Академический Документы
Профессиональный Документы
Культура Документы
Electrical Energy
2
Audit
Abstract
There are three major working expenses in the industrial plant which are mostly found out to be
on electrical energy. In this electrical energy audit of mogharbel plant we will discuss the
possibility of cost savings in each of the plants components, then electrical energy would
definitely come out on the top, and as a result electrical energy management would help in a
planned area for reducing the cost. This project for mogharbel plant will help in determining the
common features of electrical energy management. This document contains the complete result
which is required to do the electrical energy audit for the mogharbel plant industrial unit. The
We have done the complete energy analysis which is a two stage energy process for the
mogharbel plant. For this kind of work a mapping would be done for energy conservation
This energy audit is for the foundry processes done at mogharbel plant. The main purpose is to
set up the major energy flows of the whole project which will help in utilizing the other
alternatives of energy conservation. As we all know production plays a very vital role in energy
Executive Summary
In this energy audit for mogharbel plant, the production procedure will be described in sub-
procedure/procedural tools and based on that electrical energy balance sheet should be prepared.
With more demand and supply in energy objects balance sheets will be based on equipment
basis. The basic purpose of mapping of all the procedure will describe if there is any defects or
faults disclosed which might affect the consumption of energy from the system. This project
explains all the technical information about the electrical energy audit, also, this project will state
whether or not energy conservation prospects exist in this procedure, for the system inspected.
Furthermore, in this energy audit project of mogharbel foundry plant at Tamworth will help in
Acknowledgement
I would like to acknowledge my family and friends with the help of which I am able to complete
Also, I want to thanks my lecturers and the entire class for their timely guidance for this
electrical energy audit which has helped me in understanding the concept in a much better way.
Electrical Energy
4
Audit
List of Tables
Table 5
Table 6
List of Figures
Table of Contents
1. Introduction .................................................................................................................................. 7
2. Objective of this energy audit ....................................................................................................... 7
3. Scope ............................................................................................................................................. 8
4. Auditing Process............................................................................................................................ 8
5. Mogarbel Plant electrical energy consumption ............................................................................ 9
Lighting survey...................................................................................................................................... 10
6. Electric Motor survey .................................................................................................................. 10
7. Harmonic Analysis....................................................................................................................... 12
8. Recommendations ...................................................................................................................... 24
9. Conclusion................................................................................................................................... 26
References ............................................................................................................................................ 27
Electrical Energy
7
Audit
1. Introduction
Electrical energy is considered the most costly energy source for any industrial plant. As it is
used for efficient and balanced financial operation because of its litheness, electricity gives
benefits over another energy sources such as fossil fuels. A foundry industry uses electrical
energy in a very big amount, and because of that reason it is very important to conserve the extra
energy. This electrical energy audit will translate the ideas into certainty with the mix of
technical practical solutions with financial and other governmental considerations within
specified time. An electrical energy audit of a mogharbel plant will determine how and where
energy will be used and to determine the methods for saving energy and cost for the plant.
The extent of an electrical energy audit, the complications of calculations, and the level of
financial assessment are all problems that might be handled in a different way by every
individual energy auditor and this will be defined in the beginning of the auditing procedure.
Now if we are able to decrease the energy usage which will help in increasing the efficiency at
the plant, energy than can be conserved like ozone diminution and greenhouse effect that can be
improved. The energy audit of a mogharbel plant has been explained in this document.
By proper maintenance and operation energy conservation can be achieved. These actions
include using energy efficient equipment, which will improve electricity demand supervision,
thus by reducing summer temperature settings, for example turning off the light, fans etc.
3. Scope
The essential information for optimizing electricity purchases will be compared with
Energy use linking materials that are used in the systems and devices, a proper training
and education will be given to the technical staff of the Mogharbel plant
To improve propositions for the energy consumption by improving indoor air quality and
4. Auditing Process
Electrical energy audit with consent of senior management without their approval audit cannot
be carried out so, in the starting we will convince them for implementing the energy audit and
management. For this energy audit many tasks will be carried out depending on the type of the
audit facility provided for energy auditing. As a result, an energy audit will not be linear
procedure that is why it has to be integrated. Following functional activities have been followed
for the energy audit (Application of energy audit in buildings and a case study, 1993):
Electrical Energy
9
Audit
Lightning survey
MEASUREMENT WORK
Mogharbel plant is one of the cutthroat foundry industry in tamworth area which supplies around
50% production of foundry in Export. With proper marketing it has become very popular in the
domestic market of tamworth area. Because of which very extensive electrical energy audit is
The energy consumption of the mogharbel plant was identified with area wise and electric
equipment. During the plant visits the results were acquired after dimensions. Power analyzers,
clamp meters, Data loggers will be used to determine the electrical energy consumption of the
mogharbel plant. The final load of the plant comes out to be 5383.178 KW. (Electrical energy
There are four transformers of the rating11 kv/415 kV, 1000KVA and one transformer of the
The major load in the plant is that of motor, which constitutes approximately 80% of the total
load.
Total number of units consumed per month after taking averages of 12 months 16-17 million
Lighting survey
This survey will be done to evaluate the lighting requirement of the mogharbel plant and extent
of improvement of lighting value and lighting level, with a purpose of cutting down the electrical
After this survey, it is found out that numbers of luminous tubes are used with copper counter
balance. It was observed that currently reflectors are detached which results into depletion of
light towards upper limit. For this we will recommend the following things:
In ring frame area use reflector as it will improve lighting level at work area.
With copper ballast energy consumed per year = No. of lights watts 12 365
= 4, 43320
Thus 39% energy is saved after replacing copper ballast with electronics ballast
The electric motors used in mogharbel plant have artificial cooling fans. And few of the motors
are fixed with very heavy metal cooling fan. The metallic fans are heavy and due to corrosion
For large electric motors we will use cooling fans which will replace all such metallic fans by
Fiberglass permanent Plastic fans. Because of which total energy cost will be saved @ 20% of
7. Harmonic Analysis
In the mogharbel plant with the increase in use of non-linear electrical load and also with
computerization in plant, due to harmonic distortion a poor quality issue related to power has
guidelines has been used for the voltage control at the plant and after evaluating present
harmonic contents at Plant premises keeping in mind the Point of Common Coupling (PCC),
which will take counteractive sorting result. Now for harmonic limits which are in excess as
according to the IEEE- 519-1992 guidelines. The main purpose of this harmonic analysis is to
enumerate the distortion in voltage and check the current waveforms occurring in the power
distribution system of this plant. The end result will be very helpful in assessing the remedial
procedures and troubleshooting harmonic distortions problems with ease (IEEE Recommended
Following are the effects that will occur because of Harmonic Analysis
With the introduction harmonic distortion power factor of the whole system will be poor
Due to boost in rms current drawn demand for kVA for the plant will be increased
(IEEE Recommended Practice for Energy Management in Industrial and Commercial Facilities,
2008)
Electrical Energy
13
Audit
With the harmonic spectrum of LT currents in 3-phase electricity distribution system of the
mogharbel plant has been stored with the use of Harmonic and Power Analyzer. And results are
2007)
Figure no 3 Harmonic trends (Electrical energy management for low-voltage clients , 2007)
Electrical Energy
15
Audit
Figure 4 Harmonic disturbances (Electrical energy management for low-voltage clients , 2007)
Electrical Energy
16
Audit
Figure 5 Harmonic distortion (Electrical energy management for low-voltage clients , 2007)
Electrical Energy
17
Audit
Figure 6 Harmonic Alteration (Electrical energy management for low-voltage clients , 2007)
Electrical Energy
18
Audit
Figure 7 Harmonic distortion (Electrical energy management for low-voltage clients , 2007)
Figure 8 Harmonic trend (Electrical energy management for low-voltage clients, 2007)
Electrical Energy
20
Audit
Figure 9 Harmonic Disturbance (Electrical energy management for low-voltage clients, 2007)
(IEEE Recommended Practice for Energy Management in Industrial and Commercial Facilities,
2008)
Electrical Energy
21
Audit
(IEEE Recommended Practice for Energy Management in Industrial and Commercial Facilities,
2008)
With this type result as mentioned in the above table the manner in which plant consumer falls
under the type of short-circuit ratio which will lie in the range of 10<20, and the maximum
allowed THD value for this will be up to 11th harmonics (4 %). With this THD value at the
mogharbel plant is high in comparison to 4%, which is a allowable limit. Now as the measured
THD value is high as compared to permissible limit so, for that reason the mogharbel plant must
set up a harmonic filter which improve the power quality of the plant and that will save the cost
on harmonic discharge.
This will help in reducing the current flow. See the figure below to check out the exact result:
Electrical Energy
22
Audit
And after doing all the process the power optimization will look like this:
Before and after Power Optimization depicts the similar Production level, rate of production and
8. Recommendations
We will recommend that replace the Copper ballast with Electronic ballast. Replace 40Watt/36
Watt tube lights with the 35 Watt tri-phosphor. And 40W /36 watt tube rod has following
features:
With electronic ballast it has service life that is when operated:13,000 hours
Facilities, 2008)
Other Recommendations
By using false ceiling and twofold door system electric energy cost could be saved where
Fiberglass unbreakable Plastic should be used instead of metallic fans to save energy.
Harmonic filter must be installed to improve the power quality of the plant as harmonic
Now the distribution network will look like this as shown below:
Electrical Energy
25
Audit
And when the load files are loaded in the software following result will comes out as shown
below:
9. Conclusion
By performing Energy Audit with above recommendations mogharbel plant can save up to 8
million dollars per year. As electrical energy audit is an efficient device for managing energy
utilization. It will help in reducing the depletion of energy and required conservation steps will
be taken with a cost effective methods. This audit is very vital for Power optimization which will
help in reducing energy consumption of the whole plant by about 10%. With the diminution of
energy wastage, the equipment life will increase and it will increase the power distribution
utilization. And with Power utilization improvement will improve equipment consistency which
will help in saving the cost for plant. (Energy efficiency, 2012)
Electrical Energy
27
Audit
References
http://www.swerea.se/Global/Swerea_SWECAST/Foundrybench/Foundrybench%20D3
%20Common%20analysis%20method.pdf
Energy efficiency,2012,
http://www.msmementor.in/SIDBI_Publications/Energy%20Effiency%20in%20Foundry
%20Sector.pdf
Application of energy audit in buildings and a case study, 1993, H. K. Wong, and C. K.
and Management.
Electrical energy management in small and medium size industries, 1993, P. Z. Yaacoh,
Electrical energy management for low-voltage clients , 2007, Huyck and J. Capple