Вы находитесь на странице: 1из 3

METHOD STATEMENT FOR DEMOLITION WORK FOR CADANGANADANGAN MEMBINA

SEMULA SEBUAH MASJID AL-NASRIAH DUA TINGKAT BESERTA DUA (2) BUAH KUARTERS
BERKEMBAR (KELAS G) SATU TINGKAT DIATAS TANAH KERAJAAN SELUAS 1.532
HEKTAR (3.786 EKAR),MUKIM PEKAN SITIAWAN, DAERAH MANJUNG, PERAK DARUL
RIDZUAN UNTUK JABATAN KERJA RAYA PERAK.

METHOD STATEMENT

FOR

THE DEMOLITION WORK

PREPARED BY:

PERUNDING HJRS SDN. BHD.


No.21 & 21a, Laluan Pinji Seni 4,
Taman Pinji Seni,
Off Jalan Sultan Azlan Shah Selatan,
31650 Ipoh
Perak Darul Ridzuan.
Tel : 05-2435421 Fax: 05-2422489
METHOD STATEMENT FOR DEMOLITION WORK FOR CADANGANADANGAN MEMBINA
SEMULA SEBUAH MASJID AL-NASRIAH DUA TINGKAT BESERTA DUA (2) BUAH KUARTERS
BERKEMBAR (KELAS G) SATU TINGKAT DIATAS TANAH KERAJAAN SELUAS 1.532
HEKTAR (3.786 EKAR),MUKIM PEKAN SITIAWAN, DAERAH MANJUNG, PERAK DARUL
RIDZUAN UNTUK JABATAN KERJA RAYA PERAK.

1. Temporary hoarding as per architect drawing shall be erected prior to commencement


of work

2. Terminate all mechanical services such as water supply and sewerage and cart away any
arising from site. Water tank need to be emptied.

3. Terminate all electrical supply and cart away all wirings and fixtures from site

4. Manually take off all roof tiles and cart away from site

5. Manually take off all purlins, rafter and trusses from site

6. Take off the water tank and cart away from site

7. Remove all ceilings and ceiling support and cart away from site.

8. Remove all loose furniture, kitchens units, worktop, sink, lighting fixtures, fans, air-
conditioners etc. and cart away from site.

9. Remove and dismantle all windows, internal and external doors, grilles, light weight
partitions etc. and cart them away from site.

10. Hack and demolished brick wall staring from upper floors and work toward the lower
floors. All debris and arising shall be cart away from site.

11. Demolish the RC frame one storey at a time and start the demolition work from the roof
level, down using a breaker attached to an excavator. Cart away all debris from site.

12. The following precautions shall be taken during demolition work:-

i) Ensure that the site has been secured safety to prevent unintentional entry by
unauthorised personnel during demolition.

ii) Work from outside the building and never let anyone enter the building while
plant is wrecking the building.

iii) Be sure that the operator has been trained in the work or is being supervised by
experienced supervisor

iv) Make sure that debris does not build up too high as to overload the remaining
structure.

v) Debris designated for removal form site shall be loaded directly into waiting the
lorries
vi) Vehicles leaving the site shall be inspected and wash down before driving onto
the surrounding roads. Road cleaning shall be carefully monitored and clean if it
deemed to be necessary.
vii) If terraces of debris are used to enable the machine to gain height, ensure that
the terraces to well consolidate and the machine can be maintained level during
operation.
viii) Dust emission shall be reduced by spraying water at the building during the
mechanical breaking.
ix) Sheeted protection scaffold shall be erected to minimize dust.
x) Using specialist Pest Control contractor to carry out pest eradication prior to
demolition works.
13. Hack the ground floor slabs and beams and cart away all debris and crusher run from
site.
14. Root out and back all existing stumps and footings or pile caps and cart away all debris
from site.
15. Remove and cart away designated unwanted drains, drainage sumps, sewer line
manhole, inspection chambers and unwanted septic tanks. All debris and arising shall be
carted away from site.
16. The surface drainage at the site during and after demolition work shall be properly
direct to existing drainage system. Hardcode lined drain shall be properly maintained to
direct surface run off to existing road side drain.
17. The working hours shall be as per the regulation stipulated by the Majlis Perbandaran
Manjung. There are from 8.00am to 6.00pm Monday to Friday. No works shall take place
during Saturday, Sunday and all public holiday.
18. Safety precaution and procedure shall be taken as per Occupational Safety and Health
Act and Regulation and also the Factories and Machinery Act 1967 (Act 139),
Regulations & Rules

Вам также может понравиться