Вы находитесь на странице: 1из 10

OTC 4724

North Sea Marginal Fields: The Subsea


Completions Option
by B. Humphrey and S. Cow, Vetco Offshore Ltd.

Copyright 1984 Offshore Technology Conference

This paper was presented at the 16Jh Annual OTC in Houston, Texas, May 7-9, 1984. The material is sUbject to correction by the author. Permission to
copy is restricted to an abstract of not more than 300 words.

ABSTRACT
ELEMENTS OF SINGLE SUBSEA COMPLETION
The paper will identify the basic elements of a subsea
completion and review the types of overall systems A subsea completion system is basically an assembly of
available for the development of a North Sea marginal eight individual sub-systems which can be unitised in
field. A typical field development is reviewed in many forms to suit the development requirements of a
more detail, noting the importance of simple designs particular field. These sub-systems which include
for installation and maintainability and also their own running/testing/handling tools are:-
recognising the possible need for ROV/Diver
intervention. Recent developments and trends are also Support Base
noted, whilst future trends and areas requiring High Pressure Wellhead
further work are identified. The conclusions drawn Tubing Hanger
from the paper are that subsea completions systems Wellhead Connector
will become even more evident in future marginal and Valve Assembly
deepwater offshore oilfield development plans Tree Cap
especially in the North Sea. Flowline
Controls
INTRODUCTION
Support Base (Figure 1)
The last of the large North Sea fields has now been
developed, and the industry is now turning its atten- The support base is designed to carry the combined
tion to the smaller fields that initially did not weight of the conductor and casing strings, the subsea
appear viable. To develop these fields, which can Blow Out Preventer (BOP) equipment during drilling
sometimes contain recoverable reserves of only 20 - 50 operations and also provide guidance for the subsea
million barrels of oil, the 'new' technology of subsea BOP stack and ultimately the production tree assembly.
completions with a low cost topside processing Guidance onto the support base is by means of 4 sur-
facility (F.P.V., T.L.P. or tanker) will probably face tensioned guide wires which are attached to posts
prove to be the only economical system The use of on the support base itself.
subsea completion systems to develop a marginal field
is not without precedent, there is a wealth of opera- It is common to use a standard exploration style
tional experience which has been gained over the last drilling support base (permanent guide base) for wells
decade in the North Sea. which form part of a subsea production system but
which are located singly in remote areas of the field.
A worldwide review of active subsea completions shows A template structure can also be used for field devel-
that there are currently 209 active of which 52 of opment which allows for a more rapid drilling pro-
these completions are in the North Sea. The feasibi- gramme due to the virtual elimination of rig move
lity, reliability and maintenance costs are areas times and the use of batch drilling techniques. There
where research would show that the industry can supply are two main types of template in use, i.e. modular
a good deal of information. and unitised. The modular template is designed to be
assembled on the seabed by installing individual
Before we discuss the overall systems available, let interlocking bases as they are required. The modular
us firstly identify the key elements of a single sub- system lends itself for use on the smaller fields or
sea completion. to early production systems, for example on both Shell
Fulmar and Phillips Tiffany in the North Sea. The
unitised template system is intended for use on larger
Reference and illustrations at end of paper field developments and involves the fabrication of a
structure which can accommodate several wells and
131
2 NORTH SEA MARGINAL FIELDS - THE SUBSEA COMPLETIONS OPTION OTC 4724
associated production pipework, for example Shell UMC allows the connector to function while an AX ring
in the North Sea and Petrobras Bonito offshore Brazil. gasket, carried inside the connector, effects a seal
inside the wellhead.
High Pressure Wellhead (Figure 1)
A series of locking dogs are designed to engage an
The wellhead system design is of primary importance external profile on the wellhead housing and to set up
in the subsea completion system, not only does it the preload required to energise the ring gasket. The
support the casing strings and large subsea BOP stack locking dogs are activated by means of a cam ring
but also the tubing hanger and production tree asse- which is connected to the integral hydraulic system.
mbly.
The top face of the wellhead connector is most
Typically in the North Sea, subsea completions have commonly a 13-5/8" x 5,000 psi studded face per API
used the established two stack system of 21-1/4" x 6BX, onto which the production tree valve assembly is
2,000 MWP and 13-5/8" x 10,000 MWP wellheads mainly mounted.
because of rig availability. However, because of the
need for year round operations, the new harsh environ- Valve Assembly (Figure 3)
ment rigs with their single stack 18-3/4" x 10,000 MWP
systems are now becoming more evident. Due to the The valve assembly is mounted above the wellhead
size and weight of these 18-3/4" subsea BOP stacks and connector and is designed to control and direct the
marine riser systems at least one operator has decided produced hydrocarbons into the flowline system. Seal
to use the more compact 16-3/4" x 10 ,000 ~1WP system on subs in the base of the valve block extend into pock-
the Floating Production Vessel to minimise deck loads ets in the tubing hanger to isolate the flow from the
and reduce handling problems. production tubing and well annulus. A series of fail
safe gate valves in each line are built into the mas-
Tubing Hangers (Figure 2) ter block to control the fluid flow and to allow ver-
tical access through the block during installation and
The tubing hanger system is designed to be run workover operations.
inside the subsea BOP stack and to seal and lockdown
inside the high pressure wellhead assembly. Commonly Options to the basic valve assembly include the addi-
a single tubing string is suspended from the tubing ti on of a "Wye" spool to a11 ow the smooth passage of
hanger in the subsea well with provision in the hanger TFL (Through Flow Line) tool trains for downhole s.er-
for annulus access and the hydraulic control of down- vicing.
hole safety valves. Profiles in the tubing hanger
through bores allow wireline plugs to be installed for Tree Cap (Figure 3)
the safe removal of the BOP stack before installation
of the production tree assembly. In its basic form the tree cap simply acts as a
protective cover for the re-entry mandrel. It is
Two installation methods are currently available to designed to be either mechanically or hydraulically
run and control the tubing hanger system. rhe jnitial operated and to lock onto the outside profile of the
system developed makes use of two different tools to mandrel mounted above the valve assembly. The tree cap
install the hanger, the first to run, lock and seal can be used to provide a back up seal to the upper
the hanger in the wellhead, the second or tieback (swab) valves on the master valve block. Addition-
tool, to allow vertical access through the tubing ally, the cap may form part of the production tree
hanger and into the production tubing string. This control system by housing the necessary control
"Mechani ca1" system therefore requi res at 1east two valves, filters, accumulators, etc. Using the tree
trips from the rig to the wellhead and therefore cap to carry the control equipment eliminates the
should only be considered for use on the smaller sub- requirement for a separate control module and so makes
sea completion systems. the system more compact, simpler and cheaper. There
are however arguements for a separate control module
An "Hydraulic" system has been developed over the past mainly because of the possibility of damage to_the
few years which requires only one trip to install the seal areas in the re-entry mandrel during the more
hanger and tubing string. The running tool is con- frequent make up and removal sequences.
trolled by a six function hydraulic umbilical. To
reduce the installation times to a minimum, a comple- Flowline
tion riser system has been developed for use with the
hydraulic set tubing hanger. Each joint of riser is The flowline system can be broken down into two
furnished complete with tubing strings and control main areas which are, on the tree itself and between
lines which are terminated with stab subs, box up by the tree and the production facility. Flow from the
pin down. The completion riser can also used to valve assembly to the flowline is through a side
install and workover the production tree assembly. mounted gate valve known as the wing valve. The con-
nection between the flowline on the tree and the line
Although the basic hydraulic equipment is more expen- to the production facility can take many forms. The
sive than the mechanical system, the rig time saved by most simple is to use a diver to make up a conven-
the elimination of additional trips has shown this to tional API flange but more sophisticated systems are
be the more economical method on the larger field available using for example an hydraulically operated
developments. vertical stabbing connector or even a fully diverless
pull in and remote make up connection.
Wellhead Connector (Figure 3)
The flowline to the production facility can be either
The wellhead connector is designed to lock and seal a steel or flexible pipe laid from a conventional
the production tree assembly on the high pressure barge or more recently a complex bundle containing
subsea wellhead housing. An integral hydraulic system several lines including hydraulic and electrical con-
132
OTC 4724 B. HUMPHREY, S. COW 3
trol cables. This complex bundle could be fabricated iarisation with equipment and operating procedures
onshore and then towed out as a finished length to the will be invaluable when the main effort of developing
field before controlled deballasting to the seabed. the field is undertaken at a later date.
Controls An ideal example of this type of arrangement is found
Shell/Esso's UMC development where a satellite tree
There are three basic types of control system in (PI) was installed in summer 1980 and production com-
use on subsea completion systems at present, i.e. menced in January 1981, approximately 16 months prior
direct hydraulic, electrohydraulic, multiplexed to the installation of the UMC, this enabled early
electrohydraulic. production of some 7,000 bid via dual 75mm flowlines
to the South Cormorant 'A' Platform. This single
The use of a direct hydraulic control system is satellite incorporated some of the elements of the
limited to the less complex completions because of the overall system, and its performance which gave 95%
need for individual control lines from the control reliability gave a good indicator for the remainder of
station on the production facility to each operator on the project.
the subsea system. The long distances between the
trees and the control station result in extended The surface processing facility which is used in a
response times and slow closing of the tree valves production system can take several forms, a semi-
which can result in excessive wear around the face submersible being used as a F.P.V. is quite common.
sealing areas. The size of the control umbilical and On smaller developments the F.P.V. is normally a con-
control panels also limit the use of direct hydraulic verted semi-submersible drilling vessel as opposed to
controls because of the restricted space usually a 'custom built' production vessel. A ship shaped
available on offshore facilities. vessel or converted tanker can also be used depending
on the particular environmental conditions antici-
Electrohydraulic control systems require the use of a pated.
control module on the production tree itself. The
module is designed to contain a series of solenoid A single subsea completed well can stand alone as a
valves which direct hydraulic fluid to the selected viable subsea production system, in this case a single
operators on the tree. The response times are greatly anchor leg system may be installed with a permanently
improved using this method because the solenoid valves stationed tanker, (this type of system was used on the
allow the fluid in the operator line to dump outside Castellon and Tazerka fields). A custom built vessel
the module when deactivated. A single hydraulic with moonpool, riser system and dynamic positioning
supply line and multi-core electrical cable are capability is also proposed by B.P. in their Single
required between the tree and the control station. Well Oil Production System (S.W.O.P.S.) for the
exploitation of marginal fields in the U.K. sector of
For the more complex subsea completion systems, the North Sea. A conventional F.P.V. may also be
involving template and satellite trees, manifolds, justified where larger fields and higher production
sensors, etc., then a fully multiplexed rates are involved.
electrohydraulic system must be used. Closing
response times for the various operators are in line Template System
with those of the electrohydraulic system. However,
the shear volume of information which must be handled To develop satellite fields or cover extensions of
at any given time along with the much_ reduced size_of existing fields, a template system can be used. The
cables, panels etc. make the multiplexed system the template would have slots for drilling the subsea
only feasible solution in most cases. wells and also serves to house wellhead assemblies and
template production trees. Provision for manifolds,
TYPES OF SUBSEA COMPLETION SYSTEMS production riser and porches for connection of sate-
llite production flowlines can also be provided. A
The requirement for a subsea completion can arise for detailed description of a typical template system is
several reasons, the main ones being: provided later in the text.
Early production system. The template is normally a 'unitised' construction of
Coverage of remote areas and extensions of fields. tubular members, but development and appraisal wells
Development of satellite fields. can be used as the basis for a template system by
Deep water developments. utilising a 'modular guidebase ' approach during the
drilling phase, as previously described.
Single Satellite Wells
And Early Production System (Figure 4) The production from a template system can be handled
by a conventional platform or a floating production
Single satellite wells can be used as part of a vessel for surface processing with an export line to
template system to deplete the extremities of a reser- either an offloading buoy or existing pipeline.
voir or alternatively to inject and increase produc-
tion from the template wells. As previously stated satellite trees can also be used
in conjunction with the template system.
Single satellite wells can also be used for early
production. A single well in a development can pro- 'Cluster' Wells
duce to either an adjacent platform or a floating
production vessel. This can take place whilst the A variation on the use of a single large template
permanent platform or installation is under construc- and several satellite completions is the use of small
tion. This type of system can have a dual advantage satellite templates containing two or more subsea
in that the field will be producing earlier and there- production trees. These are likely to become a common
fore give a quicker return on investment, also famil- system in fields where a large reservoir area exists
133
4 NORTH SEA MARGINAL FIELDS - THE SUBSEA COMPLETIONS OPTION OTC 4724

with the oil or gas at a shallow depth below the sea- cally over pins mounted vertically on the template
bed, which restricts the use of deviated drilling structure as the tree connector lands on the high
techniques. This type of system will become increas- pressure wellhead housing. These vertical stabs allow
ingly popular in the North Sea, particularly the Nor- connection of the template piping and controls to the
wegian Sector, and is a possible development method tree. A horizontal diverless flowline pull in and
for the Troll (31/2), Sleipner and Oseberg fields. connection can be used to connect both ends of the
flowline bundle between the satellite trees and the
DESCRIPTION OF ATYPICAL FIELD DEVELOPMENT (Figure 5) template. It would be possible to tie in one or two
of the satellite wells to the template and allow for
The system discussed here represents a typical layout some Early Production while the remainder of the tem-
of the subsea completion equipment required to develop plate and satellite wells were being drilled. This
a marginal field in the North Sea. A series of sate- Early Production could be handled by the semi-
llite production/injection wells are tied back to a submersible being used to drill the template wells
large unitised template by individual flowline bundles while a second rig drilled the satellites.
tihichhave been pulled in and connected by remote
diverless techniques to the manifold pipework on the Once the additional wells have been drilled and the
template. completion equipment installed, production, injection
and sales manifolds can be installed on the template
The majority of the production trees in the field are to control the flow of fluids between the wells and
located on the large template itself. This system has the production facility. The manifolds can also be
several advantages over the single tree approach to used to control the flow of injection water or gas to
field development. Drilling, installation and the desired wells in the field using a series of gate
#orkover operations can be performed much more quickly valves and chokes. Additionally, by-pass and cross-
by minimizing rig movements between wells. Performing over lines in the manifold plumbing should also be
the same operation repeatedly on adjacent wells also included. This would give a more flexible system
reduces setting up and tear down times dramatically. which could allow, for example gas lifting on several
The subsea template allows the use of fixed pipework wells later in the life of the field without major
to connectthe many trees, including satellites to a subsea work on the template pipework. The pipework
riser or manifold system and so simplifies the pattern itself should be designed with a suitable corrosion
of flowlines and control umbilicals on the seabed. and erosion factor built in to give an extended ser-
vice life and so reduce the production downtime neces-
lue to the number of wells required in the field, 3 sary during maintenance work.
subsea manifolds have been included on the template to
reduce the number of lines in the riser system. On The control system required by a multiwell subsea
the system shown there are 16 trees, 8 on the template template and its manifolds is one of the most complex
~nd 8 satellites which could include production, water required by the industry at present. This is due to
injection and gas lift designs. Approximately 32 the large number of control functions and long separ-
riser lines from the template would have to be handled ation distances between the template and its satellite
On the production facility without the use of the wells. A multiplexed electrohydraulic system would
subsea manifolds, not to mention sales risers or appear to be the optimum solution but should be
Hydraulics and electrical cables for control func- designed in such a manner as to minimise the effect of
tions. Clearly a reduction in the number of risers each control function failure on the overall field
tiouldbe an advantage not only for handling but safety production performance. The control system should
reasons too. The template can also accommodate up to also be designed with the following features in mind:-
3 additional wells which could be drilled later by a
standard semi-submersible drilling vessel or even the Maximise retrievability of subsea components
production facility itself depending on the water Maximise redundancy of critical functions
depth, production and sales riser designs and the size Maximise operational flexibility
of vessel in question. Minimise subsea hydraulic and electrical connec-
tions
The template is designed to handle a total of 24 wells Protection for subsea umbilicals during install-
including 8 satellites with pull in flowline bundles, ation and service
3 levelling piles, 3 subsea manifolds, 3 multiplexed Protection for riser umbilicals.
electrohydraulic control modules, 2 sales lines and
work platforms for ADS (Atmospheric Diving Systems) or WORKOVER REQUIREMENTS
diver intervention. To reduce the overall size of the
template, a system has been developed which allows the During the life of the field it will inevitably be
levelling pile bays to be drilled through later and necessary to perform some degree of maintenance work
accorunodatea production tree. Using a hydraulic on the subsea equipment and even in the wells them-
levelling system has proved successful on several selves at some point to maximise the field depletion
large templates, for example Amoco North West Hutton progrannne.
in the North Sea and Petrobras Bonito offshore Brazil.
Final inclinations of less than 1/2 have been Downhole work may be required for several reasons
achieved on these structures. The well slots on the including removal of paraffin wax build up in the
template are shown complete with 4 posts for guidance tubing, replacement of SCSSV (Surface Controlled Sub-
of the subsea BOP stack and production trees. These surface Safety Valve) due to wear on the sealing ele-
posts can be replaced if damaged, by diver or remote ments and even setting plugs downhole and in the tub-
operation. ing hanger to allow safe removal of the production/
injection tree itself. Recovery of the tree may be
The production trees on the template are less complex required to allow replacement of the completion tubing
than the satellites in that they use a series of pro- string because of wear, leakage or even to convert the
duction and control connectors which stab automati- well from a production to an injection mode. During

134
OTC 4724 B. HUMPHREY, S. COW
5
the installation of the tubing and production tree, o~ment svstems mav .iustifythe use of their own pur-
vertical access must be provided through the assembly pose bui~t RMV (R~m;te Maintenance Vehicle) as for
for conventional wireline equipment. However, for example on the Shell/Esso UMC in the North Sea. Tasks
maintenance of the downhole equipment during service which can be performed routinely on the subsea equip-
it may be possible to use a second technique known as ment include cleaning and inspection, replacement of
TFL (Through Flow Line) to carry out many of the nece- damaged or worn equipment such as chokes, gate valve
ssary tasks more economically than by conventional assemblies or operators, pipe work, control modules
wireline. and monitoring equipment.

Basically a TFL system uses an assembly of tools known The layout of the subsea equipment is of great impor-
as a tool train, which can be pumped through a tance for the subsequent workover operations as indeed
flowline between the processing facility and the pro- is the identification system used to differentiate
duction tree. A large radius bend in the flowline on between the various trees and pipework sections. To
the tree directs the TFL tool train from the seabed or increase the overall efficiency of the subsea comple-
template pipeline into the vertical well bore. The tions system as a whole, it is recommended that all
entry point on the tree is known as the Wye spool assemblies are jig built to maximise their inter-
and is designed to allow for both TFL and vertical changeability and that the minimum number of different
wireline access. Once the tool train has completed types and sizes of pipe, tubing, gaskets, studs, nuts,
its downhole task it is then pumped back up out of the hydraulic fittings, etc. are used subsea to minimise
tubing and along the flowline by means of a second the variety of spares required to service the equip-
subsea flowline, tubing string and crossover joint or ment. To reduce the time spent subsea by the diverl
H member in the well. The major advantage of a TFL ROV on a particular task, a detailed training pro-
system over conventional wireline is that there is no gramme which includes onshore hands on exposure to
Iced for the intervention of a workover vessel which the equipment, tools and procedures to be used cannot
nay be the subject of considerable downtime due to bad be over emphasised.
tieather. To increase the efficiency of the TFL system
it may be possible to use a tool storage and selector RECENT DEVELOPMENTS AND FUTURE TRENDS
nechanism built into the subsea template which could
~llow work on more than one well at a time. However, The gap between the ability to drill in deepwater and
iue to the need for twin tubing strings, Wye spools, the technology t.oproduce in these depths is ever
jual flowlines and a pumping/launching station, the widening. The present drilling depth record is arounc
:osts of installing such a system are considerable. 6,400 ft whereas production by conventional means
(i.e. platforms) is approximately 1,000 ft. The sub-
Iireline tools are most connnonlyrun from a semi- sea completion option is standing somewhat less than
;ubmersible drilling vessel but depending on riser 900 ft.
~esigns and water depth, wireline could also be used
Iy a Floating Production Vessel on its template wells It is evident from the above that there exists an
it least. An additional option for vessel selection effective driving force and incentive to develop
lre the new purpose built workover vessels currently effective subsea production systems which will have a
mder construction in the U.K. spin-off effect when it comes to developing marginal
fields.
}efore starting wireline operations the tree cap must
je removed from the top of the tree to expose the The development effort on subsea production equipment
e-entry mandrel onto which an hydraulically operated can therefore be broadly divided into two sections:-
;OO1 locks and seals. A riser system is run with the
Hydraulically operated tool to give access to the (i) The development of existing equipment to suit
lertical bores in the tree and into the completion higher technological standards or development
;ubing. The riser is also required to contain any based on field experience.
)ore pressure fluctuations which may be encountered
luring the workover. The design of the riser can take (ii) The preparation of subsea production equipment
Iany forms depending on the completion tubing and for deepwater production.
~roduction tree designs and must also take into con-
sideration the anticipated environmental operating Before discussing these developments, let us firstly
:onditions. Examples of workover risers include review how subsea production equipment initially
evolved. The technology used was a compromise betweel
- fully integrated completion style surface production trees and the subsea drilling tech,
scaled down marine drilling riser nology available at that time. This type of approach
- steel tubing was consistent with the Oil Companies policy of a
- flexible hose. step by step approach with project involving subsea
production, where new technology is built upon a
he riser selected must be kept in tension by the proven technique thus limiting the risk factor. It
~orkover vessel to reduce the effe-ctsof the environ- is only recently that subsea production equipment has
mental loading conditions and also be outfitted with a been radically reviewed, working through the elements
erminal head valve assembly, wireline BOP and lubri- of the system identified earlier we can review these
ator head to allow control of the bore fluids and recent development.
ressures in addition to the safe installation and
emoval of the wireline tools and equipment. Work on
he trees, manifolds, etc. can be by saturation diver,
,DS (Atmospheric Diving System) or ROV (Remote Oper-
ted Vehicle) techniques deployed from either the
reduction
facility
itselfor a diving/workover
sup-
~ort vessel. However, the more complex subsea devel-

1
6 NORTH SEA MARGINAL FIELDS - THF SIIRSFA(7(IMPIFTTIIN< l_lDTTON
---- ------- -. .L -.-! ., .- , , ., ,
nT1-
Ulb
A77A
-t[L*

Wellhead Connector tool (T.H.R.T.) and a retractable key or pin located


on the inside diameter of the Blowout Preventer stack
The design criteria used for a production tree (BOP) to correctly orient the tubing hanger.
:onnector is quite different from that used on a sub-
;ea drilling system, in that the operational life is An alternative method makes use of a spring loaded key
nuch longer and the loading conditions are greatly in the T.H.R.T that locates in a slot in the BOP well-
educed. With this in mind, a new generation of well- head connector upper body. With this method the
lead connectors is evolving to address the production locating of the key is achieved mainly by the moni-
tree market. toring of torque build up when rotating the T.H.R.T.
It is therefore a requirement that a thrust bearing of
Mechanical Connector some description is used to increase the sensitivity
of the system.
This type of connector makes use of the conven-
tional dog segments and cam ring design, however, it The anti-rotation mechanism is generally a form of
is remotely actuated by a series of rods which extend friction grip between the tubing hanger outside
through the connector upper body and make up to a diameter and its landing bowl.
?eavy actuator ring. Two heavy duty rods, connected
to the top face of the actuator ring are stroked up Tubing hangers and tools are under constant review to
~nd down to unlock/lock the connector mechanism. The optimise running procedure, rig times and efficiency,
rods are stroked by means of hydraulic cylinders and although a non-orienting type of tubing hanger is
nounted on the tree running tool (T.R.T.) which available it does not offer the facility of access to
:onnects to the tree re-entry profile on top of the the annulus between the production casing and tubing
ialve assembly. This means that all hydraulic fit- that may be a requirement if gas lifting is antici-
tings, seals, etc. are mounted on the T.R.T. and can pated.
therefore be retrieved to surface making them easily
maintainable and less likely to fail since they are The hydraulic system referred to earlier in the text,
lot subjected to long term service subsea. In some is the system that is currently undergoing further
cases long term service can be i.nthe region of 20 developments, this system will be required to cover
to 25 years. deepwater subsea production in the near future.

Medium Duty Connector (MD-H4) Hydraulic Cleanliness and Equipment Design

A further option which addresses the ability to As the subsea systems become more complex, so the
reduce the load carrying capacity and therefore opti- choice of a multiplex system is becoming more common.
nise the design is the medium duty connector (MD-H4) The solenoid valves used in this type of system
~hich uses windows in the main body to house the dog requires that the control fluid is of a high degree of
segments. cleanliness.

Although this connector is not suitable for the Because of this requirement, there is a knock-on
fatigue loadings that are involved with the drilling effect relative to the design of the subsea equipment,
operation, its design is well suited for Subsea Tree consideration must be given to the hydraulic equipment
Operations. both for the ease of assembly, and effective flushing
of equipment to reach to cleanliness standard require-
dith this arrangement the hydraulic section of the ment. Designs of connections for control lines now
connector remains subsea, but the connector has the have to include check valve arrangements to prevent
facility for manual override in the event of an the ingression of seawater which would contaminate the
hydraulics failure. control system.
Valve Assembly Developments
Future Trends
The seal on the valves for subsea use is now of
necessity a metal to metal seal, this is of particular Future trends and developments will be dictated
importance on high production gas fields. mainlyby the requirements to produce subsea in deep-
water. There will be an increasing reliability on ROV
The master valve block designs have taken on a more intervention and increasing consideration given to the
unitised construction with the re-entry mandrel and layout and design of systems to allow operations to be
wellhead connector upper body becoming integral with effectively carried out subsea.
the block. Although this means a longer M.V.B. and a
more complex component, the advantages of a reduction Because of the depth of water and tripping time
in leak paths and a reduction in the overall height of involved it will not be possible to retrieve the tree
the tree offset the disadvantages. in the event of a valve failure. It will therefore be
a requirement to perhaps change out valve actuators
Tubing Hanger subsea. This will require the actuators to be of a
unitised construction with a quick release connection
From the early days of subsea production, one of from the M.V.B. whilst still maintaining a metal to
the main problem areas has been the orientation of the metal seal feature throughout.
tubing hanger. Field experience has now evolved sev-
eral workable solutions. At present all subsea production trees are installed
using a conventional guideline system. Obviously for
The problem lies in having the ability to initially deepwater applications guidance system akin to present
orient the hanger, but also having the capability to deepwater BOP stack guidance system will have to be
lock the hanger in position when correctly oriented. developed.
One method uses a cam on the tubing hanger running
4Oc
I Go
OTC 4724 B. HUMPHREY, S. COW
CONCLUSIONS REFERENCES

The subsea completion option will play an increasing 1. Booth D. : Subsea 1983, Resource Publications Inc.,
role in the development of marginal fields both in the Houston (1983) 100 - 123
North Sea and worldwide. The advancement of design
and operational procedures will be made by the 2. Cottrill A. : UMCs Unique Flexibility Stretches
requirement to produce from deepwater and the need to Subsea Technology, Offshore Engineer (December
produce economically from existing marginal fields. 1981) 37 -45
There already exists a good knowledge of subsea pro-
duction experience that needs to be consolidated and 3. Reimert L.E., Gray D.J., Machado Z.L. : ATen Well
advanced. The option of early production and thus Subsea Production System For The Enchova Field,
early return on investment using the subsea comple- Offshore Technology Conference, Paper 3448 (1979)
tions system is an attractive consideration. 781 - 786

4. West N.J. : The Potential Role of Subsea Comple-


tion Technology in The Development of Norwegian
Block 31/2, Underwater Technology -.82, Bergen,
Norway, (April 1982) 51 -64

Fig. 118Wn. 10,000-psi W.P. wellheadsystem.


---
1s(
I
f

TREE CAP

/- COMPL E TIO14 RISER

-i
TREE MANIFOLD 7

L.=
I 2 AN NLILUS

a
f? I

i!
I
STAB SUB

VALVE BLOCK

- HYORAULIC SET @ -
TuBING HANGER &-

I
RuNNING TOOL

ANODE

----- HYDRAULIC SET


TuBING HANGER
I
m-+
i-


1
- - -Y I I FLOW LINE
I
2
EXTENSION SUB
G
RETAINER

L-
E FRAME
- CASING HAMGERS
/

- WELL HEAD HOUSING HYDRAULIC


3- FLO
STAB PLATE
CONNE

I
I
CONNECTOR

H-4 CONNECTOR

r
r >
l-
?

~ Fig. 2The tubing hanger. Fig. STree unitization.


WORKOVER RISER WITH c
=___ TREE # TUBING HANGER ~ QUIm DISCONNECT
RW$NING ~ TE= EQUIPMENT

FLEXIBLE FLOWLINE a
COfUTROL UMEULICALS. ~ 3 SATELLITE TREE
ASSEMBLIES.

Fig. 4Typical earlyproductionsystem.


\

Вам также может понравиться