Project Schedule for Obama-Nimbe Repair and Restoration of MV ESP Cables
S/N Activities Start Date Start End Jan-March'16 April-June July-Sept '16 Oct-Dec'16 Action
'16 Party
A Tendering
C Premobilisation
10 Project kick off meeting 1/1/2016 1/1/2016
11 Documentation for Quality /HSE & Security Plan 4/1/2016 5/1/2016
12 HSE workshop 7/1/2016 7/1/2016
13 Pre-mob Inspection for Equipment/Personnel/Vehicle 8/1/2016 8/1/2016
14 Securing FTO 8/2/2016 8/2/2016
D General Mobilisation
15 Mobilisation to site of materials, personnel and Equipment 11/1/2016 15/1/2016
E Installation activities
16 Bush clearing along Right Of Way (ROW) of ESP cables 18/1/2016 22/1/2016
17 Excavation of existing faulty cable trench 25/1/2016 29/1/2016
18 Backfilling of excavated faulty cable trench 1/2/2016 5/2/2016
19 Procurement of HV Submarine Splicing kits 8/2/2016 10/2/2016
20 Procurement of HV Submarine Jointing kits 8/2/2016 10/2/2016