Академический Документы
Профессиональный Документы
Культура Документы
Summary: The effectiveness of the intended tank balance lines was investigated by performing
simulations to determine the effect of upstream transients on the dehydration tank levels. A number of
upset operating cases were simulated at both 17% and 35% WC and maximum tank level variations
calculated. The results show that the current design is adequate when compared to operating with two extra
hypothetical oil and water balance lines.
purposes
1. INTRODUCTION
dh
At = Fo F (2)
dt
4. MODELLING ROUTE
Dynamic tank level modelling was carried out using the high
fidelity hydraulic simulator TLNET, which is a component
of Energy Solutions Pipeline Studio V 3.0. The following
assumptions are made for the transient simulation:
Fig 1.Dehydration Tank Balance Lines Tank internal pressures are the same (i.e. The gas
vapour balance line has not been modelled)
Emulsion
14.8
Tank60A_Oil_Outlet
14.6
14.4
14.2
Pipe0026
14.0
M
13.8
P-060A/B/D/E
13.6
Pipe0001
Pipe0027
13.4
13.2
13.0
Tank60B_Oil_Outlet
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
used. 14.8
14.6
No hydraulic verification has been performed on the
inlet lines upstream of the dehydration tank, i.e. it is assumed 14.4
14.0
13.6
manifold. The two segregated production trains (A and B) 0 500 1000 1500 2000 2500
Elapsed Time (seconds)
3000 3500 4000 4500 5000
F
with crossover line valves closed is the normal expected
operating scenario. However, other scenarios, where the
crossover valves are open, have also been simulated. Fig. 3. Case A: TK-60B dynamic level variation
TK-60A_Emulsion TK-60B_Emulsion
Under these conditions, the maximum difference in level is
approximately 0.4m. Further tank level equalisation could be
Tank60A_Oil_Outlet
Pipe0026
P-060A/B/D/
Pipe0001
Tank60B_Oil_Outlet
Blkv0002
Pipe0017 Pipe0018 Tank60A_Water_Outlet
Pipe0012
Pipe0029
5.2 Case B Offshore Flow Disruption- Emulsion Balance
Supply0004
Pipe0016
Pipe0003
Pipe0030
P-066A/B Line Operational-17% Water Cut
Blkv0001
Pipe0013 Pipe0014 Pipe0015 Tank60B_inlet
Tank60B_Water_Outlet
At the start of the simulation the offshore rate to train A is cut 14.2
M
14.0
to only 80,000 BPD, train B maintains 182,500 BPD. The
13.8
initial tank level is 15m. Oil outlet nozzles have been set at
13.6
13m, and water outlet nozzles at 3m. The total dynamic 13.4
simulation run time is one hour and twenty minutes under 13.2
these condition. The results presented below do not include 13.0
the use of the 6 emulsion balance line. 0 1000 2000 3000 4000 5000
Elapsed Time (seconds)
14.96
M
14.95
5.3 Case C Offshore Flow Disruption- Two Additional
14.94
Balance Lines - 17% WC
14.93
14.92
This case follows the same operational scenario as A and B.
14.91
Two additional 24 balance lines have been provided at 12m
14.90
and 1m. 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
15.07
14.0
15.06
13.8
15.05
M
13.6
15.04
13.4
15.03
13.2
15.02
0 1000 2000 3000 4000 5000 15.01
Elapsed Time (seconds)
15.00
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
Fig. 6. Case C: TK-60A dynamic level variation
Fig. 8. Case D: TK-60B dynamic level variation
TK-60B
Tank Level Variation
15.0 5.4 Case E Train A to Train B Crossover Valve Open
14.8 Additional Balance Lines -17% Water Cut
14.6
14.4 The assumed scenario is the same as Case D, however two
14.2 additional balance lines at 12m and 1m have been included.
M
14.998 14.98
14.996 14.96
14.94
14.994
14.92
14.992
M
M
14.90
14.990
14.88
14.988
14.86
14.986
14.84
14.984 14.82
14.982 14.80
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds) Elapsed Time (seconds)
Fig. 9. Case E: TK-60A dynamic level variation Fig. 11. Case F: TK-60A dynamic level variation
TK-60B TK-60B
Tank Level Variation
Tank Level Variation
15.018
15.20
15.016 15.18
15.014 15.16
15.012 15.14
15.010 15.12
M
15.008 15.10
15.08
15.006
15.06
15.004
15.04
15.002
15.02
15.000
15.00
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds) 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
Fig. 10. Case E: TK-60B dynamic level variation Fig. 12. Case F: TK-60B dynamic level variation
Tank levels equalize rapidly within 500 seconds with a slight
and insignificant offset. As can be seen from the simulation results, the maximum
difference in tank level is 0.4m whilst operating under these
5.5 Case F Train A to Train B Crossover Valve Open conditions. The dynamic simulation results show that the
35% Water Cut level-flow cascade controller averaging these two levels
should still send the same signal to the existing flow
controllers thus allowing the desalter rate to be maintained.
This simulation scenario is based on 35% water cut or a total
offshore rate of approximately 467,000 BPD. It is expected
that this case represents the worst case conditions in terms of 5.6 Case G Train A to Train B Crossover Valve Open
tank level unbalancing. During transient conditions, Additional Balance Lines -35% Water Cut
dehydration tank A receives 80,000 BPD, whilst tank B
receives 387,000 BPD. The flow re-routing is carried out in The final case, simulates two 24 hypothetical balance lines
by opening only one MOV and throttling the PCV on the at 12m and 1m. The implemented dynamic disruption is the
inlet of dehydration tank A. same as case F.
TK-60A
Tank Level Variation
15.000
14.995
14.990
M
14.985
14.980
14.975
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
TK-60B
Tank Level Variation
15.025
15.020
15.015
M
15.010
15.005
15.000
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
Elapsed Time (seconds)
6. CONCLUSIONS