Академический Документы
Профессиональный Документы
Культура Документы
Tunneling
north american Dec 2012/Jan 2013
www.tunnellingjournal.com
journal
ADVANCES IN AUSTIN
JOLLYVILLE WATER TRANSMISSION MAIN
MAKES GREAT PROGRESS
Tunnelling
www.tunnellingjournal.com Dec 2012/Jan 2013
LEES SLIPFORMING
SOLUTION
BARTON - TBM AND D&B
TBMS IN MINING
12-11-09_206_ID006_eAz_Baku_Tunnelling Journal_210x297mm_4c_oc_Fassung 01
h e r r e n k n ec h t AG | ut i li ty t un n e l l i ng | T r a f f i c tu n n e lli ng AZ ER B A I J A N
B A KU | A zER B A I J A N
PR OJEC T D ATA CONTRACTOR
S-599, EPB Shield Azertunelmetro-
Diameter: 6,250mm tikinti
Cutterhead power: 945kW
Tunnel length: 3,600m
Geology: limestone, silty clay
and sand
Herrenknecht Tunnelling
Systems USA, Inc.
1613 132nd Ave E, Suite 200
Sumner, WA 98390
Phone +12534472300
Fax +12538639376
marketing@herrenknecht.com
www.herrenknecht.com
contentS
Right: Cable breakthrough
(p6)
Below: Saverne TGV (p10)
5 Editors comment
6 Snapshots of
www.tunnellingjournal.com news
56 Product News
58 Contacts
TUNNELLING JOURNAL 3
To complete your whole.
Underground Construction
From Mapei UTT line: Reliable technology for underground
construction
Alkali-free set accelerators for shotcrete.
Products for mechanized tunneling: foaming agents for soil conditioning,
polymers, sealants, lubrificants.
Products for grouting and consolidation.
Products for concrete repairing, protection and coating.
Products for waterproofing: synthetic waterproofing membranes, waterproofing
accessories.
Discover the world of Mapei: www.utt-mapei.com, hq.utt@utt.mapei.com
For 75 years weve been helping to build large and small projects.
TJ_1212_005_COMMENT.qxd:Feature 18/12/12 00:18 Page 5
editorScomment
Take a break
I WAS TALKING WITH a friend Stiffness of the material if that
recently who explained how when information is available.
he was working as an engineer in If the results could be e-mailed to
London in the 1980s on some us here at Tunnelling Journal
hand dug piles, a geotechnical (tris@tunnellingjournal.com) then
engineer and himself thought it we can have them published and
would be an interesting exercise to distributed to all, with the hope
measure the heave in the London that this will lead to a greater
Clay over the Christmas and New understanding of the behaviour of
Year break. Between them they the ground in London - helping
hammered some reinforcing bars, clients, contractors and
guarded suitably, into the bottom consultants and possibly prompt
of the excavation at the end of the future research into this effect.
final shift and then levelled these And lets not just keep this UK-
against a fixed reference point on centric, wherever you are in the
the segmental lining. world and whatever ground
Unfortunately upon their return conditions you are working in, this
they werent quite quick enough could still be applied. If youre
to obtain accurate readings before taking a break, lets see what
the miners dislodged them. happens to the ground. Its so easy
Nevertheless, it got us thinking. If to do, but could throw up some
there are enough like-minded intriguing results!
engineers out there, and with the On a final note, I was chatting
amount of underground with a student Civil Engineer just
construction work now being the other week and he said he
undertaken in London, we was really struggling to find a
probably have a once in a summer work placement that he
generation opportunity to obtain
results for heave from a range of
locations and ground types over
needs for his course, and that he
was not alone in this dilemma,
many of his student counterparts
If you are a
tunnelling company
and you have
any extended breaks, not were in the same situation. Now
necessarily just Christmas. This we all hear regularly about the
interest in taking
may well help inform us all on lack of young engineers around on a summer Civil
how the ground behaves plus these days, so why are these Engineering
provide extremely useful possible future tunnelling
information for future projects. So, engineers struggling for summer student then drop
how about it? The additional assignments? If you are a us a line and well
information we would need, if tunnelling company and you have
interest in taking on a summer
try and marry you
possible, would be the following:
The depth of excavation, Civil Engineering student then up with the right
Ground type,
Size of excavation,
Duration between readings
Weather conditions over the
drop us a line and well try and
marry you up with the right
candidate. And alternatively, if you
are a student in need of a summer
candidate.
break, placement, drop TJ a line and well
Current groundwater conditions see how we can help.
is it under-drained/dewatered,
and Tris Thomas
TUNNELLING JOURNAL 5
TJ_1212_NEWS_006_008.qxd:Feature 15/12/12 22:28 Page 6
6 TUNNELLING JOURNAL
TJ_1212_NEWS_006_008.qxd:Feature 15/12/12 22:29 Page 7
The tunnel will also have to be connected to months after the company won the tender
the existing sewer network at both ends. as part of the Salini Costruttori/Maire
Deadline for expressions of interest Tecnimont/Seli JV.
for the project, which will run for an The EPBM, worth roughly 7M was
estimated seven years from contract designed and built in 10 months in
award to finish, is 10 December. collaboration with Kawasaki. The remaining
Submission must be made via e-mail to machines for the project are scheduled to be
procurementhelpline@scottishwater.co.uk delivered in 2013.
Says President of SELI Spa, Remo
Hong Kong tenders new Grandori, The EPB TBM for the
Boundary Control tunnel Copenhagen metro is the first of the four
November 21, 2012 units that SELI is manufacturing under the
Hong Kongs Civil Engineering and industrial and license agreement with
Development Department (CEDD) has invited Kawasaki. The target of the cooperation
tenders for the contract for the road and with the Japanese giant is to develop and
tunnel works of the $15bn Liantang/Heung manufacture a new line of EPB TBMs The first Copenhagen EPBM is ready
Yuen Wai Boundary Control Point. The works
mainly comprise the construction of a dual
two-lane trunk road including an
approximately 4.8km vehicular tunnel linking
www.meyco.basf.com
TUNNELLING JOURNAL 7
TJ_1212_NEWS_006_008.qxd:Feature 15/12/12 22:29 Page 8
covering the highest segment of the EPB Tunneling Canada Corp, Klaus Ukens has expected to start by 2016 and take seven
TBM market. These TBMs are dedicated to accepted a position within Caterpillar Mining years to complete.
the most challenging projects in the and has relocated to Dortmund, Germany. In
technologically advanced markets, with a this new role Klaus will be responsible for Heijmans to build new
special focus on Europe and North shaping Caterpillars Global Underground Eindhoven station tunnel
America. Mining Strategy. October 24, 2012
Effective November 1st the position ProRail has awarded the contract for the
Strabag wins major previously held by Klaus will be divided into construction of the new Eindhoven station
Chilean hydro project two separate but complimentary roles. The tunnel to Heijmans. The contract is valued at
November 9, 2012 position of Director of Sales will be assumed over 32M. Work planning will start
The Chilean tunnelling division of STRABAG by Craig Bournes. Craig has been a key leader immediately, construction will start in the 1st
SE has signed a US$490M design and build in the sales organization for 16 years and has quarter of 2013 and the entire project will be
contract for the majority of the tunnelling and prior experience in both tunnel design and as completed by the summer of 2016.
civil works totaling 46.5km on the Alto Maipo a geotechnical engineer. A European tendering process was
Hydroelectrical Power Plant one of the The position of Director of Marketing and completed for this contract in which Heijmans
biggest private construction contracts in South Product Support will be assumed by Nick submitted the economically most
America Natale. Nick has spent the last year at advantageous tender. The work will be carried
The client is Alto Maipo SpA, a subsidiary of Caterpillar Tunneling leading marketing efforts out by the Heijmans Civil Engineering and the
the Chilean-based AES Gener and the US- and championing parts growth. In his last 14+ Heijmans Non-residential Building business
based AES Corporation. The scope of works years with Caterpillar Nick has held a variety units. The construction of rail-related and
includes detailed design engineering and the of marketing and product support roles across building-related technical installations also
construction of underground and civil works North America and Europe. forms part of the contract. The station will
of two hydroelectric plants Alfalfal II and Las
Lajas. The complete contract consists of the
tunnels and shafts totaling 46.5km excavated
by drill and blast as well as by TBMs. The
design and construction period starts in
November 2012 and will last for about four
and a half years.
The hydroelectric complex will have a total
capacity of approximately 531MW. The
location of the Alto Maipo Hydro Power Plant
is 50km south east of the city of Santiago,
area in the high Maipo River basin of the
municipal district of San Jos de Maipo
situated in the Andes close to the Argentinean
border with peaks up to 6,500m.
8 TUNNELLING JOURNAL
Tunnel 210x297.qxd:Mise en page 1 5/03/09 18:10 Page 1
NFM Technologies broad range of competences as an OEM in the cutting-edge mechanical sector means that it
can propose innovative technical solutions, integrating specific requirements for each project and guaranteeing
a high level of equipment reliability.
BORING THE
SAVERNE TG
A dual function EPB and rock driving TBM for the eastern line of the French
high speed rail is a first for Herrenknecht. Adrian Greeman reports from site
CARS PARKED OUTSIDE the site offices at way to Bratislava in Slovakia," explains least a highland enough to get in the way.
Ernolsheim-ls-Saverne in the picturesque contractor Spie Batignolles' Alain Lacroix, Hence the tunnel and also a few significant
French Alsace region soon acquire a distinctive project director for the tunnel works for a total structures.
red colouration. It comes from fine particles of 13 company joint venture. Among them are Lot 47 for the tunnel works also includes a
red sand spoil blown about from the nearby architects, consulting engineers and landscape significant viaduct structure and some major
waste heaps firms, contributing to a design build contract earthwork platforms, for example, a 35m high
A series of trucks work continuously to take for the tunnel section. Dodin Campenon embankment. But most of it comprises the
the material away, mostly to nearby canal Bernard, part of the Vinci group, is a second tunnel twin bores and their fitting out.
barge loading points and then further on. But major contractor working with Spie Batignolles These carry the line up to 100m deep
there is still a lot to come as the second of two on the excavation, and tunnel design is by beneath a picturesque, semi-wild and partly
4km long tunnels is driven for the TGV Est Swiss consultant BG Consulting Engineers. wooded highland that is one of the national
high speed rail project. Altogether some 1Mt "This is a first design/build project for the parks of France. The site sits just on the edge
has to be dealt with. client, Rseau Ferr de France," says Lacroix. of a protected area.
The work is part of the 2bn second stage The client has two consultants on its side, The geology is at first sight relatively
of the TGV Est route, which connects Paris to Tracebel and SETEC which designed the straightforward, comprising almost completely
Strasbourg and the German Rhineland border. original alignment and monitor the project. of a medium hard sandstone. There are
A first phase of the line, just over 300km to various subdivisions geologically says Lacroix
Baudecourt near Metz, was finished in 2007 The tunnel works but the rock is essentially similar from one side
with the 320km TGV trains completing their The twin 8.9m diameter parallel bores making to the other.
journey to Strasbourg on the standard line. up the tunnel, are the largest major structure There are complications however. Overlying
Now the remaining 106km of line is being on the new section of the route and in fact on limestone and clay means that there is a
completed, to shave an additional half an hour the whole line. Between Paris and the east for relatively "chaotic" section of ground to get
off the journey to the European Parliament city the first phase, the land is mostly flat and the through at the beginning of the drives, which
and connections onwards to Germany's high original section did not face any great were both made from the Alsace or eastern
speed ICE system. "In fact the line is part of an obstacles. But near the Rhine the Vosges side, and again at the end.
overall trans-European route extending all the Massif rises up, not exactly mountains but at "In the middle of the tunnel too there is a
10 TUNNELLING JOURNAL
TJ_1212_010_015.qxd:Feature 16/12/12 00:52 Page 11
TBMS
GERMA
Rheims
Saarbrucken NY
F R Metz
Gare Champagne-Ardenne Forbach
A
Baudre
N
Chalons-en-Champagne Vendenheim
Naire-sur-Marne C Bar-le-Duc
Nancy
Paris Sanrebourg Saverne
Vitry-le-Francois
E Luneville Strasbourg
LUX.
G E R M
F Saarbrucken A
N
Y
Metz R
Above: The launch sight of the
A Herrenknecht TBM
N Left: Figure 1 Maps showing
C E the location of the tunnel
Tunnel along the complete route
Baudre
Below: Figure 2 Cross section
of the tunnel
Sanrebourg Saverne
Nancy
Vendenheim
Luneville
Strasbourg
Strasbou
urg
BELGIUM
FRANCE AUSTRIA
LIECH. HUNGARY Evacuation Maintenance
SWITZERLAND walkway walkway
TUNNELLING JOURNAL 11
TJ_1212_010_015.qxd:Feature 16/12/12 00:53 Page 12
CLEVER CONVEY
TBMS
12 TUNNELLING JOURNAL
TJ_1212_010_015.qxd:Feature 16/12/12 00:53 Page 13
TBMS
means one disc every three rings on Instead the segments, and grout are delivered length of tunnel, 4km by the end of the drive"
average." by rubber tyred trucks, easily able to run inside says Lacroix.
These could be changed from behind the the clean segment lining. There is a facility to inject silicon accelerator
head. The crews tended to "save up" The delivery vehicles are TSP units by once at the machine he says.
changes until around a dozen could be done Metalliance and carry a full ring of segments For the soft ground sections the ring
at once, stopping the machine perhaps every and an 12m3 tank of grout. sequence also uses a connection made
between the rings using special plastic shear
wedges. These fit into cavities on the side of
the segments, he says. "There are two types,
with 10t capacity and 25t."
The latter stronger shear keys are used for
additional stability in the ring areas, which are
later to be broken through for side
connections. European regulations in the wake
of the Mont Blanc and other fires, now
demand cross passages and there will be
seven of these between the two bores, each
about 5m high by 5m wide. Four of these are
escape passages, with fire hydrant points and
anti-shock wave doors and three will have
equipment rooms additionally. The cross
passages were to have been excavated by
roadheader but the solid nature of the
sandstone proved too
Left: Rubber much and the excavation
tyred delivery of is using drill and blast.
the segments
Progress
Below: View
along the On the first drive good
completed tunnel progress saw some 24m
of drive daily, with a
three or four days. Once in the tunnel the segments are bolted maximum 46m on the main bore. But the
Spoil was carried away with the now normal together during the erection sequence on the pace was likely to be lost somewhat at the
system for larger tunnels, a long conveyor machine and then bolts are removed again difficult centre section, particularly with a hold
provided by Herrenknecht sister company H+E. after grouting at the end of the machine train. up of several days for the changeover to
It drops onto stockpiles at the Alsace end "It is important to make sure the grout is closed mode once again.
where a variety of Komatsu and Caterpillar sound and there is a possibility to reinject if "But in the end we avoided that," says
loaders place the spoil into trucks, which take there are any issues," says Lacroix. The grout Lacroix. It was possible to keep going in open
some to fill areas nearby and the rest for mix is a relatively complex one of sand and mode he says because the ground, while
disposal. gravel, mixed with PFA as well as cement. fractured and in places wet, was never
"There is another contract of the high speed "That helps with delivery over quite a long consistently so. "In fact we hit soft and
line using some near Strasbourg and some weathered ground in just
being disposed" says Lacroix. 7m or 8m thicknesses."
The TBM had a forward
Tunnel Lining probe drill he says which
The tunnel machine installs a segmented lining allowed some preview of
as it goes. That is easier and better than an in the ground up to 40m
situ lining says Lacroix and gives the machine ahead, "though we did
something to push off from. "I am not sure just around 20m of
this rock would prove very suitable for using drilling usually, looking for
grippers." water or soft ground."
The segment rings comprise seven main The difficulty with soft
segments and a half size key, in a universal ground, as much as
ring 2m long. anything is the loss of
The precast units are manufactured nearby pressure on the cutter
says Lacroix. "Quite often we would set up our discs he says, which
own segment works but we found a precast causes directional control
works around 30km north of Strasbourg and problems, with the
have set up the carousels in their existing machine particularly
factory where it is possible to turn out 12 rings tending to drop.
a day." It was a little difficult at first he says but But by skillful use of the
once through the learning curve the output is tilting capacity of the
good. The yard there stores 700 rings with a cutterhead it is possible to
smaller buffer stockpile on site of about 100 avoid such problems he
rings. As with many larger tunnels, and says. Like many machines
particularly by French contractors, the Saverne the cutterhead tilts a few
is not using a rail system for materials delivery. degrees and this reduces
14 TUNNELLING JOURNAL
TJ_1212_010_015.qxd:Feature 16/12/12 00:53 Page 15
TBMS
Tube two
The second bore began in September and has
been going well with 776m driven in October
for example. Lacroix is hoping the difficult
ground in the centre will not differ markedly
from the other bore, and there is no reason
why it should, so that once again the open
mode of the machine can be maintained and
time once more can be saved.
Inside the other bore meanwhile concreting
is underway for the track bed and the two side
platforms, one for emergency evacuation and
the other for maintenance. Both carry services
Above: Tunnel breakthrough in June and cabling. Lights, communication,
equipment, and other fit out has to take place.
the diameter of the cut; instead of carving out probe drilling it is not as much as the The JV also has other work to complete
slightly beyond the radius of the shield it can changeover, and then the changeback, would including substantial earthworks outside and
stay within it. have cost us." the 58m long viaduct on the Lorraine side of
"The steering issue is affected by the Back in the hard ground the machine the tunnel, which presents its own challenges.
reaction of the rock to the machine thrust and continued to make good time on the first Not least is a huge concrete reaction slab to be
by increasing friction you can compensate to drive. Even with one more change to EPB for embedded in the 35m high embankment
some extent for the softer ground." the last section, it emerged two months ahead approach to the tunnel; this must absorb the
Using this technique he says, combined with of schedule in June this year on the Lorraine full energy of an emergency braking of the
a complex guidance system, which Vinci has valley side of the hills. train on the viaduct.
developed in-house, it was possible to inch Dismantling followed and the machine was Tunnel portals, tailored by architects
forwards through the soft patches without any brought back piece by piece to the Spielmann, and landscaping by Bernard Lassus
need to switch mode on the machine. "And Ernolsheim-ls-Saverne starting point. "Both will complete the exteriors in time for train
although you lose some time with the forward drives are made from this end," says Lacroix passage scheduled to begin in 2016.
TUNNELLING JOURNAL 15
TJ_1212_016_020.qxd:Feature 15/12/12 23:00 Page 16
TBMS
Evelyn, the 3.16m diameter
CAT machine being
delivered to site
POWERING
under London What has
Caterpillar done
to Lovats TBMs
post-takeover and
will contractors
notice any
difference?
Kristina Smith
Looking
visited the
down tunnel London Power
following
the machine Tunnels project to
launch find out.
TJ_1212_016_020.qxd:Feature 15/12/12 23:00 Page 17
TBMS
ON THE WESTERN SECTION of the London The 3.16m-diameter TBM, which can work The Cat machine, named Evelyn by local
Power Tunnels project for client National Grid, in open mode or EPB mode, is the fifth large school child Chastity Nyadu-Bekoe is currently
Costain is putting a Cat 139 TBM through its utility size machine for which Caterpillar has constructing the 3.16m id, 7.2km long
paces with support from Skanska and Joseph used a common system design and more western section of a 20km tunnel which will
Gallagher ltd. This is one of the first machines common components. When we were Lovat, run between existing substations at Willesden
to benefit from the fusion of Lovat and our machines were very customised, says in North West London and Hackney in North
Caterpillar engineering, since the latters Benny Lau, senior project manager for Cat. East London, connecting the St Johns Wood
takeover of the former in April 2008. Now, with the acquisition by Caterpillar we substation en route. The longer, 4m id eastern
So far things are looking pretty good. The are leaning towards a modular design. This section is being built by Cleopatra, a
launch was recognised by all who were there improves not only build quality and velocity Herrenknecht EPBM.
to be one of the most seamless launches ever but also enables more efficient product Once Evelyn has completed her run
seen for a Cat/Lovat TBM, says tunnel agent support once the machine is in the field. between Willesden and St Johns Wood, she
Angus Mackenzie. The whole design of the It seems this approach has made a will travel south to build a tunnel between
TBM and Backup, the planning for the launch, difference. I think the Cat takeover of Lovat Wimbledon and Kensal Green, to be built in
the way the TBM/backup fitted together and has probably had more benefits than two drives: 3km from Wandsworth heading
the tech support from Cat, it just worked out disbenefits, says Mackenzie. South to Wimbledon and then 9km from
of the box. The 32km of new cable tunnels are part of Wandsworth, North to Kensal Green.
Quite a contrast from some previous launch National Grids strategy to keep up with Both machines will be driving predominantly
experiences, says Mackenzie, where increasing energy demands in the UKs capital through London Clay, although the
manufacturers have not taken the constraints without having to dig up roads. The tunnels Herrenknecht has two sections where it will
of building a machine inside a tunnel into will carry 400,000V transmission line cables, intersect with the Lambeth group and sand
account whilst mocking up the machine in a with a 4m-diameter stretch between Hackney and gravels of the Harwich formation. So far it
factory environment. Or you find a design and St Johns Wood also designed to has encountered one stretch where it was in
which worked on a computer requires some accommodate additional 132,000v cables to full EPB mode, but is mostly operating in semi-
adjustment once you get out on site. supply distribution networks. EPB mode, using the screw to extract the clay
which must be conditioned with polymer
foam in order that it can be easily handled.
The dual-mode Cat machine will be
TUNNELLING JOURNAL 17
TJ_1212_016_020.qxd:Feature 15/12/12 23:01 Page 18
RELY ON DSI
Self-Drilling
- Dr illing System
S ys
stem Solu
Solutions
tions
AT P
POWER
OWER S
SET
ET Self-Drilling
Self-Drillin Friction Bolt
The improved
proved o one-step
ne-step ffriction
riction bolt
bolt system
sy
Immediate
iate load
load-bearing
-bearing gccapacity
apacit y
Friction
nb bolt
olt pplus
lu s m
mechanical
e c ha nic a l a
anchorage:
nchor a
320 kNNc capacity
a pacit y
Automation
ation unit
unit for
for six
six bolts
bolts perper installation
i n s t a ll a sequence
Quick
k - Safe
S a fe - R
Reliable
elia ble www.alwag.com
North America, USA South America, Chile EMEA, Austria APAC (ASEAN), Australia
www.dsiunderground.com www.dsi-chile.com www.alwag.com www.dsiminingproducts.com/au
HIGH QU
QUALITY
ALLIT Y GASKE
GASKETS
TS
International Exp
Experience
perience
Proven longevityy
www.datwyler.com
18 TUNNELLING JOURNAL
TJ_1212_016_020.qxd:Feature 15/12/12 23:01 Page 19
TBMS
Kensal
Green
Willesden
substation St Johns Wood
substation
es
am
Th
River
Above: Breakthrough
Wimbledon to Kensal Green after 600m. Right:
Cutterhead condition
after 600m
gain share element which is modified breakages: its a new machine and we have no
according to the contractors performance history of component life cycles therefore parts
against a series of KPIs (key performance of it may well break without warning.
indicators). Safety is of extreme importance to Although the best advance achieved so far
National Grid, says Mackenzie. in one shift is 40 rings (48m), Mackenzie says
Getting the right approach to safety that they are not quite there yet in terms of
requires a change in thinking, says speed. Its not a TBM issue, its a system
Mackenzie. The old ways of get it done and, issue, he says. The TBM has been working
sure it will be all right just wont do any in the high 90s but the total system efficiency
more. is somewhat less. That first section has been cleaned out, with a
Some of the measures which Costain has Among the system issues which have few of the brackets which will hold the huge
employed to minimise the risks of accidents slowed things down have been some cables installed and waiting for inspection by
include installing CCTV on every crossing so problems with the rolling stock. For example, National Grid. Balfour Beatty will be installing
that any incidents can be recorded and lessons battery life is less than expected necessitating the cables, employed directly by the client.
learned, and a laser controlled system at the more frequent battery changes during the Having arrived at Channel Gate Road,
pit bottom which stops drivers if any part of shift. There are a number of factors at play where the site offices for the project are
the train is out of its kinetic envelope. here, says Mackenzie, but he has tackled one located, Evelyn headed off towards the Kensal
of them which is the complexity in charging Green 1 shaft where a headhouse will be
Record attempt and maintaining full battery charge, by located, arriving at the beginning of
Around Mackenzies desk, the route of the employing a dedicated battery charging September.
Willesden to St Johns Wood drive is pinned to person. Costain constructed the tunnel through the
two of his walls. Running largely alongside the The Caterpillar machine launched from shaft, using bolted concrete segments
route of the Grand Union Canal, it looks like a Willesden in March 2012, arriving at the supported by a bespoke transit frame and side
very wiggly worm drawn by a child. Channel Gate Road shaft, 660m away, in May. propping, which took around a week. The
Only the last section coming into St Johns main reason was to
Wood is straight and it is on this run that the Left: Breakthrough maintain the return
tunnelling team are eying up the Amec record at Kensal Green ventilation, says
of 501m in a week. The Amec achievement is Mackenzie, but also to
recorded on a certificate, displayed on one of isolate the tunnel from future activities in the
the site office desks. shaft.
It would be great to do it, because it would Now the Cat TBM is heading to St Johns
validate the design criteria of the machine Wood, with a planned arrival early January.
although consistency is more important to this This is the first time Costain has utilised an
project than record breaking, says Mackenzie. electric drive TBM, says Mackenzie. To date
The tender rate is 30 rings a shift which is it has been very reliable. We have excavated
360m a week. Thats a mighty ask, says and lined over 5000m without any significant
Mackenzie. To maintain that average means problems.
that everything has to be working in the high Some scraper teeth changes have been
ninety percentiles, week in, week out. That will required, along with modifications to the
require strong planning and maintenance gauge scrapers/wipers for the cutting head.
scheduling and it doesnt account for We found that when we were going round
TUNNELLING JOURNAL 19
TJ_1212_016_020.qxd:Feature 15/12/12 23:01 Page 20
TBMS
20 TUNNELLING JOURNAL
Get connected
With our new smartphone app you easily and quickly get access to all information you
need from Atlas Copco. Here you find our wide range of underground drilling rigs,
loaders and trucks in high resolution images, presented as 3D turntables. This makes
it possible for you to view the product from all angles, in the palm of your hand. The
app also contains videos, case stories and a social news flow. And thanks to the GPS
function, getting in contact with the nearest Atlas Copco representative has never been
easier. Available for both iPhone and Android smartpohone devices as wellas iPad and
Android reading pads, youll find it at www.underground-app.com. Downloading is
free, of course.
TBMS
Hybrid TBM
and Drill-and-Blast
from the start
Nick Barton of NB&A,Oslo, Norway describes the importance of
considering a mixed approach to long and deep tunnel construction
THE WRITER HAS been involved in the last eventually engaged as an outside industry, with concentration mostly on
stages of several TBM projects where the consultant, a wide-reaching survey of case solving the penetration rate PR and cutter
choice of TBM has clearly been incorrect, records was undertaken in Barton (2000), in life aspects of TBM prognosis. While
and the machine remains in the mountain order to try to find a better basis for TBM jointing effects may be approximately
forever, or is severely damaged and has to advance rate prognosis, which also included accounted for, the inclusion of faulting
be removed. He has also been involved in poor rock conditions. It appeared that poor delays is usually avoided. The variable
projects where drill-and-blast from the other conditions (as relating to faults) were strengths of rock masses (as opposed to
end has been advised at an early stage, but usually treated as special cases in the UCS), compared to cutter thrust levels,
ignored until very late, with adverse
consequences on completion dates, due to
too late abandonment of the TBM method, Figure 1: Results of analyses of 145 lengths of tunnel with specific properties,
and fatal consequences for some workers. involving about 1000km of open-gripper TBM case records (Barton, 2000).
Such extremes are unnecessary if more (Note: PR = penetration rate, AR = actual advance rate, U = utilization when
designers were aware of the inevitable boring, and T = time in hours). The best performances, termed WR (world
deceleration that accompanies TBM record) are represented by the uppermost lines showing best shift, day, week,
tunnelling, notwithstanding learning and month. At the other extreme, and often explainable by low Q-values, are
curves and some good or extremely good the so-called unexpected events, where faulting, extreme water, or
progress through favourable rock masses, combinations of faulting and water, or squeezing conditions, or general lack of
the latter also meaning favourable hydro- stand-up time, may block the machine for weeks or months. Some examples of
geologies. the most adverse crosses will be shown later.
2 2
minimal. TBMs may be penetrating at their 1 good
1 1
slowest rates in similar massive conditions, if
2 fair
UCS and quartz % are high, due to rock-
.5 3 poor .5
breakage difficulties, cutter wear, and .4 .4
therefore the need for too-frequent cutter .3 .3
change, the latter affecting the advance .2
e.g. Q 4 ext. p .2
rate AR. This reversed trend for slow TBM =0.1 oor
.1 .1
tunnelling in best quality, highest velocity
1hr 1day e 1wk 1mth 1yr
(VP) rock has been demonstrated on many .g.
Q=0
projects. The improved rock mass quality U . 01
ne
associated with higher Vp may not give the xp
expected advantages for TBMs, as less ec
te
jointing makes for a reduced penetration d
ev
rate, and an increased frequency of cutter e.g en
change reduces advance rate. .Q t s
=0
.0 01
Law of deceleration for TBM
As an indirect result of several seriously ? ?
delayed TBM projects, where the writer was
22 TUNNELLING JOURNAL
TJ_1212_022_032.qxd:Feature 16/12/12 15:52 Page 23
TBMS
seem also to be absent in past and recent difficult for TBMs, with or without double- Equation 3 is important because very
competing models of prognosis. Rock mass shields (Theological-empirical means that negative (-)m values make the component
1/(1+m)
strengths can be estimated from lack of belief will be paid for, in one way or too large. If the fault zone is wide
5Qc1/3MPa. another). (large L) and PR is low (due to gripper
The numerous (145) cases analysed, We need three basic equations to start problems and collapses etc.) then L/PR gets
totalling 1000km of TBM tunnelling, shown with: too big to tolerate a big component 1/(1+m) in
in Figure 1, showed general deceleration AR = PR U equation 3. It is easy (all too easy) to
trends when advance rate was plotted for U = Tm calculate an almost infinite time for
various time periods. The classic TBM- T = L/AR passing through a fault zone using this
equation linking advance rate to (Obviously the time T needed for length L theo-empirical equation. This also agrees
penetration rate in fact needs to be must be equal to L/AR, for all tunnels and with reality, in numerous, little-reported
modified to a time-dependent form, to all TBMs.) cases. The writer knows of several
capture the seldom acknowledged reality, as permanently buried, or fault-destroyed
indicated below: Therefore we have the following: TBMs (Pont Ventoux, Dul Hasti, Pinglin) and
T = L / (PR Tm). But T appears on both rockburst damaged or destroyed TBMs
The conventional equation: AR = PR U (1) sides: (Olmos, Jinping II). There are certainly many
(where U= fraction of time utilized for more, and the causes can often be related
boring) Therefore it can be rewritten as: to the logic and experience which are
T = (L/PR) 1 /(1+m) (3) embedded in equation 3.
The realistic equation: AR = PR Tm (2) So far this equation seems to be absent
(where m is a negative gradient of
deceleration, and T is actual total hours:
Figure 3: Cutter-head trapped in faulted meta-sandstones, as described by
e.g. 168hrs/week).
Shen et al., (1999).
This deceleration stands in strong contrast
to the expected learning curve or initial
speed-up of PR and AR, usually experienced
in the first months of numerous TBM
projects, as contractors/operators get
familiar with a new TBM. The deceleration
with time and tunnel length is a fact-of-
life, however much it may be disliked.
ARmean (when expressed in m/hr) has to
decline when 1 day, 1 week, 1 month, and
1 year are each evaluated in turn, for any
given project. Of course one can select
projects where this is not so, but there will
usually be geological reasons for breaking
this deceleration logic.
-1.0
-0.9 Examples of fault zone challenges
-0.8 The Pinglin Tunnel, with a stoppage event
-0.7
shown in Figure 3, is an example of TBM
-0.6
-0.5 tunnelling (actually three parallel tunnels),
-0.4 where serious faults caused such large
-0.3 cumulative delays, that drill-and-blast
-0.2 rescue from the other (western) end was
-0.1 finally allowed for completion, after some
0
13 years of struggle to drive this 15km long
.001
.002
.003
.004
.01
.02
.03
.04
0.1
.2
.3
.4
1
2
3
4
10
20
30
40
100
200
300
400
1000
TUNNELLING JOURNAL 23
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 24
Join us at the
World Tunnel Congress 2013
May 31 June 7, 2013
Geneva, Switzerland
TBMS
during conferences and courses occurring in and capabilities. only 20m of advance, representing an
Taiwan in this period. The 7km headrace tunnel for the Pont average advance rate
One of the two large diameter TBMs at Ventoux HEP in the mountains in the north- AR=20/(7720)=0.004m/hr. This is almost
Pinglin was crushed in the first difficult west of Italy, was driven parallel to a off the bottom of the chart, in the
kilometres, by collapse of a major fault marked NW-SE trending valley, and also unpredicted events area of Figure 1, where
zone, that had been successfully passed by parallel to swarms of faults hidden under crosses (+) are plotted. During 2004 the
the cutter-head. The majority of the slope screes. They represented the ultimate tunnel was completed by drill-and-blast
northern tunnel therefore had to be repeated challenge. At one location, the from the other end of the tunnel, by-
excavated by drill-and-blast, also with great fault zone performance was 7 months for passing the abandoned and rusting TBM.
Figure 4: Cutter-head of a large Figure 5: A fault of moderate width with clay core, but with high water
TBM (11.9m) and pilot TBM, pressure on one side, proved to be an insurmountable problem for the poorly
released on successive occasions. equipped inherited TBM. Note the 5 months of superimposed geologists
Photo: Dr. Chris Fong. observations, during 25m of stop-go lack of progress.
2750 fault
BH ? * ?
?
4/6/98 29/6/98 3/11/98 75 17/11/98 19/11/98 16/11/98 Open cave
shaft due
to erosion
2720 2730 2740 void
void
Continuous
steel sets void void
(css) css css
void
6/9
8 1 /12/98
29/ cave
8m 19/11/98
-1 cave
10 cave
2720 2730 2740 blocks
and
rock fragments css fines
blocks
up to 0.3-0.4m3 and
css jammed in void fines
TUNNELLING JOURNAL 25
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 26
TBMS
W
750 half of the trends from 1000km of open-
5.0 500 5.0 17 32
Seismic velocity (km/s)
Figure 8: Rock mass quality Qc-value isolines showing variation of P-wave The challenge of high rock stress
velocity with depth. The high velocity fault encountered at great depth may In recent years there have been many TBM
Fire P
be (or will be) a huge threat to tunnelling, especially to TBMs, because when tunnels with depth of cover > 1km, a few
it is exposed or at least unloaded at the face or side of the tunnel, its true also > 2km, and in two cases known to PROMAT
character becomes evident. Barton (2006). the writer, even 2.5km for short sections.
Tested
Both have suffered TBM damage or
tunnel
P- Wave Velocity (km/s) Fire tes
0 1 2 3 4 5 6
There are many iron tu
Panels
100 100
examples of inspec
200
n% = 20 5 1
200
double-shield TBM
N
300 300
getting stuck in visit
Qc = 0.001 0.01 0.1 1.0 10 100 fault zones, and
400 400
J
such delays are
Depth (m)
Depth (m)
500
1 2 3 4 5 (s -1)
500
often removed
600 600
from the generally
700
N = effect of increased porosity
700 excellent TBM
800 800 performance
J = effect of reduced jointing
900 Fault zone at
depth 700 - 800m ? Country rock ?
900 reported, as if they
1000 1000 were special cases Clyde
0 1 2 3 4 5 6
destruction due to rock bursting. Lives
have been lost in several deep TBM
reported, as if they were special cases. This is Yen are running also, possibly due to the tunnels in the last 20 years, and continue
understandable, but T (hours) is still running wrong choices (in retrospect) that were made to be lost even in the last few years. For
in reality. Unfortunately $ and Euro and some years earlier. some reason, drill-and-blast was usually
26 TUNNELLING JOURNAL
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 27
Since the 1960s Promat materials have protected more than 190 tunnels using PROMATECT boards
and more than 1.4 million m2 of tunnel linings have been protected using Cafco FENDOLITE MII*.
Tested to RWS and many international standard Tested to RWS and a wide range of internationally
tunnel fire curves. recognised fire test standards.
Fire tested for protection of both concrete and cast The worlds most specified spray applied fire
iron tunnels. protection system.
Panels can be easily removed and replaced to allow Protecting more than 1.4 million m2 of tunnel structures
inspection of the tunnel lining. globally since 1980.
Clyde Tunnel, Scotland Palm Jumeirah, Duba Bell Common Tunnel, London Groene Hart Tunnel, Netherlands
TBMS
4.0
were mostly estimated to be in the range
Receivers for the in-tunnel
3.9 of 50 to 100MPa, and from some even
seismic reflection method
higher stress experiences in China, the
3.8 recommended SRF (stress reduction factor)
ratings shown in Table 1 were developed
3.7 for excavations in massive, burst-prone
rock masses (Barton and Grimstad, 1994).
Analysis result with an in-tunnel source
3.6 Independently from the above SRF update
Analysis result without an in-tunnel source
dating from 1993/1994, and this time
3.5 coming from the field of mining as opposed
0 100 200 300 400 500 600 700 800 900 1000 to deep transport tunnels, the collection of
Distance (m) case records shown in Figure 13 also shows
stress-fracturing initiating when the
stress/strength ratio /c exceeds about
Figure 10: Early learning-curve months (1 to 4) of a double-shield project in 0.4-0.5.
massive abrasive granites. The ellipse to the right-hand side shows the mean There is some controversy concerning the
performance of four 9m diameter double-shield TBM boring a total of 56km. reason for the stress-fracturing starting
See Figure 1 for the source of this PR-AR-T method of plotting TBM progress, already when the maximum stress is only
starting with PR on the left axis, and showing advance rate (AR) progress with 0.4 to 0.5 x the UCS (laboratory-scale
time T, each on a log-log basis. Note the typical deceleration trends.
Figure 11: Four types of rock
1 10 100 1,000 10,000 100,000 mass, only one of which is
10 10 actually positive for TBM (#1,
ideally jointed: very fast progress
5 5 possible). Case #2 is designed to
4 4
3 3 represent a hard massive abrasive
2 best 2 rock like quartzite or granite, with
Penetratration rate (m/h)
28 TUNNELLING JOURNAL
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 29
TBMS
tic
AR (m/h)
PR (m/h)
th r a ll
Collapse, severe
us y
t
RMR II hard rock are both adverse for TBMs.
6 RMR I 6
5 overbreak, gripper-problems, Av. 5 Many parameters are important, including
4 cutter head seizure, PR 4 UCS (uniaxial compressive strength), q%
squeeze, flooding, etc. (hs)
3 24 Av. 3 (quartz content), CLI (cutter life index),
2 168 AR 2 and specific information about the
1 1 character of known fault zones (from
720
characterization of core, from refraction
0.001 0.003 0.01 0.03 0.1 0.3 1 3 10 30 100 300 1000 seismic, and from cross-hole seismic
RQD 0 Jr Jw SIGMA 20 q tomography).
QTBM = x x x x x x In Figure 15, imaginary rock mass
Jn Ja SRF F 10/209 CLI 20 5
quality statistics are presented for a
Table 1: SRF, the 6th parameter in the Q-value Figure 13: Initiation of stress fracturing and increased
estimation, is based on the ratio of maximum break-out when the stress/strength ratio /c exceeds
tangential stress/UCS for the case of rock-burst prone 0.4-0.5, from Martin et al. (2001). The case records are
massive rock. Note initiation of steep SRF gradient mostly from mining and nuclear waste research tunnels.
when /c exceeds 0.4-0.5. Extracted from Barton
and Grimstad (1994).
uniaxial compressive strength). A simple- TBM or Drill & Blast? planned 5km long tunnel, and for a much
minded explanation is that there is a strong In Figure 14 the choice between drill-and- longer 25km long tunnel. As may be
(Weibull-based) scale effect on UCS as blast and TBM tunnelling is clearly shown noted, there are assumed to be more
sample size increases, so that UCS x 0.4-0.5 to be Q-value dependent, with adverse extreme value rock quality statistics in
can be an approximate in situ estimate of effects for TBMs at extremely low and the longer tunnel, such as harder rock
large-scale strength. Two equations for this high rock mass qualities. Q appears as the (HH) and more serious faults (FF), and
strength reduction, from Hoek and Brown first six parameters in QTBM (see Figure 12) greater cover. It is clear from the Figure 14
and Wagner were compared and simplified and Q also determines the utilization (or comparison of drill-and-blast and TBM
in Barton (1987), and show a reduction of ()m = deceleration gradient), but only progress, each as a function of Q-value,
about 50% or more, at scales of 1 to 2m. when Q -values are significantly below 1.0 that the TBM will struggle more at both
TUNNELLING JOURNAL 29
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 30
TBMS
Figure 14: A Q-value and QTBM-value based comparison of drill-and-blast and Figure 15: The long tunnel by
(open-gripper) TBM tunnelling, using respectively cycle-time and PR-AR-m TBM or hybrid? Adverse
estimation. The tabulations of respective Q and QTBM could have similar extreme value statistics for rock
magnitudes (e.g. with cutter force = 20 tons in rock masses with 20MPa rock mass quality suggest avoidance
mass strength SIGMA (= 5 QC1/3), where Qc = Q x c/100 and = density. of TBM where there is FF-HH-FF
rock in the area of highest cover.
(FF means more serious faulting,
HH means very hard massive
200 TBM
rock). Solution: drive left half
Average rates of advance for TBM
we
decline more strongly with increased
with TBM, drive right half by
ek
drill-and-blast, starting at least 1
ly
tunnel length or time of measurement
than they do in D+B tunnelling. year before, so as to get through
150 the second FF feature before
meeting the TBM, which may
m
on
year
100 ly section, if they are physically
?
possible.
?
F H F
50
T1 = 5km
3 FF F H HH
0
0 0.01 0.1 1 10 100 1000 2
km
Q-value
1
ends of the rock quality statistic. cost for perhaps thousands of cutter 0
Recent RMR and Q statistics at a tunnel changes, if these adverse (HH) conditions 0.001 0.01 0.1 1 10 100 1000
Q - value
in very massive granites, and the slow last for many kilometers.
progress by double-shield TBM, following
incorrect site description, suggest that Drill & Blast single shell NMT F H F FF HH FF F H
drill-and-blast tunnelling would have been During the last 35 years there have been
faster, at least in the absence of a higher- huge improvements in TBM technology,
powered TBM. There are also examples of with the wide-spread use of high-thrust, T2 = 25km
slow TBM progress being rescued by high torque and double-shield
drill-and-blast, in the case of a Chinese technology, and the gradually increasing 12 FF F H HH
10
tunnel that needed to be completed by possibility to efficiently probe drill in
8
the millennium of 12 years ago. several directions, and to pre-inject in
6
km
30 TUNNELLING JOURNAL
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 31
TUNNELLING INSTRUMENTATION
Why is this man smiling?
www.geokon.com/tunnels
Dresden
Branch of Herrenknecht AG
SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com
and click on Subscription Offer
TUNNELLING JOURNAL 31
TJ_1212_022_032.qxd:Feature 16/12/12 15:53 Page 32
TBMS
is 1 to 10, while the NATM is used where through mountainous terrain. excellent stability. TBMs also exhibit
the dominant quality Q is 0.1 to 1.0. But 3. The deliberate selection of both TBM adverse characteristics at the lowest
the cost difference is nevertheless an and drill-and-blast may often be a (severely faulted rock) end of the rock
unnecessary expense, if NMT with pre- simple matter of common sense, quality spectrum.
injection is used. The concept of hybrid giving schedule advantages and cost 8. TBMs gradually decelerate with time
tunnelling (TBM and drill-and-blast) in the savings. This is the preliminary level and tunnel length, even when
same project becomes more attractive if of hybrid tunnelling. breaking records. This is a natural
the drill-and-blast section(s) can progress 4. Very often it is seen that time is lost process that should be a part of any
at rates that are less affected by hydro- while waiting for TBM delivery and realistic TBM prognosis, in preference
geological variability, and if they are assembly, and great advantages could to denial of its existence.
complete at break-through, i.e. no be gained by selective use of drill- 9. TBMs that are operating in mostly
further lining required. In fact it has been and-blast for more than just the favourable conditions, may record
suggested that most if not all of the Q- standard TBM assembly chamber and remarkable progress, and are
parameters improve with high-pressure starter tunnel. therefore an excellent investment for
pre-grouting. (Barton, 2002, 2011). 5. A second level of hybrid tunnelling part or all of many tunnelling
will be the deliberate choice, because projects.
Conclusions of the perceived advantages, of open- 10. More uniform tunnelling progress can
1. There are significant numbers of TBM gripper TBM and drill-and-blast, be obtained, both in the case of drill-
projects that end up with difficult or double-shield TBM and drill-and- and-blast and TBM tunnelling, if the
decisions to be made, namely to blast. advantages of systematic pre-
injection through problematic
stretches is better appreciated. The
Figure 16: An illustration of the use of pre-injection using up to 70 holes of typical 24 hours delay for a pre-
25m length, which are drilled and injected in approximately 24 hours, in a injection umbrella may save weeks
105m2 high-speed double-track rail tunnel driven in shales, limestones and or months in lost production.
through numerous igneous dykes with too much water. Progress was a steady
20m/week for the completed tunnel, virtually independent of pre-conditions. REFERENCES
32 TUNNELLING JOURNAL
RAPID EXCAVATION AND
TUNNELING June 23-26, 2013
CONFERENCE
RAPID
Marriott EXCAVATION
Wardman Park AND
Washington, D.C.
TUNNELING CONFERENCE
A comprehensive exhibit is held in conjunction with the conference. The exhibit features the industrys
most innovative and experienced producers and suppliers. RETC provides a rare opportunity to meet key
professionals from around the world.
The meeting will also feature field trips, short courses and specialty speakers. The program will cover:
Contracting Practices and Cost Grouting and Ground Modification East Coast Projects
Design and Planning Hard Rock TBMs SEM/NATM
Difficult Ground Large Span Tunnels and Caverns Shafts and Mining
Drill and Blast Microtunneling and Trenchless Tunneling Tunnel Rehabilitation
Environment, Health, and Safety New and Innovative Technologies Water and Gas Control
Future Projects Pressure Face TBM Case Histories International Projects
Geotechnical Considerations Pressure Face TBM Technology Tunneling for Sustainability
Ground Support and Final Lining Risk Management
Mining through
MECHANIZED
METHODS
Desiree Willis of the
Robbins Company
explains the use of
TBMs in the mining
industry
A GLOBAL POPULATION of seven billion
and counting, combined with unprecedented
demands for everything from iron ore to coal
to nickel, are making one thing certain:
deposits in todays mines are no longer found
near the surface. Mines are reaching farther
underground than ever before to access new
ore bodies and extend the life of long-running
operations. As deposits become deeper,
mechanized methods of excavation such as
TBMs have the advantage over conventional
operations. I see the quest to reach ore
bodies increasing, and this will involve longer
access tunnels. For long distance access TBMs have been used
tunnels, TBMs could give cost and time successfully in mines around
advantages, said Martin Knights, past the worlda Robbins
president of the ITA and global lead machine still in use at the
consultant at Halcrow Group Ltd. Stillwater Mine was
From mechanized excavation to continuous previously used at the
muck removal by conveyor, mines are turning Magma Copper Mine in
to new methods to reach the next level. Arizona, USA (seen here).
34 TUNNELLING JOURNAL
TJ_1212_034_037_Desiree.qxd:Feature 15/12/12 22:16 Page 35
TBMS
TUNNELLING JOURNAL 35
TJ_1212_034_037_Desiree.qxd:Feature 15/12/12 22:16 Page 36
TBMS
agreed: Mines are increasing their use of Stillwater Mining Company, believes TBMs Detection of the reef in relation to the TBM
conveyors and since many existing mines are guarantee a fast advance rate in life-of-mine requires careful analysis using two core drills
expanding to higher productivities, conveyors access tunnels. The common perception in mounted on the machine. Steering the TBM
are the more economical solution. mining is that TBMs are large and unwieldy is an interesting process because we have very
machines, but we have used them successfully complex geology here. We do diamond (core)
Moving Muck below the Big Apple for 24 years. The U.S. mine recently launched drilling ahead of the machine, above the
While wide acceptance of continuous its fourth TBM, a 5.5m diameter Robbins Main machine, and to the side after every 150m. We
conveyors in mines is still pending, their Beam machine, in autumn 2012. drill and log the core right there while we are
successful application in similar conditions is Stillwater Mine is the best model, because drilling it, then interpret the results, so it is
well documented. At New York Citys East Side of the fact that the company is comfortable concurrent with boring, said Koski.
Access subway tunnels, a Robbins continuous with TBMs and has used them over and over, The operators then make adjustments to the
conveyor system hauled muck from said Rostami. The platinum and palladium mine TBM bore path based on the perceived
simultaneous TBM operations, as well as drill first purchased a 4m diameter Kelly-type TBM distance to the reef. We dont want to get
and blast and roadheader operations. The in 1988 to excavate a mine access tunnel too far away from or too close to the ore body.
unique system carried up to 1,500 cubic through the areas characteristically layered The ore zone is located in a very distinct layer
meters of muck per day up a 23m shaft and gabbro, norite, and anorthosite rock. We of igneous rock, so if we penetrate the right
across a busy roadway to a storage yard more were faced with trying to further develop the rock types then we know we are in the right
than 370m away. mine and open up its reserves, but one of the place, and if we see some ore we know where
This job was logistically unique. Not only challenges was the ventilation. We wanted to we are. Platinum and palladium is hidden in
was it a massive undertakingwe also had base metal sulfides, so we look for the
reduce the cost of driving foot wall laterals, but
multiple different headings happening at one didnt want to have vertical ventilation shafts presence of the ore, but those metals are only
time. There were two TBMs, two roadheaders, drilled, like those that are necessary for D&B. present in core samples about 50% of the
drill and blast operations, concrete operations, We also determined that ground support for time, so the rock types guide us, said Koski.
and shotcrete lining operations, all happening circular tunnels would be less, said Mike Geotechnical probe drilling is a regular
out of one major shaft, said Don Hickey, Koski, Chief Geologist at Stillwater Mining occurrence on the TBM, in addition to core
Project Manager for the drilling to identify the reef position.
Dragados/Judlau JV. At the same time that we are
The uneven sized pieces of diamond drilling, we also want to
Manhattan schist, gneiss and identify rough ground conditions
granite rock being conveyed were that are ahead, such as weak rock,
similar to what might be water, and dykes. We probe ahead
encountered by multiple mining every 170m and look at the
operations using various excavation results, and in that way we know
methods. While TBMs tend to we are placing footwall laterals in
produce fairly uniform-sized rock the best possible ground,
chips, drill and blast and roadheader continued Koski.
excavations can result in widely The TBM is excavating Norite
varying muck consistency. rock and is capable of placing a
We limited the oversize rock variety of ground support
with a crusher, but pieces still depending on the conditions.
occasionally got through. We also Support ranges from ring beams,
had a grizzly setup at the hopper to The Blitz tunnel drive will be at least 7.1km in length and will shotcrete, and rock bolts to
limit the size of material that the cross several fault lines in mafic norite rock. McNally crown support utilizing
belt would receive, said Hickey. continuous steel slats. Were
The conveyor performed at high expecting mainly competent rock
availability throughout the project, despite the Company. The mine wound up using that with claylike material in fault zones. Our
challenges in terms of muck volume and machine for several tunnels in the late 1980s standard ground support is welded wire mesh;
consistency. Though transfer points had a and early 1990s. however, if we encounter very poor or blocky
tendency to clog, the contractor reduced the In 1999, Stillwater Mine purchased a ground, we can switch to the McNally support
number of transfer points by making the refurbished Robbins Main Beam TBM from system, said Luxner.
system a single belt and adding a booster drive, Magma Copper Mine in Arizona, using it to Excavation is planned to take about three
which increased availability. excavate access tunnels in the East Boulder years. Stillwater Mine says it will likely continue
The conveyor performed well as long as the section. The machine has since been used on to use the machine after its initial project, and
system was maintained and cleaned. We put a nearly 6km of tunnels. Most recently, it began may extend the Blitz tunnel if its successful.
lot of hours on the system and moved a lot of boring a new 2.6km long mine development
rock from different types of excavations. We tunnel, known as the Graham Creek Mines Moving Forward
were satisfied with the conveyor system and Expansion, in 2011. While other mines such as Australias Anglo-
used this equipment for five years, so it has American and Rio Tinto are taking the plunge
endured the test of time, said Hickey. Long- Blitz Tunnel into more mechanized technology, Rostami
lived conveyors are certainly a plus for mine Stillwater Mines latest endeavor is the Blitz urges greater acceptance across the board:
use, where equipment is typically in operation Tunnel, a development tunnel of at least 7.1km Miners can use TBMs in the same way as civil
for its useable life. that will provide information about the reef infrastructure projectsthe only difference is
along the eastern portion of the mine. that in most tunnelling, the hole in the ground
Montanas Stillwater TBMs The Robbins TBM is detecting the location of is the product. In mining, the tunnel is the
At Stillwater Mine, located in Nye, Montana, the reef in relation to the machine while means to an end. Mining companies need to
USA, mechanized methods have been in use simultaneously creating a rail haulage tunnel familiarize themselves with the technology and
for decades. Tyler Luxner, Project Engineer at that will be used for the life of the mine. become more comfortable in using TBMs with
36 TUNNELLING JOURNAL
TJ_1212_034_037_Desiree.qxd:Feature 15/12/12 22:16 Page 37
TUNNELLING JOURNAL 37
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:16 Page 38
Slipforming
the Lee Tunnel
shafts
Innovative
techniques are being
used in East London
to slipform some
mightily impressive
shafts, Kristina
Smith files this report
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:17 Page 39
SLIPFORMING
TUNNELLING JOURNAL 39
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:17 Page 40
SLIPFORMING
record for Bachy the first of the circular diaphragm walls for the
Beckton Overflow shaft in September 2010
with the first shaft excavation within the
The circular diaphragm walls which form pressures at the bottom of the excavated diaphragm walls starting in May 2011.
the outer skins of the four shafts for the panels, the polystyrene was pre- The Herrenknecht slurry TBM began its
Lee Tunnel project in East London are the compressed. challenging launch from the Beckton Overflow
biggest ever constructed by Bachy The flotation force provided by the shaft in December 2011. The completion date
Soletanche. We have done 1.8m wide polystyrene was significant: a 27 tonne for the whole project is April 2015.
walls before and we have done 100m cage weighed in at 20 tonnes with its The design and build project is being
deep before, but we have never done a polystyrene addition, once in the delivered under the NEC3 form, which
1.8m-diameter wall, 100m deep, says bentonite. This meant the polystyrene CH2MHills Roger Mitchell, deputy project
Bachy Soletanches Julian Gatward. had to be firmly attached to the rebar to manager on the Lee Tunnel, says has nurtured
Perhaps the biggest ask for Bachy stop it popping out of the trench. a spirit of teamwork on the job. And the use of
Soletanche was the verticality tolerance Once a panel was excavated, the a Geotechnical Baseline Report (GBR), aimed to
of 1 in 300. Over a 100m shaft, thats bentonite which had been used for reduce disputes by defining what a contractor
30cm of tolerance in verticality which is digging was replaced with clean should expect in the ground, has contributed to
rather tight to achieve, says Gatward. bentonite. Though not all contractors do this spirit. The nature of the contract helps in
Verticality is important because it this, Bachy think it is vital says Gatward. many ways the collaboration, the sharing of
ensures that the joints between the The reason is fresh bentonite has a lower information and also the culture we adopt,
panels, which make up the diaphragm specific gravity than bentonite which, says Mitchell. And the GBR helps to avoid
wall are good. And since a diaphragm although it has been through a cleaning some of those issues that would otherwise
walls job is to keep the water out, good process, still contains tiny soil particles. cause friction between the teams.
joints are essential. When concrete is delivered via tremmies
The largest diameter shaft, the 38m into the panels, the fresh bentonite will Cracking the design
pumping shaft at Beckton, has 1.8m-thick float upwards, whereas used bentonite During the value engineering phase the design
walls. The overflow and connection will have a similar specific gravity to the of the secondary lining of the shafts came
shafts have 1.5m walls and the Abbey concrete and just mix with it. under scrutiny. The reference shaft design,
Mills shaft walls are 1.2m thick. Bachy found on this job that it had to which called for traditional reinforced concrete
To construct an almost circular cross change the bentonite used for cast directly against the diaphragm walls, had
section, Bachy Soletanche had to build a excavation far more frequently than some fundamental challenges says Eddie:
many-faceted cylinder, created by intended, since the cleaning equipment The key issue is that reinforced concrete
overlapping a series of straight panels. was unable to sufficiently filter out the when cast against the diaphragm wall, is
The contractor uses an excavator to dig tiny chalk particles. This meant a change restrained, so you end up putting in a lot of
down the first few metres, followed by a in strategy to buy in more fresh steel to prevent cracking, he says. This was
hydrofraise, which works by excavating bentonite and offhire some of the exacerbated by EC2 Part 2 which results in an
the soil in bentonite. cleaning kit. extremely high quantity of reinforcement to
The 2.8m-wide and 11m-tall As for vertical tolerances, Bachy used limit crack widths.
hydrofraise has two cutter wheels on its two systems. Inclinometers on the top of With dense reinforcement required at the
underside with teeth that churn up the the hydrofraise and pressure pads on the bottom of the shafts, which will have to
soil. The bentonite and soil mixture is side of its body helped the operator withstand up to 8bar of pressure, placing
then sucked in and pumped up to the guide the machine during excavation. concrete so that it flowed around all the rebar
surface where most of the soil particles And then a Koden seismic probe was would have been a real challenge. And there
are removed from the bentonite. lowered into the bentonite post- were also some doubts whether the shafts
Bachy constructed the diaphragm walls excavation to record the cross-section at would meet the required 100-year design life
from primary and secondary panels. The different depths. The Lee Tunnel project and waterproofing specification, which called
primary panels, made from three was the first time that Bachy had linked for damp patches only.
adjacent bites of the hydrofraise were the output from the Koden to a 3D CAD MVB took on the challenges of the shaft
between 6.8m and 7.2m long, with the package, a technique now adopted linings design, in a bid to come up with
secondary or infill panels 2.8m wide. group wide. Fortunately there were no something that both saved money and worked
In order to minimise twist when problem areas to identify: We then better. Colin came up with the idea of using a
digging the secondary panels, it helps to looked at 10 slices all the way through chimney and back-filling the annulus between
have the primary panels on either side at the shaft, so that at each 10m we could the lining and the diaphragm wall, says Allen.
a similar age and strength because the see where they were compared to where That way you eliminate the restraint provided
secondary panel has to eat into the edge they should be, says Gatward. It gave by the diaphragm wall and it gives you the
of each of its two neighbours. This is us the confidence to carry on excavating opportunity to put the lining into compression
quite tricky when one panel takes a without anticipation of problems. when you put the fill material around the
week to construct. So to help guide the The diaphragm walls were a great annulus.
hydrofraise down in the right line, Bachy start, says Mitchell. Now we have So while shafts are often slipformed using
devised a system which saw polystyrene exposed the four shafts we have been formwork on the internal face of the inner
strips attached to the rebar cages along very pleased with the D-walls. None of lining only, the Lee Tunnel shafts have uniquely
the long sides of the primary panels so them have been out of tolerance and the forms on both faces to create a free-standing
that the hydrofraise could munch tolerance has probably been closer to structure. And separating the concrete cylinder
through the polystyrene. Because of the 1:500 rather than 1:300 in the end. from the base slab is a slip membrane: 2mm-
40 TUNNELLING JOURNAL
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:17 Page 41
SLIPFORMING
thick PVC membranes, the lower one glued to withstand attack from acids and sulphates in The huge base slabs of the shafts also got
the base slab, the upper one cast onto the the waste water. This was achieved by including the value engineering treatment. By changing
underside of the lining with a layer of grease in 36% of slag resulting in a low shrinkage mix their shape from a deep slab to a more
between them. The success of the slipform which is consequently chemically resistant. structurally efficient dome, MVB cut the base
technique depends on the design of the However this meant that the variation in mix reinforcement tonnage in half.
concrete, which is strengthened by steel fibres, performance had to come from retarders alone.
saving around 4,000 tonnes of steel for the The concrete was subjected to shrinkage Two down, two to go
four shafts. Only around the portals where the testing, both at the BREs testing facilities in the By November 2012 specialist contractor
TBM must break through, or where the suction UK and in Belgium where the steel fibre Slipform International had completed the
tunnel links between the Beckton Connection manufacturer Bekaert is based. The mix was linings for the Overflow and Connection shafts
and Pump shafts is there reinforcing bars. of such low shrinkage characteristics that even at Beckton, and was about to start on the shaft
The secret of designing concrete for 30m long test beams cast on a rough substrate at Abbey Mills. The 38m-diameter pumping
slipforming is that it must be just hardening as did not crack, which is unheard of, says Allen. shaft at Beckton will be the last one they tackle,
the form slides up to expose it, says Allen who The mix for the annulus infill concrete also starting in January or February 2013.
required careful design. Filling the gap between Originally MVB was not sure that the same
the diaphragm wall and the inner slipformed double-sided slipform technique would be
Figure 2: Top: Drawing of the lining, which varies in width from 250mm to appropriate for the 38m-diameter Pumping
double sided slipforming method. 750mm, the concrete must remain liquid long shaft. But some really hard work from the
Below: Plan of the double sided enough to prestress the lining, which is designers, says Mitchell, means that the same
slipforming method achieved using retarders. The infill concrete will principles can be applied, albeit with some
Climbing
barely shrink at all, says Allen. There will be slight changes to the construction sequence.
tubes autogenous [chemical] shrinkage only from the Overall, Mitchell says he is happy with the
Handrail post annulus fill, he says. Theres no drying way the shafts have been constructed and
Horizontal handrails
Concreting shrinkage because it is completely enclosed. comments on the great finish on the concrete.
1500LG. slotted channel
hatch
(125x100) timbers
The extensive testing programme also saw However, one of the practical challenges for
Hydraulic
lines Top deck level BRE put the slip membrane through its paces. Slipform International has been achieving the
6T capacity
Yoke Half coupler attached And there were slip forming trials at ground required tolerances.
slipform
jack legs to crossbar extension level on site before the real operation began. Keeping the dimensional stability of the ring
Internal truss
Sleeve box (225x50) timbers bracing Despite the low shrinkage characteristics of and the verticality is very challenging, says
and jack (100x100) timbers
anchors Working deck level the concrete, Allen was taking no chances with Eddie. This will be particularly important on the
Slotted 3660 unit beam cracking. There are places where cracking is Abbey Mills and Pumping shafts where
channel
walling more likely, for example around portals the structures must fit inside the shafts.
Hanging scaffold transition area between rebar and fibre could The first two shafts we have had some
top frame
be a potential weak spot. Here Allen designed relatively small deviances from our
Secondary
Hanging scaffold in crack inducers, supplied by Drytech, with requirements, says Mitchell. We have
bottom frame
concrete channels to allow reinjection of grout should managed to live with that, partly because they
layer
Hanging deck level cracking occur. But we couldnt even get it to are wet shafts so we dont have structures
crack there! says Allen. inside that have to join with them. It was a very
250 750
Section A-A
250
A
Diaphragm Wall
750
Hanging
deck layout
3660mm
unit beams
25 Internal truss bracing
0
Working deck layout
TUNNELLING JOURNAL 41
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:17 Page 42
SLIPFORMING
Singapore he recently worked on where a that means you dont have to fix lots of rebar in there. The main beneficiary of this new system
100m deep shaft was excavated and lined a confined space in a shaft, lowering the bars in will be the Thames Tideway Tunnel, says
internally top-down, with the inner lining with a crane. If you can reduce the risk of Eddie. There are a large number of shafts to
process alone taking eight months. accidents, thats really a big win, says Mitchell. be constructed and I see no good reason not to
Here, the whole thing can be constructed in As the shafts innovative linings continues use this technology. Mitchell agrees. You
less than six months. Thats a big change, says and the TBM starts to make decent progress need to have clever and open-minded
Mitchell. We are doing the liner in three under East London, thoughts turn to the designers who are willing to consider and
weeks now and then it takes a further week to 4.1bn Thames Tideway Tunnel project. The approach it in the right way, he says. As long
prepare and fill the annulus. Using a jump form 32km, 7.2m diameter tunnel will largely follow as you have got that, it certainly has worked for
would have taken a couple of months. the route of the River Thames at a depth of us. I am absolutely sure it will work for the
The other huge benefit is that this is safer around 67m, running from Hammersmith to Thames Tideway Tunnel. We do have close
because it requires less reinforcing steel. We Abbey Mills. It seems highly likely that MVBs dialogue with them, and share our lessons
have reduced the amount of rebar hugely and new slipform technique will be put to good use learned and our views with them.
42 TUNNELLING JOURNAL
TJ_1212_038_043_SLIPFORM.qxd:Feature 16/12/12 01:17 Page 43
morgansindall.com
MS3169
T 01788 534500
Engineering Recruitment
UK & OVERSEAS OPPORTUNITIES
Business Development and Sales Manager Hong Kong - Asia
Our client a major Australian Tunnelling and Mining Machinery Manufacturer has a requirement for a Business Development and Sales
Manager. You will work with in close contact with the company Management from Hong Kong, developing business globally, but with a
main focus being on the Asian region. You should be an accomplished sales person with contacts & experience in the Tunnelling & Mining
industry. Its essential you have experience selling Tunnelling/Mining machinery or other products used in a Tunnelling/Mining environment
(Civil Contractors and Mining Companies). You should also have the ability to work on tenders & feel comfortable pitching to major clients.
For further information on these & other opportunities, please contact Daniel Lee-Billinghurst.
Tel:+ 44 (0) 207 754 5999 Email:careers@v-engineeringrecruitment.com
Web: www.v-engineeringrecruitment.com
TUNNELLING JOURNAL 43
TJ_1212_044_045.qxd:Feature 15/12/12 21:51 Page 44
VIEWPOINT
Being analytical
Dr Benot Jones, Tunnelling and Underground Space MSc Course
Manager at the University of Warwick, UK, discusses analytical
solutions for tunnels
ANALYTICAL SOLUTIONS, or closed-form rockbolts (Bobet, 2009; Carranza-Torres, 2009), a spreadsheet has been created and checked,
solutions, are solutions that lend themselves others that include creep deformation of the this makes them ideal for parametric studies. For
easily to calculation. Mathematicians will cringe ground (Nomikos et al. 2011; Birchall & Osman, instance, by varying the stiffness of the lining
at this simplification, but another way of saying 2012), rectangular tunnels under seismic action one can immediately see the effect on the
this is that if it can be solved in a single equation (Huo et al., 2006), modelling deformation bending moments and hoop forces. Therefore,
without iteration, then it is an analytical ahead of the lining installation using a gap analytical solutions are useful in feeling your
solution. If you need to iterate and converge on parameter (Park, 2005), groundwater ingress to way around a problem and determining which
a solution, then it is a numerical method. tunnels (Kolymbas & Wagner, 2007), modelling factors are important. The simplicity of the
segmental linings (Lee et al., 2001; Hinchberger model helps by limiting the complexity of
The rise and fall of analytical solutions & El Naggar, 2008) and much, much more. interaction between different factors that may
Analytical solutions have been a useful design make it difficult to see what is going on.
tool for tunnel engineers for some 50 years. In So what is going on? In addition, many numerical modelling
that time, computer power has increased Given the superiority of numerical modelling, experts use analytical solutions to validate their
enormously, and numerical modelling programs what is the purpose of so much innovation in models. If a numerical model is made to mimic
have become ever more user-friendly. Analytical analytical solutions to allow these simple models the same boundary conditions and constitutive
solutions, due to their need to reduce the to do something just slightly more complicated behaviour as an exact analytical solution, then it
complexity of soil-structure interactions to a than they could do before? should yield the same results. If not, it indicates
single equation, usually make simplifying The argument that numerical methods are that there is a problem with the mesh, the
assumptions about geometry and about computationally expensive is often put forward element type, the boundary conditions, the
constitutive behaviour. For instance, tunnels are in the introductions to papers about analytical convergence criteria or the solution algorithm.
usually circular, and the problem is usually solutions, but is this really still the case when a Most commercially-available programs include
assumed to be either 2D plane strain or similarly simple 2D numerical model can be simple examples, which can be compared to
axisymmetric, meaning that the longitudinal created and solved on a standard PC in a few analytical solutions. The first steps in any
dimension is ignored. Simple ground and lining minutes? Even though numerical modelling campaign of numerical modelling should be to
constitutive models are used; either elastic, software can be expensive, this seems like a bit build simple models and validate them.
elastoplastic or viscoelastic, and the variation of of a red herring. Being a devils avocado, the real Once the simple case has been validated,
geotechnical parameters with depth or stratum reason for this paradox may be that most of layers of complexity can be added to a
boundaries are either grossly simplified or these papers are published by academics, and numerical model, one at a time, ensuring the
ignored. On the other hand, numerical models academics are not always trying to do input is debugged and the results are checked
can model virtually any geometry, construction something useful, sometimes they are just at each stage. This is also a kind of parametric
sequence, variation in geotechnical parameters doing something they find interesting. Although study, and enhances understanding of the
or constitutive behaviour. The construction odd to us engineers, a lot of scientists do work problem, but also allows easier debugging
sequence can be modelled explicitly in 3D, pore that has no immediate practical use. because if strange results are obtained you
pressures and consolidation can be modelled, know that it is likely to be the newest layer of
and even creep or thermal effects included. Analytical solutions as part of the design complexity that caused them. Many of us have
Given the power of numerical modelling and There may be a better argument to be made in learned through bitter experience that to try to
its increasing accessibility, it is surprising that favour of analytical solutions. Duddeck & jump immediately to the most sophisticated
there has been an explosion in the number of Erdmann (1985), in a review of structural design model makes it almost impossible to find out
papers published on the subject of analytical models for tunnels in soft soil, wrote: what is going wrong, and makes it difficult to
solutions for tunnels in recent years. A literature In many instances the stress-strain- know what behaviour should be expected.
search reveals that more than 30 papers have deformation problem of a tunnelling procedure So analytical solutions help us feel our way
been published with new analytical solutions for can be solved only by the application of a through those initial stages of tunnel design,
tunnels in peer-reviewed journals in the last 5 numerical analysis, e.g., the finite-element and give us more confidence, just as empirical
years. Many more have been published on the method. The geometry of the opening and the data, if available, help us to refine numerical
same subject without presenting a new stratigraphic layers of the ground are not simple models and have more confidence in the results
method, for example, papers that compare in most cases. Non-linear material behaviour is as the sophistication of the model increases.
analytical, empirical and numerical results. involved. The consecutive phases of the process
Google Scholar returns about 14,000 results for of driving and supporting are important for the An example
scholarly articles if you type in analytical final stresses in the linings. The problem of stress concentrations at tunnel
solution tunnel* NOT physics (ensure you This is a quite strong criticism of analytical junctions is highly complex, depending not just
restrict it to the last 5 years). solutions. However, they go on to say: on the geometry, but being strongly affected by
In recent years new analytical solutions have Comparison of the results on the basis of soil-structure interaction and the construction
appeared that take account of nonlinear numerical solutions is, however, very difficult sequence. A major issue in numerical modelling
anisotropic ground (Vu et al. 2012), the effect of and does not yield easy insight into dependence of junctions is to ensure that the element type
a radially-strengthened cylinder of ground on soil and design parameters. and mesh refinement of the shell elements
around a tunnel due to the installation of Since analytical solutions are easy to use once representing the lining will accurately predict the
44 TUNNELLING JOURNAL
TJ_1212_044_045.qxd:Feature 15/12/12 21:51 Page 45
VIEWPOINT
large stress gradients around the opening. at the stage of breaking out the opening for the
However, there are no analytical solutions for a tunnel from the shaft), compared to the very Figure 1: Stress concentration factor
tunnel junction situation. The best we can do is simple case of a plane stress plate with a hole in for a plane stress plate with a hole in
an analytical solution for a hole in a plane stress it. This enhances our understanding of the the direction parallel to the applied
plate developed by Kirsch in 1898 (see Hoek & problem. The axial hoop stresses in the 3D stress (Nx/P) along a line transverse
to the direction of the applied stress.
e MSc Course Brown, 1980). This solution does not calculate numerical model are higher than for the plane
the significant bending moments that will be stress plate, and this is due to the three-
s analytical present in the lining due to curvature of the dimensional deformation of the shaft and the 1
lining, construction sequence and soil-structure soil-structure interaction. Essentially, when the
P(kN/m)
Y 0.9
interaction, or the effect of these on the axial opening is made, the ground arches onto the
forces, but it can still be useful. shaft lining around the opening, increasing the X
0.8
-2
REFERENCES
-4 Birchall, T. J. & Osman, A. S. (2012). Response of a tunnel deeply embedded in a viscoelastic medium. Int. J.
Numer. Anal. Meth. Geomech. 36, 17171740.
-6 Bobet, A. (2009). Elastic Solution for Deep Tunnels. Application to Excavation Damage Zone and Rockbolt
Support. Rock Mech. Rock Eng. 42, 147174.
-8 Carranza-Torres, C. (2009). Analytical and Numerical Study of the Mechanics of Rockbolt Reinforcement
-1 0 1 2 3 4 5 6 around Tunnels in Rock Masses. Rock Mech. Rock Eng. 42, 175228.
Stress concentration factor Duddeck, H. & Erdmann, J. (1985). On Structural Design Models for Tunnels in Soft Soil. Underground Space
9, 246-259.
Hinchberger, S. & El Naggar, H. (2008). An analytical solution for jointed tunnel linings in elastic soil or rock.
to be used for the shaft lining, but flattened (or Can. Geotech. J. 45, No.11, 1572-1593.
unwrapped), was used to mimic the conditions Hoek, E. & Brown, E. T. (1980). Underground Excavations in Rock, 527pp. London: IMM.
in the analytical solution. The mesh refinement Huo, H., Bobet, A., Fernndez, G. & Ramrez, J. (2006). Analytical solution for deep rectangular structures
was then varied and the ability of the model to subjected to far-field shear stresses. Tunnelling and Underground Space Technology 21, 613625.
replicate the analytical solution can be seen in Jones, B. D. (2007). Stresses in sprayed concrete tunnel junctions. Eng.D. thesis, University of Southampton.
Figure 1 for the axial hoop stress above and Kolymbas, D. & Wagner, P. (2007). Groundwater ingress to tunnels The exact analytical solution. Tunnelling
below the opening. Similar graphs were plotted and Underground Space Technology 22, 2327.
for hoop stress and vertical stress in the shaft Lee, K. M., Hou, X. Y., Ge, X. W. & Tang, Y. (2001). An analytical solution for a jointed shield-driven tunnel
lining along a horizontal line at tunnel axis level. lining. Int. J. Numer. Anal. Meth. Geomech. 25, 365-390.
This exercise can be used to inform the mesh Nomikos, P., Rahmannejad, R. & Sofianos, A. (2011). Supported Axisymmetric Tunnels Within Linear
geometry used in the numerical model. For a Viscoelastic Burgers Rocks. Rock Mech. Rock Eng. 44, 553564.
different example, see Pound (2006). Figure 2 Park, K. -H. (2005). Analytical solution for tunnelling-induced ground movement in clays. Tunnelling and
shows a comparison between the Kirsch Underground Space Technology 20, 249261.
analytical solution and the numerical results Pound, C. (2006). The performance of FLAC zones in bending. Proc. 4th Int. FLAC symp. FLAC and Numerical
from the 3D modelling, again for the hoop Modeling in Geomechnics 2006 (eds. P. Varona and R. Hart), Madrid, Spain, pp.351-357. Minneapolis: Itasca
stress above and below the shaft opening. A Consulting Group, Inc.
comparison like this allows us to see what the Vu, T. M., Sulem, J., Subrin, D. & Monin, N. (2012). Semi-Analytical Solution for Stresses and Displacements in
effects of the additional complexity are a Tunnel Excavated in Transversely Isotropic Formation with Non-Linear Behavior. Rock Mech. Rock Eng.,
(curvature effects of the 3D geometry, soil Ahead of Print, July 2012.
structure interaction and construction sequence,
TUNNELLING JOURNAL 45
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 46
PROJECT REPORT
BRISBANES
AIRPORT LINK:
Scale and complexity
in record time
BRISBANES AIRPORT LINK
M7 toll road opened to traffic
in July 2012, 50 months after
the project was awarded to
BrisConnections, a consortium
involving Macquarie Queensland State structures to the existing road ongoing supply to the
Infrastructure Group (Financier) Government: network. community. The new toll road
and Thiess-John Holland Joint the Northern Busway Aside from the extensive tunnel and flyover upgrade reduced
Venture (Contractor), with (Windsor to Kedron) - a sections that are the main the areas traffic congestion by
Parsons Brinckerhoff-Arup JV 3km two-way dedicated subject of this article, the up to 45%, cutting down traffic
(PBA JV) as their designer. The Busway, including 1.5km project included 25 bridges time from the airport to the
project is characterised by its of tunnels, and (about half of which were non- Brisbane CBD to about 10
sheer size, extreme complexity the Airport Roundabout standard, curved, and/or mixed minutes (saving approximately
and world-class innovative Upgrade, including unit construction), 7km of 20 minutes), avoiding 18 sets of
design. The consortium realignment of a main surface roadways, new traffic lights.
laboured intensively with an arterial motorway and a parklands and bicycle paths.
average capital cost of $100M 750m long match cast Given the extensive nature of Alignment optimisation
per month, to deliver, in record segmental flyover bridge the tunnel connecting A reference design was
time, Australias largest ever A 45 year concession toll road structures at each end and presented as part of the project
transport infrastructure project. to operate under a Public midway along the tunnel, all EIS. The general concept is to
The Airport Link project Private Partnership (PPP) trunk services, including water, link the surface and multi-level
consists of three separate consisting of the sewer, drainage, interchange, as well as the
contracts: AirportlinkM7, 6.7km long communications, power, optic recently constructed Clem7
Two Design-and-Construct dual tunnel with additional fibre, and gas had to be re- tunnel, at Bowen Hills (named
capital works projects underground on and off designed and rebuilt with a the project Southern
undertaken for the ramps and connecting diversion strategy that assured Connection) to the East West
Arterial at Toombul (named the
project Eastern Connection)
Table 1: Summary of the project tunnel sections leading to the Brisbane Airport,
whilst providing a connection to
No of lanes Tunnel type Total length [m] Span [m] * the main North-South Arterial
3 lane main line Drained mined tunnels 3471 11.9 to 15.3 through Brisbanes north side at
3+ to 5+ lanes Drained mined caverns 1701 16.7 to 27.4 Kedron (named the project
1 to 3 lane Drained/undrained mined ramps 2124 8.1 to 17.1 Kedron Connection) which was
2 lane TBM tunnels 4060 + 580 (cavern walk) 12.5 located about mid-way along
1 to 4 lanes Cut and cover tunnels 3470 10.5 to 26 the mainline tunnels (figure 1).
Cross passages Mined drained and undrained 38 total + 2 cross cuts 5.4 to 5.7 One of the major alternatives
Underground Sumps and Mined drained tunnel 3 substations and 2 sumps 12.2 to 17.4 to the reference design that the
substations consortium selected and
Busway tunnels (2+ lane) Mined drained tunnel 503 14.5 designed for construction was
Busway tunnels (2 + lane) Cut and cover tunnels 975 13.4 to 18 to locate the highway T-
interchange (figure 2) at Kedron
* Span is to extrados of permanent lining and does not include temporary/initial lining support, i.e. excavated rock is larger than stated in the table underground to reduce the
46 TUNNELLING JOURNAL
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 47
PROJECT REPORT
So mp
ra
Figure 1: Project general arrangement
ut
hb
Southbound on-ramp (figure 4) to
ou
nd
meet the requirements of road
Entry and Exit: Gympie Rd Kedron Entry and Exit: East West Arterial grades as well as optimising the
Stafford R Ramp connections
d. Bench
A A alignment in regards to the tunnel
Entry and Exit: Stafford Rd Entry and Exit: Sandgate Rd
Ramp
and
Invert
Headwall Westbound
off ramp depth, and the length of the
ramps. In this case, stepping up of
Entry: Lutwyche Rd the upper tunnels invert, by
Ramp localised flattening of its invert
Cut and cover tunnel
Roadheader tunnel Ground with additional reinforcement,
Airport link and surface Soil nail wall
Lutwyche was required to provide sufficient
Northern Busway TBM tunnel Canopy tubes
Tunnels Earth structure Capping slab separation between the two
Elevated structure bridges tunnels, which was in the order of
Headwall Projected permanent lining
Surface roads Westbounds crown 200-300mm.
Transition structure Top heading Shotcrete collar
Bench Westbound invert As the tunnels reached the
Northern Busway Invert
surface, the connecting structures
Southbound
Windsor on-ramp were very complex (figure 5),
tunnel
Invert having to deal with multi-level
Section AA ramps, the integration of a
Bowen busway tunnel running in an
Hills Temporary
Ramp connections
Backfill capping slab arch orthogonal direction, a smoke
Exit: Bowen Bridge Rd extraction duct having to travel to
Soil Nails
a ventilation station, while at the
Westbound same time passing under a major
Entry and Exit: ICB Entry and Exit: Campbell St off-ramp
tunnel waterway and connecting to two
Invert
Entry and Exit: Clem 7 main arterial roads.
Southbound
on-ramp
In this area there are three levels
tunnel
Figure 4 (drawings right and pic below): of tunnel structure overlain by
WB off-ramp to SB On-ramp interaction surface roads, which in turn sit
below elevated bridge structures.
There are bridge piers which are
supported by transfer beams that
form the roof of cut-and-cover
tunnel structures below.
The design of these convoluted
multilevel structures had to face
further challenges: a widely
varying geology (soft soils to
200+MPa rock) and sequencing
of works on a major arterial
leading to the city centre. Three
dimensional modelling here was
of the essence, so that true
sections could be produced to
enable the contractor to visualise
surface impacts of the project. the structure and hence plan
This solution moved all large construction.
heavy traffic movements
Figure 2 (above right): 3D underground (figure 3) Mined tunnels
representation of the improving traffic flow efficiency, The geology along the alignment
underground T-interchange while keeping the surface roads of the numerous mined tunnels
at Kedron for local vehicular movements, sections varied extensively from
buses, pedestrians and cyclists. very strong rock such as Brisbane
Tuff, argillites and phyllites down
Kedron Connection to very weak siltstones with ash
At the midway interchange at (clay) bands. In various locations,
Kedron, the connection between the rock cover above the tunnels
the on and off ramps and the was very limited while the geology
main line tunnels are located could change quite rapidly along
underground in large span the alignment. Following a
caverns. Tunnel ramps intertwine geotechnical site investigation, the
above the mainline tunnels, ground conditions were
resulting locally in the interaction characterised to define rock mass
of three levels of tunnels, with classes for each of the geological
two ramps almost encroaching on units expected to be encountered
Figure 3: Rendered section of the on and off ramps below the surface each others profile (the invert of for each mined tunnel section.The
streets at Kedron the Westbound off-ramp rather extensive range in tunnel
TUNNELLING JOURNAL 47
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 48
PROJECT REPORT
48 TUNNELLING JOURNAL
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 49
PROJECT REPORT
TUNNELLING JOURNAL 49
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 50
PROJECT REPORT
Figure 13: TBM tunnel lintel and sill beam (+ bicones) opening sets
warranted the use of the steel set final cast in-situ concrete lining, employed). To facilitate easy
opening system. A single set the steel segments were filled and anchoring of the beams onto the
consisted of four or six steel encased in shotcrete to ensure segments, anchor reinforcement
segments connected together and both durability (cover) and fire cages were placed into the
the assembly provided an opening resistance (heat transmission moulds during casting of the
door in the centre while the buffer). precast SFRC segments. An
remaining structure ensured Lintel-sill beam openings - In essential element in the design
support of the ground loads the more competent ground, a was to ensure that the stiffness of
through a steel bolted portal lighter support was adopted the bicones and of the steel
frame. The design of the steel sets consisting of lintel and sill beams beams were compatible. If one
incorporated sealed ports that in combination with bicones element was too rigid compared
enabled canopy tubes to be easily between the steel fibre reinforced to the other, then it would attract
drilled and installed through the concrete rings in the more load in the system and result
Figure 11: Radial joint anti-burst- steel set prior to door removal and circumferential joints around the in a failure of the structure.
ing reinforcement steel fabrica- cross passage excavation. Prior to cross passage opening (figure 13).
tion continuous helix the removal of the door, two or The openings were three rings Fire life and safety design
four props (again dependent on wide (6m) as it was initially The project incorporates a state-
using steel sets and props were the geology) were installed to envisaged that the cross passages of-the-art tunnel fire management
adopted, two or three rings wide provide additional support against would be excavated with a road system utilising a smoke extraction
dependent on the geology. In squatting of the ring due to header, but due to schedule system via smoke ducts, along
several of these locations, ground removal behind the constraints, the cross passages with a complex deluge system
although the cross passage itself segment (figure 12). ended up being mined with creating arguably the worlds
was excavated in soft rock, the After excavation of the cross remotely operated excavators (as safest tunnel.
crown of the tunnel was sitting in passage and installation of the was the case in the softer rocks A unique aspect of the project
sandy and clayey soils, which waterproofing membrane and section where steel sets were was that the fire and deluge
50 TUNNELLING JOURNAL
TJ_1212_046_051.qxd:Feature 16/12/12 01:12 Page 51
PROJECT REPORT
TUNNELLING JOURNAL 51
TJ_1212_DIX_052_054.qxd:Feature 16/12/12 15:02 Page 52
CERTIFICATION
Emergency
Cable
Certification
Withdrawal Professor Arnold Dix
CERTIFICATION
requirements. This means that the acceptability etc. will require a detailed description, by authorization to utilize ULs certification mark
of the achieved level of fire and life safety type, dimensions, material description, on the cable will be suspended until samples
performance in tunnels must be reviewed. This manufacturer and part number for test are available and found compliant. The
is not a matter of routine 'risk assessment', it is Raceway-type, trade size and manufacturer systems described in the FUS Procedures will be
a matter of reassessment and judgement based Couplings/Connectors - type, model number, subjected to the UL 2196 test."
on the new information available about the and manufacturer A reasonable inference that can be drawn
performance of emergency cables in a fire. Boxes - type, model, and manufacturer from these interim requirements is that the
Supports - spacing, type, model number, and overall performance of these fire resistant
Interim Certification Inferences manufacturer assemblages is the function of a range of
UL have released information about interim Pulling Lubricants - If used, described by interdependent variables and that the
certification arrangements in the absence of amount to be applied, manufacturer, and performance may vary with time.
current UL certification and the withdrawal of part number The testing every six months of cables and
prior UL certification. The interim provisions System orientation - vertical, horizontal, s- assemblies raises the prospect that UL have
provide a window into the variables which UL type, or other is to be described in detail identified significantly changed fire
have identified as important when determining along with the detailed description of other performance between the initial testing of a
functional performance of a proposed new system components" product and subsequent testing. It is
interim circuit protective system. These Furthermore under the interim arrangements conceivable that processes - such as the release
requirements provide an insight into the follow up testing is required of the original of volatile fire suppressants from cables with
multiple critical factors associated with the fire tested material every six months. time - have now been identified by UL as a
performance of such electrical systems. UL "Follow-Up Testing significant factor in the ongoing performance
2196 now requires (on an interim basis) the Every six months: of these emergency systems in fire challenge
following details: Cables In addition to normal FUS inspection, scenarios.
Jacket-thickness, material a one foot long sample of each cable type will The fact that UL has not re-instated
designation/formulation, including raw be selected by UL Field Services staff and sent certification for these emergency cables and
materials by manufacturer and part number to UL laboratory facilities for a detailed analysis. assemblies also suggests that the failure modes
Conductor-type/grade of copper or other The analysis report will be compared to the identified are potentially significant.
alloy (if used) previous sample analysis and stored as a test
Insulation-thickness, material reference. NFPA 130 & NFPA 502 Update
designation/formulation, including raw Systems - Sufficient cable to construct 5 test NFPA is currently trying to reformulate
materials by manufacturer and part number systems for each of the systems described in prescriptive tests for cable performance. During
Any other cable material, such as a shield, the FUS procedure will also be selected by UL November NFPA held urgent meetings of both
drain wire, rip cord, reinforcing materials, Field Services staff. If cable is not available, the its 130 and 502 committees to formulate
mmm$lcj#]cX^$Z[
1 m
J^[j^_Yad[iie\Wif_Z[him[XWdZj^[
Z_ijWdY[h[iebkj_ede\j^[BWi[h?dj[h#
\[hec[j[h ki[Z _d KBIh BdjaY VcY
HZ\bZciBZVhjgZbZciioij[c$
TJ_1212_DIX_052_054.qxd:Feature 16/12/12 15:02 Page 54
CERTIFICATION
revised certification testing standards for in a fire situation. No matter what cable is used as being in compliance with this standard."
emergency cables. These tests will necessarily (certified or otherwise) the cable fire Such equivalency provisions within these NFPA
prescribe onerous fires during which electrical performance must be understood and standards highlights there potential to embrace
performance of cabling systems must be incorporated into the fire safety design of the change, innovation and unique project
maintained. project. circumstances. The current withdrawal of UL
The challenge with formulating such tests is I am also aware of other projects in which an emergency cable system certification could
that the origin of the performance criteria executive decision has been taken, not to readily be navigated if there were equivalency
which must be met is often obscure more a worry fires dont happen here. Such a provisions in the documents mandating use of
matter of practice than a matter of pure response would constitute criminal conduct in the NFPA 130 and 502 standards.
science. For example the time temperature some countries if a fire occurs and death results
curve for electrical cable continuity is in as a result of failed cable performance. In many Conclusions
substantial part derived from forensic countries such conduct by professionals may The current UL certification situation demands,
examination following real fire events but these result in a prison sentence if there is a loss of at the very least:
challenges may (or may not) be an appropriate life). In the absence of UL certification Informed prescription of minimum cable fire
performance standards for a specific tunnel. engineering analysis is an appropriate means of performance requirements
By way of example there is a strong documenting and determining if the use of a Urgent revision of what constitutes Listed
argument that the electrical cabling specific cable in a unique application is fire cable
performance in a tunnel fitted with an appropriate. A professional response is required The establishment of pragmatic testing
aggressive fire suppression system and with from engineers in such circumstances. criteria to better represent the conditions
cabling installed at a low level within the tunnel of real cable installation and set reliable,
may rightly differ from the cabling performance Looking Forward functional, performance requirements and,
required in a tunnel with no active fire NFPA 130 and NFPA 502 are robust standards where appropriate, reflect the unique
suppression system and cabling running along which recently adopted the concept of circumstances of a tunnel
the tunnel crown. 'equivalence'. Equivalence is a mechanism An assessment of the expected
Other discussions may rightly emerge in NFPA use to promote innovation and performance of existing installed cables in a
tunnels where there is redundancy of enhancements to fire and life safety in fire Emergency and, depending upon the
emergency circuitry or other aspects of the circumstances outside the prescriptive results of the expected cable performance
design or operational risk profile that make the requirements of the standards. mitigation of any unacceptable
electrical and mechanical systems performance The current certification withdrawal consequential safety risks
less vulnerable to single point electrical cabling highlights the need for an 'equivalence' in the For those of us tasked with making and
failure. overarching framework specifying NFPA 130 advising on immediate decision making on
To highlight this point an inspection of a and 502 standards. Drafting regulatory operational and in construction subsurface
tunnel in late November in the Middle East provisions contemplating a departure from infrastructure matters, a steady hand with an
revealed electrical cabling in hot dipped strict compliance with the standards could be eye to documentation and detail must be
conduit controlling a mist system in a road included in projects (especially outside the USA) applied. Now is the time to exercise informed
tunnel. The level of fire risks is substantially in order to mitigate the risks caused by expert judgement and to well document the
reduced albeit that the control cabling may be changes or flaws in the NFPA standards which process. In the event of failed tunnel
more vulnerable to fire damage than originally occur or are revealed in circumstances outside emergency systems with implicated failed
thought. Careful engineering judgement must the control of the client. Furthermore such emergency wiring the importance of this step
be exercised in such circumstances. equivalency positions (if properly drafted) will be critical. Exercising judgement in the
provide a way of customising an NFPA standard absence of a genuinely fire rated cable or a
Fit for Purpose for local conditions, or unique circumstances, proscriptive code is absolutely essential.
The impact of the UL certification withdrawal without invalidating the overall fire safety It is by no means clear the extent to which
directly impacts the findings of any performance achieved by the NFPA standard. the vulnerabilities revealed in the US are also
bureaucratic assessment of fitness to Such overarching equivalency provisions mirrored in other markets where other
operate tunnels because the performance of would supplement and be consistent with the certification and standards are applied. It would
the cabling installed in fire conditions has been internal equivalency provisions within NFPA be naive to presume there are no issues
questioned and NFPA 130 and 502 mandate 130 and NFPA 502. elsewhere.
certified cable. Our immediate challenge is to Currently NFPA 502 2011 Edition provides: In the future it would be useful to draft an
use engineering judgement to determine "1.5 Equivalency. Nothing in this standard equivalency framework where NFPA 130 and
which tunnels are in substance affected by the is intended to prevent the use of systems, NFPA 502 are specified. This would invite
current emergency cabling issues and to methods, or devices of equivalent or superior innovative and effective solutions when
mitigate those risks. quality, strength, fire resistance, problems arise like the blanket withdrawal of
effectiveness, durability, and safety over certification of emergency cabling for road and
Improper Responses those prescribed by this standard, provided rail tunnels.
It has been suggested during meetings over sufficient technical data demonstrates that
the last few weeks that cables bearing the UL the applied method material or device is REFERENCES
marking should be sourced and used without equivalent to or superior to the requirements
fear or hesitation as the marks the cable bears of this standard with respect to fire 1. http://www.arnolddix.com/usa-cable-fire-
were lawfully applied and therefore the cable performance and safety. rating-withdrawal.html
can properly be used. Such assertions reflect an 1.5.1 Technical documentation shall be 2. http://www.arnolddix.com/library/
inappropriate and highly unprofessional submitted to the authority having jurisdiction 3. US Emergency Systems Cables Certification
approach to ensuring the performance of to demonstrate equivalency. Withdrawn: Crisis or Crossroads?
underground fire and life safety systems and 1.5.2 The system, method, or device shall http://www.arnolddix.com/wp-
thereby the safety of tunnel users. The issue is be approved for the intended purpose. content/uploads/2012/11/TJ-Oct-Nov-12-Crisis-
not whether cable bears the UL mark - it is 1.5.3 Alternative methods or devices or-Crossroads-2.pdf
whether cable used will perform appropriately approved as equivalent shall be recognized
54 TUNNELLING JOURNAL
Constructing a
Sustainable future.
At VINCI Construction Grands Projets, we engineer solutions that are not only
financially competitive, but work sustainably for the planet. It starts with putting
Safety first, always, at all times, on every site. Health & Safety training, policies
and guidelines are all in place, but to generate the best possible results, we go
further with our innovative (A)live on Site programme. We understand that our
people are more reactive to what concerns them directly, we have a team who
visit the site, shoot a short movie and then broadcast it to the team. Each scene
is analysed with behaviour experts, underlining the good (and less good) actions.
photo credits: MVB, VINCI and subsidiaries photo libraries, Andras Nemeth, Clarence Michel.
(A)live on site has been successfully delivered to more than 2,000 people, in 12
languages, across 14 countries, including the UK.
To learn more please visit www.vinci-construction-projects.com/british-isles
TJ_1212_Products_056_057.qxd:Feature 15/12/12 21:48 Page 56
PRODUCT NEWS
56 TUNNELLING JOURNAL
TJ_1212_Products_056_057.qxd:Feature 15/12/12 21:48 Page 57
PRODUCT NEWS
TUNNELLING JOURNAL 57
TJ_1212_CONTACTS_058.qxd:Feature 15/12/12 21:35 Page 58
contact US
contributorS
Gary Tween Tris Thomas
Managing Director Editorial Director
Tel: + 44 (0) 1622 720 631 Tel: + 44 (0) 1622 720 631
Mobile: + 44 (0) 7973 205 638 Mobile: + 44 (0) 7812 011 139
gary@tunnellingjournal.com tris@tunnellingjournal.com
Kristina
Smith
Kristina Smith has been writing
about civil engineering and
construction for over 15 years,
Rory Harris Steve Caming having started her career out on
Chairman Publishing Director site as an engineer.
Mobile: + 1 (859) 321 3164 Tel: + 1 (603) 447 1187
rory@tunnelingjournal.com Mobile: + 1 (603) 662 6263
steve@tunnelingjournal.com
tunneling@roadrunner.com
Adrian
Greeman
Mark Piper Peter Bell Adrian Greeman has been
Finance Director Director
writing about international
Tel: + 44 (0) 1672 563 662 Tel: + 44 (0) 1622 720 631
civil engineering projects (in
Mobile: + 44 (0) 7768 554 646 Mobile: + 44 (0) 7770 441 867
particular tunnels, bridges
mark@tunnellingjournal.com peter@tunnellingjournal.com
and highways) for the past
16 years.
Tunnelling journal
58 TUNNELLING JOURNAL
MAN VERSUS NATURE
No two tunnels are the same. Every project has its own challenges.
Even basic elements like ground conditions often change during the bore.
To resolve any issues that you encounter, Robbins provides a full range
of support including engineering staff and on-site field service technicians.
From mixed ground to high cover conditions, weve helped our customers
overcome hundreds of challenges over the last 60 years.
Tunnelling
www.tunnellingjournal.com Dec 2012/Jan 2013
LEES SLIPFORMING
SOLUTION
BARTON - TBM AND D&B
TBMS IN MINING
NATJ_1212_NAFNTCOVER_001.qxd:cover 17/12/12 21:58 Page 1
Tunneling
north american Dec 2012/Jan 2013
www.tunnellingjournal.com
journal
ADVANCES IN AUSTIN
JOLLYVILLE WATER TRANSMISSION MAIN
MAKES GREAT PROGRESS
Tunneling
north american Dec 2012/Jan 2013
www.tunnellingjournal.com
journal
ADVANCES IN AUSTIN
JOLLYVILLE WATER TRANSMISSION MAIN
MAKES GREAT PROGRESS
comment contentS
A happy New Year
Wow, what a year, and it feels like its
flown by faster than Felix Baumgartner
overtaking a meandering seagull. So for
any of you who missed the highs and
lows, heres an end of year recap of my
best, and worst, bits of 2012.
If you happen to read my Comment on
a regular basis, youre probably sick of
me harping on about the Cutting Edge conference on pressurized
TBM tunneling, in Miami, this April. But, hey, its my Comment, and for
me it really was one to the highlights of the year. I was blown away by
the success of the event which is saying something, considering I put
together the program and the feedback we got from delegates. It Above: Storm
damage on
was also a chance to visit the stunning Port of Miami Tunnel, with
Staten Island,
Bouygues Civil Works Florida putting on a great tour of the project.
New York (p5)
At about the same time, plans were released for the new mammoth Right: A Ballard
30-mile (60km) long Bay Delta Tunnel, in California, which is sure to team undertake
feature heavily in the pages of the magazine in the year to come. The confined space
first of Sound Transits U220 drives broke through, in advance of repairs (p21)
completion of tunneling for Seattles U-Link Light Rail project, in June.
Mexicos largest TBM, a 33.5ft (10.2m) diameter Robbins EPBM, also
completed tunneling for the capitals new metro Line 12. 5 North American News
Project, contract & company news
In June, Seattles Alaskan Way bored tunnel replacement broke
ground on my birthday (which was nice); Torontos Holey and Moley
TBMs completed their first drives for the Spadina Subway extensions
8 The Insider
Goodfellow looks at how the recent US
presidential election might affect the industry
Southern Tunnels; and we all got together for a highly successful North
American Tunneling conference, in Indianapolis. July saw tunneling
completed on all of New Yorks megaprojects, with GTF JVs soft
ground East Side Access drives coming to an end; and the EA approved
10 Advancing in Austin
Excellent TBM advance rates on the
Jollyville Transmission Main are helping to
for Ottawas $2.1 billion light rail line. keep Austins WTP 4 project on track
By October, Canadas tunnel boom was in full evidence, with SNC-
Lavalin selected for Vancouvers Evergreen Line; the first Eglinton
contract awarded in Toronto; and a highly-successful Tunnelling 16 After the storm
Hurricane Sandy recovery efforts continue in
New York, with the subway and road tunnel
Association of Canada (TAC) conference, in Montreal. Unfortunately,
repair bill set to exceed $3 billion
shortly afterwards (and timed perfectly to coincide with my flight back
to the UK), Hurricane Sandy slammed New York head on causing an
estimated $3 billion worth of damage to tunnel infrastructure (p16).
So, as we head towards the end of 2012, I can only wonder what
21 Under pressure: informed interventions
Ballard Diving talks to NATJ about the
importance of pre-planning interventions
next year will have in store for us. Lets hope its a safe and happy one.
Front cover
MWH is performing construction management-at-risk services for the City of Austin on the
Jollyville Transmission Main. This is a key component of the $359 million Water Treatment
Plant 4 project currently under construction. When completed, the plant will produce 50
million gallons of potable water per day as part of a long-term plan to account for future
growth within the Austin area. With a total length of 6.5-miles and an excavated diameter
of 10ft 8in, the Jollyville Transmission Main is the longest of three tunnels included in the
WTP4 project. The MWH subcontractor for this portion of the work is a joint venture of
Southland Contracting and Mole Constructors. They are using three TBMs in three separate
reaches of approximately 4,500ft, 10,000ft and 20,000ft each and have achieved daily
advance rates of more than 200ft. Photos courtesy of The Robbins Company.
PROVEN
Offering new and used tunneling equipment
for more than 25 years.
##!#(*'
# " (#
##$(&!'
& )!#'
" #'(' MINING
( "'
EQUIPMENT
"( (#"
%)$!"(
#"
, +
, www.miningequipmentltd.com
overseers. Other team members of the the project. Remaining funds will come from
consortium include EllisDon Corp, Dragados development revenues and transit reserves.
Canada, Veolia Transportation Services, Following the December 6 announcement,
Adamson Associates, BBB Architects Ottawa, city councillors will debate the staff
Dr G Sauer & Partners Corp, Fast + Epp, Hatch recommendation twice first on December
Mott McDonald, IBI Group, L2 Advisors, 12 and again on the day they take a final vote
MMM Group, Scotia Capital, Sereca Fire on signing the contract on December 19. The
Consulting and Thurber Engineering. project is expected to start in February with
Rideau Transit Groups (RTG) proposal Mayor Watson makes the announcement work on the tunnel due to start in July.
the
insider
Bob Goodfellow, PE, CEng, Senior Vice
President, Aldea Services LLC
CONCEPT TO COMPLETION
AUTOMATED GROUT & SLURRY SYSTEMS
Featuring high shear colloidal mills
with new Mk IV mechanical seals
Fully Automated
Self Cleaning
Containerized Plants
Lo-Prole Plants
Foam & Admix Systems
www.teammixing.com
sales@teammixing.com
Ph: 1.604.556.7225
JOLLYVILLE
Left: The 270ft deep x 36ft diameter Four Four Points Shaft and the Jollyville Reservoir curve on the project has a 750ft (228m)
Points Shaft, with grouted liner plate Shaft are the staging points for three tunnel radius, with others at around 1000ft (305m).
covering the Edwards Formation bedrock drives. These are being excavated through One is to avoid going under a high school,
competent limestone, with little temporary but mainly the curves are due to easements.
Below: Four California switches will be support, at depths of up to 350ft (107m) The route pretty much follows roads, except
used within Reach 2, to facilitate rapid under residential areas and the protected under the Balcones preserve, explains Tunnel
advance rates in the 22,000ft long drive Balcones Canyonlands Wildlife Refuge. Superintendent, Kent Vest.
The reason for the depth of the alignment Greatly assisted by the fact that no ground
Below right: Mining Equipment muck cars is due to the sensitive environmental nature of support has been required within the tunnels
are hoisted within the Four Points Shaft the regions upper limestone geology. In as yet, the rapid pace of production is the
particular, karst voids within the Edwards result of extensive planning, with mucking
formation provide a habitat for endangered and ventilation logistics posing a major
cave-dwelling invertebrates including six listed challenge in the long, small diameter, tunnel
Initially, WTP4 will be capable of treating 50 species of arachnids and insects. Strict controls drives. Our progress relies on the speed of
million gallons per day, but the pipeline as a on groundwater also exist, to minimize any muck haulage, says Arciszewski. When
whole has been designed with a future potential hydrological impacts to the karst were 20,000ft into the Reach 2 drive, its
capacity of around 350 gallons per day. The system and the Balcones Canyonlands probably going to take the better part of an
overall scheme is being delivered by MWH Preserve above, which has been set-aside as a hour for the trains to get in or out. So
Constructors, who has a $359-million habitat for the Jollyville salamander and two ultimately well have four California switches
construction management-at-risk contract for species of protected rare birds. This results in a installed, one every 5000ft (1.5km), so that
the project. It represents Austin Waters first tunnel alignment within the lower Glen Rose we can have trains staged along the route.
use of this infrastructure delivery method, limestone formation (see Figure 1, p12).
which places responsibility for all the different The most interesting and challenging
construction packages with one firm. aspects of this project are the environmental
The scheme includes a tunneled lake tap at constraints, says Ray Brainard, Practice
Lake Travis, on Texas Colorado River, and a Director of Engineering Geology with Black &
0.7-mile (1.2km) long raw water tunnel that is Veatch. For example, we did extensive
under construction by Austin Hill Country groundwater assessments in the early stages
Constructors, a joint venture of Obayashi and of the preliminary design, proving that there
Manson Construction. However, by far the are two distinct groundwater systems in the
largest tunneling component of the project is region. One that feeds the springs in the
the Jollyville Transmission Main. upper Edwards aquifer and a second that
were tunneling through in the Glen Rose.
STRATEGIC SERVICES:
HYDROPOWER
WATER CONVEYANCE
COMBINED AND SANITARY SEWERS
MINING
UNDERGROUND FACILITIES
LEADING.Edge
mwhglobal.com
NATJ_1212_JOLLYVILLE_010_014.qxd:Feature 17/12/12 22:58 Page 13
JOLLYVILLE
1100
Balcones then. But we were asked by the City to design
Canyonlands Jolleyville Reservoir the project as if the salamander was already
1000 Preserve
protected, so we have taken into account any
900 and all possibilities of affecting that habitat,
says Brainard. There are also six species of
800
endangered spiders and insects that live in the
700 Four Points Edwards karsts and we are going under the
Shaft Balcones Canyonlands, which was set aside
600 for two species of birds, the Golden Cheeked
Pard Shaft Warbler and the Black Capped Vireo.
500
To address these environmental concerns
0 10,000 20,000 30,000
the City established an Environmental
Commissioning Group to act as additional
3 drive, from the Jollyville Reservoir Shaft to three or four years ago, when the current oversight during design and construction of
the PARD Shaft, has also been making stable WTP4 site was labeled less sensitive than the the project. This environmental process has
progress with 5,300ft (1.6km) mined to date. previous location. Even then, the city council enacted additional requirements and
Its basically a hybrid machine, says Vest. considered deferring completion of the project restrictions above the usual City of Austin
Due to time constraints, we had to utilize for another five to 10 years. But, when it was construction project standards. There was a
machines we already owned. This machine estimated that this would add somewhere lot of coordination while we were sinking the
was previously used on the East Side Water between $160 million to $200 million to the shafts, says Arciszewski. The Environmental
Tunnel, in Rochester, New York. Robbins overall budget, the city council decided to Commissioning Group was in the shaft 24
rebuilt it for this project with a new cutterhead keep the project moving forward. hours a day and every time we found a void
and roll correction. Although the deep tunnel alignment they were required to inspect it and make sure
No support has been required so far in any reduced the amount of contingency we had it wasnt a suitable habitat for some of the
of the tunnel drives, with ground conditions to take into account for the karsts, three of endangered species.
fairly uniform throughout the Glen Rose. On the four shafts still go down through the The temporary support design for the
Reach 3 there is some quartz, according to the Edwards formation, says Brennan. These are shafts is based on groundwater modeling,
GBR up to 12%, but not much in Reach 2, if the 220ft (67m) deep x 13ft (4m) diameter which shows there are dolomite zones within
any, says Arciszewski. But cutter wear has Water Treatment Plant (WTP) Shaft; the 270ft the Edwards formation that contain most of
been good. Following our first 4,400ft (1.3km) (82m) deep x 36ft (11m) diameter Four Points the permeability, says Brainard. But there is
Reach 1 drive, we only changed two cutters, Shaft; and the 350ft (107m) deep x 36ft very little vertical connection
which was more bearing failure than wear. (11m) diameter Jollyville Reservoir Shaft.
Water inflows have also been minimal: We There is an environmental
do get little pockets of perched water, but it coalition associated with the project
bleeds off pretty quick, says Vest. There is a
sump built into Reach 2, to enable us to
leapfrog cooling water and any groundwater Below: One of many small
back to the shaft. But we have very strict limits karst features within the
as far as how much groundwater infiltration Reach 3 tunnel, containing
we are allowed in the tunnel. If we ever quartz crystals (right)
exceed those limits we will have to start
installing grouted liner plates.
We have about a 10th of a gallon/minute
inflow along 17,000ft (5.2km) of excavated
tunnel at present, so its a dry tunnel says
Brainard. But we have strict trigger limits and
should they be exceeded it would require a lot
of work to cut off that inflow. The City
doesnt want to take chances and is willing to
commit the necessary resources to do that.
JOLLYVILLE
Dewatering &
Groundwater Control
Ground Freezing
Deep Foundations
Underpinning Systems
Grouting &
Ground Improvement
Environmental Remediation
www.moretrench.com
Geotechnical Construction Coast to Coast 800-394-MORE
NATJ_1212_SANDY_016_019.qxd:Feature 15/12/12 18:06 Page 16
HURRICANE SANDY
After the
LOWER MANHATTANS FINANCIAL
DISTRICT has seen its fair share of
destruction, most notably when the World
Trade Centres twin towers were destroyed by
terrorist attacks on September 11, 2001.
Following Hurricane Sandy, a Category 1
storm
Many of New York Citys key road and rail
storm that hit New York on October 29, it was
the southern tip of Manhattan that bore the
brunt of the destruction wrought by the storm
- at least in terms of tunnel infrastructure.
Seven of the citys subway tunnels were
flooded during Sandy, and all but three of the
tunnels were up and running little more than
a week after Sandy hit. However, these
remaining sections of subway lines were still
tunnels were inundated with salt water out of operation when NATJ went to press in
during Hurricane Sandy. Recovery work early December, and all three sections are
located in lower Manhattan. The continuing
continues well into the Christmas period, closure of these line sections - the R train
suspended between 34 St-Herald Square &
with the total repair bill expected to reach Jay St-Metrotech, the J/Z trains suspended
south of Chambers Street, and the 1 train
$3 billion. John McKenna reports suspended south of Rector Street - leaves Wall
Street commuters with just one subway line,
the 4-5 line, to cram on to (Figure 1).
Perfect storm
When Sandy hit New York, its storm surge
coincided with a new moon high tide to
inundate Lower Manhattan with flooding
that those working on the citys subway
system had never witnessed before. It is
estimated that 66 million gallons of water
had to be pumped out the subway system
following the storm.
New York City Transit Chief Maintenance
Officer, Joseph Leader, says flooding
protection such as sandbags and temporary
inflatable barriers deployed in vulnerable parts
of the system were simply overwhelmed by
the storm surge that hit Lower Manhattan.
Even with all the barricades it was just not
going to work, says Leader. It was almost a
Category 2 storm, and the surge was nearly
14 feet high.
HURRICANE SANDY
Despite flood defenses being overwhelmed the MTAs entire system, with just under $3 the pump room to get it going, and as we
by the water rushing through the tunnels, billion of that relating to tunnel infrastructure, began to bring back power we then were
Leader said he was confident the subways and $2.2 billion relating to the subways alone looking for faults and beginning a big
pumping system would move the water out (see table on p18). replacement process.
quickly enough to avoid any lasting damage As Leader hints at, both on the subways
to the infrastructure. However, what Leader No signal and the road tunnels (see below) much of the
hadnt anticipated was that all of Lower By far and away the biggest single item on replacement of electrical equipment has been
Manhattan would lose its electricity supply Sandys tunneling repair bill is the estimated a temporary patch job of replacing faulty
due to water infiltrating one of utility Con $770 million it will cost to restore the components to get New York moving again.
Edisons substations. Power only began to be Subways signalling system to pre-storm However, the MTA is under no illusions the
restored four days after the storm. conditions. With power out in Lower long term impact Sandy could have on these
Without power and with vital structural and Manhattan, much of the areas subway systems. For example, it put the cost of
electrical components resting in saltwater, signalling equipment was flooded with bringing the Brooklyn Battery (now known as
New Yorks Metropolitan Transportation saltwater for days. Indeed, it is the damage the Hugh L. Carey tunnel) back to operation
Authority (MTA) sought alternative solutions caused to signalling equipment in the at just $10 million, while the cost of properly
to pump out the water. Alongside placing Subways Montague tunnel that is causing a restoring it, including all its electrical systems,
portable diesel-fuelled high-capacity pumps at vital section of the R-Line in Lower is put at $400 million.
strategic locations throughout the subway Manhattan to remain suspended months Speaking about the damage to subway
system, the MTA also deployed its three after the storm. signalling equipment, Bianco adds: Because
pump trains. Each train comprises a flatbed The Montague tunnel for the R service of the salt infiltration we really dont know the
rail truck carrying pumps capable of pumping contains relay rooms and complicated impact that it will have on the life of
5,400 gallons per minute. equipment, says Bianco. That tube flooded components.
What an amazing asset those pump trains from floor to ceiling and we had very complex One area of the subway where signalling
were, says Carmen Bianco, New York City signal equipment totally underwater. We have equipment was successfully defended was the
Transit Senior Vice President for Subways. had to rebuild most of that equipment and on L service, also known as the BMT Canarsie
We pumped 66 million gallons out of our thats taking some time to do. Line, at a section underneath 14th Street. The
system and those trains were instrumental. Montagues problems were compounded, line is a vital east-west link running across
We know that if we had more of those we says, Leader, not only by the lack of power Manhattan all the way out to Canarsie, in
would have been able to do even better, so from Con Edison to utilise pumps, but by the Brooklyn. The majority of the line is above
we are now looking for trains not in service to fact that when power came back its key ground but goes into a tunnel at 14th street
convert so that we have a few more. pump room was still unusable. that is susceptible to flooding. It also operates
The search for more pump trains is One of the main pump rooms was an expensive computer signalling system. As a
understandable given the anticipated $4.75 completely submersed, says Leader. My result, Thomas F. Prendergast, President, MTA
billion of damage that Sandy has inflicted on people temporarily made a control panel for New York City Transit, says the decision was
Fuuulttoonn St
Fulton S N
ve
1
Ri
Rutgunnel
Man
East
Rector
ecto
ct St.
SStt.t.
T
ers S
Brid
Br
hatt
Boowling
Bowling
w inngg
wl Brrooadd St.
Broa
Bro
Broad S
St Pumping initially began at
oo ge
ge
kly
Green
reeeen
e
an
Br
Whitteh
Wh
Whitehall
ehall
eh
ha SSt. F The first tunnel connecting
Manhattan and Brooklyn,
BR
Flooded to
nel tubes about 4,000 feet long.
the ceiling 2 3
Brook
Jo Tun
K LY N
ra ne
lem l
R
lyn B
Tunn
St.
on
HURRICANE SANDY
Geotechnical,
Mineral Exploration
and Horizontal Coring
www.ruendrilling.com
NORTH AMERICAN TUNNELING JOURNAL 19
NATJ_1212_ADS_020.qxd:Feature 15/12/12 21:05 Page 20
Mind
.YV\UK*VU[YVS:VS\[PVUZ
MVY[OL4PUPUNHUK*P]PS
0UK\Z[YPLZ
Muscle
276-964-7413
^^^OLPU[aTHUUJVT
SUBSCRIBE NOW!
To order, visit www.tunnellingjournal.com and click on Subscription Offer
AT THE FACE
Under pressure:
informed interventions
High-pressure compressed air work is a daily business for Ballard
Diving & Hyperbaric Services. However, there are many variables that
must be considered when setting out to develop a hyperbaric program.
Having planned and undertaken thousands of manned interventions,
Joe Olsen and Jesse Hutton share some cautionary tales, and good
examples of early action, to illustrate how pre-planning can make all the
difference to your tunneling project. Amanda Foley reports
Top left: Confined space
conditions in a DART WE KNOW WHAT KEEPS YOU AWAKE
chamber AT NIGHT, says Jesse Hutton, Ballard Diving
& Hyperbaric Services Chief Estimator. Your
Top right: A 7 bar man- TBM sitting idle underground for months
lock is inspected prior to while some bureaucrat sits on a variance
installation on a TBM request for you to put a compressed air
worker at the face, or while you wait for a
Above right: A diver part because your man-lock doesnt have local
decompresses following compliance. One of the most important
an intervention lessons Ballard Diving & Hyperbaric Services
has learnt from its unparalleled experience in
Left: Confined space the North American tunneling industry is the
cutting during a TBM importance of getting involved early on in a
intervention project to ensure just such issues dont occur.
AT THE FACE
AT THE FACE
designed without onboard man-locks, says owner while they were developing the project machine. This pro-active pre-planning results
Olsen. So facilitating hyperbaric interventions specifications, says Olsen. And when it in a comprehensive hyperbaric program that
required a pretty innovative approach. came to the bid process STP brought us in will enable us to very rapidly deploy, and
Consulted during the conceptual design virtually from the beginning. We met with effectively utilize, a very large team of workers
phase, Ballard ended up working with both them several times during bid preparation to to perform rapid maintenance and repairs to
the contractor and the TBM manufacturer to ensure they had accurate information and an extremely high-profile TBM, says Olsen.
come up with a solution. We drew on the since then theyve involved us in every aspect
traditional concept of pressurizing the tunnel of the project related to hyperbarics. Experienced personnel
and developed a moveable bulkhead that will Ballard conducted an extensive analysis of With thousands of successful interventions
allow us to pressurize the tunnel directly hyperbaric options for the project to provide a under his belt, and currently supervising the
behind the machine, should we need it. performance cost report that would enable majority of tunnels utilizing hyperbaric services
With pressures of up to 6 bar tri-mix gas STP to make informed decisions about the in North America, Olsen is the first to
would be required for any interventions, planning of its hyperbaric operations. This acknowledge the importance of employing
therefore Ballard also developed a project analysis actually revealed the potential for a hyperbaric workers that are trained specifically
specific saturation system to enable hyperbaric reduction in intervention times that equates to to work in tunnels. We have about 150
operations in the narrow confines of the 30 days over the course of the project. divers that work for the company as a whole,
tunnel. Equipment manufacturing of such The scope of preparations for this project but only 60 of those are specialized in
specific and specialized equipment can have a includes operations through a full range of tunneling. We have a high initial turnover on
lead time of up to a year, says Olsen. Which pressures in every hyperbaric mode, from low- the tunneling side; a lot of divers decide its
is a perfect example of why pre-planning and pressure air to high-pressure saturation, says just not for them, so we take training very
early action is so important. Olsen. The extensive pre-planning has also seriously. You have to have workers that
led to the development of a first-of-its-kind understand the machines and know how to
Importance of pre-planning saturation habitat designed specifically for change out tools and make repairs quickly
All the planning and operational concepts tunnel work. It will be capable of supporting and efficiently. Most importantly, you have to
that apply to getting a good start on a tunnel 16 workers, with a surge capacity of up to have workers that are very experienced at
construction project, equally apply to getting a 24. To maximize hyperbaric productivity, the recognizing degrading face conditions. You
comprehensive hyperbaric program, says TBM is also equipped with three man-locks, always have to be concerned about the
Hutton. There are so many variables that each capable of moving six workers to and stability of the face and its something we are
have to be considered when planning a from the pressurized work areas of the constantly assessing while we work.
manned intervention. Regulatory hyperbaric
variance requests can often take up to a year
to be approved, and pressure vessels such as There is more
medical locks, materials locks and special
decompression chambers usually take up to
than one project
10 months for fabrication and delivery.
People really need to contact us at the
where we have
time they order the TBM, that way we can been called in
make sure the right equipment has been
selected says Olsen. There is more than one only to find that
project where weve been called in to do an
emergency intervention, only to find that the
the TBM is fitted
TBM is fitted with the wrong type of man-lock with the wrong
and doesnt meet the required codes. And
then you have to be the one to break the type of man-lock.
news that it means their project is now going Above: A shaft diver prepares for work
to be months behind schedule. Below: A support team checks equipment
Joe Olsen
Unfortunately, such situations are not that
few and far between. Its actually far more
common for Joe and myself to find ourselves
jumping through hoops at the last minute and
performing on an emergency basis, rather
than helping a contractor really prepare up-
front for an intervention, says Hutton.
cdmsmith.com
Minova is a leading world-wide supplier of ground support solutions to the tunneling and civil engineering
industries. In addition to being the leading manufacturer of resin cartridges for more than 40 years, we
offer a range of products from chemical-based consumables to associated equipment and services for rock
bolting, ground consolidation, fiberglass reinforcement, ventilation and water control. Minovas expe-
rienced sales and engineering staff are conveniently located throughout North America and with nine
manufacturing sites in the region, customers are assured of short lead times.
These are just a few of the many products in the Minova family of innovative solutions: