2- Which of the following processes are used to create a Project Schedule Network Diagram?
A*Sequence Activities
B*Develop Schedule
C*Create WBS
3- You are managing a construction project. You are currently estimating the duration of a very
critical activity. You have gathered the following information from the experts:
A*1.25 days
B*1.5 days
C*1 day
B*(Pessimistic - Optimistic) / 6
A*Business Case
C*Project Schedule
A*Feeding Buffer
B*Activity Buffer
C*Critical Buffer
D*Schedule Buffer
7- The following table contains information about the durations in days and predecessor activities
on a project schedule. Which of the following would be true if you increased the duration of
Activity C from '1' to '5' and decreased the duration of Activity D from '5' to '2'?
8- The first Gantt chart in the following graphic displays the schedule for a telecom site
construction project. According to the original plan, the first two activities (Select Site and
Negotiate Lease) should have been 100% completed and the third activity (Perform Civil Works)
should have been 50% completed. However, only the first two activities have actually been
completed, and no work has been performed on the third activity.
Today is 9/13/11. The project manager recalculates the schedule and this pushes the third activity
from its scheduled start date 8/29/11, to the current date 9/13/11. Because this would have made
the project late, the project manager then adds a 15 day lead time to the fourth activity to bring
the project back on schedule.
What technique has the project manager performed by adding this lead?
(Top graphic = original schedule. Bottom graphic = schedule after the changes. Effects of the
change are highlighted).
A*Resource Leveling
C*Crashing
D*Fast Tracking
9- Marilyn is managing a project to create a new mobile device application being developed for a
global insurance provider. Because Marilyn's project is behind schedule, she is using a scheduling
tool to try different techniques to help get the project back on schedule. Marilyn first adjusts some
leads and lags in order to minimize any slack on the project. She then tries to fast track the project.
As a result, the project is aligned with the current time constraint. However, when Marilyn uses
the "Level Resources" feature, the project finish date again goes past the time constraint. What
should Marilyn do next to resolve this dilemma?
A*Marilyn must make sure that she did not make a mistake when using the "Level Resources"
feature
B*Marilyn must not use the "Level Resources" feature after fast tracking the project
C*Marilyn must undo those adjustments she made to the leads and lags
D*Marilyn must examine the critical path and see how crashing affects the project
A*Mandatory Dependencies
B*External Dependencies
C*Discretionary Dependencies
D*Internal Dependencies
11- The first Gantt chart in the following graphic displays the schedule for a telecom site
construction project. It contains seven activities and a hammock activity. The chart also displays
various activity metrics. According to the original plan, the first two activities should have been
completed and 50% of the work on the third activity, Perform Civil Works, should also have been
completed. However, only the first two activities have actually been completed and due to
unforeseen circumstances, no work has been performed on the third activity.
To handle this schedule variance, the project manager decides to fast track some of the project
activities. Which of the following is the negative effect of fast tracking as displayed in the second
graphic? (Same graph in question 8)
A*Change in scope
C*Increased budget
A*Discretionary dependencies
B*External dependencies
C*Mandatory dependencies
D*Internal dependencies
13- Which of the following is not a tool or technique of the Define Activities process?
A*Decomposition
B*Analogous Estimating
D*Expert Judgment
14- Which of the following statements is true regarding Activity Duration Estimates?
A*Depreciation
B*Simulation
C*Purchase Order
D*Appraisals
16- Activity attributes can be used to identify all of the following for an activity except?
17- Which of the following is an output of the Estimate Activity Durations process?
A*Milestone List
C*Activity Attributes
18- Which of the following will not have an effect on the duration of an activity?
C*Resource Calendars
A*Detailed schedule
B*Master schedule
C*Summary schedule
D*Top-down schedule
20- Louise is managing a software development project. Louise's project is behind schedule and
the project's SPI is 0.75. What should Louise do during the Control Schedule process?
A*Make sure that everyone in her company knows that her project is lagging behind schedule
21- Which of the following is a tool or technique of the Control Schedule process?
B*Performance Reviews
D*Checklist Analysis
22- Which of the following is not an output of the Define Activities process?
A*Activity List
B*Milestone List
C*Activity Attributes
D*Scope Baseline
23- You recently estimated both the activity resources and activity durations for your project, and
you now want to create the Schedule Baseline. Which of the following processes will you perform
to create the Schedule Baseline?
A*Control Costs
B*Control Schedule
C*Develop Schedule
24- Which of the following terms is used to describe the amount of time that a schedule activity
can be delayed or extended from its early start date without delaying the project finish date or
violating a schedule constraint?
A*Free Float
B*Project Float
C*Total Float
D*Activity Float
25- You are managing a software development project. You are in the process of analyzing the
activity sequences, durations, resource requirements, and schedule constraints to create a project
schedule. What project process are you performing?
A*Develop Schedule
D*Sequence Activities
26- The process of monitoring the status of the project in order to update project progress and
manage changes to the Schedule Baseline is called?
A*Develop Schedule
B*Define Activities
C*Manage Baseline
D*Control Schedule
27- A project manager should use Contingency Reserves to support known risks. Which of the
following documents provides the details for scheduling contingency reserves on a project?
A*Schedule Data
B*Milestone Chart
C*Schedule Baseline
28- The Estimating Activity Durations does not use information from which of the following?
A*Risk Register
B*Work Packages
C*Resource Calendars
29- You are managing a software development project and are in the process of acquiring your
project team. Some of the consultants you hired are available only for a few days during the
project. You need to prepare a schedule based on limited resources. Which of the following tools
should you use in this situation?
A*Resource Leveling
D*What-if Analysis
30- You have been managing a storage yard construction project. While planning, you define
activities for the project and sort all these activities according to common characteristics to
determine the most appropriate project resources to execute the tasks. Which of the following
would be most useful in accomplishing this grouping?
B*Activity Attributes
C*Buffers
D*Total Float
31- Periodically on your project you may encounter instances where the project work expands to
fill the time available for its completion. What is this principle called?
D*Parkinson's Law
32- Ashley is managing a year-long project to create a new mobile application for a Sleep Apnea
breathing device. Her project team has developed a prototype for the application and Ashley is
currently using modeling techniques and resource optimization techniques in order to develop
work performance information to compare the work performed so far against the project
schedule. Which of the following processes is Ashley currently performing?
A*Control Schedule
C*Develop Schedule
33- Which of the following is an input to the Estimate Activity Durations process?
B*Project Schedule
D*Milestone List
A*Three-Point Estimating
B*Parametric Estimating
C*Top-Down Estimating
D*Bottom-Up Estimating
* Activity List
* Activity Attributes
C*Resource Calendars
D*Milestone List
36- As a project manager, which of the following processes should you use to update the activity
duration estimates and completed activities caused by approved change requests?
A*Develop Schedule
C*Control Schedule
D*Sequence Activities
37- The Define Activities process has three tools and techniques, including:
* Decomposition
* Expert Judgment
Which of the following tools and techniques is missing from the list?
B*Alternatives Analysis
C*Procurement Audit
38- Following is an illustration of a project network activity node that includes some information
about Activity D. Assuming that you are starting work on Day 1 (not Day 0) and given the
information provided, what is the Late Start of Activity D?
A*36
B*37
C*38
D*39
39- When is the Schedule Management Plan developed in a project?
40- You have just discovered that two of your critical tasks are going to have a one-day delay. This
requires immediate action to prevent the schedule finish date from slipping. Which of the
following processes should you use to initiate a corrective action to retain the original schedule
finish date?
A*Sequence Activities
B*Control Schedule
D*Develop Schedule
41- Which estimating technique is a quantitatively based estimating method that multiplies the
quantity of work by the rate?
A*Three-point estimating
B*Analogous estimating
C*Bottom-up estimating
D*Parametric estimating
42- Which of the following is not an output of the Develop Schedule process?
A*Schedule Baseline
B*Schedule Data
C*Activity Attributes
43- Following is an illustration of a project network activity node that includes some information
about Activity D. Assuming that you are starting work on Day 1 (not Day 0) and given the
information provided, what is the Duration of Activity D?
A*5
B*4
C*3
D*2
45- The performance baseline on a project includes schedule, scope and cost baselines. Which of
the following project processes is used to create a schedule baseline?
B*Control Schedule
C*Develop Schedule
D*Define Activities
* Project Schedule
* Schedule Baseline
* Project Calendars
C*Schedule Data
Today is 9/13/11. The project manager recalculates the schedule and this pushes the third activity
from its scheduled start date of 8/29/11, to the current date 9/13/11. The calculation also affects
all the subsequent activities and pushes the project beyond the completion deadline. The project
manager then adds a few new resources to the third activity so that it now finishes on time. This
brings the project back on track. What technique has the project manager performed for this
activity?
(The original schedule, the first Gantt chart, and the schedule after the changes, the second Gantt
chart, are both shown in the graphic. The effects of the change are also highlighted.)
A*Crashing
B*Resource Leveling
C*Fast Tracking
48- For duration estimates that include contingency reserves, which of the following is not true?
49- You are working on a construction project and you are anticipating scheduling problems in
two months, which may affect activity durations. You are using Monte Carlo Analysis to simulate
the possible outcomes of various situations in terms of your schedule. Monte Carlo Analysis is an
example of which of the following?
A*Modeling Technique
B*How-Why Diagram
C*Brainstorming Technique
D*Ishikawa Diagram
50- Rose has recently reported that her project's SPI is 1.01. However, an independent detailed
investigation reported that the project's SV is $1 million. Assuming that the independent review
was accurate, what can be concluded about Rose's honesty by looking at these metrics?
D*Though Rose did not lie, her computed SPI is not correct
C*A Dependency that involves a relationship between project and non-project activities
52- Which of the following is a major difference between decomposition in the context of the
Define Activities process as compared to decomposition in the context of the Create WBS
process?
A*The final output of the Define Activities process using decomposition is defined as Work
Packages and the final output of the Create WBS process using decomposition is defined as
Deliverables
B*The final output of the Define Activities process using decomposition is defined as Activities
and the final output of the Create WBS process using decomposition is defined as Control
Accounts
C*The final output of the Define Activities process using decomposition is defined as Deliverables
and the final output of the Create WBS process using decomposition is defined as Activities
D*The final output of the Define Activities process using decomposition is defined as Activities
and the final output of the Create WBS process using decomposition is defined as Work Packages
A*Pareto Chart
B*Control Chart
C*Reserve Analysis
D*Scheduling Software Tool
54- The following table contains information about the durations in days and predecessor
activities on a project schedule. What is the duration of the critical path?
A*10 Days
B*11 Days
C*17 Days
D*18 Days
55- You are managing a bridge construction project. You have just finished defining your activities
and you have created a network diagram. You have also assigned resources to each activity and
estimated activity durations. What should you do next?
D*Develop Schedule
56- In your project meeting, one of your key resources has started arguing with another team
member over the project schedule indicating that there have been changes made to
accommodate new contractors. Which of the following processes could be used to verify your
team member's argument?
A*Sequence Activities
C*Develop Schedule
D*Control Schedule
57- Which of the following is an output of the Develop Schedule process?
B*Schedule Data
A*CPM
B*Critical Chain
C*MS Project
D*Resource Leveling
59- Your project has many tasks to complete and some resources have been over-allocated. What
do you do?
60- Rachel is about to present her project's current schedule during the board meeting. Just
before the meeting, she opens up her scheduling tool to review her project schedule because she
has realized that some of her resources have been over allocated between two projects. After
applying the resource leveling feature, Rachel finds out that her project's critical path has
changed. The change upsets Rachel as she was not prepared to present this critical path change
during the board meeting. What is Rachel's best option during the board meeting?
A*Undo the change to remove the resource leveling from her schedule
B*Present the original critical path to the board during the meeting
C*Present the original critical path during the meeting and then "accidentally" hit the resource
leveling feature
D*Present the changed critical path along with the reason for the change
61- After creating a project schedule, the project manager could use the Control Schedule process
for all of the following activities except?
62- The Sequence Activities process has three tools and techniques, including:
* Dependency Determination
Which of the following tools and techniques is missing from the list?
A*Expert Judgment
63- Which of the following is an output of the Estimate Activity Resources process?
A*Activity Attributes
C*Scope Baseline
B*Performance Reports
D*Schedule Data
65- Which of the following processes use Earned Value Analysis as an important tool in project
performance evaluation?
A*Control Procurements
B*Control Schedule
66- While running a mobile phone project, Cindy hires some consultants for her project who will
be working only on a short-term basis. She will likely perform Resource Leveling to keep the
consultants' usage at a constant level during project execution. In this scenario, which of the
following statements about Resource Leveling is true?
67- You are managing a project to construct a covered court for a town community, and you are
currently developing the project schedule. The court will have a roof that will be supported by
two walls. The plans also include a third wall that is purely aesthetic and non-supporting. You have
the following schedule activities to manage: clearing the site, pouring the concrete, building the
walls and installing the roof. You determine that you need to compress the project schedule in
order for the court to be completely built by the town's Founding Day. All of the following are
viable schedule compression options except?
D*Using a fast drying concrete, allowing the team to start building the wall sooner.
68- Following is an illustration of a project network activity node that includes some information
about Activity D. Given the information provided, what is the Total Float of Activity D?
A*12
B*14
C*16
D*18
69- You are planning to use a lot of tools such as hammers, hand saws, screw drivers etc. in a year-
long construction project and you want to track their availability by adding them as resources.
However, you decide to use only hand tools instead of automated tools to help save some money.
Which of the following processes would you use to estimate the type and quantity of such
resources?
A*Identify Activities
D*Develop Schedule
70- Which of the following is not an input to the Estimate Activity Durations process?
A*Activity Attributes
71- Which of the following techniques is used to subdivide the project work packages into smaller,
more manageable components called activities?
B*Decomposition
C*Progressive Elaboration
D*Gold Plating
72- Which of the following is used to assess and measure the magnitude of variation of a Project
Schedule from the original baseline?
B*Buffers
74- A key stakeholder on Diana's project requests information about the planned finish date and
milestone dates. Which of the following documents will provide Diana with the most accurate
information about the planned finish date and milestone dates for her project?
A*Project Charter
B*Activity List
D*Project Schedule
75- You are running a research project. Your team has developed a project schedule and
calculated theoretical early start, early finish, late start and late finish dates for all activities using
the Critical Path Method (CPM). In this context, which of the following statements is correct?
A*This schedule becomes the final schedule since the critical path method was used to develop it
B*Resource limitations are already taken into account when using the critical path method
C*The critical chain method should be performed immediately after performing the critical path
method
D*On any network path the schedule flexibility is measured by the amount of total float
76- The following table contains information about the durations in days and predecessor
activities on a project schedule. What is the Free Float of Activity C?
A*0 Days
B*2 Days
C*7 Days
D*14 Days
77- Which of the following techniques would use parameters from previous projects to estimate
durations?
A*Reserve Analysis
B*Delphi Technique
D*Analogous Estimating
78- Which of the following contains a list of all schedule tasks in a project?
A*Schedule Baseline
B*WBS Dictionary
C*Activity List
D*Activity Attributes
79- Which of the following is a tool or technique of the Sequence Activities process?
A*Activity Attributes
C*Expert Judgment
D*Decomposition
* Activity List
* Risk Register
* Activity Attributes
* Resource Calendars
A*Stakeholder Register
C*Quality Metrics
D*Issue Log
81- The Estimate Activity Durations process has six tools and techniques, including:
* Expert Judgment
* Parametric Estimating
* Reserve Analysis
* Three-Point Estimating
Which of the following tools and techniques is missing from the list?
B*Cost Aggregation
C*Schedule Compression
D*Analogous Estimating
82- Which of the following refers to the inclusion of non-work schedule activities to help manage
project uncertainties?
A*Duration Buffers
B*Duration Float
C*Duration Reserves
D*Duration Slack
83- Kim, working as a project manager for a drug manufacturing project, wants to perform
schedule network analysis using different scenarios to assess the feasibility of the project
schedule under adverse conditions. Which of the following techniques is used in the Develop
Schedule process to perform this analysis?
B*Alternatives Analysis
D*Variance Analysis
85- Which of the following is not a tool or technique of the Estimate Activity Resources process?
A*Expert Judgment
B*Negotiated Settlements
C*Bottom-Up Estimating
86- The process of identifying specific actions and activities to be performed to produce the
project deliverables is called?
A*Define Activities
B*Sequence Activities
C*Develop Schedule
88- Jim is managing a precision instrument manufacturing project. Recently he discovered that
some of the resources have been over-allocated on certain activities. He wants to perform
resource leveling to keep resource usage at a constant level. Which of the following is not true
about resource leveling?
B*Resource leveling can have a significant effect on the preliminary estimates of the types and
quantities of resources required
89- While running a software development project, you notice a delay on a critical activity which
might delay the project finish date. You want to measure, compare, and analyze schedule
performance. Which project process would you use to complete this task?
90- The project schedule in a project can be presented in summary form, which is also referred to
as the master schedule. The project schedule in graphical form can be easier to look at than in
tabular form. Which of the following is not a graphical form of presenting a project schedule?
A*Bar Chart
B*Milestone Chart
C*Control Chart
91- Which of the following is a tool or technique of the Estimate Activity Durations process?
A*Decomposition
B*Activity Attributes
C*Parametric Estimating
D*Facilitated Workshops
B*WBS
D*Scope Baseline
93- Which of the following is a schematic display of the project's schedule activities and the logical
relationships between them?
94- You are estimating resources for your construction project. You need to rent five power drills
for 15 days from a local company for your project. However, your company has rules that prohibit
renting any equipment for more than seven days. Which of the following would you check to
verify this information?
B*Resource Calendar
95- Which of the following is an input to the Estimate Activity Resources process?
A*Resource Calendars
C*Requirements Documentation
D*Validated Deliverables
96- Based on the following activities in Projects A & B, which activity has the longer free float?
* A: "Design floor plans" finishes on Monday and the immediate successor activity 'Build structure'
starts on Thursday.
* B: "Build roof" finishes on Monday and the immediate successor activity, 'Develop floor', starts
on Tuesday.
D*Cannot be determined
97- The following Gantt chart(same graph in q.8) displays the schedule for a telecom site
construction project. According to the original plan, the first two activities (Select Site and
Negotiate Lease) should have been 100% completed and the third activity (Perform Civil Works)
should have been 50% completed. However, only the first two activities have actually been
completed, and no work has been performed on the third activity.
To handle the schedule variance, the project manager decides to crash a project activity. The
second Gantt chart in the following graphic shows the effect of the crashing. What potential
negative effect will crashing have on the project in this scenario?
A*Increased cost
B*Change in scope
C*Increased quality
D*Increased duration
98- Which of the following methods in the Control Schedule process is used to compute different
scenarios to get the project realigned with the Project Management Plan?
B*Corrective Action
C*Delphi Technique
D*Pareto Chart
99- Which of the following is an output of the Sequence Activities process?
D*Activity List
100- Which of the following is not an output of the Estimate Activity Resources process?