Contents

1 EXECUTIVE SUMMARY 1
1.1 TITLE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 OBJECTIVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 COMPANY PROFILE . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3.1 SERVICES OFFERED . . . . . . . . . . . . . . . . . . . 2
1.4 Scope of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1.5 Project Deliverables . . . . . . . . . . . . . . . . . . . . . . . . . 4

2 DETAILED PROPOSAL 5
2.1 Milestones . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.1.1 Milestone 1 . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.1.2 Milestone 2 . . . . . . . . . . . . . . . . . . . . . . . . . . 6
2.1.3 Milestone 3 . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2.1.4 Milestone 4 . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.1.5 Milestone 5 . . . . . . . . . . . . . . . . . . . . . . . . . . 9
2.1.6 Project Time-line . . . . . . . . . . . . . . . . . . . . . . . 10
2.1.7 Project Commercials . . . . . . . . . . . . . . . . . . . . . 10

1
March 31, 2017
Chapter 1

EXECUTIVE SUMMARY

1.1 TITLE
Project proposal for design and prototype development an of E-Bike frame de-
sign.

1.2 OBJECTIVES
Design and development of prototype of E-bike frame meeting clients require-
ment to the fullest wherever possible.

1.3 COMPANY PROFILE


Inoventric is a startup engineering company. We are privately owned with a head
office in Chennai and affiliate offices in Chennai and its surroundings. Since our
establishment from beginning of 2017, we aim in providing quality engineering
services to clients in INDUSTRY. The ownership group are working members
of our teams involved in all aspects of a project from conception to schematic
to final design and continuing through to the end of the prototype construction.
Our team also has some renowned peoples from various INDUSTRY as a board
of advisors for aiding in providing innovative solutions that meet our clients
needs in an effective and efficient manner. Inoventric works in collaboration
with our clients and their other engineering teams to provide quality engineering
service as required by client.

1
1.3.1 SERVICES OFFERED
DESIGN & DESIGN SUPPORT
Feasibility studies
Sustainability and green technology solutions
Pre-project reports and technical studies

Mechanical Engineering Design


Conceptual Component Design
System Design

Packaging and Feasibility


Plastics & Composites
Legacy data conversion, 2d to 3d conversion
Parametric Part modelling

CAD customization
Detailed Design
3D Solid and Surface Modeling

COMPUETR AIDED ENGINEERING


FINITE ELEMENT MODELLING
Solid and shell FE modeling

Complex plastic components, castings and composites

FINITE ELEMENT ANALYSIS


All types of static, quasi-static, linear and non-linear analysis
Metal Forming Analysis

Mold Flow Analysis

OPTIMIZATION
Linear and non-linear optimization (gage, grade and geometry)
Design studies at component and system level
Multi Disciplinary Design Optimization

2
COMPUTATIONAL FLUID DYNAMICS
FLOW REGIMES
Pressure based solver
Pressure based coupled solver
Density based solvers

TURBULENCE MODELING
Spalart-Allmaras
k-epsilon
k-omega
DES
LES
RSM

ANSYS MESHING AND ICEM CFD


Hexahedra
Tetrahedra
Polyhedra
Prisms & Pyramids

HEAT TRANSFER & RADIATION


Convection
Conduction
Radiation and conjugate heat transfer

ROTATING MACHINERY
Frozen Rotor
Stage and Transient Rotor Stator

FLUID STRUCTURE INTERACTION


Permitting combined fluid and solid physics analysis
Both one-way and two-way FSI simulations are possible

3
DYNAMIC & MOVING MESH
Innovative approach to simulating flow conditions in and around moving
objects

1.4 Scope of Work


Inoventric is contracted by client (Deepak) for the design and development of
prototype of an E-Bike frame based on the specification and requirements pro-
vided through e-mails from client (Deepak) for financial consideration of ru-
pees of 2.55 lacs and with timeline of 9 months from the starting date of the
project. This deadline may elongate if any changes are requested in requirement
or specs based on mutual consent during the life cycle of the project. Inoventric
is responsible for all work of their sub-consultants/sub-contractors to meet the
requirements of the project.

1.5 Project Deliverables


Milestone reports
Design drawings

Project Documents
Prototype

4
Chapter 2

DETAILED PROPOSAL

2.1 Milestones
The proposed project is to be done in following five milestones

2.1.1 Milestone 1
Milestone 1 scope
This milestone focuses on literature survey for available frames of an E-Bike.
The literature data is used to identify suitable material and manufacture pro-
cesses. Also benchmarking of various frames are performed to gain insight on
suitable and economical viable frame design. In addition to it criteria such as
cost of fabrication of frame, cost of material and legal criteria for the frame in
Europe.

Milestone 1 deliverables
Literature survey reports

Milestone 1 acceptance criteria


Approval of material selection from client side

Approval of fabrication methods from client side


Approval of approximate cost of frame from client side

*The approvals are to be done through E-mail within 3 days of sub-


mission of milestone deliverables. Fail of approval shall be taken as
approved and proceed with the processes.

5
Milestone 1 Commercial
Fund of INR 20,000 is to be released on the submission of milestone de-
liverables

2.1.2 Milestone 2
Milestone 2 scope
This milestone focuses on generation of ideas for the design of the frame and
concept design. The milestone processes such as Brainstorming of ideas, FMEA,
Cost benefit analysis and rough concept sketching to create a rough concept
design of the E-Bike frame.

Milestone 2 deliverables
Milestone reports
Rough Concept design

Milestone 2 responsibilities
Inoventric
Creation of ideas
Conceptual designs

Thorough investigation of proposed concepts and ideas


Arranging or utilizing human resource for completion of the milestone task
Submission of milestone related documents and data

Client
Providing with requirements

Providing design constrains

Milestone 2 acceptance criteria


Approval of ideas from client side
Approval of concept design from client side

*The approvals are to be done through E-mail within 3 days of


submission of milestone deliverables. Fail of approval shall be taken
as approved and proceed with the processes.

6
Milestone 2 Commercial
Fund of INR 75,000 is to be released on the submission of milestone de-
liverables

2.1.3 Milestone 3
Milestone 3 scope
This milestone focuses on concept designing of the E-Bike frame and validation
of the design . Based on ideation and rough concepts and refined and detailed
concept design is created. This concept design is then validated with various
CAE softwares and experts. All the standards, requirement and specs are to be
finalized at this phase.

Milestone 3 deliverables
Milestone reports
Detailed concept design
Concept design validation documents

Milestone 3 responsibilities
Inoventric
Detailed conceptual designs
Thorough investigation of design
Validation of the design
Integrity assessment of the proposed design
Submission of milestone related documents and data

Client
Providing with European safety requirements
Providing with European design constrains or any design related queries
involving European system

Milestone 3 acceptance criteria


Approval of detailed concept design from client side
Approval of validation study of the concept design from client side
*The approvals are to be done through E-mail within 3 days of sub-
mission of milestone deliverables. Fail of approval shall be taken as
approved and proceed with the processes.

7
Milestone 3 Commercial
Fund of INR 80,000 is to be released on the submission of milestone de-
liverables

2.1.4 Milestone 4
Milestone 4 scope
This milestone focuses on detailed designing of the E-Bike frame and validation
and optimization of the design. Based on engineering analysis data and experts
advices the detailed design is created taking requirement and specs also into
account from client side. The deliverable of this milestone will be the base for
prototype fabrication.

Milestone 4 deliverables
Milestone reports

Detailed design
Detailed design validation documents
Manufacturing design

Milestone 4 responsibilities
Inoventric
Detailed designing
Validation of the detailed design
Integrity assessment of the proposed detailed design

Preparation of manufacturing drawings


Collaboration with subcontractors and experts
Submission of milestone related documents and data

Client
Providing with information regarding European manufacturing capabili-
ties

8
Milestone 4 acceptance criteria
Approval of detailed design from client side
Approval of detailed design validation study from client side
Approval of manufacturing processes

*The approvals are to be done through E-mail within 3 days of sub-


mission of milestone deliverables. Fail of approval shall be taken as
approved and proceed with the processes.

Milestone 4 Commercial
Fund of INR 70,000 is to be released on the submission of milestone de-
liverables

2.1.5 Milestone 5
Milestone 5 scope
This milestone focuses on documentation of the complete project. The docu-
ments comprises of individual milestone reports, technical data, design specs,
manufacturing drawings and other project related documents. This document
serves as a frame manufacturing guideline and also future reference for further
development of the E-Bike.

Milestone 5 deliverables
Milestone reports
Manufacturing drawings
Manufacturing processes report
Technical documents

Milestone 5 responsibilities
Inoventric
Manufacturing processes selection
Manufacturing drawing preparation
Manufacturing cost estimation
Road worthiness establishment
Collaboration with subcontractors and experts for guidance
Submission of milestone related documents and data

9
Client
Providing with information regarding European roadworthy standards

Milestone 5 acceptance criteria


Approval of manufacturing drawings from client side

Approval of selection manufacturing processes from client side

*The approvals are to be done through E-mail within 3 days of


submission of milestone deliverables. Fail of approval shall be taken
as approved and proceed with the processes.

Milestone 5 Commercial
Fund of INR 10,000 is to be released on the submission of milestone de-
liverables

2.1.6 Project Time-line


MILESTONES DURATION IN MONTHS
MILESTONE 1 1 Months
MILESTONE 2 1.5 Months
MILESTONE 3 1.5 Months
MILESTONE 4 1 Months
MILESTONE 5 1 Months
Total duration 6 Months
Overhead of 1 month i.e 6+1 months is to be considered as project
has been squeezed to its maximum limit

2.1.7 Project Commercials


The total fund utilization and cost is briefed below. The price quoted are
negotiable.

PROJECT COST
MILESTONE COST
Milestone 1 20000
Milestone 2 75000
Milestone 3 80000
Milestone 4 70000
Milestone 5 10000
Total Project Cost 255000