Form BCA-BE-Permit
JOINT APPLICATION FOR PERMIT TO CARRY OUT STRUCTURAL WORKS
[Section 6 of The Building Control Act]
Commissioner of Building Control Please tick the appropriate box if the re-application of permit is made for the change of
Building and Construction Authority any of the following project party:
5 Maxwell Road #02-00 Developer
Tower Block, MND Complex
Singapore 069110 QP for supervision of structural works
Builder
QP for architectural works
We hereby apply for a permit to commence the following works and undertake to comply with The Building Control Act and its Building Regulations
Demolition Works
(i) Building Type (for mixed developments, more than 1 box maybe ticked):
Residential (Landed) Residential (Non-landed) Commercial Industrial Institutional and others
(ii) Description of Demolition Work:___________________________________________________________________________________________
(e.g. 1 unit of 2-storey semi-detached dwelling house)
(iii) Details of Demolition Work:
No. of blocks/buildings: __________ Demolition Waste Quantity (in tonnes):
No. of Storeys per blk: ___________ Quantity of concrete waste: ___________________
Total Floor Area to be demolished (m2): ___________ Quantity of brick waste: _____________________
Quantity of other waste (eg. metals, timber, glass, steel re-bars, etc): __________________
Total Demolition Waste Collected: __________________
(iv) When was the building first built (based on TOP date) before 1990 after 1990
(v) Is asbestos-containing material present in the building Yes No
Under the Factories (Asbestos) Regulations, you shall notify the Ministry of Manpower prior to commencement of work involving asbestos.
If you are uncertain whether asbestos is present, you may take a sample of the suspected material for analysis or assume that it contains asbestos
Structural Works (include Site Formation, Piling, Earth Retaining Structural Works and Geotechnical Building Works)
A. PROJECT DETAILS
Project Ref. No.: A1482-00003-2013-ST01& 02
Project Title: PROPOSED INTERIM BUS DEPOT WITH SINGLE STOREY WORKSHOP AND TWO STOREY ANCILLARY
FACILITIES
(ii) Er. _____________________________________________ of PE Registration No.: ___________________ as the Qualified Person for supervision of
geotechnical works under Section 8(1)(d)(ii) of the Building Control Act.
(iii) _____________________________________________ of UEN ___________ as the Builder under Section 8(1)(c) of the Building Control Act.
(ii) I am not a partner, officer or employee of the builder or any associate of the builder (only applicable to project that requires an Accredited Checker).
(iii) I have appointed ___________ (state total no.) of Resident Engineer(s) and ___________ (state total no.) of Resident Technical Officer(s) to undertake:
Immediate supervision of critical structural works as required in Section 7(1)(c) of the Building Control Act
Full-time supervision of structural works as required in Section 7(1)(b) of the Building Control Act
(iv) the particulars of the site supervisors are as shown in section (E).
(ii) Er. _____________________________________________ of PE Registration No.: ___________________ as the Qualified Person for supervision of
geotechnical works under Section 8(1)(d)(ii) of the Building Control Act.
Under the Building Control (Buildability) Regulations, submission of constructability score is:
1
Applicable Constructability Score has been submitted.
Constructability Score e-Submission No. : ___________________________
Constructability Score: _________ points
Will be submitted within 3 months from the date of issuance of permit to
carry out structural works.
Will be submitted within 6 months from the date of issuance of permit to
carry out structural works (for Design & Build projects only).
2
The expected start date of the superstructure works is on ___________________
1
Not Applicable GFA < 5000m2
Planning permission applied before 15 July 2011
Waiver is obtained
Exempted
+
GFA: ___________________ Square metres
+
The planning permission was first applied on : _______________
______________________________________________ _____________________________________________________
I confirm that I am appointed as the Qualified Person for architectural works under section 8(1)(b) or 11(1)(d)(ii) in respect of the works described above.