Project Schedule for Obama-Nimbe Repair and Restoration of MV ESP Cables
S/N Activities Start Date Start End Jan-March'16 April-June July-Sept '16 Oct-Dec'16 Action
'16 Party

A Tendering
C Premobilisation
10 Project kick off meeting 1/1/2016 1/1/2016
11 Documentation for Quality /HSE & Security Plan 4/1/2016 5/1/2016
12 HSE workshop 7/1/2016 7/1/2016
13 Pre-mob Inspection for Equipment/Personnel/Vehicle 8/1/2016 8/1/2016
14 Securing FTO 8/2/2016 8/2/2016
D General Mobilisation
15 Mobilisation to site of materials, personnel and Equipment 11/1/2016 15/1/2016
E Installation activities

16 Bush clearing along Right Of Way (ROW) of ESP cables 18/1/2016 22/1/2016
17 Excavation of existing faulty cable trench 25/1/2016 29/1/2016
18 Backfilling of excavated faulty cable trench 1/2/2016 5/2/2016
19 Procurement of HV Submarine Splicing kits 8/2/2016 10/2/2016
20 Procurement of HV Submarine Jointing kits 8/2/2016 10/2/2016

21 Procurement of HV scotch tapes 8/2/2016 10/2/2016

22 Procurement of HV 3 core termination kits 8/3/2016 10/3/2016

23 Troubleshooting for localization of faults on the MV cables 15/3/2016 30/12/2016

24 Splicing of identified faulty/damaged Submarine cables 16/3/2016 30/12/2016

25 De-connection & Retermination of cables 21/3/2016 31/12/2016


45 Final commissioning of all installations 28/3/2016 31/12/2016
H Project handover and Demobilisation
83 Clear site of all debris, segregation all waste from site 4/4/2016 31/12/2016
84 Handback of Project to Asset owner and Demobilise 4/5/2015 31/12/2017
LEGEND: NOTES:
PLANNED 1. 3 Days notice will be required for every cable fault re-mobilzation to site
2. Site office shall be required to warehouse cable splicing and termination kits including minor support personnel
ON GOING 3. NAOC management shall be requested to assist intervene in all host communities issues while resources will be provided by contractor

Diebu Crk Enve Upgrade: 08/20/2017