Вы находитесь на странице: 1из 30

DB Technical inf.

Tunnel PP

TECHNICAL INFRASTRUCTURE - TUNNEL "Przojna Padina"


Electroenergetics Supply line 10kV

Item No. T.S. Work Description Unit Quantity Unit Price Total
NOTE:
The provided prices encompass preparatory works, delivery of equipment and materials, delivery to the installation location, installation,
connection, finishing works, testing and commissioning, in complete accordance with the textual and graphical

1 PREPARATORY WORKS
1.1 16.2.4.2 The marking of the route with clearing of the
terrain and excavation of a trench for placement
of a cable line in the earth up to a level of
category IV on unregulated terrain. During
excavation necessary measures shall be taken to
protect existing cables m 150
1.2
Marking the route and excavation of a trench in
the walkway with uncovering of layers (gravel,
slab, dry asphalt, accessways, etc.) in earth up to
category IV. During excavation necessary
measures shall be taken to protect existing
cables and other underg
m 585
1.3 16.2.4.3
Construction of cable ducts at the street
crossing. Marking of the route, demolition of
the road surface and excavation of a trench with
dimensions 0.70x1.05m with placement of PCV
pipe 4x100/110mm in the horizontal plane.
Filling in the trench in layers
m 15
1.4 16.2.4.2 Excavation of earth (trench) for creating and
placing cable couplings and in other locations
according to the directives of the supervisory
body, where it is necessary to widen or deepen
the cable trench with filling in with layers and
compacting.
pcs. 1
1.5 16.2.4.5
Placement of support for cable couplings (from
bricks) complete with all corresponding works
calculated per completed coupling.
set 1
1.6 16.2.4.4
Delivery of necessary material and protection of
cables when they are near or intersect with other
underground installations and structures which
the designing engineer did not have information
about, in complete accordance with the
provided technical doc
set 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
1.7 16.2.4.2 Delivery and placement of PVC warning strip
above the placed cables
m 1500
1.8 16.2.4.7 Delivery and placement of route markings for
the cable line on regulated terrain.
pcs. 8
1.9 Delivery and placement of route markings for
the cable line on unregulated terrain.
pcs. 18
1.10 16.2.5
Other non-specific construction works: cleaning
of construction site, rehabilitation of damaged
surfaces and other works according to the
directives of the supervisory body.
set 1
TOTAL PREPARATORY WORKS
NOTE: Cable ducts (PVC pipes and manholes) in the zone of the tunnel and "Technical Centre" structure are planned within construction project,
Book 1.
2 ELECTRICAL INSTALLATION WORKS
2.1 16.2.4.2 Delivery and placement of cable HNE 49-A
4x(1h150/25) 6/10kV, in a linear shaft within
the opened trench and drawing it through the
already placed cable ducts.
m 1560
2.2 16.2.4.5 Delivery and installation of metal brackets on
the exterior of the TS "Dimitrovgrad 1" for
holding cable ends and overvoltage arrestors
(kg. 45)
pcs. 1
2.3 Delivery of material and fabricating cable ends
for external mounting with hardware and
materials for single wire cable type HNE 49-A
4(1 h 150/25) 6/10kV.
Complete works, brackets, clamps, hardware
and mounting tools according to the
manufacturer's cata pcs. 4
2.4 Delivery and installation of overvoltage arrestor
12kV; 10kA with hardware for mounting and
connection.
pcs. 3
2.5 Delivery of material and fabricating cable ends
for internal mounting with hardware and
materials for single wire cable type HNE 49-A
4(1 h 150/25) 6/10kV.
Complete works, brackets, clamps, hardware
and mounting tools according to the
manufacturer's cata pcs. 12
2.6
Delivery of materials and fabrication of cable
couplings with hardware for single wire cable
type HNE 49-A 4x(1h150/25) 6/10kV.
Complete works, hardware and mounting tools
according to the manufacturer's catalogue.

pcs. 1
2.7 15.4.2.3
Delivery and placement of telecommunications
cable TK 59 2 h 4 k 0.6mm in the opened trench
with drawing of cable through already placed
cable ducts. Complete TM line with cable
hardware and material.

m 1600
2.8 16.2.4.2 Installation of cable into the connection TS by
drawing through already placed cable ducts with
fabrication of brackets and clamps for fastening
cables.
set 4
2.9 16.2.5
Non-specific electrical installation works
according to the needs on site and directives of
the supervisory body, markings and number
plates with data on cables, etc.
set 1
TOTAL ELECTRICAL INSTALLATION WORKS
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
3 FINISHING WORKS
3.1 16.2.5 Geodetic recording of placed cable line with
drawing of route in technical documentation and
cadastre of underground installations of RGZ
with all necessary details. Complete route of
cable line with all appropriate details (payment
on the basis of invoic km 1.5
3.2 Power supply testing of cable line (1E10+1TM)
between cable connections, "phasing" of cable
wires with testing, placement and seal of cable
number plate with data from the protocol on
conducted tests. Payment on the basis of
invoice.
pcs. 2
3.3
Expenses for powering the control of the
distribution network with the necessary number
of manipulations according to conducted tests.
Payment on the basis of invoice.
pcs. 1
3.4
Expenses for competent public companies and
institutions for conducting technical supervision
during construction of the structure
(distribution, roads, waterworks, etc.) Payment
according to price list for provided services.

lump sum
TOTAL FINISHING WORKS
TOTAL Electroenergetics Supply line 10kV

Electric power engineering TS 1 10/0.4kV

Note:
This Bill of Quantities includes all equipment and material according to the enclosed single-pole scheme. Included are also installations of TS
lighting and earthing. The price under items includes all costs of delivery, transport and mounting on si

Item No. T.S. Work Description Unit Quantity Unit Price Total
1 TS FACILITY
1.1 16.6.1
Delivery and mounting of standard
prefabricated, mounting - concrete construction
transformer station MBTS capacity of 100KVA
at already prepared location - plateau.
Approximate dimensions of MBTS 4540 x 3450
x 2640 mm.
Statics calculation should be done
pcs. 1
TOTAL TS FACILITY

Note:
Works related to organization of plateau and access road for TS: marking, pegging out, levelling, work out of road structure, laying of humus and
final works are included in the Main Project of engineering structures, Book 7, Sheet 1, Institut za pu
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
2 16.6.3 10 kV PLANT
2.1

Standard classic high voltage block, tin metal


coated, insulated by air, for interior mounting
for rated voltage of 10 kV, Si 12 kV, short
circuit power 250 MVA (lk = 14.5kA)
consisting of four cells (transformer cell, two
output cells and one measuring-c

HV block is of stand-alone structure and made


of twice pickled sheet metal, with completed
metalsheet work and electric finish, painted and
standard tested, with certificate of compliance
for performed testing
The equipment in the plant is in all aspects

`- Disconnector switch 12kV, 630A, 250MVA,


(14.5kA) with installed ground lead and manual
drive at front side, equipped with set of
auxiliary contacts for position signalling (pcs. 1)
pcs. 2

Transformer cell, dimensions 700 x 700 x


1975 mm, equipped with:
- Disconnector switch 12kV, 630A, 250 MVA,
(14.5kA) with installed fuse base and fuses
12kV, 250 MVA, rated current 80A with
triggering mechanism and coil for working
voltage 220V, 50Hz, w

Measuring-connecting cell, with dimensions


700 x 700 x 1975mm, equipped with:
- Disconnector switch, 12kV, 630A, 250MVA,
(14.5kA) with installed ground lead and manual
drive at front side and with set of auxiliary
contacts for position signalling (pcs.

Bonding and connecting material, insulators,


buses Cu 30x5mm, bus lines, safety grounding,
conductors for wiring, flexible tubes etc.
Cells should be equipped with blind scheme,
warning labels, tag plates and kits for
installation. 10 kV distribution b
pcs. 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
2.2 Cabinet for placement of measuring group for
indirect measuring at 10kV side, made of twice
pickled metal sheet, with lock (ED lock) and
seal, approx. dimensions 500 x 600 x 260mm,
with completed metalsheet work and electric
finish, painted and tested, wi

Cabinet contains the following equipment:


Multifunction digital watthour meter (pcs. 1)
with following functions:
- Double rate three-phase double system indirect
watthour meter of active power with indicator
of reached maximum value of mean 15 minute

All clamps should be of same type and tagged


by numbers.
Line of serial clamps has to be secured in order
to disable access to ends of conductors. Clamps
are under the cover, which must have leaden
seal. The doors of cabinet must open up to an
angle of 13

Measuring group must be completely in


accordance with Regulatory requirements and
recommendations of Electric Power Supply
Company of Serbia. pcs. 1
2.3
Measuring voltage and current lines for
connecting of watthour meter to voltage and
current measuring transformers in 10kV
measuring cell are made of PP00 type cables of
10x2.5 mm2, 10m long (or of single-wire
copper conductors of P, P/J type) without ext
set 1
TOTAL 10 kV PLANT
3 16.6.2 TRANSFORMATION 10/0.4 kV
3.1 Three-phase power transformer, power 630kVA,
transformation ratio 10.000 2 x 2.5%/420V
coupling Dyn5, with natural cooling in oil
(ONAN) and provided with Bucholz relay,
contact thermometer and other standard
accessories.
pcs. 1
3.2
Delivery and installation of elastic transformer
platform with built-in pads (shock absorbers)
under the power transformer.
pcs. 1
3.3 Delivery and installation of reservoir (tub) for
oil collecting under the ET. pcs. 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
3.4 16.6.4

Current connection of transformer cells /


transformer, four single wire XHP 48 cables, 10
kV, Cu; with diameter 1x35mm (one spare),
cables prepared in workshop as standard pieces,
L = 15m,
With clamped cable endings and standard
carriers tested, with i

set 1
3.5 Current connection for power transformer and
low voltage distribution block, painted rails
ECu F30 cross-section 3x(50 x 10) + 50x5mm,
bond length up to 2.00m. set 1
3.6 Other equipment, accessories and material for
installation not specified elsewhere. set 1
TOTAL TRANSFORMATION 10/0.4 kV
4 16.6.3 0.4 kV PLANT
4.1

Standard low voltage block, for interior


installation, for rated voltage of 420 V, current
of 1000A and power u.p. 18 MVA, (26kA) for
connection to power transformer with shaped
copper rails (colored) 3 x (50 x 10 mm) and 50
x 5 mm.
Standard low voltage b

Equipment in low voltage block is in all parts


according to attached single-pole scheme:
Connection field
- Low voltage, 3-pole, automatic, safety switch
for fixed mounting 500V, 1250A, 50Hz, 55kA,
with motor drive, overload protection and short
circuit

`- Ampermeter for building in, up to 1200A


scale for connector to current transformer,
1000/5A, with maximum 15 minute indicator,
dimension 96x96mm. (pcs. 3)
- Voltmeter for building-in, for connector to the
voltage 420/230V, 50Hz with 0-500V scale,
dimen

- Voltmeter switch for measuring phase and


interphase voltages 10A, 500V, 50Hz. (pcs.1)
- Auxiliary relay similar to type PRS-104 with
two switching contacts and signaling label
220V, 50Hz. (pcs. 1)
- Testing plug, twelve-pole panel connector with
auxili

- LV fuse base 100 A, with blind link. (pcs.1)


- Battery of condensers for compensation of
reactive energy, placed in connecting or
distribution field (pcs. 1):
battery of low voltage condensers with dry
dielectric, total installed power 40kVAr, isolated
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total

Distribution field
- 3-pole output (fuse bar) equipped with switch
disconnectors with shared drive and NV fuses
500V for current up to 400A. (pcs.10)
- Connection and bonding material; buses ECu
50 x 10 mm and 50 x 5 mm, bus material,
araldite insulator
pcs. 1
4.2 Other non-specified equipment, accessories and
material for installation, current and voltage
connections for measuring and safety in TS,
made of cables and conductors of PP00 and P/F
types with cross section of 2.5 mm in pipes of
appropriate diameter.
set 1
TOTAL 0.4 kV PLANT
5 LIGHTING IN TS
5.1 16.6.4 Delivery of material and work out of single
lighting spot installation, visible on the wall,
using clips and PP-Y type conductor of 3 x
1.5mm with single pole breaker for wall
mounting, 6A, 250V, OG type with kit for
performing OG installation.
Average l pcs. 4
5.2 16.5.4 Supply and placement of ceiling lights (IP 54)
with bulb 1 x 100W and mounting kit.
pcs. 4
5.3 16.6.4 Delivery of material and work out of electric
installation for monophase on-wall plug by
conductor PP-Y 3x2.5mm2, using installation
kit for this type of installations.
pcs. 1
5.4 Other small non-specified accessories and
material. set 1
TOTAL LIGHTING IN TS
6 EARTHING IN TS
6.1 16.6.3 Outer contour around TS structure, Cu rope of
50mm cross-section, connected with
foundation earth electrode.
Complete excavation and supply of material,
laying and connecting.
pcs. 1
6.2
Foundation earth electrode for the structure is
strip FeZn25x4mm2, laid in structure
foundation, via testing joint and connected to
collection ring.
Complete manpower, material and connecting.

pcs. 1
6.3 Installation for balancing of potential in TS
(work out of collective earth electrode) of zinc
coated steel strip FeZn 25 x 4mm (25m),
completely with connecting: housing of power
transformer, 10 kV plant, 0.4 kV plant, working
earthing of measuring tran pcs. 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
6.4 Resistance measurement of earth electrode
distribution for TS 10/0.4kV joint ground,
includes:
Total resistance measurement of earth electrode
distribution for TS joint ground. (Measured
value must be less than value given in
calculation).
This measuremen pcs. 1
TOTAL EARTHING IN TS
7 OTHER EQUIPMENT
16.6.5
Supply and mounting of other equipment in TS:
- Standard locks (EDB) on all doors of
transformer station. (pcs. 2)
- Single pole scheme of TS made out on red
PVC surface for 10kV side and on purple one
for 1kV. (pcs. 1)
- First Aid Manual for persons inju
set 1
TOTAL OTHER EQUIPMENT
8 PREPARATION AND FINISHING WORKS
8.1 16.6.6
Testing of equipment in TS including the
following:
- Testing and adjustment of safety and voltage
testing of equipment in TS.
- Voltage testing of cable connection of 10kV
transformer cell / transformer, with writing
down, placement and sealing of plates
pcs. 1
8.2 Costs of High voltage plant "ED Jugoistok-Nis"
related to fitting of the new into the existing
electric power network.
Payment on the basis of invoice.
Calculation per one field visit.
set 1
8.3 Preparation and finishing works at transformer
station.
Organization of the construction site, additional
earthing electrodes, additional measurements,
additional safety measures, repair of damaged
surfaces, placing alert and warning plates,
unforeseen wo set 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
8.4
Technical inspection of the facility, work out of
Project of constructed facility, final acceptance
of the facility and startup of regular operation.
Note: Noise certificate (30dB by night and
40dB by day) is provided by the contractor of
construction wor
set 1
TOTAL PREPARATION AND FINISHING WORKS
TOTAL Electric power engineering S 1 10-0.4kV

Electric power engineering TS 2 10/0.4kV

Note:
This Bill of Quantities includes all equipment and material according to the enclosed single-pole scheme. Included are also installations of TS
lighting and earthing. The price under items includes all costs of delivery, transport and mounting on si
Item No. T.S. Work Description Unit Quantity Unit Price Total
1 16.6.3 10 kV PLANT
1.1 Standard classic high voltage block, tin metal
coated, insulated by air, for interior mounting
for rated voltage of 10 kV, Si 12 kV, short
circuit power 250 MVA (lk = 14.5kA)
consisting of four cells (transformer cell, two
output cells and one measuring-c

HV block is of stand-alone structure and made


of twice pickled sheet metal, with completed
metalsheet work and electric finish, painted and
standard tested, with certificate of compliance
for performed testing.
The equipment in the plant is in all aspect
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
Transformer cell, dimensions 700 x 700 x
1,975 mm, equipped with:
- Disconnector switch12kV, 630A, 250 MVA,
(14.5kA) with installed fuse bases and fuses
12kV, 250 MVA, rated current 80A with
triggering mechanism and coil for working
voltage 220V, 50Hz,

Measuring-connecting cell, with dimensions


700 x 700 x 1975mm, equipped with:
- Disconnector switch, 12kV, 630A, 250MVA,
(14.5kA) with installed ground lead and manual
drive at front side and with set of auxiliary
contacts for position signalling (pcs.

Cells should be equipped with blind scheme,


warning labels, tag plates and kits for
installation.
10 kV distribution block unit
pcs. 1
1.2 Cabinet for placement of measuring group for
indirect measuring at 10kV side, made of twice
pickled metal sheet, with lock (ED lock) and
leaden seal, approximate dimensions 500 x 600
x 260mm, with complete metalsheet work and
electric finish, painted and

Cabinet contains following equipment:


Multifunction digital watthour meter (pcs. 1)
with following functions:
- Double rate 3-phase double system indirect
watthour meter of active power with indicator
of reached maximum value of mean 15 minute
active po

- Double rate 3-phase indirect watthour meter of


reactive energy, 100V, 50Hz, 5A, class of
accuracy 3, with breaking element against
backward movement,
- MTK receiver 100V, 50Hz,
- Line of serial clamps VS 16 (pcs. 20),
- Bonding and mounting materia
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
Line of serial clamps has to be secured in order
to disable access to ends of conductors. Clamps
are under the cover, which must have leaden
seal. The doors of cabinet must open up to an
angle of 135o, at least.

Measuring group must be completely in


accordance with Regulatory requirements and
recommendations of Electric Power Supply
Company of Serbia.
pcs. 1
1.3 Measuring voltage and current lines for
connecting of watthour meter to voltage and
current measuring transformers in 10kV
measuring cell are made of PP00 type cables of
10x2.5 mm2, 10m long (or of single-wire
copper conductors of P, P/J type) without ext
set 1
TOTAL 10 kV PLANT
2 16.6.2 TRANSFORMATION 10/0.4 kV
2.1 Three-phase power transformer, power 630kVA,
transformation ratio 10,000 2 x 2.5%/420V
coupling Dyn5, with natural cooling in oil
(ONAN) and provided with Bucholz relay,
contact thermometer and other standard
accessories.
pcs. 1
2.2 Delivery and installation of elastic transformer
platform with built-in pads (shock absorbers)
under the power transformer.

pcs. 1
2.3 16.6.4 Current connection of transformer cells /
transformer, four single wire XHP 48 cables, 10
kV, Cu; with diameter 1x25mm (one spare),
cables prepared in workshop as standard pieces,
L = 15m,
With clamped cable endings and standard
carriers tested, with i
set 1
2.4 Current connection, power transformer and low
voltage distribution block, painted rails ECu
F30 cross-section 3x(50 x 10) + 50x5mm, bond
length up to 2.00m.
set 1
2.5 Other equipment, accessories and material for
installation not specified elsewhere.
set 1
TOTAL TRANSFORMATION 10/0.4 kV
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
3 16.6.3 0.4 kV PLANT
Standard low voltage block, for interior
installation, for rated voltage of 420 V, current
of 1000A and power u.p. 18 MVA, (26kA) for
connection to power transformer with shaped
copper rails (painted) 3 x (50x10mm) and 50x5
mm.
Standard low voltage block

3.1
Connection field
- Low voltage, 3-pole, automatic, safety switch
for fixed mounting 500V, 1250A, 50Hz, 55kA,
with motor drive, overload protection and short
circuit protection, set of auxiliary contacts,
device for parameterization and communication
mo

`- Voltmeter for building-in, for connector to the


voltage 420/230V, 50Hz with 0-500V scale,
dimensions 96 x 96mm. (pcs. 1)
- Voltmeter switch for measuring phase and
interphase voltages 10A, 500V, 50Hz. (pcs.1)
- Auxiliary relay similar to type PRS-104 with
two switching contacts and signaling label
220V, 50Hz. (pcs. 1)
- Testing plug, twelve-pole panel connector with
auxili

LV fuse base 100 A, with blind link. (pcs.1)


- Battery of condensers for compensation of
reactive energy, placed in connecting or
distribution field (pcs. 1):
battery of low voltage condensers with dry
dielectric, total installed power 40kVAr, isolated
f pcs. 1
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
`- Connection and bonding material; buses ECu
50 x 10 mm and 50 x 5 mm, bus material,
araldite insulators, strip FeZn 30x4mm, base
frame, insulated conductors P/F, serial clamps
etc.
Distribution field pcs. 2
The standard low voltage block

3.2 Other non-specified equipment, accessories and


material for installation, current and voltage
connections for measuring and safety in TS,
made of cables and conductors of PP00 and P/F
types with cross section of 2.5 mm in pipes of
appropriate diameter.
set 1
TOTAL 0.4 kV PLANT
4 LIGHTING IN TS
4.1 16.6.4 Delivery of material and work out of single
lighting spot installation, visible on the wall,
using clips and conductor of PP-Y 3 x 1.5mm
with single pole breaker for mounting on wall,
6A, 250V, OG type with kit for performing OG
installation.
Average len
pcs. 4
4.2 16.5.4 Supply and placement of ceiling lights (IP 54)
with bulb 1 x 100W and mounting kit.
pcs. 4
4.3 16.6.4 Delivery of material and work out of electric
installation for monophase on-wall plug by
conductor PP-Y 3x2,5mm2, using installation
kit for this type of installations.
pcs. 1
4.4 Other small non-specified accessories and
material. set 1
TOTAL LIGHTING IN TS
5 EARTHING IN TS
5.1 16.6.3 Installation for balancing of potential in TS
(work out of collective earth electrode) of zinc
coated steel strip FeZn 25 x 4mm (25m),
completely with connecting: housing of power
transformer, 10 kV plant, 0.4 kV plant, working
earthing of measuring tran
pcs. 1
5.2 Resistance measurement of earth electrode
distribution for TS 10/0.4kV joint ground,
includes:
Total resistance measurement of earth electrode
distribution for TS joint ground. (Measured
value must be less than value given in
calculation).
This measuremen
pcs. 1
TOTAL EARTHING IN TS
DB Technical inf. Tunnel PP

Item No. T.S. Work Description Unit Quantity Unit Price Total
6 OTHER EQUIPMENT
6.1 16.6.5 Supply and mounting of other equipment in TS:
- Standard locks (EDB) on all doors of
transformer station. (pcs. 2)
- Single pole scheme of TS made out on red
PVC surface for 10kV side and on purple one
for 1kV. (pcs. 1)
- First Aid Manual for persons inju

- User's manual "Golden rules". (pcs. 1)


- Warning plates on the outer side of the TS
door (pcs. 2)
- Red safety rods with alert plates. (pcs. 3)
- Table of maximum allowed values of
transformer station grounding resistance, with
data on type of protecti
set 1
TOTAL OTHER EQUIPMENT
7 PREPARATION AND FINISHING WORKS
7.1 16.6.6 Testing of equipment in TS including the
following:
- Testing and adjustment of safety and voltage
testing of equipment in TS.
- Voltage testing of cable connection of 10kV
transformer cell / transformer, with writing
down, placement and sealing of plates

pcs. 1
7.2 Costs of High voltage plant "ED Jugoistok-Ni"
related to fitting of the new into the existing
electric power network.
Payment on the basis of invoice.
Calculation per one field visit.
set 1
7.3 Preparation and finishing works at transformer
station.
Organization of the construction site, additional
earthing electrodes, additional measurements,
additional safety measures, repair of damaged
surfaces, placing alert and warning plates,
unforeseen wo
set 1
7.4 Technical inspection of the facility, work out of
Project of constructed facility, final acceptance
of the facility and startup of regular operation.
Note: Noise certificate (30dB by night and
40dB by day) is provided by the contractor of
construction wor
set 1
TOTAL PREPARATION AND FINISHING WORKS
TOTAL Electric power engineering S 2 10-0.4kV
Summary Przojna padina - TECHNICAL INFRASTRUCTURE
1 Electroenergetics Supply line 10kV
2 Electric power engineering S 1 10-0.4kV
3 Electric power engineering S 2 10-0.4kV
SUB-TOTAL
UNFORSEEN WORK 5% of Sub-total

TOTAL PRZOJNA PADINA - TECHNICAL INFRASTRUCTURE


DB Technical inf. Tunnel PP

Summary Tunnel PRZOJNA PADINA


1 CONSTRUCTION
2 DRAINAGE
3 HYDRANT NETWORK
4 TECHNICAL INFRASTRUCTURE

TOTAL TUNNEL PRZOJNA PADINA


DB Technical inf. Tunnel Progon

TECHNICAL INFRASTRUCTURE - TUNNEL "PROGON"


Electroenergetics Supply line 10kV

Item No. T.S. Work Description Unit Quantity Unit Price Total
NOTE:
The provided prices encompass preparatory works, delivery of equipment and materials, delivery to the installation location, installation,
connection, finishing works, testing and commissioning, in complete accordance with the textual and graphical portion of the design and
valid technical regulations and norms for this type of structure.

1 PREPARATORY WORKS
16.2.4.2 1.1
The marking of the route with clearing of the
terrain and excavation of a trench for placement
of a cable line in the earth up to a level of
category IV on unregulated terrain. During
excavation necessary measures shall be taken to
protect existing cables and other underground
installations.
The forming of bed of fine-grain earth in two
layers of 10 cm each below and above the cable.
Filling in the trench with compacting in layers
and that done manually for 30cm above the
cables and the remaining part by machine.
Loading and transport of excess earth to a
dumping area or planing it flat.
The trench shall have dimensions 0.50x0.80m
for two cables in the ground (1E10+1TM)

m 110
1.2

Marking the route and excavation of a trench in


the walkway with uncovering of layers (gravel,
slab, dry asphalt, accessways, etc.) in earth up to
category IV. During excavation necessary
measures shall be taken to protect existing
cables and other underground installations.
The forming of bed of fine-grain earth in two
layers of 10 cm each below and above the cable.
Filling in the trench with compacting in layers
and that done manually for 30cm above the
cables and the remaining part by machine.
Loading and transport of excess earth to a
dumping area or planing it flat.
Repair of walkway surface with returning the
finishing layer to its original state.
The trench shall have dimensions 0.50x0.80m
for two cables in the ground (1E10+1TM)

m 1785
16.2.4.3 1.3
Construction of cable ducts at the street
crossing. Marking of the route, demolition of
the road surface and excavation of a trench with
dimensions 0.70x1.05m with placement of PCV
pipe 4x100/110mm in the horizontal plane.
Filling in the trench in layers, returning the road
surface to its original state, loading and
transport of excess excavated material to a
dumping area or planing it flat.

m 8
16.2.4.2 1.4 Excavation of earth (trench) for creating and
placing cable couplings and in other locations
according to the directives of the supervisory
body, where it is necessary to widen or deeping
the cable trench with filling in with layers and
compacting.
pcs. 1
16.2.4.5 1.5
Placement of support for cable couplings (from
bricks) complete with all corresponding works
calculated per completed coupling.
set 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
16.2.4.4 1.6
Delivery of necessary material and protection of
cables when they are near or intersect with other
underground installations and structures which
the designing engineer did not have information
about, in complete accordance with the
provided technical documentation and valid
regulations.

set 1
16.2.4.2 1.7 Delivery and placement of PVC warning strip
above the placed cables
m 4000
16.2.4.7 1.8 Delivery and placement of route markings for
the cable line on regulated terrain.
pcs. 18
1.9 Delivery and placement of route markings for
the cable line on unregulated terrain.
pcs. 14
16.2.5 1.10
Other non-specific construction works: cleaning
of construction site, rehabilitation of damaged
surfaces and other works according to the
directives of the supervisory body.
set 1
NOTE: Cable ducts (PVC pipes and manholes) in the vicinity of the tunnel and bridges are envisaged within the construction design for
the "Progon" tunnel and bridge No. 4.
The cable ducts in the vicinity of the "Technical Centre" is envisaged within Book 8.13.9.4/9 , Book 13.

TOTAL PREPARATORY WORKS


2 ELECTRICAL INSTALLATION WORKS
16.2.4.2 2.1 Delivery and placement of cable HNE 49-A
4x(1h150/25) 6/10kV, in a linear shaft within
the opened trench and drawing it through the
already placed cable ducts.
m 3900
16.2.4.5 2.2 Delivery of material and fabricating cable ends
for internal mounting with hardware and
materials for single wire cable type HNE 49-A
4(1 h 150/25) 6/10kV.
Complete works, brackets, clamps, hardware
and mounting tools according to the
manufacturer's catalogue
pcs. 24
2.3
Delivery of materials and fabrication of cable
couplings with hardware for single wire cable
type HNE 49-A 4x(1h150/25) 6/10kV.
Complete works, hardware and mounting tools
according to the manufacturer's catalogue.
pcs. 1
15.4.2.3 2.4
Delivery and placement of telecommunications
cable TK 59 2 h 4 k 0.6mm in the opened trench
with drawing of cable through already placed
cable ducts. Complete TM line with cable
hardware and material.
m 3950
16.2.4.2 2.5 Installation of cable into the connection TS by
drawing through already placed cable ducts with
fabrication of brackets and clamps for fastening
cables.
set 6
16.2.5 2.6
Non-specific electrical installation works
according to the needs on site and directives of
the supervisory body, markings and number
plates with data on cables, etc.
set 1
TOTAL ELECTRICAL INSTALLATION WORKS
3 FINISHING WORKS
16.2.5 3.1 Geodetic recording of placed cable line with
drawing of route in technical documentation and
cadastre of underground installations of RGZ
with all necessary details. Complete route of
cable line with all appropriate details (payment
on the basis of invoice).
pcs. 4
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
3.2 Power supply testing of cable line (1E10+1TM)
between cable connections, "phasing" of cable
wires with testing, placement and seal of cable
number plate with data from the protocol on
conducted tests. Payment on the basis of
invoice.
pcs. 3
3.3
Expenses for powering the control of the
distribution network with the necessary number
of manipulations according to conducted tests.
Payment on the basis of invoice.
pcs. 1
3.4
Expenses for competent public companies and
institutions for conducting technical supervision
during construction of the structure
(distribution, roads, waterworks, etc.) Payment
according to price list for provided services.

lump sum
TOTAL FINISHING WORKS
TOTAL Electroenergetics Supply line 10kV

Electric power engineering S 1 10-0.4kV

Note:
This Bill of Quantities includes all equipment and material according to the enclosed single-pole scheme. Incorporate parts are also
installations of TS lighting and earthing. The price under items includes all costs of delivery, transport and mounting on site.

Item No. T.S. Work Description Unit Quantity Unit Price Total
1 TS FACILITY
1.1 16.6.1

Delivery and mounting of standard


prefabricated, mounting - concrete construction
transformer station MBTS capacity of 100KVA
at already prepared location - plateau.
Approximate dimensions of MBTS 4540 x 3450
x 2640 mm.
Statics calculation should be done for soil
capacity of 1 daN/cm.
Specified cable duct should be placed for cable
guiding into TS.
Sidewalk should be made of sidewalk plates on
gravel layer of min. thickness 5cm.
Chosen technical solutions must be in
accordance with requirements of responsible
Electric Power Supply Company.
MBTS shall be in all aspects in accordance with
technical description, technical requirements,
graphical documentation and type, adopted by
the Expertise Board of the responsible Electric
Power Supply Company.

pcs. 1
TOTAL TS FACILITY

Note:
Works related to organization of plateau and access road for TS: marking, pegging out, levelling, work out of road structure, laying of
humus and final works are included in the Main Project of engineering structures, Book 7, Sheet 1, Institut za puteve a.d. Belgrade.
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
2 16.6.3 10 kV PLANT
2.1
Standard classic high voltage block, tin metal
coated, insulated by air, for interior mounting
for rated voltage of 10 kV, Si 12 kV, short
circuit power 250 MVA (lk = 14.5kA)
consisting of four cells (transformer cell, two
output cells and one measuring-connecting cell)
dimensions 2800 x 700 x 1975mm, for
connection of cables type 3 x XNE-49A 1 x
150/25mm2, 10kV, at front side.
HV block is of stand-alone structure and made
of twice pickled sheet metal, with completed
metalsheet work and electric finish, painted and
standard tested, with certificate of compliance
for performed testing.

The equipment in the plant is in all aspects in


accordance with enclosed single-pole and 3-
pole schemes:
Output-input cell, with approximate
dimensions 700 x 700 x 1,975mm, equipped
with:
- Disconnector switch 12kV, 630A, 250MVA,
(14.5kA) with installed ground lead and manual
drive at front side, equipped with set of
auxiliary contacts for position signalling (pcs.1)

pcs. 2

Transformer cell, dimensions 700 x 700 x


1,975 mm, equipped with:
- Disconnector switch 12kV, 630A, 250 MVA,
(14.5kA) with installed fuse bases and fuses
12kV, 250 MVA, rated current 80A with
triggering mechanism and coil for working
voltage 220V, 50Hz, with push button for
manual switch off, completed with manual drive
at front side and set of auxiliary contacts for
position signalling (pcs. 1)
pcs.1
Measuring-connecting cell, with dimensions
700 x 700 x 1975mm, equipped with:
- Disconnector switch, 12kV, 630A, 250MVA,
(14.5kA) with installed ground lead and manual
drive at front side and with set of auxiliary
contacts for position signalling (pcs. 1.)
Bipole insulated voltage measuring transformer
of transformation ratio 10/0.1kV, class 3, core
power 50VA- (pcs. 1.)

Current measuring transformer of


transformation ratio 2x30/5A/A, class 1, Fs = 5,
core power 30VA - (pcs. 2.)
pcs.1
Bonding and connecting material, insulators,
buses Cu 30x5mm, bus lines, safety grounding,
conductors for wiring, flexible tubes etc.
Cells should be equipped with blind scheme,
warning labels, tag plates and kits for
installation.
10 kV distribution block unit

pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
2.2
Cabinet for placement of measuring group for
indirect measuring at 10kV side, made of twice
pickled metal sheet, with lock (ED lock) and
leaden seal, approx. dimensions 500 x 600 x
260mm, with completed metalsheet work and
electric finish, painted and tested, with
certificate of compliance for performed testing.
Cabinet should be installed at wall of HV
equipment room, at height of 1.20 m from floor

Cabinet contains the following equipment:


Multifunction digital watthour meter (pcs. 1)
with following functions:
- Double rate three-phase double system indirect
watthour meter of active power with indicator
of reached maximum value of mean 15 minute
active power in the accounting period, for 100V,
50Hz, 5A, class of accuracy 1, with break
element against backward movement, with at
least 5 full figures at display.
- Double rate three-phase indirect watthour
meter of reactive energy, 100V, 50Hz, 5A, class
of accuracy 3, with breaking element against
backward movement,
- MTK receiver 100V, 50Hz,
- Line of serial clamps VS 16 (pcs. 20),
- Connecting and mounting material.

All clamps should be of same type and tagged


by numbers.
Line of serial clamps has to be secured in order
to disable access to ends of conductors. Clamps
are under the cover, which must have leaden
seal. The doors of cabinet must open up to an
angle of 135o, at least.

Measuring group must be completely in


accordance with Regulatory requirements and
recommendations of Electric Power Supply
Company of Serbia. pcs. 1
2.3
Measuring voltage and current lines for
connecting of watthour meter to voltage and
current measuring transformers in 10kV
measuring cell are made of PP00 type cables of
10x2.5 mm2, 10m long (or of single-wire
copper conductors of P, P/J type) without
extensions. The lines should be laid in metal
flexible pipes of appropriate diameter,
installation steel shield pipe Re 21 or in hard
PVC pipe of diameter 23 mm, using wall
mounting clips. Connecting kit, installation
lines and accessories
set 1
TOTAL 10 kV PLANT
3 16.6.2 TRANSFORMATION 10/0.4 kV
3.1
Three-phase power transformer, power 630kVA,
transformation ratio 10,000 2 x 2.5%/420V
coupling Dyn5, with natural cooling in oil
(ONAN) and provided with Bucholz relay,
contact thermometer and other standard
accessories.
pcs. 1
3.2
Delivery and installation of elastic transformer
platform with built-in pads (shock absorbers)
under the power transformer.
pcs. 1
3.3 Delivery and installation of reservoir (tub) for
oil collecting under the ET.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
3.4 16.6.4
Current connection of transformer cells /
transformer, four single wire XHP 48 cables, 10
kV, Cu; with diameter 1x25mm (one spare),
cables prepared in workshop as standard pieces,
L = 15m,
With clamped cable endings and standard
carriers tested, with installation kit, and in
accordance with accessories catalogue of
responsible Electric Power Supply Company.
set 1
3.5 Current connection, power transformer and low
voltage distribution block, painted rails ECu
F30 cross-section 3x(50 x 10) + 50x5mm, bond
length up to 2.00m.
set 1
3.6 Other equipment, accessories and material for
installation not specified elsewhere.
set 1
TOTAL TRANSFORMATION 10/0.4 kV
4 16.6.3 0.4 kV PLANT
4.1
Standard low voltage block, for interior
installation, for rated voltage of 420 V, current
of 1000A and power u.p. 18 MVA, (26kA) for
connection to power transformer with shaped
copper rails (colored) 3 x (50 x 10 mm) and 50
x 5 mm.
Standard low voltage block is of stand-alone
structure with doors, made of twice pickled
sheet metal, with completed metalsheet work
and electric finish, painted and tested, with
certificate of compliance for performed testing.

Equipment in low voltage block is in all parts


according to attached single-pole scheme:
Connection field
- Low voltage, 3-pole, automatic, safety switch
for fixed mounting 500V, 1250A, 50Hz, 55kA,
with motor drive, overload protection and short
circuit protection, set of auxiliary contacts,
device for parameterization and communication
module (pcs. 1)
- Current measuring transformer of
transformation ratio 1000/5 A, class 1, Fs 5,
core power 10 VA.(pcs.3)

`- Ampermeter for building in, up to 1200A


scale for connector to current transformer,
1500/5A, with maximum 15 minute indicator,
dimension 96x96mm. (pcs. 3)
- Voltmeter for building-in, for connector to the
voltage 420/230V, 50Hz with 0-500V scale,
dimensions 96 x 96mm. (pcs. 1)
- Voltmeter switch for measuring phase and
interphase voltages 10A, 500V, 50Hz. (pcs.1)
- Auxiliary relay similar to type PRS-104 with
two switching contacts and signaling label
220V, 50Hz. (pcs. 1)
- Testing plug, twelve-pole panel connector with
auxiliary relay. (pcs. 1)
Single-phase plug with safety contact 10A,
250V. (pcs.1)
- LV fuse set with link 100/10 A, (pcs.5)
- LV fuse base 100 A, with blind link. (pcs.1)
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total

`- Battery of condensers for compensation of


reactive energy, placed in connecting or
distribution field (pcs. 1):
battery of low voltage condensers with dry
dielectric, total installed power 40kVAr, isolated
fuse disconnector with three high efficiency
fuses NV 160/100A, cable PP00 3x(1x35)mm2
for connection to low voltage terminals of
power transformer. pcs. 1
Distribution field
- 3-pole output (fuse bar) equipped with switch
disconnectors with shared drive and NV fuses
500V for current up to 400A. (pcs.10)
- Connection and bonding material; buses ECu
50 x 10 mm and 50 x 5 mm, bus material,
araldite insulators, strip FeZn 30x4mm, base
frame, insulated conductors P/F, serial clamps
etc. Distribution field
pcs. 2
The standard low voltage block should be
equipped with warning plates and tag labels,
and outputs should be marked with numbers.

pcs. 1
4.2
Other non-specified equipment, accessories and
material for installation, current and voltage
connections for measuring and safety in TS,
made of cables and conductors of PP00 and P/F
types with cross section of 2.5 mm in pipes of
appropriate diameter.
Completely made out connections, manpower,
transport and material.
set 1
TOTAL 0.4 kV PLANT
5 LIGHTING IN TS
5.1 16.6.4 Delivery of material and work out of single
lighting spot installation, visible on the wall,
using clips and conductor of PP-Y 3 x 1.5mm
with single pole breaker for mounting on wall,
6A, 250V, OG type with kit for performing OG
installation.
Average length of lighting spot 6 m.
pcs. 4
5.2 16.5.4 Supply and placement of ceiling lights (IP 54)
with bulb 1 x 100W and mounting kit.
pcs. 4
5.3 16.6.4 Delivery of material and work out of electric
installation for monophase on-wall plug by
conductor PP-Y 3x2,5mm2, using installation
kit for this type of installations.
pcs. 1
5.4 Other small non-specified accessories and
material.
set 1
TOTAL LIGHTING IN TS
6 EARTHING IN TS
6.1 16.6.3 Outer contour around TS structure, Cu rope of
50mm cross-section, connected with
foundation earth electrode.
Complete excavation and supply of material,
laying and connecting.
pcs. 1
6.2
Foundation earth electrode for the structure is
strip FeZn25x4mm2, laid in structure
foundation, via testing joint and connected to
collection ring.
Complete manpower, material and connecting.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
6.3
Installation for balancing of potential in TS
(work out of collective earth electrode) of zinc
coated steel strip FeZn 25 x 4mm (25m),
completely with connecting: housing of power
transformer, 10 kV plant, 0.4 kV plant, working
earthing of measuring transformers, connecting
to foundation earth electrode of the facility by
strip FeZn 25 x 4mm via test joint, as well as
work out of neutral and safety bus by cable
PP00-Y 1 x 50; 1kV, with placement of plate
joint ground.
Complete supply of material, laying and
connecting.

pcs. 1
6.4
Resistance measurement of earth electrode
distribution for TS 10/0.4kV joint ground,
includes:
Total resistance measurement of earth electrode
distribution for TS joint ground. (Measured
value must be less than value given in
calculation).
This measurement should be made with
previous connecting of all other elements of
grounding system, which are connected during
normal operation of TS, to basic earth electrode
of TS (Collective groundline in TS, 10kV cable
coatings etc.
- Inspection of all bonds and connections
between neutral and safety buses with placing
of the label tag for safety ground and sealing the
connection at test junction.

pcs. 1
TOTAL EARTHING IN TS
7 OTHER EQUIPMENT
16.6.5

Supply and mounting of other equipment in TS:


- Standard locks (EDB) on all doors of
transformer station. (pcs. 2)
- Single pole scheme of TS made out on red
PVC surface for 10kV side and on purple one
for 1kV. (pcs. 1)
- First Aid Manual for persons injured by
electric shock. (pcs. 1)
- User's manual "Golden rules". (pcs. 1)
- Warning plates on the outer side of the TS
door (pcs. 2)
- Red safety rods with alert plates. (pcs. 3)
- Table of maximum allowed values of
transformer station grounding resistance, with
data on type of protection from overvoltage in
corresponding low voltage network (pcs. 1)
- Required number of alert plates, name plates
and labels in TS.
- Pocket for holding plant register at the inner
side of distribution door 10 and 1kV. (pcs. 1)
Total for work, material and placement.

set 1
TOTAL OTHER EQUIPMENT
8 PREPARATION AND FINISHING WORKS
8.1 16.6.6
Testing of equipment in TS including the
following:
- Testing and adjustment of safety and voltage
testing of equipment in TS.
- Voltage testing of cable connection of 10kV
transformer cell / transformer, with writing
down, placement and sealing of plates and
protocol number.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
8.2 Costs of High voltage plant "ED Jugoistok-Ni"
related to fitting of the new into the existing
electric power network.
Payment on the basis of invoice.
Calculation per one field visit.
set 1
8.3
Preparing - finishing works in transformer
station. Organization of the construction site,
additional earthing electrodes, additional
measurements, additional safety measures,
repair of damaged surfaces, placing alert and
warning tables, unforseen works and expenses,
detailed inspection of executed works,
examinations, attests and test run of TS.

set 1
8.4
Technical inspection of the facility, work out of
Project of constructed facility, final acceptance
of the facility and startup of regular operation.
Note: Noise certificate (30dB by night and
40dB by day) is provided by the contractor of
construction works in transformer station.

set 1
TOTAL PREPARATION AND FINISHING WORKS
TOTAL Electric power engineering S 1 10-0.4kV

Electric power engineering S 2 10-0.4kV

Note:
This Bill of Quantities includes all equipment and material according to the enclosed single-pole scheme. Incorporate parts are also
installations of TS lighting and earthing. The price under items includes all costs of delivery, transport and mounting on site.

Item No. T.S. Work Description Unit Quantity Unit Price Total
1 TS FACILITY
1.1 16.6.1

Delivery and mounting of standard


prefabricated, mounting - concrete construction
transformer station MBTS capacity of 100KVA
at already prepared location - plateau.
Approximate dimensions of MBTS 4540 x 3450
x 2640 mm.
Statics calculation should be done for soil
capacity of 1 daN/cm.
Specified cable duct should be placed for cable
guiding into TS.
Sidewalk should be made of sidewalk plates on
gravel layer of min. thickness 5cm.
Chosen technical solutions must be in
accordance with requirements of responsible
Electric Power Supply Company.
MBTS shall be in all aspects in accordance with
technical description, technical requirements,
graphical documentation and type, adopted by
the Expertise Board of the responsible Electric
Power Supply Company.

pcs. 1
TOTAL TS FACILITY

Note:
Works related to organization of plateau and access road for TS: marking, pegging out, levelling, work out of road structure, laying of
humus and final works are included in the Main Project of engineering structures, Book 7, Sheet 1, Institut za puteve a.d. Belgrade.
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
2 16.6.3 10 kV PLANT
2.1

Standard classic high voltage block, tin metal


coated, insulated by air, for interior mounting
for rated voltage of 10 kV, Si 12 kV, short
circuit power 250 MVA (lk = 14.5kA)
consisting of four cells (transformer cell, two
output cells and one measuring-connecting cell)
dimensions 2800 x 700 x 1975mm, for
connection of cables type 3 x XNE-49A 1 x
150/25mm2, 10kV, at front side.
HV block is of stand-alone structure and made
of twice pickled sheet metal, with completed
metalsheet work and electric finish, painted and
standard tested, with certificate of compliance
for performed testing.
The equipment in the plant is in all aspects in
accordance with enclosed single-pole and 3-
pole schemes:
Output-input cell, with dimensions 700 x 700
x 1975mm, equipped with:
- Disconnector switch 12kV, 630A, 250MVA,
(14.5kA) with installed ground lead and manual
drive at front side, equipped with set of
auxiliary contacts for position signalling (pcs.1)
pcs. 2

Transformer cell, dimensions 700 x 700 x


1975 mm, equipped with:
- Disconnector switch 12kV, 630A, 250 MVA,
(14.5kA) with installed fuse bases and fuses
12kV, 250 MVA, rated current 80A with
triggering mechanism and coil for working
voltage 220V, 50Hz, with push button for
manual switch off, completed with manual drive
at front side and set of auxiliary contacts for
position signalling (pcs. 1)
pcs.1
Measuring-connecting cell, with dimensions
700 x 700 x 1975mm, equipped with:

- Disconnector switch, 12kV, 630A, 250MVA,


(14.5kA) with installed ground lead and manual
drive at front side and with set of auxiliary
contacts for position signalling (pcs. 1.)
Bipole insulated voltage measuring transformer
of transformation ratio 10/0.1kV, class 3, core
power 50VA- (pcs. 1.)
Current measuring transformer of
transformation ratio 2x30/5A/A, class 1, Fs =
5, core power 30VA - (pcs. 2.)
pcs.1
Bonding and connecting material, insulators,
buses Cu 30x5mm, bus lines, safety grounding,
conductors for wiring, flexible tubes etc.
Cells should be equipped with blind scheme,
warning labels, tag plates and kits for
installation. 10 kV distribution block unit

pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
2.2

Cabinet for placement of measuring group for


indirect measuring at 10kV side, made of twice
pickled metal sheet, with lock (ED lock) and
leaden seal, approx. dimensions 500 x 600 x
260mm, with completed metalsheet work and
electric finish, painted and tested, with
certificate of compliance for performed testing.
Cabinet should be installed at wall of HV
equipment room, at height of 1.20 m from floor
Cabinet contains the following equipment:
- Multifunction digital watthour meter (pcs. 1)
with following functions:

- Double rate three-phase double system indirect


watthour meter of active power with indicator
of reached maximum value of mean 15 minute
active power in the accounting period, for 100V,
50Hz, 5A, class of accuracy 1, with break
element against backward movement, with at
least 5 full figures at display.
- Double rate three-phase indirect watthour
meter of reactive energy, 100V, 50Hz, 5A, class
of accuracy 3, with breaking element against
backward movement,
- MTK receiver 100V, 50Hz,
- Line of serial clamps VS 16 (pcs. 20),
- Connecting and mounting material.
All clamps should be of same type and tagged
by numbers.
Line of serial clamps has to be secured in order
to disable access to ends of conductors. Clamps
are under the cover, which must have leaden
seal. The doors of cabinet must open up to, at
least, an angle of 135.

Measuring group must be completely in


accordance with Regulatory requirements and
recommendations of Electric Power Supply
Company of Serbia. pcs. 1
2.3
Measuring voltage and current lines for
connecting of watthour meter to voltage and
current measuring transformers in 10kV
measuring cell are made of PP00 type cables of
10x2.5 mm2, 10m long (or of single-wire
copper conductors of P, P/J type) without
extensions.
The lines should be laid in metal flexible pipes
of appropriate diameter, installation steel shield
pipe Re 21 or in hard PVC pipe of diameter
23 mm, using wall mounting clips.
Connecting kit, installation lines and
accessories
set 1
TOTAL 10 kV PLANT
3 16.6.2 TRANSFORMATION 10/0.4 kV
3.1 Three-phase power transformer, power 630kVA,
transformation ratio 10,000 2 x 2.5%/420V
coupling Dyn5, with natural cooling in oil
(ONAN) and provided with Bucholz relay,
contact thermometer and other standard
accessories.
pcs. 1
3.2
Delivery and installation of elastic transformer
platform with built-in pads (shock absorbers)
under the power transformer.
pcs. 1
3.3 Delivery and installation of reservoir (tub) for
oil collecting under the ET.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
3.4 16.6.4
Current connection of transformer cells /
transformer, four single wire XHP 48 cables, 10
kV, Cu; with diameter 1x25mm (one spare),
cables prepared in workshop as standard pieces,
L = 15m,
With clamped cable endings and standard
carriers tested, with installation kit, and in
accordance with accessories catalogue of
responsible Electric Power Supply Company.
set 1
3.5 Current connection, power transformer and low
voltage distribution block, painted rails ECu
F30 cross-section 3x(50 x 10) + 50x5mm, bond
length up to 2.00m.
set 1
3.6 Other equipment, accessories and material for
installation not specified elsewhere.
set 1
TOTAL TRANSFORMATION 10/0.4 kV
4 16.6.3 0.4 kV PLANT
4.1
Standard low voltage block, for interior
installation, for rated voltage of 420 V, current
of 1000A and power u.p. 18 MVA, (26kA) for
connection to power transformer with shaped
copper rails (colored) 3 x (50 x 10 mm) and 50
x 5 mm.
Standard low voltage block is of stand-alone
structure with doors, made of twice pickled
sheet metal, with completed metalsheet work
and electric finish, painted and tested, with
certificate of compliance for performed testing.
Equipment in low voltage block is in all parts
according to attached single-pole scheme:

Connection field
- Low voltage, 3-pole, automatic, safety switch
for fixed mounting 500V, 1250A, 50Hz, 55kA,
with motor drive, overload protection and short
circuit protection, set of auxiliary contacts,
device for parameterization and communication
module (pcs. 1)
- Current measuring transformer of
transformation ratio 1000/5 A, class 1, Fs 5,
core power 10 VA.(pcs. 3)

`- Ampermeter for building in, up to 1200A


scale for connector to current transformer,
1500/5A, with maximum 15 minute indicator,
dimension 96x96mm. (pcs. 3)
- Voltmeter for building-in, for connector to the
voltage 420/230V, 50Hz with 0-500V scale,
dimensions 96 x 96mm. (pcs. 1)
- Voltmeter switch for measuring phase and
interphase voltages 10A, 500V, 50Hz. (pcs.1)
- Auxiliary relay similar to type PRS-104 with
two switching contacts and signaling label
220V, 50Hz. (pcs. 1)
- Testing plug, twelve-pole panel connector with
auxiliary relay. (pcs. 1)
Single-phase plug with safety contact 10A,
250V. (pcs.1)

`- LV fuse set with link 100/10 A, (pcs. 5)


- LV fuse base 100 A, with blind link. (pcs. 1)
- Battery of condensers for compensation of
reactive energy, placed in connecting or
distribution field (pcs. 1):
battery of low voltage condensers with dry
dielectric, total installed power 40kVAr, isolated
fuse disconnector with three high efficiency
fuses NV 160/100A, cable PP00 3x(1x35)mm2
for connection to low vo
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total

ltage terminals of power transformer. pcs. 1


Distribution field
- 3-pole output (fuse bar) equipped with switch
disconnectors with shared drive and NV fuses
500V for current up to 400A. (pcs. 10)
- Connection and bonding material; buses ECu
50 x 10 mm and 50 x 5 mm, bus material,
araldite insulators, strip FeZn 30x4mm, base
frame, insulated conductors P/F, serial clamps
etc.
Distribution field
pcs. 2
The standard low voltage block should be
equipped with warning plates and tag labels,
and outputs should be marked with numbers.

pcs. 1
4.2 Other non-specified equipment, accessories and
material for installation, current and voltage
connections for measuring and safety in TS,
made of cables and conductors of PP00 and P/F
types with cross section of 2.5 mm in pipes of
appropriate diameter.
Completely made out connections, manpower,
transport and material. set 1
TOTAL 0.4 kV PLANT
5 LIGHTING IN TS
5.1 16.6.4 Delivery of material and work out of single
lighting spot installation, visible on the wall,
using clips and conductor of PP-Y 3 x 1.5mm
with single pole breaker for mounting on wall,
6A, 250V, OG type with kit for performing OG
installation.
Average length of lighting spot 6 m.
pcs. 4
5.2 16.5.4 Supply and placement of ceiling lights (IP 54)
with bulb 1 x 100W and mounting kit.
pcs. 4
5.3 16.6.4 Delivery of material and work out of electric
installation for monophase on-wall plug by
conductor PP-Y 3x2,5mm2, using installation
kit for this type of installations.
pcs. 1
5.4 Other small non-specified accessories and
material.
set 1
TOTAL LIGHTING IN TS
6 EARTHING IN TS
6.1 16.6.3 Outer contour around TS structure, Cu rope of
50mm cross-section, connected with
foundation earth electrode.
Complete excavation and supply of material,
laying and connecting.
pcs. 1
6.2
Foundation earth electrode for the structure is
strip FeZn25x4mm2, laid in structure
foundation, via testing joint and connected to
collection ring.
Complete manpower, material and connecting.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
6.3
Installation for balancing of potential in TS
(work out of collective earth electrode) of zinc
coated steel strip FeZn 25 x 4mm (25m),
completely with connecting: housing of power
transformer, 10 kV plant, 0.4 kV plant, working
earthing of measuring transformers, connecting
to foundation earth electrode of the facility by
strip FeZn 25 x 4mm via test joint, as well as
work out of neutral and safety bus by cable
PP00-Y 1 x 50; 1kV, with placement of plate
joint ground.
Complete supply of material, laying and
connecting.

pcs. 1
6.4
Resistance measurement of earth electrode
distribution for TS 10/0.4kV joint ground,
includes:
Total resistance measurement of earth electrode
distribution for TS joint ground. (Measured
value must be less than value given in
calculation).
This measurement should be made with
previous connecting of all other elements of
grounding system, which are connected during
normal operation of TS, to basic earth electrode
of TS (Collective groundline in TS, 10kV cable
coatings etc.
- Inspection of all bonds and connections
between neutral and safety buses with placing
of the label tag for safety ground and sealing the
connection at test junction.

pcs. 1
TOTAL EARTHING IN TS
7 OTHER EQUIPMENT
16.6.5
Supply and mounting of other equipment in TS:
- Standard locks (EDB) on all doors of
transformer station. (pcs. 2)
- Single pole scheme of TS made out on red
PVC surface for 10kV side and on purple one
for 1kV. (pcs. 1)
- First Aid Manual for persons injured by
electric shock. (pcs. 1)
- User's manual "Golden rules". (pcs. 1)
- Warning plates on the outer side of the TS
door (pcs. 2)

- Red safety rods with alert plates. (pcs. 3)


- Table of maximum allowed values of
transformer station grounding resistance, with
data on type of protection from overvoltage in
corresponding low voltage network (pcs. 1)
- Required number of alert plates, name plates
and labels in TS.
- Pocket for holding plant register at the inner
side of distribution door 10 and 1kV. (pcs. 1)
Total for work, material and placement.
set 1
TOTAL OTHER EQUIPMENT
8 PREPARATION AND FINISHING WORKS
8.1 16.6.6
Testing of equipment in TS including the
following:
- Testing and adjustment of safety and voltage
testing of equipment in TS.
- Voltage testing of cable connection of 10kV
transformer cell / transformer, with writing
down, placement and sealing of plates and
protocol number.
pcs. 1
DB Technical inf. Tunnel Progon

Item No. T.S. Work Description Unit Quantity Unit Price Total
8.2 Costs of High voltage plant "ED Jugoistok-Ni"
related to fitting of the new into the existing
electric power network.
Payment on the basis of invoice.
Calculation per one field visit.
set 1
8.3
Preparing-finishing works in transformer
station. Organization of the construction site,
additional earthing electrodes, additional
measurements, additional safety measures,
repair of damaged surfaces, placing alert and
warning tables, unforseen works and expenses,
detailed inspection of executed works,
examinations, attests and test run of TS.

set 1
8.4
Technical inspection of the facility, work out of
Project of constructed facility, final acceptance
of the facility and startup of regular operation.
Note: Noise certificate (30dB by night and
40dB by day) is provided by the contractor of
construction works in transformer station.

set 1
TOTAL PREPARATION AND FINISHING WORKS
TOTAL Electric power engineering S 2 10-0.4kV

SUMMARY PROGON - TECHNICAL INFRASTRUCTURE


1 Electroenergetics Supply line 10kV
2 Electric power engineering S 1 10-0.4kV
3 Electric power engineering S 2 10-0.4kV
SUB-TOTAL
UNFORSEEN WORK 5% of Sub-total

TOTAL PROGON - TECHNICAL INFRASTRUCTURE

SUMMARY TUNNEL PROGON


1 CONSTRUCTION
2 DRAINAGE
3 HYDRANT NETWORK
4 TECHNICAL INFRASTRUCTURE

TOTAL TUNNEL PROGON

Вам также может понравиться