To produce a

working model in Dealing with Construction Permits in


Kuala Lumpur for small scale non-residential projects PROCEDURE AND PROCESSING TIME
that simplify and reduces the number of existing
Process 1 : Data Gathering
procedures, time and cost. Process 4 : Final Inspection for connection to utilities and
issuance of clearances for CCC
11 CRITERIA OF OSC 1SUBMISSION 3 Procedures - 11 days

1 Small Scale Non- 6 Not within the


Residential Project : Heritage Zone
Free Standing Commercial
Building : Office, Retail, Fast Development should
7
Food Outlet, Showroom not be entitle for
Free Standing Factory strata
Building:Factory, Warehouse
Process 2 : Request and Obtain for Development Proposal Plans
Terrace Building/Shop Lot : 8 Estimated water
1 Procedure - 14 days
Office, Retail, Fast Food consumption not
more than
Outlet, Showroom
10,000 litres perday.
Terrace Building/Shop Lot : Distance not more than 30m
Factory Warehouse from the main supply with
Tadika/Taska maximum pipe diameter of
Community Building 150mm
(Multi Purpose Hall)
Petrol Station Estimated electricity
9
TNB Substation (Not exceeding consumption not
2 storeys) more than 1000kVA
(kilo volt amps)
Distance not more
2 In compliance with Kuala
than 500m from power
Lumpur City Plan 2020 source

Conform with the Process 5 : Deposit of CCC and G Form


3 10 Availability of public
expressed conditions in sewerage line nearby 1 Procedures - 1 days
the land title or
provide individual septic
4 Does not require land tank (150 PE)
enhance value
11 Availability of
5 Development on flat telecommunication Process 3 : Notificatio1
land (Class 1 Slope) network Procedure - 1 day

TOTAL : 6 PROCEDURES 27 DAYS