Академический Документы
Профессиональный Документы
Культура Документы
Paul Handley
To cite this article: Paul Handley (1997) A Critical View of the Build-Operate-Transfer
Privatisation Process in Asia, Asian Journal of Public Administration, 19:2, 203-243, DOI:
10.1080/02598272.1997.10800340
Article views: 35
Download by: [De La Salle University Manila Philippines] Date: 07 April 2017, At: 02:40
ASIAN JOURNAL OF PUBLIC ADMINISTRATION VOL 19, NO 2 (DECEMBER 1997) 203-243
PAUL HANDLEY
Since the late 1980s the "build-operate-transfer" concession, orBOT, has become
a popular option in Asiafor infrastru.ctu.ral privatisation. The experiences ofseveral
years suggest that BOT schemes are by nature too complex and fragile, and too
highly prone to politicisation, to enable governments in developing countries to
achieve the quick, efficient, and privately financed supply of infrastructure as
intended by this method of privatisation. Across Asia the number ofunqualified BOT
successes has been few. A much greater number of attempted projects has been
characterised by lengthy delays, chronic disputes, and.frequently,failure to ever get
underway. Even in the case of those which do proceed, the state often fails to attain
its principal goals.
Introduction
203
Asian Journal of Public Administration
204
Budd-Opcrate-Transfer Privatisation Process in Asia
205
Asian Journal of Public Administration
206
Build-Operate-Transfer Privatisation Process in Asia
207
Asian Journal of Public Administration
208
Budd-Operate-Transfer Privatisation Process in Asia
209
Asian Journal of Public Administration
lending. Most of the Asian countries which had benefited greatly from
cheap OECF loans also tied their currencies to the American dollar.
Just at the time when developing Asia required greater (governmental)
resources to enhance economic expansion, their financing costs on old
debt shot up.11
In sum, the economic boom that started in 1987 had placed a huge
demand for the expansion and improvement of the physical and
economic infrastructure in Asia. Governments in the region recog-
nised this but were often unable to respond adequately. Average East
Asian investment in infrastructural development lose from 3.6 per
cent of the Gross Domestic Product in the 1970s to 4.6 per cent in the
1980s. The pace quickened with total investment rising 40 per cent in
a two-year period, from US$39.6 billion in 1990 to US$55.1 billion in
1992, Yet the latter figure still only constituted 4.7 per cent of the
Gross Domestic Product on average. In East Asia, the World Bank
projects, infrastructural investment over the period from 1995 to 2004
will need to reach at least 6.5 per cent of the Gross Domestic Product,
or US$130 billion in 2000 alone.12
In order to meet this demand, governments have turned to priva-
tisation. Where in the West the privatisation trend has at least been
partially rooted in ideological beliefs (for instance, that of Margaret
Thatcher's government in Britain), in Asia, generally speaking, it has
been chosen for more fundamental functional goals. These include:
the rapid and efficient satisfaction of demand for infrastructural
services, in order to sustain economic growth; the improvement in the
implementation and management of infrastructural development so as
to maximise the return on investment and reduce the fiscal pressures
on government; the restriction of the growth of the public bureaucracy
and the SOEs; the inculcation into the public ol the "user-pays"
principle, so that infrastructural facilities can become more self-
financing.
Common options for privatisation include the corporatisation of
S OEs; making already-corporatised SOEs public; and the sale or lease
of state infrastructural assets directly to the private sector for purposes
of operation and expansion. For new infrastructural projects, the BOT
method has been a favourite course of action. BOT has several
attractive features from the government's point of view. First, it is the
210
Build-Operate-Transfer Privatisation Process in Asia
private sector sponsors of the project which bear the financial burden
of development. Second, the scheme is driven by commercial incen-
tives. Hence, the sponsors tend to undertake the quickest and most
efficient way of installing the infrastructural facilities and to manage
them better. Third, the scheme enables the government to achieve its
goals of infrastructural development without expanding the state
sector. And finally, taxes and/or royalties arising from the privatisa-
tion process, as well as the improvement in operating efficiency
generally, can help increase government's income from the develop-
ment of infrastructure.
Across Asia the BOT concept has become hugely popular, espe-
cially in capital-stricken countries. In China and the Philippines,
initial BOT projects proved to be good ways of dealing with emer-
gency situations. Thailand, Malaysia, and Indonesia, and in their wake
Pakistan, India, and others have also latched onto the concept. Even in
some of the region's least developed areas, such as China's Yunnan
province, Vietnam, Cambodia, Laos, and Myanmar, leaders spoke
avidly, if somewhat naively, of developing their infrastructure through
BOT projects.13 The character of this enthusiasm, however, was not to
see BOT development as part of a long-term process requiring
systemic changes, but instead as a one-off, quick-fix solution to
infrastructural bottlenecks. As for the long term, few governments
seem to accept the principle of private infrastructure.
These countries have been encouraged by multilateral organisa-
tions like the World Bank, the International Finance Corporation, the
Asian Development Bank, bilateral aid donors, and private sector
finance institutions, all of which from the late 1980s have begun to
make more capital available for private infrastructural development.
For example, the World Bank, the Export Import Bank of Japan, and
the governments of France, Italy, and the United States of America
joined together to form the Private Sector Energy Development Fund
to help finance private power BOT projects. Perhaps more impor-
tantly, bilateral aid donors have also increased their own support, both
loan- and equity-wise, through such state-backed export credit agen-
cies as the United States Export Import Bank and the KFW Bank of
Germany. This reflects national initiatives to export equipment and
services to rapidly growing economies in Asia, and the focus has been
211
Asian Journal of Public Administration
212
Dudd-Operate-Transfer Privatisation Process in Asia
213
Asian Journal of Public Administration
214
Build-Operate-Transfer Privatisation Process in Asia
215
Asian Journal of Public Administration
J a p a n e s e Government:
Funding
OECF
Irrplementing Agency:
State-owned Enterprise
Turnkey Contractors
Governmsnt
State-owned Enterprise
Operators Suppliers
^ \
Sponsors PROJECT COMPANY
r \
Investors
Insurers 1 /
/
Financiers (Offtake buyers)
(Fuel suppliers)
216
Build-Operate-Transfer Privatisation Process in Asia
217
Asian Journal of Public Administration
218
Build-Operate-Transfer Privatisation Process in Asia
220
Build-Operate-Transfer Privatisation Process in Asia
into BOT power generation plants. As a result, the country has had the
most successful independent power producing BOT programme in the
region. In 1987 the government declared policy support for private
power BOT projects and ended the monopoly of the National Power
Corporation, Napocor. This created a strong legal base for BOOT
projects (as opposed to BTO) and increased confidence among inves-
tors. The government's ability to take these steps demonstrated the
high degree of consensus in the public and private sectors in the
country over the basic need to obtain more power, whatever the costs.
From there, success was based on making the procurement of new
generating capacity, through private investment, virtually the sole aim
of the BOT programme. Regarding pricing of the power, the govern-
ment simply required that it be reasonable, so that it would be cheaper
than the costs of industrial consumers supplying their own. This then
allowed negotiations to concentrate on what the sponsors and their
financiers would require in terms of benefits to follow through with
their investment. Recognising the perceived high-risk environment of
the Philippines which might discourage investors, Manila was com-
mitted to guaranteeing Napocor's payments as purchaser of the power,
and also guaranteeing against foreign exchange risk. Only later, when
the environment for BOT projects was proven to be stable, did the
government begin to address the issue of competitive pricing on top of
supply. At the beginning, the larger projects were also conducted on
a negotiated basis. But by 1994, Manila was able to regularise the
process by holding competitive bids for new plants.
Yet another important aspect of the programme was the benefits
of starting with small BOT projects. As in the case of China, Hopewell
was the first foreign company to venture into this area in the Philip-
pines. But in southern China, Hopewell already had well-developed
political and business relations with the local government through
engagement in previous projects. This encouraged the company to
proceed with the large Shajiao plant. A newcomer into the Philippines,
the company was more cautious, first negotiating in 1988 a concession
for a 210 megawatt plant, Navotas. While that was under develop-
ment, in 1990 Hopewell and other sponsors also installed several small
barge-mounted power generating plants to sell power to Napocor. All
this helped to prepare the political and commercial environment for
221
Asian Journal of Public Administration
later, larger projects. The Navotas contract became, in late 1990, the
partial basis for the country's progressive BOT law.
In 1995 Thailand's EGAT issued a call for bids for independent power
producers to develop a series of BOT electricity generation projects.
The aim of the programme was to acquire generation capacity of three
to five thousand megawatts spread over several separate plant conces-
sions, under different sponsors or investors. The terms of reference
were seen by several bidders to be among the most progressive and
222
Build-Operate-Transfer Privatisation Process in Asia
well-focused in the region. The call attracted more than thirty propos-
als. With the advice of a team of independent experts, and on the basis
of a clear and transparent point system, the bids were to be weighed
and evaluated. Given that Thailand's energy supplies were adequate,
but that over the long-term there was a perceived need for greater
efficiency and less reliance on government investment and manage-
ment, the focus of the tender was on getting reliable power supplies at
the best possible price. Beyond that, plant locations, design, and fuel
were left to the bidders, though in assigning point values, the govern-
ment indicated clear if not absolute preferences.
The result was the large number of bids, offering competitively
low power sales prices which surprised and pleased both those
conducting the process and the bidders themselves.23 The terms of
reference were announced in early 1995, and by the end of 1996
bidders were close to finalising concession negotiations and preparing
for financing. The process could have gone faster, according to those
weighing the bids, had there not been so many attractive and competi-
tive proposals. The results suggested that Thailand could achieve a
fairly quick and efficient way of creating new power capacity - at not
just one but several plants - at internationally competitive sales prices.
Such success was rooted in the long process of consensus-building
among participants and the government at large, and strengthened by
the openness of the terms and the decision-making process. This
helped protect the programme from inevitable challenge by vested
political and business interests: on two occasions attempts by very
senior politicians and their business cronies to hijack the process were
shrugged off.24
However, the process was not flawless. An important consensus
problem which cropped up suggests just how hard it is to establish a
strong BOT programme. For environmental reasons the government
had expressed a preference for natural-gas-fuelled plants, without
ruling out coal or oil. (Gas plants simply earned slightly higher points
in the fuel category). However, Thailand's monopoly gas distributor,
the state-owned Petroleum Authority of Thailand, neither had firm gas
reserves or gas acquisition plans, nor standard sales contracts to be
able to commit supplies to the bidders. This left gas-plant bidders in
a situation wherein they were unable to certify their fuel supply source
223
Asian Journal of Public Administration
with the bid committee. This in turn made them uncompetitive. The
consequence was that non-gas plants came to lead the field.25
224
Build-Operate-Transfer Privatisation Process in Asia
225
Asian Journal of Public Administration
226
Budd-Operate-Transfer Privatisation Process in Asia
228
Build-Operate-Transfer Privatisation Process m Asia
The Paiton project, as mentioned above, carried a very high sales price
for the power produced at the outset (at US 8.6 cents per kilowatt-
hour). The country's second and third BOT projects were awarded at
lower prices, but still much higher than the rate of 5.6 cents per
kilowatt-hour that Thailand received in its competitive bidding proc-
ess. The difference reflects the Indonesian government's inability to
remain focused on obtaining the cheapest and most efficient supply of
power for the country. It had in fact been distracted by many other
issues. For instance, Paiton was required to build various infrastructural
facilities extraneous to the plant's functioning; to use specific contrac-
tors; and to purchase equipment from certain designated companies.
These requirements prevented the sponsor from pursuing the most
efficient development of the plant, thereby forcing it to increase
capital costs by, according to one power sector analyst, at least
US$200 million. This made concession and financing negotiations
more difficult.34 The result was that, to make the project commercially
viable on a BOT basis, the power prices had to be set at an
uncompetitively high level.
In the event, the government did not implement the staged toll
increase plan. By the time the system was to start operation in March
1993, the cabinet decided that a sharp increase in the tolls was
unreasonable and could be politically inexpedient. Only a 20 baht toll
was therefore agreed upon. Such a rate would reduce the scheduled
income of both the BECL and the ETA, thus compromising both
organisation's financial viability. (ETA would have lost its ability to
cover its current costs, much less long-term debt and land acquisition
burdens). BECL's bankers reacted by freezing financial disburse-
ments, and the ETA demonstrated that it no longer supported govern-
ment policy or the BECL concession. Thus the unwillingness of the
government to follow through on the user-pays principle caused the
original consensus surrounding the project to break down.
Several months of negotiations were unable to rebuild the consen-
sus, because, according to BECL officials and its bankers, the Thais
could not focus on the fundamentals needed to make the project work.
The BOT matrix could not be restored. Eventually the road was
opened by force by the government (ironically, at the 30 baht toll rate)
and principal sponsor Kumagai Gumi sold its shares to a group of Thai
banks and investors in 1994. The new investors accepted the deal but
only as long as the government abided by the original contract. The
project's subsequent cash flow demonstrated that it had a strong
commercial viability as originally expected.35
230
Build-Operate-Transfer Privatisation Process in Asia
Already four years into the negotiation process in 1996, the US$1.1
billion, 1,000 megawatt Cogentrix power project in Mangalore was
being delayed not only by bureaucratic infighting and public resist-
ance, but also by constant attempts on the part of the government to
renegotiate the price and other specifications. After setting specifica-
tions and pricing, and obtaining the sponsors' agreement, the govern-
ment would then alter its position and make the requirements tougher.
It was alternatively willing and unwilling to provide a crucial payment
guarantee on power sale.37 The problems reflected a lack of consensus
within the government on the principal goal of the BOT project which
was simply to obtain privately financed power generation capacity at
a reasonable price. Continued negotiations indicated a new focus on
the appropriate level of profitability for the concession-holders. This
represented a deviation from the original purpose of the use of the BOT
concept in power supply.
231
Asian Journal of Public Administration
232
Budd-Opcraie-Transfer Privatisation Process in Asia
233
Asian Journal of Public Administration
234
DuUd-Operate-Transfer Privatisation Process in Asia
Because of the lengthy delays and high risks inherent in the environ-
ment, the Pakistan government ended up absorbing much of the
project risk of the Hub Power BOT programme. The government took
on a US$582 million loan from the World Bank to support the project.
In addition it had to take significant equity participation and to
guarantee fuel supply and power off-take agreements, as well as
provide protection against foreign exchange risk. In an indirect way,
the government was also liable for the foreign government agency
(and World Bank)'s financial commitments to the project, which
together constituted 70 per cent of total project cost, some of which
passed through the Pakistan government. Total private sector invest-
ment, then, was very limited.
The risks and high costs of the Paiton power BOT project were mainly
undertaken by foreign government institutions, as commercial banks
235
Asian Journal of Public Administration
and private sponsors clearly considered the risk too high. Of the
US$1.9 billion financing package, US$900 million was supplied by
the Export-Import Bank of Japan. A further USS540 million was
supplied by the US Export-Import Bank, and another US$200 million
from the United States government's Overseas Private Investment
Corporation. Commercial banks, on the other hand, supplied only
US$274 million. Loan insurance was also provided by foreign govern-
ment institutions. The heavy foreign government involvement implies
that the onus is on the Indonesian government to make the project
work.
The sponsors have taken only short-term equity risks on the
project. According to project sources, the main shareholder, the
Mission Energy of the United States of America, w< mid recover much
of its equity in project management fees, including a sizable bullet
payment at the commissioning of the plant. A second major share-
holder, the supplier of the power plant itself, is financed by United
States Exim Bank credits, leaving it with little risk on the sales of
equipment. (Presumably profits on the equipment will cover a sub-
stantial portion of its equity exposure). The third main shareholder, the
key Indonesian partner (a relative of the President) is the principal fuel
supplier to Paiton. This company's 15 per cent equity was pre-
financed by a state bank which will itself only be repaid out of Paiton' s
profits. Upon the commissioning of the plant, the company expects to
further reduce sponsors' risk by floating the company on the stock
exchange. The implications are that first, by the time the plant is
operating, principal sponsors will have reduced their equity exposure
to almost nothing, and second, the principal holders of risk will be
foreign and local government financial institutions, which will, in case
of default, be forced to confront the Indonesian government to redress
their losses.
236
Burfd-Operate-Transfer Privatisation Process in Asia
Like Paiton, the Dabhol project was mainly financed not by commer-
cial banks or the equity of the principal sponsor, but by government
financial institutions. Of the US$920 million required for the develop-
ment of the project at the first stage, US$398 million was supplied by
two American government institutions, and then another US$295
million by Indian banks, mainly government-controlled banks led by
the Industrial Bank of India. Commercial bank financing amounted to
US$150 million, indicating the commercial banks' perception of risk.
When the project became entrapped in controversy, the American
government's pressure on Delhi implied that the Indian government
was expected to assume some kind of financial responsibility.
237
Asian Journal of Public Administration
Conclusion
238
Budd-Operate-Transfer Privatisation Process in Asia
239
Asian Journal of Public Administration
NOTES
1. World Bank, Infrastructure Development in East Asia and the Pacific (Wash-
ington DC: World-Bank, 1995), p.l.
2. Jim Rohwer, Asia Rising (Singapore: Butterworth-Heinemann Asia, 1995).
3. Studies have shown that telecommunications projects have much higher rates
of return, based on lower sunk capital costs and the ability to charge consumers high
unit prices. See World Bank, World Development Report 1994: Infrastructure for
Development (New York: Oxford University Press, 1994).
4. Worldwide, 90 per cent of these financing arrangements are carried out or
intermediated by the government, See ibid., p.89.
5. Ibid.
6. Alan Rix, Japan's Aid Program (Canberra: Australian Government Publishing
Services, 1987); and Nigel Holloway, ed., Japan in Asia (Hong Kong: Review
Publishing Co., 1992).
7. At the end of 1994, the outstanding balance of OECF loans worldwide was
8,026 billion yen. Of that 78 per cent was to Asian countries. The top five OECF
borrowers are Asian (Indonesia, China, Philippines, India, and Thailand, respec-
tively). Worldwide, over half of OECF loans were allocated to electric power and
gas, transportation, and telecommunications. Excluding OECF commodity loans,
the share of project loans to those categories of infrastructure was 66 per cent. In Asia
the level was close to 70 per cent.
8. OECF officially ended the tied aspect of projects in the late 1980s, but the
practice effectively continues even today. See Rix, Japan's Aid Program; and
Holloway, Japan on Asia.
9. However, some government-developed infrastructural facilities are often able
to produce a strong commercial return. Besides telecommunications systems,
electricity generation can also, as the case of Thailand demonstrates, meet all criteria
and remain self-financing and profitable. See Phisit Pakkasem, "Privatization in
Developing Countries: The Experience of Thailand," paper presented at the ADB
Conference on Privatisation Policies, Manila, 1985.
240
liudd-Operate-Transfer Privatisation Process in Asia
241
Asian Journal of Public Administration
24. In July 1995 the cabinet moved to replace EGAT's entire board, except for one
person, with new persons including business cronies of cabinet members. Public
reaction and a threatened strike by EGAT staff forced a reversal of the decision.
Later, in early 1996, the Prime Minister asked the committee reviewing the bids to
meet with losing bidder the TPI Group, which made an unsuccessful argument to be
included in the winners' short list.
25. Yet the process forced PTT to begin to address its shortcomings, and the gas
power plant bidders were to be favoured in a scheduled second round of bids.
26. Confidential interview with a senior adviser to the project, August 1995.
27. These were the "Skytrain," negotiated by the Expressway and Rapid Transit
Authority of Thailand with Canada's Lavalin group from 1987 to 1991, after which
the concession was cancelled; the Hopewell's combined road/rail/mass transit
project awarded by the Ministry of Transport and Communications and the State
Railways of Thailand in 1990, which was less than 10 per cent completed in 1996
(when it was to be up and running); and the "Tanayong" or BTSC concession for an
elevated light rail awarded by the Bangkok Metropolitan Area government in 1992,
but which was by mid-1996 only on the verge of securing financing, and less than
20 per cent completed.
28. Asian Wall Street Journal (AWSJ), September 20, 1996.
29. Based on interviews with government officials, and power sector representa-
tives, between 1988 and mid-94 in Thailand. The EGAT told potential sponsors that
it would not make long-term commitments to buying the power they generated; that
it required control of the fuel supplies (including pricing) to the power plant; and that
other conditions, considered unacceptable by the industry, were to be met.
30. A well-placed energy sector source in Indonesia in August 1995 said the PLN
was paying US$80 million a year to the independent producers for power it could
not sell onwards, because of its poor distribution network.
31. Confidential interview with power industry figure, Jakarta, August 1995.
32. Christine Hill, "A Dam Too Far," Institutional Investor (December 1995).
33. For instance, according to Thai energy planner Piyasawat Amranand, the
relatively advanced and progressive Thai power agency EGAT could not estimate
accurately its own avoided costs as a means of analysing and comparing bids by
private companies for independent power producer concessions licenses in 1995.
(Given the prevalence of rent extraction in state-driven projects, few slate-owned
enterprises would be willing to provide an accurate estimate of their costs, because
it would only indicate inefficiencies and corruption).
34. Comparing the costs of differing power plants is of course not a precise
measurement, but energy industry executives note that competitive costs for plants
in 1995 were roughly US$1 million per megawatt of capacity. The Managalore,
India BOT project of Cogentrix is roughly 1,000 megawatt for US$1.1 billion.
Paiton is almost double the unit cost, at US$2.5 billion for 1,230 megawatt.
35. This account is based upon numerous interviews by the author with principals
in the case; see Paul Handley, "Thailand Case Study: The Second Stage Express-
way" in Schell, Project and Infrastructure Finance in Asia.
242
Build-Operate-Transfer Privatisation Process in Asia
Paul Hundley reported for Far Eastern Economic Review from Jakarta, Hong Kong, and
Bangkok between 1985-93 From 1994 until the present, he has been a regional correspond-
ent for Institutional Investor, based in Bangkok. This paper was written with the support of
a research fellowship from the Asia Research Centre, Murdoch University, during 1996. The
author would like to thank Richard Robison and Garry Rodan of the Asia Research Centre
for their advice and support, and Guy Altree and John Palumbo of Delta Associates for their
critical comments.
243