Вы находитесь на странице: 1из 34

Introduction of ZTE MW Hardware Installation

and configuration guide


Oct 2015
Agenda |

ZTE Microwave Hardware Installation Flow

ZTE Microwave NR8250 Installation Detail

ZTE Microwave NR8950 installation Detail


ZTE Microwave NR8250 Installation Flow
ZTE Microwave NR8250 Installation (IDU installation)
Installing the IDU inside a 19-inch Portal Frame
ZTE Microwave NR8250 Installation (IDU installation)
Installing a Board

Step 1 Step 3

Step 2 Step 4
ZTE Microwave NR8250 Installation(ODU installation)
ZTE Microwave
Adjusting hardware Installation
the Polarization Mode of an ODU

Vertical Polarization Horizontal Polarization


ZTE Microwave NR8250 Installation(ODU installation)
Adjusting the Polarization Mode of an ODU

Step 1 remove the Guide Pin Step 2 Adjusting the Polarization


ZTE Microwave NR8250 Installation(ODU installation)
Integrated Installation(1+0)
Step 1 remove the waveguide diagram Step 2 put the lubricant
ZTE Microwave NR8250 Installation(ODU installation)
Step 3 installation ODU Step 4 Securing Screws
ZTE Microwave NR8250 Installation(ODU installation)
Separate Installation(1+0 )
Step 1 Install the ODU installation bracket Step 2 Install the ODU on the ODU install bracket
ZTE Microwave NR8250 Installation(ODU installation)
Separate Installation(1+0 )
Step 3 Install the waveguide Step 4 Use flexible waveguide clamps
ZTE Microwave NR8250 Installation(ODU installation)
Separate Installation(2+0 Dual-Polarization )
Step 1 Install the two ODU installation bracket Step 2 Install the ODU on the ODU install bracket
ZTE Microwave NR8250 Installation(ODU installation)
Separate Installation(2+0 Dual-Polarization )
Step 3 Install the waveguide Step 4 Use flexible waveguide clamps
ZTE Microwave NR8250 Installation(cable installation)
Installing the IDU protective Grounding Cable
ZTE Microwave NR8250 Installation(cable installation)
Installing the ODU protective Grounding Cable

a. Cut the protective


grounding cable and
crimp the terminals.
b. Fix one terminal of the
grounding cable on the
grounding screw of the
ODU
c. Connect the other end of
the protective grounding
cable to the grounding
busbar of the metal
tower.
ZTE Microwave NR8250 Installation(cable installation)
Installing Power Cable
Step 1:Markning the terminal Step 2:Connect Power to the IDU
ZTE Microwave NR8250 Installation(cable installation)
Installing Power Cable
Step 3:Install B1 on the DCPD4A Step 4:Bind the power cable

Step 5:Paste the engineering


labels at the two ends of the power
cable
ZTE Microwave NR8250 Installation(cable installation)
Installing Intermediate Frequency Cable

Step 1:Making IF Cable Step 2:Layout and route the IF Cable


ZTE Microwave NR8250 Installation(cable installation)
Routing Intermediate Frequency Cable
Routing the IF cable indoors vertically Routing the IF cable indoors Horizontally
ZTE Microwave NR8250 Installation(cable installation)
Grounding the IF Cable
a. If the antenna is installed on the metal tower , the IF cable should be grounded
at a point about 1-2m below the ODU ,and then be grounded at a point 1.5m
before the bent part where the cable is routed downwards along the tower .
b. If the IF cable is shorten than 20m, it must be grounded at the first two
grounding points
c. If the IF cable is longer than 20m but shorter than 60m,it must be grounded at
the three grounding points
d. If the IF cable is longer than 60m, an additional grounding point must be made
for every additional 20m IF cable.
ZTE Microwave NR8950 Installation Flow
ZTE Microwave NR8950 Installation Detail
Adjusting the Polarization Mode of an ODU

Removing the guide pin Rotate the guide pin 90deg clockwise place the guide pin on the hole
ZTE Microwave NR8950 Installation Detail
Integrated Installation(1+0)
Remove the waveguide diaphragm Put the lubricant
ZTE Microwave NR8950 Installation Detail
Integrated Installation(1+0)
Install AOU Fasten screws
ZTE Microwave NR8950 Installation Detail
Separate Installation(1+0)
Step 1: Install the ODU installation bracket Step 2: Install the NR8950 on the ODU install bracket
ZTE Microwave NR8950 Installation Detail
Separate Installation(1+0)
Step 3: Installing the Flexible Waveguide Step 4: Fix the Flexible Waveguide and result
ZTE Microwave NR8950 Installation Detail
Separate Installation(2+0)
Step 1: Install the ODU installation bracket Step 2: Install the NR8950 on the ODU install bracket
ZTE Microwave NR8950 Installation Detail
Separate Installation(2+0)
Step 3: Install the Flexible Waveguide Step 4: Fix the Flexible Waveguide and result
ZTE Microwave NR8950 Installation Detail
Installing the Protective grounding cable
ZTE Microwave NR8950 Installation Detail
Installing the Power Cable
ZTE Microwave NR8950 Installation Detail
Installing the Ethernet Cable
ZTE Microwave NR8950 Installation Detail
Installing the Optical Fiber
ZTE Microwave NR8950 Installation Detail
Installing the XPIC Cross-Connect Cables