Академический Документы
Профессиональный Документы
Культура Документы
High allowable momentum, Development of the degasser started with scale models. A
De-foaming characteristics, 6 and an 11 degasser were built to investigate the behavior
Liquid-liquid coalescing benefits, and of the complete system. Also the theoretical models
Gas demisting benefits. describing efficiency and pressure balance in the degasser
were verified successfully. The information gained from the
Figure 3 shows an inlet cyclone in more detail. Features of laboratory tests resulted in an 18 full-scale degasser shown in
inlet cyclones are: Figure 6.
inline demister The information gained from the laboratory tests resulted
Pipe vibrations caused by gas slugging to be in the final 18 full-scale degasser shown in Figure 6. Design
eliminated by use of an inline degasser conditions are: 60,000 Sm3/d liquid and 98,000 Sm3/d gas.
Flare scrubber performance improved by Taking into account the pressure in the system, the gas-
CFD modeling fraction is 30%v.
Tests of the full-scale 18-degasser showed that the
Oil/Water Separation Improvement measurements indeed obey the mathematical rules used as the
Inlet baffle plates are known to cause foam and emulsion design basis. The turndown appeared to be approximately
problems, especially with high momentum flows. An inlet 40% in liquid flow. For 1000 m3/hr liquid, the separation
cyclone, on the other hand, can handle high momentum flows efficiency is still satisfactory.
as well as having beneficial effects on the emulsion. As part The efficiencies are shown in Figure 13 (different liquid
of an effort to improve separation efficiency, inlet cyclones rates and gas-fractions). At the design point, the efficiency is
were tested in a North Sea test separator (2408 mm x 9000 greater than 90%, mainly because of the low pressure drop
mm SS). The vessel had been suffering from high oil in water specification. However, if degassers with larger separation
and water in oil levels caused by the inlet deflector plate. The efficiencies are needed, it is only a matter of re-designing the
results of the modifications are shown in Figure 10. internals (i.e. optimizing the efficiency for a certain maximum
Prior to the modification, the water in oil was on the order given pressure drop). During the tests, the dynamic response
of 10-14%v for certain wells. After the modifications, the of the degasser was studied thoroughly. In automatic control-
water in oil was near zero. At higher momentums, the water mode, the system remains stable when huge variations in
in oil was in the 2-6%v range. More importantly, the oil in liquid and/or gas flow are initiated.
water was on the order of 20-30 ppm which is overboard The conclusion of the experiments is that the design rules
quality (less than 40 ppm) and significantly (1-2 orders) less and test results are as expected. This implies that the degasser
than prior to modifications. Finally, the importance of the concept can be applied in a variety of applications both
cyclone liquid outlet low shear design was realized when offshore and onshore.
another type of cyclone was similarly tested. Both the water
in oil and oil in water were significantly higher for this other CFD Modeling
cyclone especially for the high momentum flows. Figure 14 shows a pictorial of a flare scrubber with carryover
The main production vessel (3800 mm x 14212 mm SS) problems. Not only was the scrubber not removing incoming
was then retrofitted with inlet cyclones. Improvements in both liquids, it actually lost liquid as evidenced by a decreasing
the oil in water (20%+ reduced to 5-6%) and water in oil (400 liquid level with closed dump valves. The original scrubber
ppm+ to less than 200 ppm) have been realized. with flow through nozzle N1 had an impact plate diverting the
flow downwards. The gas then reversed itself in order to flow
Liquid Carryover through the vane pack demister. During one retrofit, a hole
During well startup, the gas rates can sometimes be much was cut into the baffle as it was believed that the impact plate
higher than what a separation vessel has been designed to was shearing the drops into a fine mist, but the problems
handle. The well must be started slow enough so as not to remained.
cause too much liquid carryover that will flood downstream The gas flow was modeled using CFD and the results are
equipment and cause a platform shutdown. However, the shown in Figure 15. The inlet jet flows through the impact
longer the startup, the less the gas and oil production. plate hole and hits the back wall. Some of the flow is diverted
For this application, the vessels were too small (59 ID x upwards, but a large portion is diverted downwards across the
20 SS) to install new devices internally so demisting cyclones liquid interface. Figure 15 also shows the predicted velocities
were placed in a spool piece in the gas outlet piping. See across the liquid surface, which are higher than 50 m/s. This
Figure 11. The liquid from the cyclones was drained high velocity re-entrains liquids which are then carried up to
continuously to a lower pressure system through a small the vane pack. A second problem with the scrubber is
diameter orifice to control the gas purge. Well startup times illustrated by the velocities across the vane pack. A poor flow
were reduced by a factor of 5 (from 10 to 2 hours) as the distribution is predicted. Although the vane pack may have
increased liquid carryover was removed by the external had sufficient area under uniform flow, the mal-distribution
cyclones. Higher gas capacities were also realized. would result in local flooding which is compounded by the
additional liquids being swept up from the liquid surface.
Gas Slugging/Pipe Vibrations The recommended solution was two-fold: 1) reduce the
The first application for this device is shown in Figure 12. inlet velocities by splitting the flow using a second inlet
Gas, evolving from water as it depressurizes flowing through (N20), and 2) lowering the liquid level as low as possible.
hydrocyclones, is causing slug flow and subsequent vibrations When these two recommendations were implemented, the
in a downstream riser piping. The degasser will be placed carryover problem was resolved.
downstream of the hydrocyclones to remove the gas to flare
or recompression.
4 R. W. CHIN, D. I. STANBRIDGE, R. SCHOOK SPE 77495
Inline
demister
Existing
Separator Existing
Scrubber
Partial
Separation Higher
Capacity
Demister
Figure 1. Possible upgrade solutions.
January 1999
Empty Mesh Vanes Cyclones 100
14
90
Deflector
12 80
10
70
Oil-in-
% 60 Water
Water- 8
50 (ppm)
in-Oil
6 40
30
4
20
Gravity Impact 2
Coalesence Impact 0 0
Gravity 5000 15000 25000 35000 45000 55000 65000
Coalescence
Inlet momentum [kg/ms]
Increasing Flow Rates Lead to More Entrainment Figure 10. Liquid/liquid separation results with
inlet cyclones in a test separator.
Figure 7. Typical demisters.
6 R. W. CHIN, D. I. STANBRIDGE, R. SCHOOK SPE 77495
20 m
Gas outlet
line
Water flow
50,000 m/d
GWR = 1 to 2
Flow from
hydrocyclones Degasser
Cyclone
Recirculation
High Velocities
Figure 12. Inline degasser application. Leading to
Re-entrainment
Figure 15. CFD model of flare scrubber.
100
80 1000 liq
Efficiency [%]
60 1250 liq
1500 liq
40
1750 liq
20 2000 liq
2250 liq
0
2500 liq
0 10 20 30 40 50
GAS fraction [%]