Вы находитесь на странице: 1из 7

4.

standards and insulation coordination

For many years now the International shapes producible in laboratories and acceptable as regards operating safety.
Electrotechnical Commission (IEC) has having shown satisfactory equivalence. Moreover, the gradual replacement of
been concerned with the problem of Moreover, two new concepts are dealt dischargers by arresters enables
HV insulation coordination. with in this standard: reduction of the safety margin which
longitudinal insulation (between the had become superfluous between
Insulation coordination is dealt with in
terminals of the same phase of an open arrester protection level and equipment
two main documents:
device); specified insulating voltage.
IEC 664 for LV;
IEC 71 for HV. consideration of altitude and of Determining insulation levels
installation ageing. The standard does not stipulate
IEC 71 is divided into two parts, the
second part forming an exhaustive This draft-standard distinguishes invariable withstand voltages valid in all
application guide. internal insulation, external insulation cases, but enables insulation
Product standards, including: and two voltage ranges: coordination studies to be carried out in
IEC 694 common clauses for internal insulation covers everything a number of stages:
equipment; not in ambient air (for example, liquid definition of relationships between
IEC 76 transformers; insulation for transformers, SF6 or network type and choice of its
IEC 99 surge arresters; vacuum for circuit-breakers); insulations.
comply with IEC 71 as regards specific external insulation refers to air The purpose is to establish the
withstand voltages. clearances. characteristics of the maximum
range l: from 1 kV to 245 kV inclusive possible permanent voltages and the
range ll: above 245 kV. foreseeable temporary overvoltages as
HV insulation coordination a function of:
For each of these, implementation of
as in IEC 71 insulation coordination varies slightly.
network structure and its rated
One of the objectives of this standard voltage,
A table of standardised rated withstand the neutral earthing connection
which should come into force in 93 is to
voltages exists for each range. These diagram,
explain and break down the various tables have been drawn up according the substations and rotating
factors for achievement of withstand to various criteria, and, although mostly machines present on the line,
voltages. This approach encourages empirical up to now, have been the type and position of surge
search for optimisation and even confirmed, with a few reservations, by limitation devices, if any,
reduction in voltage withstand levels. experience. Indeed, it cannot be denied and according to considerations
Standard IEC 71 proposes conventional that the levels laid down, which have common to all overvoltage classes
modelling of actual stresses by wave not been changed for years, are fully defined by the standard (see fig. 26).

overvoltage low frequency transient


class permanent temporary slow front fast front very fast front
shape

f
t

100 Tf 3 ns
shape range f = 50 or 60 Hz 10 f 500 Hz 5,000 Tp 20 s 20 T1 0.1 s 0.3 f1 100 MHz
(frequency, rising front, 30 f2 300 kHz
term) Tt 3,600 s 3,600 Tt 0.03 s 20 ms T2 300 s T2 3 ms Tt
standardised shape f = 50 or 60 Hz 48 f 62 Hz Tp = 250 s T1 = 1.2 s (*)
Tt (*) Tt = 60 s T2 = 2,500 s T2 = 50 s
standardised (*) short duration switching lightning (*)
withstand test power frequency impulse test impulse test
test
(*) to be specified by the relevant product Committee

Cahier Technique Merlin Gerin n 151 / p.17


coordination of network insulation For operating voltages under 245 kV,
Once these data have been collected, the power frequency test and the
the corresponding coordination lightning impulse test are the ones
withstand voltage must be determined normally chosen.
for each overvoltage class taking into the final choice is made from
consideration the required performance standardised levels (see fig. 28) from
and, generally, the acceptable all the rated voltages.
insulation failure rate. The value
An example:
obtained is specific to the network
Figure 29 presents a calculation of this
studied and to its situation and is the Rated insulation levels to be retained:
kind taken from the application guide of
lowest withstand voltage to the the draft-revision of publication IEC 71.
overvoltage in question that the It shows the insulation coordination
network has to have in its operating study for a substation characterised by
conditions. the highest voltage for the equipment
To choose the components of a Um = 24 kV.
network, their specified withstand This example mainly deals with 125 kV chosen as a technico-
voltages must be defined. external insulation, as the chief problem economic compromise for fast front
Determination of coordination withstand facing installation and network transients, results in:
voltages consists in setting the
minimum values of the insulation
withstand voltages satisfying
performance criterion when insulation is origin and classification of constraining network analysis ( 4.02)
voltages ( 3.16)
subjected to the representative protection level of voltage limiting
overvoltages in operating conditions. devices ( 3.20)
Determination of specified insulation insulation characteristics representative voltages
withstand voltages consists in and overvoltages Urp ( 3.18)
converting the coordination withstand
voltages into appropriate standardised insulation characteristics
test conditions. This is achieved by performance criterion ( 3.21) choice of insulation satisfying
statistical distribution (+) the performance criterion ( 4.03)
multiplying the coordination withstand
inaccuracy of initial data (+)
voltages by factors compensating the (+) effects combined in a
differences between actual insulation coordination factor Kc ( 3.24)
operation conditions and standardised coordination withstand
withstand test conditions. voltage Ucw ( 3.23)

Rated insulation level is chosen by atmospheric correction


selecting the most economical series of factor ka ( 3.26)
all equipment tested (*) application of factors taking into
standardised insulation withstand production dispersion (*) consideration the differences
voltages, sufficient to prove that all the installation quality (*) between standard test conditions
specified withstand voltages are ageing in operation (*) and operating conditions ( 4.04)
satisfied. other unknown factors (*)
(*) effects combined in a safety
The study chart for final determination factor Ks ( 3.27)
of rated insulation is shown in figure 27. specified withstand voltage Urw ( 3.26)
This chart covers the two factors,
altitude and manufacturing dispersion, test conditions (Chapter 5)
defined in the draft-standard, by the test conversion factor Kt ( 3.29) choice of standardised
term of corrective factor. standardised withstand withstand voltage ( 4.05 & 4.09)
voltages ( 4.06 & 4.07)
rated withstand voltage or insulation Um ranges ( 4.08)
level is the same as specified withstand
voltage for overvoltages which can be
tested, i.e.: standardised or rated insulation level: all of Uw ( 3.32 & 3.33)
power frequency test,
switching impulse test,
lightning impulse test.
the equivalence factors proposed by
standard IEC 71 mean generally that
only two withstand voltages need be
specified out of the 3 considered.

Cahier Technique Merlin Gerin n 151 / p.18


either acceptance of a failure rate
greater than that already taken as an highest voltage standardised short standardised withstand
hypothesis, for equipment duration withstand voltage voltages to lightning
or addition of arresters to the Um at power frequency impulses
installation to ensure the latter is not kV rms kV rms kV rms
stressed beyond this level. 3.6 10 20/40
For high and extra high voltages, the 7.2 20 40/60
insulation coordination procedure is the 12 28 60/75/95
same, but equipment insulation is
17.5 38 75/95
generally qualified by its switching
impulse and lightning impulse 24 50 95/125/145
withstands. 36 70 145/170
52 95 250
72.5 140 325
123 (185)/230 450/550
145 (185)/230/275 (450)/550/650
170 (230)/275/325 (550)/650/750
245 (275)/(325)/360/395/460 (650)/(750)/850/950/1050

rated withstand voltage at short duration to lightning


kV power frequency impulses
rated withstand voltage 74 108 141
to lightning impulses
equivalence factor 1.06 1.06
slow front fast
rated withstand voltage 28 32 42 61
to an overvoltage at short
duration power frequency
equivalence factor 0.6 0.6
slow front 50 Hz
specified withstand voltage
withstand voltage 28 32 70 102 141
altitude correction 1.13 1.13 1.13
dispersion factor 1.15 1.15 1.05 1.05 1.05
coordination withstand voltage 24 28 59 86 119*
(case of equipment subjected
to atmospheric pressures)
overvoltages in operation
conventional representative short duration 250-2,500 s impulse 1.2-50 s impulse
impulse shape 50 Hz power frequency (1 mn) 2 % arcing
conventional representative 24 28 59 86
amplitude (kV) (2.6 p.U.) (3.86 p.U)
overvoltage categories phase / phase to phase / phase to phase / frame and
frame phase frame phase phase to phase
temporary slow front fast front
at power frequency (switching) (lightning)
this value comes from the following Calculation example:
criteria: for a slow front coordination withstand voltage of 59 kV
- arrester protection level: 80 kW slow front specified withstand voltage = 59 kV x 1.05 x 1.13 = 70 kV
- arrester/equipment clearance: 8 m equivalent rated withstand voltage at standard short term frequency = 70 kV x 0.6 = 42 kV
- safety factor: 1.05 equivalent rated withstand voltage to lightning impulses = 70 kV x 1.06 = 74 kV.

Cahier Technique Merlin Gerin n 151 / p.19


5. coordination applied to electrical
installation design

The high operating voltage involved for energy distributors (invoice losses), ferromagnetic resonance. To prevent
increases the economic importance of industrial consumers (production this, the capacitances must be reduced
this study. losses) and people (safety). by approaching, for example, the
Three criteria justify this statement: In LV transformer energising equipment.
increase of number of customers or In practice, the lower the operating Connection of a load prior to energising
of distributed power; voltage, the more limited the is useful since this load acts as a
increase of failure cost (cost of consequences of breakdown in power reducing resistance which can prevent
equipment to be replaced); distribution terms. However resonance.
the smaller relative part of the development of electronic equipment Earthing the neutral is also a solution
coordination study in total installation and systems is responsible for a large for phase/earth resonances.
cost. number of incidents further to Overvoltage caused by capacitive
overvoltages. In point of fact, current breaking
breakdown consequences disturbance withstand level is not The solution is to prevent successive
always specified or is not coordinated reignitions by increasing contact
Dielectric failure (breakdown or arcing)
with the level corresponding to its separation speed and using a good
can cause:
installation. dielectric (vacuum or SF6).
tripping of the protective devices in
the best possible case; However, these systems play an Overvoltage caused by closing off-
destruction of equipment in the worst increasingly large role in the integrity of load lines
possible case; installations, production and This is prevented on transmission
interruption of operation each time a management, and the economic networks by progressive energising,
failure occurs. consequences for the company obtained by adding insertion
concerned can be serious. resistances to the circuit-breaker.
In HV, the resulting power failure can
affect an entire town, a region or an Coordination of withstands is thus Overvoltage caused by lightning
iron and steel plant, and causes: vital, even in LV... stroke
a risk of network destabilisation; .... and the use of arresters should be There are three possibilities:
a loss of energy billed for the energy generalised. Today they are highly installation of earth cables to prevent
distributor; recommended for LV consumers direct impulses (see chapter 1);
production loss for industrial supplied by overhead lines. installation of protective devices at
consumers; vulnerable points (dischargers or,
a risk for people (e.g. in hospitals) reduction of overvoltage preferably, arresters), (see appendix 2);
and for computer data. creation of good quality earth
risks and level connections (see chapter 1).
To avoid such incidents, studies must
Simple solutions to the various
be conducted for each new installation
overvoltages looked at in chapter 1 can
to provide consistent and optimised risk
be considered as from the initial project
protection. of installation.
One solution is to increase installation
Overvoltage due to ferromagnetic
insulation level by increasing resonance
clearances. However, this results in
The only means of removing this
considerable increase in cost: doubling completely is for 1/C to be greater
these clearances means multiplying than the slope at the origin of L i.
eight times volumes and costs. However, other solutions can be
considered, in particular in MV where
an unbalance between the 3 phases
can occur in the case of protection by
In MV phase by phase controlled switch. The
The consequences of insulation faults greatest simultaneity possible must be
on MV networks are the same, on a sought on closing the 3 network phases
lesser scale, as those in HV. (omnipole equipment);
The consequences of the resulting closing an off-load transformer may
electricity failures can also be serious be the transient phenomenon causing

Cahier Technique Merlin Gerin n 151 / p.20


6. conclusion

Insulation coordination aims at finding rules out the possibility of absolute alongside optimisation of economy and
the right balance between equipment solutions. electrical operating stresses.
reliability from a dielectric standpoint, Although the modellings chosen may Increasing use of arresters, partly due
on the one hand, and their sizing and appear somewhat arbitrary at first sight, to improvement of their characteristics
thus cost, on the other. they have been confirmed by and reliability, contributes to greater
experience. control of protection levels.
The presentation made in this
document shows the complexity of the More detailed information can be found Consideration of this aspect by
in the publications quoted for readers international standard committees, both
parameters involved in such an
wishing to examine the subject in generally and as regards product
analysis.
greater depth. The progress made in recommendations, is proof of the
Moreover, the statistical aspect of knowledge of phenomena now ensures importance of the subject and of its
behaviour to transient overvoltages increased installation reliability associated advantages.

appendix 1: propagation of overvoltage

Whatever the origin of the overvoltage, Propagation speed approaches that of


it will propagate along the line or cable the velocity of light, i.e. approximately
making up the network. 3 x 108 m/s. This speed can also be
This propagation support can be said to be equal to 300 metres per
modelled by using values per length microsecond, thus providing an
unit of inductance and resistance in estimation of the distribution along the
longitudinal and of capacitance and conductor of a very short term wave
conductance in transverse (see fig. 30). front (see fig. 31).
The impedance, in sinusoidal state, is The theory of guided propagation
then given by: makes it possible to establish that,
when a wave propagating along a
L R
Z
C G
At the high frequencies generally
associated with overvoltages, the evolution V
inductive and capacitive terms become in time front: 300 kv/s
600 kv
preponderant. The impedance known
as "characteristic impedance" then 2 s
equals:
L t (at constant x)
Zc distribution
C V
in space front: 1 kv/m
The resistive and conductive terms
correspond to losses causing wave 600 m
attenuation during its propagation.
The magnitudes of the characteristic
impedances are: x (at constant t)
EHV lines: 300 to 500 ohms;
HVA lines (overhead); approximately
1,000 ohms,

Cahier Technique Merlin Gerin n 151 / p.21


conductor arrives at a point of zero transmitted wave and a reflected This case results in a high stress at the
impedance change, partial reflection wave with a factor -1; reflection point and in its vicinity
and transmission are observed. Za = Zc (homogeneous conductor): (vicinity in the space distribution sense
transmission equals 1 and reflection mentioned above).
If Zc is the characteristic impedance of
zero; The expression doubling of the
the first conductor and Za that of the
Za = infinite (line open): voltage at the voltage wave, frequently used, may
second, the transmission and reflection
reflection point is given by the lead to confusion by letting people think
coefficients are given by:
superimposition of the incident wave that the reflected wave is twice as large
and the reflected wave with a as the initial wave. It is only at the
factor + 1. Its maximum value will then reflection point that the maximum value
The limit values of these coefficients be equal to twice the peak of the observed is twice the value of the
correspond to simple physical cases: incident wave. Although there is no incident wave, since this is the only
Za = 0 (line closed at the frame): propagation in the medium Za, the point where the incident wave and the
voltage at the point in question is thus border value is still given by T which reflected wave join their peaks.
zero at all times: this corresponds to a also equals 2.

appendix 2: installing a surge arrester

maximum safety clearance As its conduction level (if approximated Note:


to the protection level) is 75 kV, The coefficient 2 does not mean that
Wave reflection and propagation (see
appendix 1) mean that surge arresters intervention is only possible by the peak voltage is doubled but refers to
only limit overvoltages at their superimposition of the reflected wave superimposition of the incident wave
terminals. on the incident wave. and the reflected wave (see fig. 32).
The reflected wave must have reached
The clipped wave retains the dv/dt of
a value of 75 - 62.5 = 12.5 kV.
its rising front and could develop, by cabling the surge arresters
reflection, at the opening point, a The difference between the incident
A current wave flows off to the earth
voltage twice that of limitation voltage. value (62.5 kV) and the reflected value
when an arrester is used for limitation.
As equipment withstand voltage is (12.5 kV), i.e. 50 kV, corresponds to the
This results from application of the
generally lower than twice the residual wave front distributed on the return
voltage wave to the characteristic line
voltage of the arrester, there is a journey between the arrester and the
impedance:
maximum clearance not to be open point. The return distance is thus
exceeded between the arrester and the no more than 50 m, i.e. a maximum u
line: I .
substation equipment. protection clearance of 25 m. Zc
Example:
lightning wave: 300 kV/ s;
hence a voltage gradient on the line
on passage of the rising front direction of displacement
of 1 kV/m; of the lightning wave
voltage
MV substation: impulse withstand of instants... T0 T1
125 kV;
surge arrester: residual voltage:
2 x U0 = maximum stress reached
75 kV. at T1 T1 the most severe instant
The maximum stress at the open point
will be generated by reflection of the Up = arrester protection level
wave peak limited by the arrester. This
stress will have twice the value of this U0 = value of the incident wave
peak. reached on the arrester at T0
In order to keep to the limit of 125 kV of
u = value of the reflected wave
the equipment, the arrester must reached on the arrester at T0
therefore act at the latest when the (U0 + U = Up start of conduction)
incident wave in its position d
125 locations: arrester equipment
equals: 62.5 kV
2
(instant T0 in figure 32).

Cahier Technique Merlin Gerin n 151 / p.22


A voltage drop, mainly inductive and
which may be high, then occurs in the
earthing circuit.
Example:
current wave: 1 kA/ s;
earth down-cable inductance:
1 H/m;
hence UL = 1 kV/m.
If this voltage is not to be added to
L residual voltage, the proposed
equipment must be bypassed at the
arrester terminals as regards the
lightning phenomenon.
if L < 25 m: a surge limiter placed on the pole is sufficient In practice this consists in connecting
if L 25 m: a second limiter must be placed at the transformer terminals as shown in figure 33. If the HV/
equipment link is not made on the
arrester, conductor length must be as
short as possible (see fig. 34).

arrester

transformer

wrong cabling right cabling

appendix 3: electricity standards

There are three levels of standards: the CENELEC (European


The following three organisations act at Electrotechnical Standardisation
international, European and French Committee) produces the EN
level respectively: standards and groups 18 countries,
the IEC (International mostly European. Application of the
Electrotechnical Commission) produces standards it votes is mandatory.
the IEC standards with the the UTE (Union Technique de
participation of 60 countries. Standards lElectricit) produces the French NF
are accepted only if opposition is less standards.
than 20 %. Its application may give rise
to waivers in certain countries.

Cahier Technique Merlin Gerin n 151 / p.23

Вам также может понравиться