Академический Документы
Профессиональный Документы
Культура Документы
Introduction
Off shore wind farming has become viable as well as proven technology both in Europe and China
lately because of higher plant load factor (PLF) when compared to the PLF of wind farms on land.
Moreover, the availability of land areas with good winds are reducing in our country, and also it is
becoming increasingly challenging for the acquisition of land, logistic management together with the
power evacuation. The land issues onshore no doubt adds to the capital and operational cost and also
reduces the growth rate of installation/ commissioning. In offshore, there are advantages of a calm ,
steady and less turbulent wind flow, conducive to wind electric power operation with occasional perils
of storms and cyclone which pose challenges to the design and development of off shore wind farms
International status
Globally Europe has a strong position in the market sector: worldwide, the European wind turbine
manufacturing industry has a market share of 80%,and for offshore this rises to 100%. The North Sea
Region in Europe is the global leader in offshore wind(see Fig.1), both in installed(1515 MW as on
Sept 2010) and planned capacity and capability. If the offshore wind market in the EU grows by the
same rate as its on shore industry, 50 GW of offshore wind power will be operating in Europe by 2020.
Recent advances in bankable technologies in offshore wind energy, specifically in Europe which has
about 948 off shore wind turbines with a total installed capacity of 2396 MW have made it possible to
apply the same technologies in countries like USA, India and China. World over, there are about
4464MW of offshore wind power projects either pending or under various stages of execution in
Denmark (386MW), Germany (400MW), Netherlands (280MW), UK (2630MW), USA (468MW) and
China (300MW). Even as technology leaders, Germany is successfully commissioning its first wind
farm offshore this year, after a decade of hard work. While China has already successfully installed 102
MW(34 nos x 3 MW), but India, by virtue of being second largest supplier of carbon credits (CRR) after
China, is seriously looking forward for possible offshore wind farm development.
Page 1 of 10
Fig. 1 Installed and planned capacities of Offshore Wind Power in Europe
Fig. 2 Table of measured wind resource data along some ports in the Indian coast
Page 2 of 10
Fig. 3 Probability distribution of wind speeds and direction (wind rose) on the ports
Page 3 of 10
Fig. 4 CWETs wind resource measurements at Dhanuskoti (Rameshwaram) using mast and SODAR
C-WET has undertaken preliminary studies using SODAR (Fig.4) near Dhanushkodi (Rameshwaram),
which is a narrow piece of land jutting towards Sri Lanka and the preliminary measurements indicate
wind speeds ranging from 6-27 m/s. Accordingly C-WET has decided to install a 100 m mast at
Rameshwaram, Ramanathapuram District in Tamilnadu with an objective to further examine the
feasibility (wind speed/ direction) of setting up of offshore wind farm in and around the long stretch
jutting towards Sri Lanka. CWET also measured wind resource at cape of Kanyakumari (Fig.5)
Based on the earlier recorded observations and to further gain confidence on the results, C-WET has
also signed an MoU with Riso / DTU to undertake satellite based assessment at Kanyakumari, Gulf of
Mannar, and Rameshwaram. The idea is to collect wind data above the sea surface and convert the
same to 10 m height to assess the offshore wind potential in the said location using synthetic aperture
radar (SAR) technique using satellite imageries. C-WET is also planning to undertake LIDAR
(Laser/Light Detection and Ranging) measurements which will be suitable for SAR-data validation
along the height.
Page 4 of 10
MNRE/C-WET has special collaboration with Scotland for offshore wind power project development in
India and critically discussed the relevant issues with all stake holders during a one day Indo-Scottish
workshop at C-WET, Chennai. There is growing interest among the public sector companies like NTPC,
ONGC, IOCL to assist and get associated with offshore wind power projects, in addition to a private
company called Green Shore Energy Pvt. Ltd., from Bengaluru. and M/s Suzlon, Indias major market
player onshore have also evinced keen interest in offshore projects in India.
Page 5 of 10
3. Grid constraints and Power evacuation
A review of the grid connection options will have to be performed based on distance of land
to offshore, with cable route options, technical options (AC/DC) and information collected
from EB/utility. It is not only the sub- sea cabling to transmit power to land which needs to be
addressed, but also the up-scaling of the existing transmission/distribution system needs
serious attention.
4. Construction strategies
Construction of offshore wind farms is significantly more complex than an equivalent on shore
project. Issues that need to be reviewed are;
Foundation requirements appropriate to water depths
Piling capacities and equipment for different sub-marine soil conditions
Special Vessel requirements for transporting for large fabricated
segments/components from shore
Weather windows and all weather compliant floating erection cranes and skilled team.
location of suitable ports for construction and operation for continuous logistic
support
This will allow resources and efforts to be concentrated on the most advantageous regions of
India's coastline. Accurate wind resource offshore may have to be carried out by even
private/public developers and later vetted/verified by Government Agencies to kick start
offshore wind power projects.
Page 6 of 10
For assessment of the aforementioned factors(Sl. no. 1 to 6), a Detailed Project Report has to
be prepared based on access to relevant data sources for wind resource, technical and
environmental constraints together with grid constraints. The developmental aspects towards
aforesaid activities will involve knowledge pooling from our research institutions like National
Institute of Oceanography (NIO), Goa and INCOIS Hyderabad for oceanographic studies, Data
acquisition , collation and correlation and National Institute of Ocean Technology (NIOT),
Chennai for subsea structures like Foundations, Submersible Cable Laying etc.
These technical aspects can be studied with inputs received as a core for policy formation with
a set of procedures for single window clearance of projects without which the development
can neither be fast nor continuous. Such clearance under single window approach has been
proved to be highly successful in the North sea and UK and European specially German
offshore wind power project developments recently.
Maritime/fishing activity
Cyclonic frequencies
Page 7 of 10
A STRONG POLITICAL WILL & GOVT. POLICY
Need for multi-mega watt (100s of MW) projects for economy in scale.
Prioritise the indigenous development even during the feasibility study stage
Evaluation of possible concepts and innovative designs for its suitability to India-specific
conditions including risks associated with Political/ Economical/societal/ tropical
meteorological/ topographical/ geological/technological/ecological/ environmental/ for
SUSTAINING SUPPLY CHAIN OF ALL MATERIALS/COMPONENTS/SYSTEMS FOR RELIABILITY
of offshore WEGs.
Page 8 of 10
Annexure-1
Page 10 of 10