Project Value Delivery, 2016 2016-15 rev 0 Discover more on: www.ProjectValueDelivery.com
Page 2 of 2
Getting endorsement of individual budgets and complement the standard terms & conditions of the
schedules at the Work Package level by the Scope organization.
Owner,
The Educational Role of Project Control
Developing and implementing a thorough Contract
at Project Start-Up
awareness program, including for each Project
position, a mandatory knowledge level of certain The Project Control Manager must also ensure that
sections of the Contract. relevant data is properly and timely recorded, and that
individual functions do not implement changes in their
Establishment of Requirements for systems that might jeopardize the overall data streams. In
Suppliers and Contractors
a large measure he needs to educate the entire team about
The requirements for suppliers and contractors need to
their fundamental contribution to Project Control. This
be prepared early in the Project, before critical purchase
generally happens at two levels:
orders or contracts for services are proposed for bid.
Their preparation needs to be coordinated by Project to the entire Project Team,
Control in close relation with Procurement. and to the Project Management Team.
The following describes in general what those The Project Control Manager must intervene regularly in
requirements should cover. It is town-hall meetings, and in particular during the first
important however to scale those overall kick-off meeting with
A thorough and early Project the entire Project team, to
requirements to the size and criticality
Control setup is essential for emphasize the importance of
of the supply or service and taking
Project success timely data recording.
into account the type of contract
(lump-sum or reimbursable). In particular, the full In addition to general
requirements will generally only be needed for a limited communication it is useful to remind function heads in
number of key suppliers and contractors. The full set of the Project Management Team that should they intend to
requirements is unfortunately too often used across the review and amend their processes, they should liaise with
board which is very onerous, in addition to creating many Project Control to check that they dont jeopardize the
non-conformances that need to be managed. overall data recording and management architecture. It
Finally, some of those requirements might be negotiated often happens that when individual functions try to
by the suppliers or contractors. In that case, it is optimize their processes they discard activities that do
necessary for Project Control to be involved in the not add value to themselves but are extremely valuable
review of the deviations requested, in particular on the for the entire Project.
following two aspects: Conclusion
Assess the deviation from the Project risk profile
standpoint, The Project Control setup is absolutely essential and
Assess whether the deviation jeopardizes the overall needs to be performed urgently at Project Start-Up. A
control of the Project. roadmap has been given that will ensure
The requirements to suppliers and contractors should comprehensiveness and success.
include (in addition to the standard contractual clauses of Find all these principles of Project
the organization): Control Management exposed in a
Relevant Contract flow-down from the main comprehensive manner in our new
contract, or general requirements applicable to all Handbook,
suppliers and contractors. Practical Project Control Manager
Clarity on the relevant technical specifications and Handbook
documents that are applicable for each contract or (now published, available
purchase order, and how any update will be in Paperback and Kindle versions!)
transmitted,
Relevant progress measurement standards to be used
consistently by all suppliers and contractors.
Contractual administration requirements
Relevant interface management system between
suppliers, contractors and the Project
Clear as-built documentation requirements (format
and timing). Associate the final payment to the as-
built documentation delivery.
These requirements are generally brought together in a [all links to Amazon.com]
document called special terms & conditions that