Академический Документы
Профессиональный Документы
Культура Документы
PROJECT COMPLETION
REPORT
SWS Consultancy
May, 2017
Bahir Dar, Ethiopia
Project Completion Report Abbay-3 SSIP
Project : Abbay-3 Small Scale Irrigation Project
Employer : ANRS-Water Resources Development Bureau
Consultant : SWS Consultancy
Contractor : Hamere Noah Construction
Ref. : Project Completion Report
Date : May 31, 2017
1. Project Background
Abbay-3 small scale irrigation project is one of the projects under Agriculture
Growth Program (AGP), which is located in Amhara region, Bahirdar zurya
Wereda at Huletu Yegomiya and Maj Debre Negest Kebele. The project is
designed for the development of 1,388 hectares of irrigable land. The water
resource of this project is Abbay River using the intake structure by diverting
the water on the right side of the river bank.
This irrigation project includes Diversion weir head work structure and its
appurtenant parts, irrigation infrastructure network and other structures.
Based on the site prevailing conditions design review work was done in a
manner to accommodate the design flow against the original dimension, flood
protection work and irrigation layout based on topography, social and right of
way and economy. Hence, the following design review work is done:-
The original approach canal design depth which is 0.70m is not adequate
to accommodate the discharge (2m3/s) flowing in the canal. Modification
is done to accommodate the discharge and to fit with the site conditions.
Flood protection design work is done which was not considered in the
previous design.
Design work was done for vertical and inclined drop structures on main
canal.
Finally, all the design approaches, analysis, cost comparison and all the
necessary drawings including conclusion and recommendations are presented
after approval by the client and attached herewith in the annex part.
2. Project Information
2.1 General
The contract agreement for the construction of Abbay- 3 small scale irrigation
project was signed between the employer, ANRS, Water, Irrigation and Energy
Development Bureau the contractor, Hamere-Noah Construction, on the 30 th of
August, 2013. The following table shows the detail information of the project.
3. Project Status
3.1 Technical Performance
The design work of the project for main canal, overflow canal and related
structures along main canal has been completed and submitted.
Major Structures
Flume structures
At Liba river
At Mendel River
Box Culvert
B. Financial Performance
The financial status of the project is calculated using the above table description
of cost of each item of works. So the financial progress of this project is 112.72%
against the original contract amount that all the activities done up to May 31 st
2017.
Executed works of Abbay-3 SSI project for each item of works are paid the
contractor up to the end of May 2017 as shown table below. All the advance
payment was repaid by deducting proportionate amounts from contractors
payment.
3. Outstanding Activities
i. Excavation, cart away, masonry work and concrete works on head work
structures at cut off and diverting canal.
ii. Excavation, cart away, masonry work, plastering and concrete works in
the irrigation system infrastructure works at main canal, division box,
drops and pass ways. But nothing done in the secondary canal, tertiary
canal and turn outs.
iii. Excavation, cart away, masonry work and concrete works on the flume
structures at CH 6+024, Yeshemat and Yedokit rivers.
The remaining outstanding items of works are listed based on each item of
works based on the contract.
Bill No.1 General Item.
Demobilization,
Sign indication poster,
Provision of as built drawing for the project.
Bill No. 2 Headwork Structures
2.1 Diverting Canal
9. Flume Structure
No any activity done at Ch 6+024, Yeshemat and Yedokit rivers.
10. Crossing Structure for Irrigation Water across Main Canal at Different
Locations
There are existing canals which crosses the main canal. At these sections
crossing structures required but not done till now. There is also floods in
the right side of the main canal which requires drainage structures to
protect the flood that interrupts the function or damages the main canal
3. Major Problems Encountered
3.1 Major Problems
Right off way problems
There were right of way problems on the main canal local as the
canal passes through local peoples land and their houses. There
was still construction area that has not got a solution due to this
right off way problem.