Академический Документы
Профессиональный Документы
Культура Документы
Introduction :-
I, Manish Saini, is student of Civil-II year at S.J. College of
Engineering & Technology Bhandana Distt. Dausa. As required in
the course, I was assigned to work with Engineers of Housing Board
for Vocational Training of one month. I worked with them for this
training at the Jaipur satisfactorily and his certificate is enclosed I
fulfill this requirement of the course.
Name of work
The work that was constructed there is the Foundation work of the
flats as well the another most important work that is R.C.C. Framed
Structure MIG-A (G+3) 80 flats. In this so many things are involved
like measurement of the weight of the steel bar in the foundation.
2
Acknowledgement
*****
3
PREFACE
Foundation Work :-
When constructing a foundation for a building, it is generally best to have
a professional come in and do most of the work. There are some skilled
do-it-yourselves out there, though, who can properly build a foundation
for a small outbuilding. A civil engineer must to know the details of
foundation construction as its the basic work that is required for almost
every construction project. The basic knowledge on building foundation
construction process can help a homeowner to understand the phase of
construction. It requires specific steps to ensure that the footings will
hold the weight of the building through the test of time.
Building foundations are provided to carry the load of the structure and
then to distribute the load to the soil in larger cross sectional area. The
foundation must be able to withstand the load of the structure including
live loads and environmental factors. A safety factor is provided for
safety during foundation design. The foundation is constructed according
to the design. Here are 10 steps that are generally followed during
building foundation construction. The following steps are provided for a
general idea. These are not fixed steps and steps can be varied many
ways during practical implementation depending on the construction
project.
Excavation:-
A structural engineer will be needed to determine the depth of the
excavation. All surface soil needs to be removed to expose the soil that is
compacted enough to bear the weight of the building. The depth will vary
per building. The top of the footing must be below the frost line as this
prevents the concrete from cracking when the freeze-thaw cycle occurs
in the soil surrounding the building
5
Footing:-
A footing is a poured concrete pathway that is used to spread the weight
of the building from the foundation walls to the soil. They are wider than
the foundation walls that they are supporting and form the perimeter of
the
Isolated Footing
6
Foundation
Depth of Foundation
Footing
Width of Foundation/Footings
Dry coarse and well graded dense sand have maximum shear resistance
and maximum bearing capacity. In general submerged soil and clay have
less bearing capacity.
1. The depth of the foundation should not be less than 1 meter in case
the design is not available.
2. The length, width and depth of excavation should be checked with
the help of center line and level marked on the burjis.
3. The excavated material/ earth should be dumped at a distance of 1
meter from the edges.
4. Work should be done on dry soil.
5. Arrangement of water pump should be made for pumping out rain
water.
6. The bottom layer of the foundation should be compacted.
7. There should be no soft places in foundation due to roots etc.
8. Any soft/ defective spots should be dug out and be filled with
concrete/ hard material
11
1. Weigh out the designed proportions for a 1.6 cubic foot batch of
concrete.
4. Start the mixer and mix until the aggregate is thoroughly wet
5. Carefully add all the cement with the mixer running. Try not to
make a lot of dust! Add a little more water and mix until all the
cement is blended in.
6. Incrementally add the rest of the coarse and fine aggregate mix
until blended in
7. In very small increments, add enough water from the final quarter
of the water to produce a workable mix. A little water goes a long
way!!
9. Dump some mix out of the mixer into a pan. Perform a slump test.
If results are satisfactory, skip to the next step, otherwise:
12
10. Record the final slump and the actual weight of water and cement
used.
11. If using super plasticizer, add it to the mixer and mix for one
minute.
13
Compaction by Machines
(a) The following advantages accrue by compacting the concrete by
machines and is to be adopted in circumstances other than in documents.
When the form vibrators are being used, the top 750mm portion should
not be covered by the action of the form vibrators. The above gap can be
vibrated by internal vibrator.
The form vibrators are most suitable when the reinforced section is very
heavy and the internal vibrator cannot be used at all. Form vibrator can
be attached to the exposed face of the reinforcement bars to vibrate
them.
This will help remove the air trapped under the bars. This type of
vibration will increase the bond between the concrete and reinforcement
bars.
These are mostly used for road works. The vibrator is attached to the
timber section having handles on both ends. The unit is thus called
screed vibrator. All the conditions mentioned for surface vibrators apply
to screed vibrators as well.
Construction Joints
Concreting shall be carried out continuously up to construction joints.
The position and arrangement of construction joints shall be as shown in
the structural drawings or as directed by the Engineer. Number of such
joints shall be kept minimum. Joints shall be kept as straight as possible.
Construction joints should comply with IS:11817.
Mass Concrete
(a) Mass Concrete is to be deposited in layers not exceeding 40 cm
thickness and complete layers of concrete should be laid in a day.
(b) Care shall be exercised to avoid disturbing the setting action of the
concrete, and unless sufficient time has elapsed for the setting to take
place, no imposed load, such as that caused by walking over it, laying
planks or other timber upon it or other loads, however light, shall be
allowed. Earth must never be rammed in the vicinity of reinforced
concrete less than one month old.
time when it rains, all freshly laid concrete which has not been covered
for curing purposes, shall be adequately protected by means of such
tarpaulins or other waterproof cloth. Any concrete injured by rain shall
be removed and replaced at the expense of the contractor.
(c) The concrete shall contain at least 10 percent more cement than that
required for the same mix placed in the dry, the quantity of extra cement
varying with conditions of placing. The volume or weight of the coarse
aggregate shall be not less than one and a half times, nor more than
twice, that of the fine aggregate. The concrete shallbe so proportioned as
to produce a concrete having a slump of not less than 10cm and not more
than 18 cm.
(d) The water under which the concrete is laid shall be quite still and any
movement in the water shall be stopped by sheeting so as to divide into
compartments the place where the concrete is being deposited.
19
(e) In case cofferdams or forms are being provided, the same shall be
sufficiently tight to ensure still water if practicable, and in any case to
reduce the flow of water to
less than 3m per minute through the space into which concrete is to be
deposited. Cofferdams or forms in still water shall be sufficiently tight
toprevent loss of mortar through the walls. Dewatering by Pumping shall
not be done while concrete is beingplaced, or until 24 hours thereafter.
Tremie: The concrete should be coherent and slump shall be more than
150mm but should not exceed 180mm. When concreting is carried out
under water, a temporary casing should be installed to the full depth of
bore hole or 2 m into non collapsible stratum, so that fragments of
ground cannot drop from the sides of the hole into the concrete as it is
placed. The temporary casing may not be requiredexcept near the top
when concreting under drilling mud. The top section of the tremie shall
be a hopper large enough to hold one entire batch of mix or the
entirecontents of the transporting bucket when one is used. The tremie
pipe shall be not less than 200mm in diameter and shall be large enough
to allow free flow of concrete and strong enough to withstand the
external pressure of the water in which it is suspended, even if a partial
vacuum develops inside the pipe. Preferably flanged steel pipe of
adequate strength to sustain the greatest length and weight required for
the job should be used. A separate lifting device shall be provided for
20
each tremie pipe with its hopper at the upper end. Unless the lower end
of the pipe is equipped with an approved automatic check valve, the
upper end of the pipe shall beplugged with a wadding of gunny sacking
or other approved material before delivering the concrete to the tremie
pipe through the hopper, which plug will beforced out of the bottom end
of the pipe by filling the pipe with concrete. It will be necessary to raise
slowly the tremie by 25 cm to 30 cm in order to cause a uniform flow of
the concrete, but the tremie shall not be emptied so that water enters
above the concrete in the pipe. At all times after the placing of concrete is
started and until all the concrete is placed, the lower end of the tremie
pipe shall be at least 600mm below the top surface of the plastic concrete
as ascertained by sounding. This will cause the concrete to build up from
below instead of flowing out over the surface, to avoid formation of
laitance layers. If the charge in the tremie is lost while depositing, the
tremie shall be raised above the concrete surface, and unless sealed by a
check valve, it shall be re-plugged at the top end, as at the beginning,
before refilling for depositing concrete.
Curing
General: Curing is the process of preventing loss of moisture from the
concrete. The importance of curing can be appreciated from the details
given at Annexure3.6 of Unified Standard Specifications for Works &
Materials.
Membrane Curing:
Approved curing compounds may be used in lieu of moist curing with the
permission of the Engineer. Such compound shall be applied to all
exposed surfaces of the concrete as soon as possible after the concrete
has set Impermeable membrane such as polythene sheet covering the
concrete surface may also be used to provide effective barrier against the
evaporation.
Freshly laid concrete shall be protected from rain by suitable covering.
Over the foundation concrete, the masonry work may be started after 48
hours of its completion, but the curing of exposed surfaces of cement
concrete shall be continued along with the masonry work for at least 7
days. And where the cement concrete is used as base concrete for
flooring, the flooring may be commenced before the curing period of
base concrete is over but the curing of base concrete shall be continued
along with top layer of flooring for a minimum period of 7 days.
20oC) of adding the mixing water to the dry mix of cement. Special
measures as approved by Engineer-in charge will be taken if transit
time is more than 2 hrs.
25
2 While carrying out sieve analysis, the screen shall not be kept
inclined, but held horizontally and shaken vigorously. The pieces of
ballast retained on the screen can be turned with hand to see if
they pass through but should not be pushed through the sieve.
Each tender at the time of tendering shall submit the test report of
impact value, Abrasion value, water absorption value from approved
laboratories as mentioned in para 1.1 (c). The tenderer/s shall also
furnish an undertaking that the ballast supply at all times will
conform to the specifications for track ballast as specified by Railway.
Method of Measurement:-
5.4.1 Stacking shall be done on a neat plain and firm ground with good
drainage.
The height of stack shall not be less than 1m except in hilly areas
where it may be 0.5m.
The maximum height shall not be more than 2.0m top width of stack
shall not be less than 1.0m. Top of stack shall be kept parallel to the
ground plane. The side slopes of stack should not be flatter than 1.5:1
(Horizontal: vertical). Cubical content of each stack, shall normally be
not less than 30cum in plain areas and 15 cum in hilly areas.
Shrinkage allowance:-
Payment shall be made for the gross measurements either in stacks or
in wagons without any deduction for shrinkage voids. However, when
ballast supply is made in wagons, shrinkage up to 8% shall be
permitted at destination while verifying the booked quantities by the
consignee.
27
i) L1, L3, L2 & L4 are length of bottom and top of both sides
respectively.
28
ii) B1, B3, B2 & B4 are the breadth of bottom and top on both
sides respectively
iii) H1, H3, H2 & H4 are the height taken from four
representative
locations, chosen at random. However, if necessary, more
heights can be recorded.
It is understood that the accepted rates for ballast are for materials,
which conform in all respects with the specifications laid down. If the
Engineer or his representative, deputed to measure the ballast
supplied, feels that any of above conditions and specifications have
not been fully complied with, he is at liberty to:
i) Refuse to measure the ballast supplied after communicating his
reasons in writing and to,
ii) Call upon in writing to bring the ballast up to the specifications by
either re screening the ballast to conform to the specified sizes and
grading or to re stack it to proper shape and size to enable re-
inspection and measurement and the contractor shall have no claim,
whatsoever on this account.
29
REJECTED MATERIALS:
i. The contractor/s is/are advised to bring only such material at the site
which conforms to the specifications, as given above. Any material
which fails short of the prescribed standards will be rejected and will
have to be removed by the contractor at his/their own expenses as
laid down in Para 9.13.2 below. It should be noted that all materials
will be passed at the site of delivery only. No passing will be carried
out at the sources or anywhere else.
ii. The Engineer shall mark all rejected ballast in any manner he thinks
fit to prevent rejected ballast being mixed with good ballast and the
contractor/s shall remove the rejected ballast to such places as may
be directed by the Engineer within a fortnight from the date of order
of removal. In the event of the contractor failing to do so, the Engineer
may cause it to be removed and all cost of such removal shall be
payable by the contractor/s to the Railway and without prejudice to
any other mode of recovery may be deducted from any money that
maybe due or may be come due to contractor from the contractors
bill for any other works awarded by the Railway on demand.
30
2. Fill the mold to 1/3 full by volume (about 2 1/2 inches), and rod the
bottom layer with 25 evenly spaced strokes.
3. Fill the mold to 2/3 full (about 6 inches), and rod the second layer
with 25 strokes penetrating the top of the bottom layer.
4. Heap the concrete on top of the mold, and rod the top layer with 25
strokes penetrating the top of the second layer.
5. Strike off the top surface of the concrete even to the top of the mold.
6. Remove the mold carefully in the vertical direction (take about five
seconds).
3. Tap the sides of the container with a rubber mallet to remove large air
bubbles.
6. Tap the sides of the mold with a rubber mallet to close voids made by
the tamping rod.
1 These special conditions and the work schedule shall govern the
works to be executed under this contract in addition to and/or in
part suppression of the General Conditions of Contract -2010 and
Standard Specifications as laid down in the Indian Railways Unified
Standard Specifications (Works and Material) -2010 as amended by
correction slips on or before the opening of tender.
4 As far as possible the tenderer(s) bid should not have any condition
or specification or assumption contrary to the provisions in these
tender documents on which the tenderer(s) bid is based.
Tenderer(s) own special conditions, not in conformity with the
tender specifications, are required to be listed separately & shall be
supplemented by the details of exact financial implications if
applicable. Tenderer(s) special conditions, not in conformity with
the tender specifications, are required to be listed separately.
33
Theodolite
Introduction:
Important Definition
Stone Work
Terminology
Ashlar : Stone masonry using dressed block of given dimensions having faces
perpendicular to each other and laid in courses.
Bed Joint: The joint where one stone presses on another for example, a horizontal
joint in a wall or radiating joint between the voussoirs of arch.
A concrete masonry unit with any one of the external dimensions greater than the
corresponding dimension of a brick and having one or more large holes or cavities
which either pass through the block (open cavity) or do effectively pass through the
block (closed cavity) and having the solid material between 50% and 75% of the
total volume of the block calculated from the over-all dimensions.
Solid Block
Bond Stone (Through stone): Selected long stone used to hold a wall together
transversely.
Corbel : Stone bonded well into the wall with part of it projecting out of the face of
wall to form a bearing surfaces.
38
Dowels : Dowels are small sections of metal, stone or pebbles bedded with mortar
in corresponding mortice in bed or side joint of adjacent stones.
Joggle : A key between the stones by providing a groove in one stone to take a
corresponding concealed projection in the edges on the other stone .
Parapet : A solid or pierced guard wall for flat stone terrace or balcony (or a bridge)
or a curb wall at the lower part of a pitched roof which is exposed to atmosphere on
face back and top.
Quoin : A quoin is the external angle of wall or building. The term is also applied to
stone specially selected and neatly dressed for forming such angle.
Reveal : The part of the jamb between the frame and the arise.
39
Surfacing or Dressing of Stones : The stones are dressed to have different surfaces
as indicated in definitions below.
Self Faced Surfaces : Surfaces of stones used for roofing, flooring, lintels etc., as
obtained from quarry.
Squared Back Surface : Means the surface shall be dressed back at right angles to
the face of the stone.
40
3. Classification
1. Hollow (open and closed cavity) Concrete Blocks
The hollow (open and closed cavity) concrete blocks shall conform
to the following three grades:
Grade A These are used as load bearing units and shall have
a minimum block-density of 1500 kg/m3. These shall be
manufactured for minimum average compressive strengths of
3.5, 4.5, 5.5 and 7.0 N/mm2 respectively at 28 days (see Table
6.6).
(b) Grade B These are also used as load bearing units and shall
have a block density less than 1500 kg/ m3 but not less than 1000
kg/m3. These shall be manufactured for minimum average
compressive strengths of 2.0, 3.0 and 5.0 N/mm2 respectively at 28
days
(c) Grade C - These are used as non-load bearing units and shall
have a block-density less than 1500 kg/m3 but not less than 1000/
m3. These shall be manufactured for minimum average
compressive strength of 1.5 N/mm2 at 28 days.
(d) Grade D The solid concrete blocks are used as load bearing
units and shall have a block density not less than 1800 kg/ m3..
These shall be manufactured for minimum average compressive
strengths of 4.0, and 5.0 N/mm2 respectively at 28 days.
4. Physical Requirements
(a) Compressive Strength: the average crushing strength of
eight blocks, when determined in accordance with IS: 2185
shall be not less than that specified in Table given below:-
42
COPING
PARAPET
DOWEL CORNICE
STRING COURSE
BED JOINT
COPING
METAL CRAMP
PARAPET
JOGGLE JOINT WINDOW SILL
JOGGLE
CORNICE
FIGURE 6.1 B
Plastered face
bushing not more
than 10
Bond or
through stone
one per 0.5
sqm. of wall
surface
Chips not to
exceed 20% of the
quantity of
stone masonry
SECTION ELEVATION
CONCLUSION
***