July August
ID Task name Duration Start Finish
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1.0 Install Scupper Drain 5 days 20-Jul 24-Jul
1.1 Housing area 5 days 20-Jul 24-Jul
2.0 Earth Work 8 days 20-Jul 27-Jul
2.1 Housing Area 6 days 20-Jul 25-Jul
2.2 TNB Area 3 days 25-Jul 27-Jul
3.0 Anti Climb Fencing 7 days 27-Jul 2-Aug
3.1 Purchasing & Delivery 1 day 27-Jul 27-Jul
3.2 Installation 7 days 2-Aug 2-Aug
4.0 Walkway with Curb 6 days 2-Aug 7-Aug
5.0 Construct TNB Brick Wall 4 days 7-Aug 10-Aug
6.0 Road Pavement 2 days 11-Aug 12-Aug
7.0 Final Survey 1 day 13-Aug 13-Aug
8.0 Cleaning 2 days 13-Aug 13-Aug
9.0 Survey Drawing 1 day 20-Aug 20-Aug