DESIGN AND ENGINEERING DATA Cast Iron Installation

SUPPORT SPACING AND HANGERS Support stacks at their bases and at sufficient floor
intervals to meet the requirements of local codes.
NOTE: The following information provides general Approved metal clamps or hangers should be used
guidelines. It should be used only as a reference and not for this purpose.
as a guarantee of performance. Specific installation
Horizontal Piping Support horizontal pipe and
instructions and techniques may be required as a result
fittings at sufficiently close intervals to maintain
of local plumbing and building codes, engineering
alignment and prevent sagging or grade reversal.
specifications and instructions.
Support each length of pipe by an approved hanger
located not more than 18 from the joint. Support
terminal ends of all horizontal runs or branches
and each change of direction or alignment with an
Failure to properly support or hang cast iron pipe could approved hanger.
result in system failure and/or property damage.

FIRE RESISTANCE OF CAST IRON


Cast iron soil pipe installed in the horizontal position
shall be supported at every hub (hub and spigot) or every
SYSTEMS
coupling (hubless). The hanger shall be placed within 18 When it comes to fire-resistive construction and material
of the hub or coupling. Joints used for connecting cast selection, cast iron soil pipe systems offer a piping
iron soil pipe possess sufficient shear strength to require product that is non-combustible. Cast iron soil pipe and
one hanger per joint or hub. fittings will not burn in the event of a building fire. Many
Installations requiring multiple joints within a four-foot building codes require that newly constructed buildings
developed length shall be supported at every other or be built with fire compartments and separations; these
alternating hub or coupling. separations or compartments help reduce the spread of
fire and smoke within a building in the event of a fire. In
Vertical components shall be secured at each stack base a fire-resistive constructed building, the compartments
and at sufficiently close intervals to keep the system in may be penetrated with pipe or other service penetration.
alignment and to adequately support the pipe and its Those penetrations must be sealed back to the original fire
contents. Riser clamps, sometimes called floor or friction integrity of the compartment with a material or product
clamps, are required for vertical piping in multi-story that seals the annular space around the penetration to
structures in order for each floor not to exceed 15 feet. stop the spread of flame and smoke.
Because cast iron soil pipe is considered a non-
combustible material, it is also a perfect choice to use
in return-air plenums for DWV applications.

To help ensure adequate fire-resistance, always refer to the


fire-stop system manufacturers safety information and
recommendations.

Note: This manual is not a complete engineering


reference addressing all aspects of design and installation
of a drain, waste and vent or sanitary storm system.
Vertical Piping Secure vertical piping at sufficiently
close intervals to keep the pipe in alignment and to
support the weight of the pipe and its contents.