DAFTAR HARGA SATUAN

BAHAN DAN UPAH TAHUN 2012


A. DAFTAR HARGA SATUAN BAHAN/PERALATAN

NO. JENIS BAHAN BANGUNAN SATUAN HARGA (Rp.)

1 Semen PC 50 Kg Zak 93,225.00


Semen PC 50 Kg Kg 1,864.50
Semen PC 50 Kg Tong 326,287.50
2 Semen Putih Kg 11,526.00
3 Semen Warna Kg 17,176.00
4 Pasir Urug/Timbunan M 84,750.00
5 Pasir Pasang M 84,750.00
6 Pasir Beton M 84,750.00
7 Tanah Timbunan M 70,625.00
8 Kerikil Bersih/Koral M 339,000.00
9 Kerikil Halus ( -1 cm) M 339,000.00
10 Batu Pecah (1 - 2 cm) M 339,000.00
11 Batu Pecah (2 - 3 cm) M 282,500.00
12 Batu Pecah (3 - 5 cm) M 282,500.00
13 Batu Pecah (5 - 7 cm) M 282,500.00
14 Batu Pecah (10 - 15 cm) M 141,250.00
15 Batu Gunung M 113,000.00
16 Batu Kali M 113,000.00
17 Batu Kali 15 cm M 113,000.00
18 Kawat Beton (Bendrat) Kg 28,476.00
19 Minyak Bekisting Ltr 6,500.00
20 Besi Beton Polos < 12 mm Kg 16,500.00
21 Besi Beton Polos > 12 mm Kg 16,500.00
22 Tegel Keramik Kasar 40 x 40 cm Bh 20,800.00

NO. JENIS BAHAN BANGUNAN SATUAN HARGA (Rp.)

23 Balok Kls. I M 3,390,000.00


24 Papan Kls. I M 2,599,000.00
25 Balok Kls. II M 1,638,500.00
26 Papan Kls. II M 1,638,500.00
27 Balok Kls. III M 1,525,500.00
28 Papan Kls. III M 1,525,500.00
29 Kayu Dolken 8 cm Btg 12,500.00
30 Plywood t = 9 mm Lbr 149,500.00
31 Paku Campuran 5, 7, 10, 12 cm Kg 18,419.00
B. DAFTAR UPAH PEKERJAAN

NO. URAIAN SATUAN HARGA (Rp.)

1 Pekerja Org/Hari 57,850.00


2 Tukang Kayu Org/Hari 77,975.00
3 Tukang Batu Org/Hari 77,975.00
4 Tukang Cat Org/Hari 77,975.00
5 Tukang Besi Org/Hari 77,975.00
6 Tukang Listrik Org/Hari 77,975.00
7 Tukang Pipa Org/Hari 77,975.00
8 Tukang Las Org/Hari 77,975.00
9 Kepala Tukang Org/Hari 88,250.00
10 Mandor Org/Hari 68,050.00
11 Operator Org/Hari 57,850.00
12 Pembantu Operator Org/Hari 52,300.00
13 Supir Org/Hari 57,850.00
ANALISA HARGA SATUAN PEKERJAAN

4. Menggali 1 m3 tanah biasa sedalam 1 meter (SNI 6.1)


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I TENAGA
1 Pekerja Oh 0.7500 57,850.00 43,387.50
2 Mandor Oh 0.0250 68,050.00 1,701.25

Jumlah 45,088.75
Total Jumlah 45,088.75

12. Urugan Kembali (SNI 6.9)


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I TENAGA
1 Pekerja Oh 0.1920 57,850.00 11,107.20
2 Mandor Oh 0.0190 68,050.00 1,292.95

Jumlah 12,400.15
Total Jumlah 12,400.15

15. Mengurug 1 m3 pasir urug


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Pasir Urug M 1.2000 84,750.00 101,700.00

II TENAGA
1 Pekerja Oh 0.3000 57,850.00 17,355.00
2 Mandor Oh 0.0100 68,050.00 680.50

Jumlah 119,735.50
Total Jumlah 119,735.50
ANALISA HARGA SATUAN PEKERJAAN
20. Memasang 1 m3 pondasi batu belah, campuran 1 PC : 4 PP (SNI 6.2)
Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Batu Gunung M 1.2000 113,000.00 135,600.00
2 Semen Portland Kg 163.0000 1,864.50 303,913.50
3 Pasir Pasang M 0.5200 84,750.00 44,070.00

II TENAGA
1 Pekerja Oh 1.5000 57,850.00 86,775.00
2 Tukang Batu Oh 0.6000 77,975.00 46,785.00
3 Kepala Tukang Oh 0.0600 88,250.00 5,295.00
4 Mandor Oh 0.0750 68,050.00 5,103.75

Jumlah 627,542.25
Total Jumlah 627,542.25

32. Memasang 1 M Plesteran 1 Pc : 4 Ps t = 1,5 cm (SNI 6.4)


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Semen Portland Kg 6.2400 1,864.50 11,634.48
2 Pasir Pasang M 0.0240 84,750.00 2,034.00

II TENAGA
1 Pekerja Oh 0.2000 57,850.00 11,570.00
2 Tukang Batu Oh 0.1500 77,975.00 11,696.25
3 Kepala Tukang Oh 0.0150 88,250.00 1,323.75
4 Mandor Oh 0.0100 68,050.00 680.50

Jumlah 38,938.98
Total Jumlah 38,938.98

35. 1 M Pekerjaan Rabat Beton 1 Pc : 3 Ps : 5 Kr (SNI 6.1)


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Semen Portland Kg 218.0000 1,864.50 406,461.00
2 Pasir Beton M 0.5200 84,750.00 44,070.00
3 Batu Pecah (2 - 3 cm) M 0.8700 282,500.00 245,775.00

II TENAGA
1 Pekerja Oh 1.6500 57,850.00 95,452.50
2 Tukang Batu Oh 0.2500 77,975.00 19,493.75
3 Kepala Tukang Oh 0.0250 88,250.00 2,206.25
4 Mandor Oh 0.0800 68,050.00 5,444.00

Jumlah 818,902.50
Total Jumlah 818,902.50
ANALISA HARGA SATUAN PEKERJAAN
1 m3 Membuat Plat beton bertulang (100 Kg besi + Bekesting) (SNI 6,32)
Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Kayu Kelas III M 0.3200 1,525,500.00 488,160.00
2 Paku Campuran Kg 3.2000 18,419.00 58,940.80
3 Minyak Bekisting Ltr 1.6000 6,500.00 10,400.00
4 Besi Beton Polos Kg 107.0000 16,500.00 1,765,500.00
5 Kawat Beton Kg 2.2500 28,476.00 64,071.00
6 Semen Portland Kg 336.0000 1,864.50 626,472.00
7 Pasir Beton M 0.54000 84,750.00 45,765.00
8 Batu Pecah (2 - 3 cm) M 0.81000 282,500.00 228,825.00
9 Kayu Balok III M 0.12000 1,525,500.00 183,060.00
10 Plywood 9 mm Lbr 2.00000 149,500.00 299,000.00
11 Dolken 8 cm - 4 m Btg 16.00000 12,500.00 200,000.00

II TENAGA
1 Pekerja Oh 5.3000 57,850.00 306,605.00
2 Tukang Batu Oh 0.2750 77,975.00 21,443.13
3 Tukang Kayu Oh 1.3000 77,975.00 101,367.50
4 Tukang Besi Oh 1.0500 77,975.00 81,873.75
5 Kepala Tukang Oh 0.2650 88,250.00 23,386.25
6 Mandor Oh 0.2650 68,050.00 18,033.25

Jumlah 4,522,902.68
Total Jumlah 4,522,902.68

50. 1 M Pekerjaan Lantai Keramik 40 x 40 cm (SNI 6.10)


Harga Satuan Jumlah
No. : Uraian Satuan Kuantitas
(Rp.) (Rp.)

I BAHAN
1 Keramik Kasar Bh 6.6300 20,800.00 137,904.00
2 Semen Portland Kg 9.8000 1,864.50 18,272.10
3 Pasir Pasang M 0.0450 84,750.00 3,813.75
4 Semen Warna Kg 1.3000 17,176.00 22,328.80

II TENAGA
1 Pekerja Oh 0.2500 57,850.00 14,462.50
2 Tukang Batu Oh 0.1250 77,975.00 9,746.88
3 Kepala Tukang Oh 0.0130 88,250.00 1,147.25
4 Mandor Oh 0.0130 68,050.00 884.65

Jumlah 208,559.93
Total Jumlah 208,559.93
DAFTAR KUANTITAS DAN HARGA
HARGA PERKIRAAN SENDIRI (HPS)
KEGIATAN : Pembangunan Drainase Kab. Halmahera Utara
PAKET : Pembangunan Drainase Dalam Kota Tobelo
LOKASI : Dalam Kota Tobelo
TAHUN ANGGARAN : 2013

I. PEKERJAAN PERSIAPAN/PEMBERSIHAN
1 Pek. Pemberishan, Pematangan Lahan dan Pembongkaran
1 Ls Rp. 65,000,000.00 Rp.
Saluran Lama
2 Pemasangan Bowplank 1 Ls Rp. 5,000,000.00 Rp.
3 Papan Nama Proyek 1 Ls Rp. 500,000.00 Rp.
4 Dokumentasi dan Pelaporan 1 Ls Rp. 5,000,000.00 Rp.
Rp.
II. PEKERJAAN DRAINASE
1 Pekerjaan Galian Tanah 1,056.00 M3 Rp. 45,088.75 Rp.
2 Urugan Tanah Kembali 264.00 M3 Rp. 12,400.15 Rp.
3 Urugan Pasir di bawah 56.32 M3 Rp. 119,735.50 Rp.
4 Pas. Batu Untuk Drainase 1 PC : 4 PP 436.48 M3 Rp. 627,542.25 Rp.
5 Pek. Plesteran Drainase 1 PC : 3 PP 1,858.56 M2 Rp. 38,938.98 Rp.
Rp.
III. PEKERJAAN TROTOAR
1 Pek. Plat Beton 118.27 S Rp. 4,522,902.68 Rp.
2 Pek. Cansteen 1,408.00 M1 Rp. 120,000.00 Rp.
3 Pek. Rabat Beton 49.28 M3 Rp. 818,902.50 Rp.
4 Pas. Keramik Kasar 40 X 40 985.60 M2 Rp. 208,559.93 Rp.
Rp.
IV. PEKERJAAN LAIN-LAIN
1 Pek. Griell 18.02 M2 Rp. 550,000.00
Rp.
REKAPITULASI
DAFTAR KUANTITAS DAN HARGA
KEGIATAN PROYEK : Pembangunan Drainase Kab. Halmahera Utara
PAKET PEKERJAAN : Pembangunan Drainase Dalam Kota Tobelo
LOKASI : Dalam Kota Tobelo
TAHUN ANGGARAN : 2013

I. PEKERJAAN PERSIAPAN/PEMBERSIHAN Rp.

II. PEKERJAAN DRAINASE Rp.

II. PEKERJAAN TROTOAR Rp.

IV. PEKERJAAN LAIN-LAIN Rp.

REAL COST Rp.


PPN 10 % x REAL COST Rp.
JUMLAH TOTAL/PERMETER Rp.
Rp.

Tebilang :

Drainase Dimensi
Lebar Atas 1 meter
Lebar Bawah 60 centi meter
Tinggi 1 meter

STRUKTUR
pekerjaan drainase 403,910,934.91
pekerjaan trotoar 949,804,922.46
1,353,715,857.37

/meter 192,289

Pejabat Pembuat Komitmen


Bidang Cipta Karya II
Dinas Pekerjaan Umum Kab. Halmahera Utara

JOHNY LABADA, ST. M.Si


Nip 19750508 200604 1 010
UANTITAS DAN HARGA
RKIRAAN SENDIRI (HPS)

65,000,000.00
5,000,000.00
500,000.00
5,000,000.00
75,500,000.00

47,613,720.00
3,273,639.60
6,743,503.36
273,909,641.28
72,370,430.67
403,910,934.91

534,932,745.18
168,960,000.00
40,355,515.20
205,556,662.08
949,804,922.46

9,912,320.00
9,912,320.00
REKAPITULASI
UANTITAS DAN HARGA
b. Halmahera Utara

75,500,000.00

403,910,934.91

949,804,922.46

9,912,320.00

1,439,128,177.37
143,912,817.74
1,583,040,995.10

Pejabat Pembuat Komitmen

Dinas Pekerjaan Umum Kab. Halmahera Utara

JOHNY LABADA, ST. M.Si


Nip 19750508 200604 1 010
p 704 Type 1 m

galian la lb
1.2 1.25

1.5
1056
1056

pasangan batu
1.15
1.15
0.8
panjang 3.1
tebal 0.2 0.62 436.48

pasir urug
0.08
56.32
plesteran
1.02
1.02
0.6
2.64
1858.56

Plat
0.168
118.272 m3
keramik
1.4 985.6 m2

rabat 0.07 49.28 m3

cansten 2 1408 m1

griil 0.64
bh 28.16 18.0224 m2