Addendum 1

Sr. Original Clause / Article Amended Clause / Article


No.
1 Schedule A, Annex I , Clause 2 Land Schedule A, Annex I , Modified Clause 2 Land
The Site of the Project Highway comprises the land described below: The Site of the Project Highway comprises the land described below:

Sr. No. Chainage (Km) Row Remarks Sr. No. Chainage (Km) Row Remarks
From To (m) From To (m)
Section 1 84+600 97+240 30m Total Section 1 84+600 86+100 15m to Total Length
Length 18m 1.50 km
12.640 km
86+100 97+240 24m Total Length
Section 2 97+240 122+850 30m Total 11.140 km
Length
25.610 km Section 2 97+240 122+850 30m Total Length
25.610 km

2 Schedule A, Annex II Schedule A, Modified Annex II

The dates on which the Authority shall provide Right of Way to the The dates on which the Authority shall provide Right of Way to the
Contractor on different stretches of the Site are stated below: Contractor on different stretches of the Site are stated below:

Section From Km Length Width Date of Section From Km Length Width Date of
to Km (km) (m) Providing to Km (km) (m) Providing ROW
ROW
Section 1 84+600 to 1.50 km 15 m to On appointed
Section 1 84+600 12.640 30 m On appointed Balasinor to Dev 86+100 18 m date in
Balasinor to Dev to km date in Junction 86+100 to 11.140 24 m accordance with
Junction 97+240 accordance 97+240 km Annex-IV of this
Section 1 97+240 25.610 30m with Annex- Section 2 97+240 to 25.610 30m schedule
Dev Junction to to km IV of this Dev Junction to 122+850 km
Viranya Junction 122+840 schedule Viraniya
Junction
No additional land acquisition is envisaged for the project.
Sr. Original Clause / Article Amended Clause / Article
No.

3 Schedule B. Annex I Clause 1.2.1 Schedule B. Annex I Modified Clause 1.2.1


1.2.1 Strengthening & Widening of the existing carriageway shall be 1.2.1 Strengthening & Widening of the existing carriageway shall be
undertaken. The carriageway widths shall be as under: undertaken. The carriageway widths shall be as under:

Section Carriageway Median / Total Section Carriageway Median / Total


on either sides Shoulders Carriageway on either sides Shoulders Carriageway
Width Width
Section 1 Section 1
84+600 to 7.00 m travel 1.0m 15.0m Top Width 84+600 to 7.00 m travel 1.0m 15.0m to 18.0
86+100 lanes Central 86+100 lanes Central m variable
Verge Verge Top Width

86+100 to 3.5m travel 2.0m Hard 14.0m Top Width 86+100 to 3.5m travel 2.0m Hard 14.0m Top
97+240 lane + 1.5m Side 97+240 lane + 1.5m Side Width
paved shoulder Shoulder paved shoulder Shoulder

Section 2 Section 2
97+240 to 3.5m travel 2.0m Hard 14.0m Top Width 97+240 to 3.5m travel 2.0m Hard 14.0m Top
122+850 lane + 1.5m Side 122+850 lane + 1.5m Side Width
paved shoulder Shoulder paved shoulder Shoulder

4 Schedule B, Annex V (b) New Minor Bridges Schedule B, Modified Annex V (b) New Minor Bridges

Sr. Chainage Existing Improvement Remarks Sr. Chainage Proposed Configuration Improvement Remarks
No. (Km) No. of Spans Widt Proposal No. (Km) No. of Width Proposal
with span h Spans with (m)
length (m) span length
(m) (m)
1 110/0 to 110/2 3 x 18.0m 12.0 New Major 1 109+552 3 x 18.0m 12.0 m New Minor New Minor
(Luni Bridge) m Bridge adjacent (Luni Bridge Bridge
to existing Bridge) adjacent to
bridge existing bridge
Sr. Original Clause / Article Amended Clause / Article
No.
5 Schedule B, Appendix B-1, TCS 1 Schedule B, Appendix B-1, Modified TCS 1

Schedule B, Appendix B-1, TCS 2A Schedule B, Appendix B-1, Modified TCS 2A


Sr. Original Clause / Article Amended Clause / Article
No.
Schedule B, Appendix B-1, TCS 3 Schedule B, Appendix B-1, Modified TCS 2B

Schedule B, Appendix B-1, TCS 4 Schedule B, Appendix B-1, Modified TCS 3

6 Schedule H Modified Schedule H Attached.


Addendum-2

Sr.No. Original Clause RFQ 2.2.4 (iii) Amended Clause RFQ 2.2.4 (iii)

For the purpose of this RFQ

(a) Highways sector would be deemed to include (a) Highways sector would be deemed to include
1 highways, expressways, bridges, tunnels and airfields highways, roads, expressways, bridges, tunnels and
and airfields and

(b) Core sector would be deemed to include ports, (b) Core sector would be deemed to include ports, airports,
airports, railways, metrorail, industrial parks / estates, railways, metrorail, industrial parks / estates, logistic parks,
2
logistic parks, pipelines, irrigation, water supply, pipelines, irrigation, water supply, sewerage and real estate
sewerage and real estate development development, buildings

Clause 3.2.1
(a) Highways sector would be deemed to include (a) Highways sector would be deemed to include
1 highways, expressways, bridges, tunnels and airfields highways, roads, expressways, bridges, tunnels and
and airfields and
(b) Core sector would be deemed to include ports, (b) Core sector would be deemed to include ports, airports,
airports, railways, metrorail, industrial parks / estates, railways, metrorail, industrial parks / estates, logistic parks,
2
logistic parks, pipelines, irrigation, water supply, pipelines, irrigation, water supply, sewerage and real estate
sewerage and real estate development development, buildings
Clarifications to Pre-bid queries for Construction of Standard Two Lane road with 1.5m paved shoulders on either
side (10mtr.) i.e. Widening and Strengthening of Ahmedabad Kuha Kathlal Balasinor Dev Namnar - Lunawada
Santrampur Zalod Road km.84/600 to 122/850
Sr. Description Query / Recommendation Clarification
No.
1 As per Tender Documents EMD Exemption Certificate is not accepted. Not agreed, RFQ remains unchanged

- As per general govt. tendering norms, tenders invited by your


department i.e. R & B Department, EMD Exemption Certificate is
allowed. So, we request you to please allow EMD Exemption
Certificate against EMD for this tender also

2 As per Tender Documents in case of Joint Venture each of other JV Not agreed, RFQ remains unchanged
members shall meet at least 30% requirement of Technical and
Financial capacity.

- The criteria of this tender are set as per the pre qualification criteria
of tenders invited by National Highway Authority of India (NHAI).As this
tender is invited by the Govt. of Gujarat, R & B Department, the criteria
shall be sought as per the Govt. of Gujarat R & B Department
Resolution No. SSR/1097/32/C dated 15/06/2011.

- Accordingly, in case of JV, for other members, qualifying threshold


amount of updated completion cost would be 20.4% of amount put to
tender, therefore we hereby request you to
change the criteria in line with the GR of Govt. of Gujarat. A copy of
Resolution is attached herewith.

3 As per tender documents Enhancement factor @ 10% is allowed for Kindly refer Clause 2.2.14 of RFQ, No
which base year is F.Y. 2015-16 (Factor 1.00) modification required.

- As per the tender documents, the last date of submission of this


tender is during the year 2016-17. So, we request you to change the
enhancement factor by taking 2016-17 as a base year.
Sr. Description Query / Recommendation Clarification
No.

- Accordingly the revised enhancement factor shall be as follows:

Sr. Particulars Updation


No. Factor
1 Year - 1 (2015-16) 1.10
2 Year - 2 (2014-15) 1.21
3 Year - 3 (2013-14) 1.33
4 Year - 4 (2012-13) 1.46
5 Year - 5 (2011-12) 1.61

4 As per Tender Documents Applicant shall, over the past 5 (five) Not agreed, RFQ remains unchanged
financial years preceding the Bid Due Date, have received payments
for construction of Eligible Project(s) or has undertaken construction
works by itself in a PPP project, such that the sum total thereof is more
than Rs. 250.00 crore (Rs. Two Hundred Fifty Crores Only) (the
Threshold Technical Capacity).

- As per Govt. of Gujarat R & B Department Resolution No


SSR/1097/32/C dated 15/06/2011 Anuual Turnover of any one of the
last five financial year updated to current financial year shall be more
than or equal to 100% of ECV. We request you to kindly allow the
same as Threshold Technical Capacity.

5 As per Tender Documents Experience in Eligible Projects is based on Not agreed, RFQ remains unchanged
Factors given for Highways and Core Sector i.e. 1 & 0.5

- As per Govt. of Gujarat R & B Department Resolution No.


SSR/1097/32/C dated 15/06/2011 such type of factors are not
considered for Experience in Eligible Projects,
therefore we hereby request you to please remove such type of
requirement for Eligible Experience and allow only requirement of
20.4% of amount put to tender as eligible experience.
Sr. Description Query / Recommendation Clarification
No.
6 We also request you to set the qualifying financial and technical Not agreed, RFQ remains unchanged
criteria based on the Govt. of Gujarat R & B Department Resolution
No. SSR/1097/32/C dated 15/06/2011 in place of criteria set as
qualifying criteria of National Highway Authority of India (NHAI) as this
tender is invited by the R & B Department.(Copy for the same is
attached herewith)
7 Agarwada Bridge The said bridge is on a Mahi perennial river and after site visit it was R&BD, Design Circle has carried out
Improvement observed that there is always standing water of 30-40 ft depth underwater videography prior to
Works: throughout the year, due to more than 15 kms length of reservoir of preparation of the estimate. Snapshots
The following works Vanakbori Dam. Under such circumstances that are a specialized task from the videography are attached in
are included in the to estimate and make DPR of the damage to the existing foundations / Appendix 1. The videography DVDs are
improvement works sub structure in such short span of time is itself is such a big job. We available in the office of the Executive
of Agrawada Bridge have approached institutions like National Institute of Oceanography, Engineer which can be availed by
(As per Schedule which has special divers with capabilities and instruments to assess prospective bidders for estimation purpose.
B Appendix B-VI): the damage to underwater structure, but they are unavailable to send
Foundation their teams on such short notice. Hence it is not possible to estimate For scope refer Appendix-B-VI.
Strengthening, Pier any damage to the bridge structure under water within such short time
jacketing with RCC, period which is mandatory requirement to assess the rehabilitation
Patching of steps required to be taken for Major Bridge.
damaged concrete
surface with
polymer concrete It may be noted that rehabilitation was carried out on the same bridge
and curing in the year 1998. As per the information gathered on site, it is
compounds, confirmed that the bridge was closed for traffic from 1990 and after real
wearing coat assessment and the rehabilitation required for the bridge to open for
Replacement, M.S. traffic, the rehabilitation was carried out only in 1998 after final
Grill above Parapet assessment. The approved tenders were 1000% higher than the
(remaining length) invited bid cost. It shows the seriousness of the work.
and Expansion joint
Replacement. And
Bank Protection It is practically impossible for the contractor to estimate and bid for its
with Gabion wall rehabilitation works within one month in a present situation.
and mattresses
Sr. Description Query / Recommendation Clarification
No.
Without proper surveys, generalized words like Foundation
strengthening may require works like correction in deflections of well,
tilt, shift if any etc., very specialized teams having capabilities to work
underwater will be required, besides deployment of pontoons and
winch structures that will facilitate to carry out under water
rehabilitation works.

Under such circumstances, it is impossible for the contractor to


estimate cost and time implication for the rehabilitation works. Hence
the following suggestion is extended:

Option A

The rehabilitation work for Major Bridge shall be DELETED


from the present scope of work. It shall have to be assessed
in actual by the help of specialized agency and shall be invited
individually for rehabilitation of Major Bridge from the Bidders
with the specialized prequalification criteria having the due
experience related to rehabilitation in the field of such type of
water structures

Option B

Kindly give more specific details like execution drawings and


rehabilitation methodology assessed, designed, signed by a
competent authority as well as quantification of the type and
quantum of repair to be carried out. Construction period may be
revised accordingly. The contractors liability shall be limited
only to repairs carried out with respect to the execution
drawings and rehabilitation methodology given along with the
tender. The clear scope is required to be spelled out.
Sr. Description Query / Recommendation Clarification
No.

NOTE Composite scope i.e. development of highway +


rehabilitation ob bridge in the present Bid will be futile i.e.
incapable of producing any useful result. So, The rehabilitation
work for Major Bridge shall be DELETEDfrom the present scope
of work.

8 Schedule H -Major - The weightage in percentage to contract price of different Revised Schedule_H issued, pl. refer to
Bridge works and components of major bridge repair and widening are not given Addendum 1
ROB/RUB in schedule H
- Since huge cost and time implication is likely to happen, as
indicated in point no. 1, suitable separate provision for its
payment should be made.
- Please specify the percentage weightage of major bridge repair

9 Annex I Schedule - The available right of way is 30 m from 84+600 to 97+240 as Revised Schedule issued, pl. refer to
A (2) Land, Annex mentioned in the Annex I Schedule A and Appendix B-I, TCS Addendum 1 for corrected TCS-1, 2A, 2B
II of Sch. A (pg. A - 1, but ROW for these Chainages as specified in Annex II of Sch. & 3.
128),Appendix B-I, A (pg. A -128) is 15M to 18M only
TCS 1 - Kindly clarify the right of way available section wise

10 Para 5.3.3 ,Overlay - This provision obliges the contactor to provide minimum overlay RFP provision remains unchanged.
design under Annex (BM equivalent) of 200mm in section 1 and 185 mm in section
I , Schedule B 2, irrespective of quantum of deflection calculate based on BBD
Request to allow tests and actual traffic calculated as per the fresh traffic survey.
contractor to carry - This may translate to 40 mm BC and 100 mm DBM for section 1
out overlay design and 40 mm BC and 100 mm DBM in addition to profile
based and not fix correction course, which is huge wasteful cost for overlay.
minimum - Since Authoritys Engineer is going to review the pavement
requirements. design, it is suggested that instead of stipulating these minimum
overlay thicknesses design freedom to be given to contractor to
calculate the overlay requirements based on the actual
deflection and present traffic conditions.
- This will also result into economizing the project cost.
Sr. Description Query / Recommendation Clarification
No.
11 Article 17 clause - Article 17 stipulates defect liability period of 2 years , while the Not agreed, EPC agreement remains
17.1.1,Article 14 contractor has been obliged to maintain the project highway for unchanged
clause 5 years without any payment as per article 14.1.1. The clause
14.1.1,14.1.5 14.1.3 of the article obliged the contractor to hand over the
Maintenance project highway with less than 2500 mm /km which most
obligations and certainly will require either overlay or renewal coat of 40 mm BC
expenditure to be which has huge financial cost.
incurred prior to - It is not equitable that the contractor shall bear such a liability
project hand over under free maintenance and well beyond period of his defect
liability. In view of above it is required that either this provision
be removed or separate payment for it should be made.
- This is also not possible task to estimate the extent of such
damage and repairs needed beyond the control of the
Contractor. Hence the contractor will have to calculate the
maintenance cost of overlay design and include the
maintenance cost of five years in his current bid value.
12 Para 7.1.2 of Annex - In para 7.1.2 the proposed width of carriageway at Luni bridge Revised Schedule B issued, pl. refer to
I Schedule B, is shown as 12 m , in Appendix B V(b) , under improvement Addendum-1.
Appendix B V(b) proposal no width is specified for this bridge , and width of
Clarification in existing bridge is given as 7.7 m
width of Luni - The appendix under improvement proposal shall have the
Bridge. provision for the span arrangement and width of the structure as
given in para 7.1.2 may be mentioned to avoid disputes at later
stage

13 Appendix B V (b) - Under this provision a new minor bridge at Chainage 109+552 Land acquisition is under process.
new minor bridges (Luni bridge) is proposed. Milestones shall be readjusted at no cost to
Land required for - Please clarify whether additional land acquisition for the Govt. and without levying penalty to
approaches of construction of this bridge and its approaches has been carried contractor.
Luni Bridge out or not as it is likely to be located beyond the existing ROW
- The status of LAQ for this bridge shall be provided.
Sr. Description Query / Recommendation Clarification
No.
14 General(Estimation - Please inform the SOR rates for which year were used in SOR of 2015-16.
related) preparation of DPR

15 Annex IV Schedule - Schedule A shows that the forest clearance and tree cutting - In such case Milestones shall be
A, permission is likely to be achieved in about 6 months and readjusted at no cost to Govt. and
Schedule J (2) Bridge work can be started immediately. This implies that the without levying penalty to contractor
Rescheduling of construction of project road cannot be started during first 6
milestones based months of appointed date.
on realistic - In such a situation what is the sanctity of stipulating achieving
assessment. milestone 1 in 90 days and milestone 2 in 180 days
- These should be modified based on the realistic assessment of
likely time it may take to procure forest clearance and tree
cutting permission

16 Appendix B-I (2) - Drains shown in TCS 1 already exist at site The drains are existing and new drains are
Drain Section - Please Clarify whether new drain section is to be constructed? not to be constructed.
shown in TCS 1.
17 RFQ Clause no - Considering the number of clearances / utility shifting etc. to be Not agreed to. RFQ remains unchanged
1.1.1 provided by the Government as well as the scope of project
Request to revise which includes foundation strengthening of Agarwada Bridge
construction time and its bank protection works it is requested that the
limit construction time of 18 months fixed for Completion of Project
be increased to 30 months ; with the condition that detailed
scope for Major Bridge i.e. Agarwada shall be defined in the
BID.
Appendix 1: Snapshots of underwater videography
Appendix 1: Snapshots of underwater videography
SCHEDULE - H
(See Clauses10.1.4 and 19.3)

1. The Contract Price for this Agreement is Rs. _________ Cr.

2. Proportions of the Contract Price for different stages of Construction of the Project
Highway shall be as specified below:

Item Weightage in Stage for Payment Percentage


percentage to Weightage
the contract
price
Road works 86.73% A- Widening and strengthening of
including existing road including Junctions
culverts,
minor bridges, (1) Earthwork up to top of the
underpasses, sub-grade 15.90%
overpasses,
approaches to (2) Granular work (sub-base, base,
ROB/RUB/ shoulders) 22.12%
MajorBridges/
(3) Bituminous work 35.69%
Structures (but
excluding (4) Widening and repair / 1.37%
service roads) Reconstruction of Pipe culverts
(5) Widening and repair /
Reconstruction of Slab / Box 21.91%
culverts & minor bridges
B - New culverts, minor
bridges, underpasses,
overpasses on existing
road, realignments,
bypasses:
Minor Bridge 3.01%

Total 100.00%
Major Bridge 0%
works and
ROB/RUB

C- New Major Bridges


(1) Foundation
(2) Sub Structure

(3) Super Structure (including


crash barriers etc. complete)

Total 100.00%
Item Weightage in Stage for Payment Percentage
percentage to Weightage
the contract
price
Other works 13.27% 1. Road signs, markings, km 28.10%
stones, safety devices,
4.79%
2. Bus Shelters
3. Protection Works 60.31%

4. Restoration of existing major 6.80%


bridge

Total 100.00%

Total 100.00%

The above list is illustrative and may require modification as per the scope of the work.

Procedure of estimating the value of work done.

Road works including approaches to minor bridges, Major Bridges and Structures (excluding
service roads).

Procedure for estimating the value of road work done shall be as follows:

Stage for payment Percentage Payment Procedure


Weightage

A- Widening and strengthening


of existing road
(1) Earthwork up to top of the 15.90% Unit of measurement is linear length.
sub-grade Payment of each stage shall be made on pro
rata basis on completion of a stage in a length
(2) Granular work (sub-base, base, 22.12% of not less than 10 (ten) percent of the total
shoulders) length.
(3) Bituminous work 35.69%

(4) Widening and repair / 1.37% Cost of five completed culverts shall be
Reconstruction of Pipe culverts determined pro rata with respect to the total
number of culverts. Payment shall be made
on the completion of five culverts.

(5) Widening and repair / 21.91% Cost of each structure shall be determined on
Reconstruction of Slab / Box pro rata basis with respect to the total linear
culverts & minor bridges length of the minor bridges. Payment shall be
made on the completion of a minor bridge.
B - New culverts, minor
bridges, underpasses,
overpasses on existing
road, realignments,
bypasses:
Minor Bridge 3.01% Cost of five completed culverts shall be
determined pro rata with respect to the total
number of culverts. Payment shall be made
on the completion of five culverts.

@ For example, if the total length of bituminous work to be done is 100 km, the cost per km of
bituminous work shall be determined as follows:

Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)

Where
P = Contract Price
L = Total length in km

Similarly, the rates per km for stages (1), (2) and (4) above shall be worked out.

Procedure for estimating the value of Major Bridge / ROB / RUB done shall be as follows:

Stage for payment Percentage Payment Procedure


Weightage

C- New Major Bridges

(1) Foundation Cost of each Major Bridge


(widening and repairs)
(2) Sub Structure shall be determined on pro
rata basis with respect to
(3) Super Structure (including the total linear length (m) of the
crash barriers etc. complete) Major Bridges
(widening and repairs).
Payment shall be made on
completion of each stage
of a Major Bridge as per
the weightage given in this table.
Procedure for estimating the value of Other Works:

Stage for payment Percentage Payment Procedure


Weightage

Other Works
Road signs, markings, km stones, 28.10% Unit of measurement is linear
safety devices, length in km. Payment shall be
made on pro rata basis on
completion of a stage in a length
of not less than 10% (ten percent)
of the total length.

Bus Shelters 4.79% Payment shall be made on pro


rata basis for completed facilities.

Protection Works 60.31% Unit of measurement is linear


length in km. Payment shall be
made on pro rata basis on
completion of a stage in a length
of not less than 10% (ten percent)
of the total length.

Restoration of existing major 6.80% Payment shall be made on pro


bridge rata basis for completed bridges.

2 Procedure for payment for Maintenance

Deleted