Академический Документы
Профессиональный Документы
Культура Документы
ABSTRACT: Slurry shields are commonly used not only in Singapore but worldwide. As these are often
used in very challenging nonhomogeneous ground conditions, it is crucial to understand and improve the
processes which will help to prevent over-excavation, sinkhole and settlement risks. Slurry shields utilize a
bentonite suspension to provide support to the tunnel face and to transport spoil to the surface. By comparing
the measured inflow and outflow rates it is possible to calculate and display on real time basis the amount of
excavated material. For this purpose there are flow meters and density meters installed in the slurry circuit.
Based on the measurements there are different methods to calculate the quantity of excavated material. These
can be presented as excavated volume, mass or dry mass following different formulae. As the calculation
methods differ slightly in their approach, the sensitivity to the various influences on the slurry circuit
depends on the chosen calculation approach. Such influences can be measurement errors, mechanical,
electrical and hydraulic issues, the influence of time as well as changing geology. Also in case there is over-
excavation of solids, ingress of ground water or bentonite loss into the ground, the different formulae will
reflect these effects through different results. While one approach may be more suitable under certain
conditions, another approach will be more appropriate in other conditions. In order to provide the industry a
clear view of the advantages and disadvantages of the various approaches under different conditions, this
paper presents a set of definitions for all the parameters involved. The different calculation approaches are
then compared on the basis of the unified definitions. The focus of the study centres on the behaviour of the
different calculation methods, during situations such as a face collapse, calibration error of sensors, water
inflows or compressed air interventions. A simulation tool in Excel is presented which allows defining
several real life examples and the different calculation methods. Subsequently the behaviour of different
calculation algorithms is shown and explained. This analysis and comparison allows not only the
improvement of practical excavation control systems in the future but also helps the various stakeholders to
better understand and interpret the measurements and calculation results obtained by the different systems
available in the market.
1. INTRODUCTION
The slurry shield, previously known as bentonite tunnelling machine, was invented and full scale trials were
conducted in the UK in the early 1970s for the sole purpose of achieving better control of excavation in
difficult ground conditions [2]. At the time the challenge was to excavate safely through submerged sand and
gravels without causing over-excavation or instability of the tunnel face. Slurry shields are nowadays used in
a variety of ground conditions which include hard rock and stiff clays primarily to take advantage of their
superior ability to respond to sudden variations in the grounds conditions. The monitoring of the slurry
circuit is an important task for quality control of tunnelling processes; this includes the continuous
monitoring during tunnelling as well as regular reviews of the latest progress but also the back analysis after
project completion of incidents which require investigation. The main parties concerned are the contractors
under whose responsibility TBMs are operated but also project owners, authorities, consultants and TBM
suppliers [19]. There are several different approaches to measure and calculate the amount of excavated
material. The calculation formulae used in the industry have been developed by suppliers of TBMs, slurry
circuits and monitoring systems. There are typical solutions developed by individuals for their employers and
as a result different TBM suppliers use different approaches. There are also specific approaches requested by
contractors and implemented by the suppliers. Although these approaches are all based on the same
underlying principles, they vary in terms of hardware, signal processing and calculation procedures. There
are several simplified formulae which are theoretically not correct but have been used successfully on site.
The theoretical target value of excavation quantity is difficult to determine because of the variations in
specific gravity, moisture content, pre-existing voids etc. in the ground. The user interface and visualization
of the systems available in the market can differ quite a lot so results are not necessarily comparable. On top
of all this, there are claims by some suppliers about the high level of accuracy of their system which when
examined closely could be classified best as technically incorrect if not fictitious.
This paper gives an insight into the implications arising from the use of different formulae and clearly
defines the theory of excavation management which can be used as a reference for future work and
discussions. The authors intend to present a unified theoretical basis which is unbiased towards any single
individual developer and built on the standards set by the large industry associations such as ITA, DAUB or
BTS. To make the results tangible, an Excel based simulation tool is presented which allows the comparison
of different formulae. This tool is then used with input data which corresponds to experiences from actual
projects. The tool simulates one ring of advance and it can process the input data for different scenarios and
produce the measurement results for each type of calculation formula.
2. DEFINITIONS
The parameters and expressions describing excavation management vary between different countries and
different publications. This causes a lot of misunderstanding when technical information is communicated
between different parties in the industry. This Section introduces the input and output parameters for
excavation management and provides a precise foundation for further work by setting out exact
mathematical definitions for all relevant parameters. Where possible the definitions follow the Geotechnical
Engineering Handbook [28] as well as the typical industry standards.
The following definitions apply to the operational and geotechnical parameters which are relevant for the
excavation management system:
Solids Density is the average density of the solid materials in the ground. This refers to the solid particles
only and does not take into account the packing density or any fluids or gasses in the voids between the
particles. Therefore it depends solely on the mineral composition of the solids. Table 3 gives an overview for
a number of common minerals. The solids density is different from the dry density and a common mistake in
practice of mixing these two should be avoided.
= [3 ]
Water Content is the percentage (by volume) of water in the ground. The water fills the voids between solid
(soil) particles or rock formations. The water content is defined as the ratio of volume of water to the volume
of solids. In fully saturated soil below the groundwater table, the water content is equal to the volume of
voids between the particles [7]. The difficulty in measuring the actual water content of the soil lies in
measuring it without changing its value by the disturbance created by the measurement process.
= [%]
= (Eq. 1)
In Situ Density is the average density of the ground in its undisturbed state before excavation or other
interference. As there are voids between particles and rock formations which are filled with water, the actual
in situ density is always lower than the solids density or the dry density defined below. In fully saturated
soils, all voids are completely filled with water. Therefore the in situ density can be defined as the follows:
= [3 ]
= (1 ) + (Eq. 2)
Dry Density is the bulk density of the solid material without any water filling the voids. It depends on the
solids density and the compaction of the material. ASTM D4254 [1] defines it as the ratio of dry solid mass
per bulk volume. A density index developed by Terzhagi [28] can be used to define the relative compaction
level between maximum and minimum packing density. It should be remembered that the dry density is less
than and not equal to the solids density.
= [3 ]
= (Eq. 3)
Bentonite Powder Density is the solids density of the bentonite powder which depends only on its mineral
composition. This density is very similar to the particle density of the soil and many dry mass calculation
formulae are simplified in such a way that it is assumed as the same as the solids density of the ground.
= [3 ]
Feed Slurry Density is the density of the bentonite suspension in the slurry feed line. Its value depends on
the type and quality of freshly mixed bentonite suspension as well as on the fines content from excavated
muck which is accumulating in the slurry until removed in the separation plant.
= [3 ]
Discharge Slurry Density is the density of the bentonite suspension in the discharge line. The density is a
resultant of mixing muck into the bentonite suspension in the excavation chamber. Sometimes it is referred
to as discharge density.
= [3 ]
Feed Slurry Flow is the flow rate in the slurry feed line. As fluids are incompressible it is always constant at
every point in the slurry circuit.
3
= [ ]
Discharge Slurry Flow is the flow rate in the discharge line. It is usually higher than the slurry feed flow as
there is sealing water and muck mixed into the discharge flow. As for the slurry feed flow rate, the discharge
flow is constant throughout the whole circuit as fluids are incompressible [13].
3
= [ ]
Chamber Volume is the volume of material in the excavation chamber of the TBM. This is usually constant
for TBMs with a single chamber while in TBMs with a double chamber and air bubble the volume of muck
stored can vary as the face support pressure is regulated to maintain a constant pressure while the filling level
can change. The fluctuation over time should be considered in an excavation management system by
measuring the level in the second chamber. This change is then calculated over time and included in the
excavation management system [10].
= []
Theoretical Dry Mass is the theoretical in situ mass of excavated solids. This value can potentially form the
reference value of an excavation management system. The practical difficulty in obtaining the value lies in
the challenge of measuring the bulk density and water content reliably. As this depends on the weathering
grade as well as the size, orientation and distribution of rock joints or other features of the ground, it can
change rapidly from ring to ring. Also by attempting an in situ measurement, one might change the packing
density and therefore the water content [7], [8]. The theoretical dry mass plays an important role in practical
application as it is possible to measure it in the slurry circuit as well as to some extent on belt scales. Thereby
it allows independent double measurement of the same parameter.
= , []
, = (1 ) (Eq. 4)
Theoretical Solids Volume is the volume of excavated solids. This value does not consider the packing
density of the soil or rock particles and does not change with varying compaction level. In fully saturated
soil, the theoretical solids volume for one ring can be determined by deducting the water content from the
total volume [28]. The practical determination of solids volume cannot be done easily. It can only be
measured by using fluids and their displacement which is an indirect measurement method that cannot be
performed for large volumes on site. Nonetheless dry solids volume can be an important measure as a
reference value in an excavation management system as it can be estimated based on water (moisture)
content normally defined in the geotechnical baseline report.
= , []
, = (1 ) (Eq. 5)
Theoretical Dry Volume is the bulk volume of the dry material. It depends mainly on the relative
packing density of the material and changes easily when the ground is disturbed by any interaction or
external influences. Therefore it is hard to define in general but can only be defined for a certain state the
material is in with the current porosity n. When using it as a reference for an excavation management
system which is done regularly, this difficulty must be considered. Also any comparison to the material in
the muck pit is incorrect as the porosity (in the muck pit) differs totally from that in the ground.
Nonetheless dry volume plays an important role as a possible reference value for excavation management
systems.
= , []
, = (1 ) (Eq. 6)
Theoretical Volume is the volume theoretically excavated from the ground. This volume contains all solids
and water. It depends on the mechanism of slurry penetration into the ground and the formation of filter cake
as shown in Figure 3. This mechanism defines, how much ground water is displaced by the slurry or how
much is entering the chamber and is discharged with the solids [25]. Following formula assumes that all
water present at the tunnel face will be excavated. The real value lies between this theoretical volume and the
theoretical solids volume. It can vary during excavation according to ground properties. Therefore a range of
results should be seen as correct instead of just one number.
= []
= (Eq. 7)
Theoretical Mass is the mass of excavated materials. This value contains all solids and water which are
excavated. Similar to the theoretical volume, there is a certain range which is to be expected depending on
the mechanisms of face support. The following formula poses a theoretical value which can decrease when
considering bentonite losses into the soil or increase if excess ground water is discharged.
= []
= (Eq. 8)
3. EXCAVATION MANAGEMENT FORMULAE
At present the industry uses a number of different formulae to calculate the results presented by excavation
management systems. The formulae are used for calculating different types of final results such as those
mentioned in Section 2 and utilize different input parameters which have to be keyed in by the user. This
Section introduces common approaches adopted at present by different suppliers and contractors and
explains these in more detail.
= [( )] + (Eq. 9)
= ( + ) (Eq. 10)
= [( )] + (Eq. 11)
3.4 Excavated Dry Mass
As many of the measurement errors in excavation management systems originate in the volume flow
measurement which is influenced by many events on the machine, calculating the dry mass eliminates most
of these influences from the calculation results. Therefore dry mass and dry volume based excavation
management systems offer the advantage of being less unstable and easier to calibrate. Their downside is that
they do not indicate the influence of groundwater clearly. Generally for a given amount of material, the dry
mass can be calculated when the individual densities of solids and water as well as the total density of the
mixture is known. Practically the excavated dry mass can be calculated from the density and flow readings of
both lines, given the individual densities of the rock or soil particles are known [35]. Figure 4 and following
formula illustrate the principle of this approach:
= (Eq. 12)
This formula is applied to the feed and the discharge material and the result will be the excavated dry mass.
As there are various forms of development by different contractors and different TBM suppliers for
excavation management system, there are a number of different formulae which are used throughout the
industry. They differ mainly in the type of simplifications which are adopted. Also some use different input
values depending on the preference of the TBM supplier or operator. The simplifications are necessary to not
overcomplicate the measurement process and allow smooth operation on site. The following Section presents
a number of different approaches in the calculation of the amount of dry solids material excavated.
The resulting excavated dry mass for one ring can therefore be determined by considering the change
during a given time period t :
= ( )
+ (Eq. 15)
This approach requires knowledge of the ground particle density which can be determined precisely as
well as of the bentonite powder density. Both need to be keyed in by the operator or must be
hardcoded in the software system. The last expression which includes the effect of changing chamber
levels into the formula can only be approximated as the actual chamber density is not homogenous.
Therefore this section represents a mass instead of a dry mass which allows the closest possible
approximation.
This formula is the theoretically correct method of calculating the excavated dry mass. It can be
simplified as shown in sub-section b) below.
+ (Eq. 16)
This formula is a simplification of a) that does not take into account the possible density differences
between bentonite and ground particles. As this difference is usually very small, the ensuing error is
considered to be very small compared to possible other sources of errors. Table 3 gives an overview of
different minerals densities. This formula allows a useful simplification in the operation of an
excavation management system, as keying in bentonite density can be omitted and assumed equal to
ground particle density. Also fixing water density at 1 t/m is a reasonable simplification that makes
sense and simplifies the operation. This formula is also used in the paper from Yamazaki et al [34] in
1984.
= ( ) (Eq. 17)
This formula allows calculation based on in situ density. This means that the solids density and
bentonite density need not be known but only the in situ density of the ground. This allows an easier
comparison with the theoretically excavated dry mass as a target. This value is also calculated based
on the same in situ density. Therefore there is no need for different input parameters for target and
measurement such as separate particle density and ground water content. This formula is a typical
example of an approximation which is not scientifically correct but used on site for several projects in
the US. The theoretical incorrectness becomes obvious when calculating the units in the formula which
are incorrect.
( 1) ( 1)
= ( )
( ) ( 1)
+ (Eq. 18)
The given formula is another calculation based on in situ density. It is an extension of the formula
mentioned in c). Different to the previous formula the density of water, again simplified to 1 t/m3, is
included. The Formula also assumes knowledge of the particle density. Similar to the formula
mentioned in c), this formula is not scientifically correct but an approximation which has been used in
a number of projects. As with the formula shown in c) the units in this formula are incorrect.
This formula is applied for calculating the Solids Material Volume [21]. The last sequence includes the
addition of the volume of the chamber level change. It is essentially based on dry mass calculation
methods but is shortened by deleting the density multipliers from the calculation. This allows
calculating only the solids volume. The actual dry volume cannot be measured as the packing density
of the particles changes constantly while handling. The upper and lower boundaries are shown in
Figure 5. In the published literature and practice it can often be found that the solids material volume is
called dry material volume. This ambiguity is theoretically incorrect but seldom discussed in practice
as its influence is marginal compared to many other effects.
4. MEASUREMENT HARDWARE
The measurement of the excavated quantity of material takes place directly in the slurry circuit and TBM
working chamber. A number of sensors to measure flow rate, density and level are arranged in such a way
that they can measure the flow volume and density in the system for the determination of the excavated
quantity of material.
4.1 Flow Meters
The tunneling industry is generally using electromagnetic flow meters at present. Their accuracy typically
depends on the uniformity of flow, the even distribution of solids and the flow speed in the pipe as well as
the behavior of the solids [27]. Typically in TBMs the magnetic flow meters are operated at the lower end of
their permissible flow speed range. Below a certain flow speed, the stochastic measurement errors increase.
This effect starts usually below around 2 m/sec [13] as can be seen in Figure 6. Nonetheless this error does
not affect the practical measurement dramatically, as the large number of individual readings and the
stochastic nature of the error leads to a strong equalization effect. The sensors in feed line and discharge line
must be calibrated relative to each other. In case they have an offset between their calibrations, this will
directly affect any measurement significantly [36]. Therefore it is necessary to spend considerable effort on
the relative calibration of the flow meters [24]. This can only be done when the machine is driven in bypass
mode regularly.
In order to test and visualize different calculation approaches described in Section 3 and analyze how these
respond to certain conditions and events an Excel based simulation framework has been developed. This
allows the definition of various input scenarios and determine the consequences for the slurry circuit and its
operating parameters.
The measurements and readings from the sensors are used as input data. The different calculation algorithms
are then implemented in the simulation to produce different output corresponding to the calculation methods.
Then the output of the different algorithm results are plotted and compared to target curves.
In the simulation tool one theoretical ring is created on which the effects of different scenarios are applied
and the results with different formulae are demonstrated. The example ring in this Excel tool is built during a
total cycle time of 2 h. The advance time amounts to 1.5 h, including 5 min bypass mode at the end. The next
30 min is the standstill during ring building, which also ends with 5 min bypass mode before the next ring.
During the TBM advance a constant mining rate is considered. The different scenarios which are compared
are staged in typical geological conditions in Singapore. Data from Circle Line project [26], [20] has been
used to simulate GIII and GVI Bukit Timah Granite. Water and solid content of the ground material are
based on the data presented in Figure 2. All calculations assume an average particle density of the soil and
rock minerals of:
= 2.65 [ 3 ]
The sensors are put in individually in the simulation so miscalibration can be addressed and visualized in the
result graphs. Furthermore the parameters which have to be input by the users of excavation management
systems can be adjusted in the simulation so that possibly wrong values can be simulated and the
consequences can be studied.
6. RESULTS
In order to compare the behavior of the different formulae, the results of different simulation conditions are
shown in a condensed form. All results are presented first and the inaccurate calculation approaches are
eliminated from further consideration. Subsequently comparisons are carried out for the scenarios described
in Section 5. Figure 9 shows the outcome from the first simulation and the general principles for comparison
of results. While a certain scenario is studied by the simulation tool, the resulting curves are plotted for all
calculation methods.
Figure 9. The simulation results for all calculation approaches for standard ring
Figure 9 shows an overview of results for different calculation approaches and target curves. The plot on the
left side shows different dry mass and dry volume obtained from the simulation tool. The plot on the right
side shows the values from manual analysis of the ground conditions as well as excavated total mass and
total volume. With regards to the 5% maximum deviation of the results which is often stated or demanded,
the 20% spread between different dry mass calculation formulae is unacceptable. As a first consequence, the
dry mass formulae using in situ density is seen to produce results that lie too far away from the theoretical
target values and therefore should be ruled out from usage. When comparing the theoretical dry mass with
the two remaining dry mass formulae, our initial assumption that the dry mass formulae using generalized
particle density and fixed water density are fairly accurate. Their deviation from the target line is small
enough to be used practically without loss of accuracy. The solids material volume formula produces an
accurate result as well. But the solids volume of a sample of excavated material is practically difficult to
measure. It is not easy to double check the results obtained on site within the required level of accuracy.
Therefore the following steps of this study focus on the comparison of the dry mass with a generalized solids
and fixed water density to the total mass and total volume measurements.
Figure 10. Simulation results for GIII and GVI Bukit Timah Granite
The excavated dry mass readings show the clearest difference when tunnelling through varying geologies. As
the water content of GVI is high that the solids volume makes up only around 50% of the total volume, and
the dry mass drops accordingly. The measurement deviation increases as well with increasing water content.
6.3 Reaction to a sudden Face Collapse
A theoretical estimation of face collapse measurement has been described by Yamazaki [34]. For the
simulation of a face collapse it has been assumed that part of the face collapses leading to an increase in the
solids in the chamber while the amount of slurry decreases as it replaces the space created by the fall.
One fact immediately becomes obvious is that as the face collapse is volume-neutral there is no significant
increase in the volume of material in the cutter-head chamber. That means it is necessary to observe the
amount of excavated solids (by dry mass/volume) detect such event. A sudden rise of the density meter
readings can also act as an indicator. When comparing the mass and dry mass readings, the gradient of the
dry mass measurement increases steeper directly after the event. Thereby making it easier to detect a collapse
through observation of the dry mass readings.
When discussing water inflow there is an important difference between dry mass or solids volume on one
hand and mass or volume on the other hand. Due to the principle of dry mass or solids volume calculation,
additional water ingress cannot be detected. This can be seen in the left side graph in Figure 12. While the
volume and the mass graphs react immediately to the inflow, the dry mass graph does not.
As a steady over-excavation scenario means constant additional inflow of solids and water, it can be detected
by of all the different results. The magnitude of deviation depends on the water content of the ground. The
higher the water content, the clearer is the difference between dry material method and total material method.
The results from miscalibrated flow meters simulations demonstrate a proportional deviation of mass and
volume during excavation. The dry mass is less strongly affected by the miscalibration of the flow meter as
the percentage of solids in the slurry lines is rather small. This leads to the measurement error being kept
small which is an advantage of using dry mass or volume formulae. During bypass the values will quickly
deviate strongly if the flow meters are miscalibrated. Again this influence is reduced for the dry material
calculation.
The miscalibration of the density meter has very severe consequences. This can be seen in the right hand side
graph in Figure 13. While the slurry discharge line density meter is miscalibrated by only 2%, the apparent
increase in the excavated dry mass is almost 90% while the excavated mass is close to 50%. This underlines
the importance of the accuracy of the sensor hardware.
6.6 Particle Density Miscalibration
The dry mass calculation is done on the basis of the particle density of the solids in the ground as outlined in
Section 3. As all the dry mass formulae carry the particle density in the denominator, keying in a lower
particle density will increase the result of the equation. This behaviour is shown in Figure 14. The left hand
side graph depicts the result of dry mass and dry volume calculation with an artificially increased particle
density whereas the right hand side a lower density. The outcome reflects a corresponding reduction in the
results for the dry mass with increased particle density and the opposite for the lower density which
illustrates exactly what happens on site when the operator keys in an unsuitable particle density value. The
excavated volume and mass in this situation remain unaffected as expected, while the solids volume follows
a similar trend as the dry solids mass.
This paper summarises the current knowledge of excavation management formulae and permits a greater
understanding of their behaviour under different excavation conditions as well as measurement scenarios.
This is done using an Excel based simulation tool which facilitates the visualization of the behaviour of
different calculation approaches.
The comparison of different approaches which are known today shows that the use of dry mass or dry
volume is advantageous compared to volume or mass based measurements in most cases but it also has
certain limitations. Therefore a combination of volume and dry mass or volume and dry volume are
considered to be the most recommended approach for excavation management. Generally mass based
approaches allow using belt scales as an independent secondary measuring method whereas the solid volume
is very hard to measure. The dry material bulk volume could be measured for reference but this is not
directly comparable to the solids volume.
Overall, the most recommended calculation method is the simplified dry mass formula with the dry volume
formula being technically good but hard to compare to a reference value. The dry mass formulae using in situ
density should not be used. A pure volume based calculation can be useful in homogenous ground conditions
eg. sands and gravels but it has certain drawbacks in mixed ground conditions.
The theory of excavation management can be partly seen as well understood with the advent of widespread
use of slurry machines. However there are areas where the whole industry has to make improvements with
respect to the technology, procedures and operation. The areas for improvement include development of best
and consistent practices to minimise the margin of error, quick and precise detection of over excavation,
practical recommendations for site installation of the sensors and subsequent calibration.
Detailed knowledge of the geomechanical processes and flows during face collapses or over-excavation
would greatly improve the possibility for early detection of such events based on the results of data analysis.
This can be complemented by large scale study of the sensor accuracy, the repeatability of the measurements
through effective calibration and increased knowledge on the uncertainty in measurements. With these steps
the Authors believe the industry will soon benefit from a more reliable and effective excavation management
system for slurry machines.
REFERENCES
[1] ASTM D4254, Standard Test Methods for Minimum Index Density and Unit Weight of Soils and
Calculation of Relative Density, ASTM International, West Conshohocken, PA, 2014.
[2] Bartlett, J. V., Biggart, A. R., Triggs, R. L., (1974) Bentonite Tunnelling Machine, Proceedings of the
Institution of Civil Engineers, Part 1, 7670, UK.
[3] Berthold Technologies (2015). Density Meter LB 444, Berthold Technologies GbmH & Co. KG, USA.
[4] Bochon, A., Rescamps, Y., Chantron, L. (1997). Detecting Anomalies During Slurry Shield Excavation:
Method Applied on EOLE site, France.
[5] BTS/ICE (2005). Closed-face Tunnelling Machines and Ground Stability: A Guideline for Best Practice.
British Tunnelling Society with the Institution of Civil Engineers, Thomas Telford, 77 p.
[6] DAUB (2006). Recommendations for Design and Operation of Shield Machines, German Committee for
Underground Construction Inc. (DAUB), Tunnel 6/2000, Germany.
[7] DIN 18 123 (1983). Baugrund; Untersuchung von Bodenproben; Bestimmung der Korngrenverteilung,
Hrsg. Deutsches Institut fr Normung, Beuth Verlag, Berlin.
[8] DIN 18 125 (1986). Baugrund; Bestimmung der Dichte des Bodens; Teil 1: Laborversuche, Hrsg.
Deutsches Institut fr Normung, Beuth Verlag, Berlin.
[9] Duhme, R. (2015). Excavation Management in Slurry TBMs- Theoretical Foundations and Practical
Challenges, TUCSS Tunneling Course 2015, Tunnel and Underground Construction Society Singapore
[10] Duhme, R. (2015). Apparatus for Driving a Tunnel, Singapore Patent Application Number:
10201502431W (DE 102014104580.7)
[11] Earthnix Corporation (2014). On-line Density Meters GD-8000 Operation Manual, Earthnix
Corporation, Tokyo, Japan.
[12] Eichler, K. (2007). Fels- und Tunnelbau II, Expert Verlag, Renningen, Germany.
[13] Endress + Hauser (2007). Proline Promag 55 Electromagnetic Flow Measuring System,
BA119D/06/en/11.0, Endress + Hauser , Germany.
[14] Endress + Hauser (2007). Liquicap M FMI51, FMI52 Capacitance level measurement for continuous
measurement in liquids, TI00401F/00/en, Endress + Hauser , Germany.
[15] Golder Associates (2009). GeoReport No. 249, Ground Control for Slurry TBM Tunnelling. Hong
Kong.
[16] Guglielmetti, V. (2007). Process Control in Mechanized urban tunneling, Mechanized Tunneling in
Urban Areas. Design Methodology and Construction Control.
[17] Japan Society of Civil Engineers. (1984). Thesis Report No. 343, Tokyo, Japan.
[18] Maidl, B., Herrenknecht, M., Maidl, U., Wehrmeyer, G. (2001). Mechanised Shield Tunneling Ernst &
Sohn, Berlin.
[19] McChesney, S., Gasson, P., Nair, R. (2008). Slurry TBM Tunnelling Risk Control & Lessons learnt on
CCL Stage 4 Contract 854, International Conference in Deep Excavations, Singapore.
[20] Nakano, A., Sahabdeen, M., Kulaindran, A., Seah, T. (2007). Excavation Management for Slurry TBMs
Tunnelling under Residential Houses at C853 (CCL3) Project, Underground Singapore 2007, Singapore.
[21] Ow, Chun Nam, Ariaratnam, K., Tiong Peng, S. (2007). Construction of Rail Tunnels Using Slurry
Machines on Circle Line Stage 3, Singapore, ACUUS Conference, Underground Space: Expanding the
Frontiers, Athens, Greece.
[22] Press, F., Siever R., (1985). Earth, W. H. Freeman and Company, New York.
[23] Rosenbusch, N. (2015). Mass Balance for Hydroshield TBM using Dry Mass Calculation and
IRIS.tunnel, ITC Advanced Engineering Asia Pte Ltd., Singapore.
[24] Rysdahl, B., Mooney, M., Grasmick, J. (2015). Calculation of Volume Loss using Machine Data from
Two Slurry TBMs during the Excavation of the Queens Bored Tunnels. Proc. Rapid Excavation and
Tunneling Conference 2015, New Orleans, USA
[25] Rysdahl, B., (2015). Determination of the Uncertainty in Excavated Volume Estimation from Slurry
Shield Tunnel Boring Machines used on the Queens Bored East Side Access Tunneling Project. Dissertation,
Colorado School of Mines, USA
[26] Sahabdeen, M., Kulaindran, A., Nakano, A. (2007). Dry Soil Volume for Excavation Management of
Slurry TBMs Tunnelling at C853 Project, Singapore, International Conference in Deep Excavations,
Singapore
[27] Shook, C.A., Roco, M.C., (1991). Slurry Flow- Principles and Practice, Butterworth Heinemann,
Boston, USA.
[28] Smoltczyk, U. (2002). Geotechnical Engineering Handbook Volume 1: Fundamentals, Ernst & Sohn,
Berlin, Germany.
[29] Uchida, Y., Ishiwata, K. (1977). Apparatus and Method of Shield Excavation, US Patent No. 4040666
[30] Wehrmeyer, G. (2000). Zur Kontrolle der gefrderten Aushubmassen beim Tunnelvortrieb mit
Flssigkeitsschilden, Dissertation, Ruhr University Bochum, Bochum
[31] Wehrmeyer, G. (2002). Massenkontrolle bei Schildvortrieben Stand und Erfahrungen, Taschenbuch
Tunnelbau, VGE Verlag, Essen, Germany
[32] Wehrmeyer, G. (1999). Mglichkeiten der Aushubkontrolle bei Schildvortrieben, Bauingenieur Bd. 74
(1999) Nr. 2, Germany
[33] Yamazaki, H. (1983). Excavation Controlling Method in Hydraulic Shield Tunneling, US Patent No.
4384807
[34] Yamazaki, H. et al. (1984). Face Stability and Control of Excavation in the Shield Method, Journal
Report of Japan Civil Engineering Society 3/1984, Japan.
[35] Yamazaki, H. et al. (1976). Apparatus and Method of Measuring Fluctuations of Excavated Mud
Amount in a Slurry Line, US Patent No. 3946605.
[36] Yokogawa (2006). Magnetic Flowmeter ADMAG AXF, CA, Yokogawa Electric Corporation, Japan.