Академический Документы
Профессиональный Документы
Культура Документы
FIELD INSTRUMENTATION
BY
W. L. DE GROFF
JHRP
JOINT HIGHWAY RESEARCH PROJECT
PURDUE UNIVERSITY AND
INDIANA STATE HIGHWAY COMMISSION
Interim Report
Respectfully submitted,
Harold L. Michael
Associate Director
HLM:ms
cc: W. Dolch
L. M. L. Hayes C. F. Scholer
R. Eskew
L. C. W. Lovell M. B. Scott
W. H. Goetz G. W. Marks J. A. Spooner
M. J. Gutzwiller R. D. Miles N. W. Steinkamp
G. K. Hallock J. W. Miller H. R. J. Walsh
R. H. Harrell G. T. Satterly E. J. Yoder
Digitized by the Internet Archive
in 2011 with funding from
LYRASIS members and Sloan Foundation; Indiana Department of Transportation
http://www.archive.org/details/compactedcohesivOOdegr
TECHNICAL REPORT STANDARD TITLE PAGE
1. Report No. ?. Government Accession No. 3. Recipient's Catalog No.
JHRP-2-73
9. Performing Organization Name and Address 10. Wort Unit No.
Joint Highway Research Project
Purdue University II. Contract or Grant No.
Civil Engineering Building HPR-lflOl Part II
West Lafayette, Indiana 47907 13. Type of Report ond Period Covered
12. Sponsoring Agency Name and Addres" Interim Report, Field
Indiana State Highway Commission Test Phase to Dec. 72
i4. Sponsoring Agency Code
CA 375
15. Supplementary Note*
In cooperation with the Department of Transportation, Federal
Highway Administration; Research Study Title "Long Term Deformation
of Clay"
16. Abstract
19. Security Closslf. (of this report) 20. Security Closslf. (of this page) 21. No. of Pages
by
W. L. De Groff
Purdue University
West Lafayette, Indiana
February 8, 1972
TABLE OF CONTENTS
Page
Summary ii
Introduction 1
Site Conditions 1
Field Instrumentation 2
Bench Marks 12
Piezometers 2k
Slope Indicators kk
References Cited 59
Bench Marks 60
Piezometers 63
Slope Indicator 65
SUMMARY
LIST OF FIGURES
Page
Figure
3. Piezometer Locations 5
Figure Page
Figure Page
verify the degree to which the procedures, developed from work to date,
report
state highway system. The test section is the area from Sta 789 + 00
to Sta 790 + 00 by 250 feet left and right of center line of state
SITE CONDITIONS
FIELD INSTRUMENTATION
contractor under the joint direction of ISHC and the Purdue personnel.
The sides of the model were of clear plexiglass; aluminum rods and
bars were used for pipes and trenches. The back side of the model and
The earth fill used in the test embankment was a locally available
scrapers (Figure 9). The fill was compacted, near optimum water
5
" o
(/>?
O O 0i
( 1 ?
1-
oe
1-
.2o
D
b
in Is
(M K E
o
in en
o
m in (A
3
in
E E
+ *f T>
E
3 3 3
0i
QC
0)
P
O
b 0>
5 s
1 1
2
i~
&
>> > 3
f
8s p p o <
CDW
in Si O
^_ 2 >.
o
u O 2-
in i/i
*"s-
o 11
<u P 01
in
in
</i
h to 1
>>
p_ in
>
E
o
O
* o Q
o 5 El
*i > >.
3 D
in
15?
So
m >
0)
S -o
c >.
o>
mo O >>
si
c
o cin
N 5>. i
2 o;t
2
coin coin
2
_ji/>
in
"" >>
c
2
O **
S 2
O ODU
=1
5^
Tn M III
w s mo
55
m E 15
^ 3 >l E*
+ i
52
l_ >.
|8
8 1,2 15
2
W E 5 &
coin o uu oin
Ofe
US o> o E
g-g o
ill E_
i$
SE
so
I* P
O ODU OQ
o o
o> co
o <
a:
a.
V)
i
N
o yj
o ffi
u.
o fc
to o
fU) UOJ40A3I3
550 r
540
530
520
+
p-ID p- 2D
Sta 789 + 70
c
510
o
D
> + + Sta 789 + 60
UJ p-i P-2 p-3 P-4
500 1
*
Sta 789+30
+ P-5 B
i
+ p -5A
480 -
P-6A
+
Sta 789+ 40
470 I L J i I
O
0> 3
<
o O
o 1-
o z
B
2
UJ
o
<
O U5
Ifi
Q
CM) U0IJDA3I3
fjj) J0JDA9I3
550
X 7/A^V7
540 2 777W?X$fr '
530
520
510
w 500
490
480
470 J u
789+00 789+20 789+40 789+60 789+80 789+100
Sta , Location
UJ
I-
o
z
<
I-
z
UJ
z
<
CD
ui
UJ
Q
O
I
00
UJ
o:
O
u.
iu
z
<
m
W
z
-J
D
<
I
i
0)
UJ
O
12,
are provided as guidance for others who may undertake similar field
studies. All such comments are subject to the caveat that they are
Bench Marks
Bozozuk et al (1962).
The bench mark is a datum rod which extends from solid base material
from within two feet of the datum rod base to ground surface. This was
the first item installed after obtaining soil samples. All following
installations were then referenced from the bench marks. The location
=
I I-
z
111
z
m
Ul
I-
li.
o
o
t-
u
2
z
8
I
g
UJ
DC
D
O
u.
)
Steel Cover
i r Berm Grade
About 3'
Compressible H
l /4 Galvanized Iron Pipe ( Coupled in Sections
Soil
Casing
Lifted 2 ft.
a Steel Foot
Refusal : Bedrock -
X
o
z
u
CD
CM
UJ
EC
16.
Figure 13, based on Bozozuk (1968), shows the spiral foot and a
to the surface. Figure lU shows the foot, casing and handle to turn
the foot into the soil. The gauge is installed by drilling a hole to
within six inches of the desired measurement depth. The gauge is then
down the inside of the datum pipe and out the holes above the foot,
filling the casing with oil. The subsoil was very soft at this
down the pipe first to help loosen any soil pushed in the pipe when it
was placed. Locations of the gauges are shown in Figures 2 and 7, and
embankment was constructed, the datum rod and casing were extended
lateral movement of a point within the fill. Steel plates were buried
is encased in tubing extending out of the fill (Figure 19) and enters
the instrument house at the side of the fill. The cable is pulled
.*
Sis
m
5
LU z
V)
(/)
o
< 1-
<
III J
U> -1
3 <
K
< tft
e>
i-
z
2 UJ
LU
s o
LU <
> u>
O 1-
2 z
o UJ
z
3
z
Ul
o J
a: 1-
1-
Ul
(A
1-
o
o
u.
-1
<
QL
Q.
<n
i
IO
*"**
UJ
D
O
U.
!*
UJ
CC
O
U.
UJ
CO
UJ
e>
D
<
o
i
_l
<
CC
0.
(A
u
0.
>
I-
I
UJ
CC
D
o
o
t
CO
o
Q.
u>
<
e>
O
o
<
e>
z
i
</>
<
i
LU
a:
O
li_
UJ
-I
m
<
o
o
8
I
t
UJ
UJ
Z
m
>
o
o
N
a:
o
i
i
UJ
ql
D
O
u.
Ui
>
O
c
UJ o "5
> Z
in 2 UJ
2
O 1/ IU
I
s
h-
z
UJ
Ql
D ^B- \zv\r*
z
f T\
0>
3
O
0_ Q.
c
6
-I
-I
0)
z z
UJ
u.
z Q o
< O
m
UJ
00 <
-I
x a.
Q
o <
0_ a:
UJ
z
> UJ
uo
in
o
I
a>
.Q
O c UJ
"C
o a:
en D
in
tt
O
u.
I
o
z
UJ
I-
Q
UJ
_l
_l
z
Ui
f"
I-
z
Ui
s
UI
>
o
p
z
o
N
QC
O
X
I
0)
UI
o
u.
2k.
cables coming into the instrument house from elevation 520 feet.
on the centerline.
house. The cables were brought up to the house via a pulley box
attempt was made to use the tubing in a curve and the friction was
large enough to prevent the cable from moving. The pull on the cables
and the size of the protective tubing should be increased when the
Piezometers
has a diaghragm between the pore fluid and air supplied under pressure
ball valve which is open when the return line pressure is lower than
FIGURE 20- STATION FOR READING DISPLACEMENT OF
HORIZONTAL MOVEMENT PLATES
Q.
D
</>
UJ
_l
CD
<
O
UJ
z
UJ
UJ
u
<
-J
0.
in
Q
z
o
N
o
I
UJ
1
o
z
or
muj
Is
ui
31
i
UJ
k
D
u.
27.
the pore pressure. When the return pressure equals the pore pressure
the ball valve is closed and the return line pressure is not allowed
in Figure 22. The supply and return line from the piezometer are
The supply and return lines are 1/8 inch nylon tubing, these
tubes are both encased in a 1/2 inch polyethene tube. Four piezometers
performance of these four suggested that two of the failures were due
to the 1/8 inch line being bent, and the other two were due to dirt
system and air supply tank. The toggle valve board to select a piezometer,
the air tank to pressure the input line, and the readout box are shown
in Figure 20.
The total pressure plates determine the average total normal pressure
a double diaphragm cell filled with oil (Figure 29). This cell is
loaded by the soil and the pressure developed goes to one side of a
<z
3 S2 o
z
1
O
5;
if)
V)
LlI
or 52 D
Q. 2
hi
UJ 4> <o
ft = to
o!
Q.
u. <
DC
HI
_l
U
GO 8 g Ui
PI Q. " S
O a 6? lip'
/>
C o
CL
N
UJ
a.
i
CM
CM
UJ
cc
u.
ID
2
CL
D
O
(U
3
O
O
<
UJ
g
o
UJ
I-
o
UJ
o
u
K
UJ
I-
UJ
o
N
UJ
Q.
I
10
(Si
UJ
or
D
O
u.
18 inches x 6 inches Sand Trench
Sand
.i :
o
hi
o
z
UJ
00
oc
111
I-
UJ
o
N
UJ
ID
CM
Ul
OC
O
U.
tu
Ul
z
o
N
UJ
3
O
QC
o
Ul
a:
3
O
0_
O
Z
UJ
m
o
z
<
!
I-
O
I
<0
CM
Ul
ce
D
O
u.
o
CO
UJ
LU
S
o
N
UJ
a.
z
o
o
CO
ffi
UJ
t
z
g
z
UJ
ffi
o
z
L
Q.
O
OC
O
i
N
CM
UJ
or
3
o
u.
<
id
ui
t
z
e
z
UI
ffi
o
z
I-
o
z
o
u
a:
UI
2
<
I
i
CD
CM
UI
O
U.
5
CD
UJ
UJ
o
UJ
or
</>
</>
UJ
a.
i
0>
M
UJ
DC
D
O
U_
.
36.
diaphragm cutting off flow from the input line to the return line;
when the input line pressure reaches the cell pressure the diaphragm
will open permitting flow to the return line. Thus, the maximum
indicated that the sand transmitted the pressure applied, and that
for elevation differences between the readout device and the cells
so that the complete stress field in the plane normal to the axes
in the fill, with the cells embedded in sand pocket to provide good
O
UJ
O
UJ
z
z
o
o
UJ
-I
Q_
UJ
or
3
(A
(A
UJ
or
0.
I
o
10
UJ
or
D
O
C
-I
-I
UJ
-I
Q.
uj
UJ
UJ
or
D
</>
(/>
UJ
o:
Q.
UJ
or
D
O
u.
I-
lli
u
o
0.
o
UJ
o
<
-I
<L
tu
Id
(A
(A
UJ
tfc
0.
5
J
Q.
s
iu
I-
i
CM
10
UJ
o:
D
O
u.
o
3
_l
li.
I
I-
UJ
z
UJ
<
UJ
tL
D
<n
UJ
or
q.
u.
i
10
10
UJ
DC
U.
<
(ft
>
CD
O
UJ
oc
UJ
>
o
o
(ft
UJ
Si
UJ
oc
(ft
(ft
UJ
oc
o.
i
10
UJ
oc
e>
u.
X
u
z
UJ
a:
o
z
CD
D
I-
IU
I-
<
-I
Q.
UJ
QC
(A
(ft
UJ
or
0.
ro
UJ
or
O
u.
UJ
z
UJ
I-
z
UJ
u
UJ
<
2
Q
Z
<
or
<
_j
U
o
z
Id
0.
or
UJ
0.
(A
UJ
-J
u
QC
z>
<A
</>
UJ
or
q.
x
i-
10
UJ
K
D
O
U.
kk.
Slope Indicators
bedrock, and socketed three feet into the rock. The tubing was
plumb line are taken at different elevations, one set parallel and
profiles with time are obtained. The profiles are compared to define
A six inch long sleeve is left between the 5 foot length so that
UJ
Q.
O
u.
UJ
-I
o
X
o
Q
00
IO
UJ
or
3
O
u.
UJ
<
ffi
fe
-I
<
UJ
UJ
>
UJ
I
o
<
g
e>
z
</>
<
o
I-
u
D
o:
l-
<n
z
o
o
o
z
a:
UJ
2
<
X
i
0>
10
UJ
or
u.
z
(A
<
O
QC
1U
Q.
3
(9
Z
I-
Ul
>
q:
q.
o
o.
i
o
iii
o:
D
O
FIGURE 41- PLACING PREASSEMBLED SLOPE INDICATOR CASING
IN HOLE .
FIGURE 42- READING SLOPE INDICATOR
51.
construction.
the tube to measure the head relative to the overflow elevation. From
The settlement tube was installed in a trench cut into the fill
as shown in Figure *5. After the tube was placed, the trench was
slope should be at least 1:100 to allow air to flow out when the
tube is filled with ethylene glycol. A second problem was the effect
the tube. The most difficult problem, was the effect of temperature
5 1-
3 UJ
111
I- J
LU
(/>
<
l/>
I
UJ
o
<
UJ
s
UJ
_!
I-
UJ
W)
u
-I
<
Q
>-
01 X
-D.9-
0Q_ -I
<
o
u
H c
0.
>-
C L_
o I
5 o a
> K)
o tn o> i
s_
0>_
<D I O o a> UJ
a:
or
D
O
in o ai
3 Ol
*
E
C'C ?
C Ql It:
U
q:lu=_
(/
eg
tt>
<D
Aluminum Pulley
' 1
A I
1
A
t
f
L
i
i
1 (
Scale
B-
PLAN
_l
uj
l-
u.
<
z
o
z
UJ
or
i-
UJ
O
ID
<
UJ
2
UJ
_l
I-
I-
UJ
</>
o
<
or
Q
>-
X
o
u.
o
<
m
i
UJ
or
D
O
u.
56.
Figure ^7.
instrument while readings are being taken within the body of the
is recommended.
w
ft
in
D
Hi
a.
z
o Hi
I-
-o
c I
a I-
ft
C o
o ft
ft
U UJ
a ft
E u
u
D
o
</>
.C
z
<
ft
<L>
m i
2 N
LU O
UJ
0) ft
.c D
I- O
U.
CO CM CD O
o o O O O
O O O
Idd} Ui J0JJ3
58.
subsequent project.
would be selected.
59.
REFERENCES CITED
Bozozuk, et. al, (1962), "Deep Bench Marks in Clay and Permafrost
Areas", Am. Soc. Testing Mater., Spec. Tech. Publ. 322, 1962.
APPENDIX
shown in Figure 9.
61.
2. The datum pipe with the foot attached and casing surrounding
was pushed to the bottom of the hole. For holes deeper than
6 feet water was pumped through the inner, and out the
k. S.A.E. #80 oil was pumped through the inner pipe and out the
ports at the bottom of the datum rod. The oil carries loose
shows the grease truck pumping oil down the datum pipe.
Figure 13.
h inch pipe casing and steel cap the same as shown for the
For the trench at elevation 520 the trench extends from the
vibrating compactor.
3. The wire cable was connected to the plates and threaded thru
h. The plate was pushed or hammered into the soil at the bottom
Figure 19. A tube carrying the wire from one other plate
is also shown.
shown in Figure 21. The cables are placed around the pulleys
compaction.
Installation of Piezometers
3. The casing was then cleaned out with a rotary bit until
5. The hole was filled with Ottawa sand to the piezometer tip
hour.
25.
piezometer.
a time.
6k.
15. Lengths of casing were remove until the top of the casing
16. The tubing was placed in an "S" pattern along the trench to
17. The trench was backfilled with sand, and the 1/8 inch tubes
with fluid (90$ Kerosene and 10$ oil) the top was pressurize
with the pump; the oil flows into the lines from the bottom.
65.
Each plate has its own input line but the out lines return
32.
5. The Plates were covered with sand, Figure 3 1*, and the sand
was compacted.
10. The remaining portion of the pit was backfilled with fill
at the base.
.
66.
h inch
3. A rock auger was put down the casing to drill a
back into the hole, the toe of the casing will catch the
rivets
3. A one inch P.V.C. tube was laid on the bottom of the trench
and extended out the ends. The two trenches below berm
truck was used to blow the stopper thru the tube. The wire
68.