Вы находитесь на странице: 1из 6

Time for Completion

The Contractor shall commence work on the Contract on a date to


be specified in a written order by the Employer acting through
the Engineer, and shall fully complete the work within the
time for completion stated in the Form of Tender from and
including the date thereof. The specified time for completion
shall be considered to include public, official, religious and
Information for Tenderers summer holidays.

FIDIC In order to assure the completion of the work within the time
stated in the Contract the Engineer reserves the right to order
the Contractor to employ more men or equipment or to
expedite the work in any way he may deem necessary.

The specified date for the Contractor to commence work


shall be no later than Sixty (60) calendar days from the
Engineer's order to commence work. In this respect allowance
of one month was considered necessary for the Contractor to
arrange the supply of the pipes and fittings and of the rest of the
materials for the purposes of the contract.

Time for Completion Substantial Completion of Parts of the Work


The Engineer shall give to the Contractor the order to As soon as, in the opinion of the Engineer, the
commence work not later than 15 days after the date of the Works or self-contained parts of the works, which can
execution of the Contract unless the Employer specifically
sanctions an extension of such period to 30 days. be put into operation as agreed by the Engineer, have
been substantially completed and have
satisfactorily passed any final test that may be
prescribed by the Contract, the Engineer shall, as
specified in Section 48 of the General Conditions, on
receiving a written undertaking by the Contractor
to finish any outstanding work during the Period of
Defects Liability, issue such Certificate of
Completion in respect of the Works, and the Period
of Defects Liability shall commence from the date
of such Certificate of Completion.

Progress Claims
Period of Defects Liability

The Period of Defects Liability, as specified in Section The Contractor shall submit to the Engineer, at the
49 of the General Conditions, shall be for a period of end of each calendar month, a fully itemized
78 weeks from the date of the Certificate of statement showing the estimated value of the
Completion, as specified in Section 48 of the General permanent work executed up to the end of the
Conditions. month. This shall be based on items and prices
shown in the Schedule of Items and Prices.

1
Liquidated Damages Liquidated Damages

In accordance with Section 47 (1) of the General Conditions, As specified in the Clause 47 of the General
should the Contractor fail to complete the works to the
satisfaction of the Engineer within the time for completion Conditions, deductions for Liquidated Damages due
specified in the Contract or the extended time allowed in may be made from any money in the hands of the
writing by the Engineer, the Contractor shall pay to the Employer, including retention money and Bank
Employer as liquidated damages the sum of Four Hundred Guarantees. However, deductions for this purpose
Cypriot Pounds (C400) in addition to the fees payable in shall not be made from retention money or Bank
respect of resident engineer(s) and inspector(s), for each
calendar day that the works remain uncompleted after the Guarantees until all funds available for work done
time so specified or allowed. have been used first.

The total amount of liquidated damages payable by the


Contractor to the Employer in accordance with Sub-Clauses
47(1) and 47(2) shall not exceed the maximum amount of
liquidated damages or 15 per cent of the Contract Price as
stated in the Form of Tender.

Temporary Advance for Mobilization


Sub-Contractors and Suppliers

The Tenderer shall give in sub-section 5 (i) of the An Advance in the amount of ten Percent of the
Form of Tender, the name and address of each Tender Price will be available to the Contractor on
proposed sub-contractor used in making up his submission of an irrevocable bank guarantee after
tender, stating the portion of the work allotted to execution of the formal contract. Repayment will begin
each. Only one sub- contractor shall be named for on the first payment certificate after the total work done
each part of the work to be sublet. on the contract reaches thirty per cent of the total
Tender Price. Repayment from then on will be in equal
Tenderers are also required to indicate in the Form monthly amounts so that it is all repaid by the end of
of Tender the manufacturers/ suppliers they the Time for Completion of the contract. Further details
propose for the supply of materials. are available in Clause 60.(J) of Conditions of
Contract, Part II - Conditions for particular Application.
After this tender has been accepted by the Employer,
the Contractor shall not be allowed to substitute
other sub-contractors or manufacturers in place of
those named in his tender without written approval
from the Engineer.

Quantities
Specifications
The Quantities as set out in the Form of Tender are estimates The specification includes many sections in order to cover all
only, and their inaccuracy shall in no way affect the validity of the
Tender or any contract based hereon. The total amount for the issues. It is divided into sections for example:
various items set out in the Form of Tender, at the rates of
prices inserted by the Tenderer, shall be stated in each case,
but this figure is required solely for the purpose of facilitating - Section 1: General Clauses
the comparison of the various Tenders received and shall not - Section 2: Clearing the Site
be deemed to be the actual sum which is to be paid to the
Contractor for the execution of the works. The actual sum to - Section 3: Excavation, Backfilling and Grading
be paid to the Contractor whose Tender is accepted will be - Section 4: Material supply and installation
determined by measuring work actually done in accordance
with the Contract and valuing it at the unit rates or prices - Section 5: Testing
inserted by the Contractor in the Form of Tender. - Section 6: Restoration and clean up
- Section 7: Concrete
The Bidders' attention is directed to the provision of Clause
52(3) of the Particular Specification under which the Employer - Section 8: Reinforcement
reserves the right to vary the sum of works by up to 15% of - Section 9: Payment
the total Contract Price.

2
To note:
In the specification sections the Engineer can specify:

the materials to be used,

the method to be used for a certain work

the requirements each material has to satisfy Specifications


the standards each material has to satisfy (European
Standard, Cyprus Standard, British Standard etc) Section 1 - General Clauses
which tests are required to be carried out

payment issues

etc

Drawings and Specifications Construction Schedule

The works are to be built of the materials and to the sizes, Notwithstanding Clause 14 of the General Conditions, the
dimensions and grades as called for in the Contractor shall, within thirty days from the date of the
Specifications and Contract Drawings and such other Letter of Acceptance of his tender submit his proposed
Drawings as may be added from time to time by the construction schedule to the Engineer for
Engineer during the progress of the work. approval. This construction schedule shall show clearly in
weekly stages the proposed progress on the main items,
These Drawings are the Contract Drawings and are made structures and sub-trades of the Contract and shall indicate
a part of this Contract. Additional drawings showing details where applicable the labour, construction crews, plant and
in accordance with which the work is to be constructed will equipment to be employed.
be furnished from time to time by the Engineer if found
necessary and shall then become a part thereof. The The Engineer may require the Contractor to revise his
Contractor shall be governed by figured dimensions, as proposed schedule at any time, as provided for in the
given on the Drawings. Where required dimensions are not General Conditions.
shown in figures, the Contractor shall obtain such portion of
the work to which they refer. In every case detail drawings
shall take precedence over general drawings. Where
Drawings are not consistent with the text of the
Specifications the text shall govern.

Hours of Work Hours of Work

No Sunday or Saturday work will be permitted except


The Contractor may normally perform the work during in the case of an emergency or if directed by the
normal working hours from Monday to Friday provided Engineer. As far as possible, the Contractor shall refrain
that he so conducts his operations as not to create from working on days which are legal holidays within the
nuisance or disturb the peace unnecessarily and providing area of the Contract. If he desires to work upon any
such hours meet with the approval of the such holidays, he shall request the written approval of
Engineer. Whenever the Contractor desires to depart the Engineer at least four (4) days in advance of such
from normal working hours he shall obtain the written holidays. If the Contractor fails to give notice in
approval of the Engineer at least forty-eight hours prior advance of any holiday or fails to obtain the Engineer's
to the contemplated change in operations. written approval for working thereon, such failure shall
be considered as notification that no work on this
Contract is to be done on such a holiday.

3
Hours of Work
Samples

Whenever, in the judgment of the Engineer, it may be In addition to any specific provision in the Contract for the
necessary or expedient to do work at night or on sampling and testing of materials, the Contractor shall
Sundays or on holidays or after or before the regular submit to the Engineer, as he may require, samples of
time of ending or beginning labour, such night or all materials and goods which he proposes to use or
overtime work shall be performed by the Contractor employ in or for the Works. Such samples, if approved,
without additional or extra cost to the Employer will be retained by the Engineer. No materials or goods of
beyond the price bid for the work. which samples have been submitted, shall be used in
the Works, unless and until such samples have been
approved in writing by the Engineer.

The Engineer may reject any materials and goods


which in his opinion, are inferior to the samples thereof
previously approved and the Contractor shall promptly
remove such materials and goods from the Site, at his
own expense.

Tests in General

The Engineer may examine and may require to be


tested any materials or goods required in or for the
Works such as he may decide from time to time. The
Contractor shall arrange for the Engineer to have
unrestricted access to the Contractor's, Sub-Contractor's
and suppliers' premises for such purposes at all times.
Specifications
Various clauses of the Specification state the types of
test which the Contractor shall carry out for the control
of the quality of the Works, together with the
frequencies at which each type of test shall be Section 2 Clearing the Site
conducted. The Contractor's attention is drawn to the
fact that the frequencies of testing specified in the
relevant clauses are intended to represent only a
general guide. The Engineer's Representative shall be
empowered to vary the frequencies at which tests are
conducted should he deem this necessary for the
proper control of the quality of the Works.

Disposal of Materials

All materials derived from the clearing,


demolition and grubbing operations shall
become the property of the Contractor and
shall be satisfactorily disposed of the site by
the Contractor at his own expense.
Specifications

Section 3 Excavation, Backfilling


and Grading

4
Bedding Materials
Bedding material shall be placed from 150mm below the invert of the pipe or 1/4 Excavated material
of the outside diameter of gravity pipe ODG for pipes greater than 600mm
diameter, to 300mm above the crown of the pipe in accordance with the
Drawings.
Bedding material shall be approved imported granular material and shall
conform to the requirements of Table 3.12.A and Table 3.12.B below.
SieveSize(mm) Percentage bymass passing(%)
80 100-100
SieveSize (mm) Percentage by mass passing(%)
56 98-100
25 100-100 40 80-99
12,5 75-99 20 50-90
6.3 47-87 10 30-75
1 15-75
4 15-60
1 0-35
0,063 0-15
0,063 0-15

Excavated material Section 8: Concrete


Work to be Done
No excavated material shall be used for backfilling
without the written approval of the Engineer following Under this Section, the Contractor shall supply all labour, materials, and
equipment to complete concrete work shown, and/or specified herein.
examination of the test reports of the excavated material. Unless otherwise stated, concrete shall be grade C30 expect benching to
Excavated material intended to be used for backfilling shall manholes which shall be C25.
be free from cinders, ashes, refuse, vegetable and organic
The specifications for concrete shall comply with Cyprus Standards, in particular
material. with CYS 111:1990, CYS EN 12620:2002-1551 (includes Cor. 1:2004), CYS
152 par 1:1986, CYS 153:1996 and CYS EN 12390-3:2002.
If following the conformity tests the excavated material is not
considered as suitable for backfilling by the Engineer, the
excavated material shall be transported and disposed of by Note: It is important apart from showing it in a drawing, to
the Contractor at the Contractors own expense to a disposal specify the requirements because as it is said earlier in the
site approved by the Local Authorities. Contract, if there is discrepancy, the Contractor shall use
If the excavated material is considered unsuitable for the specification and not the drawing.
backfilling, imported material shall be used, satisfying the
requirements of Table 3.13.A and Table 3.13.B with no
additional payment to the Contractor.

Section 8: Concrete Section 8: Concrete


Tests
Tests on concrete, Portland cement, and aggregates will be carried out
by the Employer at his expense, in accordance with B.S. 1881.
Aggregates
The Contractor shall provide samples of all materials, as required by the
Engineer.
Aggregates shall consist of natural sands and gravels, crushed rock, or
other inert substances having clean, uncoated grains of hard, strong,
Ingredients
durable, materials and conforming to CYS EN 12620:2002.
All concrete shall be composed of cement, fine aggregate, coarse
aggregate, admixtures, as required, and water in such proportions as
The Contractor shall notify the Engineer of the source of each kind of
may be approved or directed by the Engineer.
aggregate that he proposes to use, not less than three weeks in
advance of the concreting operations.
Cement
Cement shall be ordinary Portland Cement conforming to CYS EN 197-
The Engineer may request at any time from the Contractor, to perform
1:2000 Portland Cement.
such tests as to establish the conformity of the material used with CYS
Cement will be inspected and tested by the Engineer at his discretion.
EN 12620:2002.
Cement which has been rejected must be removed immediately by the
Contractor at his own expense.

5
Section 8: Concrete Section 8: Concrete
Concrete Mix Design

Mixes for the grades of concrete shown in the table below shall
be designed by the Contractor who shall take into account the
strength and durability requirements, the choice of
Water aggregates, the required workability and the specified finished
appearance of the concrete.
Water shall be of potable quality, clean and free from oil, acid, alkali,
organic matter or any other deleterious substance according to BS Concrete Specified Min cement Water/Cement Slump
EN 1008:2002 and shall be supplied by the Contractor at his own Grade characteristic Content ratio mm
Strength 28 day (kg/ m3) (max) (max)
expense. (N/mm2 )

The source of the water shall be subject to the Engineer's approval. C10 10 210 0,70 -
Non-potable water may be used only after approval by the C15 15 250 0,70 -
C20 20 290 0,55 80
Engineer. C25 25 320 0,55 80
C30 30 340 0,55 80

Section 9: Payment Section 9: Payment


UNIT RATES DEDUCTION FOR CONCRETE OF
Financial deductions in case the premix does not GRADE C10, C15, C20, C25, C30
comply
with he requirements of the technical specifications Definitions: a= Average Strength of four
consecutive test cubes
In case the premix slightly deviates from the specifications at 28 days, or the strength
and it is decided that it will be accepted, there will be
financial deductions which will be calculated by using the of any tests at 28 days which do not comply with the
following formula. Specifications according to Clause 8.15C. In the case
A = a2/100 . b . c . d . where where neither the average nor the individual strength
A = financial deductions comply with the specifications then a will be taken to
a = deviation from the technical specifications be the average strength.
b = coefficient which changes according to what deviates
from the specifications Ao= Percentage of the unit rate of concrete to
be deducted
c = purchase price of the premix per ton
d = quantity affected in tons
These financial deductions will consist of sums which should
not exceed 50% of the cost of premix. The coefficient -b-
can have the following values:

Section 9: Payment

C10 C15 C20 C25 C30


a a a a a
N/mm2 Ao % N/mm2 Ao % N/mm2 Ao % N/mm2 Ao % N/mm2 Ao %
12 0 17 0 23 0 28 0 33 0
11 7 16 7 22 3 27 3 32 3
10 10 15 10 21 6 26 6 31 6
9 17 14 17 20 10 25 10 30 10
8 25 13 25 19 17 24 17 29 17
7 35 12 35 18 25 23 25 28 25
6 49 11 49 17 35 22 35 27 35

Вам также может понравиться