.78 141.48 959.19
ENCOFRADO METALICO H.M. 5.08 112.00 569.49
COMPACTADOR VIBR. TIPO PLANCHA 4 HP H.M. 12.71 784.34 9970.42
VIBRADOR DE 3/4 - 2 CONCRETO H.M. 4.24 365.47 1548.59
TEODOLITO H.M. 4.66 169.43 789.74
NIVEL DE INGENIERO H.M. 3.18 169.43 538.46
HERRAMIENTAS MANUALES %M.O. 283148.58 0.03 8510.93

MATERIALES
ABRAZADERA FF 8 PZA 15.25 28.00 427.12
ADAPTADOR PVC SAP 6 UNID 15.25 1.00 15.25
ADAPTADOR PVC SAP 8 UNID 16.95 4.00 67.80
AGUA M3 0.10 1357.35 135.73
ALAMBRE NEGRO NACIONAL # 16 KG 2.03 1047.54 2130.59
ALAMBRE NEGRO NACIONAL # 8 KG 2.03 515.18 1047.82
ANDAMIO DE MADERA P2 2.12 372.12 788.39
ANILLO UF 160 MM UNID 4.24 1057.80 4482.22
ANILLO UF 200 MM UNID 4.66 164.76 767.97
ARCILLA M3 8.47 214.11 1814.46
ARENA FINA M3 38.14 136.21 5194.40
ARENA GRUESA M3 38.14 326.99 12470.04
ATAGUIAS MADERA TORNILLO P2 4.24 62.00 262.71
CAJA CONCRETO SIMPLE DESAG. 0.30 X 0.60 UNID 16.95 446.00 7559.32
CANASTILLA DE BRONCE DE 8 BRIDADA UNID 67.80 2.00 135.59
CARTEL DE OBRA, SUMINISTRO E INSTAL GLB 296.61 1.00 296.61
CEMENTO PORTLAND TIPO I (42.5KG) BLS 16.78 5113.71 85806.37
CLAVOS KG 2.03 405.13 824.00
CLAVOS PARA MADERA C/C 3 KG 2.03 196.94 400.56
CODO DE 45 PVC SAL DE 6 UNID 76.27 1.00 76.27
CODO DE 45 PVC SAL DE 8 UNID 77.97 14.00 1091.53
CODO DE 90 PVC SAL DE 8 UNID 77.97 6.00 467.80
CODO PVC SAL 4 UNID 8.47 4.00 33.90
CODO PVC SAP 8 X 45 PZA 67.80 13.00 881.36
CODO PVC SAP 8 X 90 PZA 76.27 19.00 1449.15
CODO PVC SEL 4 X 45 UNID 38.14 446.00 17008.47
COMPUERTA METALICA 1/8; 0.45 X 0.50 UNID 135.59 1.00 135.59
COMPUERTA TIPO I UNID 127.12 2.00 254.24
ESTACA DE FIERRO UNID 0.25 48.56 12.34
ESTACA DE MADERA P2 0.59 144.04 85.45
FIERRO CORRUGADO KG 1.36 20357.20 27602.98
FIERRO LISO 1/2 ML 1.36 26.20 35.53
FLETE TERRESTRE GLB 1.00 32068.70 32068.70
GRAVA TRITURADA < 1 PULG. M3 42.37 306.06 12968.46
IMPERMEAB. MORTERO/CONCRETO CHEMA 1 POLVO KG 38.14 381.66 14554.98
LIJA # 40 (PLIEGO) UNID 1.69 294.59 499.31
LIJA PARA METAL UNID 1.69 31.44 53.29
LUBRICANTE UF GLN 46.61 22.09 1029.83
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 2.03 3036.18 6175.27
RELACION DE INSUMOS

MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA
Costo
COSTO
DESCRIPCION DE INSUMOS UNID. P.UNIT. CANT. TOTAL
PARCIAL

MADERA NACIONAL P/ ENCOFRADO-CARP P2 2.03 7563.30 15382.99


MATERIAL DE PRESTAMO SELECCIONADO-OBRA M3 4.24 29.75 126.06
MATERIAL PARA CAMA DE APOYO M3 8.47 472.28 4002.40
PEGAMENTO GLN 33.90 0.02 0.51
PEGAMENTO PLASTICO PVC GLN 33.90 4.60 156.09
PETROLEO GLN 6.95 98.47 684.30
PIEDRA CHANCADA 1/2 M3 42.37 354.00 14999.95
REDUCCION PVC SAL P/DESAGUE DE 6 A 4 UNID 21.19 446.00 9449.15
REJILLA C/ PERFIL 1 1/4X11/4+L 1 1/1/4 M2 152.54 0.64 97.41
REJILLA DE FIERRO 1 X 1/8 UNID 1.69 302.00 511.86
SOLDADURA CELLOCORD KG. 6.36 6.29 39.97
TAPA C/ MARCO Fo Fo DE DESAGUE 11 X 22 PZA 21.19 446.00 9449.15
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 6.78 137.00 928.81
TEE SANITARIA DOBLE PVC SAL DE 8 UNID 42.37 6.00 254.24
TEE SANITARIA SIMPLE PVC SAL DE 8 UNID 38.14 4.00 152.54
TUB. PVC SAP PRESION C-10 R. 3/4 X 5m UNID 11.02 672.28 7406.49
TUBERIA DE FIERRO NEGRO 02 ML 10.17 110.04 1119.05
TUBERIA PVC S25 160 MM ML 12.71 6563.48 83434.01
TUBERIA PVC S25 200 MM ML 19.49 1038.53 20242.48
TUBERIA PVC SAL 4 ML 7.20 2035.28 14660.92
TUBO-CACHIMBA C.S.N. U.F. 6 UNID 16.95 446.00 7559.32
VALVULA DE COMPUERTA-BB 8 UNID 610.17 2.00 1220.34
VALVULA DE PASO BRONCE DE 6 UNID 338.98 1.00 338.98
VERTEDERO METALICO UNID 42.37 1.00 42.37
YEE PVC SAL 8 UNID 50.85 3.00 152.54
YEE PVC SAL DOBLE DE 8 UNID 118.64 2.00 237.29
YESO EN BOLSAS DE 25 KG BLS 3.05 76.08 232.12

COSTO DIRECTO
RELACION DE INSUMOS

: OCT/2002

TOTAL

S/. 283,148.58

S/. 25,432.16
RELACION DE INSUMOS

: OCT/2002

TOTAL

S/. 433,992.76

S/. 742,573.49
CALCULO DE FLETE TERRESTRE
MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

PESO PESO TOTAL


DESCRIPCION DE INSUMOS UNID. METRADO
UNIT. PARCIAL (KG)

EQUIPO
MEZCLADORA DE CONCRET DE 9 A 11 P3 KG 150 1.00 150.00
EQUIPO DE SOLDAR KG 30 1.00 30.00
ENCOFRADO METALICO KG 100 1.00 100.00
COMPACTADOR VIBR. TIPO PLANCHA 4 HP KG 30 1.00 30.00
VIBRADOR DE 3/4 - 2 CONCRETO KG 25 1.00 25.00 335.00

MATERIALES
ABRAZADERA FF 8 KG 0.5 28.00 14.00
ADAPTADOR PVC SAP 6 KG 0.5 1.00 0.50
ADAPTADOR PVC SAP 8 KG 0.5 4.00 2.00
ALAMBRE NEGRO NACIONAL # 16 KG 1 1047.54 1047.54
ALAMBRE NEGRO NACIONAL # 8 KG 1 515.18 515.18
ANDAMIO DE MADERA KG 0.25 372.12 93.03
ANILLO UF 160 MM KG 0.4 1057.80 423.12
ANILLO UF 200 MM KG 0.4 164.76 65.91
ANILLO UF 250 MM KG 0.4 0.00 0.00
ATAGUIAS MADERA TORNILLO KG 0.25 62.00 15.50
CAJA CONCRETO SIMPLE DESAG. 0.30 X 0.60 KG 2 446.00 892.00
CANASTILLA DE BRONCE DE 8 BRIDADA KG 30 2.00 60.00
CARTEL DE OBRA, SUMINISTRO E INSTAL KG 30 1.00 30.00
CEMENTO PORTLAND TIPO I (42.5KG) KG 42.5 5113.71 217332.81
CLAVOS KG 1 405.13 405.13
CLAVOS PARA MADERA C/C 3 KG 1 196.94 196.94
CODO DE 45 PVC SAL DE 6 KG 0.4 1.00 0.40
CODO DE 45 PVC SAL DE 8 KG 0.4 14.00 5.60
CODO DE 90 PVC SAL DE 8 KG 0.4 6.00 2.40
CODO PVC SAL 4 KG 0.3 4.00 1.20
CODO PVC SAP 8 X 45 KG 0.4 13.00 5.20
CODO PVC SAP 8 X 90 KG 0.4 19.00 7.60
CODO PVC SEL 4 X 45 KG 0.2 446.00 89.20
COMPUERTA METALICA 1/8; 0.45 X 0.50 KG 25 1.00 25.00
COMPUERTA TIPO I KG 20 2.00 40.00
ESTACA DE FIERRO KG 0.2 48.56 9.71
ESTACA DE MADERA KG 0.2 144.04 28.81
FIERRO CORRUGADO KG 1 20357.20 20357.20
FIERRO LISO 1/2 KG 1 26.20 26.20
IMPERMEAB. MORTERO/CONCRETO CHEMA 1 POLVO KG 1 381.66 381.66
LIJA # 40 (PLIEGO) KG 0.08 294.59 23.57
LIJA PARA METAL KG 0.1 31.44 3.14
LUBRICANTE UF KG 3.5 22.09 77.33
MADERA TORNILLO INC. CORTE P/ENCOFRADO KG 0.25 3036.18 759.04
MADERA NACIONAL P/ ENCOFRADO-CARP KG 0.25 7563.30 1890.83
PEGAMENTO KG 3.5 0.02 0.05
PEGAMENTO PLASTICO PVC KG 3.5 4.60 16.12
PETROLEO KG 3.5 98.47 344.65
TUBERIA DE FIERRO NEGRO 02 KG 1.2 110.04 132.05
TUBERIA PVC S25 160 MM KG 1.65 6563.48 10829.74
TUBERIA PVC S25 200 MM KG 2.6 1038.53 2700.17
TUBERIA PVC S25 250 MM KG 4.01 0.00 0.00
TUBERIA PVC SAL 4 KG 0.78 2035.28 1587.52
TUBO-CACHIMBA C.S.N. U.F. 6 KG 9.9 446.00 4415.40
VALVULA DE COMPUERTA-BB 8 KG 40 2.00 80.00
VALVULA DE PASO BRONCE DE 6 KG 35 1.00 35.00
VERTEDERO METALICO KG 30 1.00 30.00
YEE PVC SAL 8 KG 0.4 3.00 1.20
YEE PVC SAL DOBLE DE 8 KG 1.2 2.00 2.40
YESO EN BOLSAS DE 25 KG KG 25 76.08 1902.10 266904.14
CALCULO DE FLETE TERRESTRE
MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

PESO PESO TOTAL


DESCRIPCION DE INSUMOS UNID. METRADO
UNIT. PARCIAL (KG)

267239.14
ANALISIS DE COSTOS UNITARIOS

CONCEJO DISTRITAL DE CANARIA


OBRA : SISTEMA DE ALCANTARILLADO CANARIA
DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

Partida 01.01.00 CARTEL DE OBRA PREFABRICADO


Rendimiento 1.000 UND/Dia Costo Unitario por : (UNID) 296.61

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
CARTEL DE OBRA, SUMINISTRO E INSTAL GLB 1.0000 296.61 296.61
296.61

Partida 01.02.00 FLETE TERRESTRE


Rendimiento 1.000 GLB Costo Unitario por : (GLB) 32068.70

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
FLETE TERRESTRE GLB 267239.14 0.12 32068.70
32068.70

Partida 02.01.01 LIMPIEZA DE TERRENO MANUAL


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.12

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 2.00 0.3200 3.39 1.08
1.08
Equipos, Herramientas
% MO 3.0000 1.08 0.03
0.03

Partida 02.01.02 TRAZO Y REPLANTEO LINEAL


Rendimiento 350.000 ML/DIA Costo Unitario por : ML 0.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
TOPOGRAFO HH 1.500 0.0343 7.50 0.26
PEON HH 2.000 0.0457 3.39 0.15
0.41
Materiales
YESO EN BOLSAS DE 25 KG BLS 0.0090 3.0508474576 0.03
ESTACA DE MADERA P2 0.0200 0.59 0.01
0.04
Equipos, Herramientas
MIRAS Y JALONES HM 1.00 0.0229 1.27 0.03
TEODOLITO HM 1.00 0.0229 4.66 0.11
NIVEL DE INGENIERO HM 1.00 0.0229 3.18 0.07
HERRAMIENTAS MANUALES % MO 3.0000 0.41 0.01
0.22

Partida 02.02.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27
Partida 02.02.02 EXCAVACION MANUAL ROCA SUELTA
Rendimiento 2.000 M3/DIA Costo Unitario por : M3. 13.97

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 4.0000 3.39 13.56
13.56
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 13.56 0.41
0.41

Partida 02.02.03 REFINE Y NIVELACION DE ZANJA


Rendimiento 50.000 ML/DIA Costo Unitario por : ML. 0.56

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 0.1600 3.39 0.54
0.54
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.54 0.02
0.02

Partida 02.02.04 CAMA DE APOYO, e = 5 cm.


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.28

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OFICIAL HH 0.10 0.0160 5.08 0.08
PEON HH 1.00 0.1600 3.39 0.54
0.62
Materiales
MATERIAL PARA CAMA DE APOYO M3 0.0750 8.47 0.64
0.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.62 0.02
0.02

Partida 02.02.05 RELLENO Y COMPACTACION DE ZANJA


Rendimiento 8.000 ML/DIA Costo Unitario por : ML. 4.52

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.0000 3.39 3.39
3.39
Materiales
AGUA M3 0.0830 0.10 0.01
0.01
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 0.08 0.0800 12.71 1.02
HERRAMIENTAS MANUALES % MO 3.0000 3.39 0.10
1.12

Partida 02.03.01 INSTALACION DE TUBERIAS PVC 160 mm ISO 4435


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 15.21

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
OFICIAL HH 1.00 0.0533 5.08 0.27
PEON HH 3.00 0.1600 3.39 0.54
1.17
Materiales
LIJA # 40 (PLIEGO) UNID 0.0400 1.69 0.07
TUBERIA PVC S25 160 MM ML 1.0300 12.71 13.09
LUBRICANTE UF GLN 0.0030 46.61 0.14
ANILLO UF 160 MM UNID 0.1660 4.24 0.70
14.00
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.17 0.04
0.04

Partida 02.03.02 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 22.08

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
OFICIAL HH 1.00 0.0533 5.08 0.27
PEON HH 2.00 0.1067 3.39 0.36
0.99
Materiales
LIJA # 40 (PLIEGO) UNID 0.0400 1.69 0.07
TUBERIA PVC S25 200 MM ML 1.0300 19.49 20.08
LUBRICANTE UF GLN 0.0030 46.61 0.14
ANILLO UF 200 MM UNID 0.1660 4.66 0.77
21.06
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.99 0.03
0.03

Partida 02.03.03 PRUEBA HIDRAULICA


Rendimiento 100.000 ML/DIA Costo Unitario por : ML. 1.14

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0800 6.78 0.54
PEON HH 2.00 0.1600 3.39 0.54
1.08
Materiales
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.0010 16.78 0.02
AGUA M3 0.0840 0.10 0.01
0.03
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.08 0.03
0.03

Partida 03.01.00 LIMPIEZA DE TERRENO MANUAL


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.12

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 2.00 0.3200 3.39 1.08
1.08
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.08 0.03
0.03

Partida 03.02.00 TRAZO Y REPLANTEO LINEAL


Rendimiento 350.000 ML/DIA Costo Unitario por : ML. 0.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
TOPOGRAFO HH 1.50 0.0343 7.50 0.26
PEON HH 2.00 0.0457 3.39 0.15
0.41
Materiales
YESO EN BOLSAS DE 25 KG BLS 0.0090 3.05 0.03
ESTACA DE MADERA P2 0.0200 0.59 0.01
0.04
Equipos, Herramientas
MIRAS Y JALONES HM 1.00 0.0229 1.27 0.03
TEODOLITO HM 1.00 0.0229 4.66 0.11
NIVEL DE INGENIERO HM 1.00 0.0229 3.18 0.07
HERRAMIENTAS MANUALES % MO 3.0000 0.41 0.01
0.22

Partida 03.03.00 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 03.04.00 EXCAVACION MANUAL ROCA SUELTA


Rendimiento 2.000 M3/DIA Costo Unitario por : M3. 13.97

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 4.0000 3.39 13.56
13.56
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 13.56 0.41
0.41

Partida 03.05.00 REFINE Y NIVELACION ZANJA


Rendimiento 60.000 ML/DIA Costo Unitario por : ML. 0.47

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 0.1333 3.39 0.45
0.45
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.45 0.01
0.01

Partida 03.06.00 CAMA DE APOYO, e = 5 cm.


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.28

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OFICIAL HH 0.10 0.0160 5.08 0.08
PEON HH 1.00 0.1600 3.39 0.54
0.62
Materiales
MATERIAL PARA CAMA DE APOYO M3 0.0750 8.47 0.64
0.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.62 0.02
0.02

Partida 03.07.00 RELLENO Y COMPACTACION DE ZANJA


Rendimiento 5.000 ML/DIA Costo Unitario por : ML. 7.22
Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de obra
PEON HH 1.00 1.6000 3.39 5.42
5.42
Materiales
AGUA M3 0.0540 0.10 0.01
0.01
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 0.08 0.1280 12.71 1.63
HERRAMIENTAS MANUALES % MO 3.0000 5.42 0.16
1.79

Partida 03.08.00 INSTALACION DE TUBERIAS PVC 200 mm ISO 4435


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 21.80

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
PEON HH 2.00 0.1067 3.39 0.36
0.72
Materiales
LIJA # 40 (PLIEGO) UNID 0.0400 1.69 0.07
TUBERIA PVC S25 200 MM #REF! 1.0300 19.49 20.08
LUBRICANTE UF GLN 0.0030 46.61 0.14
ANILLO UF 200 MM #REF! 0.1660 4.66 0.77
21.06
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.72 0.02
0.02

Partida 03.09.00 PRUEBA HIDRAULICA


Rendimiento 100.000 ML/DIA Costo Unitario por : ML. 1.14

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0800 6.78 0.54
PEON HH 2.00 0.1600 3.39 0.54
1.08
Materiales
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.0010 16.78 0.02
AGUA M3 0.0840 0.10 0.01
0.03
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.08 0.03
0.03

Partida 04.01.00 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 04.02.00 EXCAVACION MANUAL ROCA SUELTA


Rendimiento 2.000 M3/DIA Costo Unitario por : M3. 13.97

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 4.0000 3.39 13.56
13.56
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 13.56 0.41
0.41

Partida 04.03.00 BUZON TIPO I DIAM=1.20, H=1.20 a H=1.50


Rendimiento 3.000 UNID/DIA Costo Unitario por : UNID. 556.37

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 5.3333 6.78 36.16
OFICIAL HH 2.00 5.3333 5.08 27.09
PEON HH 6.00 16.0000 3.39 54.24
117.49
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.6000 2.03 1.22
CLAVOS KG 0.4000 2.03 0.81
FIERRO CORRUGADO KG 22.9000 1.36 31.05
ARENA FINA M3 0.0800 38.14 3.05
PIEDRA CHANCADA 1/2 M3 1.2900 42.37 54.66
ARENA GRUESA M3 0.8700 38.14 33.18
CEMENTO PORTLAND TIPO I (42.5KG) BLS 15.6200 16.78 262.10
AGUA M3 0.1500 0.10 0.02
MADERA NACIONAL P/ ENCOFRADO-CARP P2 19.5000 2.03 39.66
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
432.53
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.25 0.6667 4.24 2.82
HERRAMIENTAS MANUALES % MO 3.0000 117.49 3.52
6.35

Partida 04.04.00 BUZON TIPO II DIAM=1.20, H=1.50 a H=2.00


Rendimiento 2.250 UNID/DIA Costo Unitario por : UNID. 686.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 7.1111 6.78 48.21
OFICIAL HH 2.00 7.1111 5.08 36.12
PEON HH 6.00 21.3333 3.39 72.32
156.66
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.6000 2.03 1.22
CLAVOS KG 0.6000 2.03 1.22
FIERRO CORRUGADO KG 23.5000 1.36 31.86
ARENA FINA M3 0.1200 45.00 5.40
PIEDRA CHANCADA 1/2 M3 1.5400 42.37 65.25
ARENA GRUESA M3 1.0300 38.14 39.28
CEMENTO PORTLAND TIPO I (42.5KG) BLS 18.6900 16.78 313.61
AGUA M3 0.2500 0.10 0.03
MADERA NACIONAL P/ ENCOFRADO-CARP P2 26.0000 2.03 52.88
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
517.54
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.50 1.7778 4.24 7.53
HERRAMIENTAS MANUALES % MO 3.0000 156.66 4.70
12.23

Partida 04.05.00 BUZON TIPO III DIAM=1.20, H=2.00 a H=2.50


Rendimiento 1.800 UNID/DIA Costo Unitario por : UNID. 817.29

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 8.8889 6.78 60.27
OFICIAL HH 2.00 8.8889 5.08 45.16
PEON HH 6.00 26.6667 3.39 90.40
195.82
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.8000 2.03 1.63
CLAVOS KG 0.8000 2.03 1.63
FIERRO CORRUGADO KG 28.6670 1.36 38.87
ARENA FINA M3 0.1400 38.14 5.34
PIEDRA CHANCADA 1/2 M3 1.7800 42.37 75.42
ARENA GRUESA M3 1.2000 38.14 45.76
CEMENTO PORTLAND TIPO I (42.5KG) BLS 21.7300 16.78 364.62
AGUA M3 0.2500 0.10 0.03
MADERA NACIONAL P/ ENCOFRADO-CARP P2 32.5000 2.03 66.10
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
606.18
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.50 2.2222 4.24 9.42
HERRAMIENTAS MANUALES % MO 3.0000 195.82 5.87
15.29

Partida 04.06.00 BUZON TIPO IV DIAM=1.20, H=2.50 a H=3.00


Rendimiento 1.500 UNID/DIA Costo Unitario por : UNID. 968.72

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 10.6667 6.78 72.32
OFICIAL HH 2.00 10.6667 5.08 54.19
PEON HH 5.00 26.6667 3.39 90.40
216.91
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 3.3000 2.03 6.71
CLAVOS KG 1.0000 2.03 2.03
FIERRO CORRUGADO KG 56.0000 1.36 75.93
ARENA FINA M3 0.1700 38.14 6.48
PIEDRA CHANCADA 1/2 M3 2.0200 42.37 85.59
ARENA GRUESA M3 1.3600 38.14 51.86
CEMENTO PORTLAND TIPO I (42.5KG) BLS 24.6500 16.78 413.62
AGUA M3 0.1500 0.10 0.02
MADERA NACIONAL P/ ENCOFRADO-CARP P2 39.0000 2.0339 79.32
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
728.35
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.75 4.0000 4.24 16.95
HERRAMIENTAS MANUALES % MO 3.0000 216.91 6.51
23.46

Partida 04.07.00 BUZON TIPO V DIAM=1.20, H=3.00 a H=3.50


Rendimiento 1.000 UNID/DIA Costo Unitario por : UNID. 1288.73

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 16.0000 6.78 108.48
OFICIAL HH 2.00 16.0000 5.08 81.28
PEON HH 6.00 48.0000 3.39 162.72
352.48
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 3.8000 2.03 7.73
CLAVOS KG 1.2000 2.03 2.44
FIERRO CORRUGADO KG 68.0000 1.36 92.20
ARENA FINA M3 0.2000 38.14 7.63
PIEDRA CHANCADA 1/2 M3 2.2600 42.37 95.76
ARENA GRUESA M3 1.5200 38.14 57.97
CEMENTO PORTLAND TIPO I (42.5KG) BLS 27.9300 16.78 468.66
AGUA M3 0.6480 0.10 0.06
MADERA NACIONAL P/ ENCOFRADO-CARP P2 9.1700 2.03 18.65
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
757.88
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.75 6.0000 4.24 25.42
ENCOFRADO METALICO HM 3.50 28.0000 5.08 142.37
HERRAMIENTAS MANUALES % MO 3.0000 352.48 10.57
178.37

Partida 04.08.00 BUZON TIPO VI DIAM=1.20, H=3.50 a H=4.00


Rendimiento 1.000 UNID/DIA Costo Unitario por : UNID. 1345.26

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 2.00 16.0000 6.78 108.48
OFICIAL HH 2.00 16.0000 5.08 81.28
PEON HH 5.00 40.0000 3.39 135.60
325.36
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 3.0400 2.03 6.18
CLAVOS KG 0.2200 2.03 0.45
FIERRO CORRUGADO KG 79.0000 1.36 107.12
ARENA FINA M3 0.3000 38.14 11.44
PIEDRA CHANCADA 1/2 M3 2.8800 42.37 122.03
ARENA GRUESA M3 1.4700 38.14 56.06
CEMENTO PORTLAND TIPO I (42.5KG) BLS 29.9400 16.78 502.38
AGUA M3 0.6400 0.10 0.06
MADERA NACIONAL P/ ENCOFRADO-CARP P2 10.5000 2.03 21.36
TAPA DE CONCRETO DIAM = 0.60 MTS PZA 1.0000 6.78 6.78
833.87
Equipos, Herramientas
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 8.0000 4.24 33.90
ENCOFRADO METALICO HM 3.50 28.0000 5.08 142.37
HERRAMIENTAS MANUALES % MO 3.0000 325.36 9.76
186.03

Partida 04.09.00 CONCRETO fc= 210 Kg/cm2 PARA PANTALLA DE BUZON CON CAIDA
Rendimiento 6.000 M3/DIA Costo Unitario por : M3. 270.50

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.3333 6.78 9.04
OFICIAL HH 2.00 2.6667 5.08 13.55
PEON HH 5.00 6.6667 3.39 22.60
45.19
Materiales
PIEDRA CHANCADA 1/2 M3 0.5600 42.37 23.73
ARENA GRUESA M3 0.5500 38.14 20.97
CEMENTO PORTLAND TIPO I (42.5KG) BLS 10.2100 16.78 171.32
AGUA M3 0.2100 0.10 0.02
216.04
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 0.50 0.6667 8.47 5.65
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.40 0.5333 4.24 2.26
HERRAMIENTAS MANUALES % MO 3.0000 45.19 1.36
9.27

Partida 04.10.00 ENCOFRADO Y DESENCOFRADO


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.2150 2.03 0.44
CLAVOS KG 0.1300 2.03 0.26
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.8300 2.03 9.82
10.53
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 04.11.00 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 04.12.00 SUMINISTRO Y COLOCACION DE ACCESORIOS BUZON DE CAIDA


Rendimiento 10.000 UNID/DIA Costo Unitario por : UNID. 200.60

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
5.42
Materiales
PEGAMENTO GLN 0.0030 33.90 0.10
YEE PVC SAL 8 UNID 1.0000 50.85 50.85
CODO PVC SAP 8 X 45 PZA 1.0000 67.80 67.80
CODO PVC SAP 8 X 90 PZA 1.0000 76.27 76.27
195.02
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 5.42 0.16
0.16

Partida 05.01.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.01.02 SOLADO DE CONCRETO 1:10 e=10cm.


Rendimiento 20.000 M2/DIA Costo Unitario por : M2. 57.82

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.50 0.6000 6.78 4.07
OFICIAL HH 0.50 0.2000 5.08 1.02
PEON HH 3.00 1.2000 3.39 4.07
9.15
Materiales
ARENA GRUESA M3 1.2600 38.14 48.05
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.0204 16.78 0.34
AGUA M3 0.0150 0.10 0.00
48.39
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.15 0.27
0.27

Partida 05.01.03 CONCRETO fc= 175 Kg/cm2 EN LOSAS


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.01.04 ENCOFRADO Y DESENCOFRADO


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.2150 2.03 0.44
CLAVOS KG 0.1300 2.03 0.26
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.8300 2.03 9.82
10.53
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.01.05 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.01.06 REVESTIMIENTO CON MORTERO 1:5


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 12.29

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 0.50 0.4000 3.39 1.36
6.78
Materiales
CLAVOS KG 0.0200 2.03 0.04
ARENA FINA M3 0.1170 38.14 4.46
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.0160 16.78 0.27
MADERA NACIONAL P/ ENCOFRADO-CARP P2 0.2640 2.03 0.54
5.31
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 6.78 0.20
0.20

Partida 05.01.07 SUMISTRO Y COLOCACION DE REJILLA 1/4"x1/2"xL 1 1/4"


Rendimiento 16.000 M2/DIA Costo Unitario por : M2. 160.61

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.5000 6.78 3.39
3.39
Materiales
REJILLA C/ PERFIL 1 1/4X11/4+L 1 1/1/4 M2 1.0300 152.54 157.12
157.12
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 3.39 0.10
0.10

Partida 05.02.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.02.02 CONCRETO fc= 175 Kg/cm2


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.02.03 ENCOFRADO Y DESENCOFRADO


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.01

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.3000 2.03 0.61
CLAVOS KG 0.3100 2.03 0.63
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.2400 2.03 8.62
9.86
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.02.04 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.02.05 TARRAJEO DE MUROS CON MORTERO


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 10.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 0.50 0.4000 3.39 1.36
6.78
Materiales
CLAVOS KG 0.0300 2.03 0.06
ARENA FINA M3 0.0180 38.14 0.69
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.1000 16.78 1.68
AGUA M3 0.0015 0.10 0.00
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 0.5000 2.03 1.02
3.44
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 6.78 0.20
0.20

Partida 05.02.06 SUMISTRO Y COLOCACION ACCESORIOSDE REJILLA 1/4"x1/2"xL 1 1/4"


Rendimiento 6.000 UNID/DIA Costo Unitario por : UNID. 486.85

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.3333 6.78 9.04
PEON HH 1.00 1.3333 3.39 4.52
13.56
Materiales
VERTEDERO METALICO UNID 1.0000 42.37 42.37
CODO DE 45 PVC SAL DE 6 UNID 1.0000 76.27 76.27
ADAPTADOR PVC SAP 6 UNID 1.0000 15.25 15.25
VALVULA DE PASO BRONCE DE 6 UNID 1.0000 338.98 338.98
472.88
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 13.56 0.41
0.41
Partida 05.02.07 COMPUERTA METALICA 0.45 x 0.50 mts. x 3/16"
Rendimiento 2.000 UNID/DIA Costo Unitario por : UNID. 135.59

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
COMPUERTA METALICA 1/8; 0.45 X 0.50 UNID 1.0000 135.59 135.59
135.59

Partida 05.03.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.03.02 CONCRETO fc= 175 Kg/cm2


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.03.03 ENCOFRADO Y DESENCOFRADO


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.2150 2.03 0.44
CLAVOS KG 0.1300 2.03 0.26
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.8300 2.03 9.82
10.53
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.03.04 TARRAJEO DE MUROS INTERIORES CON MORTERO


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 10.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 0.50 0.4000 3.39 1.36
6.78
Materiales
CLAVOS KG 0.0300 2.03 0.06
ARENA FINA M3 0.0180 38.14 0.69
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.1000 16.78 1.68
AGUA M3 0.0015 0.10 0.00
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 0.5000 2.03 1.02
3.44
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 6.78 0.20
0.20

Partida 05.03.05 COMPUERTA METALICA C/BORDES METALICOS


Rendimiento 2.000 UNID/DIA Costo Unitario por : UNID. 127.12

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
COMPUERTA TIPO I UNID 1.0000 127.12 127.12
127.12

Partida 05.04.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.04.02 CONCRETO fc= 175 Kg/cm2 EN MUROS


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.04.03 ENCOFRADO Y DESENCOFRADO


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.67

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.2150 2.03 0.44
CLAVOS KG 0.1300 2.03 0.26
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.8300 2.03 9.82
10.53
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.04.04 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.04.05 TARRAJEO DE MUROS INTERIORES CON MORTERO


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 10.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 0.50 0.4000 3.39 1.36
6.78
Materiales
CLAVOS KG 0.0300 2.03 0.06
ARENA FINA M3 0.0180 38.14 0.69
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.1000 16.78 1.68
AGUA M3 0.0015 0.10 0.00
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 0.5000 2.03 1.02
3.44
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 6.78 0.20
0.20

Partida 05.05.01 LIMPIEZA DE TERRENO MANUAL


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.12

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 2.00 0.3200 3.39 1.08
1.08
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.08 0.03
0.03

Partida 05.05.02 TRAZO Y REPLANTEO


Rendimiento 200.000 M2/DIA Costo Unitario por : M2. 1.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.50 0.0600 6.78 0.41
PEON HH 3.00 0.1200 3.39 0.41
0.81
Materiales
CLAVOS KG 0.0010 2.03 0.00
YESO EN BOLSAS DE 25 KG BLS 0.0100 3.05 0.03
ESTACA DE FIERRO UNID 0.5000 0.25 0.13
0.16
Equipos, Herramientas
TEODOLITO HM 1.00 0.0400 4.66 0.19
NIVEL DE INGENIERO HM 1.00 0.0400 3.18 0.13
HERRAMIENTAS MANUALES % MO 3.0000 0.81 0.02
0.34

Partida 05.05.03 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.05.04 RELLENO Y COMPACTADO DEL PISO


Rendimiento 7.000 M3/DIA Costo Unitario por : M3. 22.88

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.1429 3.39 3.87
3.87
Materiales
MATERIAL DE PRESTAMO SELECCIONADO-OBRA M3 1.0300 4.24 4.36
4.36
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 1.00 1.1429 12.71 14.53
HERRAMIENTAS MANUALES % MO 3.0000 3.87 0.12
14.64

Partida 05.05.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 MTS


Rendimiento 6.000 M3/DIA Costo Unitario por : M3. 4.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.3333 3.39 4.52
4.52
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 4.52 0.14
0.14

Partida 05.05.06 CONCRETO fc= 210 Kg/cm2


Rendimiento 8.000 M3/DIA Costo Unitario por : M3. 253.76

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.0000 6.78 6.78
OFICIAL HH 2.00 2.0000 5.08 10.16
PEON HH 6.00 6.0000 3.39 20.34
37.28
Materiales
PIEDRA CHANCADA 1/2 M3 0.5300 42.37 22.46
ARENA GRUESA M3 0.5100 38.14 19.45
CEMENTO PORTLAND TIPO I (42.5KG) BLS 9.7300 16.78 163.27
AGUA M3 0.2100 0.10 0.02
205.19
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 1.0000 8.47 8.47
VIBRADOR DE 3/4 - 2 CONCRETO HM 0.40 0.4000 4.24 1.69
HERRAMIENTAS MANUALES % MO 3.0000 37.28 1.12
11.29

Partida 05.05.07 CONCRETO fc= 175 Kg/cm2


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.05.08 ENCOFRADO Y DESENCOFRADO MUROS REFORZADOS


Rendimiento 8.000 M2/DIA Costo Unitario por : M2. 19.42

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.0000 6.78 6.78
OFICIAL HH 1.00 1.0000 5.08 5.08
11.86
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.2000 2.03 0.41
CLAVOS PARA MADERA C/C 3 KG 0.2000 2.03 0.41
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 2.8000 2.03 5.69
PETROLEO GLN 0.1000 6.95 0.69
7.20
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 11.86 0.36
0.36

Partida 05.05.09 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.05.10 TARRAJEO CON IMPERMEABILIZANTE DE LOSA DE FONDO-PISO, CANALES


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 31.99

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 2.00 1.6000 3.39 5.42
10.85
Materiales
ARENA FINA M3 0.1170 38.14 4.46
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.0160 16.78 0.27
IMPERMEAB. MORTERO/CONCRETO CHEMA 1 POLVO KG 0.4000 38.14 15.25
AGUA M3 0.0090 0.10 0.00
ANDAMIO DE MADERA P2 0.3900 2.12 0.83
20.81
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 10.85 0.33
0.33

Partida 05.05.11 INSTALACION DE TUBERIA PVC 200 mm ISO 4435


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 22.08

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
OFICIAL HH 1.00 0.0533 5.08 0.27
PEON HH 2.00 0.1067 3.39 0.36
0.99
Materiales
LIJA # 40 (PLIEGO) UNID 0.0400 1.69 0.07
TUBERIA PVC S25 200 MM ML 1.0300 19.49 20.08
LUBRICANTE UF GLN 0.0030 46.61 0.14
ANILLO UF 200 MM UNID 0.1660 4.66 0.77
21.06
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.99 0.03
0.03

Partida 05.05.12 SUMINISTRO Y COLOCACION DE TEE PVC 200 mm


Rendimiento 6.000 UNID/DIA Costo Unitario por : UNID. 87.28

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.3333 6.78 9.04
9.04
Materiales
CODO DE 90 PVC SAL DE 8 UNID 1.0000 77.97 77.97
77.97
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.05.13 SUMINISTRO Y COLOCACION DE CODO PVC 200 mm x 45


Rendimiento 10.000 UNID/DIA Costo Unitario por : UNID. 83.55

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
5.42
Materiales
CODO DE 45 PVC SAL DE 8 UNID 1.0000 77.97 77.97
77.97
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 5.42 0.16
0.16

Partida 05.05.14 SUMINISTRO Y COLOCACION DE ACCESORIOS


Rendimiento 10.000 UNID/DIA Costo Unitario por : UNID 1300.26
Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 1.00 0.8000 3.39 2.71
8.14
Materiales
PEGAMENTO GLN 0.0030 33.90 0.10
CANASTILLA DE BRONCE DE 8 BRIDADA UNID 1.0000 67.80 67.80
ABRAZADERA FF 8 PZA 6.0000 15.25 91.53
TUBERIA PVC S25 200 MM ML 8.1000 19.49 157.88
TEE SANITARIA SIMPLE PVC SAL DE 8 UNID 2.0000 38.14 76.27
ADAPTADOR PVC SAP 8 UNID 2.0000 16.95 33.90
YEE PVC SAL DOBLE DE 8 UNID 1.0000 118.64 118.64
CODO PVC SAP 8 X 45 PZA 2.0000 67.80 135.59
VALVULA DE COMPUERTA-BB 8 UNID 1.0000 610.17 610.17
1291.88
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 8.14 0.24
0.24

Partida 05.05.15 PASAMANO DE TUBO GALVANIZADO DE 2"


Rendimiento 8.000 ML/DIA Costo Unitario por : ML. 31.53

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 1.0000 6.78 6.78
PEON HH 1.00 1.0000 3.39 3.39
10.17
Materiales
FIERRO LISO 1/2 ML 0.2500 1.36 0.34
SOLDADURA CELLOCORD KG. 0.0600 6.36 0.38
LIJA PARA METAL UNID 0.3000 1.69 0.51
TUBERIA DE FIERRO NEGRO 02 ML 1.0500 10.17 10.68
11.91
Equipos, Herramientas
EQUIPO DE SOLDAR HM 1.35 1.3500 6.78 9.15
HERRAMIENTAS MANUALES % MO 3.0000 10.17 0.31
9.46

Partida 05.06.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.06.02 CONCRETO fc= 175 Kg/cm2 EN LOSAS


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.06.03 ENCOFRADO Y DESENCOFRADO MUROS


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.01

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.3000 2.03 0.61
CLAVOS KG 0.3100 2.03 0.63
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.2400 2.03 8.62
9.86
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.06.04 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.06.05 TARRAJEO DE MUROS INTERIORES CON MORTERO


Rendimiento 10.000 M2/DIA Costo Unitario por : M2. 10.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 0.50 0.4000 3.39 1.36
6.78
Materiales
CLAVOS KG 0.0300 2.03 0.06
ARENA FINA M3 0.0180 38.14 0.69
CEMENTO PORTLAND TIPO I (42.5KG) BLS 0.1000 16.78 1.68
AGUA M3 0.0015 0.10 0.00
MADERA TORNILLO INC. CORTE P/ENCOFRADO P2 0.5000 2.03 1.02
3.44
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 6.78 0.20
0.20

Partida 05.06.06 TUBERIA PVC SAP CLASE 10; 3/4"


Rendimiento 180.000 ML/DIA Costo Unitario por : ML. 12.00

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0444 6.78 0.30
PEON HH 2.00 0.0889 3.39 0.30
0.60
Materiales
PEGAMENTO PLASTICO PVC GLN 0.0010 33.90 0.03
TUB. PVC SAP PRESION C-10 R. 3/4 X 5m UNID 1.0300 11.02 11.35
11.38
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.60 0.02
0.02

Partida 05.06.07 VERTEDERO TRIANGULAR DE MADERA


Rendimiento 2.000 UNID/DIA Costo Unitario por : UNID. 39.15

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 4.0000 6.78 27.12
PEON HH 0.50 2.0000 3.39 6.78
33.90
Materiales
ATAGUIAS MADERA TORNILLO P2 1.0000 4.24 4.24
4.24
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 33.90 1.02
1.02

Partida 05.06.08 FILTRO DE GRAVA


Rendimiento 6.000 M3/DIA Costo Unitario por : M3. 48.30

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.3333 3.39 4.52
4.52
Materiales
GRAVA TRITURADA < 1 PULG. M3 1.0300 42.37 43.64
43.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 4.52 0.14
0.14

Partida 05.07.01 LIMPIEZA DE TERRENO MANUAL


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.12

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 2.00 0.3200 3.39 1.08
1.08
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 1.08 0.03
0.03

Partida 05.07.02 TRAZO Y REPLANTEO


Rendimiento 1,000.000 M2/DIA Costo Unitario por : M2. 0.43

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
TOPOGRAFO HH 2.00 0.0160 7.50 0.12
PEON HH 3.00 0.0240 3.39 0.08
0.20
Materiales
YESO EN BOLSAS DE 25 KG BLS 0.0450 3.05 0.14
ESTACA DE FIERRO UNID 0.0500 0.25 0.01
0.15
Equipos, Herramientas
WINCHA DE ACERO H.M. 5.00 0.0400 0.34 0.01
TEODOLITO H.M. 1.00 0.0080 4.66 0.04
NIVEL DE INGENIERO H.M. 1.00 0.0080 3.18 0.03
HERRAMIENTAS MANUALES % MO 3.0000 0.20 0.01
0.08

Partida 05.07.03 EXCAVACION EN CONGLOMERADO


Rendimiento 2.800 M3/DIA Costo Unitario por : M3. 9.98

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.8571 3.39 9.69
9.69
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.69 0.29
0.29

Partida 05.07.04 RELLENO Y COMPACTADO DEL PISO


Rendimiento 120.000 M3/DIA Costo Unitario por : M3. 8.11

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 31.20 2.0800 3.39 7.05
7.05
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP H.M. 1.00 0.0667 12.71 0.85
HERRAMIENTAS MANUALES % MO 3.0000 7.05 0.21
1.06

Partida 05.07.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 MTS


Rendimiento 6.000 M3/DIA Costo Unitario por : M3. 4.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.3333 3.39 4.52
4.52
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 4.52 0.14
0.14

Partida 05.07.06 NIVELACION Y COMPACTADO DEL LECHO


Rendimiento 10.000 M3/DIA Costo Unitario por : M3. 5.59

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 2.00 1.6000 3.39 5.42
5.42
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 5.42 0.16
0.16

Partida 05.07.07 CONCRETO fc= 175 Kg/cm2 DE MUROS


Rendimiento 9.000 M3/DIA Costo Unitario por : M3. 227.66

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8889 6.78 6.03
OFICIAL HH 0.50 0.4444 5.08 2.26
PEON HH 6.00 5.3333 3.39 18.08
26.36
Materiales
PIEDRA CHANCADA 1/2 M3 0.5500 42.37 23.31
ARENA GRUESA M3 0.5400 38.14 20.59
CEMENTO PORTLAND TIPO I (42.5KG) BLS 8.6600 16.78 145.31
189.21
Equipos, Herramientas
MEZCLADORA DE CONCRET DE 9 A 11 P3 HM 1.00 0.8889 8.47 7.53
VIBRADOR DE 3/4 - 2 CONCRETO HM 1.00 0.8889 4.24 3.77
HERRAMIENTAS MANUALES % MO 3.0000 26.36 0.79
12.09

Partida 05.07.08 ENCOFRADO Y DESENCOFRADO MUROS


Rendimiento 12.000 M2/DIA Costo Unitario por : M2. 18.01

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.6667 6.78 4.52
OFICIAL HH 1.00 0.6667 5.08 3.39
7.91
Materiales
ALAMBRE NEGRO NACIONAL # 8 KG 0.3000 2.03 0.61
CLAVOS KG 0.3100 2.03 0.63
MADERA NACIONAL P/ ENCOFRADO-CARP P2 4.2400 2.03 8.62
9.86
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 7.91 0.24
0.24

Partida 05.07.09 ACERO DE REFUERZO


Rendimiento 200.000 KG/DIA Costo Unitario por : KG. 2.06

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0400 6.78 0.27
OFICIAL HH 1.00 0.0400 5.08 0.20
0.47
Materiales
ALAMBRE NEGRO NACIONAL # 16 KG 0.0600 2.03 0.12
FIERRO CORRUGADO KG 1.0700 1.36 1.45
1.57
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.47 0.01
0.01

Partida 05.07.10 INSTALACION DE TUBERIA PVC - 8 ISO 4435


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 22.08

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
OFICIAL HH 1.00 0.0533 5.08 0.27
PEON HH 2.00 0.1067 3.39 0.36
0.99
Materiales
LIJA # 40 (PLIEGO) UNID 0.0400 1.69 0.07
TUBERIA PVC S25 200 MM ML 1.0300 19.49 20.08
LUBRICANTE UF GLN 0.0030 46.61 0.14
ANILLO UF 200 MM UNID 0.1660 4.66 0.77
21.06
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.99 0.03
0.03

Partida 05.07.11 SUMINISTRO Y COLOCACION DE ACCESORIOS PVC


Rendimiento 6.000 UNID/DIA Costo Unitario por : UNID. 1072.02
Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de obra
OPERARIO HH 1.00 1.3333 6.78 9.04
9.04
Materiales
ABRAZADERA FF 8 PZA 8.0000 15.25 122.03
TEE SANITARIA DOBLE PVC SAL DE 8 UNID 3.0000 42.37 127.12
CODO PVC SAP 8 X 45 PZA 3.0000 67.80 203.39
CODO PVC SAP 8 X 90 PZA 8.0000 76.27 610.17
1062.71
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.07.12 REJILLAS DE PROTECCION DE 1" x 1/8"


Rendimiento 2.000 UNID/DIA Costo Unitario por : UNID. 1.69

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
REJILLA DE FIERRO 1 X 1/8 UNID 1.0000 1.69 1.69
1.69

Partida 05.07.13 ARCILLA COMPACTADA e=10cms.


Rendimiento 100.000 M2/DIA Costo Unitario por : M2. 10.58

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 0.50 0.0400 6.78 0.27
PEON HH 2.00 0.1600 3.39 0.54
0.81
Materiales
ARCILLA M3 1.0300 8.47 8.73
8.73
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 1.00 0.0800 12.71 1.02
HERRAMIENTAS MANUALES % MO 3.0000 0.81 0.02
1.04

Partida 05.07.14 RELLENO CON GRAVA GRUESA e=2"


Rendimiento 6.000 M3/DIA Costo Unitario por : M3. 48.30

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.3333 3.39 4.52
4.52
Materiales
GRAVA TRITURADA < 1 PULG. M3 1.0300 42.37 43.64
43.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 4.52 0.14
0.14

Partida 05.07.15 RELLENO CON ARENA


Rendimiento 8.000 M3/DIA Costo Unitario por : M3. 42.77

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.0000 3.39 3.39
3.39
Materiales
ARENA GRUESA M3 1.0300 38.14 39.28
39.28
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 3.39 0.10
0.10

Partida 05.08.01 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 05.08.02 REFINE Y NIVELACION DE ZANJA


Rendimiento 50.000 ML/DIA Costo Unitario por : ML. 0.56

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 0.1600 3.39 0.54
0.54
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.54 0.02
0.02

Partida 05.08.03 CAMA DE APOYO DE ARENA, e=5cms.


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.28

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OFICIAL HH 0.10 0.0160 5.08 0.08
PEON HH 1.00 0.1600 3.39 0.54
0.62
Materiales
MATERIAL PARA CAMA DE APOYO M3 0.0750 8.47 0.64
0.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.62 0.02
0.02

Partida 05.08.04 RELLENO COMPACTADO DE ZANJA


Rendimiento 8.000 ML/DIA Costo Unitario por : ML. 4.52

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.0000 3.39 3.39
3.39
Materiales
AGUA M3 0.0830 0.10 0.01
0.01
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 0.08 0.0800 12.71 1.02
HERRAMIENTAS MANUALES % MO 3.0000 3.39 0.10
1.12

Partida 05.08.05 TUBERIA PVC SAL DE 4"


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 8.23

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
PEON HH 2.00 0.1067 3.39 0.36
0.72
Materiales
PEGAMENTO PLASTICO PVC GLN 0.0020 33.90 0.07
TUBERIA PVC SAL 4 ML 1.0300 7.20 7.42
7.49
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.72 0.02
0.02

Partida 05.08.06 SUMINISTRO Y COLOCACION DE CODO PVC 4"


Rendimiento 0.000 UNID/DIA Costo Unitario por : UNID. 8.47

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Materiales
CODO PVC SAL 4 UNID 1.0000 8.47 8.47
8.47

Partida 06.01.00 EXCAVACION MANUAL MATERIAL SUELTO


Rendimiento 3.000 M3/DIA Costo Unitario por : M3. 9.31

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 2.6667 3.39 9.04
9.04
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 9.04 0.27
0.27

Partida 06.02.00 REFINE Y NIVELACION DE ZANJA


Rendimiento 50.000 ML/DIA Costo Unitario por : ML. 0.56

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 0.1600 3.39 0.54
0.54
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.54 0.02
0.02

Partida 06.03.00 CAMA DE APOYO DE ARENA, e=5cms.


Rendimiento 50.000 M2/DIA Costo Unitario por : M2. 1.28

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OFICIAL HH 0.10 0.0160 5.08 0.08
PEON HH 1.00 0.1600 3.39 0.54
0.62
Materiales
MATERIAL PARA CAMA DE APOYO M3 0.0750 8.47 0.64
0.64
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.62 0.02
0.02

Partida 06.04.00 RELLENO COMPACTADO DE ZANJA


Rendimiento 8.000 ML/DIA Costo Unitario por : ML. 4.52

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
PEON HH 1.00 1.0000 3.39 3.39
3.39
Materiales
AGUA M3 0.0830 0.10 0.01
0.01
Equipos, Herramientas
COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 0.08 0.0800 12.71 1.02
HERRAMIENTAS MANUALES % MO 3.0000 3.39 0.10
1.12

Partida 06.05.00 TUBERIA PVC SAL DE 4"


Rendimiento 150.000 ML/DIA Costo Unitario por : ML. 8.23

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.0533 6.78 0.36
PEON HH 2.00 0.1067 3.39 0.36
0.72
Materiales
PEGAMENTO PLASTICO PVC GLN 0.0020 33.90 0.07
TUBERIA PVC SAL 4 ML 1.0300 7.20 7.42
7.49
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 0.72 0.02
0.02

Partida 06.06.00 CONEXIN DOMICILIARIA DE AGUA


Rendimiento 10.000 UNID/DIA Costo Unitario por : UNID. 25.33

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 0.8000 6.78 5.42
PEON HH 1.00 0.8000 3.39 2.71
8.14
Materiales
TUBO-CACHIMBA C.S.N. U.F. 6 UNID 1.0000 16.95 16.95
16.95
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 8.14 0.24
0.24

Partida 06.07.00 CAJA DE REGISTRO, TAPA DE 12"x 24" Y ACCESORIOS


Rendimiento 2.000 UNID/DIA Costo Unitario por : UNID. 139.36

Descripcion Insumo Unidad Cuadrilla Cantidad Precio Parcial


Mano de obra
OPERARIO HH 1.00 4.0000 6.78 27.12
PEON HH 1.00 4.0000 3.39 13.56
40.68
Materiales
CAJA CONCRETO SIMPLE DESAG. 0.30 X 0.60 UNID 1.0000 16.95 16.95
TAPA C/ MARCO Fo Fo DE DESAGUE 11 X 22 PZA 1.0000 21.19 21.19
REDUCCION PVC SAL P/DESAGUE DE 6 A 4 UNID 1.0000 21.19 21.19
CODO PVC SEL 4 X 45 UNID 1.0000 38.14 38.14
97.46
Equipos, Herramientas
HERRAMIENTAS MANUALES % MO 3.0000 40.68 1.22
1.22
FORMULA POLINOMICA

VALOR REFERENCIAL 2

FORMULA PARA EL REAJUSTE DEL PRECIO BASE: OCT de 2002

CLAVE CONCEPTO INDICE

M0 MANO DE OBRA 47
EH EQUIPOS Y HERRAMIENTAS 48
AM ACERO, ALAMBRE, CLAVO, CALAMINA 3
CP CEMENTO PORTLAND, CAL, TUB. PVC 21
AG AGREGADOS 4
MN MADERA NACIONAL Y OTROS 43
GU GASTOS GENERALES, I.G.V. Y UTILIDAD 39

Indice CREPCO para el area geografica Andahuaylas

MOa EHa AMa CPa AGa MNa


KVR2 = 0.3023
MOo
+ 0.0272
EHo
+ 0.0499
AMo
+ 0.2981
CPo
+ 0.0551
AGo
+ 0.0260
MNo
+ 0.2072
RMULA POLINOMICA

EL REAJUSTE DEL PRECIO BASE: OCT de 2002

GUa
GUo
FORMULA POLINOMICA

VALOR REFERENCIAL 1

FORMULA PARA EL REAJUSTE DEL PRECIO BASE: OCT de 2002

CLAVE CONCEPTO INDICE

M0 MANO DE OBRA 47
EH EQUIPOS Y HERRAMIENTAS 48
AM ACERO, ALAMBRE, CLAVO, CALAMINA 3
CP CEMENTO PORTLAND, CAL, TUB. PVC 21
AG AGREGADOS 4
MN MADERA NACIONAL Y OTROS 43
GU GASTOS GENERALES, I.G.V. Y UTILIDAD 39

Indice CREPCO para el area geografica Andahuaylas

MOa EHa AMa CPa AGa MNa


KVR1 = 0.2801
MOo
+ 0.0252
EHo
+ 0.0462
AMo
+ 0.2762
CPo
+ 0.0510
AGo
+ 0.0241
MNo
+ 0.2654
RMULA POLINOMICA

EL REAJUSTE DEL PRECIO BASE: OCT de 2002

GUa
GUo
CRONOGRAMA DE EJECUSION FISICA
MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

MESES
PARTIDA DESCRIPCION
PRIMER SEGUNDO TERCER CUARTO QUINTO SEXTO SEPTIMO

01.00.00 OBRAS PRELIMINARES 100.00%

02.00.00 RED DE COLECTORES


02.01.00 TRABAJOS PRELIMINARES 50.00% 50.00%

02.02.00 MOVIMIENTO DE TIERRAS 20.00% 20.00% 20.00% 20.00% 20.00%

02.03.00 INSTALACION DE TUBERIAS 25.00% 25.00% 25.00% 25.00%

03.00.00 LINEA EMISOR 50.00% 50.00%

04.00.00 CONSTRUCCION DE BUZONES 25.00% 25.00% 25.00% 25.00%

05.00.00 PLANTA DE TRATAMIENTO


05.01.00 CAMARA DE REJAS 50.00% 50.00%

05.02.00 DESARENADOR 50.00% 50.00%

05.03.00 CAJA DE DISTRIBUCION 100.00%

05.04.00 CAJA DE INSPECCION 100.00%

05.05.00 TANQUE IMHOFF 02 UNIDADES 25.00% 25.00% 25.00% 25.00%

05.06.00 FILTRO BIOLOGICO 25.00% 25.00% 25.00% 25.00%

05.07.00 LECHOS DE SECADO 02 UNIDADES 25.00% 25.00% 25.00% 25.00%

05.08.00 TUBERIA DE EVACUACION FINAL 50.00% 50.00%

06.00.00 CONEXIONES DOMICILIARIAS 30.00% 30.00% 40.00%


CRONOGRAMA DE EJECUSION FINANCIERA (VR2)
MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

COSTO MESES
PARTIDA DESCRIPCION
TOTAL PRIMER SEGUNDO TERCER CUARTO QUINTO SEXTO SEPTIMO

01.00.00 OBRAS PRELIMINARES 32,365.31 32,365.31

02.00.00 RED DE COLECTORES


02.01.00 TRABAJOS PRELIMINARES 8,554.43 4,277.22 4,277.22
02.02.00 MOVIMIENTO DE TIERRAS 99,519.41 19,903.88 19,903.88 19,903.88 19,903.88 19,903.88
02.03.00 INSTALACION DE TUBERIAS 104,231.45 26,057.86 26,057.86 26,057.86 26,057.86

03.00.00 LINEA EMISOR 44,322.20 22,161.10 22,161.10

04.00.00 CONSTRUCCION DE BUZONES 91,545.65 22,886.41 22,886.41 22,886.41 22,886.41

05.00.00 PLANTA DE TRATAMIENTO


05.01.00 CAMARA DE REJAS 892.82 446.41 446.41
05.02.00 DESARENADOR 1,402.39 701.19 701.19
05.03.00 CAJA DE DISTRIBUCION 577.10 577.10
05.04.00 CAJA DE INSPECCION 1,319.45 1,319.45
05.05.00 TANQUE IMHOFF 02 UNIDADES 127,243.47 31,810.87 31,810.87 31,810.87 31,810.87
05.06.00 FILTRO BIOLOGICO 70,390.97 17,597.74 17,597.74 17,597.74 17,597.74
05.07.00 LECHOS DE SECADO 02 UNIDADES 47,525.45 11,881.36 11,881.36 11,881.36 11,881.36
05.08.00 TUBERIA DE EVACUACION FINAL 3,508.08 1,754.04 1,754.04

06.00.00 CONEXIONES DOMICILIARIAS 109,175.31 32,752.59 32,752.59 43,670.12

COSTO DIRECTO 742,573.50 56,546.41 73,125.37 69,995.76 155,343.39 185,051.82 95,796.61 106,714.14
GASTOS GENERALES (15% C.D.) 111,386.02 8481.961 10968.806 10499.365 23301.508 27757.774 14369.491 16007.121
SUB-TOTAL 853,959.52 65028.366 84094.180 80495.128 178644.897 212809.598 110166.097 122721.258
I.G.V. (18% (EQ. + MAT.)) 82,696.49 6297.274 8143.586 7795.058 17299.772 20608.243 10668.362 11884.189
TOTAL PRESUPUESTO 936,656.01 71325.640 92237.767 88290.186 195944.669 233417.841 120834.459 134605.447
CRONOGRAMA DE EJECUSION FINANCIERA (VR1)
MUNICIPALIDAD DISTRITAL DE CANARIA

OBRA : SISTEMA DE ALCANTARILLADO CANARIA


DEPARTAMENTO : AYACUCHO
PROVINCIA : FAJARDO
DISTRITO : CANARIA Costo : OCT/2002

COSTO MESES
PARTIDA DESCRIPCION
TOTAL PRIMER SEGUNDO TERCER CUARTO QUINTO SEXTO SEPTIMO

01.00.00 OBRAS PRELIMINARES 32,365.31 32,365.31

02.00.00 RED DE COLECTORES


02.01.00 TRABAJOS PRELIMINARES 8,554.43 4,277.22 4,277.22
02.02.00 MOVIMIENTO DE TIERRAS 99,519.41 19,903.88 19,903.88 19,903.88 19,903.88 19,903.88
02.03.00 INSTALACION DE TUBERIAS 104,231.45 26,057.86 26,057.86 26,057.86 26,057.86

03.00.00 LINEA EMISOR 44,322.20 22,161.10 22,161.10

04.00.00 CONSTRUCCION DE BUZONES 91,545.65 22,886.41 22,886.41 22,886.41 22,886.41

05.00.00 PLANTA DE TRATAMIENTO


05.01.00 CAMARA DE REJAS 892.82 446.41 446.41
05.02.00 DESARENADOR 1,402.39 701.19 701.19
05.03.00 CAJA DE DISTRIBUCION 577.10 577.10
05.04.00 CAJA DE INSPECCION 1,319.45 1,319.45
05.05.00 TANQUE IMHOFF 02 UNIDADES 127,243.47 31,810.87 31,810.87 31,810.87 31,810.87
05.06.00 FILTRO BIOLOGICO 70,390.97 17,597.74 17,597.74 17,597.74 17,597.74
05.07.00 LECHOS DE SECADO 02 UNIDADES 47,525.45 11,881.36 11,881.36 11,881.36 11,881.36

05.08.00 TUBERIA DE EVACUACION FINAL 3,508.08 1,754.04 1,754.04

06.00.00 CONEXIONES DOMICILIARIAS 109,175.31 32,752.59 32,752.59 43,670.12

COSTO DIRECTO 742,573.500 56,546.41 73,125.37 69,995.76 155,343.39 185,051.82 95,796.61 106,714.14
GASTOS GENERALES (15% C.D.) 111,386.02 8481.961 10968.806 10499.365 23301.508 27757.774 14369.491 16007.121
UTILIDAD 74,257.35 5654.641 7312.537 6999.576 15534.339 18505.182 9579.661 10671.414
SUB-TOTAL 928,216.87 70683.006 91406.718 87494.704 194179.236 231314.780 119745.758 133392.672
I.G.V. (18% (EQ. + MAT.)) 82,696.49 6297.274 8143.586 7795.058 17299.772 20608.243 10668.362 11884.189
TOTAL PRESUPUESTO 1,010,913.36 76980.281 99550.304 95289.763 211479.008 251923.024 130414.120 145276.861
HOJA DE METRADO

ESTRUCTURA N 01 : RED COLECTORA 6372.31 ML


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
01,00,00 OBRAS PRELIMINARES
01,01,00 Cartel de Obra 1 1.00 UNID

02,0,00 RED DE COLECTORES


02,01,01 TRABAJOS PRELIMINARES
02,01,01 Limpieza deTerreno 6372.31 0.60 3823.38 3823.38 M2
02,01,02 Trazo y Replanteo 6372.31 6372.31 6372.31 ML

02,02,00 MOVIMIENTO DE TIERRA


02,02,01 Excavacion de Zanjas en Material Suelto; 1 VER HOJA ANEXO 5406.19 5406.19 M3
02,02,02 Excavacion de Zanjas en Roca Suelto/ ML; 1 855.72 855.72 M3
02,02,03 Refine y nivelacion de Zanjas 6372.31 6372.31 ML
02,02,04 Cama de apoyo para tuberias de 6 - 8 - 10 6372.31 0.60 3823.38 M2
02,02,05 Relleno y compactacion de zanjas VER HOJA ANEXO 6372.31 ML

02,03,00 INSTALACIONES DE TUBERIAS


02,03,01 Tuberia UPVC - S25 de 160 mm ISO 4435 1 6372.31 6372.31 6372.31 ML
02,03,02 Tuberia UPVC - S25 de 200 mm ISO 4435 1 0.00 0.00 0.00 ML
02,03,03 Prueba Hidraulica 1 6372.31 6372.31 6372.31 ML

ESTRUCTURA N 02 : RED EMISORA 829.55086 ML


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
03,00,00 LINEA EMISOR
03,01,00 Limpieza de Terreno Manual 1 829.55 0.60 497.73 497.73 M2
03,02,00 Trazo y Nivelacion Lineal 1 829.55 829.55 829.55 ML
03,03,01 Excavacion de Zanjas en Material Suelto; 1 VER HOJA ANEXO 1374.63 1374.63 M3
03,04,01 Excavacion de Zanjas en Roca Suelto/ ML; 1 VER HOJA ANEXO 312.46 312.46 M3
03,06,02 Refine y nivelacion de Zanjas 1 829.55 829.55 829.55 ML
03,06,02 Cama de apoyo para tuberias 1 829.55 0.60 497.73 497.73 M2
03,07,03 Relleno Compactado de Zanjas, H = 1,2 - 2.0 m 1 829.55 829.55 829.55 ML
03,08,03 Tuberia UPVC - S25 mm ISO 4435 1 829.55 829.55 829.55 ML
03,09,04 Prueba Hidraulica 1 829.55 829.55 829.55 ML

ESTRUCTURA N 03:CONSTRUCCION DE BUZONES


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
04,00,00 CONSTRUCCION DE BUZONES
04,01,00 Excavacion de Zanjas en Material Suelto 1 VER HOJA ANEXO 372.50 372.50 M3
04,02,00 Excavacion de Zanjas en Roca Suelta 1 VER HOJA ANEXO 69.27 69.27 M3
04,03,00 Buzon de Concret Tipo I en T.N., H = 1.2 a H = 1.50 m 100 100.00 UNID.
04,04,00 Buzon de Concret Tipo II en T.N., H = 1.50 a H = 2.00 m 20 20.00 UNID.
04,05,00 Buzon de Concret Tipo III en T.N., H = 2.00 a H = 2.50 m 8 8.00 UNID.
04,06,00 Buzon de Concret Tipo IV en T.N., H = 2.50 a H = 3.00 m 5 5.00 UNID.
04,07,00 Buzon de Concret Tipo V en T.N., H = 3.00 a H = 3.50 m 0 0.00 UNID.
04,08,00 Buzon de Concret Tipo VI en T.N., H = 3.50 a H = 4.85 m 4 4.00 UNID.
04,09,00 Pantalla de concreto Fc = 210 Kg/ cm2 3 1.80 0.60 0.20 0.65 0.65 M3
04,10,00 Encofrado y Desencofrado 3 1.80 0.60 3.24 6.12 M2
6 1.80 0.20 2.16
6 0.60 0.20 0.72

04.08.00 Acero Fy = 4200 Kg/cm2 43.54 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
1/2 24 1.60 38.40 38.17
1/2 9 0.60 5.40 5.37
04.09.00 Suministro e colocacion de accesorios en buzon de caida 3.00 UNID.
3 3.00

ESTRUCTURA N 04: CAMARA DE REJAS (01 UNIDAD)


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
05.00.00 PLANTA DE TRATAMIENTO
05.01.00 CAMARA DE REJAS
05.01.01 Excavacion en material Suelto 3.85 M3
1 3.10 0.70 1.00 2.17
1 2.40 0.70 1.00 1.68

05.01.02 Solado de concreto 1:10 e=05cm. 0.19 M3


1 3.10 0.70 0.05 0.11
1 2.40 0.70 0.05 0.08

05.01.03 concreto fc= 175 kg/cm2 1.50 M3


Muros 1 1.75 0.15 1.00 0.26
1 1.35 0.15 0.85 0.17
1 1.55 0.15 0.85 0.20
1 3.20 0.15 1.00 0.48
losa 1 3.10 0.70 0.10 0.22
1 2.40 0.70 0.10 0.17

05.01.04 encofrado y desencofrado 16.05 M2


Muros 2 7.85 1.00 15.70
Tapa 1 0.50 0.70 0.35
HOJA DE METRADO

05.01.05 Acero Fy = 4200 Kg/cm2 2.41 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
losa de piso 3/8 3 0.50 1.50 0.84
3/8 4 0.70 2.80 1.57

05.01.06 Tarrajeo de muro interior, mortero 1:5, e = 1.50 cms. 8.20 M2


1 7.85 1.00 7.85
1 0.50 0.70 0.35

05.01.07 suministro y colocacin de rejilla 1/4"x1/2"xl 1 1/4" 0.62 M2


1 1.55 0.40 0.62

05.02.00 DESARENADOR
05.02.01 excavacin manual material suelto 3.13 M3
1 0.60 0.60 0.50 0.18
1 4.10 0.90 0.80 2.95

05.02.02 concreto fc= 175 kg/cm2 1.52 M3


Piso 1 0.60 0.60 0.10 0.04
1 4.00 0.80 0.10 0.32
Muros 1 9.50 0.80 0.15 1.14
Tapa 1 0.70 0.70 0.05 0.02

05.02.03 encofrado y desencofrado 17.76 M2


Piso 2 4.00 0.10 0.80
Muro 2 9.90 0.80 15.84
tapa 2 0.80 0.70 1.12

05.02.04 Acero Fy = 4200 Kg/cm2 1.08 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
1/4 3.00 0.50 1.50 0.38
1/4 4.00 0.70 2.80 0.70

05.02.05 tarrajeo de muros con mortero 7.92 M2


1 9.90 0.80 7.92

05.02.06 suministro y colocacin accesorios de rejilla 1/4"x1/2"xl 1 1/4" 1.00 UNID.


1 1.00

05.02.07 compuerta metlica 0.45 x 0.50 mts. x 3/16" 1.00 UNID.


1 1.00

05.03.00 CAJA DE DISTRIBUCIN


05.03.01 excavacin manual material suelto 1.44 M3
1 1.20 1.20 1.00 1.44

05.03.02 concreto fc= 175 kg/cm2 0.49 M3


Piso 1 1.20 1.20 0.10 0.14
Muros 1 5.00 0.10 0.70 0.35

05.03.03 encofrado y desencofrado 7.48 M2


Piso 4 1.20 0.10 0.48
Muros 2 5.00 0.70 7.00

05.03.04 tarrajeo de muros interiores con mortero 5.50 M2


1 5.00 1.10 5.50

05.03.05 compuerta metlica c/bordes metlicos 2.00 UNID.


2 2.00

05.04.00 CAJA DE INSPECCIN


05.04.01 excavacin manual material suelto 3.60 M3
4 1.00 0.90 1.00 3.60

05.04.02 concreto fc= 175 kg/cm2 en muros 1.68 M3


Piso 4 0.80 0.80 0.15 0.38
Muros 4 2.80 1.00 0.10 1.12
Tapa 4 1.00 0.90 0.05 0.18

05.04.03 encofrado y desencofrado 24.20 M2


Piso 4 3.00 0.15 1.80
Muros 8 2.80 1.00 22.40

05.04.04 Acero Fy = 4200 Kg/cm2 24.44 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
3/8 36.00 0.90 32.40 18.14
1/4 28.00 0.90 25.20 6.30

05.04.05 tarrajeo de muros interiores con mortero 38.40 M2


muros 4 3.20 0.90 11.52
losa 4 8.00 0.80 25.60
borde de muro 4 3.20 0.10 1.28

ESTRUCTURA N 05: TANQUE DE TRATAMIENTO: TANQUE IMHOFF DIGESTOR (02 UNID.).


HOJA DE METRADO

N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
05.05.00 TANQUE IMHOFF
TRABAJOS PRELIMINARES
05.05.01 limpieza de terreno manual 228.00 M2
1 12.00 19.00 228.00

05.05.02 trazo y replanteo 73.71 M2


1 10.15 6.60 66.99
2 2.10 1.60 6.72
MOVIMIENTO DE TIERRAS
05.05.03 excavacin manual material suelto 613.11 M3
Tanque 1 10.15 6.60 8.40 562.72
Caja de valvulas 4 1.00 1.00 1.00 4.00
4 2.50 6.60 0.60 39.60
Tuberias 2 10.15 0.40 0.60 4.87
4 2.00 0.40 0.60 1.92

05.05.04 relleno y compactado del piso 28.88 M3


4 0.90 0.90 0.10 0.32
2 10.20 2.00 0.70 28.56

05.05.05 eliminacin de material excedente hasta 30.00 mts 730.28 M3


1.25 584.22 730.28

OBRAS DE CONCRETO
05.05.06 concreto fc= 210 kg/cm2 136.22 M3
Muros 3 0.30 6.60 8.40 49.90
2 0.30 10.15 8.40 51.16
Muro centro 2 6.60 0.30 3.10 12.28
2 6.60 0.30 4.00 15.84
Pantalla difusora (deflectora) 4 10.00 0.15 0.60 3.60
Canaleta interior 2 10.00 0.15 0.70 2.10
Canaleta exterior 1 10.00 0.15 0.90 1.35

05.05.07 concreto fc= 175 kg/cm2, sin mezcladora 1.65 M3


Caja de valvulas 4 3.20 0.10 0.90 1.15
Tapa de valvula 4 0.70 0.70 0.05 0.10
paredes de fondo 4 1.00 1.00 0.10 0.40

05.05.08 encofrado y desencofrado muros reforzados 984.72 M2


Muros 6 6.60 8.40 332.64
4 10.15 8.40 341.04
Muros centro 4 6.60 3.10 81.84
4 6.60 4.00 105.60
Pantalla difusora (deflectora) 8 10.00 0.60 48.00
Canaleta interior 4 10.00 0.80 32.00
Canaleta exterior 2 10.00 1.00 20.00
Caja de valvulas 8 3.20 0.90 23.04
Tapa de valvula 4 2.80 0.05 0.56

05.05.09 Acero Fy = 4200 Kg/cm2 11272.99 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
Muro (vertical) 5/8 3.00 418.00 1254.00 1946.21
5/8 2.00 646.00 1292.00 2005.18
Muro (horizontal) 5/8 3.00 621.00 1863.00 2891.38
5/8 2.00 919.80 1839.60 2855.06
Muro centro (Vertical) 1/2 2.00 125.40 250.80 249.30
1/2 2.00 92.40 184.80 183.69
Muro centro (Horizontal) 1/2 2.00 133.00 266.00 264.40
1/2 2.00 98.00 196.00 194.82
Canaleta interior (vertical) 3/8 2.00 61.20 122.40 68.54
Canaleta interior (horizontal) 3/8 2.00 43.00 86.00 48.16
Canaleta exterior (vertical) 3/8 1.00 71.40 71.40 39.98
Canaleta exterior (horizontal) 3/8 1.00 53.75 53.75 30.10
Base (tranversal) 3/8 2.00 245.00 490.00 274.40
Base (Horizontal) 3/8 2.00 198.00 396.00 221.76

05.05.10 tarrajeo con impermeabilizante de losa de fondo-piso, canales 954.16 M2


Muros 6 6.60 8.40 332.64
4 10.15 8.40 341.04
Muro centro 4 6.60 3.40 89.76
4 6.60 4.30 113.52
Pantalla 8 1.00 0.90 7.20
Canaleta interior 4 10.00 1.10 44.00
Canaleta exterior 2 10.00 1.30 26.00

TUBERIAS, VALVULAS Y ACCESORIOS


05.05.11 instalacin de tubera pvc 200 mm iso 4435 77.00 ML
1 77.00 77.00

05.05.12 suministro y colocacin de tee pvc 200 mm 6.00 UNID.


6 1.00 6.00

05.05.13 suministro y colocacin de codo pvc 200 mm x 45 y x 90 14.00 UNID.


HOJA DE METRADO

14 1.00 14.00

05.05.14 suministro y colocacin de accesorios 2.00 UNID.


2 1.00 2.00

05.05.15 pasamano de tubo galvanizado de 2" 104.80 UNID.


1 104.80 104.80

05.06.00 FILTRO BIOLGICO


05.06.01 excavacin manual material suelto 592.20 M3
1 16.00 11.75 3.15 592.20

05.06.02 concreto fc= 175 kg/cm2 88.38 M3


Piso 1 16.00 11.40 0.15 27.36
Muros 1 54.80 0.30 3.00 49.32
Murete (piso) 12 10.70 0.15 0.50 9.63
canaleta 1 16.00 0.70 0.15 1.68
Murete vertedero 62 0.25 0.10 0.25 0.39

05.06.03 encofrado y desencofrado 487.52 M2


Piso 1 54.80 0.15 8.22
Muros 2 54.80 3.00 328.80
Murete (piso) 24 10.70 0.50 128.40
canaleta 2 16.00 0.40 12.80
Murete vertedero 124 0.30 0.25 9.30

05.06.04 Acero Fy = 4200 Kg/cm2 3196.34 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
losa prefabricada 3/8 187.00 12.90 2412.30 1350.89
muro (vertical) 3/8 220.00 4.00 880.00 492.80
muro (horizontal) 3/8 16.00 46.00 736.00 412.16
vigas de soporte 0.20x0.20 3/8 2.00 66.40 132.80 74.37
piso (transversal) 3/8 55.00 12.00 660.00 369.60
piso (horizontal) 3/8 40.00 16.60 664.00 371.84
canaleta (vertical) 3/8 55.00 1.50 82.50 46.20
canaleta (horizontal) 3/8 5.00 16.60 83.00 46.48
estribo de viga 1/4 2.00 64.00 128.00 32.00

05.06.05 Tarrajeo de muros interiores con mortero 506.10 M2


Piso 1 16.00 11.75 188.00
Muros 1 54.80 3.00 164.40
Murete (piso) 24 10.70 0.50 128.40
canaleta 2 16.00 0.50 16.00
murete (vertedero) 124 0.30 0.25 9.30

05.06.06 tubera pvc sap clase 10; 3/4" 652.70 ML


61 10.70 652.70

Tuberia UPVC diam. 6" 5.00 ML


1.00 5.00 5.00

05.06.07 vertedero triangular de madera 62.00 UNID.


62.00 62.00

286.75 M3
05.06.08 filtro de grava 1 15.40 9.80 1.90 286.75

ESTRUCTURA N 07: PLANTA DE TRATAMIENTO: LECHO DE SECADO.


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
05.07.00 LECHOS DE SECADO
05.07.01 limpieza de terreno manual 317.00 M2
2 11.00 14.00 308.00
4 1.50 1.50 9.00

05.07.02 trazo y replanteo 234.00 M2


2 12.80 9.00 230.40
4 0.90 1.00 3.60

MOVIMIENTO DE TIERRAS
05.07.03 excavacin en conglomerado 696.96 M3
2 12.80 9.00 3.00 691.20
metrado de las cajas de registro en todo el sistema 6 1.20 0.80 1.00 5.76

05.07.04 relleno y compactado del piso 115.20 M3


2 12.80 9.00 0.50 115.20

05.07.05 eliminacin de material excedente hasta 30.00 mts 727.20 M3


1.25 581.76 727.20

05.07.06 nivelacin y compactado del lecho 230.40 M2


2 12.80 9.00 230.40

OBRAS DE CONCRETO
05.07.07 concreto fc= 175 kg/cm2 de muros 60.74 M3
HOJA DE METRADO

Muro lateral 2 54.10 0.15 1.70 27.59


zapata de muro 2 54.10 0.60 0.30 19.48
Canal colector 4 12.30 1.10 0.10 5.41
Tapa de canal 4 12.30 0.40 0.05 0.98
Salpicador 8 1.00 1.00 0.15 1.20
Caja de registro (muro) 6 4.00 0.10 0.90 2.16
losa de fondo de caja de registro 6 1.20 0.80 0.10 0.58
tapa de caja de registro 6 1.10 0.70 0.05 0.23
Dado 8 0.40 0.40 0.30 0.38
8 0.20 0.40 0.30 0.19
Losa de concreto armado 4 8.45 0.50 0.15 2.54

05.07.08 encofrado y desencofrado 516.90 M2


Muro lateral 4 54.10 1.70 367.88
zapata de muro 4 54.10 0.30 64.92
canal colector 8 12.30 0.25 24.60
Dado 32 0.40 0.30 3.84
32 0.40 0.30 3.84
caja de registro 6 4.00 0.90 21.60
caja de registro fondo 6 4.00 0.10 2.40
caja de registro tapa 6 4.00 0.05 1.20
tapa canal 8 12.30 0.05 4.92
salpicador 32 1.00 0.15 4.80
Losa de concreto 4 8.45 0.50 16.90

05.07.09 Acero Fy = 4200 Kg/cm2 1133.85 Kg.


Diam. Veces Long. Total (ml.) Parcial (kg.)
muro (vertical) 3/8 2 360.00 720.00 403.20
muro (horizontal) 3/8 7 110.00 770.00 431.20
zapata (transversal) 3/8 350 0.50 175.00 98.00
zapata (horizontal) 3/8 3 110.00 330.00 184.80
caja de registro tapa 1/4 6 11.10 66.60 16.65

TUBERIA Y ACCESORIOS
05.07.10 instalacin de tubera pvc - 8 iso 4435 1 86.00 86.00 86.00 ML
05.07.11 suministro y colocacin de accesorios pvc 2 2.00 2.00 UNID.
05.07.12 rejillas de proteccin de 1" x 1/8" 1 302.00 302.00 302.00 UNID.

LECHO DE FILTROS
05.07.13 arcilla compactada e=10cms. 2 12.30 8.45 207.87 207.87 M3
05.07.14 relleno con grava gruesa e=2" 2 12.30 8.45 0.05 10.39 10.39 M3
05.07.15 relleno con arena 2 12.30 8.45 0.20 41.57 41.57 M3

ESTRUCTURA N 08: EVACUACION FINAL


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
05.08.00 TUBERA DE EVACUACIN FINAL
05.08.01 excavacin manual material suelto 2.00 96.00 0.60 1.00 115.20 115.20 M3
05.08.02 refine y nivelacin de zanja 2.00 96.00 192.00 192.00 ML
05.08.03 cama de apoyo de arena, e=5cms. 2.00 96.00 192.00 192.00 ML
05.08.04 relleno compactado de zanja 2.00 96.00 0.60 0.90 103.68 103.68 M3
05.08.05 tubera pvc sal de 4" 2.00 96.00 192.00 192.00 ML
05.08.06 suministro y colocacin de codo pvc 4" 4.00 4.00 4.00 UNID.

ESTRUCTURA N 09: CONEXIONES DOMICILIARIAS 446 unidades


N DE DIMENSIONES
CODIGO DESCRIPCION PARCIAL TOTAL UND
VECES LARGO ANCHO ALTO
06.00.00 CONEXIONES DOMICILIARIAS
06.01.00 excavacin manual material suelto 1.00 1784.00 0.60 1.20 1284.48 1284.48 M3
06.02.00 refine y nivelacin de zanja 1.00 1784.00 1784.00 1784.00 ML
06.03.00 cama de apoyo de arena, e=5cms. 1.00 1784.00 1784.00 1784.00 ML
06.04.00 relleno compactado de zanja 1.00 1784.00 0.60 1.20 1284.48 1284.48 M3
06.05.00 tubera pvc sal de 4" 1.00 1784.00 1784.00 1784.00 ML
06.06.00 conexin domiciliaria de agua 446.00 446.00 446.00 ML
06.07.00 caja de registro, tapa de 12"x 24" y accesorios 446.00 446.00 446.00 UNID.
HOJA DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
BUZON TRAMO DE TUBERIA Coeficiente de CAUDALES (Q)
TUBERIA
Distribucion fo
Pendiente Longitud (lts/seg/ml) En el Anterior Laterales (pulgadas) Longitud Longitud
Bi Bj dH dL Total
S (mts.) tramo al tramo al tramo 6" (mts.) 8" (mts.)

43 42 0.32 26.80 1.194% 26.802 0.001415 0.038 0.000 0.000 0.038 0.636 26.802 0.000
42 41 1.30 40.25 3.230% 40.271 0.001415 0.057 0.038 0.000 0.095 0.745 40.271 0.000
41 40 1.91 36.83 5.186% 36.879 0.001415 0.052 0.095 0.000 0.147 0.803 36.879 0.000
40 37 1.80 26.97 6.674% 27.030 0.001415 0.038 0.147 0.093 0.279 0.974 27.030 0.000
37 36 1.02 24.90 4.096% 24.921 0.001415 0.035 0.279 0.000 0.314 1.116 24.921 0.000
36 31 1.53 43.35 3.529% 43.377 0.001415 0.061 0.314 0.130 0.505 1.371 43.377 0.000
31 30 1.17 53.55 2.185% 53.563 0.001415 0.076 0.505 0.061 0.642 1.641 53.563 0.000
30 29 4.84 85.95 5.631% 86.086 0.001415 0.122 0.642 0.000 0.764 1.467 86.086 0.000
29 28 1.52 36.30 4.187% 36.332 0.001415 0.051 0.764 0.000 0.815 1.589 36.332 0.000
28 27 4.02 74.67 5.384% 74.778 0.001415 0.106 0.815 0.122 1.043 1.662 74.778 0.000
27 26 1.69 37.53 4.503% 37.568 0.001415 0.053 1.043 0.000 1.096 1.751 37.568 0.000
26 25 0.80 71.05 1.126% 71.055 0.001415 0.101 1.096 0.000 1.197 2.347 71.055 0.000
25 24 0.25 20.25 1.235% 20.252 0.001415 0.029 1.197 0.000 1.225 2.328 20.252 0.000
24 22 0.34 28.70 1.185% 28.702 0.001415 0.041 1.225 0.000 1.266 2.375 28.702 0.000
22 23 2.29 80.85 2.832% 80.882 0.001415 0.114 0.633 0.089 0.837 1.726 80.882 0.000
23 8 5.31 79.15 6.709% 79.328 0.001415 0.112 0.418 0.127 0.658 1.342 79.328 0.000

18 19A 9.06 37.90 23.905% 38.968 0.001415 0.055 0.000 0.000 0.055 0.417 38.968 0.000
19A 19 6.36 31.80 20.000% 32.430 0.001415 0.046 0.055 0.000 0.101 0.542 32.430 0.000
19 23A 4.51 44.70 10.089% 44.927 0.001415 0.064 0.051 0.089 0.204 0.801 44.927 0.000
23A 23 2.75 35.68 7.707% 35.786 0.001415 0.051 0.204 0.000 0.254 0.915 35.786 0.000
23 48 2.29 40.02 5.722% 40.085 0.001415 0.057 0.127 0.418 0.602 1.338 40.085 0.000
48 52 1.78 40.40 4.406% 40.439 0.001415 0.057 0.602 0.000 0.659 1.453 40.439 0.000
52 52A 0.67 34.50 1.942% 34.507 0.001415 0.049 0.330 0.031 0.410 1.418 34.507 0.000
52A 59 0.69 46.59 1.481% 46.595 0.001415 0.066 0.410 0.000 0.476 1.578 46.595 0.000
59 64A 0.45 41.41 1.087% 41.412 0.001415 0.059 0.159 0.000 0.217 1.246 41.412 0.000
64A 64 0.44 39.80 1.106% 39.802 0.001415 0.056 0.217 0.000 0.274 1.354 39.802 0.000
64 67 0.54 53.20 1.015% 53.203 0.001415 0.075 0.137 0.000 0.212 1.251 53.203 0.000
67 70 0.94 65.21 1.441% 65.217 0.001415 0.092 0.212 0.000 0.304 1.341 65.217 0.000

73 70 1.33 57.62 2.310% 57.635 0.001415 0.082 0.000 0.000 0.082 0.749 57.635 0.000

73 78 0.76 39.35 1.934% 39.357 0.001415 0.056 0.000 0.000 0.056 0.671 39.357 0.000

82 79 0.44 40.00 1.100% 40.002 0.001415 0.057 0.000 0.000 0.057 0.751 40.002 0.000
79 78 0.75 51.82 1.447% 51.825 0.001415 0.073 0.057 0.000 0.130 0.974 51.825 0.000

82 86 0.84 43.35 1.938% 43.358 0.001415 0.061 0.000 0.000 0.061 0.696 43.358 0.000
86 88 8.26 75.40 10.955% 75.851 0.001415 0.107 0.061 0.000 0.169 0.735 75.851 0.000
88 89 6.25 42.44 14.727% 42.898 0.001415 0.061 0.169 0.000 0.229 0.780 42.898 0.000
89 90 5.93 36.21 16.377% 36.692 0.001415 0.052 0.229 0.000 0.281 0.826 36.692 0.000
90 91 10.70 30.08 35.572% 31.926 0.001415 0.045 0.281 0.000 0.327 0.755 31.926 0.000

20 20A 4.39 20.00 21.950% 20.476 0.001415 0.029 0.000 0.000 0.029 0.333 20.476 0.000
20A 21 6.61 50.81 13.009% 51.238 0.001415 0.073 0.029 0.000 0.102 0.588 51.238 0.000
21 22A 6.11 40.99 14.906% 41.443 0.001415 0.059 0.051 0.013 0.122 0.615 41.443 0.000
22A 22 5.73 39.15 14.636% 39.567 0.001415 0.056 0.122 0.000 0.178 0.711 39.567 0.000
22 47 3.16 41.35 7.642% 41.471 0.001415 0.059 0.089 0.633 0.781 1.397 41.471 0.000
47 50 2.79 39.70 7.028% 39.798 0.001415 0.056 0.781 0.000 0.837 1.456 39.798 0.000
50 60 0.81 79.87 1.014% 79.874 0.001415 0.113 0.837 0.098 1.048 2.277 79.874 0.000
60 60A 0.76 48.13 1.579% 48.136 0.001415 0.068 1.048 0.305 1.421 2.350 48.136 0.000
60A 63 0.82 34.20 2.398% 34.210 0.001415 0.048 1.421 0.000 1.469 2.200 34.210 0.000
63 66 0.59 52.80 1.117% 52.803 0.001415 0.075 1.469 0.256 1.801 2.740 52.803 0.000
66 69 0.70 64.45 1.086% 64.454 0.001415 0.091 1.801 0.000 1.892 2.806 64.454 0.000
69 74 0.52 45.35 1.147% 45.353 0.001415 0.064 1.892 0.625 2.581 3.121 45.353 0.000
74 76 0.72 61.72 1.167% 61.724 0.001415 0.087 2.581 0.000 2.669 3.150 61.724 0.000
76 83A 0.49 44.98 1.089% 44.983 0.001415 0.064 2.669 0.542 3.275 3.445 44.983 0.000
83A 84 1.34 41.75 3.210% 41.771 0.001415 0.059 3.275 0.000 3.334 2.832 41.771 0.000
84 85 4.99 46.45 10.743% 46.717 0.001415 0.066 3.334 0.000 3.400 2.275 46.717 0.000
85 92 6.66 48.30 13.789% 48.757 0.000311 0.015 3.400 0.000 3.415 2.174 0.000 48.757
92 96 0.33 25.21 1.309% 25.212 0.000311 0.008 3.415 0.000 3.423 3.384 0.000 25.212
96 97 1.73 74.79 2.313% 74.810 0.000311 0.023 3.423 0.000 3.446 3.049 0.000 74.810
97 98 2.88 48.05 5.994% 48.136 0.000311 0.015 3.446 0.000 3.461 2.555 0.000 48.136
98 99 1.42 51.95 2.733% 51.969 0.000311 0.016 3.461 0.000 3.477 2.965 0.000 51.969
99 91 7.17 54.66 13.117% 55.128 0.000311 0.017 3.477 0.000 3.495 2.214 0.000 55.128
HOJA DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
BUZON TRAMO DE TUBERIA Coeficiente de CAUDALES (Q)
TUBERIA
Distribucion fo
Pendiente Longitud (lts/seg/ml) En el Anterior Laterales (pulgadas) Longitud Longitud
Bi Bj dH dL Total
S (mts.) tramo al tramo al tramo 6" (mts.) 8" (mts.)

21A 21 1.32 18.38 7.182% 18.427 0.001415 0.026 0.000 0.000 0.026 0.395 18.427 0.000
21 19B 1.89 28.62 6.604% 28.682 0.001415 0.041 0.013 0.051 0.104 0.675 28.682 0.000
19B 19 6.34 52.28 12.127% 52.663 0.001415 0.075 0.104 0.000 0.179 0.737 52.663 0.000
19 15 4.85 79.65 6.089% 79.798 0.001415 0.113 0.089 0.051 0.253 0.955 79.798 0.000
15 14 2.52 44.07 5.718% 44.142 0.001415 0.062 0.126 0.053 0.242 0.951 44.142 0.000
14 13 4.68 38.00 12.316% 38.287 0.001415 0.054 0.242 0.000 0.296 0.888 38.287 0.000
13 3 2.58 58.51 4.410% 58.567 0.001415 0.083 0.148 0.056 0.287 1.064 58.567 0.000

11 12 5.25 36.00 14.583% 36.381 0.001415 0.051 0.000 0.000 0.051 0.446 36.381 0.000
12 13 4.15 42.34 9.802% 42.543 0.001415 0.060 0.051 0.000 0.112 0.643 42.543 0.000
13 6 3.33 36.39 9.151% 36.542 0.001415 0.052 0.056 0.148 0.256 0.889 36.542 0.000
6 55 4.71 45.42 10.370% 45.664 0.001415 0.065 0.256 1.235 1.555 1.708 45.664 0.000
55 54A 2.64 47.85 5.517% 47.923 0.001415 0.068 1.555 0.378 2.001 2.113 47.923 0.000
54A 54 0.35 32.25 1.085% 32.252 0.001415 0.046 2.001 0.000 2.046 2.890 32.252 0.000

33 34 9.29 41.80 22.225% 42.820 0.001415 0.061 0.000 0.000 0.061 0.438 42.820 0.000
34 35 5.46 26.20 20.840% 26.763 0.001415 0.038 0.061 0.000 0.098 0.532 26.763 0.000
35 36 1.28 22.00 5.818% 22.037 0.001415 0.031 0.098 0.000 0.130 0.750 22.037 0.000

9 10 2.16 37.47 5.765% 37.532 0.001415 0.053 0.000 0.000 0.053 0.537 37.532 0.000

10A 10 1.84 67.93 2.709% 67.955 0.001415 0.096 0.000 0.000 0.096 0.774 67.955 0.000

45A 45 2.23 22.84 9.764% 22.949 0.001415 0.032 0.000 0.000 0.032 0.405 22.949 0.000
45 62 5.98 42.47 14.081% 42.889 0.001415 0.061 0.032 0.000 0.093 0.561 42.889 0.000
62 28 1.95 20.00 9.750% 20.095 0.001415 0.028 0.093 0.000 0.122 0.664 20.095 0.000

8 7 1.07 13.25 8.075% 13.293 0.001415 0.019 0.329 0.147 0.495 1.165 13.293 0.000
7 55 6.47 91.70 7.056% 91.928 0.001415 0.130 0.248 0.000 0.378 1.080 91.928 0.000

64 63A 1.47 41.50 3.542% 41.526 0.001415 0.059 0.000 0.137 0.196 0.960 41.526 0.000
63A 63 0.85 42.96 1.979% 42.968 0.001415 0.061 0.196 0.000 0.256 1.185 42.968 0.000

10 2A 5.64 40.00 14.100% 40.396 0.001415 0.057 0.000 0.149 0.206 0.756 40.396 0.000
2A 2 2.54 27.03 9.397% 27.149 0.001415 0.038 0.206 0.000 0.245 0.870 27.149 0.000

5 4 0.79 56.06 1.409% 56.066 0.001415 0.079 0.000 0.000 0.079 0.814 56.066 0.000
4 3 0.51 22.64 2.253% 22.646 0.001415 0.032 0.079 0.000 0.111 0.846 22.646 0.000

32 44 6.68 32.40 20.617% 33.081 0.001415 0.047 0.000 0.000 0.047 0.404 33.081 0.000
44 31 1.29 10.00 12.900% 10.083 0.001415 0.014 0.047 0.000 0.061 0.487 10.083 0.000

1 2 6.52 80.45 8.104% 80.714 0.001415 0.114 0.000 0.000 0.114 0.672 80.714 0.000
2 3 2.21 25.32 8.728% 25.416 0.001415 0.036 0.114 0.245 0.395 1.055 25.416 0.000
3 6 0.76 66.80 1.138% 66.804 0.001415 0.095 0.395 0.398 0.888 2.095 66.804 0.000

7 6 1.76 69.88 2.519% 69.902 0.001415 0.099 0.000 0.248 0.347 1.268 69.902 0.000

59 58 1.94 76.12 2.549% 76.145 0.001415 0.108 0.000 0.159 0.266 1.146 76.145 0.000
58 57A 5.39 54.63 9.866% 54.895 0.001415 0.078 0.133 0.140 0.351 0.986 54.895 0.000
57A 57 5.11 27.25 18.752% 27.725 0.001415 0.039 0.351 0.000 0.390 0.910 27.725 0.000

59 59A 0.68 42.00 1.607% 42.005 0.001415 0.059 0.000 0.159 0.218 1.160 42.005 0.000
59A 60 0.81 41.88 1.946% 41.888 0.001415 0.059 0.218 0.000 0.277 1.224 41.888 0.000
0.000 0.000
61 60 0.32 19.62 1.631% 19.623 0.001415 0.028 0.000 0.000 0.028 0.534 19.623 0.000

17 16 5.67 27.45 20.656% 28.029 0.001415 0.040 0.000 0.000 0.040 0.379 28.029 0.000
16 16A 6.76 32.55 20.768% 33.245 0.001415 0.047 0.040 0.000 0.087 0.508 33.245 0.000
16A 15 1.85 13.95 13.262% 14.072 0.001415 0.020 0.087 0.000 0.107 0.597 14.072 0.000
15 15A 5.81 46.05 12.617% 46.415 0.001415 0.066 0.053 0.126 0.245 0.824 46.415 0.000
15A 8 1.93 34.88 5.533% 34.933 0.001415 0.049 0.245 0.000 0.295 1.030 34.933 0.000
8 8A 1.52 45.12 3.369% 45.146 0.001415 0.064 0.147 0.329 0.540 1.418 45.146 0.000
8A 53 1.61 36.60 4.399% 36.635 0.001415 0.052 0.540 0.000 0.592 1.396 36.635 0.000
HOJA DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
BUZON TRAMO DE TUBERIA Coeficiente de CAUDALES (Q)
TUBERIA
Distribucion fo
Pendiente Longitud (lts/seg/ml) En el Anterior Laterales (pulgadas) Longitud Longitud
Bi Bj dH dL Total
S (mts.) tramo al tramo al tramo 6" (mts.) 8" (mts.)

71 68 1.79 59.75 2.996% 59.777 0.001415 0.085 0.000 0.000 0.085 0.723 59.777 0.000
68 65 1.61 60.26 2.672% 60.282 0.001415 0.085 0.085 0.000 0.170 0.960 60.282 0.000
65 58 1.62 77.89 2.080% 77.907 0.001415 0.110 0.170 0.000 0.280 1.214 77.907 0.000
58 53B 0.52 41.85 1.243% 41.853 0.001415 0.059 0.140 0.133 0.333 1.426 41.853 0.000
53B 53 0.51 40.00 1.275% 40.003 0.001415 0.057 0.333 0.000 0.389 1.505 40.003 0.000

71 72 0.65 55.70 1.167% 55.704 0.001415 0.079 0.000 0.000 0.079 0.841 55.704 0.000
72 80 1.62 32.96 4.915% 33.000 0.001415 0.047 0.079 0.000 0.126 0.764 33.000 0.000
80 81 2.40 76.76 3.127% 76.798 0.001415 0.109 0.063 0.000 0.171 0.935 76.798 0.000
81 87 2.57 47.21 5.444% 47.280 0.001415 0.067 0.171 0.000 0.238 0.954 47.280 0.000

75 76 2.53 40.45 6.255% 40.529 0.001415 0.057 0.000 0.000 0.057 0.545 40.529 0.000
0.000 0.000
80 78 2.68 79.68 3.363% 79.725 0.001415 0.113 0.000 0.063 0.176 0.931 79.725 0.000
78 77 1.62 42.80 3.785% 42.831 0.001415 0.061 0.176 0.186 0.422 1.265 42.831 0.000
77 76 1.46 44.55 3.277% 44.574 0.001415 0.063 0.422 0.000 0.485 1.369 44.574 0.000

54 100 1.67 60.00 2.783% 60.023 0.001415 0.085 0.000 3.610 3.694 3.023 60.023 0.000
100 57 0.40 40.00 1.000% 40.002 0.001415 0.057 3.694 0.000 3.751 3.684 40.002 0.000
57 101 1.51 60.00 2.517% 60.019 0.001415 0.085 3.751 0.390 4.226 3.240 60.019 0.000
101 102 3.25 60.00 5.417% 60.088 0.001415 0.085 4.226 0.000 4.311 2.827 60.088 0.000
102 103 2.71 57.64 4.702% 57.704 0.001415 0.082 4.311 0.000 4.393 2.924 57.704 0.000
103 94 1.05 23.91 4.391% 23.933 0.001415 0.034 4.393 0.000 4.427 2.970 23.933 0.000
94 104 2.39 58.45 4.089% 58.499 0.001415 0.083 4.427 0.129 4.639 3.063 58.499 0.000
104 105 1.17 60.00 1.950% 60.011 0.001415 0.085 4.639 0.000 4.723 3.544 60.011 0.000
105 106 0.96 40.00 2.400% 40.012 0.001415 0.057 4.723 0.000 4.780 3.424 40.012 0.000
106 107 0.64 40.00 1.600% 40.005 0.001415 0.057 4.780 0.000 4.837 3.710 40.005 0.000
107 95 0.73 60.15 1.214% 60.154 0.001415 0.085 4.837 0.000 4.922 3.933 60.154 0.000
95 108 0.65 59.85 1.086% 59.854 0.000311 0.019 4.922 0.371 5.311 4.132 0.000 59.854
108 109 0.58 57.09 1.016% 57.093 0.000311 0.018 5.311 0.000 5.329 4.190 0.000 57.093
109 110 3.90 62.91 6.199% 63.031 0.000311 0.020 5.329 0.000 5.349 2.989 0.000 63.031
110 91 0.55 50.41 1.095% 50.413 0.000311 0.016 5.349 0.000 5.364 4.141 0.000 50.413
91 111 13.74 49.59 27.703% 51.458 0.000311 0.016 5.364 3.821 9.202 2.767 0.000 51.458
111 112 6.34 35.39 17.912% 35.953 0.000311 0.011 9.202 0.000 9.213 3.004 0.000 35.953
112 113 15.61 44.61 34.994% 47.263 0.000311 0.015 9.213 0.000 9.227 2.651 0.000 47.263

51 52 0.69 44.35 1.556% 44.355 0.001415 0.063 0.000 0.000 0.063 0.731 44.355 0.000
52 53 4.42 78.97 5.597% 79.094 0.001415 0.112 0.031 0.330 0.473 1.227 79.094 0.000
53 53A 3.61 41.68 8.661% 41.836 0.001415 0.059 0.473 0.981 1.514 1.749 41.836 0.000
53A 54 3.77 35.00 10.771% 35.202 0.001415 0.050 1.514 0.000 1.563 1.699 35.202 0.000

51 50 1.79 37.65 4.754% 37.693 0.001415 0.053 0.000 0.000 0.053 0.558 37.693 0.000

49 50 0.33 31.20 1.058% 31.202 0.001415 0.044 0.000 0.000 0.044 0.689 31.202 0.000

87 87A 7.04 37.47 18.788% 38.126 0.001415 0.054 0.000 0.238 0.292 0.816 38.126 0.000
87A 95 15.77 53.23 29.626% 55.517 0.001415 0.079 0.292 0.000 0.371 0.819 55.517 0.000

71 70A 2.02 28.90 6.990% 28.971 0.001415 0.041 0.000 0.000 0.041 0.470 28.971 0.000
70A 70 3.46 52.69 6.567% 52.803 0.001415 0.075 0.041 0.000 0.116 0.702 52.803 0.000
70 69A 0.59 42.31 1.394% 42.314 0.001415 0.060 0.116 0.386 0.562 1.698 42.314 0.000
69A 69 0.88 45.00 1.956% 45.009 0.001415 0.064 0.562 0.000 0.625 1.659 45.009 0.000

71 93 7.98 43.15 18.494% 43.882 0.001415 0.062 0.000 0.000 0.062 0.458 43.882 0.000
93 94 16.12 44.30 36.388% 47.142 0.001415 0.067 0.062 0.000 0.129 0.530 47.142 0.000

113 114 16.42 50.00 32.840% 52.627 0.000311 0.016 9.227 0.000 9.244 2.684 0.000 52.627
114 115 14.17 70.00 20.243% 71.420 0.000311 0.022 9.244 0.000 9.266 2.942 0.000 71.420
115 116 4.06 36.20 11.215% 36.427 0.000311 0.011 9.266 0.000 9.277 3.288 0.000 36.427

38 39 6.42 26.70 24.045% 27.461 0.001415 0.039 0.000 0.000 0.039 0.366 27.461 0.000
39 40 7.62 37.83 20.143% 38.590 0.001415 0.055 0.039 0.000 0.093 0.525 38.590 0.000
HOJA DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
BUZON TRAMO DE TUBERIA Coeficiente de CAUDALES (Q)
TUBERIA
Distribucion fo
Pendiente Longitud (lts/seg/ml) En el Anterior Laterales (pulgadas) Longitud Longitud
Bi Bj dH dL Total
S (mts.) tramo al tramo al tramo 6" (mts.) 8" (mts.)

TOTAL 6372.31 829.55


A DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
TUBERIA
Longitud
10" (mts.)

0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

0.000

0.000

0.000
0.000

0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
A DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
TUBERIA
Longitud
10" (mts.)

0.000
0.000
0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000

0.000

0.000

0.000
0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000
0.000

0.000

0.000
0.000
0.000

0.000
0.000

0.000

0.000
0.000
0.000
0.000
0.000
0.000
0.000
A DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
TUBERIA
Longitud
10" (mts.)

0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000

0.000
0.000
0.000

0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000

0.000

0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000

0.000
0.000
0.000

0.000
0.000
A DE METRADOS DE TUBERIAS

DIAMETRO COMERCIAL DE
TUBERIA
Longitud
10" (mts.)

0.000
HOJA DE METRADOS DE BUZONES Y EXCAVACION DE ZANJAS

COTA COTA DE VOLUMEN DE EXCAVACIONES EN


BUZON TRAMO DE TUBERIA EXCAVACION PARA TUBERIAS EXCAVACION PARA BUZONES
TERRENO FONDO TUBERIAS POR TIPO DE MATERIAL
Ancho Volumen V=b*Hp*L COLECTORES EMISORES Altura
Longitud tipo de H prom. Tipo de N de Diam
Bi Bj Bi Bj Bi Bj dH dL S (%) zanja buzon
(m) terreno Buzon tuberia TN TSR TN TSR TN TSR Buzon .(m)
(mts.) (m)

43 42 3120.45 3121.12 3119.25 3118.93 0.32 26.80 1.19% 26.802 TN 1.695 0.6 C 27.258 0.000 27.258 0.000 0.000 0.000 43 1.20 1.5
42 41 3121.12 3118.93 3118.93 3117.63 1.30 40.25 3.23% 40.271 TN 1.745 0.6 C 42.164 0.000 42.164 0.000 0.000 0.000 42 2.19 1.5
41 40 3118.93 3117.02 3117.63 3115.72 1.91 36.83 5.19% 36.879 TN 1.300 0.6 C 28.766 0.000 28.766 0.000 0.000 0.000 41 1.30 1.5
40 37 3117.02 3115.22 3115.72 3113.92 1.80 26.97 6.67% 27.030 TN 1.300 0.6 C 21.083 0.000 21.083 0.000 0.000 0.000 40 1.30 1.5
37 36 3115.22 3114.30 3113.92 3112.90 1.02 24.90 4.10% 24.921 TN 1.350 0.6 C 20.186 0.000 20.186 0.000 0.000 0.000 37 1.30 1.5
36 31 3114.30 3112.77 3112.90 3111.37 1.53 43.35 3.53% 43.377 TN 1.400 0.6 C 36.437 0.000 36.437 0.000 0.000 0.000 36 1.40 1.5
31 30 3112.77 3111.60 3111.37 3110.20 1.17 53.55 2.18% 53.563 TN 1.400 0.6 C 44.993 0.000 44.993 0.000 0.000 0.000 31 1.40 1.5
30 29 3111.60 3106.76 3110.20 3105.36 4.84 85.95 5.63% 86.086 TN 1.400 0.6 C 72.312 0.000 72.312 0.000 0.000 0.000 30 1.40 1.5
29 28 3106.76 3105.24 3105.36 3103.84 1.52 36.30 4.19% 36.332 TN 1.400 0.6 C 30.519 0.000 30.519 0.000 0.000 0.000 29 1.40 1.5
28 27 3105.24 3101.02 3103.84 3099.82 4.02 74.67 5.38% 74.778 TN 1.300 0.6 C 58.327 0.000 58.327 0.000 0.000 0.000 28 1.40 1.5
27 26 3101.02 3099.33 3099.82 3098.13 1.69 37.53 4.50% 37.568 TN 1.200 0.6 C 27.049 0.000 27.049 0.000 0.000 0.000 27 1.20 1.5
26 25 3099.33 3101.03 3098.13 3097.33 0.80 71.05 1.13% 71.055 TN 2.450 0.6 C 104.450 0.000 104.450 0.000 0.000 0.000 26 1.20 1.5
25 24 3101.03 3101.48 3097.33 3097.08 0.25 20.25 1.23% 20.252 TN 4.050 0.6 C 49.211 0.000 49.211 0.000 0.000 0.000 25 3.70 1.5
24 22 3101.48 3099.64 3097.08 3096.74 0.34 28.70 1.18% 28.702 TN 3.650 0.6 C 62.857 0.000 62.857 0.000 0.000 0.000 24 4.40 1.5
22 23 3099.64 3095.93 3096.74 3094.45 2.29 80.85 2.83% 80.882 TN 2.190 0.6 C 106.280 0.000 106.280 0.000 0.000 0.000 22 2.90 1.5
23 8 3095.93 3090.64 3094.45 3089.14 5.31 79.15 6.71% 79.328 TN 1.490 0.6 C 70.919 0.000 70.919 0.000 0.000 0.000 23 1.48 1.5

18 19A 3118.34 3109.38 3117.14 3108.08 9.06 37.90 23.91% 38.968 TSR 1.250 0.6 C 0.000 29.226 0.000 29.226 0.000 0.000 18 1.20 1.5
19A 19 3109.38 3103.22 3108.08 3101.72 6.36 31.80 20.00% 32.430 TSR 1.400 0.6 C 0.000 27.241 0.000 27.241 0.000 0.000 19A 1.30 1.5
19 23A 3103.22 3098.71 3101.72 3097.21 4.51 44.70 10.09% 44.927 TSR 1.500 0.6 C 0.000 40.434 0.000 40.434 0.000 0.000 19 1.50 1.5
23A 23 3098.71 3095.96 3097.21 3094.46 2.75 35.68 7.71% 35.786 TN 1.500 0.6 C 32.207 0.000 32.207 0.000 0.000 0.000 23A 1.50 1.5
23 48 3095.96 3093.67 3094.46 3092.17 2.29 40.02 5.72% 40.085 TN 1.500 0.6 C 36.077 0.000 36.077 0.000 0.000 0.000 23
48 52 3093.67 3091.89 3092.17 3090.39 1.78 40.40 4.41% 40.439 TN 1.500 0.6 C 36.395 0.000 36.395 0.000 0.000 0.000 48 1.50 1.5
52 52A 3091.89 3091.22 3090.39 3089.72 0.67 34.50 1.94% 34.507 TN 1.500 0.6 C 31.056 0.000 31.056 0.000 0.000 0.000 52 1.50 1.5
52A 59 3091.22 3090.53 3089.72 3089.03 0.69 46.59 1.48% 46.595 TN 1.500 0.6 C 41.936 0.000 41.936 0.000 0.000 0.000 52A 1.50 1.5
59 64A 3090.53 3090.13 3089.03 3088.58 0.45 41.41 1.09% 41.412 TN 1.525 0.6 C 37.892 0.000 37.892 0.000 0.000 0.000 59 1.50 1.5
64A 64 3090.13 3089.84 3088.58 3088.14 0.44 39.80 1.11% 39.802 TN 1.625 0.6 C 38.807 0.000 38.807 0.000 0.000 0.000 64A 1.55 1.5
64 67 3089.84 3089.80 3088.14 3087.60 0.54 53.20 1.02% 53.203 TN 1.950 0.6 C 62.247 0.000 62.247 0.000 0.000 0.000 64 1.70 1.5
67 70 3089.80 3088.96 3087.60 3086.66 0.94 65.21 1.44% 65.217 TN 2.250 0.6 C 88.043 0.000 88.043 0.000 0.000 0.000 67 2.20 1.5

73 70 3089.49 3088.96 3087.99 3086.66 1.33 57.62 2.31% 57.635 TN 1.900 0.6 C 65.704 0.000 65.704 0.000 0.000 0.000 73 1.50 1.5

73 78 3089.49 3089.13 3087.99 3087.23 0.76 39.35 1.93% 39.357 TN 1.700 0.6 C 40.145 0.000 40.145 0.000 0.000 0.000

82 79 3089.92 3089.48 3088.42 3087.98 0.44 40.00 1.10% 40.002 TN 1.500 0.6 C 36.002 0.000 36.002 0.000 0.000 0.000 82 1.50 1.5
79 78 3089.48 3089.13 3087.98 3087.23 0.75 51.82 1.45% 51.825 TN 1.700 0.6 C 52.862 0.000 52.862 0.000 0.000 0.000 79 1.50 1.5

82 86 3089.92 3089.08 3088.42 3087.58 0.84 43.35 1.94% 43.358 TN 1.500 0.6 C 39.022 0.000 39.022 0.000 0.000 0.000
86 88 3089.08 3080.72 3087.58 3079.32 8.26 75.40 10.95% 75.851 TN 1.450 0.6 C 65.990 0.000 65.990 0.000 0.000 0.000 86 1.50 1.5
88 89 3080.72 3074.47 3079.32 3073.07 6.25 42.44 14.73% 42.898 TSR 1.400 0.6 C 0.000 36.034 0.000 36.034 0.000 0.000 88 1.40 1.5
89 90 3074.47 3068.54 3073.07 3067.14 5.93 36.21 16.38% 36.692 TSR 1.400 0.6 C 0.000 30.822 0.000 30.822 0.000 0.000 89 1.40 1.5
90 91 3068.54 3059.94 3067.14 3056.44 10.70 30.08 35.57% 31.926 TSR 2.450 0.6 C 0.000 46.932 0.000 46.932 0.000 0.000 90 1.40 1.5
HOJA DE METRADOS DE BUZONES Y EXCAVACION DE ZANJAS

COTA COTA DE VOLUMEN DE EXCAVACIONES EN


BUZON TRAMO DE TUBERIA EXCAVACION PARA TUBERIAS EXCAVACION PARA BUZONES
TERRENO FONDO TUBERIAS POR TIPO DE MATERIAL
Ancho Volumen V=b*Hp*L COLECTORES EMISORES Altura
Longitud tipo de H prom. Tipo de N de Diam
Bi Bj Bi Bj Bi Bj dH dL S (%) zanja buzon
(m) terreno Buzon tuberia TN TSR TN TSR TN TSR Buzon .(m)
(mts.) (m)

20 20A 3122.16 3118.07 3120.96 3116.57 4.39 20.00 21.95% 20.476 TSR 1.350 0.6 C 0.000 16.586 0.000 16.586 0.000 0.000 20 1.20 1.5
20A 21 3118.07 3111.46 3116.57 3109.96 6.61 50.81 13.01% 51.238 TSR 1.500 0.6 C 0.000 46.114 0.000 46.114 0.000 0.000 20A 1.50 1.5
21 22A 3111.46 3105.35 3109.96 3103.85 6.11 40.99 14.91% 41.443 TSR 1.500 0.6 C 0.000 37.299 0.000 37.299 0.000 0.000 21 1.50 1.5
22A 22 3105.35 3099.62 3103.85 3098.12 5.73 39.15 14.64% 39.567 TN 1.500 0.6 C 35.610 0.000 35.610 0.000 0.000 0.000 22A 1.50 1.5
22 47 3099.62 3095.06 3096.72 3093.56 3.16 41.35 7.64% 41.471 TN 2.200 0.6 C 54.741 0.000 54.741 0.000 0.000 0.000
47 50 3095.06 3092.27 3093.56 3090.77 2.79 39.70 7.03% 39.798 TN 1.500 0.6 C 35.818 0.000 35.818 0.000 0.000 0.000 47 1.50 1.5
50 60 3092.27 3089.16 3088.37 3087.56 0.81 79.87 1.01% 79.874 TN 2.750 0.6 C 131.792 0.000 131.792 0.000 0.000 0.000 50 3.90 1.5
60 60A 3089.16 3088.30 3087.56 3086.80 0.76 48.13 1.58% 48.136 TN 1.550 0.6 C 44.766 0.000 44.766 0.000 0.000 0.000 60 1.60 1.5
60A 63 3088.30 3087.48 3086.80 3085.98 0.82 34.20 2.40% 34.210 TN 1.500 0.6 C 30.789 0.000 30.789 0.000 0.000 0.000 60A 1.50 1.5
63 66 3087.48 3087.49 3085.98 3085.39 0.59 52.80 1.12% 52.803 TN 1.800 0.6 C 57.028 0.000 57.028 0.000 0.000 0.000 63 1.50 1.5
66 69 3087.49 3087.29 3085.39 3084.69 0.70 64.45 1.09% 64.454 TN 2.350 0.6 C 90.880 0.000 90.880 0.000 0.000 0.000 66 2.10 1.5
69 74 3087.29 3087.07 3084.69 3084.17 0.52 45.35 1.15% 45.353 TN 2.750 0.6 C 74.832 0.000 74.832 0.000 0.000 0.000 69 2.60 1.5
74 76 3087.07 3086.25 3084.17 3083.45 0.72 61.72 1.17% 61.724 TN 2.850 0.6 C 105.548 0.000 105.548 0.000 0.000 0.000 74 2.90 1.5
76 83A 3086.25 3085.16 3083.45 3082.96 0.49 44.98 1.09% 44.983 TN 2.500 0.6 C 67.474 0.000 67.474 0.000 0.000 0.000 76 2.80 1.5
83A 84 3085.16 3083.22 3082.96 3081.62 1.34 41.75 3.21% 41.771 TN 1.900 0.6 C 47.620 0.000 47.620 0.000 0.000 0.000 83A 2.20 1.5
84 85 3083.22 3078.13 3081.62 3076.63 4.99 46.45 10.74% 46.717 TN 1.550 0.6 C 43.447 0.000 43.447 0.000 0.000 0.000 84 1.60 1.5
85 92 3078.13 3071.77 3076.63 3069.97 6.66 48.30 13.79% 48.757 TN 1.650 0.6 E 48.269 0.000 0.000 0.000 48.269 0.000 85 1.50 1.5
92 96 3071.77 3071.24 3069.97 3069.64 0.33 25.21 1.31% 25.212 TN 1.700 0.6 E 25.716 0.000 0.000 0.000 25.716 0.000 92 1.80 1.5
96 97 3071.24 3069.11 3069.64 3067.91 1.73 74.79 2.31% 74.810 TSR 1.400 0.6 E 0.000 62.840 0.000 0.000 0.000 62.840 96 1.60 1.5
97 98 3069.11 3066.43 3067.91 3065.03 2.88 48.05 5.99% 48.136 TSR 1.300 0.6 E 0.000 37.546 0.000 0.000 0.000 37.546 97 1.20 1.5
98 99 3066.43 3064.81 3065.03 3063.61 1.42 51.95 2.73% 51.969 TN 1.300 0.6 E 40.536 0.000 0.000 0.000 40.536 0.000 98 1.40 1.5
99 91 3064.81 3059.94 3063.61 3056.44 7.17 54.66 13.12% 55.128 TN 2.350 0.6 E 77.731 0.000 0.000 0.000 77.731 0.000 99 1.20 1.5

21A 21 3112.44 3111.42 3111.24 3109.92 1.32 18.38 7.18% 18.427 TN 1.350 0.6 C 14.926 0.000 14.926 0.000 0.000 0.000 21A 1.20 1.5
21 19B 3111.42 3109.43 3109.92 3108.03 1.89 28.62 6.60% 28.682 TN 1.450 0.6 C 24.954 0.000 24.954 0.000 0.000 0.000
19B 19 3109.43 3103.19 3108.03 3101.69 6.34 52.28 12.13% 52.663 TN 1.450 0.6 C 45.817 0.000 45.817 0.000 0.000 0.000 19B 1.40 1.5
19 15 3103.19 3098.34 3101.69 3096.84 4.85 79.65 6.09% 79.798 TN 1.500 0.6 C 71.818 0.000 71.818 0.000 0.000 0.000
15 14 3098.34 3095.82 3096.84 3094.32 2.52 44.07 5.72% 44.142 TN 1.500 0.6 C 39.728 0.000 39.728 0.000 0.000 0.000 15 1.50 1.5
14 13 3095.82 3091.14 3094.32 3089.64 4.68 38.00 12.32% 38.287 TN 1.500 0.6 C 34.458 0.000 34.458 0.000 0.000 0.000 14 1.50 1.5
13 3 3091.14 3089.26 3089.64 3087.06 2.58 58.51 4.41% 58.567 TN 1.850 0.6 C 65.009 0.000 65.009 0.000 0.000 0.000 13 1.50 1.5

11 12 3100.44 3095.29 3099.04 3093.79 5.25 36.00 14.58% 36.381 TSR 1.450 0.6 C 0.000 31.651 0.000 31.651 0.000 0.000 11 1.40 1.5
12 13 3095.29 3091.14 3093.79 3089.64 4.15 42.34 9.80% 42.543 TSR 1.500 0.6 C 0.000 38.289 0.000 38.289 0.000 0.000 12 1.50 1.5
13 6 3091.14 3088.31 3089.64 3086.31 3.33 36.39 9.15% 36.542 TSR 1.750 0.6 C 0.000 38.369 0.000 38.369 0.000 0.000
6 55 3088.31 3083.10 3086.31 3081.60 4.71 45.42 10.37% 45.664 TN 1.750 0.6 C 47.947 0.000 47.947 0.000 0.000 0.000 6 2.00 1.5
55 54A 3083.10 3080.46 3081.60 3078.96 2.64 47.85 5.52% 47.923 TN 1.500 0.6 C 43.130 0.000 43.130 0.000 0.000 0.000 55 1.50 1.5
54A 54 3080.46 3080.11 3078.96 3078.61 0.35 32.25 1.09% 32.252 TN 1.500 0.6 C 29.027 0.000 29.027 0.000 0.000 0.000 54A 1.50 1.5

33 34 3130.33 3121.04 3128.93 3119.64 9.29 41.80 22.22% 42.820 TN 1.400 0.6 C 35.969 0.000 35.969 0.000 0.000 0.000 33 1.40 1.5
34 35 3121.04 3115.68 3119.64 3114.18 5.46 26.20 20.84% 26.763 TN 1.450 0.6 C 23.284 0.000 23.284 0.000 0.000 0.000 34 1.40 1.5
35 36 3115.68 3114.30 3114.18 3112.90 1.28 22.00 5.82% 22.037 TSR 1.450 0.6 C 0.000 19.172 0.000 19.172 0.000 0.000 35 1.50 1.5
HOJA DE METRADOS DE BUZONES Y EXCAVACION DE ZANJAS

COTA COTA DE VOLUMEN DE EXCAVACIONES EN


BUZON TRAMO DE TUBERIA EXCAVACION PARA TUBERIAS EXCAVACION PARA BUZONES
TERRENO FONDO TUBERIAS POR TIPO DE MATERIAL
Ancho Volumen V=b*Hp*L COLECTORES EMISORES Altura
Longitud tipo de H prom. Tipo de N de Diam
Bi Bj Bi Bj Bi Bj dH dL S (%) zanja buzon
(m) terreno Buzon tuberia TN TSR TN TSR TN TSR Buzon .(m)
(mts.) (m)

9 10 3101.40 3099.34 3100.20 3098.04 2.16 37.47 5.76% 37.532 TN 1.250 0.6 C 28.149 0.000 28.149 0.000 0.000 0.000 9 1.20 1.5

10A 10 3101.08 3099.34 3099.88 3098.04 1.84 67.93 2.71% 67.955 TN 1.250 0.6 C 50.966 0.000 50.966 0.000 0.000 0.000 10A 1.20 1.5

45A 45 3115.20 3113.37 3114.00 3111.77 2.23 22.84 9.76% 22.949 TN 1.400 0.6 C 19.277 0.000 19.277 0.000 0.000 0.000 45A 1.20 1.5
45 62 3113.37 3107.19 3111.77 3105.79 5.98 42.47 14.08% 42.889 TSR 1.500 0.6 C 0.000 38.600 0.000 38.600 0.000 0.000 45 1.60 1.5
62 28 3107.19 3105.24 3105.79 3103.84 1.95 20.00 9.75% 20.095 TN 1.400 0.6 C 16.880 0.000 16.880 0.000 0.000 0.000 62 1.40 1.5

8 7 3090.64 3089.77 3089.14 3088.07 1.07 13.25 8.08% 13.293 TN 1.600 0.6 C 12.761 0.000 12.761 0.000 0.000 0.000 8 1.50 1.5
7 55 3089.77 3083.10 3088.07 3081.60 6.47 91.70 7.06% 91.928 TSR 1.600 0.6 C 0.000 88.251 0.000 88.251 0.000 0.000 7 1.70 1.5

64 63A 3089.84 3088.37 3088.34 3086.87 1.47 41.50 3.54% 41.526 TN 1.500 0.6 C 37.373 0.000 37.373 0.000 0.000 0.000
63A 63 3088.37 3087.52 3086.87 3086.02 0.85 42.96 1.98% 42.968 TN 1.500 0.6 C 38.672 0.000 38.672 0.000 0.000 0.000 63A 1.50 1.5

10 2A 3098.75 3093.10 3097.45 3091.81 5.64 40.00 14.10% 40.396 TN 1.295 0.6 C 31.387 0.000 31.387 0.000 0.000 0.000 10 1.30 1.5
2A 2 3093.10 3090.77 3091.81 3089.27 2.54 27.03 9.40% 27.149 TN 1.395 0.6 C 22.724 0.000 22.724 0.000 0.000 0.000 2A 1.29 1.5

5 4 3089.57 3088.78 3088.37 3087.58 0.79 56.06 1.41% 56.066 TN 1.200 0.6 C 40.367 0.000 40.367 0.000 0.000 0.000 5 1.20 1.5
4 3 3088.78 3089.27 3087.58 3087.07 0.51 22.64 2.25% 22.646 TN 1.700 0.6 C 23.099 0.000 23.099 0.000 0.000 0.000 4 1.20 1.5

32 44 3120.64 3114.06 3119.34 3112.66 6.68 32.40 20.62% 33.081 TN 1.350 0.6 C 26.796 0.000 26.796 0.000 0.000 0.000 32 1.30 1.5
44 31 3114.06 3112.77 3112.66 3111.37 1.29 10.00 12.90% 10.083 TN 1.400 0.6 C 8.470 0.000 8.470 0.000 0.000 0.000 44 1.40 1.5

1 2 3097.00 3090.78 3095.80 3089.28 6.52 80.45 8.10% 80.714 TN 1.350 0.6 C 65.378 0.000 65.378 0.000 0.000 0.000 1 1.20 1.5
2 3 3090.78 3089.27 3089.28 3087.07 2.21 25.32 8.73% 25.416 TN 1.850 0.6 C 28.212 0.000 28.212 0.000 0.000 0.000 2 1.50 1.5
3 6 3089.27 3088.31 3087.07 3086.31 0.76 66.80 1.14% 66.804 TN 2.100 0.6 C 84.173 0.000 84.173 0.000 0.000 0.000 3 2.20 1.5

7 6 3089.77 3088.31 3088.07 3086.31 1.76 69.88 2.52% 69.902 TN 1.850 0.6 C 77.591 0.000 77.591 0.000 0.000 0.000

59 58 3090.54 3088.60 3089.04 3087.10 1.94 76.12 2.55% 76.145 TN 1.500 0.6 C 68.530 0.000 68.530 0.000 0.000 0.000
58 57A 3088.60 3083.21 3087.10 3081.71 5.39 54.63 9.87% 54.895 TN 1.500 0.6 C 49.406 0.000 49.406 0.000 0.000 0.000 58 1.50 1.5
57A 57 3083.21 3080.10 3081.71 3076.60 5.11 27.25 18.75% 27.725 TN 2.500 0.6 C 41.587 0.000 41.587 0.000 0.000 0.000 57A 1.50 1.5

59 59A 3090.54 3089.87 3089.04 3088.37 0.68 42.00 1.61% 42.005 TN 1.500 0.6 C 37.805 0.000 37.805 0.000 0.000 0.000
59A 60 3089.87 3089.15 3088.37 3087.55 0.81 41.88 1.95% 41.888 TN 1.550 0.6 C 38.956 0.000 38.956 0.000 0.000 0.000 59A 1.50 1.5

61 60 3088.97 3089.15 3087.87 3087.55 0.32 19.62 1.63% 19.623 TN 1.350 0.6 C 15.894 0.000 15.894 0.000 0.000 0.000 61 1.10 1.5

17 16 3112.34 3108.17 3111.14 3105.47 5.67 27.45 20.66% 28.029 TSR 1.950 0.6 C 0.000 32.794 0.000 32.794 0.000 0.000 17 1.20 1.5
16 16A 3108.17 3099.91 3105.47 3098.71 6.76 32.55 20.77% 33.245 TSR 1.950 0.6 C 0.000 38.896 0.000 38.896 0.000 0.000 16 2.70 1.5
16A 15 3099.91 3098.36 3098.71 3096.86 1.85 13.95 13.26% 14.072 TSR 1.350 0.6 C 0.000 11.398 0.000 11.398 0.000 0.000 16A 1.20 1.5
15 15A 3098.36 3092.55 3096.86 3091.05 5.81 46.05 12.62% 46.415 TSR 1.500 0.6 C 0.000 41.774 0.000 41.774 0.000 0.000
15A 8 3092.55 3090.62 3091.05 3089.12 1.93 34.88 5.53% 34.933 TN 1.500 0.6 C 31.440 0.000 31.440 0.000 0.000 0.000 15A 1.50 1.5
HOJA DE METRADOS DE BUZONES Y EXCAVACION DE ZANJAS

COTA COTA DE VOLUMEN DE EXCAVACIONES EN


BUZON TRAMO DE TUBERIA EXCAVACION PARA TUBERIAS EXCAVACION PARA BUZONES
TERRENO FONDO TUBERIAS POR TIPO DE MATERIAL
Ancho Volumen V=b*Hp*L COLECTORES EMISORES Altura
Longitud tipo de H prom. Tipo de N de Diam
Bi Bj Bi Bj Bi Bj dH dL S (%) zanja buzon
(m) terreno Buzon tuberia TN TSR TN TSR TN TSR Buzon .(m)
(mts.) (m)

8 8A 3090.62 3089.10 3089.12 3087.60 1.52 45.12 3.37% 45.146 TN 1.500 0.6 C 40.631 0.000 40.631 0.000 0.000 0.000
8A 53 3089.10 3087.59 3087.60 3085.99 1.61 36.60 4.40% 36.635 TN 1.550 0.6 C 34.071 0.000 34.071 0.000 0.000 0.000 8A 1.50 1.5

71 68 3093.32 3091.83 3092.12 3090.33 1.79 59.75 3.00% 59.777 TSR 1.350 0.6 C 0.000 48.419 0.000 48.419 0.000 0.000 71 1.20 1.5
68 65 3091.83 3090.22 3090.33 3088.72 1.61 60.26 2.67% 60.282 TSR 1.500 0.6 C 0.000 54.253 0.000 54.253 0.000 0.000 68 1.50 1.5
65 58 3090.22 3088.60 3088.72 3087.10 1.62 77.89 2.08% 77.907 TN 1.500 0.6 C 70.116 0.000 70.116 0.000 0.000 0.000 65 1.50 1.5
58 53B 3088.60 3087.98 3087.10 3086.58 0.52 41.85 1.24% 41.853 TN 1.450 0.6 C 36.412 0.000 36.412 0.000 0.000 0.000
53B 53 3087.98 3087.67 3086.58 3086.07 0.51 40.00 1.27% 40.003 TN 1.500 0.6 C 36.003 0.000 36.003 0.000 0.000 0.000 53B 1.40 1.5

71 72 3093.32 3093.17 3092.12 3091.47 0.65 55.70 1.17% 55.704 TN 1.450 0.6 C 48.462 0.000 48.462 0.000 0.000 0.000
72 80 3093.17 3091.45 3091.47 3089.85 1.62 32.96 4.92% 33.000 TN 1.650 0.6 C 32.670 0.000 32.670 0.000 0.000 0.000 72 1.70 1.5
80 81 3091.45 3089.05 3089.85 3087.45 2.40 76.76 3.13% 76.798 TN 1.600 0.6 C 73.726 0.000 73.726 0.000 0.000 0.000 80 1.60 1.5
81 87 3089.05 3086.48 3087.45 3084.88 2.57 47.21 5.44% 47.280 TN 1.600 0.6 C 45.389 0.000 45.389 0.000 0.000 0.000 81 1.60 1.5

75 76 3087.88 3086.25 3086.68 3084.15 2.53 40.45 6.25% 40.529 TN 1.650 0.6 C 40.124 0.000 40.124 0.000 0.000 0.000 75 1.20 1.5

80 78 3091.51 3089.13 3089.91 3087.23 2.68 79.68 3.36% 79.725 TN 1.750 0.6 C 83.711 0.000 83.711 0.000 0.000 0.000
78 77 3089.13 3087.11 3087.23 3085.61 1.62 42.80 3.79% 42.831 TN 1.700 0.6 C 43.687 0.000 43.687 0.000 0.000 0.000 78 1.90 1.5
77 76 3087.11 3086.25 3085.61 3084.15 1.46 44.55 3.28% 44.574 TN 1.800 0.6 C 48.140 0.000 48.140 0.000 0.000 0.000 77 1.50 1.5

54 100 3080.11 3078.14 3078.61 3076.94 1.67 60.00 2.78% 60.023 TN 1.350 0.6 C 48.619 0.000 48.619 0.000 0.000 0.000 54 1.50 1.5
100 57 3078.14 3076.54 3076.94 3076.54 0.40 40.00 1.00% 40.002 TN 0.600 0.6 C 14.401 0.000 14.401 0.000 0.000 0.000 100 1.20 1.5
57 101 3076.54 3076.53 3076.54 3075.03 1.51 60.00 2.52% 60.019 TN 0.750 0.6 C 27.009 0.000 27.009 0.000 0.000 0.000 57 0.00 1.5
101 102 3076.53 3073.28 3075.03 3071.78 3.25 60.00 5.42% 60.088 TN 1.500 0.6 C 54.079 0.000 54.079 0.000 0.000 0.000 101 1.50 1.5
102 103 3073.28 3071.10 3071.78 3069.07 2.71 57.64 4.70% 57.704 TN 1.765 0.6 C 61.108 0.000 61.108 0.000 0.000 0.000 102 1.50 1.5
103 94 3071.10 3069.52 3069.07 3068.02 1.05 23.91 4.39% 23.933 TN 1.765 0.6 C 25.345 0.000 25.345 0.000 0.000 0.000 103 2.03 1.5
94 104 3069.52 3067.13 3068.02 3065.63 2.39 58.45 4.09% 58.499 TN 1.500 0.6 C 52.649 0.000 52.649 0.000 0.000 0.000 94 1.50 1.5
104 105 3067.13 3065.46 3065.63 3064.46 1.17 60.00 1.95% 60.011 TN 1.250 0.6 C 45.009 0.000 45.009 0.000 0.000 0.000 104 1.50 1.5
105 106 3065.46 3065.00 3064.46 3063.50 0.96 40.00 2.40% 40.012 TN 1.250 0.6 C 30.009 0.000 30.009 0.000 0.000 0.000 105 1.00 1.5
106 107 3065.00 3064.36 3063.50 3062.86 0.64 40.00 1.60% 40.005 TN 1.500 0.6 C 36.005 0.000 36.005 0.000 0.000 0.000 106 1.50 1.5
107 95 3064.36 3064.13 3062.86 3062.13 0.73 60.15 1.21% 60.154 TSR 1.750 0.6 C 0.000 63.162 0.000 63.162 0.000 0.000 107 1.50 1.5
95 108 3064.13 3063.18 3062.13 3061.48 0.65 59.85 1.09% 59.854 TSR 1.850 0.6 E 0.000 66.437 0.000 0.000 0.000 66.437 95 2.00 1.5
108 109 3063.18 3063.00 3061.48 3060.90 0.58 57.09 1.02% 57.093 TSR 1.900 0.6 E 0.000 65.086 0.000 0.000 0.000 65.086 108 1.70 1.5
109 110 3063.00 3058.20 3060.90 3057.00 3.90 62.91 6.20% 63.031 TSR 1.650 0.6 E 0.000 62.400 0.000 0.000 0.000 62.400 109 2.10 1.5
110 91 3058.20 3056.45 3057.00 3056.45 0.55 50.41 1.10% 50.413 TSR 0.600 0.6 E 0.000 18.149 0.000 0.000 0.000 18.149 110 1.20 1.5
91 111 3056.45 3080.04 3056.45 3042.71 13.74 49.59 27.70% 51.458 TN 18.665 0.6 E 576.275 0.000 0.000 0.000 576.275 0.000 91 0.00 1.5
111 112 3080.04 3037.87 3042.71 3036.37 6.34 35.39 17.91% 35.953 TN 19.415 0.6 E 418.819 0.000 0.000 0.000 418.819 0.000 111 37.33 1.5
112 113 3037.87 3022.26 3036.37 3020.76 15.61 44.61 34.99% 47.263 TN 1.500 0.6 E 42.536 0.000 0.000 0.000 42.536 0.000 112 1.50 1.5

51 52 3092.24 3091.85 3091.04 3090.35 0.69 44.35 1.56% 44.355 TN 1.350 0.6 C 35.928 0.000 35.928 0.000 0.000 0.000 51 1.20 1.5
52 53 3091.85 3087.53 3090.35 3085.93 4.42 78.97 5.60% 79.094 TN 1.550 0.6 C 73.557 0.000 73.557 0.000 0.000 0.000
53 53A 3087.53 3083.72 3085.93 3082.32 3.61 41.68 8.66% 41.836 TN 1.500 0.6 C 37.652 0.000 37.652 0.000 0.000 0.000 53 1.60 1.5
53A 54 3083.72 3080.05 3082.32 3078.55 3.77 35.00 10.77% 35.202 TN 1.450 0.6 C 30.626 0.000 30.626 0.000 0.000 0.000 53A 1.40 1.5
HOJA DE METRADOS DE BUZONES Y EXCAVACION DE ZANJAS

COTA COTA DE VOLUMEN DE EXCAVACIONES EN


BUZON TRAMO DE TUBERIA EXCAVACION PARA TUBERIAS EXCAVACION PARA BUZONES
TERRENO FONDO TUBERIAS POR TIPO DE MATERIAL
Ancho Volumen V=b*Hp*L COLECTORES EMISORES Altura
Longitud tipo de H prom. Tipo de N de Diam
Bi Bj Bi Bj Bi Bj dH dL S (%) zanja buzon
(m) terreno Buzon tuberia TN TSR TN TSR TN TSR Buzon .(m)
(mts.) (m)

51 50 3092.24 3092.20 3091.04 3089.25 1.79 37.65 4.75% 37.693 TN 2.075 0.6 C 46.927 0.000 46.927 0.000 0.000 0.000

49 50 3089.83 3092.20 3088.73 3088.40 0.33 31.20 1.06% 31.202 TN 2.450 0.6 C 45.867 0.000 45.867 0.000 0.000 0.000 49 1.10 1.5

87 87A 3086.48 3079.34 3084.88 3077.84 7.04 37.47 18.79% 38.126 TN 1.550 0.6 C 35.457 0.000 35.457 0.000 0.000 0.000 87 1.60 1.5
87A 95 3079.34 3064.07 3077.84 3062.07 15.77 53.23 29.63% 55.517 TN 1.750 0.6 C 58.293 0.000 58.293 0.000 0.000 0.000 87A 1.50 1.5

71 70A 3093.33 3091.61 3092.13 3090.11 2.02 28.90 6.99% 28.971 TN 1.350 0.6 C 23.466 0.000 23.466 0.000 0.000 0.000
70A 70 3091.61 3088.95 3090.11 3086.65 3.46 52.69 6.57% 52.803 TN 1.900 0.6 C 60.196 0.000 60.196 0.000 0.000 0.000 70A 1.50 1.5
70 69A 3088.95 3087.66 3086.65 3086.06 0.59 42.31 1.39% 42.314 TN 1.950 0.6 C 49.508 0.000 49.508 0.000 0.000 0.000 70 2.30 1.5
69A 69 3087.66 3087.28 3086.06 3085.18 0.88 45.00 1.96% 45.009 TN 1.850 0.6 C 49.960 0.000 49.960 0.000 0.000 0.000 69A 1.60 1.5

71 93 3093.33 3085.55 3092.13 3084.15 7.98 43.15 18.49% 43.882 TN 1.300 0.6 C 34.228 0.000 34.228 0.000 0.000 0.000
93 94 3085.55 3069.53 3084.15 3068.03 16.12 44.30 36.39% 47.142 TN 1.450 0.6 C 41.013 0.000 41.013 0.000 0.000 0.000 93 1.40 1.5

113 114 3022.28 3005.84 3020.76 3004.34 16.42 50.00 32.84% 52.627 TN 1.510 0.6 E 47.680 0.000 0.000 0.000 47.680 0.000 113 1.52 1.5
114 115 3005.84 2991.67 3004.34 2990.17 14.17 70.00 20.24% 71.420 TN 1.500 0.6 E 64.278 0.000 0.000 0.000 64.278 0.000 114 1.50 1.5
115 116 2991.67 2987.61 2990.17 2986.11 4.06 36.20 11.22% 36.427 TN 1.500 0.6 E 32.784 0.000 0.000 0.000 32.784 0.000 115 1.50 1.5

38 39 3132.94 3126.92 3131.74 3125.32 6.42 26.70 24.04% 27.461 TN 1.400 0.6 C 23.067 0.000 23.067 0.000 0.000 0.000 38 1.20 1.5
39 40 3126.92 3119.00 3125.32 3117.70 7.62 37.83 20.14% 38.590 TN 1.450 0.6 C 33.573 0.000 33.573 0.000 0.000 0.000 39 1.60 1.5

TOTALIZANDO VALORES 7201.857 6780.820 1168.176 5406.194 855.717 1374.626 312.459


OS DE BUZONES Y EXCAVACION DE ZANJAS

EXCAVACION PARA BUZONES TUBERIA BUZONES

Volumen (m3) Tipo Tipo Tipo Tipo Tipo


Colector Emisor Tipo I
TN TSR II III IV V VI

2.121 0.000 26.802 0.000 1 0 0 0 0 0


3.870 0.000 40.271 0.000 0 0 1 0 0 0
2.297 0.000 36.879 0.000 1 0 0 0 0 0
2.297 0.000 27.030 0.000 1 0 0 0 0 0
2.297 0.000 24.921 0.000 1 0 0 0 0 0
2.474 0.000 43.377 0.000 1 0 0 0 0 0
2.474 0.000 53.563 0.000 1 0 0 0 0 0
2.474 0.000 86.086 0.000 1 0 0 0 0 0
2.474 0.000 36.332 0.000 1 0 0 0 0 0
2.474 0.000 74.778 0.000 1 0 0 0 0 0
2.121 0.000 37.568 0.000 1 0 0 0 0 0
2.121 0.000 71.055 0.000 1 0 0 0 0 0
6.538 0.000 20.252 0.000 0 0 0 0 0 1
7.775 0.000 28.702 0.000 0 0 0 0 0 1
5.125 0.000 80.882 0.000 0 0 0 1 0 0
2.615 0.000 79.328 0.000 1 0 0 0 0 0

0.000 2.121 38.968 0.000 1 0 0 0 0 0


0.000 2.297 32.430 0.000 1 0 0 0 0 0
0.000 2.651 44.927 0.000 1 0 0 0 0 0
2.651 0.000 35.786 0.000 1 0 0 0 0 0
40.085 0.000
2.651 0.000 40.439 0.000 1 0 0 0 0 0
2.651 0.000 34.507 0.000 1 0 0 0 0 0
2.651 0.000 46.595 0.000 1 0 0 0 0 0
2.651 0.000 41.412 0.000 1 0 0 0 0 0
2.739 0.000 39.802 0.000 0 1 0 0 0 0
3.004 0.000 53.203 0.000 0 1 0 0 0 0
3.888 0.000 65.217 0.000 0 0 1 0 0 0

2.651 0.000 57.635 0.000 1 0 0 0 0 0

39.357 0.000

2.651 0.000 40.002 0.000 1 0 0 0 0 0


2.651 0.000 51.825 0.000 1 0 0 0 0 0

43.358 0.000
2.651 0.000 75.851 0.000 1 0 0 0 0 0
0.000 2.474 42.898 0.000 1 0 0 0 0 0
0.000 2.474 36.692 0.000 1 0 0 0 0 0
0.000 2.474 31.926 0.000 1 0 0 0 0 0
OS DE BUZONES Y EXCAVACION DE ZANJAS

EXCAVACION PARA BUZONES TUBERIA BUZONES

Volumen (m3) Tipo Tipo Tipo Tipo Tipo


Colector Emisor Tipo I
TN TSR II III IV V VI

0.000 2.121 20.476 0.000 1 0 0 0 0 0


0.000 2.651 51.238 0.000 1 0 0 0 0 0
0.000 2.651 41.443 0.000 1 0 0 0 0 0
2.651 0.000 39.567 0.000 1 0 0 0 0 0
41.471 0.000
2.651 0.000 39.798 0.000 1 0 0 0 0 0
6.892 0.000 79.874 0.000 0 0 0 0 0 1
2.827 0.000 48.136 0.000 0 1 0 0 0 0
2.651 0.000 34.210 0.000 1 0 0 0 0 0
2.651 0.000 52.803 0.000 1 0 0 0 0 0
3.711 0.000 64.454 0.000 0 0 1 0 0 0
4.595 0.000 45.353 0.000 0 0 0 1 0 0
5.125 0.000 61.724 0.000 0 0 0 1 0 0
4.948 0.000 44.983 0.000 0 0 0 1 0 0
3.888 0.000 41.771 0.000 0 0 1 0 0 0
2.827 0.000 46.717 0.000 0 1 0 0 0 0
2.651 0.000 0.000 48.757 1 0 0 0 0 0
3.181 0.000 0.000 25.212 0 1 0 0 0 0
0.000 2.827 0.000 74.810 0 1 0 0 0 0
0.000 2.121 0.000 48.136 1 0 0 0 0 0
2.474 0.000 0.000 51.969 1 0 0 0 0 0
2.121 0.000 0.000 55.128 1 0 0 0 0 0

2.121 0.000 18.427 0.000 1 0 0 0 0 0


28.682 0.000
2.474 0.000 52.663 0.000 1 0 0 0 0 0
79.798 0.000
2.651 0.000 44.142 0.000 1 0 0 0 0 0
2.651 0.000 38.287 0.000 1 0 0 0 0 0
2.651 0.000 58.567 0.000 1 0 0 0 0 0

0.000 2.474 36.381 0.000 1 0 0 0 0 0


0.000 2.651 42.543 0.000 1 0 0 0 0 0
36.542 0.000
3.534 0.000 45.664 0.000 0 1 0 0 0 0
2.651 0.000 47.923 0.000 1 0 0 0 0 0
2.651 0.000 32.252 0.000 1 0 0 0 0 0

2.474 0.000 42.820 0.000 1 0 0 0 0 0


2.474 0.000 26.763 0.000 1 0 0 0 0 0
0.000 2.651 22.037 0.000 1 0 0 0 0 0
OS DE BUZONES Y EXCAVACION DE ZANJAS

EXCAVACION PARA BUZONES TUBERIA BUZONES

Volumen (m3) Tipo Tipo Tipo Tipo Tipo


Colector Emisor Tipo I
TN TSR II III IV V VI

2.121 0.000 37.532 0.000 1 0 0 0 0 0

2.121 0.000 67.955 0.000 1 0 0 0 0 0

2.121 0.000 22.949 0.000 1 0 0 0 0 0


0.000 2.827 42.889 0.000 0 1 0 0 0 0
2.474 0.000 20.095 0.000 1 0 0 0 0 0

2.651 0.000 13.293 0.000 1 0 0 0 0 0


0.000 3.004 91.928 0.000 0 1 0 0 0 0

41.526 0.000
2.651 0.000 42.968 0.000 1 0 0 0 0 0

2.297 0.000 40.396 0.000 1 0 0 0 0 0


2.280 0.000 27.149 0.000 1 0 0 0 0 0

2.121 0.000 56.066 0.000 1 0 0 0 0 0


2.121 0.000 22.646 0.000 1 0 0 0 0 0

2.297 0.000 33.081 0.000 1 0 0 0 0 0


2.474 0.000 10.083 0.000 1 0 0 0 0 0

2.121 0.000 80.714 0.000 1 0 0 0 0 0


2.651 0.000 25.416 0.000 1 0 0 0 0 0
3.888 0.000 66.804 0.000 0 0 1 0 0 0

69.902 0.000

76.145 0.000
2.651 0.000 54.895 0.000 1 0 0 0 0 0
2.651 0.000 27.725 0.000 1 0 0 0 0 0

42.005 0.000
2.651 0.000 41.888 0.000 1 0 0 0 0 0

1.944 0.000 19.623 0.000 1 0 0 0 0 0

0.000 2.121 28.029 0.000 1 0 0 0 0 0


0.000 4.771 33.245 0.000 0 0 0 1 0 0
0.000 2.121 14.072 0.000 1 0 0 0 0 0
46.415 0.000
2.651 0.000 34.933 0.000 1 0 0 0 0 0
OS DE BUZONES Y EXCAVACION DE ZANJAS

EXCAVACION PARA BUZONES TUBERIA BUZONES

Volumen (m3) Tipo Tipo Tipo Tipo Tipo


Colector Emisor Tipo I
TN TSR II III IV V VI

45.146 0.000
2.651 0.000 36.635 0.000 1 0 0 0 0 0

0.000 2.121 59.777 0.000 1 0 0 0 0 0


0.000 2.651 60.282 0.000 1 0 0 0 0 0
2.651 0.000 77.907 0.000 1 0 0 0 0 0
41.853 0.000
2.474 0.000 40.003 0.000 1 0 0 0 0 0

55.704 0.000
3.004 0.000 33.000 0.000 0 1 0 0 0 0
2.827 0.000 76.798 0.000 0 1 0 0 0 0
2.827 0.000 47.280 0.000 0 1 0 0 0 0

2.121 0.000 40.529 0.000 1 0 0 0 0 0

79.725 0.000
3.358 0.000 42.831 0.000 0 1 0 0 0 0
2.651 0.000 44.574 0.000 1 0 0 0 0 0

2.651 0.000 60.023 0.000 1 0 0 0 0 0


2.121 0.000 40.002 0.000 1 0 0 0 0 0
0.000 0.000 60.019 0.000 1 0 0 0 0 0
2.651 0.000 60.088 0.000 1 0 0 0 0 0
2.651 0.000 57.704 0.000 1 0 0 0 0 0
3.587 0.000 23.933 0.000 0 0 1 0 0 0
2.651 0.000 58.499 0.000 1 0 0 0 0 0
2.651 0.000 60.011 0.000 1 0 0 0 0 0
1.767 0.000 40.012 0.000 1 0 0 0 0 0
2.651 0.000 40.005 0.000 1 0 0 0 0 0
0.000 2.651 60.154 0.000 1 0 0 0 0 0
0.000 3.534 0.000 59.854 0 1 0 0 0 0
0.000 3.004 0.000 57.093 0 1 0 0 0 0
0.000 3.711 0.000 63.031 0 0 1 0 0 0
0.000 2.121 0.000 50.413 1 0 0 0 0 0
0.000 0.000 0.000 51.458 1 0 0 0 0 0
65.968 0.000 0.000 35.953 0 0 0 0 0 1
2.651 0.000 0.000 47.263 1 0 0 0 0 0

2.121 0.000 44.355 0.000 1 0 0 0 0 0


79.094 0.000
2.827 0.000 41.836 0.000 0 1 0 0 0 0
2.474 0.000 35.202 0.000 1 0 0 0 0 0
OS DE BUZONES Y EXCAVACION DE ZANJAS

EXCAVACION PARA BUZONES TUBERIA BUZONES

Volumen (m3) Tipo Tipo Tipo Tipo Tipo


Colector Emisor Tipo I
TN TSR II III IV V VI

37.693 0.000

1.944 0.000 31.202 0.000 1 0 0 0 0 0

2.827 0.000 38.126 0.000 0 1 0 0 0 0


2.651 0.000 55.517 0.000 1 0 0 0 0 0

28.971 0.000
2.651 0.000 52.803 0.000 1 0 0 0 0 0
4.064 0.000 42.314 0.000 0 0 1 0 0 0
2.827 0.000 45.009 0.000 0 1 0 0 0 0

43.882 0.000
2.474 0.000 47.142 0.000 1 0 0 0 0 0

2.686 0.000 0.000 52.627 0 1 0 0 0 0


2.651 0.000 0.000 71.420 1 0 0 0 0 0
2.651 0.000 0.000 36.427 1 0 0 0 0 0

2.121 0.000 27.461 0.000 1 0 0 0 0 0


2.827 0.000 38.590 0.000 0 1 0 0 0 0

372.497 69.272 6372.307 829.551 100 20 8 5 0 4


DISEO DE MEZCLAS (CONCRETO fc = 210 KG/CM2)

Exigencias de la Especificacion:
fc = 210 Kg/cm2
Agregado grueso maximo = 1/2"
Materiales de calidad controlada, dosificacion en peso

Calidad de los materiales


Cemento portland Tipo I
Agregado grueso: Peso unitario seco y compacta : 1600 Kg/m3
Modulo de fineza : 2.60
Contenido de humedad : 1.50 %
% absorcion : 0.50 %
Agregado fino: Modulo de fineza : 2.60
Contenido de humedad : 4.00 %
% de absorcion : 2.00 %

Diseo
1.- Para el tipo de estructuctura a construirse, se considerar:
Slump = 3 "
2.- Calculo del agua de mezclado (usando tablas pre-establecidas)
Para Slump = 3 "
Tamao de agregado grueso 1/2"
Resulta: Agua de mezclado 215 Kg/m3
3.- Relacion a/c
Usando tablas, para los valores calculados K = 1.14
De donde: fcr = 1.14 x 210 = 240.03 Kg/cm2
Interpolando valores de a/c en las tablas, tenemos
fcr = 240.03 Kg/cm2, sin aire incorporado:
fc a/c
210 0.58
245 0.51
de donde:
240.03 0.52
Luego a/c = 0.52
4.- Contenido de cemento
Cemento = 215/0.52 = 413.5 Kg/m3
Equivalente a 9.73 bls
5.- Contenido de agregado grueso:
Para: Modulo de fineza = 2.60
0.57 m3
Tamao maximo a.g. = 1/2"
p.u.s.c. = 1600 Kg/m3
Agregado grueso = 912 Kg
6.- Contenido de agregado fino:
Tamano max. Agregado. Grueso = 1/2" peso concreto = 2360 Kg/m3
Concreto sin aire incorporado
Agregado fino = 819.5 Kg.
7.- Ajuste por humedad del peso de los agregados:
Agregado grueso = 925.68 Kg
Agregado fino = 852.2704 Kg
Agua en el agregado grueso 925.68 (1.5%-0.5%) = 9.12 Kg
Agua en el agregado fino 852.27(4%-2%) = 16.39 Kg
25.51 Kg
Agua de mezclado neto = 215 - 25.51 = 189.49 Kg

Dosificacion en volumen resultante


Partiendo de los resultados obtenidos y conocidos los pesos unitarios saturados:
Agregado grueso = 1750 Kg/m3
Agregado fino = 1655 Kg/m3
Se tiene:
Cemento = 413.51 Kg 9.73 bls
Agregado grueso = 0.53 m3
Agregado fino = 0.51 m3
Agua de mezclado = 0.19 m3
DISEO DE MEZCLAS (CONCRETO fc = 175 KG/CM2

Exigencias de la Especificacion:
fc = 175 Kg/cm2
Agregado grueso maximo = 1/2"
Materiales de calidad controlada, dosificacion en peso

Calidad de los materiales


Cemento portland Tipo I
Agregado grueso: Peso unitario seco y compacta : 1600 Kg/m3
Modulo de fineza : 2.60
Contenido de humedad : 1.50 %
% absorcion : 0.50 %
Agregado fino: Modulo de fineza : 2.60
Contenido de humedad : 4.00 %
% de absorcion : 2.00 %

Diseo
1.- Para el tipo de estructuctura a construirse, se considerar:
Slump = 3 "
2.- Calculo del agua de mezclado (usando tablas pre-establecidas)
Para: Slump = 3 "
Tamao de agregado grueso 1/2"
Resulta: Agua de mezclado 215 Kg/m3
3.- Relacion a/c
Usando tablas, para los valores calculados K = 1.19
De donde fcr = 1.19 x 175 = 208.425 Kg/cm2
Interpolando valores de a/c en las tablas, tenemos
fcr = 208.425 Kg/cm2, sin aire incorporado:
fc a/c
175 0.67
210 0.58
de donde:
208.43 0.58
Luego a/c = 0.58
4.- Contenido de cemento
Cemento = 215/0.58 = 368.1 Kg/m3
Equivalente a 8.66 bls
5.- Contenido de agregado grueso:
Para: Modulo de fineza = 3.00
0.571 m3
Tamao maximo a.g. = 1/2"
p.u.s.c. = 1600 Kg/m3
Agregado grueso = 913.6 Kg
6.- Contenido de agregado fino:
Tamano max. Agregado. Grueso = 1/2" peso concreto = 2360 Kg/m3
Concreto sin aire incorporado
Agregado fino = 863.3 Kg.
7.- Ajuste por humedad del peso de los agregados:
Agregado grueso = 927.304 Kg
Agregado fino = 897.8121 Kg
Agua en el agregado grueso 927.30(1.5%-0.5%) = 9.136 Kg
Agua en el agregado fino 897.81(4%-2%) = 17.27 Kg
26.40 Kg
Agua de mezclado neto = 215 + 26.40 = 188.60 Kg

Dosificacion en volumen resultante


Partiendo de los resultados obtenidos y conocidos los pesos unitarios saturados:
Agregado grueso = 1700 Kg/m3
Agregado fino = 1655 Kg/m3
Se tiene:
Cemento = 368.12 Kg 8.66 bls
Agregado grueso = 0.55 m3
Agregado fino = 0.54 m3
Agua de mezclado = 0.19 m3
PRESUPUESTO ANALITICO CONSOLIDADO

Proyecto
Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion :
Modalidad Supervision :
Fecha de Elaboracion :

Especifica de Gastos COSTO DIRECTO G. GENERALES G. SUPERVISION G. LIQUIDACION G. EXPEDIENTE TCNICO Total PRESUPUESTO

2.3.2.5.1 .CONTRATOS - - - - - -

2.3.2.4.1.: PERSONAL 73,962.76 60,000.00 17,500.00 6,000.00 6,000.00 163,462.76

2.3.1.1.1.1: BIENES 102,452.40 2,221.50 736.00 1,113.75 670.00 107,193.65

2.3.2.7.2 : SERVICIOS 32,240.00 400.00 - - 32,640.00

274.60 - 3,530.00 3,804.60

TOTAL 208,655.16 62,896.10 18,236.00 7,113.75 10,200.00 307,101.01


PRESUPUESTO ANALITICO DESAGREGADO COSTO DIRECTO

Proyecto

Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion : Administracion Directa
Modalidad Supervision : Supervision de Planta
Fecha de Elaboracion :
Resumen :
2.3.2.4.1.: PERSONAL 73,962.76
2.3.2.4.2: BIENES 102,452.40
2.3.2.4.2 : SERVICIOS 32,240.00
TOTAL 208,655.16

DESAGREGADO ANALITICO DE COSTOS DIRECTOS

ESPECIFICA DESCRIPCION Und. Cantidad Costo unitario Parcial


2.3.2.4.1.: COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL
TOPOGRAFO MES 46.9060 21.24 996.28
OBRERO III hh 820.7050 16.48 13,525.22
OBRERO II hh 305.6086 13.67 4,177.67
OBRERO I hh 4,482.0426 12.33 55,263.59
73,962.76

ESPECIFICA COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA -BIENES


2.3.1.1.1.1: BIENES
CLAVOS PARA MADERA C/C 3" kg 26.5773 7.00 186.04
CLAVOS PARA MADERA C/C 4" kg 68.2290 7.00 477.60
ALAMBRE NEGRO N16 kg 18.7983 6.20 116.55
ALAMBRE NEGRO N8 kg 23.3543 7.00 163.48
FIERRO CO. FY=4200 KG/CM2 (GRADO 60) kg 40.0000 8.00 320.00
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 782.0072 7.50 5,865.05
FIERRO ANGULAR 3/4"X3/4"X1/8" m 125.0000 45.00 5,625.00
ARENA FINA m3 3.5663 300.00 1,069.89
PIEDRA CHANCADA DE 3/4" m3 4.3123 300.00 1,293.69
ARENA GRUESA m3 2.9740 300.00 892.20
YESO BOLSA 28 kg BOL 0.0363 7.00 0.25
PIEDRA MEDIANA DE 6" m3 7.3248 200.00 1,464.96
CEMENTO PORTLAND TIPO I (42.5KG) BOL 274.7325 32.00 8,791.44
CANASTILLA DE PVC 2" und 3.0000 15.00 45.00
DISCO DE CORTE DE METAL 7" und 40.0000 12.00 480.00
CINTA TEFLON und 108.0000 3.00 324.00
IMPERMEABILIZANTE gln 11.5938 120.00 1,391.26
PEGAMENTO PARA PVC gln 0.6056 120.00 72.67
FORMADOR DE EMPAQUETADURA und 16.0000 9.60 153.60
SOLDADURA CELLOCORD P 3/16" kg 22.1000 20.00 442.00
TUBERIA DE FIERRO GALVANIZADO DE 2" und 10.0000 150.00 1,500.00
TUBERIA DE FIERRO GALVANIZADO DE 1 1/2" und 0.7500 90.00 67.50
TUBERIA DE FIERRO GALVANIZADO DE 1" und 1.0000 65.00 65.00
BISAGRA und 3.0000 15.00 45.00
CANDADO MEDIANO und 1.0000 45.00 45.00
GASOLINA 84 OCTANOS gln 18.3666 16.00 293.87
CORDEL m 0.0726 8.00 0.58
CORDEL rll 0.5451 8.00 4.36
HORMIGON DE RIO m3 20.5131 200.00 4,102.62
AGUA m3 30.6441 60.00 1,838.65
PRUEBAS DE RESISTENCIA DEL CONCRETO GLB 3.0000 255.00 765.00
GIGANTOGRAFIA DE VINIL INCLUYE IMPRESION m2 8.6418 22.00 190.12
MADERA AGUANO 2"X3"X10' pza 100.4173 25.00 2,510.43
MADERA AGUANO 2"X2"X10' pza 0.3873 16.00 6.20
MADERA AGUANO 1 1/2"X8"X10' und 351.0507 27.00 9,478.37
LIJA PARA PARED plg 23.3763 3.00 70.13
TRAPO INDUSTRIAL kg 84.6240 12.00 1,015.49
LIJA DE FIERRO #40 plg 38.1378 3.00 114.41
RODILLO TORO N12 und 5.5888 12.00 67.07
ROLLIZO DE EUCALIPTO DE 6" X 6.00 M pza 3.0000 25.00 75.00
ROLLIZO DE EUCALIPTO DE 4" X 3M pza 23.3543 15.00 350.31
ESTACA DE MADERA und 0.7260 5.00 3.63
ESCOBILLON DALIA GRANDE CON FIBRAS DE PLASTICO und 0.4460 12.00 5.35
MALLA DE ALAMBRE GALV. # 10 2" X 2" m2 133.0100 19.35 2,573.74
TAPA METALICA DE 0.60X0.60 M und 6.0000 100.00 600.00
COMPUERTA TIPO IZAJE .40X.40m, PLCHA 3/16", MARCO ANG.
und 3.0000 400.00 1,200.00
1.5"x3/16", L=1.40m
REJILLA METALICA 1.00x0.2m, FIERRO LISO 1/2" C/EJE DE GIRO und 1.0000 400.00 400.00
REJILLA METALICA 3.40x0.50m, FIERRO LISO 1/2" C/EJE DE GIRO und 1.0000 1,200.00 1,200.00
THINER gln 8.7953 25.00 219.88
DESAGREGADO ANALITICO DE COSTOS DIRECTOS

ESPECIFICA DESCRIPCION Und. Cantidad Costo unitario Parcial


PETROLEO gln 25.2252 16.00 403.60
PINTURA LATEX SUPERMATE gln 3.7243 55.00 204.84
IMPRIMANTE kg 11.1775 25.00 279.44
PINTURA ANTICORROSIVA gln 4.0000 70.00 280.00
PINTURA ESMALTE gln 8.1596 60.00 489.58
PLACA RECORDATORIA und 1.0000 1,500.00 1,500.00
HOJA DE SIERRA und 16.3908 7.00 114.74
UNION UNIVERSAL DE FIERRO GALVANIZADO DE 2" und 6.0000 23.00 138.00
NIPLE DE F GALV. DE 2" X 3" pza 6.0000 16.00 96.00
LUBRICANTE PARA TUBERIA PVC gln 0.0660 65.00 4.29
TUB. PVC SAP PRESION C-10 EC 2" x 5m und 6.0000 40.00 240.00
TUB. PVC SAP PRESION C-10 EC 1/2" x 5m C/R m 35.0000 5.50 192.50
CONO DE REBOSE PVC 4" X 2" und 3.0000 9.00 27.00
ACCESORIOS PARA PRUEBA HIDRAULICA GLB 3.0282 250.00 757.05
TUBERIA DE POLIETILENO DE 4" m 635.9115 52.00 33,067.40
REDUCCION PVC SAP 3/4" A 1/2" C-10 R und 8.0000 8.00 64.00
REDUCCION PVC SAP 1" A 3/4" C-10 R und 6.0000 9.60 57.60
REDUCCION PVC SAP 2" A 1" C-10 R und 4.0000 12.00 48.00
ADAPTADOR PVC-SAP TIPO UPR 2" und 6.0000 5.40 32.40
ADAPTADOR PVC-SAP TIPO UPR 4" und 12.1126 8.40 101.75
TUBERIA PVC UF NTP ISO 1452 DE 110 MM. C-10 m 31.5000 20.00 630.00
CODO PVC SAP 2" X 90 pza 8.0000 5.40 43.20
CODO PVC SAP 3/4" X 90 pza 12.0000 3.20 38.40
CODO PVC SAP 1" X 90 pza 12.0000 4.60 55.20
CODO PVC SAP S/P 1/2" X 90 und 35.0000 2.50 87.50
CODO PVC SAP S/P 2" X 90 und 4.0000 5.40 21.60
CODO PVC SAP C/R 1/2" X 90 und 40.0000 2.80 112.00
TEE PVC SAP DE 2" S/P, AGUA und 9.0000 6.80 61.20
TEE PVC SAP DE 1/2" C/R, AGUA und 32.0000 2.80 89.60
TEE PVC SAP DE 3/4" C/R, AGUA und 8.0000 4.60 36.80
TEE PVC SAP DE 1" C/R, AGUA und 12.0000 4.00 48.00
VALVULA ESFERICA DE 1/2" und 1.0000 35.00 35.00
VALVULA COMPUERTA BRONCE 2", pesado und 3.0000 45.00 135.00
0.00
97,474.08

ESPECIFICA DESCRIPCION Und. Cantidad Costo unitario Parcial


2.3.2.7.2 : COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - EQUIPOS
BROCHA DE 4" und 6.8102 35.00 238.36
REGLA DE ALUMINIO 1" X 4" X 8" und 0.4260 80.00 34.08
BALDE DE PRUEBA HIDRAULICA hm 96.9008 8.00 775.21
MEZCLADORA DE CONCRETO DE 9 -11P3 hm 42.9030 20.00 858.06
COMPACTADOR VIBR. TIPO PLANCHA 4 HP da 41.8129 8.00 334.50
VIBRADOR DE CONCRETO 4 HP 1.25" hm 7.9302 2.00 15.86
ESTACION TOTAL da 1.5310 8.00 12.25
NIVEL TOPOGRAFICO hm 10.9014 4.00 43.61
ESTACION TOTAL hm 18.1690 8.00 145.35
2,457.28
HERRAMIENTAS MANUALES
HERRAMIENTAS MANUALES %MO 1 2521.04 2,521.04
2,521.04

ESPECIFICA DESCRIPCION Und. Cantidad Costo unitario Parcial


2.3.2.7.2 : COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS
SC TAPA METALICA PARA TANQUE ELEVADO DE (0.60 X 0.60 m) und 2.0000 120.00 240.00
ALQUILER DE ALMACEN Y OFICINA mes 5.0000 400.00 2,000.00
FICHA DE CUMPLIMIENTO AMBIENTAL GLB 1.0000 3,000.00 3,000.00
TALLER DE EDUCACION AMBIENTAL Y PRIMEROS AUXILIOS GLB 1.0000 1,000.00 1,000.00
GLB 2.0000 4,000.00 8,000.00
ELABORACION DE UN PLAN DE MONITOREO ARQUEOLOGICO DESDE INICIO Y CIERR

OBRAS ESCULTURALES GLB 1.0000 10,000.00 10,000.00

FLETE TERRESTRE CUSCO - CHOQUELLUSCA


GLB 1.0000 4,000.00 4,000.00

FLETE TERRESTRE CHOQUELLUSCA - ZONA PASE AEREO(CAPTACION) GLB 2.0000 2,000.00 4,000.00
32,240.00
DESAGREGADO ANALITICO DE GASTOS GENERALES

Proyecto
Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion : Administracion Directa
Modalidad Supervision : Supervision de Planta
Fecha de Elaboracion :

Resumen de Gastos Generales


2.3.2.5.1 .CONTRATOS 0.00
2.3.2.4.1.: PERSONAL 60,000.00
2.3.1.1.1.1: BIENES 2,221.50
2.3.2.7.2 : SERVICIOS 400.00
2.3.2.7.1.1 : OTROS 274.60
TOTAL 62,896.10

2.3.2.4.1.: PERSONAL
Costo
Especifica Perfil Participacion Cantidad/mes Parcial (S/.)
unitario
Personal Profesional
Residente Ing. Civil 1.00 5.00 7,000.00 35,000.00
Sub Total 35,000.00
Personal Tecnico
Asistente Tecnico Tec. Const. Civil 0.50 5.00 4,000.00 10,000.00
Asistente Administrativo Tec. Const. Civil 0.50 5.00 2,000.00 5,000.00
Sub Total 15,000.00
Personal Control Obrero
Maestro de Obra Experencia Ejec. Obras hidraulicas 1.00 5.00 2,000.00 10,000.00
Sub Total 10,000.00
-
Total 60,000.00

2.3.1.1.1.1: BIENES
Costo
Especifica Unidad Cantidad Parcial (S/.)
unitario
Bienes de Consumo
AGUA OXIGENADA MEDIANO 120ML UND 3.00 5.00 15.00
BUSCAPINA UND 10.00 1.50 15.00
TAPSIN UND 10.00 1.50 15.00
ASPIRINA UND 10.00 0.50 5.00
DOLOFLAM UND 10.00 1.80 18.00
FRASCO DE ALCOHOL MEDIANO 250 ML UND 1.00 8.00 8.00
GASA ESTERILIZADA 5m x 10 cm. PQT 1.00 2.50 2.50
ESPARADRAPO DE SEDA 5 cm x 4.5 m. RLL 1.00 4.00 4.00
VENDA ELASTICA 3" x 5 ydas RLL 1.00 5.00 5.00
ALGODN HIDROFILO X 250 GR. PQT 1.00 12.50 12.50

Sub Total 100.00


Material de Escritorio
CUADERNO DE OBRA X 100 HOJAS AUTOCOPIABLE UND 4.00 50.00 200.00
PAPEL A4 75 GR BLANCO MILLAR 5.00 30.00 150.00
CUADERNO CUADRICULADO X 200 HOJAS UND 5.00 8.00 40.00
PARTE DIARIO DE MAQUINARIA X 50 HOJAS 3 COPIAS AUTOCOPIABLE BLOCK 5.00 30.00 150.00
NOTA DE ENTRADA A ALMACEN X 50 HOJAS 3 COPIAS AUTOCOPIABLE BLOCK 5.00 10.00 50.00
NOTA DE SALIDA DE ALMACEN X 50 HOJAS 3 COPIAS AUTOCOPIABLE BLOCK 5.00 10.00 50.00
TARJETAS DE CONTROL DE ALMACEN CIENTO 1.00 35.00 35.00
CINTA MASKING UND 5.00 6.00 30.00
FOLDER MANILA CON FASTENER UND 50.00 1.00 50.00
POSIT UND 5.00 3.50 17.50
VINIFAN TAMAO OFICIO UND 4.00 12.00 48.00
CUTTER UND 4.00 2.00 8.00
ENGRAMPADOR UND 1.00 14.00 14.00
LAPICERO FABER CASTELL UND 20.00 1.20 24.00
CORRECTOR (FABER CASTELL) UND 5.00 3.00 15.00
PEGAMENTO EN BARRA UHU UND 5.00 6.00 30.00
ARCHIVADORES DE LOMO ANCHO UND 10.00 6.00 60.00
PAPEL LUSTRE COLOR AZUL UND 10.00 1.00 10.00
THONNER PARA IMPRESORA UND 1.00 200.00 200.00
FOTOCOPIAS CIENTO 1.00 100.00 100.00
DESAGREGADO ANALITICO DE GASTOS GENERALES
Sub Total 1281.50
DESAGREGADO ANALITICO DE GASTOS GENERALES
Implementos de Seguridad
(a) Implementos Personal Tecnico
CASCO DE SEGURIDAD PARA PERSONAL TECNICO UND 2.00 35.00 70.00
LENTES DE PROTECCION PARA PERSONAL TECNICO UND 2.00 30.00 60.00
CAPUCHA IMPERMEABLE PARA PERSONAL TECNICO UND 2.00 45.00 90.00
CHALECOS DE SEGURIDAD PARA PERSONAL TECNICO UND 2.00 60.00 120.00
ZAPATOS DE SEGURIDAD PARA PERSONAL TECNICO UND 2.00 250.00 500.00

Sub Total 840.00


Total 2221.50
2.3.2.7.2 : SERVICIO
Costo
Especifica unidad Cantidad veces Parcial (S/.)
unitario
Apoyo Logistico
Legalizacion de Cuaderno de Obra Und 1.00 5.00 80.00 400.00
Sub Total 400.00
Total 400.00

2.3.2.7.1.1 : OTROS
Costo
Especifica unidad meses cantidad Parcial (S/.)
unitario
Varios
viaticos para el personal de planta GLB 274.60
Sub Total 274.60
Total 274.60
DESAGREGADO ANALITICO DE GASTOS POR SUPERVISION

Proyecto
Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion : Administracion Directa
Modalidad Supervision : Supervision de Planta
Fecha de Elaboracion :

Resumen de Gastos por Supervision


2.3.2.5.1 .CONTRATOS
2.3.2.4.1.: PERSONAL 17,500.00
2.3.1.1.1.1: BIENES 736.00
2.3.2.7.2 : SERVICIOS
2.3.2.7.1.1 : OTROS 0.00
TOTAL 18,236.00

2.3.2.4.1.: PERSONAL

Especifica Perfil Participacion Cantidad/mes Costo unitario Parcial (S/.)

Personal Profesional
Ingeniero Inspector Ing. Civil 0.50 5.0 7000.00 17500.00
Sub Total 17500.00
Personal Tecnico

Sub Total 0.00


Personal Auxiliar
Sub Total 0.00
Total 17500.00

2.3.1.1.1.1: BIENES
Especifica Unidad Cantidad Costo unitario Parcial (S/.)
Material de Escritorio
Papel A-4, 75 gr/cm2 Millar 5.00 30.00 150.00
CUADERNO CUADRICULADO X 200 HOJAS UND 3.00 8.00 24.00
POSIT UND 3.00 3.00 9.00
CORRECTOR (FABER CASTELL) UND 3.00 3.00 9.00
PEGAMENTO EN BARRA UHU UND 3.00 4.00 12.00
LAPICERO FABER CASTELL UND 10.00 1.20 12.00
CAMARA DIGITAL 13.2 MEGA PIXELS UND 1.00 520.00 520.00
736.00

Total 736.00

2.3.2.7.1.1 :OTROS

Especifica unidad meses cantidad Costo unitario Parcial (S/.)


Varios

viaticos para el personal de planta mes


Otros 0.00
Sub Total 0.00
Total 0.00
DESAGREGADO ANALITICO DE GASTOS POR LIQUIDACIN

Proyecto
Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion : Administracion Directa
Modalidad Supervision : Supervision de Planta
Fecha de Elaboracion :

Resumen de Gastos por Supervision


2.3.2.5.1 .CONTRATOS
2.3.2.4.1.: PERSONAL 6,000.00
2.3.1.1.1.1: BIENES 1,113.75
2.3.2.7.2 : SERVICIOS
2.3.2.7.1.1 : OTROS 0.00
TOTAL 7,113.75

2.3.2.4.1.: PERSONAL

Especifica Perfil Participacion Cantidad/mes Costo unitario Parcial (S/.)

Personal Profesional
Tecnico Liquidador Ing. Civil 0.50 1.0 7000.00 3500.00
Tecnico Financiero Contador 0.50 1.0 5000.00 2500.00
Sub Total 6000.00
Personal Tecnico

Sub Total 0.00


Personal Auxiliar
Sub Total 0.00
Total 6000.00

2.3.1.1.1.1: BIENES

Especifica Unidad Cantidad Costo unitario Parcial (S/.)

Material de Escritorio
FOTOCOPIAS GLB 1.00 500.00 500.00
MICAS UNIDAD 25.00 0.85 21.25
ANILLOS UNIDAD 25.00 1.00 25.00
ARCHIVADORES DE LOMO ANGOSTO UND 10.00 10.00 100.00
RESALTADOR UND 20.00 2.00 40.00
Papel A-4, 75 gr/cm2 Millar 3.00 30.00 90.00
CUADERNO CUADRICULADO X 200 HOJAS UND 5.00 8.00 40.00
POSIT UND 5.00 3.50 17.50
CORRECTOR (FABER CASTELL) UND 5.00 3.00 15.00
PEGAMENTO EN BARRA UHU UND 2.00 4.00 8.00
LAPICERO FABER CASTELL UND 10.00 1.20 12.00
THONER PARA IMPRESORA LASER UND 1.00 245.00 245.00

Total 1113.75

2.3.2.7.1.1 :OTROS

Especifica unidad meses cantidad Costo unitario Parcial (S/.)


Varios
Otros 0.00
Sub Total 0.00
Total 0.00
DESAGREGADO ANALITICO DE GASTOS POR EXPEDIENTE TECNICO

Proyecto
Localizacion :
Plazo de Ejecucion :
Modalidad Ejecucion : Administracion Directa
Modalidad Supervision : Supervision de Planta
Fecha de Elaboracion :

Resumen de Gastos por Supervision


2.3.2.5.1 .CONTRATOS
2.3.2.4.1.: PERSONAL 6,000.00
2.3.1.1.1.1: BIENES 670.00
2.3.2.7.2 : SERVICIOS
2.3.2.7.1.1 : OTROS 3,530.00
TOTAL 10,200.00

2.3.2.4.1.: PERSONAL

Especifica Perfil Participacion Cantidad/mes Costo unitario Parcial (S/.)

Personal Profesional
Incidencia del Proyectista Ing. Civil 1.00 1.0 6000.00 6000.00
Sub Total 6000.00
Personal Tecnico
Sub Total 0.00
Personal Auxiliar
Sub Total 0.00
Total 6000.00

2.3.1.1.1.1: BIENES
Especifica Unidad Cantidad Costo unitario Parcial (S/.)
Material de Escritorio
PAPEL BOND A4 MILL 5.00 25.00 125.00
PAPEL A3 MILL 0.50 65.00 32.50
PAPEL A1 MILL 0.10 250.00 25.00
MICAS UNIDAD 20.00 1.00 20.00
ANILLOS UNIDAD 20.00 1.00 20.00
LIBRETAS DE CAMPO TRANS BOOK UNIDAD 2.00 6.50 13.00
ARCHIVADORES DE LOMO ANGOSTO UND 5.00 10.00 50.00
CD RW UND 5.00 1.00 5.00
DVD UND 5.00 2.00 10.00
TINTA PARA IMPRESORA UND 1.00 100.00 100.00
THONER PARA IMPRESORA LASER UND 1.00 245.00 245.00
POSIT UND 2.00 3.50 7.00
CORRECTOR (FABER CASTELL) UND 2.00 3.00 6.00
PEGAMENTO EN BARRA UHU UND 1.00 4.00 4.00
LAPICERO FABER CASTELL UND 5.00 1.50 7.50

Total 670.00

2.3.2.7.1.1 :OTROS

Especifica unidad meses cantidad Costo unitario Parcial (S/.)


Varios
Levantamiento topogrfico glb 1.00 700.00 700.00
Estudio de Suelos glb 1.00 700.00 700.00
Estudio de Impacto Ambiental glb 1.00 2130.00 2,130.00

Total 3530.00